CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

EXPEDIENTE TCNICO : MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. N 34501 EN EL CENTRO POBLADO
DE LORENCILLO I, DISTRITO DE CONSTITUCION-OXAPAMPA-PASCO"
ENTIDAD : GOBIERNO DISTRITAL DE LORENCILLO I HECHO POR
FECHA: 09-02-2017 REVISADO
DIAS CALENDARIO
Item Descripcin Parcial (S/.) TOTAL
1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES
01 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD 232,690.62
01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 220,050.62 220,050.62 220,050.62

01.02 SEGURIDAD Y SALUD 12,640.00 1,580.00 1,580.00 1,580.00 1,580.00 1,580.00 1,580.00 1,580.00 1,580.00 12,640.00

02 REMOCIONES Y DEMOLICIONES 37,576.31 37,576.31 37,576.31

03 MEJORAMIENTO Y ESTABILIZAACION DEL TERRENO CON EL SISTEMA SUELO REFORZADO 335,352.97

TRABAJOS PRELIMINARES

MOVIMIENTO DE TIERRAS

SUELO REFORZADO

GEOSINTETICO 64631.74

CONSTRUCCION DE PABELLON N 01-1ER PISO: 04 AULAS DE 56.60 M2 C/U + 01 ESCALERA DE MATERAIL


04 408,575.84
SEMI-NOBLE
04.01 MOVIMIENTO DE TIERRAS 42,550.06 42550.06 42,550.06

04.02 OBRAS DE CONCRETO SIMPLE 17,806.22 17806.22 17,806.22

04.03 OBRAS DE CONCRETO ARMADO 214,794.11 42958.822 171835.288 214,794.11

04.04 MUROS Y TABIQUES DE ALBAILERIA 23,637.95 18910.36 4727.59 23,637.95

04.05 VARIOS 569.92 569.92 569.92

01.01 REVOQUES Y REVESTIMIENTOS 24,384.64 109,217.58 14630.784 9753.856 133,602.22

01.02 CIELORRASOS 8,792.81 8792.81 8,792.81

01.03 PISOS Y PAVIMENTOS 29,425.16 23540.128 5885.032 29,425.16

01.04 ZOCALOS Y CONTRAZOCALOS 5,988.78 1197.756 4192.146 598.878 5,988.78

01.05 CARPINTERIA DE MADERA 19,467.89 17521.101 1946.789 19,467.89

01.06 CARPINTERIA METALICA 2,023.61 1821.249 202.361 2,023.61

01.07 CERRAJERIA 931.40 931.4 931.40

01.08 PINTURA 13,459.69 13459.69 13,459.69

01.09 VARIOS 4,743.60 4743.6 4,743.60

CONSTRUCCION DE PABELLON N 01-1ER PISO: 04 AULAS DE 56.60 M2 C/U + 01 ESCALERA DE MATERAIL


05 306,042.71
SEMI-NOBLE
05.01 CONCRETO ARMADO 20,853.21 16682.568 2085.321 2085.321 20,853.21

05.02 MUROS Y TABIQUES DE ALBAILERIA 21,393.73 17114.984 4278.746 21,393.73

05.03 ESTRUCTURA DE MADERA 11,644.51 8151.157 3493.353 11644.51

05.04 VARIOS 569.92 569.92 569.92


9
02.01 REVOQUES Y REVESTIMIENTOS 33,785.05 10135.515 23649.535 33,785.05

02.02 CIELO RASOS 17,874.75 10724.85 7149.9 17,874.75

02.03 PISOS Y PAVIENTOS 24,534.43 4906.886 9813.772 9813.772

02.04 ZOCALOS Y CONTRAZOCALOS 5,601.33 3920.931 1680.399 5,601.33

02.05 COBERTURAS 104,095.16 251,581.34 20819.032 83276.128 355,676.50

02.06 CARPINTERIA DE MADERA 20,274.53 4054.906 14192.171 2027.453 20,274.53

02.07 CARPINTERIA METALICA 7,856.12 4713.672 3142.448 7,856.12

02.08 CERRAJERIA 754.72 377.36 377.36 754.72

02.09 PINTURA 17,731.39 7092.556 10638.834 17,731.39

02.10 SISTEMA DE DRENAJE PLUVIAL 15,725.24 15725.24 15,725.24

02.11 VARIOS 3,348.62 3348.62 3,348.62

CONSTRUCCION DE PABELLON N 02-1ER PISO: 01 AULA DE 56.60 M2, COMEDOR EQUIPADO 69.77 M2, 01
06 COCINA 22.40 M2 , TOPICO Y PSICOLOGIA 21.90 M2 , 01 DIRECCION + SECRET+SALA DE 434,809.20
ESPERA+ARCHIVO+S.S.H.H. 56.66 M2 + 01 ESCALERA DE MATERIAL SEMINOBLE
06.01 MOVIMIENTO DE TIERRAS 41,731.95 41731.95 41,731.95

