PROGRESS PER AREA

No PEKERJAAN KUBIKASI BETON SAT YANG SUDAH DIKERJAKAN SAT PERSENTASE (%) KETERANGAN
AREA 1
1 Pondasi gantry mPA1 13,565 m3 13,565 m3 100% Selesai
BORE PILE 4 TITIK D400 9,04 m3 9,04 m3 100% Selesai
2 Pondasi gantry mPA2 13,565 m3 13,565 m3 100% Selesai
BORE PILE 4 TITIK D400 9,04 m3 9,04 m3 100% Selesai
3 Pondasi gantry mPA3 13,565 m3 13,565 m3 100% Selesai
BORE PILE 4 TITIK D400 9,04 m3 9,04 m3 100% Selesai
4 Pondasi gantry mPA4 13,565 m3 13,565 m3 100% Selesai
BORE PILE 4 TITIK D400 9,04 m3 9,04 m3 100% Selesai
5 Pondasi gantry mPA5 13,565 m3 13,565 m3 100% Selesai
BORE PILE 4 TITIK D400 9,04 m3 9,04 m3 100% Selesai
6 Pondasi gantry mPA6a 13,565 m3 13,565 m3 100% Selesai
BORE PILE 4 TITIK D400 9,04 m3 9,04 m3 100% Selesai
7 Pondasi gantry Mpa6b 13,565 m3 13,565 m3 100% Selesai
BORE PILE 4 TITIK D400 9,04 m3 9,04 m3 100% Selesai
8 Pondasi post insulator 13,565 m3 13,565 m3 100% Selesai
9 Pondasi disconecting switch axis 1' 11,826 m3 11,826 m3 100% Selesai
10 Pondasi disconecting Switch axis 2' 11,826 m3 11,826 m3 100% Selesai
11 Pondasi disconecting Switch axis 3' 11,826 m3 11,826 m3 100% Selesai
12 Pondasi post insulator 2,432 m3 2,432 m3 100% Selesai
13 Pondasi CB dead tank type 16,69 m3 16,69 m3 100% Selesai
14 Pondasi surge arrester 8,94 m3 8,940 m3 100% Selesai
15 Pondasi transformer 46,286 m3 0 m3 0%
BORE PILE 12 TITIK D400 27,12 m3 27,12 m3 100% Selesai
16 Pondasi oil tank 42,379 m3 42,379 m3 100% Selesai
BORE PILE 6 TITIK D400 13,56 m3 13,56 m3 100% Selesai
364,685 m3 318,399 m3 87,31%
AREA 2
1 Pondasi surge arrester 4,526 m3 4,526 m3 100% Selesai
2 Pondasi potential transformer 4,53 m3 4,53 m3 100% Selesai
3 Pondasi disconnecting switch (4 Unit) 21,07 m3 10,43 m3 50% Dalam Proses
4 Pondasi gantry mP1 (6 Unit) 19,008 m3 7,2864 m3 38% Dalam Proses
BORE PILE 1 UNIT 2 TITIK D300 15,24 m3 15,24 m3 100% Selesai
5 Pondasi capacitor bank (3 Unit) 41,664 m3 41,664 m3 100% Selesai
BORE PILE 1 UNIT 4 TITIK D300 15,24 m3 15,24 m3 100% Selesai
6 Pondasi (m12,m16) (3 Unit) 26,865 m3 26,865 m3 100% Selesai
7 Pondasi potential transformer 4,53 m3 m3 0%
8 Pondasi post insulator (3 Unit) 13,565 m3 m3 0%
9 Pondasi current transformer 4,832 m3 m3 0%
171,07 m3 125,78 m3 73,53%
AREA 3
1 Pondasi capacitor bank (6 Unit) 78,12 m3 m3 0%
Bore pile 4 titik D300 30,48 m3 30,48 m3 100% Selesai
2 Pondasi (m12,m16) (6 Unit) 8,955 m3 m3 0%
3 Pondasi disconnecting switch (6 Unit) 3,95 m3 m3 0%
4 Pondasi post insulator (6 Unit) 81,39 m3 m3 0%
202,895 m3 30,48 m3 15%
AREA 4
1 Pondasi capacitor bank (2 Unit) 26,04 m3 m3 0%
Bore pile 4 titik D300 10,16 m3 10,16 m3 100% Selesai
2 Pondasi (m12,m16) (2 Unit) 17,91 m3 m3 0%
3 Pondasi disconnecting switch (2 Unit) 7,9 m3 m3 0%
4 Pondasi post insulator (2 Unit) 27,13 m3 m3 0%
89,14 m3 10,16 m3 11%
AREA 3 DAN 4 292,035 m3 40,64 m3 14%
AREA 5
1 Pondasi gantry mP3 (2 Unit) 9,728 m3 4,608 m3 47% Dalam Proses
Bore pile 2 titik D300 5,08 m3 5,08 m3 100% Selesai
2 Pondasi gantry mP2 (3 Unit) 14,592 m3 2,304 m3 16% Dalam Proses
Bore pile 2 titik D300 7,62 m3 7,62 m3 100% Selesai
3 Pondasi post insulator (2 Unit) 27,13 m3 m3 0%
4 Pondasi mCSE 2,432 m3 m3 0%
5 Pondasi (m13-B,m12, m16) (2 Unit) 13,069 m3 m3 0%
6 Pondasi (mCSE, m16) 13,054 m3 m3 0%
92,705 m3 19,612 m3 21%
AREA 2 DAN 5 263,775 m3 145,39 m3 55,12%
AREA 6
1 AU 1,2 m3 m3
1,2 m3 0 m3 0%

NOTE :
Progress Area 1 naik menjadi 87,31% dari 74,61%.
Progress Area 2 naik menjadi 73,53 dari 70,51%.
Progress Area 2 dan 5 naik menjadi 55,12% dari 50,54%.