I PEKERJAAN PERSIAPAN 400,000.00

II PEKERJAAN RENOVASI KANTOR BP3K KECAMATAN TULIS


A PEKERJAAN LANTAI 399,089.16
B PEKERJAAN KUNCI DAN PENGGANTUNG 2,058,500.00
C PEKERJAAN SANITASI 1,566,050.00
D PEKERJAAN PENGECATAN 4,534,128.15
E PEKERJAAN PAVING 22,860,989.28
JUMLAH II 31,418,756.59

JUMLAH TOTAL ( I + II ) 31,818,756.59

PPN 10 % 3,181,875.66

JUMLAH TOTAL 35,000,632.25

JUMLAH TOTAL ( DIBULATKAN ) 35,000,000.00

TERBILANG : TIGA PULUH LIMA JUTA RUPIAH

BATANG, 2014
MENYETUJUI DIPERIKSA DIRENCANAKAN
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS / PPHP CV. PIRAMID REKATAMA KONS
KETUA

EDI SANTOSO, SH DANANG PURWANTO, ST, MM ADI PRABOWO, ST


NIP. 19680615 199312 1 002 NIP. 19800826 200501 1 009 Direktur

MENGETAHUI / / MENYETUJUI MENGETAHUI


KEPALA BADAN PELAKSANA PENYULUHAN KABID. TATA BANGUNAN DAN LINGKUNGAN
DAN KETAHANAN PANGAN KABUPATEN BATANG DCKTRESDM KABUPATEN BATANG

Drs. MURDIYONO, MM NURHARYANTO, ST


NIP. 19620727 198607 1 001 NIP. 19670510 199903 1 004

-1
DANG PERTANIAN / SARANA DAN PRASARANA PENYULUHAN PERTANIAN

KABID. TATA BANGUNAN DAN LINGKUNGAN

-2
RENCANA ANGGARAN BIAYA

KEGIATAN : DAK NON DR BIDANG PERTANIAN / SARANA DAN PRASARANA PENYULUHAN PERTANIAN
PEKERJAAN : RENOVASI KANTOR BP3K KECAMATAN TULIS
LOKASI : KECAMATAN TULIS KABUPATEN BATANG
TAHUN : 2014

HARGA JUMLAH
NO JENIS PEKERJAAN VOLUME ANALISA SATUAN HARGA

( Rp ) ( Rp )
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1 Papan Nama Kegiatan 1.00 ls taksir 100,000.00 100,000.00
2 Pekerjaan Pengukuran, Pembongkaran dan Mobilisasi Peralatan 1.00 ls taksir 300,000.00 300,000.00
JUMLAH - I 400,000.00

II PEKERJAAN RENOVASI KANTOR BP3K KECAMATAN TULIS


A PEKERJAAN LANTAI
1 Perbaikan Rabat Keliling Teras 0.548 m3 CT.3b.1 728,929.97 399,089.16
SUB TOTAL - A 399,089.16
B PEKERJAAN KUNCI DAN PENGGANTUNG
1 Pasang Kunci Tanam 9.000 bh KK.1c 156,500.00 1,408,500.00
2 Pasang Pintu KM/WC PVC 1.000 bh taksir 400,000.00 400,000.00
3 Perbaikan Pintu Masuk Pagar Halaman Kantor 1.000 ls taksir 250,000.00 250,000.00
SUB TOTAL - B 2,058,500.00
C PEKERJAAN SANITASI
1 Pasang Closet Jongkok 1.000 bh SNT.1e 391,050.00 391,050.00
2 Perbaikan Bak Mandi (Bocor) 1.000 ls taksir 200,000.00 200,000.00
3 Perbaikan / Rehab Septictank & peresapan 1.000 unit taksir 850,000.00 850,000.00
4 Pasang Kran Air Bak Cuci Dapur (model leher angsa) 1.000 bh taksir 125,000.00 125,000.00
SUB TOTAL - D 1,566,050.00
D PEKERJAAN PENGECATAN
1 Pek. Cat Kayu 113.321 m2 CT.2e 33,393.00 3,784,128.15
2 Pek. Cat Tralis 1.000 ls taksir 750,000.00 750,000.00
SUB TOTAL - D 4,534,128.15

