Citation
URL http://hdl.handle.net/10722/51910
The new model was employed in thermal response test analysis using
parameter estimation technique to determine the groundwater velocity. It was found
that the estimated groundwater velocity scattered at repeated trials with test data
generated using a low groundwater velocity. At higher groundwater flows exceeding
2x10-7m/s, the groundwater velocity could be estimated with more confidence. For a
longer test period of 30 days, confident results could be obtained with groundwater
velocity down to 10-7m/s. Experimental thermal response tests were performed and
the results were analysed using the present model. Large errors in the estimated
groundwater velocities were found due to several reasons. The range of the
estimated soil thermal conductivity was lower than the maximum value determined
in laboratory soil thermal conductivity measurement test.
by
November 2008
Declaration
I declare that this thesis rpresentsmy ovn work, except wherc due
is made,andthat it hasnot beenpreviouslyincludedin a thsis,
acknowledgement
dissertationor rcport suhnittedto this Univrsityor to any otherinstitutionfor a
degree,diplomaor otherMifications.
ii
Acknowledgements
I would also like to thank Mr. W. K. Leung and Mr. C. C. Chan, the
technicians in Yam Pat Building, for helping me to arrange the laboratory work place
and necessary testing equipment. Their prompt response enabled me to carry out the
experimental work smoothly. My special thank went to Mr. William Lee who helped
me very much in setting up and modification of the test rig.
I would also like to express my great gratitude to Dr. Daniel Pahud of SUPSI
and Professor Jeffrey D. Spitler of Oklahoma State University in providing me the
site thermal response test data. Dr. Pahud strongly supported me in understanding
the application of the TRNVDSTP TRNSYS module for simulation. Professor
Spitler gave valuable advice to me when we met in the conference at Beijing in 2007.
iii
Table of Contents
Declaration i
Acknowledgement iii
Table of Contents iv
List of Figures x
List of Tables xxi
List of Abbreviations xxvii
Nomenclature xxviii
Chapter 1 : Introduction 1
1.1 Geothermal Heat Pump Systems 1
1.2 Liquid Desiccant Dehumidification Systems 4
1.3 Objective of This Research 6
iv
3.1 Ground Heat Exchanger Borefield 36
3.1.1 Heat Transfer Around Borehole 36
3.1.2 Heat Transfer Inside Borehole 38
3.1.2.1 Flow Process 39
3.1.2.2 No Flow Process 41
3.1.3 Solution Methodology 42
3.1.4 Borefield Performance Formulation 43
3.1.5 Thermal Response Test Analysis 44
3.2 Liquid Desiccant Systems 45
3.2.1 Desiccant Packed Tower 45
3.2.2 Desiccant-to-desiccant Heat Exchanger 47
3.2.3 Desiccant Heater/Cooler 47
3.3 Vapour Compression Air Conditioning Systems 48
3.3.1 Compressor 49
3.3.2 Condenser or Desiccant Heater 49
3.3.3 Expansion Device 52
3.3.4 Evaporator or Desiccant Cooler 52
3.3.5 Air-to-air Heat Exchanger 54
3.3.6 Air Heater 55
3.3.7 Ground-coupled Coil 55
3.3.8 Air Cooler 55
3.3.8.1 Approximate Iterative Method 56
3.3.8.2 Finite Difference Method 57
3.3.9 Single Zone 57
v
5.2 Thermal Response Test Analysis 68
5.3 Modelling of Ground-coupled Liquid Desiccant Air 69
Conditioners
vi
6.1.6.1 Variation of PV for Square Borefields 88
6.1.6.2 Variation of PV for Non- square Borefields 89
6.1.6.3 Variation of PV for Different Borefield 90
Scales
6.2 Thermal Response Test Analysis 91
6.2.1 Finalisation of Parameters to be Determined 91
6.2.2 Analysis Based on the Generated TRT data with 93
Specified Groundwater Velocity
6.2.2.1 Analysis Based on a Normal Test Period 94
6.2.2.2 Analysis Based on a Long Test Period 96
6.2.3 Analysis Based on the Generated TRT data 98
Including Groundwater Velocity in the Parameter
Estimation Scheme
6.2.3.1 Analysis Based on a Normal Test Period 98
6.2.3.2 Analysis Based on a Long Test Period 99
6.2.3.3 Effects of Other Parameters on the 100
Confident Minimum of Estimated
Groundwater Velocity
6.2.3.4 Effects of Far Field Temperature and 101
Borefield Load on the Estimated Parameters
6.2.4 Analysis of Experimental Thermal Response Test 103
Results
6.2.4.1 Parameter Estimation Results of 104
Experimental TRT
6.2.4.2 Laboratory Soil Thermal Conductivity 105
Measurement Test Results
6.2.4.3 Source of Experimental Errors 106
6.2.5 Analysis of Site Thermal Response Test Results 108
Provided by Others
6.3 Modelling of Ground-coupled Liquid Desiccant Air 112
Conditioners
6.3.1 Determination of Final Configuration of Liquid 112
Desiccant Dehumidifying Cycle
vii
6.3.1.1 Effect of Desiccant Cooler on Performance 113
of Liquid Desiccant Dehumidifier
6.3.1.2 Effect of Regenerative Air Heater on 113
Performance of Liquid Desiccant
Dehumidifier
6.3.1.3 Effect of Regenerative Air Heat Exchanger 114
on Performance of Liquid Desiccant
Dehumidifier
6.3.2 Performance of Heat-pump-coupled Liquid 115
Desiccant Dehumidifier (HPCLDD)
6.3.3 Analysis of Ground-coupled Liquid Desiccant Air 118
Conditioner (GCLDAC) and Comparison with
Conventional Ground Source Heat Pump (GSHP)
6.3.3.1 Ultimate Configuration of GCLDAC 118
6.3.3.2 Determination of Design Duty of 119
GCLDAC/GSHP
6.3.3.3 Setting of Design Parameters of 121
GCLDAC/GSHP
6.3.3.4 Performance of GCLDAC/GSHP at Design 123
Conditions
6.3.3.5 Dynamic Simulation of GCLDAC/GSHP at 124
No Groundwater Flow
6.3.3.6 Dynamic Simulation of GCLDAC/GSHP 128
with Groundwater Flow
Appendices 135
A. Transformation of Thermal Interference Coefficients 135
Between Tubes Inside a Borehole
B. Algorithm for Calculating Condenser Coil Performance 137
viii
C. Determination of Mean Refrigerant Density along 139
Saturated Region in Counter-flow Condenser/Evaporator
D. Algorithm for Calculating Evaporator Coil Performance 141
E. Algorithm for Calculating Air Cooler Performance Based 143
on Approximate Iterative Method
F. Modified Numerical Integration Method Used for FLSM 145
G. Modified Numerical Integration Method Used for LSMGA 146
H. Borehole Thermal Interference Based on FLSMGA 147
I. Calibration Curves for Measuring Instruments Used in 150
Laboratory Tests
J. Detailed Performance Curves at Different Groundwater 152
Directions and Load Profiles for Various Borefields
K. Parameter Estimation Results with Specified Groundwater 163
Flow Using LSMGA on Generated TRT Data for 5 Days at
Different Groundwater Velocities
L. Parameter Estimation Results with Specified Groundwater 166
Flow Using LSMGA on Generated TRT Data for 30 Days
at Different Groundwater Velocities
M. Parameter (Including Groundwater Velocity) Estimation 169
Results Using LSMGA on Generated TRT Data Using
LSMGA for 5 Days at Different Groundwater Velocities
N. Parameter (Including Groundwater Velocity) Estimation 171
Results Using LSMGA on Generated TRT Data Using
LSMGA for 30 Days at Different Groundwater Velocities
O. Logged Temperature Profiles in Experimental Thermal 173
Response Tests
P. Dynamic Simulation Results of GCLDAC/GSHP with 175
Groundwater Flow
References 177
ix
List of Figures
x
(a) front view, (b) rear view
Figure 6.1 Temperature rise along single borehole without 77
groundwater flow at different times
Figure 6.2 Loading along single borehole without groundwater 77
flow at different times
Figure 6.3 Comparison of fluid and borehole temperature rise in 77
single borehole without groundwater flow after 1 year
Figure 6.4 Ground temperature profiles around single borehole 78
without groundwater flow after 5 years
Figure 6.5 Ground temperature profiles around single borehole 78
without groundwater flow after 10 years
Figure 6.6 Variation of borefield load during a daily operation 81
schedule of 12 hours for single borehole without
groundwater flow
Figure 6.7 Variation of leaving fluid temperature rise of single 81
borehole at different Darcy velocities of groundwater flow
Figure 6.8 Temperature rise along single borehole after 5 years at 82
various groundwater velocities
Figure 6.9 Temperature rise along single borehole after 10 years at 82
various groundwater velocities
Figure 6.10 Loading along single borehole after 5 years at various 82
groundwater velocities
Figure 6.11 Loading along single borehole after10 years at various 82
groundwater velocities
Figure 6.12 Performance of single borehole at no groundwater flow 83
for different load profiles
Figure 6.13 Performance of single borehole at groundwater velocity 83
-7
10 m/s for different load profiles
Figure 6.14 Performance of single borehole at groundwater velocity 83
2x10-7m/s for different load profiles
Figure 6.15 Performance of single borehole after 1 year at high 83
groundwater velocity for different load profiles
Figure 6.16 Variation of borehole length ratio with groundwater 84
xi
velocity at different load profiles with fixed leaving fluid
temperature rise for single borehole
Figure 6.17 Variation of borehole capacity ratio with groundwater 84
velocity at different load profiles with fixed leaving fluid
temperature rise for single borehole
Figure 6.18 Variation of borehole length ratio with groundwater 85
velocity at different load profiles with fixed leaving fluid
temperature rise for2x2 borefield
Figure 6.19 Variation of borehole capacity ratio with groundwater 85
velocity at different load profiles with fixed leaving fluid
temperature rise for 2x2 borefield
Figure 6.20 Variation of leaving fluid temperature rise ratio of 86
single borehole with short borehole length at different
groundwater velocities and load profiles
Figure 6.21 Variation of leaving fluid temperature rise ratio of 86
single borehole with long borehole length at different
groundwater velocities and load profiles
Figure 6.22 Variation of leaving fluid temperature rise ratio of 2x2 86
borefield with short borehole length at different groundwater
velocities and load profiles
Figure 6.23 Variation of leaving fluid temperature rise ratio of 2x2 86
borefield with long borehole length at different groundwater
velocities and load profiles
Figure 6.24 Variation of leaving fluid temperature rise ratio with 87
short borehole length at different groundwater velocities and
borefields under load profile 3
Figure 6.25 Variation of leaving fluid temperature rise ratio with 87
long borehole length at different groundwater velocities and
borefields under load profile 3
Figure 6.26 Variation of leaving fluid temperature rise ratio of 2x2 88
borefield with short borehole length at different groundwater
velocities and load profiles based on fixed leaving fluid
temperature rise at default borehole length
xii
Figure 6.27 Variation of leaving fluid temperature rise ratio of 2x2 88
borefield with long borehole length at different groundwater
velocities and load profiles based on fixed leaving fluid
temperature rise at default borehole length
Figure 6.28 Variation of PV with groundwater velocity for 2x2 89
borefield
Figure 6.29 Variation of PV with groundwater velocity for 3x3 89
borefield
Figure 6.30 Variation of PV with groundwater velocity for 1x2 89
borefield
Figure 6.31 Variation of PV with groundwater velocity for 1x3 89
borefield
Figure 6.32 PV of various borefields with groundwater velocity of 90
10-5m/s at constant load with a daily schedule
Figure 6.33 Sensitivity of ground volumetric heat capacity on 92
borehole performance at different groundwater velocity in
TRT
Figure 6.34 Sensitivity of ground thermal conductivity on borehole 92
performance at different groundwater velocity in TRT
Figure 6.35 Sensitivity of borehole thermal resistance on borehole 92
performance at different groundwater velocity in TRT
Figure 6.36 Sensitivity of groundwater volumetric heat capacity on 92
borehole performance at different groundwater velocity in
TRT
Figure 6.37 Performance of single borehole in TRT at different 93
groundwater velocity
Figure 6.38 Variation of applied load with temperature difference 106
across soil in laboratory soil thermal conductivity
measurement test
Figure 6.39 Schematic of advanced liquid desiccant dehumidifier 112
Figure 6.40 Schematic diagram of heat-pump-coupled liquid 115
desiccant dehumidifier
Figure 6.41 Outdoor temperature profile for 1986 116
xiii
Figure 6.42 Performance of ACFAU for 1986 116
Figure 6.43 Performance of HPCLDD with dp=0.02 for 1986 117
Figure 6.44 Performance of HPCLDD with dp=0.015 for 1986 117
Figure 6.45 Schematic diagram of ground-coupled liquid desiccant 119
air conditioner (cooling mode)
Figure 6.46 Building load profile for Case 1 120
Figure 6.46 Building load profile for Case 2 120
Figure 6.47 Performance of GSHP at no groundwater flow for Case 125
1 within 1986~1995
Figure 6.48 Performance of GCLDAC at no groundwater flow for 126
Case 1 within 1986~1995
Figure 6.49 Performance of GSHP at no groundwater flow for Case 128
2 within 1986~1995
Figure 6.50 Required borehole lengths of GCLDAC/GSHP at 129
different groundwater velocities for Case 1
Figure 6.51 Required borehole lengths of GCLDAC/GSHP at 129
different groundwater velocities for Case 2
Figure F.1 Variation of integrand of Eq. (2.33) with s 145
Figure I.1 Calibration curve for borehole temperature logger 150
Figure I.2 Calibration curves for temperature log buttons 150
Figure I.3 Calibration of thermocouples for soil thermal 151
conductivity measurement
Figure I.4 Calibration curve for voltmeter 151
Figure I.5 Calibration curve for ammeter 151
Figure J.1 Performance of 2x2 borefield with groundwater velocity 152
10-7m/s at different groundwater directions under load
profile 1
Figure J.2 Performance of 2x2 borefield with groundwater velocity 152
-7
2x10 m/s at different groundwater directions under load
profile 1
Figure J.3 Performance of 2x2 borefield with groundwater velocity 152
5x10-7m/s at different groundwater directions under load
profile 1
xiv
Figure J.4 Performance of 2x2 borefield with high groundwater 152
velocity after 2 years at different groundwater directions
under load profile 1
Figure J.5 Performance of 2x2 borefield with groundwater velocity 152
-7
10 m/s at different groundwater directions under load
profile 2
Figure J.6 Performance of 2x2 borefield with groundwater velocity 152
2x10-7m/s at different groundwater directions under load
profile 2
Figure J.7 Performance of 2x2 borefield with groundwater velocity 153
-7
5x10 m/s at different groundwater directions under load
profile 2
Figure J.8 Performance of 2x2 borefield with high groundwater 153
velocity after 2 years at different groundwater directions
under load profile 2
Figure J.9 Performance of 2x2 borefield with groundwater velocity 153
-7
10 m/s at different groundwater directions under load
profile 3
Figure J.10 Performance of 2x2 borefield with groundwater velocity 153
2x10-7m/s at different groundwater directions under load
profile 3
Figure J.11 Performance of 2x2 borefield with groundwater velocity 153
-7
5x10 m/s at different groundwater directions under load
profile 3
Figure J.12 Performance of 2x2 borefield with high groundwater 153
velocity after 2 years at different groundwater directions
under load profile 3
Figure J.13 Performance of 2x2 borefield with groundwater velocity 154
-7
10 m/s at different groundwater directions under load
profile 4
Figure J.14 Performance of 2x2 borefield with groundwater velocity 154
2x10-7m/s at different groundwater directions under load
profile 4
xv
Figure J.15 Performance of 2x2 borefield with groundwater velocity 154
5x10-7m/s at different groundwater directions under load
profile 4
Figure J.16 Performance of 2x2 borefield with high groundwater 154
velocity after 2 years at different groundwater directions
under load profile 4
Figure J.17 Performance of 3x3 borefield with groundwater velocity 154
10-7m/s at different groundwater directions under load
profile 1
Figure J.18 Performance of 3x3 borefield with groundwater velocity 154
-7
2x10 m/s at different groundwater directions under load
profile 1
Figure J.19 Performance of 3x3 borefield with groundwater velocity 155
5x10-7m/s at different groundwater directions under load
profile 1
Figure J.20 Performance of 3x3 borefield with high groundwater 155
velocity after 2 years at different groundwater directions
under load profile 1
Figure J.21 Performance of 3x3 borefield with groundwater velocity 155
10-7m/s at different groundwater directions under load
profile 2
Figure J.22 Performance of 3x3 borefield with groundwater velocity 155
-7
2x10 m/s at different groundwater directions under load
profile 2
Figure J.23 Performance of 3x3 borefield with groundwater velocity 155
5x10-7m/s at different groundwater directions under load
profile 2
Figure J.24 Performance of 3x3 borefield with high groundwater 155
velocity after 2 years at different groundwater directions
under load profile 2
Figure J.25 Performance of 3x3 borefield with groundwater velocity 156
10-7m/s at different groundwater directions under load
profile 3
xvi
Figure J.26 Performance of 3x3 borefield with groundwater velocity 156
2x10-7m/s at different groundwater directions under load
profile 3
Figure J.27 Performance of 3x3 borefield with groundwater velocity 156
-7
5x10 m/s at different groundwater directions under load
profile 3
Figure J.28 Performance of 3x3 borefield with high groundwater 156
velocity after 2 years at different groundwater directions
under load profile 3
Figure J.29 Performance of 3x3 borefield with groundwater velocity 156
-7
10 m/s at different groundwater directions under load
profile 4
Figure J.30 Performance of 3x3 borefield with groundwater velocity 156
2x10-7m/s at different groundwater directions under load
profile 4
Figure J.31 Performance of 3x3 borefield with groundwater velocity 157
-7
5x10 m/s at different groundwater directions under load
profile 4
Figure J.32 Performance of 3x3 borefield with high groundwater 157
velocity after 2 years at different groundwater directions
under load profile 4
Figure J.33 Performance of 1x2 borefield with groundwater velocity 157
-7
10 m/s at different groundwater directions under load
profile 1
Figure J.34 Performance of 1x2 borefield with groundwater velocity 157
2x10-7m/s at different groundwater directions under load
profile 1
Figure J.35 Performance of 1x2 borefield with groundwater velocity 157
-7
5x10 m/s at different groundwater directions under load
profile 1
Figure J.36 Performance of 1x2 borefield with high groundwater 157
velocity after 2 years at different groundwater directions
under load profile 1
xvii
Figure J.37 Performance of 1x2 borefield with groundwater velocity 158
10-7m/s at different groundwater directions under load
profile 2
Figure J.38 Performance of 1x2 borefield with groundwater velocity 158
-7
2x10 m/s at different groundwater directions under load
profile 2
Figure J.39 Performance of 1x2 borefield with groundwater velocity 158
5x10-7m/s at different groundwater directions under load
profile 2
Figure J.40 Performance of 1x2 borefield with high groundwater 158
velocity after 2 years at different groundwater directions
under load profile 2
Figure J.41 Performance of 1x2 borefield with groundwater velocity 158
10-7m/s at different groundwater directions under load
profile 3
Figure J.42 Performance of 1x2 borefield with groundwater velocity 158
-7
2x10 m/s at different groundwater directions under load
profile 3
Figure J.43 Performance of 1x2 borefield with groundwater velocity 159
5x10-7m/s at different groundwater directions under load
profile 3
Figure J.44 Performance of 1x2 borefield with high groundwater 159
velocity after 2 years at different groundwater directions
under load profile 3
Figure J.45 Performance of 1x2 borefield with groundwater velocity 159
10-7m/s at different groundwater directions under load
profile 4
Figure J.46 Performance of 1x2 borefield with groundwater velocity 159
-7
2x10 m/s at different groundwater directions under load
profile 4
Figure J.47 Performance of 1x2 borefield with groundwater velocity 159