06.02 OBRAS DE CONCRETO SIMPLE 20,131.02 20131.02 20,131.02

06.03 OBRAS DE CONCRETO ARMADO 232,335.00 185868 46,467.00 232,335.00

06.04 MUROS Y TABIQUES DE ALBAILERIA 20,088.78 12053.268 8,035.51 20,088.78

06.05 VARIOS 572.98 572.98 572.98

03.01 MUROS Y TABIQUES DE ALBAILERIA 5,465.88 119,949.47 3279.528 2,186.35 125415.35

03.02 REVOQUES Y REVESTIMIENTOS 26,561.60 21,249.28 5,312.32 26,561.60

03.03 CIELORRASOS 8,874.93 6212.451 2,662.48 8,874.93

03.04 PISOS Y PAVIMENTOS 28,438.80 8531.64 11375.52 8,531.64 28,438.80

03.05 ZOCALOS Y CONTRAZOCALOS 7,763.37 3881.685 3,881.69 7,763.37

03.06 CARPINTERIA DE MADERA 21,208.49 12725.094 8,483.40 21,208.49

03.07 CARPINTERIA METALICA 2,101.46 1471.022 630.44 2,101.46

03.08 CERRAJERIA 1,662.12 1,662.12 1,662.12

03.09 PINTURA 14,019.82 12,617.84 1,401.98 14,019.82

03.10 VARIOS 3,853.00 3,853.00 3,853.00

CONSTRUCCION DE PABELLON N 02-2DO PISO: 01 CENTRO DE RECURSOS EDUCT-BIBLIOTECA 87.10 M2,


07 AULA DE INNOVACION PEDAGOGICA 75.55 M2, S.S.H.H. DAMAS Y VARONES 30.33 M2 Y 01 SALA DE 427,021.89
PROFESORES 36.75 M2
07.01 CONCRETO ARMADO 122,978.54 98382.832 24595.708 122,978.54

07.02 MUROS Y TABIQUES DE ALBAILERIA 23,865.66 9546.264 14319.396 23,865.66

07.03 ESTRUCTURA DE MADERA 11,609.06 2321.812 9287.248 11,609.06

07.04 VARIOS 566.74 566.74 566.74

04.01 MUROS Y TABIQUES DE ALBAILERIA 15,104.66 268,001.89 3020.932 9062.796 3020.932 283106.55

04.02 REVOQUES Y REVESTIMIENTOS 32,341.71 22639.197 9702.513 32,341.71


CRONOGRAMA DE AVANCE DE OBRA VALORIZADO
EXPEDIENTE TCNICO : MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. N 34501 EN EL CENTRO POBLADO
DE LORENCILLO I, DISTRITO DE CONSTITUCION-OXAPAMPA-PASCO"
ENTIDAD : GOBIERNO DISTRITAL DE LORENCILLO I HECHO POR
FECHA: 09-02-2017 REVISADO
DIAS CALENDARIO
Item Descripcin Parcial (S/.) TOTAL
1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES
04.03 CIELO RASOS 18,042.45 14433.96 3608.49 18,042.45

