ADC-GID Classic Schedule Layout 08-Sep-16 09:50

Activity ID Activity Name Original BL Project Actual BL Project Finish 5 2016 2017
Duration Start Start Finish uly A S O N D J F M April May June July A S O N D J F M April May June July A S O N
0 1 0 1 0 2 0 2 0 2 0 2
ADC-GID 725d 01-Jul-15 31-Oct-17 31-Oct-17 31-O

General Mile
M Stone 100d 01-Jul-15 01-Nov-15 01-Nov-15 01-Nov-15, General Mile Stone
A1000 Start Project "Actual start dates should b 0d 01-Nov-15 Start Project "Actual start dates should be the actual date of site receipt "
A1010 Finish Project 0d 01-Jul-15 01-Jul-15 Finish Project

Mobilization
Mobilizat 55d 01-Nov-15 11-Jan-16 11-Jan-16 11-Jan-16, Mobilization

A26930 Security Fences 15d 01-Nov-15 19-Nov-15 19-Nov-15 Security Fences


A26940 Temporary site utilities 27d 19-Nov-15 24-Dec-15 24-Dec-15 Temporary site utilities
A1050 Site Offices for the Contractor 18d 19-Nov-15 13-Dec-15 13-Dec-15 Site Offices for the Contractor
A1070 Parking Area Preparation 22d 13-Dec-15 11-Jan-16 11-Jan-16 Parking Area Preparation
A1055 Site Offices for the Consultant 18d 13-Dec-15 05-Jan-16 05-Jan-16 Site Offices for the Consultant

Engineering & Procurement


Engineer 576d 01-Jul-15 30-Jul-17 30-Jul-17 30-Jul-17, Engineering &

Final Design
Desig approval 24d 01-Nov-15 01-Dec-15 01-Dec-15 01-Dec-15, Final Design approval
DEA11.08FD Concept Design Approval 6d 01-Nov-15 08-Nov-15 08-Nov-15 Concept Design Approval
DEA11.08FD Architectural Design Drawing 9d 09-Nov-15 19-Nov-15 19-Nov-15 Architectural Design Drawing
DEA11.08FD Structural Design Drawing 9d 21-Nov-15 01-Dec-15 01-Dec-15 Structural Design Drawing
DEA11.08FD Mechanical Design Drawing 9d 21-Nov-15 01-Dec-15 01-Dec-15 Mechanical Design Drawing
DEA11.08FD Electrical Design Drawing 9d 21-Nov-15 01-Dec-15 01-Dec-15 Electrical Design Drawing
Shop Drawings
Draw Submittals 194d 01-Jul-15 15-Mar-16 15-Mar-16 15-Mar-16, Shop Drawings Submittals
Material Submittal
Su / Approval / Procurement 576d 01-Jul-15 30-Jul-17 30-Jul-17 30-Jul-17, Material Subm

Construction Stage
Construc 639d 01-Jul-15 25-Oct-17 25-Oct-17 25-Oc

Main Building
Buildi 492d 09-Nov-15 14-Aug-17 14-Aug-17 14-Aug-17, Main Build
Substructure
Substructu 130d 09-Nov-15 26-Apr-16 26-Apr-16 26-Apr-16, Substructure
A23900 Excavation work 19d 09-Nov-15 02-Dec-15 02-Dec-15 Excavation work
A23910 Soil Replacement 9d 03-Dec-15 14-Dec-15 14-Dec-15 Soil Replacement
A23920 Plain concrete 5d 15-Dec-15 21-Dec-15 21-Dec-15 Plain concrete
A23930 Waterproofing & Screed Protection 11d 22-Dec-15 04-Jan-16 04-Jan-16 Waterproofing & Screed Protection
A23940 Raft Foundation 19d 05-Jan-16 28-Jan-16 28-Jan-16 Raft Foundation
A23950 R.C for Column necks & Retaining wall 13d 02-Feb-16 18-Feb-16 18-Feb-16 R.C for Column necks & Retaining wall necks
A24220 Backfilling up to Slab on Grade level 19d 26-Mar-16 18-Apr-16 18-Apr-16 Backfilling up to Slab on Grade level
A24230 Slab on Grade 5d 20-Apr-16 26-Apr-16 26-Apr-16 Slab on Grade
A23955 R.C. for grade beams 11d 08-Mar-16 21-Mar-16 21-Mar-16 R.C. for grade beams
A23965 Back filling to grade beams level 11d 23-Feb-16 07-Mar-16 07-Mar-16 Back filling to grade beams level
Ground Floor
Flo 364d 19-Apr-16 08-Aug-17 08-Aug-17 08-Aug-17, Ground Flo
Concrete work 67d 30-Apr-16 25-Jul-16 25-Jul-16 25-Jul-16, Concrete work
M.B-B2-2 R.C for Columns 22d 30-Apr-16 28-May-16 28-May-16 R.C for Columns
M.B-B2-3 R.C for Slabs 27d 21-Jun-16 25-Jul-16 25-Jul-16 R.C for Slabs
M.B-B2-3 R.C for Walls 36d 30-Apr-16 14-Jun-16 14-Jun-16 R.C for Walls
Finishing 271d 18-Aug-16 08-Aug-17 08-Aug-17 08-Aug-17, Finishing
A27380 Block work 27d 18-Aug-16 21-Sep-16 21-Sep-16 Block work
A27390 Plaster work 31d 14-Nov-16 24-Dec-16 24-Dec-16 Plaster work
A27500 Painting work - Final Coat 13d 23-Jul-17 08-Aug-17 08-Aug-17 Painting work - Final C
Data centre
cen 1A 71d 25-Dec-16 27-Mar-17 27-Mar-17 27-Mar-17, Data centre 1A
M.B-B2-3 Raised Floor Works 18d 05-Mar-17 27-Mar-17 27-Mar-17 Raised Floor Works
M.B-B2-3 Wall Finishing 18d 17-Jan-17 08-Feb-17 08-Feb-17 Wall Finishing
M.B-B2-3 Floor Finishing 18d 25-Dec-16 16-Jan-17 16-Jan-17 Floor Finishing
M.B-B2-3 Ceiling 18d 09-Feb-17 04-Mar-17 04-Mar-17 Ceiling
M.B-B2-3 Raised Floor Instalation 27d 17-Jan-17 20-Feb-17 20-Feb-17 Raised Floor Instalation
Data centre
cen 1B 71d 17-Jan-17 19-Apr-17 19-Apr-17 19-Apr-17, Data centre 1B

Actual Work Critical Remaining Work Summary Page 1 of 10 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