5x10-7m/s at different groundwater directions under load
profile 4
xviii
Figure J.48 Performance of 1x2 borefield with high groundwater 159
velocity after 2 years at different groundwater directions
under load profile 4
Figure J.49 Performance of 1x3 borefield with groundwater velocity 160
-7
10 m/s at different groundwater directions under load
profile 1
Figure J.50 Performance of 1x3 borefield with groundwater velocity 160
2x10-7m/s at different groundwater directions under load
profile 1
Figure J.51 Performance of 1x3 borefield with groundwater velocity 160
-7
5x10 m/s at different groundwater directions under load
profile 1
Figure J.52 Performance of 1x3 borefield with high groundwater 160
velocity after 2 years at different groundwater directions
under load profile 1
Figure J.53 Performance of 1x3 borefield with groundwater velocity 160
-7
10 m/s at different groundwater directions under load
profile 2
Figure J.54 Performance of 1x3 borefield with groundwater velocity 160
2x10-7m/s at different groundwater directions under load
profile 2
Figure J.55 Performance of 1x3 borefield with groundwater velocity 161
-7
5x10 m/s at different groundwater directions under load
profile 2
Figure J.56 Performance of 1x3 borefield with high groundwater 161
velocity after 2 years at different groundwater directions
under load profile 2
Figure J.57 Performance of 1x3 borefield with groundwater velocity 161
-7
10 m/s at different groundwater directions under load
profile 3
Figure J.58 Performance of 1x3 borefield with groundwater velocity 161
2x10-7m/s at different groundwater directions under load
profile 3
xix
Figure J.59 Performance of 1x3 borefield with groundwater velocity 161
5x10-7m/s at different groundwater directions under load
profile 3
Figure J.60 Performance of 1x3 borefield with high groundwater 161
velocity after 2 years at different groundwater directions
under load profile 3
Figure J.61 Performance of 1x3 borefield with groundwater velocity 162
10-7m/s at different groundwater directions under load
profile 4
Figure J.62 Performance of 1x3 borefield with groundwater velocity 162
-7
2x10 m/s at different groundwater directions under load
profile 4
Figure J.63 Performance of 1x3 borefield with groundwater velocity 162
5x10-7m/s at different groundwater directions under load
profile 4
Figure J.64 Performance of 1x3 borefield with high groundwater 162
velocity after 2 years at different groundwater directions
under load profile 4
Figure O.1 Logged temperature profiles for Test A in experimental 173
TRT
Figure O.2 Logged temperature profiles for Test B in experimental 173
TRT
Figure O.3 Logged temperature profiles for Test C in experimental 173
TRT
Figure O.4 Logged temperature profiles for Test D in experimental 174
TRT
Figure O.5 Logged temperature profiles for Test E in experimental 174
TRT
Figure O.6 Logged temperature profiles for Test F in experimental 174
TRT
xx
List of Tables
xxi
Table 6.12 Parameter estimation results with specified groundwater 96
flow using LSMGA on generated TRT data for 5 days with
groundwater velocity 10-6m/s
Table 6.13 Parameter estimation results with specified groundwater 97
flow using LSMGA on generated TRT data for 30 days with
groundwater velocity 2x10-8m/s
Table 6.14 Parameter estimation results with specified groundwater 97
flow using LSMGA on generated TRT data for 30 days with
groundwater velocity 5x10-8m/s
Table 6.15 Parameter (including groundwater velocity) estimation 98
results using LSMGA on generated TRT data for 5 days
with groundwater velocity 5x10-8m/s
Table 6.16 Parameter (including groundwater velocity) estimation 99
results using LSMGA on generated data for 5 days with
groundwater velocity 10-7m/s
Table 6.17 Parameter (including groundwater velocity) estimation 99
results using LSMGA on generated data for 5 days with
groundwater velocity 2x10-7m/s
Table 6.18 Parameter (including groundwater velocity) estimation 100
results using LSMGA on generated data for 30 days with
groundwater velocity 5x10-8m/s
Table 6.19 Parameter (including groundwater velocity) estimation 100
results using LSMGA on generated data for 30 days with
groundwater velocity 10-7m/s
Table 6.20 Estimated groundwater velocities using LSMGA based 101
on generated data with various ground thermal
conductivities and borehole thermal resistances
Table 6.21 Effects of Qbf and T0 on parameter estimation results 102
using LSMGA on generated data with groundwater velocity
5x10-7m/s
Table 6.22 Effects of Qbf and T0 on parameter estimation results 102
using LSMGA on generated data with groundwater velocity
10-6m/s
xxii
Table 6.23 Applied conditions for different experimental TRTs 104
Table 6.24 Analysis results of experimental TRT data 105
Table 6.25 Percentage error of estimated groundwater flow based on 105
experimental TRT data
Table 6.26 Temperature differences across soil at different applied 106
loads in laboratory soil thermal conductivity measurement
test
Table 6.27 Parameter estimation results of TRT data at north 108
borehole of Luzern using different models
Table 6.28 Parameter estimation results of TRT data conducted on 110
th
18 September 1998 for Maxey School at Lincoln using
different models
Table 6.29 Parameter estimation results of TRT data conducted on 110
30th June 1999 for Maxey School at Lincoln using different
models
Table 6.30 Parameter estimation results of TRT data conducted on 111
th
15 September 1998 for Campbell School at Lincoln using
different models
Table 6.31 Parameter estimation results of TRT data conducted on 111
8th October 1998 for Campbell School at Lincoln using
different models
Table 6.32 Effect of desiccant cooler on performance of liquid 113
desiccant dehumidifier
Table 6.33 Effect of regenerative air heater on performance of 114
liquid desiccant dehumidifier
Table 6.34 Effect of regenerative air heat exchanger on performance 114
of liquid desiccant dehumidifier
Table 6.35 Design requirement of GCLDAC/GSHP 121
Table 6.36 Parameters used for GSHP 121
Table 6.37 Parameters used for GCLDAC 122
Table 6.38 Performance of GSHP/GLCDAC at design conditions 124
for Case 1
Table 6.39 Performance of GSHP/GLCDAC at design conditions 124
xxiii
for Case 2
Table 6.40 Simulation results of GSHP with borehole length 250m 125
at no groundwater flow for Case 1 within 1986~1995
Table 6.41 Simulation results of GCLDAC with borehole length 126
250m at no groundwater flow for Case 1
Table 6.42 Simulation results of GSHP/GCLDAC at no 127
groundwater flow for Case 2
Table K.1 Parameter estimation results with specified groundwater 163
flow using LSMGA on generated TRT data for 5 days with
groundwater velocity 10-8m/s
Table K.2 Parameter estimation results with specified groundwater 163
flow using LSMGA on generated TRT data for 5 days with
groundwater velocity 2x10-8m/s
Table K.3 Parameter estimation results with specified groundwater 164
flow using LSMGA on generated TRT data for 5 days with
groundwater velocity 5x10-8m/s
Table K.4 Parameter estimation results with specified groundwater 164
flow using LSMGA on generated TRT data for 5 days with
groundwater velocity 10-7m/s
Table K.5 Parameter estimation results with specified groundwater 165
flow using LSMGA on generated TRT data for 5 days with
groundwater velocity 5x10-7m/s
Table L.1 Parameter estimation results with specified groundwater 166
flow using LSMGA on generated TRT data for 30 days
without groundwater flow
Table L.2 Parameter estimation results with specified groundwater 166
flow using LSMGA on generated TRT data for 30 days with
groundwater velocity 10-8m/s
Table L.3 Parameter estimation results with specified groundwater 167
flow using LSMGA on generated TRT data for 30 days with
groundwater velocity 10-7m/s
Table L.4 Parameter estimation results with specified groundwater 167
flow using LSMGA on generated TRT data for 30 days with
xxiv
groundwater velocity 2x10-7m/s
Table L.5 Parameter estimation results with specified groundwater 168
flow using LSMGA on generated TRT data for 30 days with
groundwater velocity 5x10-7m/s
Table L.6 Parameter estimation results with specified groundwater 168
flow using LSMGA on generated TRT data for 30 days with
groundwater velocity 10-6m/s
Table M.1 Parameter (including groundwater velocity) estimation 169
results using LSMGA on generated TRT data for 5 days
without groundwater
Table M.2 Parameter (including groundwater velocity) estimation 169
results using LSMGA on generated TRT data for 5 days
with groundwater velocity 10-8m/s
Table M.3 Parameter (including groundwater velocity) estimation 169
results using LSMGA on generated TRT data for 5 days
with groundwater velocity 2x10-8m/s
Table M.4 Parameter (including groundwater velocity) estimation 170
results using LSMGA on generated TRT data for 5 days
with groundwater velocity 5x10-7m/s
Table M.5 Parameter (including groundwater velocity) estimation 170
results using LSMGA on generated TRT data for 5 days
with groundwater velocity 10-6m/s
Table M.6 Parameter (including groundwater velocity) estimation 170
results using LSMGA on generated TRT data for 5 days
with groundwater velocity 2x10-6m/s
Table N.1 Parameter (including groundwater velocity) estimation 171
results using LSMGA on generated TRT data for 30 days
without groundwater
Table N.2 Parameter (including groundwater velocity) estimation 171
results using LSMGA on generated TRT data for 30 days
with groundwater velocity 10-8m/s
Table N.3 Parameter (including groundwater velocity) estimation 171
results using LSMGA on generated TRT data for 30 days
xxv
with groundwater velocity 2x10-8m/s
Table N.4 Parameter (including groundwater velocity) estimation 172
results using LSMGA on generated TRT data for 30 days
with groundwater velocity 2x10-7m/s
Table N.5 Parameter (including groundwater velocity) estimation 172
results using LSMGA on generated TRT data for 30 days
with groundwater velocity 5x10-7m/s
Table N.6 Parameter (including groundwater velocity) estimation 172
results using LSMGA on generated TRT data for 30 days
with groundwater velocity 10-6m/s
Table P.1 Simulation results of GSHP/GCLDAC with Darcy 175
velocity 10-7m/s of groundwater flow for Case 1
Table P.2 Simulation results of GSHP/GCLDAC with Darcy 175
velocity 5x10-7m/s of groundwater flow for Case 1
Table P.3 Simulation results of GSHP/GCLDAC with Darcy 175
velocity 10-6m/s of groundwater flow for Case 1
Table P.4 Simulation results of GSHP/GCLDAC with Darcy 176
velocity 10-7m/s of groundwater flow for Case 2
Table P.5 Simulation results of GSHP/GCLDAC with Darcy 176
velocity 5x10-7m/s of groundwater flow for Case 2
Table P.6 Simulation results of GSHP/GCLDAC with Darcy 176
velocity 10-6m/s of groundwater flow for Case 2
xxvi
List of Abbreviations
xxvii
Nomenclature
xxviii
g Time dependent function according to Eq. (2.2)
H Effective borehole length (m)
h Specific enthalpy (kJ/kg)
h = H gw c gwV gw / 2k g according to Eq. (2.40)
xxix
Nu Average Nusselt number over borehole surface
NZ Number of discretisation segment of desiccant packed
tower
nzbore Number of ground grid points along borehole length
P Pressure (kPa)
p = r / rb according to Eq. (2.24)
xxx
S Cross sectional area (m2)
s Specific entropy (kJ/kgK)
s Integrating variable in Eqs. (2.33), (2.34), (2.39),
(2.41) and (2.43)
Sc Schmidt number according to Eq. (3.35)
T Temperature (oC or K)
~ Weighted average of temperature according to Eq.
T
(3.8) (oC or K)
t Time (s)
t Integration variable in Eqs. (2.35)
UA Overall heat transfer coefficient (kW/K)
URF Under relaxation factor according to Eq. (3.16)
V Parameter according to Eqs. (2.27&29)
V = gw c gwV gw / g c g according to Eq. (2.35) (m/s)
Subscript
aahxr Air-to-air heat exchanger
AC Air conditioning
ac Air cooler
xxxi
aci Inlet of air cooler
ac1 Intermediate state of refrigerant in air cooler according
to Figure 3.8
adp Air dewpoint
avg Average
b Borehole
bf Borefield
co Condenser outlet
comp Compressor
cond Condenser
conv Convection by groundwate
cool Cooling
deh Dehumidifier tower
dc Desiccant cooler
dci Desiccant cooler inlet
dc1 Intermediate state of refrigerant in desiccant cooler
according to Figure 3.6
dh Desiccant heater
dhi Desiccant heater inlet
dh1, dh2 Intermediate states of refrigerant in desiccant heater
according to Figure 3.5
dh1 Alternative state of dh1
di Dehumidifier tower inlet
dis Compressor discharge
do Dehumidifier tower outlet
dsa Dry supply air
dzone Dry zone air
ea Exhaust air stream in air-to-air heat exchanger
eao Exhaust air discharge
ei Evaporator inlet
evap Evaporator
f Fluid
f Saturated liquid refrigerant
xxxii
fl Fluid at middle of control volume of pipe inside
borehole
flsm Finite line source model
flsmga Finite line source model with groundwater advection
G Gas
g Ground
g Saturated gaseous refrigerant
gc Ground coupled coil
gw Ground water
he Heat exchanger
heat Heating
i Discretisation step of ground and borehole in z-
direction
ia Intake air stream in air-to-air heat exchanger
iao Intake air discharge
in Inlet
inf Thermal interference
inst Instantaneous
j Discretisation step of ground in x-direction
L Liquid desiccant
lat Latent
ll Liquid line
m Discretisation step of ground in y-direction
ma Mixed air
max Maximum
min Minimum
nf No fluid flow inside borehole
ngw No groundwater flow
out Outlet
p Discritisation step of intake air stream in air-to-air heat
exchanger
psga Point source with groundwater advection
q Discritisation step of exhaust air stream in air-to-air
xxxiii
heat exchanger
qfact Load factor
r Refrigerant
ra Regenerative air
rahi Regenerative air heater inlet
rai Regenerative air intake
rao Regenerative air discharge
reg Regenerator tower
ri Regenerator tower inlet
ro Regenerator tower outlet
rs Refrigerant in saturated region
rta Return air
s Heat source
sa Supply air
sat Saturated region
sen Sensible
sc Sub-cooled region
sh Superheated region
store Ground heat store
suc Compressor suction
t Liquid desiccant system
total Total effect including groundwater advection
u,v Tube designation inside borehole
w Water
wet Wet
wG Water in gas phase
wL Water in liquid desiccant phase
x+ From downstream grid point in x-direction
x- From upstream grid point in x-direction
y+ From downstream grid point in y-direction
y- From upstream grid point in y-direction
z+ From downstream grid point in z-direction
z- From upstream grid point in z-direction
xxxiv
zone Building zone
0 Undisturbed condition
Far field
Superscript
n Discretisation step in time
Symbol
Parameter according to Eqs. (2.27&28)
Integrating variable in Eqs. (2.5), (2.6), (2.8) and
(2.25)
= (Tr T f ,in )C f / mr h f g according to Eq. (C.4)
Quality of refrigerant
h f g Specific enthalpy difference between saturated
gaseous and liquid refrigerant (kJ/kg)
f g Density difference between saturated liquid and
gaseous refrigerant (kg/m3)
Heat transfer effectiveness
Euler constant ( = 0.57721)
= g + f g ( in + e NTU ) according to Eq. (C.7)
(kg/m3)
Specific latent heat of evaporation of water (kJ/kg)
l Characteristic length across coil
Dynamic viscosity (kg/ms)
= 2k g / qb according to Eq. (2.38)
xxxv
Liquid desiccant concentration
Integrand of Eq. (2.35)
Integrand of Eq. (2.37)
Density (kg/m3)
Mean density (kg/m3)
= (k b k g ) /(k b + k g ) according to Eq. (A.4)
xxxvi
Chapter 1 : Introduction
With the increasing concern for global warming nowadays, the reduction of
release of greenhouse gases, especially carbon dioxide into the atmosphere has
become an important task worldwide. The higher usage of renewable energy sources
including solar, wind, tidal, hydrothermal, etc., provides one way of solution.
However, the cost of renewable energy plants used to be higher than that of
conventional power plants. In addition, renewable energy supplies rely on the
environmental conditions, which tend to be unstable. A better utilisation of energy
offers another key direction. Besides transportation, buildings are the major energy
consumers. Further investigation indicates that air conditioning systems constitute
the highest proportion of the total energy demand. Clearly, the development of a
more energy-efficient air conditioning system helps reduce the release of carbon
dioxide and consequently the energy cost significantly.
1
Geothermal heat pump systems which are sometimes referred to as ground
source heat pump systems use the ground as the medium of heat exchange with the
surrounding rather than water or air. Being lower than the ambient in summer and
warmer in winter, the more stable and favourable temperature of the ground
combined with its higher thermal capacity as compared with air makes the systems
more energy-efficient than air-cooled systems. Besides, the release of condensing
heat to the ground instead of the ambient helps relieve the heat island effect. Figure
1.1 shows the schematic diagram of a typical geothermal heat pump system.
Fresh air
Supply Evaporator
air fan
Return air
Condenser
Compressor
Expansion valve
Borefield
The pipework connecting the ground and the condenser may operate as open
or closed systems. For open systems, the underground water is directly pumped from
one well and drained back to the ground through another well, as shown in Figure 1.2.
Open systems offer a better heat transfer performance, but to sustain long term
operation, the hydraulic conductivity of the ground must be high. Moreover,
groundwater may corrode the condenser coil. The application of open systems is
thus limited.
2
Condenser
Ground surface
3
therefore be required, which is costly and the thick pipe wall reduces the heat transfer
rate of the boreholes.
Borehole
Tube
Grouting
Ground surface
Tout
Tin
Borefield
4
(supply) air by circulating strong liquid desiccant solution in a dehumidifier packed
tower in contact with the air as shown in Figure 1.4. The diluted desiccant solution
is then reheated before entering a regenerator packed tower where it releases
moisture to the regenerative air stream. Usually, the regenerative heat comes from a
low-grade heat source such as waste heat from a power plant or an industrial process,
or even from a solar system.
Desiccant
heat
Dehumidifier exchanger Regenerator
Process
tower tower
air fan
Weak Strong
desiccant desiccant
pump pump
The addition of heat pumps to liquid desiccant dehumidifiers may solve the
problem. Heat dissipated in the condenser is used to regenerate the liquid desiccant
before entering the regenerator tower, and the evaporator is used to cool the liquid
desiccant before entering the dehumidifier tower, thus providing a certain amount of
5
sensible cooling. Still, such design can only handle the fresh air with satisfactory
performance, and auxiliary facility is needed to deal with the return air.
6
desiccant dehumidifier coupled with a heat pump is efficient in handling the fresh air,
the combination of a liquid desiccant dehumidifier with the conventional geothermal
heat pump system seems to be a suitable choice where a single compressor will be
used to provide desiccant cooling/heating and air conditioning for the return air.
Computer simulation will be carried out to investigate the potential of this new
hybrid system in terms of the borehole length reduction and overall energy efficiency
change under different groundwater conditions.
7
Chapter 2 : Literature Review
2.1.1 General
With the awareness of energy crisis in late 1970s and environmental concern,
the quest for sustainable power sources and energy-efficient systems has become a
hot issue. Besides industrial processes, building air conditioning systems, especially
for heating purposes in winter, account for the major portion of the total energy
consumption. The development of better heating systems is one key direction for
improvement. The cogeneration of heat and power from power plants is an obvious
solution, but heating can only be provided to nearby areas around the power stations.