04.04 PISOS Y PAVIMENTOS 22,586.90 6776.07 15810.83 22,586.90

04.05 ZOCALOS Y CONTRAZOCALOS 9,065.59 6345.913 2719.677 9,065.59

04.06 COBERTURAS 104,095.16 93685.644 10409.516 104,095.16

04.07 CARPINTERIA DE MADERA 23,795.97 23795.97 23795.97

04.08 CARPINTERIA METALICA 8,231.76 8231.76 8,231.76

04.09 CERRAJERIA 1,991.48 1991.48 1,991.48

04.10 PINTURA 15,648.89 15648.89 15,648.89

04.11 SISTEMA DE DRENAJE PLUVIAL 15,725.24 15725.24 15,725.24

04.12 VARIOS 1,372.08 1372.08 1,372.08

08 CONSTRUCCION DE S.U.M DE MATERAIL NOBLE A= 232.10 M2 502,855.64


08.01 MOVIMIENTO DE TIERRAS 18,741.30 18741.3 18741.3

08.02 OBRAS DE CONCRETO SIMPLE 13,866.78 4160.034 9706.746 13866.78

08.03 OBRAS DE CONCRETO ARMADO 180,723.97 144579.176 36144.794 180723.97

08.04 ESTRUCTURAS METALICAS 21,096.82 6329.046 14767.774 21096.82

08.05 COBERTURAS 34,358.94 34358.94 34358.94

08.06 VARIOS 1,971.30 1971.3 1971.3

05.01 MUROS Y TABIQUES DE ALBAILERIA 16,371.29 232,096.53 9822.774 6548.516 248467.82

05.02 REVOQUES Y REVESTIMIENTOS 29,823.40 11929.36 17894.04 29823.4

05.03 CIELORRASOS 44,745.20 13423.56 13423.56 17898.08 44745.2

05.04 PISOS Y PAVIMENTOS 20,972.26 8388.904 6291.678 6291.678 20972.26

05.05 ZOCALOS Y CONTRAZOCALOS 8,155.47 4893.282 3262.188 8155.47

05.06 CARPINTERIA DE MADERA 6,791.40 6791.4 6791.4

05.07 CARPINTERIA METALICA Y HERRERIA 89,292.09 89292.09 89292.09

05.08 CERRAJERIA 2,951.54 2951.54 2951.54

05.09 PINTURA 10,874.26 2174.852 8699.408 10874.26

05.10 VARIOS 2,119.62 2119.62 2119.62

09 CONSTRUCCION DE SERVICOS HIGIENICOS DE MATERAIL NOBLE A=66.20 M2 166,069.56


09.01 MOVIMIENTO DE TIERRAS 16,694.27 16694.27 16694.27

09.02 OBRAS DE CONCRETO SIMPLE 5,105.03 5105.03 5105.03


9
09.03 OBRAS DE CONCRETO ARMADO 38,070.06 22842.036 7614.012 7614.012 38070.06

09.05 ESTRUCTURA DE MADERA 3,440.91 2752.728 688.182 3440.91

09.06 VARIOS 308.20 308.2 308.2

06.01 MUROS Y TABIQUES DE ALBAILERIA 7,296.81 102,451.09 5837.448 1459.362 109747.9

06.02 REVOQUES Y REVESTIMIENTOS 14,693.06 11754.448 2938.612 14693.06

06.03 CIELO RASOS 12,879.52 3863.856 7727.712 1287.952 12879.52

06.04 PISOS Y PAVIMENTOS 12,007.33 3602.199 7204.398 1200.733 12007.33

06.05 ZOCALOS Y CONTRAZOCALOS 11,716.93 5858.465 5858.465 11716.93

06.06 COBERTURAS 23,321.70 6996.51 16325.19 23321.7

06.07 CARPINTERIA DE MADERA 7,848.93 6279.144 1569.786 7848.93

06.08 CARPINTERIA METALICA 478.00 191.2 286.8 478

06.09 CERRAJERIA 1,522.11 1522.11 1522.11