-3
HARGA JUMLAH
NO JENIS PEKERJAAN VOLUME ANALISA SATUAN HARGA

( Rp ) ( Rp )
1 2 3 4 5 6

E PEKERJAAN PAVING, KANSTEIN, DAN RABAT BETON


1 Pasang Paving Hexagonal, tbl = 6 cm K -175 195.143 m2 BOW 91,000.00 17,758,019.83
2 Pasang Kanstein 39.000 m1 taksir 85,000.00 3,315,000.00
3 Plesteran Kanstein batu kali + Acian (existing) 16.500 m2 SNI 2837 : 2008.6.6 39,778.20 656,340.30
4 Pengecatan Kanstein (exterior) 30.150 m2 CT.3b.1 21,661.00 653,079.15
5 Pengecoran beton pintu masuk 1 : 2 : 3 0.563 m3 taksir 850,000.00 478,550.00
SUB TOTAL - E 22,860,989.28
JUMLAH - II 31,418,756.59

JUMLAH TOTAL ( I + II ) 31,818,756.59

PPN 10 % 3,181,875.66

JUMLAH TOTAL 35,000,632.25

JUMLAH TOTAL ( DIBULATKAN ) 35,000,000.00

TERBILANG : TIGA PULUH LIMA JUTA RUPIAH

BATANG, 2014
MENYETUJUI DIPERIKSA DIRENCANAKAN
PEJABAT PEMBUAT KOMITMEN TIM TEKNIS / PPHP CV. PIRAMID REKATAMA
KETUA

EDI SANTOSO, SH DANANG PURWANTO, ST, MM ADI PRABOWO, ST


NIP. 19680615 199312 1 002 NIP. 19800826 200501 1 009 Direktur

MENGETAHUI / / MENYETUJUI MENGETAHUI


KEPALA BADAN PELAKSANA PENYULUHAN KABID. TATA BANGUNAN DAN LINGKUNGAN
DAN KETAHANAN PANGAN KABUPATEN BATANG DCKTRESDM KABUPATEN BATANG

Drs. MURDIYONO, MM NURHARYANTO, ST


NIP. 19620727 198607 1 001 NIP. 19670510 199903 1 004

-4
NA DAN PRASARANA PENYULUHAN PERTANIAN

-5
-632.25

-6
DAFTAR HARGA SATUAN PEKERJAAN

KEGIATAN : DAK NON DR BIDANG PERTANIAN / SARANA DAN PRASARANA PENYULUHAN PERTANIAN
PEKERJAAN : RENOVASI KANTOR BP3K KECAMATAN TULIS
LOKASI : KECAMATAN TULIS KABUPATEN BATANG
TAHUN : 2014

NO KODE ANALISA PEKERJAAN SAT HARGA SATUAN

1 2 3 4 5

PEKERJAAN TANAH
1 SNI 2835 :2008 .6.1 Galian tanah biasa m3 Rp 39,000.00
2 SNI 2835 :2008 .6.9 Urugan tanah kembali m3 Rp 13,000.00
3 SNI 2835 :2008 .6.11 Urugan pasir m3 Rp 188,400.00
4 SNI 2835 :2008 .6.15.b Urugan Tanah Baru m3 Rp 68,000.00
5 SNI 2835 :2008 .6.15.c Urugan Tanah ( tanah sudah ada di lokasi / bekas galian ) m3 Rp 14,000.00

PEKERJAAN DINDING
1 SNI 6897 :2008 .6.11 Pasangan batu bata camp. 1 : 6 tebal 1/2 bata m2 Rp 100,639.00

PEKERJAAN PLESTERAN
1 SNI 2837 : 2008.6.6 Plesteran tebal 15 mm dengan campuran 1 : 6 + Acian m2 Rp 39,778.20

PEKERJAAN BETON
1 SNI 7394 : 2008. 6.4 Pekerjan lantai kerja / rabat beton m3 Rp 728,929.97