Geothermal energy is another possible choice where high-grade geothermal heat can
be directly used for power generation and medium-grade heat can be extracted for
space heating. ASHRAE (2003) outlined some details in designing geothermal
power system for heating service. Lund (2003) summarised the status of direct-use
of geothermal energy in USA, while Kepinska (2003) discussed the situation in
Poland.
However, the availability of geothermal heat sources for direct heating is still
restricted to limited locations. Alternatively, geothermal heat pump systems can be
developed to extract heat from the ground through conventional vapour compression
systems, where the amount of heat supplied can be much higher than the energy
input due to the high COP value of the systems. Research work increases rapidly in
Europe and USA. Gourlburn and Fearon (1983) investigated a domestic heat pump
system with the low pressure refrigerant directly fed into the U-tube of the ground
heat exchangers for evaporation. Sliwa and Kotyza (2003) discussed the
employment of existing wells for geothermal heat pump systems in Poland. Petit and
Meyer (1998) compared the costs of geothermal and air-cooled systems in South
Africa. Hepbasli and Akdemir (2004) performed energy and exergy case analysis of
particular geothermal heat pump installation in Turkey. Sanner et al. (2003) briefed
8
the current situation of geothermal heat pump system application in Europe. The
systems gain greater acceptance in Sweden, Switzerland and Austria, but the
development is slow in UK, possibility due to the competition from cheap gas supply.
In USA, geothermal heat pump systems are not only used for heating, as cooling
is also required in summer. This helps relieve the ground temperature change, thus
reducing the required borehole lengths and consequently the installation costs and
promoting the wider acceptance of the systems. ASHRAE (1998) presented case
studies of various installations in USA. Various design guidelines/manuals were
issued, including those by Bose et al. (1985), ASHRAE (1995) and Kavanaugh and
Rafferty (1997). Sachs (2002) discussed the geological aspects of geothermal heat
pump system installation. Bose et al. (2002) presented an overview of the recent
situations and developments of geothermal heat pump systems in USA. Spitler
(2005) reviewed the design methodology of geothermal heat pump systems, and
proposed areas for further investigation.
To reduce the high installation cost of geothermal heat pump systems due to
drilling of long boreholes, hybrid systems are developed. The most common design
is the parallel operation of ground heat exchangers and cooling towers. Kavanaugh
(1998) outlined a design methodology of such system, and discussed the various cost
consideration and operation criteria for the system. Yavuzturk (1999) also studied
the performance of hybrid geothermal heat pump systems coupled with cooling
towers based on his short time-step model. Gasparella et al. (2005) described the
operation of a combined liquid desiccant and geothermal heat pump system in Italy
9
with different operation modes in various seasons. The reduction in borehole length
can also be achieved by minimising the unbalance of the annual borehole loads. In
heating dominated regions, this can be accomplished by re-charging the heat into the
ground by operating a solar system in summer. Ozgener and Hepbasli (2006)
discussed the costing of a solar-assisted geothermal heat pump system.
In projects where concrete piles are to be used for structural reason, the
insertion of ground heat exchangers into concrete piles (energy piles) can
significantly lower the installation cost of the geothermal heat pump systems, as the
drilling work is significantly reduced. Pahud et al. (1996) developed a modified
version of the Hellstroms DST model implemented in TRNSYS (DSTP) to estimate
the performance of energy piles. Fromentin et al. applied the DSTP model to
simulate the performance of several existing installations. Pahud (1999) further
modified the DSTP model to PILSIM for ease of application. Pahud et al. (1999)
applied PILSIM for design in a project at the Zurich Airport. Morino and Oka (1994)
studied numerically and experimentally the heat transfer between a steel pile
circulated with water and the surrounding soil. Hamada et al. (2007) investigated the
performance of energy piles installed at site. They also analysed the capacity of
energy pile with different configuration of heat exchanger pipes installed, and found
that indirect double pipe provided a higher capacity than single or double U-pipe.
Laloui et al. (2006) studied numerically and experimentally the mechanical
behaviour of energy pile at different mechanical and thermal loading conditions.
Brandl (2006) discusses various types of thermal structures and presented case
studies of various installations.
10
and modified LSM to the experimental data, and found that his model predicted
better than the other two models, especially if the effect of backfill was included.
All analytical models are based on a continuous load step. In dealing with a
varying load profile, the loading is piecewise transformed into a number of step loads
as shown in Figure 2.1, and the final solution by superposition. When the simulation
period is long, the quantity of load steps becomes very large, which leads to very
long computation time. Bernier et al. (2004) outlined a multiple load aggregation
algorithm which allowed annual simulation to be conducted efficiently even at
hourly intervals. Past thermal loads were aggregated in parts at different time
intervals corresponding to the past day, week, month and years while recent thermal
11
loads were not aggregated. A similar approach was adopted by Yavuzturk (1999),
but he lumped up the past loads with fixed time intervals.
Load Load
Q1
Q1 Q2 Q3 Q4 Q5 Q2-Q1
Q3-Q2
Time Time
Q4-Q5
Q3-Q4
where R g is a time dependent thermal resistance of the ground and q is the heat load
per unit length rejected to the ground. R g characterises the ground response due to
12
where Rb is the thermal resistance of the boreholes. The overall effect of the
circulating fluid on the ground is then defined by combining Eqs. (2.1) and (2.3),
giving
T f T0 = qb ( Rg + Rb ) (2.4)
By applying the analogy between electric current and heat flow, Eqs. (2.3) and (2.4)
can be symbolically represented as shown in Figure 2.2.
Rb Rs
Tf Tb T0
Ground
qb
Borehole
Figure 2.2 Electrical analogy of heat transfer between borehole circulating fluid and
surrounding ground
One of the earliest adopted analytical models is the line source model (LSM)
from Ingersoll et al. (1954) for calculation of heat conduction around a single
borehole without groundwater effect under a constant heat load step. The line source
model assumes that the borehole can be approximated by an infinite line of radius
zero, and the ground temperature only varies in the radial direction. The temperature
rise is calculated as
e
2
r
I
q qb
Tg T0 = b
2k g
d =
2k g 4a t
(2.5)
r / 4ag t g
e
2
r
where I ( ) = d and = (2.6)
4a g t
Tabulated values for I () are given by Ingersoll et al. (1954). For < 0.2 ,
13
1 4
2
I ( ) ln + 0.2886 (2.7)
2 8
In real situations, the borehole size is finite, and heat is propagated from the
borehole surface instead of the borehole centre. Hence, the heat front from a line
source will lag behind the actual thermal effect, especially soon after the start of the
load step and at distance close to the borehole centre. Ingersoll et al. (1954) stated
that the line source model is not accurate at short time duration and for borehole with
large diameter where a g t / rb2 < 20 . Eq. (2.5) can alternatively be written as
e r2
qb qb
Ei = qb Ei ( )
Tg T0 =
4k g 2
d =
4k g 4a g t 4k g
(2.8)
r / 4ag t
where Y = r 2 / 4a g t (2.9)
q b 4a g t
Tg T0 ln 2 (2.12)
4k g r
Eskilson (1987) suggested that Eq. (2.12) was applicable for 5rb2 / a g < t < H 2 / 90a g .
14
+ 0.05519968 6 0.00970064 8 + 0.00107857 10 ) (2.13)
while for 1 < ,
1
I ( ) 2
(2.14)
2 2 e
where
= 8 + 8.5733287 6 + 18.059017 4 + 8.637609 2 + 0.2677737 (2.15)
and
= 8 + 9.5733223 6 + 25.632956 4 + 21.0996531 2 + 3.9684969 (2.16)
Eq. (2.10) and (2.13) are basically the same. Bose et al. (1985) defined the ground
formation resistance for single borehole as
I ( rb ) rb
R g ( ) = with rb = (2.17)
2k g 4a g t
and
COPcool + 1
CAPcool ( Rb + R g RFcool )
COPcool
H cool = (2.19)
T f ,max T0
where CAP is the capacity of the heat pump system, Rb is the borehole thermal
resistance as defined in Eq. (2.3) and Rs is the ground thermal resistance as defined in
Eq. (2.1).
Hart and Couvillion (1986) also applied the LSM and derived method used
by NWWA (National Water Well Association). They assumed that the ground
temperature remained unchanged beyond a far field radius defined as
r = 4 a g t (2.20)
15
They proposed an equation for the calculation of ground temperature rise as
qb r
(1) N +1 4r 2
N
Tg T0 = ln 0.9818 + 2 (2.21)
2k g r 2 N N ! r
N =1
and
1 r
(1) N +1 4r 2
N
Rg = ln 0.9818 + 2 (2.22)
2k g r N =1 2 N N ! r
Similar to the IGSHPA approach, Eq. (2.4) was used to calculate the borehole length.
ASHRAE (1995) outlined design procedures based on their approach. Kyriakis et al.
(2006) adopted LSM and derive maximum borehole loading under different load
duration and undisturbed ground temperatures.
The weakness of requiring long time step for LSM is overcome by the
application of cylindrical source model (CSM) developed by Carslaw and Jaeger
(1959), which assumes the borehole to be a cylinder of infinite length. Constant heat
flux is injected from the cylinder surface. Again, the ground temperature only varies
in radial direction, and groundwater effect is not considered. The solution is
obtained by solving the following one-dimensional heat conduction equation in
cylindrical coordinates by Laplace transform method,
2 1 1
+ =0 for rb < r < (2.23)
r 2 r r a g t
where = Tg T0 , yielding
qb ag t r
= G ( , p ) with = 2
p= (2.24)
kg rb rb
and
e 1
[J 0 ( p )Y1 ( ) J 1 ( )Y0 ( p )] d2
2
1
G ( , p) = 2 2 (2.25)
0 J 1 ( ) + Y1 ( )
2
By comparing Eq. (2.24) with Eqs. (2.1&2),
G ( ,1)
Rg = and g = 2G ( ,1) (2.26)
kg
16
the Bessel functions. He quoted an alternative form of solution by applying a
numerical inversion technique to the Laplace domain, and the solution becomes
q 10 V j1 K 0 ( j1 r )
=
2rb k g
j1=1 j1 j1 K 1 ( j1 rb )
(2.27)
j1ln(2)
where j1 = (2.28)
ag t
and
Min ( j1, 5 )
(1) j15 n 5 (2n)!
V j1 =
n = Int (( j11) / 2 ) (5 n)!( n 1)! n!( j1 n)!( 2n j1)!
(2.29)
Fujii et al. (2004a) also proposed formulae to approximate the borehole temperature
rise G ( ,1) based on CSM as follows:
CSM has been widely used by previous workers. Deerman and Kavanaugh
(1991) and Kavanaugh (1992) applied CSM in their analaysis. Bernier (2001) also
adopted CSM in his work. Kavanaugh (1985, 1995) used CSM to calculate the
ground thermal resistance and proposed modified formulae similar to Eqs. (2.18&19)
to calculate the required borehole length in cooling and heating modes. He included
terms to account for thermal interference between adjacent legs of the U-tubes inside
boreholes, and between adjacent boreholes. His approach was implemented in the
GchpCalc design software and presented in Kavanaugh and Rafferty (1997).
Bernier (2000, 2006) proposed modification of Kavanaughs approach.
Dobson et al. (1995) discretised the U-tube of a ground heat exchanger with
surrounding ground by various horizontal layers, and applied CSM for each portion
of tubes. The coupled fluid temperatures along the U-tube were solved numerically.
The variation of ground thermal properties at different depths was also accounted for.
Sutton et al. (2002) adopted a similar approach to estimate the performance of a
vertical ground heat exchanger in a stratified geological regime. They used Eqs.
17
(2.27~29) to calculate the ground temperature change. The U-tube inside the
borehole was represented by a single tube with equivalent diameter.
r 2 + ((d + H ) / 2 + s ) 2
erfc b
4a g t
ds (2.34)
rb2 + ((d + H ) / 2 + s ) 2
Lamarche and Beauchamp (2007) defined the g function based on the average
borehole surface temperature, resulting in a double integral. They proposed
18
alternative expression for the double integral which was much faster to compute.
However, in their derivation, they assumed that the borehole heat exchanger had no
insulated depth (i.e. d = 0 ).
19
(1998a) developed an expression for an equivalent diameter ( Deq = 2 rpo b ) to
appropriate the two legs of U-tube. The resultant borehole became a composite
cylinder and Gu and ONeal (1995, 1998b) investigated the borehole performance
based on different thermal properties of the backfill.
20
was represented by a non-circular section, and a geometry factor introduced to
account for this. Vertical heat conduction in the ground was neglected, and a quasi
three-dimensional analysis is made by applying the numerical scheme layer by layer
so that the temperature variation along the U-tubes could be estimated.
One of the simplest analytical model including groundwater effect is the line
source model with groundwater advection (LSMGA) based on the moving line
source concept as stated by Carslaw and Jaeger (1959). They presented results for
steady state condition. Diao et al. (2004) derived an expression for the transient
temperature rise in the ground based on LSMGA as
[ x V ' ( t t ' )] 2 + y 2
q t 1 gw c gwV gw
0 t t ' e
4a g (t t ' )
= b dt ' V' = (2.35)
4k g g cg
or in polar coordinates (r , ) as
V ' r cos 1 V ' 2 r 2
q 2 a g 4ag t / r 2 1 16 a 2
= b e
d
g
e (2.36)
4k g 0
21
They also proposed a formula for the average dimensionless temperature rise around
a circle from the line source which can be used to compute the average borehole
temperature rise as
1 R12
1 R1 4 Fo / R12 1 16
= d =I e
d (2.37)
2
0
0 2 0
2k g V 'r V ' 2t
where = R1 = and Fo = (2.38)
qb ag ag
Claesson and Hellstrom (2000) adopted the solution from Carslaw and Jaeger
(1959) for the ground temperature rise around a finite line source along 0 < z < H in
an infinite surrounding with groundwater advection. They expressed the borehole
temperature rise in terms of a generalised g function based on the same approach as
used in Eqs. (2.1&2) as given by g total = g ngw g gw , and derived a formula for g gw
as
g gw ( , h) =
1
(
0 2s '
1 e h2s' / 4
) (
erfm 1 / s ' ds ' ) (2.39)
where
4a g t H gwcgwVgw
= h' = (2.40)
H2 2k g
and
1 ex
2
1 x
erfm( x) = erf ( s ' )ds ' = erf ( x) (2.41)
x 0 x
For < 1 , they proposed
1 e s '
'
x
Ein( x) = '
ds ln( x + e x ) + 0.577(1 e 7 x / 4 ) (2.43)
0 s
They further simplified Eq. (2.42) for h ' < 1 as
h'2 4
g gw 1 (2.44)
8
9
22
Following the same approach as in FLSM where no temperature rise at ground
surface is assumed by adding an image sink above the ground and including
insulated depth for borehole, the final g function for finite line source model with
ground water advection (FLSMGA) is given as
g flsmga = g flsm g gw ( , h ' ) + (1 + d ' ) g gw ( / 4(1 + d ' ) 2 ,2(1 + d ' )h ' )
+ d ' g gw ( / 4d '2 ,2d 'h ' ) (1 + 2d ' ) g gw ( /(1 + 2d ' ) 2 , (1 + 2d ' )h ' ) (2.45)
Pahud and Hellstrom (1996) modified the DST model to account for
groundwater effect in two manners, long-term and short-term effects. According to
Pahud et al. (1996), the long-term effect, which influences the global temperature
field, determines the heat transferred by groundwater. Two methods were proposed.
The first one is based on the average temperature difference between the inner and
outer surface of the store boundary as
Econv = Vgw S store gwcgw (Tstore ,in Tstore , out )t (2.46)
where t is the time step for calculating the global temperature field in the ground.
The second method is based on the difference between the average store temperature
and the undisturbed ground temperature as
Econv = Vgw S store wcw (Tsore, avg T0 )t (2.47)
The short-term effect influences the local solution governing the heat transfer
between borehole and surrounding ground. Based on the equation for calculating the
average steady state heat transfer at a cylinder surface inside a porous medium (Nield
and Bejan, 1992) applied to the boreholes,
0.5
q conv 2V r
Nu = Nu = 1.015 gw b (2.49)
(Tb T0 )k g a
g
23
where q conv is the average convective heat transfer on the borehole surface. As DST
assumes the borehole to be closely packed, the heat flux at mid-distance between
boreholes becomes zero, and Hellstrom (1991) gave
q r12 r1 1 rb2
Tb T0 = 2 ln + 2 (2.50)
2k g r1 rb
2
rb 2 2r1
where r1 is the mid centre-to-centre distance between two boreholes. Combining Eq.
(2.49) and (2.50),
According to Pahud and Hellstrom (1996), Eq. (2.51) represents the difference
between actual heat transfer as compared with that without groundwater effect, and
the ratio is used as a correction factor in calculating the heat transfer rate of the
boreholes only if the ratio is greater than 1.
Chiasson et al. (2000) applied a two-dimensional finite element scheme to
discretise the boreholes and the surrounding ground under groundwater advection.
They analysed the variation of average borehole fluid temperature at different soil
materials under a preset hydraulic gradient. They found that with shale where the
groundwater velocity is very low, the borehole performance was not much different
from that without groundwater flow. With fine sand, the difference was only minor.
However, for coarse sand with high groundwater velocity, the difference was very
significant. They also investigated the effect of groundwater velocity on the thermal
response test result by simulating test data using the numerical scheme and analysed
the data based on the method adopted by Austin et al. (2000). The predicted thermal
conductivity increases with groundwater velocity, and the variation is more
pronounced with longer test period. Finally, the numerical scheme was used to
simulate the performance of a 4x4 borefield under various groundwater conditions.
24
groundwater in thermal response test. Li et al. (2005) applied a two-dimensional
finite difference scheme which assumed that heat and mass transfer in the vertical
direction was negligible, and studied the quasi three-dimensional heat and moisture
transfer in a borefield. The boreholes were taken as inner heat sources in the
discretisation control volume. The performance of single borehole at different soil
properties and loading patterns was analysed. The model was further used (Li et al.,
2006) to simulate the performance of an existing installation comprising both
conventional vertical borehole heat exchangers and energy piles.
Fujii et al. (2004b) utilised the FEFLOW software (Diersch, 2002) to estimate
the groundwater flow pattern and heat transfer in an existing installation based on
site measured boundary parameters. Each borehole was approximated as a thermal
well. They compared the simulated data with CSM at no groundwater flow, giving
good agreement. The simulated performance for a single borehole with groundwater
flow was validated with thermal response test data, showing very little difference in
the heat exchange rate. The long-term behaviour of the entire borefield was then
predicted under four loading patterns. They commented that in designing a ground
thermal store with groundwater advection, the heat storage period and frequency
should be carefully selected depending on the groundwater velocity. He (2007) also
used FEFLOW to simulate the groundwater flow pattern in the Hong Kong
International Wetland Park. The estimated groundwater velocity was very small
with the same order of magnitude as the one calculated based on geological data
from construction site in the same district area.
25
and the fluid temperatures at inlet and outlet of borehole recorded. Medium-scale
laboratory TRT was made by Smith et al. (1999b) and recently, micro-scale
laboratory TRT was conducted by Katsura et al. (2006).
The underlying principle of TRT falls into two main approaches. The first
one is the application of LSM to determine the ground thermal conductivity
graphically. By combining Eq. (2.3) and (2.12),
qb 4a g t
T f T0 ln 2 + qRb (2.52)
4k g rb
measuring the gradient of the fluid temperature rise profile, the ground thermal
conductivity can be calculated. Besides, the borehole thermal resistance can also be
estimated.
