KOMPONINDO BETONJAYA
DATA
BOARD OF COMMISIONERS
PRESIDENT DIRECTOR
GENERAL MANAGER
PURCHASING MANAGER
PT. KOMPONINDO BETONJAYA\
FACTORY BIRDVIEW
A.1. JALAN
1. Pavement
2. Concrete Block
A.2. JEMBATAN
1. Balok Jembatan
2. Pondasi Jembatan
3. Oprit Jembatan
1. BALOK JEMBATAN
4
2
2. Concrete Piles
2. Key Stones
PENGGUNAAN BETON PRECAST
CIVIL STRUCTURES
B. Drainage Structures
RC. Ditchs
RC. Box Culverts
RC. Pipes
C. Normalisasi Sungai
PC. Sheet Piles
Piles and Concrete Panel
2. Box Culvert
3. Pipes
Sheet Piles
1. PC. Corrugated Sheet Piles
D. Dermaga (Berth)
Concrete Piles
Pile Caps
Head Stocks
Deck Slabs
Fender Walls
Breasting Dolphins
Mooring Dolphins
Concrete Piles
E. Others
Breakwaters/Pemecah Ombak
Diaphragm Walls
PC Sleepers
1. RC Precast
Setting Inner Mould Demoulding
Curing
Flow Chart Proses Produksi Beton Precast
2. PC Precast Pre Tension
Laying PC Strand
Casting and
Compacting
Concrete
Stressing PC Strand
SEGMENTAL MONOLITH
Apply Mould Oil
Curing Curing
Placing Rebar Demoulding
Demoulding
Finishing Stressing
Install Sheath and
Anchoring Blocks Finishing
Stock Yard
Stock yard
Setting Outer
Mould Stressing at Site
Delivery RC / PC Precast
Equipment yang dipakai :
- Crane untuk angkat
I. Angkutan Darat
1. Proses Persiapan
3. Proses penekanan
pile ke bawah
4. Proses penyambungan
Pile
5. Proses penekanan
pile sampai dasar
5(b).Under Reamed and Kneading
Method ( from Rodex )
1 2 3 4 5 6 Keterangan :
7. Memasukkan drilling
rod sampai dasar
9. Memasukkan cairan
semen sampai pada
bagian bawah