ADC-GID Classic Schedule Layout 08-Sep-16 09:50

Activity ID Activity Name Original BL Project Actual BL Project Finish 5 2016 2017
Duration Start Start Finish uly A S O N D J F M April May June July A S O N D J F M April May June July A S O N
0 1 0 1 0 2 0 2 0 2 0 2
M.B-B2-4 Raised Floor Works 18d 28-Mar-17 19-Apr-17 19-Apr-17 Raised Floor Works
M.B-B2-4 Wall Finishing 18d 09-Feb-17 04-Mar-17 04-Mar-17 Wall Finishing
M.B-B2-4 Floor Finishing 18d 17-Jan-17 08-Feb-17 08-Feb-17 Floor Finishing
M.B-B2-4 Ceiling 18d 05-Mar-17 27-Mar-17 27-Mar-17 Ceiling
M.B-B2-4 Raised Floor Instalation 18d 09-Feb-17 04-Mar-17 04-Mar-17 Raised Floor Instalation
Technical Corridors
Technica 71d 09-Feb-17 13-May-17 13-May-17 13-May-17, Technical Corridors
M.B-B2-4 Raised Floor Works 18d 20-Apr-17 13-May-17 13-May-17 Raised Floor Works
M.B-B2-4 Wall Finishing 18d 05-Mar-17 27-Mar-17 27-Mar-17 Wall Finishing
M.B-B2-4 Floor Finishing 18d 09-Feb-17 04-Mar-17 04-Mar-17 Floor Finishing
M.B-B2-4 Ceiling 18d 28-Mar-17 19-Apr-17 19-Apr-17 Ceiling
M.B-B2-4 Raised Floor Instalation 18d 05-Mar-17 27-Mar-17 27-Mar-17 Raised Floor Instalation
UPS & Switch
Sw Gear Rooms 40d 20-Apr-17 11-Jun-17 11-Jun-17 11-Jun-17, UPS & Switch Gear Roo
M.B-B2-4 Wall Finishing 13d 08-May-17 24-May-17 24-May-17 Wall Finishing
M.B-B2-5 Floor Finishing 13d 25-May-17 11-Jun-17 11-Jun-17 Floor Finishing
M.B-B2-5 Ceiling 13d 20-Apr-17 07-May-17 07-May-17 Ceiling
Rooms o
on the outer line 53d 25-Dec-16 04-Mar-17 04-Mar-17 04-Mar-17, Rooms on the outer line
M.B-B2-5 Painting Work - Putty & First coat 18d 17-Jan-17 08-Feb-17 08-Feb-17 Painting Work - Putty & First coat
M.B-B2-5 Floor Finishing 18d 25-Dec-16 16-Jan-17 16-Jan-17 Floor Finishing
M.B-B2-5 Ceiling 18d 09-Feb-17 04-Mar-17 04-Mar-17 Ceiling
Wet Area 44d 25-Dec-16 19-Feb-17 19-Feb-17 19-Feb-17, Wet Area
A27420 Wall Ceramic work 13d 05-Jan-17 22-Jan-17 22-Jan-17 Wall Ceramic work
A27450 Waterproofing for wet Area 9d 25-Dec-16 04-Jan-17 04-Jan-17 Waterproofing for wet Area
A29630 Ceiling work 11d 06-Feb-17 19-Feb-17 19-Feb-17 Ceiling work
A29770 Floor Ceramic work 11d 23-Jan-17 05-Feb-17 05-Feb-17 Floor Ceramic work
Offices 53d 25-Dec-16 04-Mar-17 04-Mar-17 04-Mar-17, Offices
M.B-B2-5 Glass Partitions 13d 29-Jan-17 14-Feb-17 14-Feb-17 Glass Partitions
M.B-B2-5 Floor Finishing 13d 25-Dec-16 10-Jan-17 10-Jan-17 Floor Finishing
M.B-B2-5 Ceiling 13d 15-Feb-17 04-Mar-17 04-Mar-17 Ceiling
M.B-B2-5 Gypsom Partitions 13d 11-Jan-17 28-Jan-17 28-Jan-17 Gypsom Partitions
Stairs 53d 30-Aug-16 07-Nov-16 07-Nov-16 07-Nov-16, Stairs
M.B-B2-5 Wall Finishing 18d 22-Sep-16 15-Oct-16 15-Oct-16 Wall Finishing
M.B-B2-5 Floor Finishing 18d 16-Oct-16 07-Nov-16 07-Nov-16 Floor Finishing
M.B-B2-6 Ceiling 18d 30-Aug-16 21-Sep-16 21-Sep-16 Ceiling
Doors & w
windows 116d 17-Jan-17 17-Jun-17 17-Jun-17 17-Jun-17, Doors & windows
A28060 wooden doors 4d 17-Jan-17 22-Jan-17 22-Jan-17 wooden doors
A28070 Aluminum doors 4d 20-Feb-17 25-Feb-17 25-Feb-17 Aluminum doors
A28080 Metal doors 4d 12-Jun-17 17-Jun-17 17-Jun-17 Metal doors
MEP work 350d 19-Apr-16 22-Jul-17 22-Jul-17 22-Jul-17, MEP work
Mechanical work
Mechanic 164d 18-Aug-16 21-Mar-17 21-Mar-17 21-Mar-17, Mechanical work
Plumbing System
Plumbin 155d 18-Aug-16 08-Mar-17 08-Mar-17 08-Mar-17, Plumbing System
A27610 Potable water piping above false ceiling 13d 18-Aug-16 04-Sep-16 04-Sep-16 Potable water piping above false ceiling
A27620 Drainage pipes below slab 9d 18-Aug-16 29-Aug-16 29-Aug-16 Drainage pipes below slab
A27640 Drainage pipes in block wall 12d 22-Sep-16 08-Oct-16 08-Oct-16 Drainage pipes in block wall
A27650 Potable Water Piping in block wall 9d 22-Sep-16 03-Oct-16 03-Oct-16 Potable Water Piping in block wall
A27660 Sanitary Fixtures and Toilet Accessories 13d 20-Feb-17 08-Mar-17 08-Mar-17 Sanitary Fixtures and Toilet Accessories
A27670 Residential Electric Water Heater 11d 23-Jan-17 05-Feb-17 05-Feb-17 Residential Electric Water Heater
A27680 Isolating Valves & Water Hammer Arres 11d 06-Feb-17 19-Feb-17 19-Feb-17 Isolating Valves & Water Hammer Arrestors
Fire Fighting
Figh System 164d 18-Aug-16 20-Mar-17 20-Mar-17 20-Mar-17, Fire Fighting System
A27540 Black steel pipes and Fittings 22d 18-Aug-16 15-Sep-16 15-Sep-16 Black steel pipes and Fittings

Actual Work Critical Remaining Work Summary Page 2 of 10 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