Pahud and Mathey (2001) applied this method to determine the thermal
resistance of a borehole with double U-tubes at different alignments and backfills,
and the results were compared with those calculated based on the equations from
Hellstrom (1991). Pahud (2001) also used this approach to analyse the TRT results
of two boreholes near Luzern, and the results were compared with those obtained by
laboratory test of soil samples. The advantage of this approach is ease of application
without the need of computation work. However, LSM assumes no groundwater
flow. In case this is not fulfilled, the calculated ground thermal conductivity will
increase with time, as noted by Katsura et al. (2006). The calculated ground thermal
conductivity increases with groundwater velocity and may eventually go to infinity
when the fluid temperature rise becomes constant after a certain test period.
26
minimise the error term. There are various kinds of optimisation methods available.
Jain (1999) reviewed the characteristics of different methods and compared their
performance when applied in the analysis of TRT results. He commented that the
Nelder-Mead simplex method (Nelder and Mead, 1965) was one of best in terms of
rate of convergence and precision of method. This is a direct search method using
three basic operations (reflection, expansion and contraction) to optimise a function
with multi-dimensional domains.
Austin et al. (2000) adopted the short time step model developed by
Yavuzturk (1999) to analyse the TRT result using the Nelder-Mead simplex method.
They investigated the data from site and the results from Smith et al. (1999). They
also studied the sensitivity of parameters, and the effects of test period, far field
temperature, shank spacing, ground volumetric heat capacity, etc on the estimated
ground thermal conductivity. They commented that the TRT period should be at
least 50 hours. Gehlin and Hellstrom (2003a) used the Nelder-Mead simplex method
to compare the results of TRT analysis based on LSM (using Eqs. (2.8~10)),
simplified LSM (using Eq. (2.12)), CSM and a one-dimensional numerical model.
They also concluded that the test period should be at least 50 hours. They found that
the results obtained by using LSM and simplified LSM basically have no difference.
LSM predicted better than CSM and numerical model at the early stage of test. By
excluding results for the first 10-15 hours, CSM performed the best. If results for the
first 5-10 hours were excluded, the numerical model gave the nearest estimate.
Wagner and Clauser (2005) developed a numerical model for the borehole
and applied parameter estimation graphically using the ground thermal conductivity
and thermal diffusivity as parameters to minimise a misfit function. Shonder and
Beck (1999) derived a one-dimensional numerical model with the U-tube replaced by
a single pipe of equivalent diameter and applied parameter estimation using the
Gauss minimisation technique to investigate the TRT results from a laboratory setup.
Georgiev et al. (2006) analysed the TRT data of a shallow borehole using both
approaches. The model of Shonder and Beck (1999) was used in the second
approach and results compared. The estimated parameters were then applied to
simulate the performance of the borehole with periodic charging from a solar panel
and discharging using the TRNSYS DST model.
27
Researches on TRT analysis including groundwater effect were also made.
Gehlin and Hellstrom (2003b) developed three models to study the groundwater
effect on the borehole performance installed in hard rock under different assumptions
of groundwater flow conditions. At low groundwater velocity, the three models
differ mildly, while at high groundwater, the difference is prominent. They
presented graph showing the ratio of effective ground thermal conductivity to actual
thermal conductivity at different groundwater velocity based on the three models.
With the effective thermal conductivity determined from TRT and actual thermal
conductivity from laboratory test or other means, the groundwater velocity can be
estimated from the graph.
Katsura et al. (2006) applied the first approach to analyse the TRT results
performed using a laboratory setup at no groundwater flow in order to estimate the
effective soil thermal conductivity. They then used the estimated soil thermal
conductivity and adopt the LSMGA stated by Diao et al. (2004) to compare the
simulated data with the experimental TRT results under controlled groundwater
velocities. The differences were found to be small. They further proposed a method
to estimate the groundwater velocity from the TRT results based on known ground
thermal properties.
2.2.1 General
28
As noted by Griffiths (1992), the sole employment of conventional vapour
compression system for achieving a low sensible/latent load ratio usually required
sub-cooling to a very low temperature and reheating of the supply air. This implies
that the capacity of the air conditioning system should be higher than what is actually
necessary and sub-cooling to low temperature reduces the energy efficiency of the
system, resulting in a high operating cost. Liquid desiccant dehumidification
systems offer the advantages that the duty of the dehumidifier matches exactly the
requirement and that low-grade or even waste heat can be utilised, thus reducing the
operating cost.
29
Ghaddar et al. (2003) studied a solar-assisted liquid desiccant
dehumidification system installed in Beirut where the regenerative heat came partly
from the solar system and partly from a gas heater. A cooling tower is used to pre-
cool the strong desiccant solution before entering the dehumidifier tower. They
found that if no solar panel was used, the payback was immediate. With more solar
panels used, the payback period would be longer although the energy cost would be
lower. The regeneration temperature was about 45-50oC, which offered extra saving
potential if waste heat was available.
The application of liquid desiccant to air conditioning system can also take in
other form. Yuan and Alberce (2004) developed a cross-flow air-to-air total heat
recovery unit incorporating membranes soaked with desiccant solution placed
between the two air streams. Heat and moisture is transferred through the
membranes across the two air streams. They claimed that the total heat recovery
efficiency could be more than 80%, and was maintenance free as no moving part was
included. This was considered to be more beneficial as compared with a system
using a desiccant heat wheel.
The key item in a liquid desiccant dehumidifier is the packed tower. The
performance of the packed tower depends on the simultaneous heat and mass transfer
along the tower. There are mainly two modelling approaches. The first one is based
on coupled fundamental heat and mass transfer equations which are solved
numerically by using the finite difference method to determine the variation of states
in the air and desiccant stream along the tower. As counter-flow packed tower is
usually studied, a fully implicit scheme is used. Treybal (1969) applied this
approach and developed a design method for the packed tower which accounted for
the mass and heat transfer resistances of the liquid phase. Factor and Grossman
(1980) followed similar ideas to develop a model for the packed tower. They
compared the simulated data with the test results from an experimental setup using
lithium bromide solution and good agreement was found.
30
Lazaarin et al. (1999) also adopted the same method to derive a numerical
model for a packed tower and compared the computed data with the test results using
lithium bromide and calcium chloride solution, showing a maximum error of about
20%. They compared the performance of the packed tower in terms of humidity
reduction and tower efficiency at different solution-to-air mass flowrate ratios. Both
parameters increased with the mass flowrate ratio. They commented that maximum
humidity reduction was attained when the leaving air water vapour pressure was the
same as the saturated water vapour pressure of the entering desiccant solution. Fumo
and Goswami (2002) studied experimentally the dehumidification and regeneration
performance of a liquid desiccant packed tower using lithium chloride solution.
They investigated the dehumidification and regeneration rate at different air and
desiccant conditions, showing a linear correlation in most cases. They also
compared the test results with the numerical tower model.
Mago et al. (2006) applied the numerical tower model to investigate the
performance of a hybrid liquid desiccant system with an auxiliary process air cooler
after the dehumidifier tower. The tower performance agreed with experimental
results from previous research work. They also found that at constant desiccant inlet
temperature and incoming air condition, a higher dehumidification rate in the packed
tower would result in a lower capacity required for the auxiliary air cooler to meet
the same cooling demand. Khan and Ball (1992) derived the governing heat and
mass equations in a simplified way. They then proposed a generalised formula for
the leaving air humidity ratio which related to the entering air humidity ratio,
solution temperature and concentration, and determined the corresponding
coefficient from the simplified numerical model.
In the numerical model, the heat and mass transfer coefficient are important
parameters. Most workers adopted equation for the mass transfer coefficient with
different formulations for different packing types in various air and liquid mass flow
range and derived solution for the heat transfer coefficient based on the analogy
between heat and mass transfer. Gandhidasan et al. (1986) proposed simplified
correlations suitable for use within a wide range of air and liquid flow conditions.
Chung et al. (1996) proposed empirical equations for the heat and mass transfer
coefficients based on experimental data for random and structured packed tower
31
using lithium chloride solution. Their formulations did not follow the analogy
between heat and mass transfer. Elasrrag et al. (2004) conducted a similar study for
a structured packed column using triethylene glycol. They proposed alternative
equations for the mass transfer coefficient in terms of the Sherwood number based on
different solution-to-air mass flow ratio ranges. Analogy between heat and mass
transfer was then applied to evaluate the heat transfer coefficient.
32
Elsayed (1994) studied the performance of a liquid desiccant
dehumidification system with desiccant cooler before the dehumidifier tower and
regenerative air heat exchanger and heater but without desiccant-to-desiccant heat
exchanger. He assumed fixed values for the humidity ratio and enthalpy
effectiveness for the dehumidifier and regenerator towers. He found that for normal
operation of the system, there was a minimum value for the desiccant to air mass
flow ratio which depended on the operating conditions. He also derived expression
for the COP of the system. He investigated the effects of various parameters on the
COP and concludes that for high COP, regenerative heater was not required if the
system operates at the minimum desiccant to air mass flow ratio, and the design mass
ratio should be close to the minimum value.
The vapour compression system employing the reverse Carnot cycle is the
most common type of equipment used for air conditioning and refrigeration.
Gaseous refrigerant is compressed to high pressure and temperature through the
compressor before entering a condenser where the refrigerant is condensed, in most
cases, to become a sub-cooled liquid. The high pressure liquid refrigerant is then
expanded through an expansion device before entering the evaporator where it is
usually evaporated to a super-heated gas. ASHRAE (2004, 2006) described the
various aspects of vapour compression systems used for air conditioning and
refrigeration, and ASHRAE (2005) provided information of properties in the form of
tables and charts for a number of refrigerants commonly used.
33
obtained by balancing the energy change and refrigerant mass flow through the cycle
iteratively until convergence is reached. This most popular approach allows
investigation of the effects of various parameters on performance of the vapour
compression system. In some cases, performance of individual component is
estimated by interpolation or equation fitting of the performance data from the
component suppliers.
34
heat transfer coefficients were adopted instead of just assigning a fixed value, and the
log mean temperature was used instead of the arithmetic mean temperature. For the
evaporator, different formulations were used depending on whether the evaporating
fluid was water or air. Condensation and frosting was accounted for if the
evaporating fluid was air. The model was also verified with test data.
Stefanuk et al. (1992) followed the same approach as Domanski and Didion
(1984) to simulate the performance of a water-to-water heat pump with thermostatic
expansion valve. Refrigerant charge balance was used instead of specified sub-
cooling at condenser outlet for cycle iteration. The calculation of heat transfer and
refrigerant charge in the coils within the saturated region of the refrigerant was
carried out in a numerical way by subdividing those parts of the coils into various
segments. The parameters used to model the compressor were estimated from the
suppliers performance data/curves by trial-and-error. Again, the model was
validated with experimental results.
Jin and Spitler (2002) also developed a model for a water-to-water heat pump
using thermostatic expansion valve. Isentropic compression was assumed, and
pressure drops at compressor inlet/outlet were accounted for. For the condenser and
evaporator, the refrigerant was assumed to be mostly in the saturated region. Hence,
the simple thermal effectiveness equation with fixed temperature on one side was
adopted. The refrigerant leaving the condenser was a saturated liquid with no sub-
cooling. Refrigerant charge balance was not applied. All design parameters
including coil effectiveness, compressor efficiency, etc. were then determined using
a parameter estimation technique from the system catalog data. No experimental
work or data for individual components were required, and the error level was still
satisfactory.
Jung et al. (1999) modified the model developed by Stoecker and Jones
(1982), including the effect of pressure drop due to sub-cooling and area contraction,
to determine the characteristic of capillary tube. They derived empirical equations to
relate the refrigerant mass flowrate with tube diameter, tube length, condensing
temperature and degree of sub-cooling suitable for different refrigerants with
different sets of coefficients.
35
Chapter 3 : Mathematical Formulations for
Geothermal and Liquid Desiccant Systems
In developing the numerical model for the ground heat exchanger borefield,
the following assumptions are adopted in order that comparison with the analytical
models can be made:
All subsequent analyses in this research will thus be based on the above
assumptions.
Figure 3.1 shows the grid scheme used for the ground around a borehole.
The implicit difference equation with regular grids can be obtained by direct
36
discretisation of the following governing differential equation for conductive heat
transfer in the ground with ground water advection:
Tg Tg Tg
g cg = k g 2Tg gw c gwV gw cos + sin + Qs (3.1)
t x y
Eq. (3.1) can be written in energy balance form with non-uniform grids as
Tgn,i+,1j ,m Tgn,i , j ,m Q x + + Q x + Q y + + Q y + Q z + + Q z + Qcx + Qcy + Qs q fact
= (3.2)
t g c g x j y m z i
where
Tgn,+i ,1j +1,m Tgn,i+,1j ,m
Q x + = k g y m z i
dx j
37
Ground surface
y dx
d
x
Tg,i-1,j,m
Tg,i,j,m+1
Borehole
H zi
Tg,i,j,m dy
dzi
Tg.i,j-1,m Tg,i,j,m Tg,i,j+1,m y
Tg,i+1,j,m
Tg,i,j,m-1
Vgw
x
z
Tube u Tube v
Borehole
buv
z
Tg,i,j,m+1 Tg,i,j+1,m+1
Figure 3.2 shows the grid scheme used for the boreholes. With fluid flowing
in the tubes, the fluid temperatures along the tubes are strongly coupled. Hence, all
grid fluid temperatures have to be solved simultaneously. However, assuming
conduction along the boreholes to be small compared with that in the transverse
direction when there is no fluid flowing in the tubes, the fluid temperatures along the
38
tubes not within the same control volume are only weakly coupled. Hence, the
numerical formulation is different. The borehole temperature (Tb,i) and loading (qb,i)
are defined at mid level of the control volume while the ground temperatures are
defined at the grid points. The borehole temperature is computed by averaging the
ground temperatures around the borehole surface. Hence, eight ground temperatures
are required to calculate the borehole temperature in each control volume, and that
the source term (Qs) at particular ground grid point on the borehole surface should be
determined from the borehole loadings above and below the ground grid point.
For a borehole containing nt tubes, the energy transfer at any tube u inside the
borehole can be determined from
dT fl ,u nt
T fl ,u T fl ,v T fl ,u Tb
(1) C f
m1
=
+
Cf = mf cf (3.3)
dz v =1
Ruv Ruu
v u
(T f ,i ,u + T f ,i +1,u ) 2Tb ,i
+
(3.4)
2 Ruu
Eq. (3.4) represents (nt x (nzbore -1)) coupled equations in (nt x nzbore) variables (Tf,i,u)
for one borehole by writing Eq. (3.4) consecutively for i=1 to (nzbore -1) for all
control volumes and u=1 to nt for all tubes, which are solved iteratively based on the
prescribed fluid inlet temperature, pipe connection configuration and borehole
temperatures. If all boreholes are connected in parallel, the borehole fluid inlet
temperature will be the borefield fluid entering temperature, and the borefield fluid
leaving temperature will be the average of all the borehole fluid outlet temperatures
which may be different depending on the relative positions of the boreholes in the
borefield. If some of the boreholes are connected in series, the fluid inlet and outlet
39
temperatures for the inter-connected boreholes will be coupled. The borehole
loading of each borehole is then calculated as
nt
T f ,i +1,u T f ,i ,u nt
(T f ,i ,u + T f ,i +1,u ) 2Tb ,i
qb ,i = (1) m1 C f =
(3.5)
u =1 dzi u =1 2 Ruu
The derivation of Ruv is given in the Appendix A. If all tubes are identical with
equal distance from the borehole centre, Ruu will be the same for all u, and Eq. (3.5)
can be re-written as
1 nt
nt Tb,i
qb,i = (T
u =1
f ,i ,u + T f ,i +1,u )
(3.6)
2 R11 R11
It should be noted that due to the difference in the borehole temperature profile, the
loading of each borehole in a borefield can still be different even if the borehole fluid
inlet temperature is the same.
Recalling Eq. (2.3) and defining the fluid temperature, borehole temperature
and borehole load as a weighted average along the borehole, then
~ ~
~ T f Tb
qb = ~ (3.7)
Rb
where
nzbore 1
qb ,i dz i ~ nt nzbore 1
(T f ,i ,u + f ,i +1,u )dz i ~
nzbore 1
Tb ,i dz i
q~b = Tf = Tb = (3.8)
i =1 H u =1 i =1 2nt H i =1 H
40
other researchers as the outlet fluid temperature is the most important parameter to be
determined rather than the actual fluid temperature variation inside the borehole.
nt
T fln,+i ,1u T fln,+i ,1v T fln,+i ,1u Tbn,i
Cf (T fln,+i ,1u T fln,i ,u ) =
+
(3.11)
v =1 Rnf ,uv Rnf ,uu
vu
rpi2 f c f
where Cf = (3.12)
t
The derivation of Rnf ,uv is also given in the Appendix A. Eq. (3.11) represents nt
equations in nt unknowns (T fln,+i1,u ) by writing Eq. (3.11) consecutively for u=1 to nt for
all tubes at the ith control volume. To solve T fln,+i1,u , Eq. (3.11) is re-written as
nt n +1
Tbn,i nt
T fln,+i ,1v 1 T fl ,i ,u
CfT n
fl , i , u +
=
+ + Cf (3.13)
Rnf ,uu v =1 Rnf ,uv v =1 R R
vu nf , uv nf ,uu
Eq. (3.13) can be expressed in matrix form as
n
CfT n + Tb ,i = R n +1
[ ]
*
nf ,uv T fl ,i ,v
fl ,i ,u
Rnf ,uu
where
* 1
Rnf ,uv = for u v and
R nf ,uv
41
* N 1
nf ,uu + Cf
R =
v =1 R
nf ,uv
Hence,
1
* n
Tbn,i
[
n +1
Rnf ,uv CfT fl ,i ,v + = T fl ,i ,u ] (3.14)
Rnf ,vv
All the borehole fluid temperatures will be solved by applying Eq. (3.14)
consecutively for each control volume of the boreholes in the borefield. Following a
similar transformation methodology applied to flow processes with identical tubes
and at the same distance from the borehole centre,
~ R
Rnf ,b = nf ,11 (3.15)
nt
Again, the borehole thermal resistance will be independent of the temperature
variation along the tubes and borehole surface, and the pipe connection configuration
inside the borehole. The weighted average of the fluid temperatures inside the
borehole will be used as the borehole fluid outlet temperature for the next fluid-
flowing time step.
42
|Tnew iteration step Told iteration step| < Tolerance (3.17)
where QAC is the applied air conditioning load to the borefield. In practice, the
applied borefield loading varies with time or the system does not operate
continuously within a day. Hence, there is a transient response in the borefield
performance, usually resulting in a time delay. The load transferred to the borefield
is then evaluated as
Qbf = mbf , f c f (Tbfn +, 1f ,in Tbfn +. 1f ,out ) (3.19)
The borefield thermal resistance indicates the overall performance of the entire
borefield while the borehole thermal resistance shows the situation for individual
borehole. Unlike Eqs. (3.9&15), the borefield and borehole thermal resistances will
depend on the temperature variation along the borehole surface and within the
borehole fluid. The borehole thermal resistance can also be different depending on
the relative position of the borehole in the borefield.