PEKERJAAN KUNCI DAN KACA


1 KK.1c Pasang kunci tanam bh Rp 156,500.00

PEKERJAAN SANITASI
1 SNT.1e Memasang kloset jongkok porselen bh Rp 391,050.00
2 SNT.13a Memasang kran 3/4" atau 1/2" bh Rp 27,540.00
3 SNT.14a Memasang floor drain / Affour Lantai bh Rp 16,000.00

PEKERJAAN PENUTUP LANTAI DAN DINDING


1 SNI 7395 : 2008.6.36 Pasang lantai keramik 20 x 20 cm m2 Rp 149,605.00

PEKERJAAN PENGECATAN
1 CT.2e Pengecatan bidang kayu m2 Rp 33,393.00
2 CT.3b Pengecatan tembok - cat interior m2 Rp 14,381.00
3 CT.3b.1 Pengecatan tembok - cat exterior m2 Rp 21,661.00

PEKERJAAN PEMASANGAN PAVING


1 BOW Pemasangan Paving Hexagonal tb. 6 cm tanpa spesi per m2 m2 Rp 91,000.00

BATANG, 2014
DIRENCANAKAN
CV. PIRAMID REKATAMA KONSULTAN

ADI PRABOWO, ST

Daftar Satuan Pekerjaan - 7


1 2 3 4 5
Direktur

Daftar Satuan Pekerjaan - 8


UHAN PERTANIAN

Daftar Satuan Pekerjaan - 9


Daftar Satuan Pekerjaan - 10
ANALISA HARGA SATUAN PEKERJAAN

KEGIATAN : DAK NON DR BIDANG PERTANIAN / SARANA DAN PRASARANA PENYULUHAN PER
PEKERJAAN : RENOVASI KANTOR BP3K KECAMATAN TULIS
LOKASI : KECAMATAN TULIS KABUPATEN BATANG
TAHUN : 2014

HARGA UPAH HARGA


No KODE ANALISA URAIAN PEKERJAAN SATUAN PEKERJA BAHAN JUMLAH (Rp.)
( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7

PEKERJAAN TANAH

1 SNI 2835 :2008 1 m3 Galian Tanah Biasa sedalam 1 meter


6.1. 0.0250 org Mandor 60,000.00 1,500.00 1,500.00
0.7500 org Pekerja 50,000.00 37,500.00 37,500.00
39,000.00 39,000.00
2 SNI 2835 :2008 1 m3 Urugan Tanah Kembali
6.9 0.0083 org Mandor 60,000.00 500.00 500.00
0.2500 org Pekerja 50,000.00 12,500.00 12,500.00
13,000.00 13,000.00
3 SNI 2835 :2008 1 m3 Urugan Pasir
6.11 1.2000 m3 Pasir Urug 144,000.00 172,800.00 172,800.00

0.0100 org Mandor 60,000.00 600.00 600.00


0.3000 org Pekerja 50,000.00 15,000.00 15,000.00
15,600.00 172,800.00 188,400.00
4 SNI 2835 :2008 1 m3 Urugan Tanah Baru
6.15.b 1.2000 m3 Tanah baru 45,000.00 54,000.00 54,000.00

0.0250 org Mandor 60,000.00 1,500.00 1,500.00


0.2500 org Pekerja 50,000.00 12,500.00 12,500.00
14,000.00 54,000.00 68,000.00
5 SNI 2835 :2008 1 m3 Urugan Tanah ( tanah sudah ada di lokasi / bekas galian )
6.15.c 1.2000 m3 Tanah baru 0.00 0.00 0.00

0.0250 org Mandor 60,000.00 1,500.00 1,500.00


0.2500 org Pekerja 50,000.00 12,500.00 12,500.00
14,000.00 0.00 14,000.00

PEKERJAAN DINDING

1 SNI 6897 :2008 1 m2 Pasangan batu bata camp. 1 : 6, tebal 1/2 bata
6.11 70.0000 bh Bata merah 750.00 52,500.00 52,500.00
8.3200 kg Portland cement ( PC ) 1,450.00 12,064.00 12,064.00
0.0490 m3 Pasir pasang (muntilan) 275,000.00 13,475.00 13,475.00