06.10 PINTURA 5,631.25 1689.375 3941.875 5631.25

06.11 SISTEMA DE DRENAJE PLUVIAL 3,564.17 3564.17 3564.17

06.12 VARIOS 1,491.28 1491.28 1491.28

10 CONSTRUCCION DE TRIBUNAS Y COBERTURA METALICA DE LOSA DEPORTIVA 879,223.81


10.01 MOVIMIENTO DE TIERRAS 67,291.55 67291.55 67291.55

10.032 OBRAS DE CONCRETO SIMPLE 55,348.21 55,348.21 55348.21

10.03 OBRAS DE CONCRETO ARMADO 389,002.63 311202.104 77800.526 389002.63

10.04 MUROS Y TABIQUES DE ALBAILERIA 35,116.08 14046.432 21069.648 35116.08

10.05 ESTRUCTURA METALICA Y COBERTURAS 215,501.44 86200.576 129300.864 215501.44

07.01 REVOQUES Y REVESTIMIENTOS 55,652.81 116,963.90 11130.562 22261.124 22261.124 172616.71

07.02 CIELORRASOS 5,525.78 3868.046 1657.734 5525.78

07.03 PISOS Y PAVIMENTOS 4,013.10 802.62 3210.48 4013.1

07.04 ZOCALOS Y CONTRAZOCALOS 1,425.11 712.555 712.555 1425.11

07.05 CARPINTERIA DE MADERA 760.06 304.024 304.024 152.012 760.06

07.06 CARPINTERIA METALICA 14,955.18 10468.626 4486.554 14955.18

07.07 PINTURAS 29,903.72 29,903.72 29903.72

07.08 SISTEMA DE DRENAJE PLUVIAL 4,728.14 4,728.14 4728.14


CRONOGRAMA DE AVANCE DE OBRA VALORIZADO
EXPEDIENTE TCNICO : MEJORAMIENTO Y AMPLIACION DE LOS SERVICIOS DE EDUCACION PRIMARIA EN LA I.E. N 34501 EN EL CENTRO POBLADO
DE LORENCILLO I, DISTRITO DE CONSTITUCION-OXAPAMPA-PASCO"
ENTIDAD : GOBIERNO DISTRITAL DE LORENCILLO I HECHO POR
FECHA: 09-02-2017 REVISADO
DIAS CALENDARIO
Item Descripcin Parcial (S/.) TOTAL
1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES 8 MES
11 CONSTRUCCION DE LOSA MULTI-DEPORTIVA(720M2) 69,114.67
11.01 MOVIMIENTO DE TIERRAS 9,897.02 9,897.02 9,897.02

11.02 OBRAS DE CONCRETO SIMPLE 48,425.89 48,425.89 48,425.89

08.01 CARPINTERIA METALICA 3,959.34 10,791.76 3,959.34 14,751.10

08.02 PINTURAS 2,111.14 2,111.14 2,111.14

08.03 VARIOS 4,721.28 4,721.28 4,721.28

12 CONSTRUCCION DE TANQUE ELEVADO CAP:8.00 M3 36,803.69


12.01 MOVIMIENTO DE TIERRAS 2,601.73 2,601.73 2,601.73

12.02 OBRAS DE CONCRETO SIMPLE 1,448.76 1,448.76 1,448.76

12.03 OBRAS DE CONCRETO ARMADO 24,266.78 16986.746 7280.034 24,266.78

09.01 REVOQUES Y REVESTIMIENTOS 4,889.20 8,486.42 2444.6 2444.6 13,375.62

09.02 PISOS Y PAVIMENTOS 734.55 587.64 146.91 734.55

09.03 PINTURA 1,096.04 1,096.04 1,096.04

09.04 VARIOS 1,766.63 1,766.63 1,766.63

CONSTRUCCION DE CERCO PERIMETRICO (213.50 ML) Y PORTICO DE INGRESO PRINCIPAL


13 656,624.77
13.01 CERCO METALICO H=3.00 m, L=457.90m 563,577.25
13.01.01 MOVIMIENTO DE TIERRAS 55,117.52 55,117.52 55117.52