A borefield usually contains more than one borehole, and the effect of
groundwater on each borehole is different. The global effect on the entire borefield
depends on the position and connection configuration of the boreholes. In this way,
a change in the groundwater direction may result in a substantial difference in the
performance of the borefield under a specified groundwater flowrate, system
configuration and loading profile. To analyse the problem, a percentage variation
43
(PV) is defined based on the borefield leaving fluid temperature rise applicable to
sub-tropical regions under different groundwater directions as
(T f , simulated T f ,measured ) 2
MSD = 1
(3.22)
ndata
44
3.2 Liquid Desiccant Systems
TG,out TL,in
out in
G'out L'in
PACKED TG + dTG TL
TOWER + d
G' + dG' L'
dz
TG TL + dTL
+ d
z G' L' + dL'
TG,in TL,out
in out
G'in L'out
d M w FwG a 1 PwL / Pt
= ln (3.24)
dz G 1 PwG / Pt
dG = G d (3.25)
dL = dG (3.26)
45
dL
d = (3.27)
L + dL
The sensible heat transfer between air and liquid desiccant is given as
dTG hc ,G a (TG TL )
'
= (3.28)
dz G cG
FwG a (3.31)
Dw w G
d p2
= 5.20 x10 5 (1 )1.56 L Prw0.333 Re1w.6
0.50
h a
'
(3.32)
c ,G
kw G
and for the structured packing case as
M w d eq2
= 2.25 x10 4 (1 ) 0.75 L Sc w0.333 Re1w.0
0.10
FwG a (3.33)
Dw w G
d eq2
= 2.78 x10 6 (1 )1.8 L Prw0.333 Re1w.6
0.40
h a
'
(3.34)
c ,G
kw G
Here,
w
Sc w = (3.35)
Dw w
d c wVG
Re w = (3.36)
w
46
cw w
Prw = (3.37)
kw
The change of states along the entire tower will be solved simultaneously by using an
iterative method for all segments along the tower. This approach is similar to the
calculation of the variation of fluid temperature inside a borehole in a flow process.
Assuming no change in the thermal properties for the desiccant across the
heat exchanger and employing an average value for the overall heat transfer
coefficient along the heat exchanger, the temperature effectiveness of a counter-flow
heater exchanger can be determined using the approach by Bejan (1993) as
1 e [ NTU (1Cmin / Cmax )] UA
= NTU = (3.38)
1 (C min / C max )e [ NTU (1Cmin / Cmax )] C min
Eq. (3.38) basically applies to any two fluids with no change in physical states and
nearly constant heat capacities within the temperature range considered. It is
difficult to say if C will be higher for desiccant solution at dehumidifier tower outlet
or regenerator tower outlet. Indeed, they may differ only slightly. If C min C max ,
Eq. (3.38) becomes
NTU
= (3.39)
1 + NTU
47
3.3 Vapour Compression Air Conditioning Systems
T
sr,dis
48
3.3.1 Compressor
In the condenser, the refrigerant can change from a superheated gas to a sub-
cooled liquid if sufficient cooling is provided and the refrigerant leaves the
condenser at least as a saturated mixture. However, there will be no change in the
composition of the condensing fluid if it is a liquid desiccant, and thus a constant
specific heat capacity can be assumed. As the refrigerant undergoes phase changes
during the cycle, the heat transfer coefficient will vary substantially within the coil
depending on the state of the refrigerant. Since an actual coil configuration is much
more complicated than just a single straight pipe, it is not easy to follow the
refrigerant path to determine the heat transfer between the refrigerant and the liquid
desiccant. Hence, instead of applying relevant formulae to evaluate the heat transfer
49
coefficient at different states of the refrigerant, an average value will again be
adopted throughout the coil. To calculate the global performance, the condenser coil
is divided into three parts, namely superheated, saturated and sub-cooled stage, as
shown in Figure 3.5.
T
Tr,dis
Trs,cond
Tr,co TL,ri
TL,dh2
TL,dhi
TL,dh1
0 x'cond,sc x'cond,sc+x'cond,sat 1
Figure 3.5 Change of state of refrigerant and condensing fluid across condenser
Here, x (0 < x < 1) is the proportion of coil for each stage, and l the characteristic
coil length where 0 refers to desiccant inlet and 1 the refrigerant inlet. Clearly,
, sc + xcond
xcond , sat + xcond
, sh = 1 (3.43)
To further simplify the analysis, average specific heat capacities are used for the
refrigerant along the superheated and sub-cooled regions.
In the superheated stage, Eq. (3.38) is applicable. Since the mass flowrate of
refrigerant is generally much lower than that for the liquid desiccant, the temperature
effectiveness for the superheated stage can be calculated as
[ NTU cond , sh (1C r , cond , sh / C L , dhi )]
1 e
cond , sh = [ NTU cond , sh (1 Cr , cond , sh / C L , dhi )]
(3.44)
1 (C r ,cond , sh / C L ,dhi )e
, shUAcond
xcond
where NTU cond , sh = (3.45)
C r ,cond , sh
The temperature change for the refrigerant and liquid desiccant can then be
determined as
50
Trs , cond = Tr , dis cond , sh (Tr , dis TL , dh 2 ) (3.46)
In the saturated stage, the refrigerant temperature remains constant except for
the zeotropic refrigerant mixtures like R407C. The temperature effectiveness
becomes
cond , sat = 1 e NTU cond , sat
(3.48)
, satUAcond
xcond
where NTU cond , sh = (3.49)
C L ,dhi
Should no sub-cooling occurs, the enthalpy change for the refrigerant is given by
C L ,dhi (TL ,dh 2 TL ,dh1 )
hr ,co = hr ,cond (3.51)
mr
with TL ,dh1 = TL ,dhi . The same condition will apply for Eq. (3.50).
xcond , scUAcond
where NTU cond , sc = (3.53)
Cr , cond , sc
The temperature change for the refrigerant and liquid desiccant are evaluated as
Tr , co = Trs , cond cond , sc (Trs , cond TL , dhi ) (3.54)
51
Appendix B. With all parameters estimated, the refrigerant charge in the condenser
can be calculated by
+ r ,co
, sat r ,cond , sat + x cond
M r ,cond = VOLcond xcond ,sc r ,cond (3.56)
2
The derivation of r ,cond , sat is given in Appendix C.
and
DSH = Tr , suc Trs ,evap = Const. (3.58)
TL,dc1 TL,dci
TL,di Tr,suc
Trs,evap
0 x'evap,sat 1
Figure 3.6 Change of state of refrigerant and evaporating fluid across evaporator
52
superheated gas if it is sufficiently heated. All other assumptions remain the same
unless the evaporating fluid is air, which will be dealt with in Section 3.3.8. The
calculation can be much simpler if there is no superheating of refrigerant, as direct
evaluation can be performed without any need for an iterative method. Figure 3.6
indicates the various states for the refrigerant and evaporating fluid (liquid desiccant)
in the evaporator. The derivations of the governing equations are similar to those for
condensers. It follows that
, sat + xevap
xevap , sh = 1 (3.59)
, satUAevap
xevap
where NTU evap , sh = (3.61)
C L ,dci
with TL ,dc1 = TL ,dci . The same condition will apply for Eq. (3.62).
, shUAevap
xevap
where NTU evap , sh = (3.65)
C r ,evap , sh
The temperature change for the refrigerant and liquid desiccant can then be
determined by
Tr , suc = Trs ,evap + evap , sh (TL ,dci Trs ,evap ) (3.66)
53
The evaporator performance can be determined by solving Eqs. (3.59~67).
As mentioned before, an iterative method may not be necessary. The algorithm for
the solution methodology is given in Appendix D. The refrigerant charge in the
evaporator is then given by
, sat r ,evap , sat
M r ,evap = VOLevap xevap (3.68)
Tia,p+1,q
EA Tea,p,q Tea,p,q+1
q
Tia,p,q
IA
Figure 3.7 Discretisation scheme for air-to-air heat exchanger
Assume that both the intake air and exhaust air streams are discretised into
the same number of equal segments (naahxr ) . The heat transfer across each tiny cell
can be determined from
54
UAaahxr (Tea , p , q Tia , p , q )
Cia , aahxr (Tia , p +1, q Tia , p , q ) = Cea , aahxr (Tea , p , q Tea , p , q +1 ) = 2
(3.69)
naahxr
Eq. (3.69) is an explicit formulation of the finite difference equation, which is
appropriate for a cross-flow system. For a counter-flow system, an implicit scheme
must be used. The temperature variation inside the heat exchanger is obtained by
solving Eq. (3.69) for p=1 to naahxr and q=1 to naahxr . The newly estimated
temperatures are used to calculate the temperatures in the downstream cells. The
outlet temperatures for the intake and exhaust air streams will be given by
naahxr naahxr
Tia, p,q +1
p =1
T
q =1
ea , p +1, q
The model for an air heater is basically the same as a condenser by using air
as the condensing fluid. The much higher mass flowrate of condensing air as
compared with that for the refrigerant allows the same formulations to be applied
except by replacing liquid desiccant properties with air properties.
The modelling of an air cooler is more complicated than the desiccant cooler
due to the possibility of condensation of moisture from the air. Two approaches can
be used, the first one being an approximate iterative method which is similar to that
55
for a desiccant cooler but with additional iteration work required, and the second one
the finite difference method.
To simplify the analysis, an average specific heat capacity is adopted for the
air along the saturation line. The enthalpy of the condensing water is neglected. In
this way, the air cooler can be considered to be composed of two partial coils (dry
and wet if sufficiently cooled) with similar formulations but having different air heat
capacities. The assumptions and governing equations for the partial coils are
basically the same as those for the desiccant cooler (Eqs.(3.59~68)) except that the
refrigerant may enter the coil as a superheated gas.
Figure 3.8 denotes the parameters used for the air cooler. x ac , wet is the
portion of wet air cooler which can be zero. The refrigerant entering the dry coil
may be saturated (Tr ,ac1 = Trs ,evap ) or superheated (Tr ,ac1 > Trs ,evap ) but the air enters
the wet coil at the dewpoint of air entering the air cooler (Tadp ,aci ) . The algorithm
Ta,aci
Tadp,aci
Tr,suc
Tsa
Trs,evap Tr,ac1
0 x'ac,wet 1
Figure 3.8 Change of state of refrigerant and air across air cooler
56
3.3.8.2 Finite Difference Method
With the air cooler sub-divided into numerous segments (nac ) , the heat
transfer rate across each segment is calculated from
H ac = UAac (Ta Tr ) / nac (3.71)
The enthalpy changes in the air and refrigerant streams are given by
ha = H ac / ma and hr = H ac / mr (3.72)
The complete solution is obtained by writing Eqs. (3.71&72) consecutively for each
coil segments and solving them iteratively. Different formulations will be used for
the air enthalpy change in the dry and wet regions. Basically, the finite difference
approach can also be used to obtain solutions for the case of an air condenser.
Figure 3.9 shows a single-zone under air conditioning control. The zone
material is assumed to be a lumped mass, and no time delay is considered in the
response of the zone temperature and relative humidity to the corresponding heat
load and supply air condition. By balancing the energy and moisture across the zone
at one time interval,
Cap zone
Qsen = C sa (Trta Tsa ) + C zone (Trta Tzone ) C zone =
t
Qsen + C sa Tsa + C zoneTzone
Trta = (3.73)
C sa + C zone
57
SA RTA
Tzone, zone
Single Zone
Figure 3.9 Single zone with air conditioning
58
Chapter 4 : Laboratory Setup for Experimental
Thermal Response Tests
Figure 4.1 shows a schematic diagram of the thermal response test rig
designed for use in this study. A test tank of size 0.8m(W)x0.8m(D)x1.2m(H) and
made of galvanized steel is used to hold the soil for the test. A model borehole,
made of a PVC tube of diameter 34mm and length 200mm, is inserted into the test
tank at 0.4m above the tank bottom level. An electric heater and a PT100
temperature sensor of 150mm in length is inserted inside the model borehole and
backfilled with a thermal enhanced grouting. A voltmeter and current meter is used
to measure the power consumption of the electric heater. Due to the high design
rating (650W at 220VAC) of the electric heater, the supply voltage to the electric
heater is stepped down by using a variable transformer to about 24VAC and the
rating dropped to about 6W. The temperature sensor is connected to a transmitter,
powered by a 30VDC supply, to convert the temperature signal from 0~104oC to
1~5VDC signal through a 250-ohm high precision resistor for logging by a computer.
Two remote temperature logging buttons are used to record the circulating water
temperature and the test room temperature.
The test tank is filled with sand up to a height of about 0.8m from the tank
bottom. A water pool is maintained on top of the sand by circulating water from and
to the circulating tank of size 0.4m(W)x0.5m(L)x0.4m(H) by a submersible pump
inside the circulating tank. The height of the water level in the test tank can be
controlled by regulating the supply and return water valves. This provides a
hydraulic head to push the water downward into the soil, thus simulating a
groundwater flow across the model borehole, to a drain connection at the bottom
level of the test tank. A valve is installed at the drain outlet for controlling the
groundwater flowrate which is measured by a direct readout flowmeter. The model
59
groundwater is directed to the floor drain of the test room. Fresh tap water is fed into
the circulating tank to make up for the lost groundwater.
Supply pipe
Overflow pipe
Return pipe
Soil
Circulating tank
From tap water
Groundwater
Constant Circulating flowmeter
temperature pump
water bath
To floor drain Test tank
Borehole
temperature
sensor
Borehole
60
As actual groundwater temperature at site tends to be constant, especially
below some depth from the ground surface, it is essential to maintain the circulating
water temperature within a narrow range. This is achieved by first passing the
circulating water through a constant-temperature water bath set at 23~24oC provided
by using a temperature sensor calibrating equipment before it enters the test tank. A
1500W electric heater, controlled by a built-in thermostat, is used to maintain the
required room temperature for tests conducted in winter. To further minimise the
effect of room temperature variation on the soil temperature, the test tank and the
circulating tank are wrapped with thermal insulation. A top cover is provided to the
test tank. A photo of the entire test rig inside the test room is shown in Figure 4.2.
Copper plates
Thermal insulation
Soil
Plate type heater
Cooling fan
Acrylic frame
Figure 4.3 Details of experimental setup for measuring soil thermal conductivity
Fig. 4.3 shows the details of the experimental setup used for measuring the
soil thermal conductivity. An acrylic frame of internal size 140mmx140mm and
thickness 6mm is used to house a lump of wet soil sandwiched by two copper plates.
A plate-type electric heater of capacity 125W at 120VAC is stuck on the exterior
surface of one copper plate, and the exterior surface of the other copper plate open to
the surrounding with a cooling fan placed to enhance the heat transfer in order to
reduce the temperature rise in the soil. The temperature difference across the soil is
61
measured by two thermocouples placed on each exterior surface of copper plates. To
ensure that most of the heat generated by the heater be transferred to the soil, the
acrylic frame and the heater side is covered with a layer of thermal insulation. A
variable transformer is used to control the heater output, and the power consumption
measured by a high precision power meter. A photo of the complete experimental
setup is shown in Figure 4.4.
62
to 40oC with 1oC interval while the thermocouples will be calibrated from 30 to 50oC
with 1oC interval.
63
High
precision
power meter load
(a) (b)
Figure 4.7 Layout of calibration setup for voltmeter and ammeter: (a) front view, (b)
rear view
The precision of all the measuring devices results in some uncertainties in the
measured or logged data. For the borehole temperature logger, a possible noise of
0.104oC is found, which will affect the logged borehole temperature profile and the
determination of the initial or farfield ground temperature (T0). The voltmeter and
the ammeter used for measuring the borehole loading (Qb) have a precision of
0.01V and 0.01A respectively, which accounts for an uncertainty in the borehole
loading of 0.0001W. The effect of uncertainties in T0 and Qb on the thermal
response test analysis results will be given in Section 6.2.3.4. The thermocouples
used in the soil thermal conductivity measurement test have a precision of 0.1oC.
64
The resulting uncertainty in the estimated soil thermal conductivity (kg) depends on
the actual kg and the heat flux through the soil. Based on a heat load of 20W passing
through the soil of thermal conductivity 3.0W/mK, the uncertainty in kg will range
from -0.268 to +0.326W/mK.
65
Chapter 5 : Methodologies for Simulation and
Analysis
To apply the numerical model developed in Section 3.1, the setting of the
grids and the load factor are to be determined first by comparing the simulated
ground temperatures with those using analytical models. This is essential in order
that the accuracy of the numerical scheme can be maintained without becoming
computationally expensive. Once the grid system is finalised, borefield performance
simulation can then be conducted both with and without groundwater advection.
Comparisons are also made with relevant analytical models. The effect of loading
profiles and groundwater conditions on the borefield performance will also be
investigated. Four loading profiles will be analysed:
1. Continuous constant load;
2. Constant load with a daily operating schedule of twelve hours;
3. Annual periodic load (approximated by a sine curve) with a zero minimum load
and daily operating schedule;
4. Annual periodic load with heating period (peak cooling load/peak heating load =
4) and daily operating schedule.
Unless otherwise specified, the peak cooling load for each loading profile will be
assumed to be the same. The annual heat injection to the ground corresponding to
Loading Profiles 2, 3 and 4 will then be 0.5, 0.25 and 0.1875 times that under
Loading Profile 1 respectively.
66
The determination of the definite integrals will be accomplished as indicated in
Appendix F. When determining the g-function, a weighted average is used instead of
a double integral using the same discretisation method as that used for the numerical
model. The thermal interference between adjacent boreholes will also be estimated
in a similar way. For LSMGA, Eqs. (2.37&38) will be used to calculate the average
borehole temperature with simplification made as shown in Appendix G. When
evaluating the thermal interference effect, Eq. (2.35) will be applied. The estimation
of the definite integral follows the approach presented in Appendix F. When dealing
with FLSMGA, the average borehole temperature is determined based on Eqs.
(2.42~45). The thermal interference effect is computed as shown in Appendix H.
Again, a weighted average for the ground temperature within the effective borehole
depth will be adopted.
Table 5.1 Default values of parameters used for simulation of borefield performance
67
Unless otherwise specified, the values given in Table 5.1 will be used in the
analysis. The effective ground thermal properties refer to those for wet soil, but the
groundwater velocity may be zero. This is to avoid a sudden discontinuity in the
ground thermal properties between dry and wet soil when the groundwater velocity
approaches zero for ease of comparison between the borefield performance with and
without groundwater advection. All boreholes are assumed to be connected in
parallel. The borefield load refers to the total loading handled by the borefield, but
the loadings for individual boreholes will be different in most cases.
Before performing the TRT analysis, besides the groundwater velocity, the
number of independent parameters to be estimated simultaneously has to be finalised
first. A sensitivity analysis will be made to select suitable parameters for analysis.
Once the parameter list is set, analysis can be conducted. In applying the parameter
estimation, initial guess points have to be assigned. For ease of generating the initial
guess points, each parameter is given a range with presumed minimum and
maximum values. This will not actually limit the search range in the simplex method
and the final result can be outside this range. The first guess point is selected
randomly within 30~50% of the corresponding parameter range for each parameter.
The second guess point will be the same as the first guess point except that the first
parameter will be increased by 20% of the first parameter range. The third guess
point differs from the first guess point by increasing the second parameter by 20% of
the second parameter range. The remaining guess points can be obtained by
following the same method.
In each analysis, three trials will be made. This allows the elimination of pre-
mature completion according to the second completion criterion as stated in Eq.
(3.23) where the MSDs of all the test points may be very close to each other but
none of them are the optimum points. Moreover, the confidence of the parameter
estimation method in determining the groundwater velocity can be investigated. This
is achieved by first analysing the test data generated from the same model but
excluding groundwater velocity in the parameter list. The result is then compared
68
with that analysed with groundwater velocity in the parameter list. Three models
will be applied, namely LSMGA, FLSMGA and the present numerical model. The
effect of the test period on the sensitivity of estimated groundwater velocity will also
be studied.
