LITERATURE REVIEW
Many studies were carried out to investigate and assess the causes of
delays in construction projects. Daniel W M Chan et al (1998) surveyed
the causes of time overruns in Hong Kong construction projects as seen
by clients, contractors and consultants, and examined the factors
affecting productivity. The survey revealed differences in perceptions of
the relative significance of factors between the three groups, indicative
of their experiences, possible prejudices and lack of effective
communication. The results of the research indicate that five principal
and common causes of delays are: poor site management and
supervision; unforeseen ground condition; low speed decision making
involving all project teams; client initiated variation; and necessary
variation of works. Mansfield et al. (19994) studied the causes of delay
and cost overrun in construction projects in Nigeria. The results showed
that the most important factors are financing and payment for
completed works, poor contract management, changes in site
conditions, shortage of material, and improper planning.
David Arditi et al. (1985) studied the reasons for delays in public
projects in Turkey. The results indicate that shortages of some
resources; public agencies and contractors financial difficulties;
organizational deficiencies and delays in design work, frequent change
orders and considerable extra work are the most important sources of
delay.
In John W. Ralls article on how to avoid delays and delay claims on wind
power projects, it is stated that jobs finish late for all types of
overlapping reasons, including:
1. Inaccurate geotechnical information.
2. Failure to secure needed permits.
3. Late equipment manufacturing.
4. Late equipment deliveries.
5. Design changes.
6. Failure to provide site access.
7. Bad weather.
8. Labour problems
9. Late or poor performance by installation contractors.
10. Problems with testing and commissioning.
Ogunlana, et al (1996), studied the delays in building projects in
Thailand, as an example of problem faced by the developing
economies. They concluded that problems of the construction industry
in developing economies can be nested in three layers: problem of
shortages of inadequacies in industry infrastructure, mainly supply of
resources, problems caused by clients and consultants; and problems
caused by incompetence of contractors.
All the research mentioned have largely focused on Asia. Very few of
the research under this review have concentrated on Africa and only
one has been done on Ghana in the area of groundwater project.
Therefore to the best of my knowledge there has not been much
research on the causes of delay in road construction projects in Ghana.
completed within the stipulated time frame and is caused jointly or severally by the client,
Construction delays are general costly, since there is usually the use of loans in financing the
project which charges interest involvement of time related charges such as project supervisors
Before investigating the causes of delays, a clear understanding of the general types of delays is
1. Excusable-Non-Compensatory (concurrent)
2. Non-Excusable
3. Excusable-Compensatory
party outside the control of the client or contractor or consultant. Thus concurrent delays affect
the critical path rather than the float time. Examples of causes are: excessive inclement weather,
Also, concurrent delays may arise if the client cause delays take place at the same time as a
contractor cause delay. In this, case the contractor is entitled to extension of time without cost. In
a situation where concurrent delays cannot be separated, neither the client nor the contractor can
recover damages for the resulting project delays. Hence, concurrent delays are treated as
The events that cause these delays are: insufficient manpower, late material deliveries, lack of
of the client. Examples of causes are: variation orders that impact the critical path, late return of