ADC-GID Classic Schedule Layout 08-Sep-16 09:50

Activity ID Activity Name Original BL Project Actual BL Project Finish 5 2016 2017
Duration Start Start Finish uly A S O N D J F M April May June July A S O N D J F M April May June July A S O N
0 1 0 1 0 2 0 2 0 2 0 2
A27550 Fire fighting Sprinklers 12d 05-Mar-17 20-Mar-17 20-Mar-17 Fire fighting Sprinklers
A27560 Novec piping and fitting installation 27d 14-Nov-16 18-Dec-16 18-Dec-16 Novec piping and fitting installation
A27570 Zone Control Valve Assembly 6d 24-Oct-16 31-Oct-16 31-Oct-16 Zone Control Valve Assembly
A27580 Fire Hose Cabinets 6d 09-Feb-17 16-Feb-17 16-Feb-17 Fire Hose Cabinets
A27590 Landing Valves 6d 16-Oct-16 23-Oct-16 23-Oct-16 Landing Valves
A27600 Novec Cylinders and Nozzles 13d 19-Dec-16 04-Jan-17 04-Jan-17 Novec Cylinders and Nozzles
HVAC System
Sy 164d 18-Aug-16 21-Mar-17 21-Mar-17 21-Mar-17, HVAC System
A27690 Chilled water Piping & valves 67d 18-Aug-16 13-Nov-16 13-Nov-16 Chilled water Piping & valves
A27700 Indoor Unit Installation 40d 14-Nov-16 04-Jan-17 04-Jan-17 Indoor Unit Installation
A27710 Air Terminals 13d 05-Mar-17 21-Mar-17 21-Mar-17 Air Terminals
A27720 Duct work installation 27d 30-Aug-16 03-Oct-16 03-Oct-16 Duct work installation
A27730 Duct Insulation 13d 04-Oct-16 20-Oct-16 20-Oct-16 Duct Insulation
A27740 Fire Dampers and Access doors 13d 04-Oct-16 20-Oct-16 20-Oct-16 Fire Dampers and Access doors
A28110 Chilled water Piping insulation 36d 14-Nov-16 29-Dec-16 29-Dec-16 Chilled water Piping insulation
A28120 Crac & inrow units 27d 31-Dec-16 02-Feb-17 02-Feb-17 Crac & inrow units
Electrical work 350d 19-Apr-16 22-Jul-17 22-Jul-17 22-Jul-17, Electrical work
A27750 Piping 1st Fix 40d 22-Sep-16 13-Nov-16 13-Nov-16 Piping 1st Fix
A27760 Wire pulling 27d 14-Nov-16 18-Dec-16 18-Dec-16 Wire pulling
A27770 Panel boards and termination 27d 19-Dec-16 22-Jan-17 22-Jan-17 Panel boards and termination
A27780 Lighting fixture and wiring devices 18d 28-Mar-17 19-Apr-17 19-Apr-17 Lighting fixture and wiring devices
A27790 Cable tray and fittings 53d 01-Aug-16 09-Oct-16 09-Oct-16 Cable tray and fittings
A27800 Cable Pulling 27d 10-Oct-16 13-Nov-16 13-Nov-16 Cable Pulling
A27810 Earthing 18d 09-Feb-17 04-Mar-17 04-Mar-17 Earthing
A27820 1st fix in slab on grade 9d 19-Apr-16 30-Apr-16 30-Apr-16 1st fix in slab on grade
A27990 UPS Instalation 44d 25-May-17 22-Jul-17 22-Jul-17 UPS Instalation
Low current
curr work 222d 22-Sep-16 10-Jul-17 10-Jul-17 10-Jul-17, Low current work
A27840 Public Address 1st Fix 18d 22-Sep-16 15-Oct-16 15-Oct-16 Public Address 1st Fix
A27850 Public Address 2nd Fix 9d 16-Oct-16 26-Oct-16 26-Oct-16 Public Address 2nd Fix
A27860 Public Address 3rd fix installation 9d 27-Oct-16 07-Nov-16 07-Nov-16 Public Address 3rd fix installation
A27870 Fire Alarm 1st Fix 18d 22-Sep-16 15-Oct-16 15-Oct-16 Fire Alarm 1st Fix
A27880 Fire Alarm 2nd Fix 9d 16-Oct-16 26-Oct-16 26-Oct-16 Fire Alarm 2nd Fix
A27890 Fire Alarm 3rd Fix 9d 27-Oct-16 07-Nov-16 07-Nov-16 Fire Alarm 3rd Fix
A27900 CCTV 1st Fix 18d 22-Sep-16 15-Oct-16 15-Oct-16 CCTV 1st Fix
A27910 CCTV 2nd Fix 9d 16-Oct-16 26-Oct-16 26-Oct-16 CCTV 2nd Fix
A27920 CCTV 3rd Fix 9d 27-Oct-16 07-Nov-16 07-Nov-16 CCTV 3rd Fix
A27930 Access Control 1st Fix 18d 22-Sep-16 15-Oct-16 15-Oct-16 Access Control 1st Fix
A27940 Access Control 2nd Fix 9d 16-Oct-16 26-Oct-16 26-Oct-16 Access Control 2nd Fix
A27950 Access Control 3rd Fix 9d 27-Oct-16 07-Nov-16 07-Nov-16 Access Control 3rd Fix
A27960 MATV 1st Fix 18d 22-Sep-16 15-Oct-16 15-Oct-16 MATV 1st Fix
A27970 MATV 2nd Fix 9d 16-Oct-16 26-Oct-16 26-Oct-16 MATV 2nd Fix
A27980 MATV 3rd Fix 9d 27-Oct-16 07-Nov-16 07-Nov-16 MATV 3rd Fix
A28000 BMS 1st fix 18d 22-Sep-16 15-Oct-16 15-Oct-16 BMS 1st fix
A28020 BMS 2nd fix 9d 16-Oct-16 26-Oct-16 26-Oct-16 BMS 2nd fix
A28030 BMS 3rd fix 13d 27-Oct-16 13-Nov-16 13-Nov-16 BMS 3rd fix
A28040 Data & telephone system 1st fix 27d 22-Sep-16 26-Oct-16 26-Oct-16 Data & telephone system 1st fix
A28050 Data & telephone system 2nd fix 27d 27-Oct-16 30-Nov-16 30-Nov-16 Data & telephone system 2nd fix
A28130 Data & telephone system 3rd fix 18d 01-Dec-16 24-Dec-16 24-Dec-16 Data & telephone system 3rd fix
A28140 Racks instalations 80d 28-Mar-17 10-Jul-17 10-Jul-17 Racks instalations
First Floor 292d 28-Jul-16 14-Aug-17 14-Aug-17 14-Aug-17, First Floo

Actual Work Critical Remaining Work Summary Page 3 of 10 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


ADC-GID Classic Schedule Layout 08-Sep-16 09:50

Activity ID Activity Name Original BL Project Actual BL Project Finish 5 2016 2017
Duration Start Start Finish uly A S O N D J F M April May June July A S O N D J F M April May June July A S O N
0 1 0 1 0 2 0 2 0 2 0 2
Concrete work 68d 28-Jul-16 25-Oct-16 25-Oct-16 25-Oct-16, Concrete work
M.B-B2-6 R.C for Columns 22d 28-Jul-16 25-Aug-16 25-Aug-16 R.C for Columns
M.B-B2-6 R.C for Slabs 27d 21-Sep-16 25-Oct-16 25-Oct-16 R.C for Slabs
M.B-B2-6 R.C for Walls 36d 31-Jul-16 14-Sep-16 14-Sep-16 R.C for Walls
Finishing 205d 19-Nov-16 14-Aug-17 14-Aug-17 14-Aug-17, Finishing
A31660 Block work 11d 19-Nov-16 01-Dec-16 01-Dec-16 Block work
A31670 Plaster work 13d 12-Dec-16 28-Dec-16 28-Dec-16 Plaster work
A31680 Painting work - Final Coat 13d 29-Jul-17 14-Aug-17 14-Aug-17 Painting work - Final C
Offices & Rooms area 92d 29-Dec-16 27-Apr-17 27-Apr-17 27-Apr-17, Offices & Rooms area
M.B-B2-8 Glass Partitions 19d 21-Feb-17 16-Mar-17 16-Mar-17 Glass Partitions
M.B-B2-8 Floor Finishing - Porcelain 18d 29-Dec-16 21-Jan-17 21-Jan-17 Floor Finishing - Porcelain
M.B-B2-8 Ceiling Finishing - Aqusting for offices 18d 05-Apr-17 27-Apr-17 27-Apr-17 Ceiling Finishing - Aqusting for offices
M.B-B2-8 Ceiling Finishing - Gypsum board for B 18d 05-Apr-17 27-Apr-17 27-Apr-17 Ceiling Finishing - Gypsum board for Bed Ro
A32300 Flooring work Terrazzo 18d 29-Dec-16 21-Jan-17 21-Jan-17 Flooring work Terrazzo
M.B-B2-8 Gypsom Partitions 23d 22-Jan-17 20-Feb-17 20-Feb-17 Gypsom Partitions
M.B-B2-9 Painting work - Putty & first coat 16d 15-Mar-17 04-Apr-17 04-Apr-17 Painting work - Putty & first coat
A32340 Carpet For Mosque 9d 22-Jan-17 01-Feb-17 01-Feb-17 Carpet For Mosque
Hall Way area 36d 29-Dec-16 13-Feb-17 13-Feb-17 13-Feb-17, Hall Way area
M.B-B2-7 Painting work - Putty & first coat 18d 29-Dec-16 21-Jan-17 21-Jan-17 Painting work - Putty & first coat
M.B-B2-7 Floor Finishing ( Porcelain) 18d 22-Jan-17 13-Feb-17 13-Feb-17 Floor Finishing ( Porcelain)
M.B-B2-7 Ceiling Aqusting tiles 18d 22-Jan-17 13-Feb-17 13-Feb-17 Ceiling Aqusting tiles
Technical Rooms
Technica 28d 05-Apr-17 11-May-17 11-May-17 11-May-17, Technical Rooms
M.B-B2-7 Wall Finishing 11d 05-Apr-17 18-Apr-17 18-Apr-17 Wall Finishing
M.B-B2-7 Floor Finishing 9d 19-Apr-17 30-Apr-17 30-Apr-17 Floor Finishing
M.B-B2-7 Ceiling 9d 01-May-17 11-May-17 11-May-17 Ceiling
Cafeteria 39d 10-Apr-17 30-May-17 30-May-17 30-May-17, Cafeteria
M.B-B2-6 Wall Finishing 18d 10-Apr-17 02-May-17 02-May-17 Wall Finishing
M.B-B2-7 Floor Finishing 16d 26-Apr-17 16-May-17 16-May-17 Floor Finishing
M.B-B2-7 Ceiling 18d 08-May-17 30-May-17 30-May-17 Ceiling
Wet Area 68d 29-Dec-16 27-Mar-17 27-Mar-17 27-Mar-17, Wet Area
A31690 Wall Ceramic work 18d 17-Jan-17 08-Feb-17 08-Feb-17 Wall Ceramic work
A31700 Waterproofing for wet Area 14d 29-Dec-16 16-Jan-17 16-Jan-17 Waterproofing for wet Area
A31710 Ceiling work 18d 05-Mar-17 27-Mar-17 27-Mar-17 Ceiling work
A31720 Floor Ceramic work 18d 09-Feb-17 04-Mar-17 04-Mar-17 Floor Ceramic work
Stairs 53d 22-Jan-17 01-Apr-17 01-Apr-17 01-Apr-17, Stairs
M.B-B2-8 Wall Finishing 18d 14-Feb-17 08-Mar-17 08-Mar-17 Wall Finishing
M.B-B2-8 Floor Finishing 18d 09-Mar-17 01-Apr-17 01-Apr-17 Floor Finishing
M.B-B2-8 Ceiling Finishing 18d 22-Jan-17 13-Feb-17 13-Feb-17 Ceiling Finishing
Director area
a 43d 10-May-17 04-Jul-17 04-Jul-17 04-Jul-17, Director area
M.B-B2-6 Wall Finishing 18d 27-May-17 18-Jun-17 18-Jun-17 Wall Finishing
M.B-B2-6 Floor Tiles 18d 10-May-17 01-Jun-17 01-Jun-17 Floor Tiles
M.B-B2-6 Ceiling 18d 12-Jun-17 04-Jul-17 04-Jul-17 Ceiling
Doors & w
windows 76d 14-Feb-17 23-May-17 23-May-17 23-May-17, Doors & windows
A32250 Wooden doors 18d 14-Feb-17 08-Mar-17 08-Mar-17 Wooden doors
A32260 Aluminum doors 18d 14-Feb-17 08-Mar-17 08-Mar-17 Aluminum doors
A32270 Metal doors 18d 01-May-17 23-May-17 23-May-17 Metal doors
MEP work 192d 19-Nov-16 27-Jul-17 27-Jul-17 27-Jul-17, MEP work
Mechanical work
Mechanic 187d 19-Nov-16 20-Jul-17 20-Jul-17 20-Jul-17, Mechanical work
Plumbing System
Plumbin 112d 19-Nov-16 13-Apr-17 13-Apr-17 13-Apr-17, Plumbing System