Analysis will then be made on the TRT results from an experimental setup
with controlled groundwater flowrate in order to verify the method. Regarding the
diameter and length of the experimental borehole with a length-to-diameter ratio of
less than 7, only the present numerical model will be used. Different groundwater
velocities will be tested and the estimated groundwater velocities compared with the
test values. The estimated soil thermal conductivity will also be compared with that
determined by laboratory method. Finally, the new parameter estimation method
including groundwater velocity will be used to analyse site TRT results provided by
others to investigate the possible outcome.
69
largest humidity ratio (and hence water vapour pressure in the air) from 1986 to 1995
based on the weather data from the Hong Kong Observatory. This condition will
also be used in the design of the ground-coupled liquid desiccant air conditioning
system. Random packing will be assumed throughout the analysis.
Table 5.2 Default parameter values used for determination of final configuration of
liquid desiccant dehumidifier
With the configuration for the liquid desiccant dehumidifier fixed, a heat
pump will be incorporated into the system, and the performance analysed in terms of
70
the COP for which only the compressor power is considered. Comparison will be
made with the conventional air-cooled fresh air unit (ACFAU) based on the same
coil properties, air flow and refrigerant charge under different outdoor conditions for
1986. Extra design parameters to be used are given in Table 5.3. Scroll compressor
(Model ZH15K4E) and R134a refrigerant will be used in the analysis.
Table 5.3 Additional parameter values used for analysis of heat-pump-coupled liquid
desiccant dehumidifier
71
considered in the building. The TRNSYS software package will be used to generate
a room loading profile for simulation. The building thermal capacitance indicated in
Table 5.4 includes the effect of building material and furniture as suggested by
Bradley (2007).
72
Chapter 6 : Results and Discussions
Before any simulation could be carried out, the grid sizes had to be carefully
set so that accuracy could be maintained without use of excessive computation time.
An analytical model was to be chosen for calibration. CSM was selected since it was
an exact solution under the presumed boundary conditions. As CSM excluded
groundwater effect, the calibration was performed for zero groundwater velocity.
Before setting grid sizes, the boundary of the borefield in vertical and
transverse directions had to be determined first. According to Eskilson (1987), the
distance travelled by a heat front from the heat source after time t could be estimated
as r = 3 a g t . By defining a maximum time (tmax) for analysis which was assumed
boreholes in the transverse directions and from the bottom of boreholes in vertical
direction where the ground was discretised.
To set the grid sizes in the transverse directions, Eq. (3.2) was simplified to a
two-dimensional case for a single borehole of infinite length, with the results
compared with those from CSM based on a constant continuous load along the
borehole for ten years. The grids and the load factor were adjusted so that the
calculated ground temperatures along borehole and those at particular distances from
the boreholes would be very close to those obtained by using CSM. Upon repeated
trial and errors, the first grid on the borehole surface would be rb / 2 from the
borehole centre. The second, third and fourth grid would be 3rb, 5rb and 7rb from the
borehole centre respectively. Beyond that, the grid spacing would be 1.65 times the
preceding grid spacing. This grid scheme applied to both transverse directions. The
73
load factor was set to 1.047. A comparison of ground temperatures with CSM based
on the above grid system and load factor was shown in Table. 6.1 based on a
constant borehole loading of 30W/m.
With the transverse grids fixed, the vertical grids were to be set. The method
used by Eskilson (1987) was adopted for depths within and below the boreholes.
The number of discretisation segments along the borehole was chosen so that the
minimum segment length along the borehole would be around one metre. For depths
above the boreholes, the grid spacing from top of boreholes would be the minimum
segment length along the borehole as determined by Eskilson (1987). With the entire
grid scheme fixed, a comparison of ground temperatures was made with FLSM based
on a continuous constant load of 30W/m along borehole, as shown in Table 6.2. The
simulated results between the two models were quite close. Comparison was also
made between the simulated fluid leaving temperature from a single borehole using
Eq. (3.4) by adopting the finalised borehole discretisation scheme with the analytical
solution stated by Zeng (2002) based on a single U-tube inside the borehole and a
constant borehole temperature. The results agreed well with each other.
74
Table 6.2 Comparison of present model with FLSM
With the inclusion of groundwater effect, the numerical model for the two-
dimensional case was then compared with LSMGA based on a loading 30W/m after
10 years, as shown in Table 6.3. It could be noted that the differences were small
and no more than 2.8%. The complete three-dimensional model with groundwater
effect was finally compared with FLSMGA as shown in Table 6.4 using the
parameters indicated in Table 5.1.
75
Table 6.4 Comparison of present model with FLSMGA
Figures 6.1&2 showed the temperature rise and loading along single borehole
at different times against a dimensionless parameter (z-d)/H which assumed values of
one and zero at the borehole bottom and top respectively. It was found that neither
the temperature nor the loading was constant along the borehole. The borehole
temperature reached a maximum near the top part of borehole rather than near the
middle level of borehole if a finite line source model was used. The borehole
loading decreased with depth up to the bottom end of borehole. This could be
explained by considering the fact that the mean fluid temperature inside the borehole
decreased with depth as shown in Figure 6.3. Hence, near the top of borehole where
the borehole temperature increased with depth, the borehole loading would decrease
due to reduced temperature difference between the fluid and the borehole. The
situation changed only beyond the depth where the borehole temperature decreased
with depth at a higher rate than the mean fluid temperature near the lower part of
borehole. Basically, the borehole temperature and loading profiles changed very
76
mildly with time. Indeed, very similar profiles were obtained when using a
cylindrical coordinate system for a single borehole.
0.2 0.2
1 year 1 year
(z-d)/H
(z-d)/H
1 1
Figure 6.1 Temperature rise along single Figure 6.2 Loading along single borehole
borehole without groundwater flow at different without groundwater flow at different times
times
16
Temperature rise (K)
14
Down flow fluid
12
Up flow fluid
10
Mean fluid
8
Borehole
6
4
0 0.2 0.4 0.6 0.8 1
(z-d)/H
Figure 6.3 Comparison of fluid and borehole temperature rise in single borehole
without groundwater flow after 1 year
77
borehole temperature profile and thermal resistance of each borehole could thus be
different. The present numerical method accounted for the varying coupling effect
between the ground and the borehole fluid temperatures along the boreholes. Hence,
individual finite difference scheme would be needed for each borehole for a precise
simulation when the method of superposition was used to determine the performance
of a borefield. A simpler way would be to discretise the entire borefield, and
perform the simulation for all boreholes simultaneously. This was easily achieved
when using a rectangular coordinate system by expanding the original grid system in
transverse directions to cover the entire borefield.
Ground temperature profile after 5 years Ground temperature profile after 10 years
0.4 0.4
2m 2m
0.6 0.6
5m 5m
0.8 10m 0.8 10m
1 1
Figure 6.4 Ground temperature profiles around Figure 6.5 Ground temperature profiles around
single borehole without groundwater flow after 5 single borehole without groundwater flow after 10
years years
Table 6.5 Comparison of average ground temperature rise between present model
and FLSM after 10 years
Table 6.5 compared the mean ground temperature rise within the borehole
depth at various distances from the borehole calculated using the present simulation
78
tool and the finite line source model. It could be observed that at a distance of 5m or
less, the differences between numerical and analytical results were small and less
than 2%. However, at 10m from borehole, the situation changed with a resultant
difference of up to 12.5%, contrary to a value of less 1% for ground temperature at
mid borehole level as shown in Table 6.2 which assumed a constant borehole load
profile. This could lead to substantial deviation in estimating the performance of a
large borefield when considering the thermal interference effects from distant
boreholes. To verify this, the performance of various borefields with a borehole
spacing of 5m was simulated using the present finite difference scheme and the finite
line source model, as shown in Table 6.6. For a small borefield of up to 3x3
boreholes, the percentage difference was no more than 2.1. However, for a 5x5
borefield, the percentage difference rose up to more than 5. It could be anticipated
that for a larger borefield of more than 10x10 boreholes, the percentage difference
could be more than 10%. The present model was considered to be more accurate as
it accounted for the variation of temperature and loading along the boreholes which
occurred in real-life situations.
Table 6.6 Comparison of average borehole temperature rise between present model
and FLSM after 10 years for various borefields
Table 6.7 showed the variation of borefield thermal resistance (Rbf) according
to Eq. (3.20) with time for various borefield configurations. For a single borehole,
the thermal resistance changed very little with time. This could be explained by
considering the fact that the borehole temperature profile, which affected the thermal
resistance, did not change much with time as already shown in Figure 6.1. For a
79
borefield with more than one borehole, the thermal interference from adjacent
boreholes depended on distance, depth and time. This caused the borefield thermal
resistance to vary more with time, especially for larger borefields. When using
FLSM based on an average borehole temperature along borehole, the thermal
resistance was fixed at around 0.1253. This deviation of thermal resistance between
the present numerical method and FLSM would lead to an extra difference when
estimating the fluid temperature rise.
Table 6.7 Variation of borefield thermal resistances with time for various borefields
without groundwater flow
80
was switched on and off frequently during the low-load period. This also illustrated
the benefit of applying numerical modeling for the borefield in the dynamic
simulation of an actual system as compared with the load aggregation method using
an analytical model.
4000
3500
Figure 6.6 Variation of borefield load during a daily operation schedule of 12 hours
for single borehole without groundwater flow
12.5
12
11.5
Tbf,f,out - To (K)
DV=0
11
DV=1E-7
10.5
DV=2E-7
10
DV=5E-7
9.5
9
8.5
0 20000 40000 60000 80000
Simulation time (Hours)
Figure 6.7 Variation of leaving fluid temperature rise of single borehole at different
Darcy velocities of groundwater flow
Figure 6.7 showed the variation of fluid leaving temperature rise of a single
borehole at different Darcy velocities of groundwater flow through a 10-year period
under a continuous constant load. At a very low Darcy velocity, the leaving fluid
temperature increased throughout the 10-year period. With a sufficiently high
groundwater velocity, the leaving fluid temperature reached a steady state within 1
year. The temperature rise was reduced with an increase in the groundwater velocity,
81
indicating the importance of an accurate prediction of the groundwater velocity in the
optimisation of a borefield design.
Figures 6.8&9 showed the temperature rises and Figures 6.10&11 the
loadings along a single borehole at different Darcy velocity of groundwater. The
curves were basically similar to those of Figures 6.1&2. The temperature profiles
and consequently the borehole thermal resistance did not change much with
groundwater velocity. This was important in thermal response test analysis which
would be discussed in Section 6.2, as borehole thermal resistance could be
considered as independent of groundwater velocity.
Borehole temperature rise variation after 5 years Borehole temperature rise variation after 10 years
0.2 0.2
DV=0 DV=0
(z-d)/H
(z-d)/H
1 1
Figure 6.8 Temperature rise along single Figure 6.9 Temperature rise along single
borehole after 5 years at various groundwater borehole after 10 years at various groundwater
velocities velocities
Borehole loading variation after 5 years Borehole loading variation after 10 years
0.2 0.2
DV=0 DV=0
(z-d)/H
(z-d)/H
1 1
Figure 6.10 Loading along single borehole after Figure 6.11 Loading along single borehole
5 years at various groundwater velocities after10 years at various groundwater velocities
82
Figures 6.12~15 indicated the performance of a single borehole under
different loading profiles but with the same peak cooling load. It could be found that
the introduction of a daily operating schedule of 12 hours reduced the fluid leaving
temperature rise by less than 35% at no groundwater flow although the total heat
rejection to the ground was decreased by 50%. The application of a periodic load
only changed the borehole performance a little, and the inclusion of heating period
had insignificant effects. In contrast to a 81.25% reduction in the total heat injection
to the ground, the fluid leaving temperature rise for Profile 4 was only reduced by
42%. Indeed, the effect of loading profiles decreased with increase in groundwater
velocity, and the borehole performance became independent of the loading profiles at
a very high groundwater velocity, say 10-5m/s or higher. This indicated that the peak
cooling load was a very important parameter in the design of the borefield. The
reduction of the peak cooling load by other means, such as adopting a hybrid system
to share the cooling load at the peak-load season, could significantly reduce the
required borehole lengths especially when the groundwater velocity was high.
Leaving fluid temperature rise with no groundwater flow Leaving fluid temperature rise with groundwater velocity
at different load profiles 1E-7m/s at different load profiles
14 12
12
Tbf,f,out - To (K)
10
Tbf,f,out - To (K)
10 Profile 1 Profile 1
8
8 Profile 2 Profile 2
6
6 Profile 3 Profile 3
4 4
Profile 4 Profile 4
2 2
0 0
0 20000 40000 60000 80000 100000 0 20000 40000 60000 80000 100000
Time (Hour) Time (Hour)
Figure 6.12 Performance of single borehole at Figure 6.13 Performance of single borehole at
no groundwater flow for different load profiles groundwater velocity 10-7m/s for different load
profiles
Leaving fluid temperature rise with groundwater velocity Leaving fluid temperature rise after 1 year with high
2E-7m/s at different load profiles groundwater velocity at different load profiles
12 12
10
Tbf,f,out - To (K)
10
Tbf,f,out - To (K)
Profile 1 Profile 1
8 8
Profile 2 Profile 2
6 6
Profile 3 Profile 3
4 4
Profile 4 Profile 4
2 2
0 0
0 20000 40000 60000 80000 100000 0 20 40 60 80 100
Figure 6.14 Performance of single borehole at Figure 6.15 Performance of single borehole after
groundwater velocity 2x10-7m/s for different load 1 year at high groundwater velocity for different
profiles load profiles
83
6.1.4 Effect of Groundwater Velocity on Borefield Design Length at Different
Load Profiles
Table 6.8 Variation of peak borefield load with fixed leaving fluid temperature rise
at different load profiles for single and 2x2 borefield without groundwater flow
Variation of borehole length ratio with groundwater Variation of borehole capacity ratio with groundwater
velocity at different load profiles for single borehole velocity at different load profiles for single borehole
1.2 2.5
Borehole capacity ratio
Borehole length ratio
1
Profile 1 2 Profile 1
0.8
Profile 2 Profile 2
0.6 1.5
Profile 3 Profile 3
0.4
Profile 4 1 Profile 4
0.2
0 0.5
0 20 40 60 80 100 0 20 40 60 80 100
Figure 6.16 Variation of borehole length ratio Figure 6.17 Variation of borehole capacity ratio
with groundwater velocity at different load with groundwater velocity at different load
profiles with fixed leaving fluid temperature rise profiles with fixed leaving fluid temperature rise
for single borehole for single borehole
84
Variation of borehole length ratio with groundwater Variation of borehole capacity ratio with groundwater
velocity at different load profiles for 2x2 borefield velocity at different load profiles for 2x2 borefield
1.2 3.5
Figure 6.18 Variation of borehole length ratio Figure 6.19 Variation of borehole capacity ratio
with groundwater velocity at different load with groundwater velocity at different load profiles
profiles with fixed leaving fluid temperature rise with fixed leaving fluid temperature rise for 2x2
for2x2 borefield borefield
The borehole length determined the initial cost of geothermal heat pump
systems. Hence, the understanding of the effect of borehole length on borefield
performance helped select the best length to be used. Analysis was made for single
and 2x2 borefields by comparing the borefield performance having longer ( H = 120)
and shorter ( H = 100) effective borehole lengths with that using the default length
( H = 110) in terms of the leaving fluid temperature rise ratios under different
groundwater velocities assumed to be parallel to the x-axis and load profiles, as
shown in Figures 6.20~23.
85
Variation of leaving fluid temperature rise ratio of single Variation of leaving fluid temperature rise ratio of single
borehole with short borehole length borehole with long borehole length
1.14 0.915
Figure 6.20 Variation of leaving fluid temperature Figure 6.21 Variation of leaving fluid temperature
rise ratio of single borehole with short borehole rise ratio of single borehole with long borehole
length at different groundwater velocities and load length at different groundwater velocities and load
profiles profiles
Variation of leaving fluid temperature rise ratio of 2x2 Variation of leaving fluid temperature rise ratio of 2x2
borefield with short borehole length borefield with long borehole length
1.135 0.92
Temperature rise ratio
Figure 6.22 Variation of leaving fluid temperature Figure 6.23 Variation of leaving fluid temperature
rise ratio of 2x2 borefield with short borehole rise ratio of 2x2 borefield with long borehole
length at different groundwater velocities and load length at different groundwater velocities and load
profiles profiles
It could be found that the temperature rise ratio departed more from unity
with an increasing groundwater velocity, indicating that the borefield performance
was more sensitive to borehole length at a higher groundwater flow. The curves
basically differed very little under different loading profiles, unlike the borefield
performance which changed substantially with the application of daily operating
schedule. Hence, the study of borefield size on the temperature rise ratio needed
only be based on one loading profile such as a periodic load with no heating with a
daily operating schedule.
Figures 6.24&25 depicted the variation of the leaving fluid temperature rise
ratio for various borefields. The curves shifted towards the unity line where
temperature ratio equals 1 when the borefield size increased, indicating that the
percentage change in borefield performance became smaller under the same change
in borehole length. In other words, the benefits in the form of a much higher energy
efficiency for the geothermal heat pumps due to a lower leaving fluid temperature
86
rise from the borefield could only be achieved at the expense of a much higher cost
because of the larger increase in the borehole length for a large borefield. This
illustrated again the importance of considering every possible means for improving
the borefield performance when designing a large borefield, including groundwater
direction effect to be discussed later.
Variation of temperature rise ratio with short borehole Variation of temperature rise ratio with long borehole
length for different borefields length for different borefields
1.14 0.93
Temperature rise ratio
Figure 6.24 Variation of leaving fluid temperature Figure 6.25 Variation of leaving fluid temperature
rise ratio with short borehole length at different rise ratio with long borehole length at different
groundwater velocities and borefields under load groundwater velocities and borefields under load
profile 3 profile 3
In the above analysis, the peak applied borefield load per borehole was fixed
at the default value. This meant that the leaving fluid temperature rise would be
lower at higher groundwater velocities. It might not be clear if the temperature rise
ratios shown in Figures 6.20~25 could not reflect the actual change in the leaving
fluid temperature rise which determined the heat pump performance. Hence, another
analysis was made for a 2x2 borefield where the borefield load was adjusted so that
the same leaving fluid temperature rise of 12.269oC would apply as used in Section
6.1.4 for the default borehole length, as shown in Table 6.9.
Table 6.9 Variation of peak borefield load at different load profiles and groundwater
flow for 2x2 borefield based on fixed leaving fluid temperature rise at default
borehole length
87
Figures 6.26&67 showed the variation of the leaving fluid temperature rise
ratio at different groundwater velocities and load profiles. The trends were very
similar except that the introduction of daily operating schedule produced a greater
difference in the temperature rise ratio, especially at higher groundwater velocities.
Hence, it could be expected that the same patterns could be obtained for Figures
6.24&25 even with a fixed leaving fluid temperature rise at the default borehole
length.
Variation of leaving fluid temperature rise ratio of 2x2 Variation of leaving fluid temperature rise ratio of 2x2
borefield with short borehole length borefield with long borehole length
1.14 0.92
0.915
1.13
Profile 1 0.91 Profile 1
1.12 Profile 2 0.905 Profile 2
Figure 6.26 Variation of leaving fluid temperature Figure 6.27 Variation of leaving fluid temperature
rise ratio of 2x2 borefield with short borehole rise ratio of 2x2 borefield with long borehole
length at different groundwater velocities and load length at different groundwater velocities and load
profiles based on fixed leaving fluid temperature profiles based on fixed leaving fluid temperature
rise at default borehole length rise at default borehole length
88
Figures 6.28&29 showed the variation of PV for 2x2 and 3x3 borefield at
different groundwater velocities. It could be found that PV generally increased with
increase in groundwater velocity. PV was highest for the case of a continuous
constant load. With the introduction of a daily operating schedule, the maximum PV
was reduced by more than 40%. Replacing the constant load with a periodic load
approximated by a sine curve had insignificant effects even when a heating period
was applied to the load cycle (peak cooling load/peak heating load = 4). The patterns
were very similar to the performance for a single borehole as shown previously in
Figures 6.12~15. Basically, the effect of groundwater direction was small for square
borefields, and was negligible for groundwater velocities below 10-6m/s.
