Note: Attempt all five questions. Part a, b, and c of each question is compulsory and carries
2, 2, and 3 marks respectively. Out of parts d and e (7 marks each) any one of them is
to be attempted. Missing data, if any, may be assumed suitably.
1. a. Name any two types of project plans required for project planning process.
b. Enumerate various phases of a construction project.
c. What is meant by project scheduling and what are its constraints?
d. The following project is to be represented by a bar chart. The duration for each activity is
in days. These are the actual work days. The project commences on Wednesday,
OCTOBER 14, with the five work-days a week. Draw the bar chart with the horizontal
scale denoting calendar dates.
Activity A B C D E F G H
Duration(days) 9 5 7 9 3 3 14 19
Activities A and B can occur concurrently. Activity C can take place after activity B is
completed. Activities D, F, and C can occur concurrently. Activity H can start 4 days after
the commencement of activity F. Activity G should follow activity E. Activity E can begin
concurrently with activity H. On what calendar date can we expect the project to be
completed?
e. What is work breakdown structure (WBS)? A security guards goomty having a plinth
area of 19 m2 and consisting of load bearing walls, RCC Slab, Internal and external plaster
with two coats of paint and IPS Flooring is required to be finished in 15 days. Identify the
activities and draw a network diagram.
#1/3
(The activity and its duration in days are shown on arrow)
Fig.1 Network Diagram
a. Name three time estimates used in PERT to estimate expected activity duration.
3. b. Define earliest event time and latest event time.
c. What is the significance of slack in a PERT network. How is it computed?
d. How do you compute the variance of an activity and standard deviation of a project?
e. A construction company has sublet a sub-project as detailed below. For various activities
of the project the three time estimate (i.e. optimistic t o, most likely tl and pessimistic
tp in days are as follows. Determine the probability of completing this project in 48
days.
Z Z 3 , 5 im p lie s S S = 3 & F F = 5 FS 0
E FF 7
9
ZZ 3 , 5 S F 2 ,1 0
SS 8
D FS 0 F G
A B
12 11 10
12 10
S F 7 ,1 4
FF 5
C
SS 3
18
SS 8
FF 3
I
FS 7 H 7
11 FF 3
3
F(1 5 0 0 )
B (2 0 0 0 )
2 (1 )
4 (2 )
A (2 0 0 0 ) D (4 0 0 0 ) G ( N IL )
1 2 5 6
4 (3 ) 5 (5 )
3 (2 )
C (4 0 0 0 ) E(3 0 0 0 )
3 (1 ) 5 (2 )
4
**************************
#3/3