13.01.02 OBRAS DE CONCRETO SIMPLE 104,735.44 104,735.44 104735.44

13.01.03 OBRAS DE CONCRETO ARMADO 228,486.51 159940.557 68545.953 228486.51

13.01.04 VARIOS 0

10.01.01 REVOQUES Y REVESTIMIENTOS 11,386.61 175,237.78 5693.305 5693.305 186624.39

10.01.02 CARPINTERIA METALICA 163,851.17 163,851.17 163851.17

13.02 PORTICO DE INGRESO PRINCIPAL 93,047.52


13.02.01 MOVIMIENTO DE TIERRAS 2,234.60 2,234.60 2,234.60

13.02.02 OBRAS DE CONCRETO SIMPLE 174.92 174.92 174.92

13.02.03 OBRAS DE CONCRETO ARMADO 73,468.77 66121.893 7346.877 73,468.77

10.02.01 REVOQUES Y REVESTIMIENTOS 3,803.44 17,169.23 1901.72 1901.72 20,972.67

10.02.02 PISOS Y PAVIMENTOS 1,995.04 1396.528 598.512 1,995.04

10.02.03 ZOCALOS Y CONTRAZOCALOS 38.69 38.69 38.69

10.02.04 ESTRUCTURA DE MADERA Y COBERTURA 1,784.75 1070.85 713.9 1784.75

10.02.05 CARPINTERIA METALICA 6,726.47 4708.529 2017.941 6726.47

10.02.06 CERRAJERIA 881.35 881.35 881.35

10.02.07 PINTURA 1,317.43 1,317.43 1317.43

10.02.08 VARIOS 622.06 622.06 622.06

14 OBRAS EXTERIORES(VEREDAS, JARDINERAS, PODIO DE BANDERAS Y RAMPAS) 44,850.34


14.01 MOVIMIENTO DE TIERRAS 1,643.64 0.00

14.02 OBRAS DE CONCRETO ARMADO 1,501.23 0.00

11.01 PISOS Y PAVIMENTOS 24,861.39 41,705.47 41,705.47

11.03 VARIOS 16,844.08 0.00

15 IMPACTO AMBIENTAL 6,499.72


15.01 MEDIDAS DE PREVENCION 300.00 0.00

15.02 PROGRAMA DE EDUCACION AMBIENTAL 300.00 0.00

15.03 MEDIOS DE CONCIENTIZACION 600.00 0.00

15.04 PROTECCION DE AREAS SENSIBLES 4,799.72 0.00

15.05 MEDIDAS DE CONTINGENCIA 500.00 0.00

13 EQUIPAMIENTO Y MOBILIARIO 146,155.00


13.01 MOBILIARIO 53,395.00 0.00

13.02 EQUIPAMIENTO 92,760.00 0.00

16 INSTALACIONES ELECTRICAS 131,396.00 13,139.60 13,139.60 13,139.60 13,139.60 13,139.60 13,139.60 13,139.60 91,977.20

17 INSTALACIONES SANITARIAS 146,713.48 14,671.35 14,671.35 14,671.35 14,671.35 14,671.35 14,671.35 14,671.35 102,699.44

Costo Directo 4,492,761.68 1,712,859.39 204,298.42 585,844.08 831,045.66 1,022,718.58 884,931.06 526,596.76 37,443.86 ###
Gastos Generales 10% 449,276.17 171,285.94 20,429.84 58,584.41 83,104.57 102,271.86 88,493.11 52,659.68 3,744.39 578,122.14
Utilidad 10% 449,276.17 171,285.94 20,429.84 58,584.41 83,104.57 102,271.86 88,493.11 52,659.68 3,744.39 578,122.14
Sub Total 5,391,314.02 2,055,431.27 245,158.10 703,012.89 997,254.79 1,227,262.30 1,061,917.27 631,916.11 44,932.63 ###
IGV 18% 970,436.52 369,977.63 44,128.46 126,542.32 179,505.86 220,907.21 191,145.11 113,744.90 8,087.87 ###
Valor Total Referencial 6,361,750.53 2,425,408.90 289,286.56 829,555.21 ### 1,448,169.51 1,253,062.38 745,661.01 53,020.51 ###
CALENDARIO DE DESEMBOLSOS
OBRA :"AMPLIACION DE LA INFRAESTRUCTURA EDUCATIVA Y MEJORAMIENTO DE LOS SERVICIOS COMPLEMENTARIOS DE LA
ENTIDAD : GOBIERNO REGIONAL DE UCAYALI
FECHA : NOVIEMBRE 2012

PLAZO
ITEM ESPECIALIDAD UND CANTIDAD PRECIO UNIT PARCIAL
MES 01
1 ESTRUCTURAS und 1.00 1,606,601.71 1,606,601.71 321,320.34
2 ARQUITECTURA und 1.00 858,636.19 858,636.19 29,273.54
3 INSTALACIONES ELECTRICAS und 1.00 159,605.23 159,605.23 0.00
4 INSTALACIONES SANITARIAS und 1.00 134,881.08 134,881.08 0.00
COSTO DIRECTO(S/.) 2,759,724.21 350,593.88
GASTOS 275,972.42 35,059.39
GENERALES(10%)
UTILIDADES(1 275,972.42 35,059.39
0%)
SUB TOTAL 3,311,669.05 420,712.65
I.G.V.(18%) 596,100.43 75,728.28
EQUIPAMIENT 184,988.60 0.00
O
TOTAL DEL 4,092,758.08 496,440.93
PRESUPUESTO

20.00
3.41
DESEMBOLSOS
VICIOS COMPLEMENTARIOS DE LA I.E. N 65002 AURISTELA DAVILA ZEVALLOS"

PLAZO DE EJECUCION
TOTAL(S/.)
MES 02 MES 03 MES 04 MES 05 MES 06
610,508.65 321,320.34 176,726.19 160,660.17 16,066.02 1,606,601.71
155,389.07 170,658.63 249,475.99 221,239.71 32,599.26 858,636.19
6,046.87 23,596.22 40,900.14 49,261.58 39,800.42 159,605.23
6,306.27 15,898.49 22,949.43 36,393.41 53,333.49 134,881.08
778,250.86 531,473.68 490,051.74 467,554.87 141,799.19 2,759,724.21
77,825.09 53,147.37 49,005.17 46,755.49 14,179.92 275,972.42
77,825.09 53,147.37 49,005.17 46,755.49 14,179.92 275,972.42
933,901.03 637,768.41 588,062.09 561,065.85 170,159.03 3,311,669.06
168,102.19 114,798.31 105,851.18 100,991.85 30,628.62 596,100.43
0.00 0.00 0.00 0.00 186,729.10 186,729.10
1,102,003.22 752,566.73 693,913.27 662,057.70 387,516.75 4,094,498.59

38.00 20.00 11.00 10.00 1.00


18.10 19.88 29.05 25.77 3.80 100
3.79 14.78 25.63 30.86 24.94
4.68 11.79 17.01 26.98 39.54

Anda mungkin juga menyukai