Actual Work Critical Remaining Work Summary Page 4 of 10 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


ADC-GID Classic Schedule Layout 08-Sep-16 09:50

Activity ID Activity Name Original BL Project Actual BL Project Finish 5 2016 2017
Duration Start Start Finish uly A S O N D J F M April May June July A S O N D J F MApril May June July A S O N
0 1 0 1 0 2 0 2 0 2 0 2
A32040 Potable water piping above false ceiling 4d 19-Nov-16 23-Nov-16 23-Nov-16 Potable water piping above false ceiling
A32050 Drainage pipes above false ceiling 9d 19-Nov-16 29-Nov-16 29-Nov-16 Drainage pipes above false ceiling
A32070 Drainage pipes in block wall 12d 03-Dec-16 18-Dec-16 18-Dec-16 Drainage pipes in block wall
A32080 Potable Water Piping in block wall 9d 03-Dec-16 13-Dec-16 13-Dec-16 Potable Water Piping in block wall
A32090 Sanitary Fixtures and Toilet Accessories 13d 28-Mar-17 13-Apr-17 13-Apr-17 Sanitary Fixtures and Toilet Accessories
A32100 Residential Electric Water Heater 11d 24-Nov-16 07-Dec-16 07-Dec-16 Residential Electric Water Heater
A32110 Isolating Valves & Water Hammer Arres 11d 08-Dec-16 21-Dec-16 21-Dec-16 Isolating Valves & Water Hammer Arrestors
Fire Fighting
Figh System 187d 19-Nov-16 20-Jul-17 20-Jul-17 20-Jul-17, Fire Fighting Sys
A32120 Black steel pipes and Fittings 22d 19-Nov-16 17-Dec-16 17-Dec-16 Black steel pipes and Fittings
A32130 Fire fighting Sprinklers 12d 05-Jul-17 20-Jul-17 20-Jul-17 Fire fighting Sprinklers
A32140 Novec piping and fitting installation 27d 03-Dec-16 05-Jan-17 05-Jan-17 Novec piping and fitting installation
A32150 Zone Control Valve Assembly 6d 14-Feb-17 21-Feb-17 21-Feb-17 Zone Control Valve Assembly
A32160 Fire Hose Cabinets 6d 14-Feb-17 21-Feb-17 21-Feb-17 Fire Hose Cabinets
A32170 Landing Valves 6d 09-Mar-17 16-Mar-17 16-Mar-17 Landing Valves
A32180 Novec Cylinders and Nozzles 13d 07-Jan-17 23-Jan-17 23-Jan-17 Novec Cylinders and Nozzles
HVAC System
Sy 181d 19-Nov-16 13-Jul-17 13-Jul-17 13-Jul-17, HVAC System
A32190 Chilled water Piping & Valves 67d 19-Nov-16 13-Feb-17 13-Feb-17 Chilled water Piping & Valves
A32200 Indoor Unit Installation 40d 14-Feb-17 06-Apr-17 06-Apr-17 Indoor Unit Installation
A32210 Air Terminals 11d 01-Jul-17 13-Jul-17 13-Jul-17 Air Terminals
A32220 Duct work installation 27d 03-Dec-16 05-Jan-17 05-Jan-17 Duct work installation
A32230 Duct Insulation 13d 07-Jan-17 23-Jan-17 23-Jan-17 Duct Insulation
A32240 Fire Dampers and Access doors 13d 02-Apr-17 18-Apr-17 18-Apr-17 Fire Dampers and Access doors
A32192 Chilled water Piping insulation 36d 14-Feb-17 01-Apr-17 01-Apr-17 Chilled water Piping insulation
Electrical work 192d 19-Nov-16 27-Jul-17 27-Jul-17 27-Jul-17, Electrical work
A31730 Piping 1st Fix 53d 03-Dec-16 09-Feb-17 09-Feb-17 Piping 1st Fix
A31740 Wire pulling 27d 11-Feb-17 16-Mar-17 16-Mar-17 Wire pulling
A31750 Panel boards and termination 27d 14-Feb-17 20-Mar-17 20-Mar-17 Panel boards and termination
A31760 Lighting fixture and wiring devices 18d 05-Jul-17 27-Jul-17 27-Jul-17 Lighting fixture and wiring
A31770 Cable tray and fittings 40d 19-Nov-16 09-Jan-17 09-Jan-17 Cable tray and fittings
A31780 Cable Pulling 27d 10-Jan-17 13-Feb-17 13-Feb-17 Cable Pulling
Low current
curr work 75d 28-Nov-16 05-Mar-17 05-Mar-17 05-Mar-17, Low current work
A31820 Public Address 1st Fix 11d 28-Nov-16 11-Dec-16 11-Dec-16 Public Address 1st Fix
A31830 Public Address 2nd Fix 9d 12-Dec-16 22-Dec-16 22-Dec-16 Public Address 2nd Fix
A31840 Public Address 3rd fix installation 9d 24-Dec-16 03-Jan-17 03-Jan-17 Public Address 3rd fix installation
A31850 Fire Alarm 1st Fix 11d 28-Nov-16 11-Dec-16 11-Dec-16 Fire Alarm 1st Fix
A31860 Fire Alarm 2nd Fix 9d 12-Dec-16 22-Dec-16 22-Dec-16 Fire Alarm 2nd Fix
A31870 Fire Alarm 3rd Fix 9d 24-Dec-16 03-Jan-17 03-Jan-17 Fire Alarm 3rd Fix
A31880 CCTV 1st Fix 11d 28-Nov-16 11-Dec-16 11-Dec-16 CCTV 1st Fix
A31890 CCTV 2nd Fix 9d 12-Dec-16 22-Dec-16 22-Dec-16 CCTV 2nd Fix
A31900 CCTV 3rd Fix 9d 24-Dec-16 03-Jan-17 03-Jan-17 CCTV 3rd Fix
A31910 Access Control 1st Fix 11d 28-Nov-16 11-Dec-16 11-Dec-16 Access Control 1st Fix
A31920 Access Control 2nd Fix 9d 12-Dec-16 22-Dec-16 22-Dec-16 Access Control 2nd Fix
A31930 Access Control 3rd Fix 9d 24-Dec-16 03-Jan-17 03-Jan-17 Access Control 3rd Fix
A31940 MATV 1st Fix 11d 28-Nov-16 11-Dec-16 11-Dec-16 MATV 1st Fix
A31950 MATV 2nd Fix 9d 12-Dec-16 22-Dec-16 22-Dec-16 MATV 2nd Fix
A31960 MATV 3rd Fix 9d 24-Dec-16 03-Jan-17 03-Jan-17 MATV 3rd Fix
A31970 Data & Telephone system 1st fix 27d 03-Dec-16 05-Jan-17 05-Jan-17 Data & Telephone system 1st fix
A31980 BMS 1st fix 11d 28-Nov-16 11-Dec-16 11-Dec-16 BMS 1st fix
A32000 BMS 2nd fix 9d 12-Dec-16 22-Dec-16 22-Dec-16 BMS 2nd fix