Change of PV with groundwater velocity after 10 years at Change of PV with groundwater velocity after 10 years at
different load profiles different load profiles
4 6
5
3 Profile 1 Profile 1
4
PV (%)
PV (%)
Profile 2 Profile 2
2 3
Profile 3 Profile 3
Profile 4
2 Profile 4
1
1
0 0
0 20 40 60 80 100 0 20 40 60 80 100
Darcy velocity of groundwater (10-7m/s) Darcy velocity of groundwater (10-7m/s)
Figure 6.28 Variation of PV with groundwater Figure 6.29 Variation of PV with groundwater
velocity for 2x2 borefield velocity for 3x3 borefield
Change of PV with groundwater velocity after 10 years at Change of PV with groundwater velocity after 10 years at
different load profiles different load profiles
8 14
12
6 Profile 1 10 Profile 1
PV (%)
PV (%)
Profile 2 8 Profile 2
4
Profile 3 6 Profile 3
2 Profile 4 4 Profile 4
2
0 0
0 20 40 60 80 100 0 20 40 60 80 100
Darcy velocity of groundwater (10-7m/s) Darcy velocity of groundwater (10-7m/s)
Figure 6.30 Variation of PV with groundwater Figure 6.31 Variation of PV with groundwater
velocity for 1x2 borefield velocity for 1x3 borefield
89
reached a maximum, and then decreased with further increase in groundwater
velocity. The maximum PV was nearly twice that at a Darcy velocity of 10-5m/s
under a constant load and with a daily operating schedule.
10
8
Square
PV (%)
6
1:2
4
2:3
2
0
0 2 4 6 8 10 12
Number of boreholes in x-direction
90
The reduction in the leaving fluid temperature rise affected the design length
of the boreholes, and the effect could be investigated by reviewing Figures 6.24&25.
With the temperature rise ratio closer to unity, a larger reduction in borehole length
could be achieved for the same improvement in borefield performance. In Figure
6.24 where the effective borehole length was reduced from 110 to 100m (about
9.091% reduction in length), a temperature rise ratio of lower than 1.1 would mean
that the percentage reduction in borehole length could be higher than the percentage
decrease in borefield performance. This applied to large borefields at low
groundwater flow velocities. The same finding could be made if the temperature rise
ratio is higher than 0.9167 as shown in Figure 6.25. Hence, a 10% decrease in the
leaving fluid temperature rise could possibly result in up to 15% decrease in the
borehole length for very large borefields, leading to a significant saving in the
installation cost. This was based on the assumption that the same allowable
maximum leaving fluid temperature and the recognition that a 10% decrease in the
temperature rise required a 11.1% increase in order to bring the temperature rise back
to the maximum limit. This highlighted the importance of understanding the
groundwater conditions in regard to both the magnitude and the direction in order to
achieve an optimal design. A correct setting of the orientation of the borefields could
cause a substantial reduction in the installation cost and shortening of the payback
period.
91
velocity. By performing simulation using Eq. 3.3 based on the correlations for the
thermal interference coefficients as proposed by Hellstrom (1991), it was found that
the borehole thermal resistance was very weakly affected by the ground thermal
conductivity. Hence, there were basically five independent parameters left.
Sensitivity of ground volumetric heat capacity on Sensitivity of ground thermal conductivity on borehole
borehole performance at different groundwater velocity performance at different groundwater velocity
Borehole fluid temperature rise
Borehole fluid temperature rise
1.025 1.15
1.02 DV=0 DV=0
1.015 1.1
DV=1E-7 DV=1E-7
1.01
DV=2E-7 1.05 DV=2E-7
1.005
ratio
ratio
1 DV=5E-7 DV=5E-7
1
0.995
DV=1E-6 DV=1E-6
0.99 0.95
0.985 DV=2E-6 DV=2E-6
0.98 DV=5E-6 0.9 DV=5E-6
0.8 0.9 1 1.1 1.2 DV=1E-5 0.8 0.9 1 1.1 1.2 DV=1E-5
Ground volumetric heat capacity ratio Ground thermal conductivity ratio
Figure 6.33 Sensitivity of ground volumetric heat Figure 6.34 Sensitivity of ground thermal
capacity on borehole performance at different conductivity on borehole performance at different
groundwater velocities in TRT groundwater velocities in TRT
Sensitivity of borehole thermal resistance on borehole Sensitivity of groundwater volumetric heat capacity on
performance at different groundwater velocity borehole performance at different groundwater velocity
Borehole fluid temperature rise
Borehole fluid temperature rise
1.2 1.07
1.15 DV=0 1.05 DV=0
1.1 DV=1E-7 DV=1E-7
1.03
1.05 DV=2E-7
DV=2E-7
ratio
ratio
1 1.01
DV=5E-7 DV=5E-7
0.95 0.99
DV=1E-6 DV=1E-6
0.9
0.97 DV=2E-6
0.85 DV=2E-6
0.8 DV=5E-6 0.95 DV=5E-6
0.8 0.9 1 1.1 1.2 0.8 0.9 1 1.1 1.2 DV=1E-5
DV=1E-5
Borehole thermal resistance ratio Groundwater volumetric heat capacity ratio
Figure 6.35 Sensitivity of borehole thermal Figure 6.36 Sensitivity of groundwater volumetric
resistance on borehole performance at different heat capacity on borehole performance at
groundwater velocities in TRT different groundwater velocities in TRT
92
For a parameter variation of 20% in the nominal parameter value, it could be
found that the ground volumetric heat capacity only changed the borehole
performance by less than 2%. The sensitivity was reduced as the groundwater
velocity increased, and became zero at high groundwater velocities. For the
groundwater volumetric heat capacity, the sensitivity was also low (less than 2%) for
groundwater velocity below 2x10-6m/s. A low sensitivity for a particular parameter
would result in a lower precision for the respective parameter value obtained by
applying appropriate parameter estimation techniques. Accordingly, the ground and
groundwater volumetric heat capacities would be specified instead of being
determined in the TRT analysis.
The role of groundwater was complicated, as its effect could be small in TRT
at low groundwater velocities as depicted in Figure 6.37 with Darcy velocities less
than 10-6m/s, but still had substantial influence on the long-term borehole
performance as already discussed in Section 6.1.3.1. Hence, a separate study needed
to be conducted first to investigate the behaviour of groundwater velocity in TRT
analysis before the final parameter estimation scheme could be set.
9
8 DV=0
7
DV=1E-7
Tout - To (K)
6
5 DV=2E-7
4 DV=5E-7
3
DV=1E-6
2
1 DV=2E-6
0 DV=5E-6
0 20 40 60 80 100 120 DV=1E-5
T ime (Hours)
6.2.2 Analysis Based on the Generated TRT Data with Specified Groundwater
Velocity
93
generated from the models were used. The advantage was that a very small MSD
(theoretically zero) could result if the estimated and specified parameters matched
with the ones used to generate the data. Three models were tried, namely the
LSMGA, FLSMGA and present numerical model. A borehole thermal resistance of
0.1253mK/W was used to generate the data. For LSMGA, a borehole loading of
30W/m was adopted. Initially, several optimisation methods had been applied,
namely the gradient search method, the genetic algorithm and the Nelder-Mead
simplex method. It was found that the simplex method gave the fastest convergence
and highest precision, and was thus adopted in all the subsequent analysis.
Table 6.10 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 5 days without groundwater
Table 6.10 showed the results using LSMGA based on generated TRT data
without groundwater flow for 5 days. At a specified groundwater velocity of 10-7m/s
or less, the estimated average MSD, k g and Rb were almost the same and very close
to the theoretical values of 3.5 for k g and 0.1253 for Rb . This agreed with the
94
velocity went beyond 2x10-7m/s, a more significant deviation of the analysis results
from the theoretical values was observed, and the MSD became much higher.
Table 6.11 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 5 days with groundwater velocity 2x10-7m/s
Table 6.11 indicated the analysis results based on the generated data
corresponding to a groundwater velocity of 2x10-7m/s. Again, the results were
almost the same as those for a specified groundwater velocity of 10-7m/s or less,
which were slightly differentiable from those at a specified groundwater velocity of
2x10-7m/s. It could be expected that if the actual groundwater velocity in the thermal
response test was very low (say 10-7m/s or less), a possible range of groundwater
velocity might be obtained from parameter estimation ranging from 0 to 10-7m/s.
However, at high groundwater velocities, the results seemed promising as shown in
Table 6.12. In other words, precise determination of low groundwater velocity from
the thermal response test was not possible, or there existed a confident minimum
for the groundwater velocity above which it was able to estimate its value from TRT
analysis with confidence. The significance of this confident minimum was
demonstrated in Section 6.2.3 where the groundwater velocity was also included in
the parameter estimation scheme. Analysis results for other specified groundwater
velocities were presented in Appendix K. Corresponding studies based on the
95
generated data using FLSMGA and the present numerical model followed the same
trends as those using LSMGA.
Table 6.12 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 5 days with groundwater velocity 10-6m/s
As mentioned in previous section, the analysis results were very close at low
groundwater velocities of less than 10-7m/s. To differentiate the thermal response
test performance at this low velocity range, a longer test period of 30 days was tried
with data generated using LSMGA as shown in Table 6.13&14 under groundwater
velocities of 2x10-8m/s and 5x10-8m/s. It could be observed that the MSDs were
almost the same for groundwater velocities 5x10-8m/s or less. This meant that it
should be able to predict the groundwater velocity with confidence when it was
greater than 5x10-8m/s with the test period extended to 30 days. The confident
minimum for the estimated groundwater velocity decreased with increase in the test
period. The significance of groundwater effect at this velocity range depended on
the scale of the borefield, which could still be substantial for a large borefield. In
other words, in designing a large borefield, it would be beneficial to perform the
TRT with a longer testing period. The corresponding results at other groundwater
96
velocities were shown in Appendix L. Again, the analysis using other models led to
similar findings.
Table 6.13 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 30 days with groundwater velocity 2x10-8m/s
Table 6.14 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 30 days with groundwater velocity 5x10-8m/s
97
6.2.3 Analysis Based on the Generated TRT Test Data Including Groundwater
Velocity in the Parameter Estimation Scheme
Tables 6.15~17 indicated the analysis results based on generated data using
LSMGA with groundwater velocities of 5x10-8, 10-7 and 2x10-7m/s respectively for a
test period of five days. From Tables 6.15&16, the estimated groundwater velocity
in the three trials scattered and deviated much from the theoretical values while the
estimated ground thermal conductivity and borehole thermal resistance converged to
the theoretical values. It should be noted that the sign was unimportant for single
borehole performance. This agreed with the findings in Section 6.2.2.1. In Table
6.17, the situation was quite different. The estimated groundwater velocity was
much closer to the theoretical value, and the confident minimum for the estimated
groundwater velocity under a normal test period of five days was 2x10-7m/s. Above
the confident minimum, the convergence of the estimated groundwater velocity was
even much better as shown in Appendix M. Analysis with other models reached
very similar results.
98
Table 6.16 Parameter (including groundwater velocity) estimation results using
LSMGA on generated data for 5 days with groundwater velocity 10-7m/s
Tables 6.18&19 showed the analysis results based on the generated data
using LSMGA with groundwater velocities of 5x10-8 and 10-7m/s for a test period of
30 days. It was evident that the estimated groundwater velocity converged much
more readily to the theoretical value at a groundwater velocity of 10-7m/s than that at
a groundwater velocity of 5x10-8m/s. This totally agreed with the analysis in Section
6.2.2.2 that for a longer test period, confident results could still be obtained even at
lower groundwater flow velocities. The confident minimum for the estimated
groundwater velocity was reduced to 10-7m/s at a long test period of 30 days.
Corresponding analysis results with other groundwater velocities were shown in
Appendix N, and the results using other models were basically the same at that using
LSMGA.
99
Table 6.18 Parameter (including groundwater velocity) estimation results using
LSMGA on generated data for 30 days with groundwater velocity 5x10-8m/s
with the same extent even at different groundwater velocities. For k g , a lower value
tended to yield less scattering in the estimated groundwater velocities. This was due
100
to the fact that a lower k g resulted in a higher ground temperature rise and
consequently a higher fluid temperature rise and the convective effect of the
groundwater became more substantial. Hence, the separation of the borehole
temperature rise profiles at different groundwater velocities would increase, meaning
that it would become easier to differentiate the groundwater effect, thus leading to a
reduction of the confident minimum of the estimated groundwater velocity.
Table 6.20 Estimated groundwater velocities using LSMGA based on generated data
with various ground thermal conductivities and borehole thermal resistances
6.2.3.4 Effects of Far Field Temperature and Borehole Load on the Estimated
Parameters
When conducting the TRT, the borefield load (Qb ) was provided by an
electric water heater and calculated from the logged temperature difference between
the borehole inlet and outlet. There might be a small fluctuation in Qb due to noise
in the supply power, temperature logger and change in heat transfer rate in the
101
electric heater due to the water temperature rise. Usually, an average value was used
in the analysis and error might be induced. The far field temperature (T0 ) was
normally estimated from the borehole temperature or the ground temperature
somewhere in the borefield within a period before the start of the test. The
appropriateness of the estimation method might also lead to a certain degree of error.
To investigate their effects on the estimated parameters, analysis was made using
LSMGA with Qb and T0 in the parameter estimation scheme assuming values
different from the default values of 30W/m for Qb and 20oC for T0 as adopted in the
generated data. The details were shown in Table 6.21&22 for groundwater velocities
of 5x10-7 and 10-6m/s respectively.
102
It could be observed that T0 had negligible effect on the estimated k g and Vgw.
The reason was that with different T0 , the borehole temperature rise profile would
only shift up and down without changing the shape of the curve. Hence, only Rb
would be affected which was similar to what was discussed in Section 6.2.3.3. Of
course, T0 was assumed to be constant throughout the test, which was appropriate in
actual TRT where a long borehole was used and the boundary ground temperature
was stable below certain depths. However, the situation could be different when
laboratory TRT was conducted where the boundary temperature might vary more
substantially. For Qb , the influence was more significant for k g and Rb . A 16%
the estimated Vgw varied only by not more than 7.1% which became smaller for a
lower groundwater velocity. As a 16% error in Qb was unlikely, the actual effect on
V would be very small.
Six formal tests were conducted with the applied conditions given in Table
6.23. As stated in Section 4.3, the groundwater flow was measured after each test,
and the groundwater velocity calculated accordingly. The loading was determined
by averaging the recorded values over the entire test period which was around 4 days
for each test. The far field temperature was estimated by averaging the logged
borehole temperature over one day before the start of each test.
103
Table 6.23 Applied conditions for different experimental TRTs
Table 6.24 showed the analysis results. Basically, the results varied with the
starting point of the analysed data, but they seemed to approach certain limits if more
of the starting data record was discarded except Test B where the estimated
groundwater velocity with analysis starting at Test Record 8 appeared to be off-track.
Nevertheless, the results of the analysis starting at Test Record 10, i.e. skipping the
earlier 9 hours of data, were taken as the representative ones. The estimated k g
ranged from 2.399 to 2.602 while Rb ranged from 0.2461 to 0.2826. The percentage
differences were less than 15% when compared with the lowest values, showing that
the method yielded similar results for k g and Rb at different groundwater flow
velocities. Table 6.25 compared the estimated groundwater velocities with the actual
values. The percentage errors were large except for Test C, and the error seemed
smaller with a higher applied load as indicated in the results of Tests A & B.
However, a higher applied load was not used at other groundwater flow since the
logged borehole temperature as shown in Appendix O in Test A slightly exceeded
the calibration range of the logger which was 20~40oC.
104
Table 6.24 Analysis results of experimental TRT data
105
curve was shown in Figure 6.38. Under steady state conditions, the temperature drop
across the sandwiched soil should be proportional to the heat flux passing through
the soil. By applying linear regression method, the calculated k g was 3.73W/mK.
35
30
Applied load (W)
25
20
15
10
5
0
1 1.5 2 2.5 3
Figure 6.38 Variation of applied load with temperature difference across soil in
laboratory soil thermal conductivity measurement test
In the laboratory TRT, large errors were found in the estimated groundwater
flow in most cases. The major reason was that the boundary temperature of the test
tank, as reflected by the circulating water temperature indicated in Appendix O,
106
could not be maintained constant over the test period. This was different from the
actual site TRT condition. Although efforts had been made, including applying
insulation to the test tank, providing an electric heater inside test room, and passing
the circulating water through the constant-temperature water bath inside the
temperature calibrator before entering the test tank, the result was still unsatisfactory.
This inevitably affected the estimated groundwater velocity. The solving of the
problem required the re-design and erection of a new experimental setup, which was
not feasible within the limited time schedule in the study.
Another cause of error came from the size of the test tank. The distance
travelled by the heat front as calculated from the numerical model was far longer
than the width of the test tank within the test period. Thus, the actual heat transfer
pattern was disturbed and different from the one simulated by the numerical model.
The difference was large at small groundwater flow as indicated by the high
percentage error of estimated groundwater flow for Test F, and reduced with an
increasing groundwater velocity. It might be contemplated if better results could be
obtained by testing with a much higher groundwater flow. However, the hydraulic
conductivity and depth of the soil limited the groundwater flow that could be
modelled, and it was found that 260 l/min was basically the maximum that could be
achieved.
Finally, it might actually need a much longer time to achieve steady state in each
107
measurement. Thus the assumption of attainment of steady state led to errors in the
recorded temperatures.
To verify the new parameter estimation scheme in actual TRT analysis, the
site TRT data provided by Pahud (2006) and Spitler (2006) were used. One set of
data from Pahud (2006) was provided from a test near Luzern, Switzerland at the
north borehole (Pahud 2001), while four sets of data from Spitler (2006) were
obtained from tests at two schools (two tests for each school), Campbell and Maxey,
in Lincoln, Nebraska, USA. Analysis would be based on the hourly recorded data.
Table 6.27 Parameter estimation results of TRT data at north borehole of Luzern
using different models
Table 6.27 summarised the analysis results of TRT data provided by Pahud
(2006) using various models of ground heat exchangers under different starting data
records. The estimated V varied from 1.58x10-9 to 1.11x10-7m/s. The testing period
was 5 days. According to Section 6.2.3.1, V should be more than 2x10-7m/s for
confident results. Hence, it could be deduced that the actual groundwater flow was
below this level. Indeed, Pahud (2001) stated that no groundwater flow was present
108
at that site, which agreed with the analysis results. The estimated k g varied mildly,
with an average value of 2.896W/mK, which was close to the value of 3W/mK
determined based on the LSM approach by Pahud (2001). According to Pahud
(2001), laboratory tests were conducted on soil samples collected at different depths
of the site, yielding an average value of 3.5W/mK. The estimated Rb changed very
little at different starting record data for LSMGA and the present numerical model,
but the trend with FLSMGA was completely different where Rb increased
substantially when more record data at beginning of test were skipped. If excluding
those using FLSMGA, the average estimated Rb was 0.0843mK/W which was not
far from the value of 0.088mK/W determined by Pahud (2001). Generally speaking,
the estimated results from the new parameter estimation scheme agreed with the
findings from Pahud (2001).
