Anda di halaman 1dari 2

Project Information

Project Milestones

Cabin John Trunk February 17

Project Start

Relief Sewer Spring 19

Project Completion

The Cabin John Trunk Relief Sewer Project is a new, 3,200 linear Note: Work on the project will
foot, 24 diameter sewer segment being built within the Cabin occur during the day and at
John watershed. This sewer will supplement the capacity of an night, depending on the
existing sewer in this location. type of work being
performed, weather and
other circumstances. Work
during the day will be
performed only during
permitted hours between
9am and 3pm. For more
information, see phasing
diagram under Additional
Resources section.

Additional Resources
Project Map
Who Project Map (Aerial)
The project is part of the Washington Suburban Sanitary Phasing Plan
Overview of System
Commissions approved Capital Improvements Program and
Development
is being constructed by Gaines Construction and Jansen
Charges Presentation
Land Consulting, on behalf of by Federal Realty Investment Maintenance of
Trust, which is required by WSSC to build the project as part Traffic Plan
of the approvals for its Pike & Rose development project.
When completed, the project will become part of WSSCs
system, and WSSC will handle ongoing operations and
maintenance.

Information provided by Federal Realty Investment Trust Page 1 of 2


December 15, 2016
More Project News
Where
The project will span approximately 3,200 linear feet, starting on
Contact
Seven Locks Road several hundred feet south of the intersection
with River Road, continuing north through that intersection, then Timothy Brooks
west onto River Road until its intersection with the Cabin John Contract Manager, Systems
Creek (see project map below). The sewer itself will traverse that Inspection Group
Washington Suburban Sanitary
route underneath the roadway, either in a travel lane or the
Commission
shoulder, for its entire route, save for a small segment (about 100) 301-206-7339
at the western terminus, where it will run north from River Road to Timothy.Brooks@WSSCwater.com
connect with an existing sewer adjacent to the Cabin John Creek.
This route is a revision to the original plan for the project, which
called for the sewer to be installed immediately adjacent to the More Information
Cabin John Creek in the wooded area to the south of River Road www.cabinjohnsewerproject.com
in this location.

Why
The project is necessary to provide additional capacity to handle
wastewater from current and future development and
redevelopment, including Pike & Rose, within the Cabin John
basin. The project will also reduce the risk of sewer overflow events
in the basin during periods of heavy usage.

How
The project team will use a combination of trenching and
tunneling to install the new sewer beneath the roadways,
connecting with existing sewers on each end. Work will proceed in
phases starting at the southern end of the project on Seven Locks
Road and proceeding to the northern end on River Road. During
daytime construction, one lane of traffic in each direction will be
maintained. Because project work is largely confined to the
roadway, there will be minimal impact to existing trees. Any trees
that are impacted will be replaced as part of reforestation process
at the conclusion of the project. The project is expected to cost
approximately $14m and will be paid for by Federal Realty
Investment Trust, who will then be repaid by other users of the
system via the System Development Charge (SDC) Program. As
such, no taxpayer or ratepayer money will be used to fund the
project.

Information provided by Federal Realty Investment Trust Page 2 of 2


December 15, 2016

Anda mungkin juga menyukai