Actual Work Critical Remaining Work Summary Page 5 of 10 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


ADC-GID Classic Schedule Layout 08-Sep-16 09:50

Activity ID Activity Name Original BL Project Actual BL Project Finish 5 2016 2017
Duration Start Start Finish uly A S O N D J F M April May June July A S O N D J F M April May June July A S O N
0 1 0 1 0 2 0 2 0 2 0 2
A32010 BMS 3rd fix 9d 24-Dec-16 03-Jan-17 03-Jan-17 BMS 3rd fix
A31972 Data & Telephone system 2nd fix 27d 07-Jan-17 09-Feb-17 09-Feb-17 Data & Telephone system 2nd fix
A31974 Data & Telephone system 3rd fix 18d 11-Feb-17 05-Mar-17 05-Mar-17 Data & Telephone system 3rd fix
Roof Floor 218d 30-Oct-16 10-Aug-17 10-Aug-17 10-Aug-17, Roof Floor
Concrete work 22d 30-Oct-16 27-Nov-16 27-Nov-16 27-Nov-16, Concrete work
A21100 Roof Concrete work 22d 30-Oct-16 27-Nov-16 27-Nov-16 Roof Concrete work
Finishing 182d 15-Dec-16 10-Aug-17 10-Aug-17 10-Aug-17, Finishing
A21110 Block work 13d 15-Dec-16 01-Jan-17 01-Jan-17 Block work
A21120 Plaster work 18d 02-Jan-17 24-Jan-17 24-Jan-17 Plaster work
A21140 Painting work putty & First coat 7d 23-Feb-17 04-Mar-17 04-Mar-17 Painting work putty & First coat
A21240 Painting work - Final Touch 9d 31-Jul-17 10-Aug-17 10-Aug-17 Painting work - Final T
A27230 Roof Waterproofing System 22d 25-Jan-17 22-Feb-17 22-Feb-17 Roof Waterproofing System
Doors & w
windows 18d 23-Feb-17 18-Mar-17 18-Mar-17 18-Mar-17, Doors & windows
A21170 Metal doors 4d 23-Feb-17 28-Feb-17 28-Feb-17 Metal doors
A26490 Windows 4d 13-Mar-17 18-Mar-17 18-Mar-17 Windows
MEP work 160d 02-Jan-17 30-Jul-17 30-Jul-17 30-Jul-17, MEP work
Mechanical work
Mechanic 160d 02-Jan-17 30-Jul-17 30-Jul-17 30-Jul-17, Mechanical wo
Plumbing System
Plumbin 31d 25-Jan-17 06-Mar-17 06-Mar-17 06-Mar-17, Plumbing System
A21180 Potable water and Drainage piping 9d 23-Feb-17 06-Mar-17 06-Mar-17 Potable water and Drainage piping
A21440 Roof Drains 9d 25-Jan-17 05-Feb-17 05-Feb-17 Roof Drains
HVAC System
Sy 120d 23-Feb-17 30-Jul-17 30-Jul-17 30-Jul-17, HVAC System
A21320 Duct & Insulation works 107d 23-Feb-17 12-Jul-17 12-Jul-17 Duct & Insulation works
A21470 Sound Attenuator installation 13d 13-Jul-17 30-Jul-17 30-Jul-17 Sound Attenuator installa
A29290 Fans installation 13d 23-Feb-17 12-Mar-17 12-Mar-17 Fans installation
A29310 AHU instalations 40d 23-Feb-17 16-Apr-17 16-Apr-17 AHU instalations
Elevators work
Elevator 80d 02-Jan-17 16-Apr-17 16-Apr-17 16-Apr-17, Elevators work
A21280 Installation of Elevators 80d 02-Jan-17 16-Apr-17 16-Apr-17 Installation of Elevators
Electrical work 67d 23-Feb-17 21-May-17 21-May-17 21-May-17, Electrical work
A21200 Lightning protection works 27d 05-Mar-17 08-Apr-17 08-Apr-17 Lightning protection works
A21210 Cable Tray Installation 40d 23-Feb-17 16-Apr-17 16-Apr-17 Cable Tray Installation
A21220 Cables and wires pulling and equipment 27d 17-Apr-17 21-May-17 21-May-17 Cables and wires pulling and equipment
A21230 Lighting fixture, wiring devices and othe 9d 05-Mar-17 15-Mar-17 15-Mar-17 Lighting fixture, wiring devices and other third fix
A21290 Panel board instalation 27d 05-Mar-17 08-Apr-17 08-Apr-17 Panel board instalation
Low current
curr work 111d 02-Jan-17 27-May-17 27-May-17 27-May-17, Low current work
A21250 BMS 1st Fix 27d 02-Jan-17 05-Feb-17 05-Feb-17 BMS 1st Fix
A21260 BMS 2nd Fix 18d 23-Feb-17 18-Mar-17 18-Mar-17 BMS 2nd Fix
A21270 BMS 3rd fix 13d 19-Mar-17 04-Apr-17 04-Apr-17 BMS 3rd fix
A21300 CCTV instalation 40d 05-Apr-17 27-May-17 27-May-17 CCTV instalation
General work
w 102d 02-Jan-17 15-May-17 15-May-17 15-May-17, General work
Service Building
Bu 604d 01-Jul-15 09-Sep-17 09-Sep-17 09-Sep-17, Serv
Substructure
Substructu 108d 27-Apr-16 15-Sep-16 15-Sep-16 15-Sep-16, Substructure
A31570 Excavation work 16d 27-Apr-16 17-May-16 17-May-16 Excavation work
A31590 Plain concrete 4d 30-May-16 04-Jun-16 04-Jun-16 Plain concrete
A31610 Foundation 12d 13-Jun-16 28-Jun-16 28-Jun-16 Foundation
A31620 R.C for Column necks 9d 03-Jul-16 13-Jul-16 13-Jul-16 R.C for Column necks
A31640 Backfilling up to Slab on Grade level 12d 24-Aug-16 08-Sep-16 08-Sep-16 Backfilling up to Slab on Grade level
A31650 Slab on Grade 5d 10-Sep-16 15-Sep-16 15-Sep-16 Slab on Grade
A32330 Soil Replacement 9d 18-May-16 29-May-16 29-May-16 Soil Replacement
A31625 Back filling up to grade beams level 12d 18-Jul-16 02-Aug-16 02-Aug-16 Back filling up to grade beams level

