In-Plant Training

At Sierra Construction (Private) Limited

TRAINING PERIOD 12 WEEKS


Ochini Chandrasena
EN 14 5131 38
Project Background
Project: Sierra Head Quarters (Sierra Tower Project)
Client: Sierra Developments Ltd
Designed & Built by: Sierra Construction (Pvt) Ltd
Commenced: 01st September 2014
Expected to complete: 19th August 2016
Total Floor Area: 9620.00 square meters
Expected Cost: Approx. Rupees 925 million
Training Experience
Week Area Start Date End Date

01st Week to 04th Week Reinforcement Work 26/10/2015 21/11/2015

05th Week to 08th Week Surveying & Levelling Work 23/11/2015 18/12/2015

Post-Tension Work
09th Week to 12th Week 21/12/2015 17/01/2016
Formwork
1) Reinforcement Work
The main duties assigned were:

1. Making bar schedules

2. Calculating weight of the reinforcement bars

3. Inspection of the arrangement of reinforcement bars in beams,


columns and slabs.
Stirrups
200mm
spacing

Stirrups
100mm
spacing
Stirrups

Beam Reinforcement Column Reinforcement


Slab Reinforcement

10 200 C/C
MESH BOTH WAYS

Bottom Net Top Additional Net


2) Surveying and Leveling Work
The main duties assigned were:
1. Leveling of slab, beam and staircase landing formwork
To get the accurate floor height in between two floors

2. Marking the 1000mm lines on the columns and lift


walls
As a reference line for placing beam bottoms, slab soffits
and for floor finishes
3. Setting out of grid and column offsets
As reference lines for placing kicker in column
formwork and to check verticality

4. Marking the lines on slab formwork for sideboards and ducts


To mark the edge of the slab for the bar benders in laying the bottom r/f net
and for carpenters to fix sideboards.
To mark the locations of ducts to avoid tying of r/f and putting concrete.
5. Leveling the surface of the concrete
To ensure the slab is properly leveled and
the slab has the required thickness.

6. Spot Leveling
To evaluate the level of the slab and to analyze the finish floor level.
3) Formwork
The main duties assigned were:
1. To check the verticality of the column formwork

2. To inspect the beam bottom heights

3. To record the daily man-power

Plumb
bobs
4) Post-Tension Work
The main duties assigned were:
1. Measuring and checking the height
of stools
Tendons

2. Measuring and recording the elongation during the Tendon Stressing.

3. Recording the time taken during the Tendon Grouting.


5) Office Work
Checking the Invoice Bills (Request from the Sub Contractors Interim)
with the bar schedules from Basement Level to Third Floor Level.

Making the Labour Supply for Post-Tension (PT) work in MS Excel.

Updating the Concrete Cube Test Records in MS Excel.


Conclusion
12 weeks of internship was an excellent and rewarding experience to
learn how theoretical knowledge applies in the practical scenarios at
site.