0.0150 org Mandor 60,000.00 900.00 900.00


0.0100 org Kep. Tukang 70,000.00 700.00 700.00
0.1000 org Tukang batu 60,000.00 6,000.00 6,000.00
0.3000 org Pekerja 50,000.00 15,000.00 15,000.00

Analisa Pekerjaan - 11
HARGA UPAH HARGA
No KODE ANALISA URAIAN PEKERJAAN SATUAN PEKERJA BAHAN JUMLAH (Rp.)
( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7
22,600.00 78,039.00 100,639.00

PEKERJAAN PLESTERAN
1 SNI 2837 : 2008 1 m2 Plesteran tebal 15 mm dengan campuran 1:6 + Acian
6.6 4.4160 kg Portland cement ( PC ) 1,450.00 6,403.20 6,403.20
0.0270 m3 Pasir pasang (muntilan) 275,000.00 7,425.00 7,425.00

0.0150 org Mandor 60,000.00 900.00 900.00


0.0150 org Kep.Tukang 70,000.00 1,050.00 1,050.00
0.1500 org Tukang batu 60,000.00 9,000.00 9,000.00
0.3000 org Pekerja 50,000.00 15,000.00 15,000.00
25,950.00 13,828.20 39,778.20

PEKERJAAN BETON

1 SNI 7394 : 2008 1 m3 Pekerjan lantai rabat beton


6.4 230.0000 kg PC 1,450.00 333,500.00 333,500.00
0.7607 m3 kerikil 188,000.00 143,019.26 143,019.26
0.6379 m3 Pasir beton (muntilan) 275,000.00 175,410.71 175,410.71

0.0600 org Mandor 60,000.00 3,600.00 3,600.00


0.0200 org Kep. Tukang 70,000.00 1,400.00 1,400.00
0.2000 org Tukang batu 60,000.00 12,000.00 12,000.00
1.2000 org Pekerja 50,000.00 60,000.00 60,000.00
77,000.00 651,929.97 728,929.97

PEKERJAAN KUNCI DAN KACA


1 KK.1c 1 buah pasang kunci tanam
1.0000 bh Kunci tanam 125,000.00 125,000.00 125,000.00

0.0050 org Mandor 60,000.00 300.00 300.00


0.0100 org Kep.Tukang 70,000.00 700.00 700.00
0.5000 org Tukang kayu 60,000.00 30,000.00 30,000.00
0.0100 org Pekerja 50,000.00 500.00 500.00
31,500.00 125,000.00 156,500.00

PEKERJAAN SANITASI
1 SNT.1e Memasang 1 buah kloset jongkok porselen
1.0000 bh Kloset jongkok porselen 125,000.00 125,000.00 125,000.00
6.0000 kg Portland cement ( PC ) 1,450.00 8,700.00 8,700.00
0.0100 m3 Pasir pasang (muntilan) 275,000.00 2,750.00 2,750.00

0.1600 org Mandor 60,000.00 9,600.00 9,600.00


1.5000 org Kep.Tukang 70,000.00 105,000.00 105,000.00
1.5000 org Tukang batu 60,000.00 90,000.00 90,000.00
1.0000 org Pekerja 50,000.00 50,000.00 50,000.00
254,600.00 136,450.00 391,050.00

Analisa Pekerjaan - 12
HARGA UPAH HARGA
No KODE ANALISA URAIAN PEKERJAAN SATUAN PEKERJA BAHAN JUMLAH (Rp.)
( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7

4 SNT.13a Memasang 1 buah kran 3/4" atau 1/2"


1.0000 bh Kran air 20,000.00 20,000.00 20,000.00
0.0250 bh Seal tape 1,600.00 40.00 40.00