Actual Work Critical Remaining Work Summary Page 6 of 10 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


ADC-GID Classic Schedule Layout 08-Sep-16 09:50

Activity ID Activity Name Original BL Project Actual BL Project Finish 5 2016 2017
Duration Start Start Finish uly A S O N D J F M April May June July A S O N D J F M April May June July A S O N
0 1 0 1 0 2 0 2 0 2 0 2
A31635 R.C. for grade beams & Trenches 16d 03-Aug-16 23-Aug-16 23-Aug-16 R.C. for grade beams & Trenches
A31959 Water proofing for tanks 6d 05-Jun-16 12-Jun-16 12-Jun-16 Water proofing for tanks
Ground Floor
Flo 604d 01-Jul-15 09-Sep-17 09-Sep-17 09-Sep-17, Gro
Concrete work 44d 17-Sep-16 12-Nov-16 12-Nov-16 12-Nov-16, Concrete work
M.B-B2-3 R.C for Columns 13d 17-Sep-16 03-Oct-16 03-Oct-16 R.C for Columns
M.B-B2-3 R.C for Slabs 27d 09-Oct-16 12-Nov-16 12-Nov-16 R.C for Slabs
M.B-B2-3 R.C.for water tanks walls 22d 17-Sep-16 15-Oct-16 15-Oct-16 R.C.for water tanks walls
Finishing 182d 06-Dec-16 01-Aug-17 01-Aug-17 01-Aug-17, Finishing
A30840 Block work 27d 06-Dec-16 09-Jan-17 09-Jan-17 Block work
A30850 Plaster work 27d 21-Mar-17 24-Apr-17 24-Apr-17 Plaster work
A30860 Painting work - Final Coat 22d 04-Jul-17 01-Aug-17 01-Aug-17 Painting work - Final Coa
Wet Area 20d 25-Apr-17 20-May-17 20-May-17 20-May-17, Wet Area
A30940 Wall Ceramic work 6d 01-May-17 08-May-17 08-May-17 Wall Ceramic work
A30950 Waterproofing for wet Area 4d 25-Apr-17 30-Apr-17 30-Apr-17 Waterproofing for wet Area
A30960 Ceiling work 4d 15-May-17 20-May-17 20-May-17 Ceiling work
A30970 Floor Ceramic work 4d 09-May-17 14-May-17 14-May-17 Floor Ceramic work
Offices 28d 13-May-17 18-Jun-17 18-Jun-17 18-Jun-17, Offices
A30880 Flooring work Porcelain 6d 24-May-17 31-May-17 31-May-17 Flooring work Porcelain
A30920 Ceiling work 13d 01-Jun-17 18-Jun-17 18-Jun-17 Ceiling work
A30930 Painting work putty & First coat 9d 13-May-17 23-May-17 23-May-17 Painting work putty & First coat
Transformers & Generator Area
Transform 22d 25-Apr-17 23-May-17 23-May-17 23-May-17, Transformers & Generator
A32320 Flooring work - Epoxy 13d 07-May-17 23-May-17 23-May-17 Flooring work - Epoxy
A32350 Painting work putty & First coat 9d 25-Apr-17 06-May-17 06-May-17 Painting work putty & First coat
Water Tank
Tan Area 27d 25-Apr-17 29-May-17 29-May-17 29-May-17, Water Tank Area
A32390 Internal water proofing 27d 25-Apr-17 29-May-17 29-May-17 Internal water proofing
Technical Rooms
Technica 9d 07-May-17 17-May-17 17-May-17 17-May-17, Technical Rooms
M.B-B2-8 Painting work putty & First coat 4d 07-May-17 11-May-17 11-May-17 Painting work putty & First coat
M.B-B2-9 Floor Finishing 4d 13-May-17 17-May-17 17-May-17 Floor Finishing
Corridors and Stairs 28d 24-May-17 29-Jun-17 29-Jun-17 29-Jun-17, Corridors and Stairs
A30980 Flooring work 18d 07-Jun-17 29-Jun-17 29-Jun-17 Flooring work
A31000 Painting work putty & First coat 11d 24-May-17 06-Jun-17 06-Jun-17 Painting work putty & First coat
Doors & w
windows 557d 01-Jul-15 05-Jul-17 05-Jul-17 05-Jul-17, Doors & windows
A31530 wooden doors 6d 01-Jun-17 08-Jun-17 08-Jun-17 wooden doors
A31550 Metal doors 4d 01-Jul-17 05-Jul-17 05-Jul-17 Metal doors
A31560 Aluminum windows 4d 01-Jul-15 06-Jul-15 06-Jul-15 Aluminum windows
A31555 Roll Shutter doors 18d 24-May-17 15-Jun-17 15-Jun-17 Roll Shutter doors
MEP work 233d 05-Nov-16 09-Sep-17 09-Sep-17 09-Sep-17, MEP
Mechanical work
Mechanic 182d 10-Jan-17 09-Sep-17 09-Sep-17 09-Sep-17, Mec
Plumbing System
Plumbin 133d 10-Jan-17 03-Jul-17 03-Jul-17 03-Jul-17, Plumbing System
A31320 Potable water piping above false ceiling 9d 10-Jan-17 21-Jan-17 21-Jan-17 Potable water piping above false ceiling
A31330 Drainage pipes below slab 9d 10-Jan-17 21-Jan-17 21-Jan-17 Drainage pipes below slab
A31350 Drainage pipes in block wall 9d 10-Jan-17 21-Jan-17 21-Jan-17 Drainage pipes in block wall
A31360 Potable Water Piping in block wall 9d 10-Jan-17 21-Jan-17 21-Jan-17 Potable Water Piping in block wall
A31370 Sanitary Fixtures and Toilet Accessories 9d 10-Jun-17 20-Jun-17 20-Jun-17 Sanitary Fixtures and Toilet Acces
A31380 Residential Electric Water Heater 9d 22-Jan-17 01-Feb-17 01-Feb-17 Residential Electric Water Heater
A31390 Isolating Valves & Water Hammer Arres 9d 10-Jan-17 21-Jan-17 21-Jan-17 Isolating Valves & Water Hammer Arrestors
A31580 Instalation of pumps 36d 18-May-17 03-Jul-17 03-Jul-17 Instalation of pumps
Fire Fighting
Figh System 102d 25-Apr-17 09-Sep-17 09-Sep-17 09-Sep-17, Fire
A31400 Black steel pipes and Fittings 13d 25-Apr-17 11-May-17 11-May-17 Black steel pipes and Fittings

Actual Work Critical Remaining Work Summary Page 7 of 10 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


ADC-GID Classic Schedule Layout 08-Sep-16 09:50

Activity ID Activity Name Original BL Project Actual BL Project Finish 5 2016 2017
Duration Start Start Finish uly A S O N D J F M April May June July A S O N D J F M April May June July A S O N
0 1 0 1 0 2 0 2 0 2 0 2
A31410 Fire fighting Sprinklers 7d 19-Jun-17 27-Jun-17 27-Jun-17 Fire fighting Sprinklers
A31420 Novec piping and fitting installation 53d 13-May-17 20-Jul-17 20-Jul-17 Novec piping and fitting inst
A31430 Zone Control Valve Assembly 4d 06-Jul-17 11-Jul-17 11-Jul-17 Zone Control Valve Assembly
A31440 Fire Hose Cabinets 9d 07-Jun-17 18-Jun-17 18-Jun-17 Fire Hose Cabinets
A31450 Landing Valves 4d 01-Jul-17 05-Jul-17 05-Jul-17 Landing Valves
A31460 Novec Cylinders and Nozzles 36d 22-Jul-17 09-Sep-17 09-Sep-17 Novec Cylinders
HVAC System
Sy 131d 10-Jan-17 29-Jun-17 29-Jun-17 29-Jun-17, HVAC System
A31470 Chilled water piping & valves instalatio 13d 10-Jan-17 26-Jan-17 26-Jan-17 Chilled water piping & valves instalation
A31480 Indoor Unit Installation 13d 05-Feb-17 21-Feb-17 21-Feb-17 Indoor Unit Installation
A31490 Air Terminals 9d 19-Jun-17 29-Jun-17 29-Jun-17 Air Terminals
A31500 Duct work installation 27d 10-Jan-17 13-Feb-17 13-Feb-17 Duct work installation
A31510 Duct Insulation 13d 14-Feb-17 02-Mar-17 02-Mar-17 Duct Insulation
A31520 Fire Dampers and Access doors 13d 04-Mar-17 20-Mar-17 20-Mar-17 Fire Dampers and Access doors
A32430 Chilled water piping isulation 6d 28-Jan-17 04-Feb-17 04-Feb-17 Chilled water piping isulation
Electrical work 181d 05-Nov-16 29-Jun-17 29-Jun-17 29-Jun-17, Electrical work
A31010 Piping 1st Fix 27d 10-Jan-17 13-Feb-17 13-Feb-17 Piping 1st Fix
A31020 Wire pulling 18d 14-Feb-17 08-Mar-17 08-Mar-17 Wire pulling
A31040 Lighting fixture and wiring devices 18d 07-Jun-17 29-Jun-17 29-Jun-17 Lighting fixture and wiring devic
A31050 Cable tray and fittings 53d 10-Jan-17 20-Mar-17 20-Mar-17 Cable tray and fittings
A31060 Cable Pulling 40d 21-Mar-17 11-May-17 11-May-17 Cable Pulling
A31070 Earthing 13d 14-Feb-17 02-Mar-17 02-Mar-17 Earthing
A31090 MDB & ATS connection & termination 62d 16-Jan-17 06-Apr-17 06-Apr-17 MDB & ATS connection & termination
A31250 Instalation of Generators 27d 25-Mar-17 27-Apr-17 27-Apr-17 Instalation of Generators
A32410 Instalation of transformers 27d 30-Mar-17 03-May-17 03-May-17 Instalation of transformers
A31340 RMU unit 18d 05-Nov-16 27-Nov-16 27-Nov-16 RMU unit
A32440 Bus way instalation 53d 10-Jan-17 20-Mar-17 20-Mar-17 Bus way instalation
A31270 UPS instalation 27d 10-Dec-16 12-Jan-17 12-Jan-17 UPS instalation
Low current
curr work 138d 18-Dec-16 15-Jun-17 15-Jun-17 15-Jun-17, Low current work
A31100 Public Address 1st Fix 18d 10-Jan-17 01-Feb-17 01-Feb-17 Public Address 1st Fix
A31110 Public Address 2nd Fix 9d 02-Feb-17 13-Feb-17 13-Feb-17 Public Address 2nd Fix
A31120 Public Address 3rd fix installation 9d 14-Feb-17 25-Feb-17 25-Feb-17 Public Address 3rd fix installation
A31130 Fire Alarm 1st Fix 18d 10-Jan-17 01-Feb-17 01-Feb-17 Fire Alarm 1st Fix
A31140 Fire Alarm 2nd Fix 9d 02-Feb-17 13-Feb-17 13-Feb-17 Fire Alarm 2nd Fix
A31150 Fire Alarm 3rd Fix 9d 14-Feb-17 25-Feb-17 25-Feb-17 Fire Alarm 3rd Fix
A31160 CCTV 1st Fix 18d 18-Dec-16 09-Jan-17 09-Jan-17 CCTV 1st Fix
A31170 CCTV 2nd Fix 9d 10-Jan-17 21-Jan-17 21-Jan-17 CCTV 2nd Fix
A31180 CCTV 3rd Fix 9d 22-Jan-17 01-Feb-17 01-Feb-17 CCTV 3rd Fix
A31190 Access Control 1st Fix 18d 10-Jan-17 01-Feb-17 01-Feb-17 Access Control 1st Fix
A31200 Access Control 2nd Fix 9d 02-Feb-17 13-Feb-17 13-Feb-17 Access Control 2nd Fix
A31210 Access Control 3rd Fix 9d 14-Feb-17 25-Feb-17 25-Feb-17 Access Control 3rd Fix
A31220 Data system 1st Fix 53d 10-Jan-17 20-Mar-17 20-Mar-17 Data system 1st Fix
A31230 Data System 2nd Fix 27d 21-Mar-17 24-Apr-17 24-Apr-17 Data System 2nd Fix
A31240 Data System 3rd Fix 40d 25-Apr-17 15-Jun-17 15-Jun-17 Data System 3rd Fix
A31260 BMS 1st fix 40d 10-Jan-17 02-Mar-17 02-Mar-17 BMS 1st fix
A31280 BMS 2nd fix 27d 04-Mar-17 06-Apr-17 06-Apr-17 BMS 2nd fix
A31290 BMS 3rd fix 27d 08-Apr-17 11-May-17 11-May-17 BMS 3rd fix
First Floor 164d 16-Nov-16 18-Jun-17 18-Jun-17 18-Jun-17, First Floor
Finishing 111d 24-Jan-17 18-Jun-17 18-Jun-17 18-Jun-17, Finishing
A32470 Block work 1d 24-Jan-17 24-Jan-17 24-Jan-17 Block work

Actual Work Critical Remaining Work Summary Page 8 of 10 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