0.0050 org Mandor 60,000.00 300.00 300.00


0.0100 org Kep.Tukang 70,000.00 700.00 700.00
0.1000 org Tukang batu 60,000.00 6,000.00 6,000.00
0.0100 org Pekerja 50,000.00 500.00 500.00
7,500.00 20,040.00 27,540.00
5 SNT.14a Memasang 1 buah floor drain / Affour Lantai
1.0000 bh Floor drain 8,500.00 8,500.00 8,500.00

0.0050 org Mandor 60,000.00 300.00 300.00


0.0100 org Kep.Tukang 70,000.00 700.00 700.00
0.1000 org Tukang batu 60,000.00 6,000.00 6,000.00
0.0100 org Pekerja 50,000.00 500.00 500.00
7,500.00 8,500.00 16,000.00

PEKERJAAN PENUTUP LANTAI

1 SNI 7395 : 2008 Pasang lantai keramik 20 x 20 cm per 1 m2


6.36 1.0000 m2 ubin keramik 61,600.00 61,600.00 61,600.00
10.4000 kg Portland cement ( PC ) 1,450.00 15,080.00 15,080.00
0.0450 m3 Pasir pasang (muntilan) 275,000.00 12,375.00 12,375.00

0.0350 org Mandor 60,000.00 2,100.00 2,100.00


0.0350 org Kep. Tukang 70,000.00 2,450.00 2,450.00
0.3500 org Tukang batu 60,000.00 21,000.00 21,000.00
0.7000 org Pekerja 50,000.00 35,000.00 35,000.00
60,550.00 89,055.00 149,605.00

PEKERJAAN PENGECATAN

1 CT.2e Pengecatan bidang kayu (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup per m2
0.2000 kg Cat meni 22,500.00 4,500.00 4,500.00
0.1500 kg Plamir 21,500.00 3,225.00 3,225.00
0.1700 kg Cat dasar 37,000.00 6,290.00 6,290.00
0.2600 kg Cat penutup 2 kali 56,800.00 14,768.00 14,768.00

0.0025 org Mandor 60,000.00 150.00 150.00


0.0060 org Kep.Tukang 70,000.00 420.00 420.00
0.0090 org Tukang cat 60,000.00 540.00 540.00
0.0700 org Pekerja 50,000.00 3,500.00 3,500.00
4,610.00 28,783.00 33,393.00

Analisa Pekerjaan - 13
HARGA UPAH HARGA
No KODE ANALISA URAIAN PEKERJAAN SATUAN PEKERJA BAHAN JUMLAH (Rp.)
( Rp. ) ( Rp. ) ( Rp. )
1 2 3 4 5 6 7

2 CT.3b Pengecatan tembok (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) - interior per m2
0.1000 kg Plamir 12,500.00 1,250.00 1,250.00
0.1000 kg Cat dasar 20,400.00 2,040.00 2,040.00
0.2600 kg Cat penutup 2 x ( interior ) 22,000.00 5,720.00 5,720.00

0.0025 org Mandor 60,000.00 150.00 150.00


0.0063 org Kep.Tukang 70,000.00 441.00 441.00
0.0630 org Tukang cat 60,000.00 3,780.00 3,780.00
0.0200 org Pekerja 50,000.00 1,000.00 1,000.00
5,371.00 9,010.00 14,381.00
3 CT.3b.1 Pengecatan tembok (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup) - exterior per m2
0.1000 kg Plamir 12,500.00 1,250.00 1,250.00
0.1000 kg Cat dasar 20,400.00 2,040.00 2,040.00
0.2600 kg Cat penutup 2 x ( exterior ) 50,000.00 13,000.00 13,000.00

0.0025 org Mandor 60,000.00 150.00 150.00


0.0063 org Kep.Tukang 70,000.00 441.00 441.00
0.0630 org Tukang cat 60,000.00 3,780.00 3,780.00
0.0200 org Pekerja 50,000.00 1,000.00 1,000.00
5,371.00 16,290.00 21,661.00
PEKERJAAN PEMASANGAN PAVING

1 BOW Pemasangan Paving Hexagonal tb. 6 cm K-175 tanpa spesi per m2


1.0000 m2 Paving Hexagonal tb. 6 cm 60,000.00 60,000.00 60,000.00
0.0500 m3 Pasir urug 144,000.00 7,200.00 7,200.00

0.0200 org Mandor 60,000.00 1,200.00 1,200.00


0.0200 org Kep.Tukang 70,000.00 1,400.00 1,400.00
0.0200 org Tukang batu 60,000.00 1,200.00 1,200.00
0.4000 org Pekerja 50,000.00 20,000.00 20,000.00
23,800.00 67,200.00 91,000.00

BATANG, 2014
DIRENCANAKAN
CV. PIRAMID REKATAMA

ADI PRABOWO, ST
Direktur

Analisa Pekerjaan - 14
NG PERTANIAN / SARANA DAN PRASARANA PENYULUHAN PERTANIAN

Analisa Pekerjaan - 15
Analisa Pekerjaan - 16
Analisa Pekerjaan - 17
Analisa Pekerjaan - 18
DAFTAR HARGA MATERIAL, UPAH DAN PERALATAN

KEGIATAN : DAK NON DR BIDANG PERTANIAN /


SARANA DAN PRASARANA PENYULUHAN PERTANIAN
PEKERJAAN : RENOVASI KANTOR BP3K TULIS
LOKASI : KECAMATAN TULIS KABUPATEN BATANG
TAHUN : 2014

HARGA
NO. JENIS / URAIAN SATUAN SATUAN
(Rp)
1 2 3 4
I BAHAN
A MATERIAL DASAR
1 Batu Merah bh 750.00
2 Batu Pecah 2 - 3 / Kerikil / Split m3 188,000.00
3 Pasir Beton Muntilan m3 275,000.00
4 Pasir Pasang m3 194,000.00
5 Pasir Urug m3 144,000.00
6 Portland Cement Type I kg 1,450.00
7 Portland Cement ( Putih ) / Semen warna kg 2,200.00
8 Tanah urug m3 45,000.00

B MATERIAL BESI
1 Paku kg 14,000.00

C MATERIAL KUNCI, ENGSEL DAN GRENDEL


1 Kunci Tanam 2 x slag bh 125,000.00

D MATERIAL PENUTUP DINDING


1 Keramik Lantai KM 20 x 20 pak 61,600.00

E MATERIAL BAHAN CAT


A. Kayu
1 Plamur Kayu Kg 21,500.00
2 Cat dasar Kayu Kg 37,000.00
3 Cat Menie Kg 22,500.00
4 Cat Kayu / Warna Kg 56,800.00
5 Dempul Kayu Kg 23,000.00

Harga Bahan dan Upah - 19


1 2 3 4

B. Tembok
1 Plamur Tembok Kg 12,500.00
2 Cat Dasar Tembok Kg 20,400.00
3 Cat Tembok Exterior Kg 50,000.00
4 Cat Tembok Interior Kg 22,000.00
5 Cat Kayu / Besi Kg 56,800.00
6 Lem Kayu Kg 15,000.00

F MATERIAL SANITAIR
1 Floor drain bh 8,500.00
2 Kloset Jongkok bh 125,000.00
3 Kran air bh 20,000.00
4 Seal tape bh 1,600.00

G MATERIAL BAHAN CETAK


1 Kanstein 10/15x30x50 cm bh 30,000.00
2 Paving Hexagonal t=6 Cm K - 175 m2 60,000.00

II UPAH
1 Mandor OH 60,000.00
2 Kepala tukang ( batu , kayu, cat,besi ) OH 70,000.00
3 Tukang ( batu , kayu , besi,cat ) OH 60,000.00
4 Pekerja/ Laden ( batu,kayu, cat ) OH 50,000.00

III PERALATAN

BATANG, 2014
DIRENCANAKAN
CV. PIRAMID REKATAMA

ADI PRABOWO, ST
Direktur

Harga Bahan dan Upah - 20


Harga Bahan dan Upah - 21
2014

Harga Bahan dan Upah - 22

Anda mungkin juga menyukai