ADC-GID Classic Schedule Layout 08-Sep-16 09:50

Activity ID Activity Name Original BL Project Actual BL Project Finish 5 2016 2017
Duration Start Start Finish uly A S O N D J F M April May June July A S O N D J F M April May June July A S O N
0 1 0 1 0 2 0 2 0 2 0 2
A32480 Plastering work 1d 25-Jan-17 25-Jan-17 25-Jan-17 Plastering work
A32490 Painting work - 1st coat 1d 26-Jan-17 26-Jan-17 26-Jan-17 Painting work - 1st coat
A32500 Painting work - final coat 1d 18-Jun-17 18-Jun-17 18-Jun-17 Painting work - final coat
Concrete work 35d 16-Nov-16 31-Dec-16 31-Dec-16 31-Dec-16, Concrete work
A32450 R.C.for Columns 19d 16-Nov-16 10-Dec-16 10-Dec-16 R.C.for Columns
A32460 R.C. for slab 13d 14-Dec-16 31-Dec-16 31-Dec-16 R.C. for slab
Doors & w
windows 87d 28-Jan-17 21-May-17 21-May-17 21-May-17, Doors & windows
A32510 Metal Doors 13d 28-Jan-17 13-Feb-17 13-Feb-17 Metal Doors
A32520 Louvers 18d 29-Apr-17 21-May-17 21-May-17 Louvers
Roof Floor 156d 30-Nov-16 22-Jun-17 22-Jun-17 22-Jun-17, Roof Floor
Concrete work 53d 04-Jan-17 14-Mar-17 14-Mar-17 14-Mar-17, Concrete work
A30780 Roof Concrete work 53d 04-Jan-17 14-Mar-17 14-Mar-17 Roof Concrete work
Finishing 156d 30-Nov-16 22-Jun-17 22-Jun-17 22-Jun-17, Finishing
A30790 Block work 6d 30-Nov-16 07-Dec-16 07-Dec-16 Block work
A30800 Plaster work 6d 08-Dec-16 15-Dec-16 15-Dec-16 Plaster work
A30810 Painting work putty & First coat 4d 09-Apr-17 13-Apr-17 13-Apr-17 Painting work putty & First coat
A30820 Painting work - Final Touch 4d 18-Jun-17 22-Jun-17 22-Jun-17 Painting work - Final Touch
A30830 Roof Waterproofing System 19d 15-Mar-17 08-Apr-17 08-Apr-17 Roof Waterproofing System
MEP work 150d 08-Dec-16 22-Jun-17 22-Jun-17 22-Jun-17, MEP work
Mechanical work
Mechanic 68d 21-Mar-17 17-Jun-17 17-Jun-17 17-Jun-17, Mechanical work
Plumbing System
Plumbin 19d 21-Mar-17 13-Apr-17 13-Apr-17 13-Apr-17, Plumbing System
A30740 Potable water and Drainage piping, fittin 4d 09-Apr-17 13-Apr-17 13-Apr-17 Potable water and Drainage piping, fittings and H
A30750 Roof Drains 4d 21-Mar-17 26-Mar-17 26-Mar-17 Roof Drains
Fire Fighting
Figh System 53d 09-Apr-17 17-Jun-17 17-Jun-17 17-Jun-17, Fire Fighting System
A32660 Pumps Instalation 53d 09-Apr-17 17-Jun-17 17-Jun-17 Pumps Instalation
HVAC System
Sy 53d 09-Apr-17 17-Jun-17 17-Jun-17 17-Jun-17, HVAC System
A30690 Duct & Insulation works 36d 09-Apr-17 24-May-17 24-May-17 Duct & Insulation works
A30700 Sound Attenuator installation 13d 25-May-17 11-Jun-17 11-Jun-17 Sound Attenuator installation
A30710 Fans installation 18d 25-May-17 17-Jun-17 17-Jun-17 Fans installation
A30720 Chiller Units instalation 36d 09-Apr-17 24-May-17 24-May-17 Chiller Units instalation
Electrical work 58d 09-Apr-17 22-Jun-17 22-Jun-17 22-Jun-17, Electrical work
A30650 Lightning protection works 13d 15-Apr-17 01-May-17 01-May-17 Lightning protection works
A30660 Cable Tray Installation 27d 09-Apr-17 13-May-17 13-May-17 Cable Tray Installation
A30670 Cables and wires pulling and equipment 18d 14-May-17 05-Jun-17 05-Jun-17 Cables and wires pulling and equipm
A30680 Lighting fixture, wiring devices and othe 13d 06-Jun-17 22-Jun-17 22-Jun-17 Lighting fixture, wiring devices an
Low current
curr work 42d 08-Dec-16 31-Jan-17 31-Jan-17 31-Jan-17, Low current work
A30610 1st Fix BMS 11d 08-Dec-16 21-Dec-16 21-Dec-16 1st Fix BMS
A30620 2nd Fix BMS 18d 22-Dec-16 14-Jan-17 14-Jan-17 2nd Fix BMS
A30630 3rd fix BMS 13d 15-Jan-17 31-Jan-17 31-Jan-17 3rd fix BMS
A30640 LC 1st Fix 4d 22-Dec-16 27-Dec-16 27-Dec-16 LC 1st Fix
General work
w 15d 08-Dec-16 27-Dec-16 27-Dec-16 27-Dec-16, General work
A30520 Marble Cladding 4d 08-Dec-16 13-Dec-16 13-Dec-16 Marble Cladding
A30590 Installation of handrails 4d 22-Dec-16 27-Dec-16 27-Dec-16 Installation of handrails
A30600 Granite for stair case 4d 17-Dec-16 21-Dec-16 21-Dec-16 Granite for stair case
External Si
Site Work 524d 03-Dec-15 25-Oct-17 25-Oct-17 25-Oc
Civil Works 421d 03-Dec-15 07-Jun-17 07-Jun-17 07-Jun-17, Civil Works
Fuel Tanks 40d 03-Dec-15 24-Jan-16 24-Jan-16 24-Jan-16, Fuel Tanks
A32610 Excavation 9d 03-Dec-15 14-Dec-15 14-Dec-15 Excavation
A32620 R.C. For Raft 9d 15-Dec-15 26-Dec-15 26-Dec-15 R.C. For Raft

Actual Work Critical Remaining Work Summary Page 9 of 10 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation


ADC-GID Classic Schedule Layout 08-Sep-16 09:50

Activity ID Activity Name Original BL Project Actual BL Project Finish 5 2016 2017
Duration Start Start Finish uly A S O N D J F M April May June July A S O N D J F M April May June July A S O N
0 1 0 1 0 2 0 2 0 2 0 2
A32630 R.C.For Walls 13d 27-Dec-15 12-Jan-16 12-Jan-16 R.C.For Walls
A32640 R.C. For slab 9d 13-Jan-16 24-Jan-16 24-Jan-16 R.C. For slab
Car parking
parkin Shed 27d 04-May-17 07-Jun-17 07-Jun-17 07-Jun-17, Car parking Shed
A32650 R.C. For Footing 27d 04-May-17 07-Jun-17 07-Jun-17 R.C. For Footing
Archituctural works
Archituctu 156d 30-Mar-17 25-Oct-17 25-Oct-17 25-Oc
A7990 Concrete & Interlock Tiles 31d 18-Apr-17 28-May-17 28-May-17 Concrete & Interlock Tiles
A8000 Curbstone of sidewalk 23d 30-Mar-17 29-Apr-17 29-Apr-17 Curbstone of sidewalk
A8170 Planting 19d 30-Apr-17 23-May-17 23-May-17 Planting
A8010 Car Parking Shed instalation 71d 20-Jul-17 25-Oct-17 25-Oct-17 Car Pa
A8020 Asphalt works 40d 29-May-17 19-Jul-17 19-Jul-17 Asphalt works
A8030 Fountain instalation 40d 30-Mar-17 21-May-17 21-May-17 Fountain instalation
Mechanical Network Works
Mechanica 120d 28-Nov-16 03-May-17 03-May-17 03-May-17, Mechanical Network Works
A26400 Storm water 58d 18-Feb-17 03-May-17 03-May-17 Storm water
A26390 Drainage Network 40d 28-Nov-16 18-Jan-17 18-Jan-17 Drainage Network
A26450 Water Network 40d 06-Feb-17 29-Mar-17 29-Mar-17 Water Network
A29250 Fire Fighting Network 40d 21-Dec-16 11-Feb-17 11-Feb-17 Fire Fighting Network
A26460 Chilled water Network 40d 14-Jan-17 06-Mar-17 06-Mar-17 Chilled water Network
Electrical w
works 165d 19-Jan-17 23-Aug-17 23-Aug-17 23-Aug-17, Electrica
A8040 Electrical 1st fix 19d 19-Jan-17 12-Feb-17 12-Feb-17 Electrical 1st fix
A8050 Main Cable Pulling 53d 13-Feb-17 23-Apr-17 23-Apr-17 Main Cable Pulling
A8060 Lighting Poles instalation 27d 20-Jul-17 23-Aug-17 23-Aug-17 Lighting Poles instal
A26410 Earthing 13d 13-Feb-17 01-Mar-17 01-Mar-17 Earthing
A8070 Low current cables 18d 24-Apr-17 16-May-17 16-May-17 Low current cables

Furniture 23d 16-Aug-17 18-Sep-17 18-Sep-17 18-Sep-17, Fu


A11890 Installation of Furniture as per interior d 23d 16-Aug-17 18-Sep-17 18-Sep-17 Installation of F

Handing Over 112d 03-Jun-17 31-Oct-17 31-Oct-17 31-O


A29410 Snag List 107d 03-Jun-17 24-Oct-17 24-Oct-17 Snag L
A29420 Preliminary Handing Over 27d 23-Aug-17 01-Oct-17 01-Oct-17 Preliminary
A29430 As Built drawings 80d 20-Jun-17 07-Oct-17 07-Oct-17 As Built dr
A29440 O & M Manuals 22d 29-Aug-17 01-Oct-17 01-Oct-17 O & M Man
A29450 Project Handing over & start maintenan 5d 25-Oct-17 31-Oct-17 31-Oct-17 Proje
A29460 De-Mobilization work 27d 19-Sep-17 24-Oct-17 24-Oct-17 De-Mo

Testing & Commissioning 80d 15-Jul-17 31-Oct-17 31-Oct-17 31-O

A5390 All testing & Commissioning 80d 15-Jul-17 31-Oct-17 31-Oct-17 All te

Actual Work Critical Remaining Work Summary Page 10 of 10 TASK filter: All Activities

Remaining Work Milestone Oracle Corporation