Tables 6.28&29 indicated the analysis results based on TRT data from Spitler
(2006) for Maxey School. The average estimated values of k g and V gw differed in
the two particular tests. For the test conducted on 18th September 1998, they were
1.915W/mK & 1.5x10-6m/s respectively, and the corresponding values for the test
conducted on 30th June 1999 were 2.29W/mK & 1.14x10-6m/s respectively. The
inhomogeneity in the ground might account for the difference in the estimated k g , as
the tests were conducted using separate boreholes at some distance apart. The
difference in the estimated V gw might reflect the change in the groundwater condition
at site, as the dates for the two tests differed by nearly 9 months. Again, the trend for
the estimated Rb was different with FLSMGA as compared with those from other
numerical models.
109
Table 6.28 Parameter estimation results of TRT data conducted on 18th September
1998 for Maxey School at Lincoln using different models
Table 6.29 Parameter estimation results of TRT data conducted on 30th June 1999
for Maxey School at Lincoln using different models
Table 6.30 Parameter estimation results of TRT data conducted on 15th September
1998 for Campbell School at Lincoln using different models
110
Average Starting record data to analyse
estimated
Model parameters 1 2 4 6 8 10
kg (W/mK) 2.004 2.045 2.140 2.164 2.178 2.149
LSMGA Rb (mK/W) 0.1338 0.1355 0.1388 0.1401 0.1408 0.1391
Vgw (10-9m/s) 89.9 76.9 23.5 8.80 3.43 4.61
kg (W/mK) 1.996 2.047 2.125 2.149 2.162 2.129
FLSMGA Rb (mK/W) 0.134 0.1584 0.1826 0.1996 0.2102 0.2173
Vgw (10-9m/s) 87.6 68.9 24.9 4.43 1.97 5.59
kg (W/mK) 1.973 2.033 2.101 2.135 2.146 2.115
Present Rb (mK/W) 0.1357 0.1379 0.1405 0.1419 0.1426 0.1408
Vgw (10-9m/s) 92.8 69.9 26.0 3.03 3.24 2.51
Table 6.31 Parameter estimation results of TRT data conducted on 8th October 1998
for Campbell School at Lincoln using different models
Tables 6.30&31 showed the corresponding results for Campbell School. The
estimated V gw in the two tests varied considerably from 9.86x10-9 to 9.55x10-7m/s.
In fact, the estimated V gw scattered very much in each trial. As the duration of each
test was only 50 hours, the actual groundwater flow, if any, was probably outside the
111
range for confident estimated result which was similar to the situation when using
Pahuds data. The average estimated k g for the two tests, i.e. 2.1 and 1.998W/mK,
differed only mildly. Neglecting results using FLSMGA, the average estimated
values of Rb at 0.139 and 0.11mK/W were substantially different for the two tests.
This might be due to the structural difference induced during the construction of the
boreholes including orientation of U-tube, workmanship of backfilling, etc. In
practice, the thermal resistance for each borehole in a borefield would not be exactly
the same.
Desiccant
heat Regenerative
Process Dehumidifier exchanger Regenerator air heat
air fan tower tower exchanger
Weak Strong
Tpa,di Tra,ri Trahi
desiccant desiccant
pump pump
TL,do TL,ro
Regenerative Trao
air heater
For a ground-coupled liquid desiccant air conditioner, the design concern was
the total enthalpy drop rather than just the dehumidification rate. Hence, the
selection of components for the liquid desiccant dehumidifying cycle might not be
exactly the same as that for a pure liquid desiccant dehumidifier. Figure 6.39
showed a schematic diagram of a more advanced liquid desiccant dehumidifier
which incorporated additional components including a desiccant cooler, regenerative
112
air heat exchanger and regenerative air heater as compared with the basic system as
shown in Figure 1.4. The effect of incorporating each additional component into the
basic system on the dehumidification rate and enthalpy drop of process air would be
investigated to decide if a particular component would be used. The parameters
values set in Table 5.2 were used in the analysis.
Table 6.32 summarised the change of dehumidification rate and process air
cooling capacity at different desiccant cooling loads. Clearly, the introduction of
desiccant cooling rendered both the dehumidification rate and the cooling capacity to
improve. Hence, desiccant cooler would be used.
113
which was not beneficial for an air conditioner. In view of this, regenerative air
heater was discarded.
Table 6.34 indicated the effect of regenerative air heat exchanger on the
dehumidification rate and process air cooling capacity of liquid desiccant
dehumidifier without regenerative air heating and under a constant desiccant cooling
load of 4kW. The trend was similar to that using a regenerative air heater. For the
114
same reason, regenerative air heat exchanger would also not be used in the liquid
desiccant air conditioner, and Trai became Tra , ri .
Desiccant Desiccant
cooler heater
TL,dci TL,dhi
Process Regenerative
Desiccant
air fan heat air fan
TL,di exchanger TL,ri
Tpa,do Tra,ro
Dehumidifier Regenerator
tower tower
Weak Strong
desiccant desiccant
Tpa,di Tra,ri
pump pump
TL,do TL,ro
Compressor
Expansion
valve
Comparison was made with a conventional air-cooled fresh air unit (ACFAU)
based on the weather data for 1986, as shown in Figures 6.41~43 in respect of the
results obtained from simulation carried out only when the outdoor temperature
exceeded 20oC. For ACFAU, the COP was lowest in the peak load season where the
outdoor temperature was high. On the other hand, HPCLDD tended to be more
energy efficient in the peak load season, which was beneficial in terms of the overall
energy input.
115
Outdoor temperature profile for 1986
Time (hour)
4
3.8
3.6
3.4
3.2
COP
3
2.8
2.6
2.4
2.2
2
1 731 1461 2191 2921 3651 4381 5111 5841 6571 7301 8031
Time (hour)
By comparing Figures 6.42 and 6.43, the COP of ACFAU was still higher
than that for HPCLDD in most cases. This was probably due to the effectiveness of
the liquid desiccant cycle. By using a smaller packing size of 0.015m for dp for both
the dehumidifier and regenerator towers, the heat and mass transfer rate was
enhanced, and the simulation result was shown in Figure 6.44. The performance was
improved and generally better than that for ACFAU throughout peak load period.
116
Performance HPCLDD with dp=0.02 for 1986
4
3.8
3.6
3.4
3.2
COP
3
2.8
2.6
2.4
2.2
2
1 731 1461 2191 2921 3651 4381 5111 5841 6571 7301 8031
Time (hour)
4
3.8
3.6
3.4
3.2
COP
3
2.8
2.6
2.4
2.2
2
1 731 1461 2191 2921 3651 4381 5111 5841 6571 7301 8031
Time (hour)
117
formulation of compressor performance provided by the manufacturer was used
instead, which would restrict the simulation of the vapour compression cycle at the
specified degree of superheat of 5.56oC at the compressor suction, and that only
thermostatic expansion valve could be used for the expansion device.
Initially, an approximate iterative method was used for the evaporator of the
ACFAU. However, it was found that under certain outdoor conditions, the
simulation time was very long as compared with the finite difference method. This
was probably due to the double iterations in the method, leading to higher chance of
oscillation in the simulated results. To ensure stable and fast dynamic system
simulation, the finite difference method would be used for the air cooler in the
subsequent analysis.
With the fresh air being handled by the liquid desiccant cycle, auxiliary
components were needed to treat the mixed air in order to meet the complete air
conditioning requirement. This could be achieved by coupling the liquid desiccant
system with a conventional geothermal heat pump system, as shown in Figure 6.45
which indicated cooling mode operation. Two selective valves were used to control
the refrigerant flow direction for normal or reverse operation of the system to provide
cooling or heating where necessary. Two 3-way bypass valves were added so that
the refrigerant would only pass the desiccant cooler/heater in the cooling mode,
allowing the dehumidifying cycle to have the best performance as mentioned in
previous section. The desiccant pumps and regenerative air fan were turned off
when no cooling was required, and the borefield circulating pump stopped when
there was no air conditioning demand for either cooling or heating. The supply air
fan was running within the entire operating schedule.
118
Trta Desiccant Desiccant
cooler heater
Dehumidifier Regenerator
tower Weak Strong tower
desiccant desiccant
Tpa,di Tra,ri
pump pump
Ground
TL,do TL,ro coupled coil
Selector
valve
Compressor
Selector
valve Expansion
valve
Tbf,f,out
Borefield
Tbf,f,in
Borefield circulating
pump
Before the design parameters for the GSHP & GCLDAC could be set, the
loading requirement had to be estimated first. Figures 6.46&47 showed the room
loading demand based on the weather data from 1986 to 1995. The latent load was
stable throughout the period, as occupants were the only source of latent load. The
room loading demand was used to determine the supply air condition which was
assumed to be saturated moist air neglecting reheat through the process air fan and
air duct corresponding to the design indoor condition of 24oC and 54%RH. The peak
sensible and latent loads were used for this purpose as only one supply air
temperature could meet exactly the required sensible to latent load ratio. The fresh
air requirement was calculated based on ASHRAE (2005). The loading requirement
for the unit was then evaluated by adding the room loading to the ventilation load
due to fresh air based on design outdoor condition of 31oC and 83%RH as shown in
Table 6.35.
119
Figure 6.46 Building load profile for Case 1
120
Table 6.35 Design requirement of GCLDAC/GSHP
Case 1 Case 2
Peak room sensible load (kW) 7.102 7.745
Peak room latent load (kW) 1.044 1.606
Supply air flow (m3/s) 0.53 0.575
Supply air temperature (oC) 13.13 12.63
Fresh air amount (m3/s) 0.035 0.070
Fresh air ratio 0.066 0.122
Unit design sensible load (kW) 7.612 9.045
Unit design latent load (kW) 2.307 4.222
Unit design total load (kW) 9.919 13.27
Case 1 Case 2
Overall heat transfer value of supply air coil, UAsa (kW/K) 1.5 1.9
Overall heat transfer value of ground coupled coil, UAgc 1.5 1.9
(kW/K)
Volume of refrigerant in supply air coil, VOLsa (m3) 0.006 0.008
3
Volume of refrigerant in ground coupled coil, VOLgc (m ) 0.006 0.008
Volume of refrigerant in liquid line, VOLll (m3) 0.0002 0.00025
Refrigerant charge, Mr (kg) 1.5 3.0
No. of discretisation segment for supply air coil, nsa 50 50
Borefield fluid mass flowrate, mbf (kg/s) 0.5 0.6
Compressor model used ZH30K4E ZH38K4E
121
Table 6.37 Parameters used for GCLDAC
Case 1 Case 2
Overall heat transfer value of desiccant cooler, UAL,dc (kW/K) 0.1 0.2
Overall heat transfer value of desiccant heater, UAL,dh (kW/K) 0.15 0.3
Overall heat transfer value of supply air coil in cooling mode, 1.3 1.7
UAsa,cool (kW/K)
Overall heat transfer value of supply air coil in heating mode, 1.5 1.9
UAsa,heat (kW/K)
Overall heat transfer value of ground coupled coil in cooling 1.3 1.7
mode, UAgc,cool (kW/K)
Overall heat transfer value of ground coupled coil in heating 1.5 1.9
mode, UAgc,heat (kW/K)
Volume of refrigerant in desiccant cooler, VOLdc (m3) 0.0005 0.0015
Volume of refrigerant in desiccant heater, VOLdh (m3) 0.0005 0.0015
3
Volume of refrigerant in supply air coil, VOLsa (m ) 0.0055 0.0065
Volume of refrigerant in ground coupled coil, VOLgc (m3) 0.0055 0.0065
Volume of refrigerant in liquid line, VOLll (m3) 0.0002 0.00025
No. of discretisation segment for supply air coil, nsa 50 50
Height of desiccant towers (m) 0.5 0.6
No. of discretisation segment for desiccant towers 50 50
Cross-sectional area of dehumidifier tower, Sdeh (m2) 0.0225 0.0625
Packing size of dehumidifier tower, dp,deh (m) 0.01 0.015
Cross-sectional area of regenerator tower, Sreg (m2) 0.0625 0.1225
Packing size for regenerator tower, dp,reg (m) 0.01 0.015
Regenerative air flow, V&ra (m3/s) 0.07 0.15
122
The next step involved the selection of the various coil, tower and refrigerant
properties. In order to allow the possibility of reverse cycle operation, the volume
and overall heat transfer values of the condenser and evaporator were chosen to be
the same. For GCLDAC under the cooling mode, the condenser was composed of
two coils, namely the ground-coupled coil and desiccant heater while the evaporator
consisted of the supply air coil and desiccant cooler. The overall heat transfer values
of coils reflected the mean temperature difference between the two fluids, and were
selected so as to compromise between energy efficiency and equipment cost. In this
analysis, the values were chosen so that the mean temperature difference would be
between 5 to 10oC. The parameters for the desiccant cycle were selected so that the
loading of the two systems would be similar under comparable coil properties and
with the same refrigerant charge. Tables 6.36&37 summarised the values of various
parameters to be used for GSHP and GCLDAC. A single borehole would be used in
order to be able to neglect the effect of groundwater direction as mentioned in
Section 6.1.6. To increase the capacity of the borehole, a double U-tube with the 1-
3,2-4 connection configuration as recommended by Zeng et al. (2003) was adopted
with other borehole parameters being the same as those indicated in Table 5.1 except
H, N, mf and QAC.
123
Table 6.38 Performance of GSHP/GLCDAC at design conditions for Case 1
GSHP GCLDAC
Supply air condition (DB/RH) (oC/%) 12.80/100 12.85/100
Borefield fluid entering temperature (oC) 35.87 35.26
Cooling capacity (kW) 10.07 9.98
Load transferred to borefield (kW) 12.10 10.88
COP 4.97 4.94
GSHP GCLDAC
Supply air condition (DB/RH) (oC/%) 12.61/100 12.61/100
Borefield fluid entering temperature (oC) 36.18 35.26
Cooling capacity (kW) 12.74 12.74
Load transferred to borefield (kW) 15.29 13.08
COP 5.11 5.15
124
Table 6.40 Simulation results of GSHP with borehole length 250m at no
groundwater flow for Case 1 within 1986~1995
31
29
27
25 Room
23 T bf,f,out
21
19
17
15
0 20000 40000 60000 80000
The first trial was made for Case 1 using GSHP with a borehole length of
250m for ten years from 1986 to 1995 at no groundwater flow, and the results were
shown in Table 6.40 and Figure 6.47. The total energy transferred after the first year
was smaller than the average value over the entire ten-year period, and heating was
required for each year with the demand being highest in the first year as reflected by
a lower borefield leaving fluid temperature. Based on the results from the first trial,
the borehole length would be chosen to have the maximum borefield fluid leaving
temperature maintained at around 31.67oC after ten years simulation in all ongoing
simulations.
125
Table 6.41 Simulation results of GCLDAC with borehole length 225m at no
groundwater flow for Case 1 within 1986~1995
31
29
27
Room
25
23 T bf,f,out
21
19
17
15
0 20000 40000 60000 80000
Table 6.41 and Figure 6.48 summarised the corresponding results for
GCLDAC with a borehole length of 225m upon repeated trials in order to maintain
the same maximum borefield fluid leaving temperature. The total cooling energy to
room was around 0.3% lower than that using GSHP after one year and ten years,
which could be considered to be the same, while the estimation based on design
conditions as mentioned in previous section indicated a reduction of less than 0.1%.
The potential saving in borehole length under the same capacity of both systems was
10%. The total energy transferred to borefield was 10.2% and 10.4% less than that
with GSHP after one year and ten years respectively. The total energy input to the
compressor was only 0.5% higher for GCLDAC which was comparable to around
0.6% difference in COP based on the design conditions as shown in Table 6.38. The
126
said difference was very small. Consequently, the new hybrid system was capable of
maintaining the energy efficiency of GSHP.
Table 6.42 summarised the simulation results for Case 2. The situation was
very similar to that for Case 1. The reduction in borehole length was 13.8% while
the total heat energy to borefield was 14.6% lower for GCLDAC. The total energy
input to compressor was 0.5% lower for GCLDAC, indicating that GCLDAC was
slightly more energy-efficient, which was in line with the higher COP for GCLDAC
at the design condition listed in Table 6.39.
127
Figure 6.49 depicted the performance of GSHP with ten year simulation for
Case 2. The profiles were similar to those for Case 1 as shown in Figures 6.47&48.
The room temperature profiles indicated that the units were suitably sized in both
cases in order to meet the design loadings. The heating period was short in each year
which was typical for sub-tropical area and appeared to be similar in both cases.
31
29
27
25 Room
23 T bf,f,out
21
19
17
15
0 20000 40000 60000 80000
required borehole lengths were shown in Figures 6.50&51. More detailed simulation
data were given in Appendix O. The average reduction in borehole length for
GCLDAC was 10.11% in Case 1 and 14.31% in Case 2 with very minor fluctuations
at different groundwater velocities. Clearly, the reduction in borehole length with
the new hybrid system increased with the fresh air ratio. It could be expected that up
to 20% saving in borehole length could be reached with a fresh air ratio of 0.15
which was common for applications with higher occupant density and/or indoor air
quality requirement like schools or hospitals. Most importantly, the energy
efficiency of GSHP could still be maintained, which meant that GCLDAC would be
a useful potential alternative system for installation in sub-tropical regions.
128
Comparison of required borelength between GSHP &
GCLDAC for Case 1
270
250
Bore length (m)
230
GSHP
210
GCLDAC
190
170
150
0 2 4 6 8 10 12
350
Bore length (m)
300
GSHP
250
GCLDAC
200
150
0 2 4 6 8 10 12
129
Chapter 7 : Conclusions and Recommendations
7.1 Conclusions
2. The simulation results based on the present model with no groundwater flow
showed little difference from those obtained by using analytical models for a
single borehole. However, the bigger difference in the ground temperature
rise at locations distant from the borehole resulted in a larger deviation in
performance for a large borefield between the present model and the
analytical models with superposition. The borefield thermal resistance also
showed similar discrepancies. As the analytical models assumed a constant
loading along the boreholes which might not reflect the actual situations, the
present numerical model should be used especially when designing for a large
borefield.
130
4. The effect of loading profiles with the same peak cooling load on the
borehole performance at different groundwater flow conditions was studied.
The borehole leaving fluid temperature rise was highest for a continuous
constant load. The provision of a daily operating schedule reduced the
temperature rise substantially. The introduction of a periodic load lowered
the temperature rise further, but to a much lesser extent. The inclusion of a
heating period had insignificant effects. The reduction in the leaving fluid
temperature rise was much smaller than the decrease in the total heat
injection to the ground for the cases corresponding to Load Profiles 1 to 4.
Indeed, the effect of loading profiles diminished with the groundwater
velocity. At high groundwater flow conditions with a groundwater velocity
greater than 10-5m/s, the leaving fluid temperature rise became independent
of the loading profiles. This reflected the importance of the peak cooling
load in determining the borehole performance. The reduction in the peak
cooling load, such as by adopting a hybrid system to share the cooling load in
the peak-load period, could significantly reduced the required borehole length
especially when the groundwater velocity was high.
131
thermal conductivity, borehole thermal resistance and groundwater velocity
simultaneously. The results obtained by using the generated test data based
on a small groundwater flow indicated that the estimated groundwater
velocity was scattered for repeated trials. This was due to the fact that the
borehole performance was very close at small groundwater velocities within
the normal thermal response test period. More confident results on the
estimated groundwater velocity could only be achieved for a groundwater
velocity higher than 2x10-7m/s. This indicated that a confident minimum
existed for the estimated groundwater velocity above which the groundwater
velocity could be determined with confidence in the TRT analysis. Moreover,
an extension of the test period could reduce this confident minimum. For a
test period of 30 days, the groundwater velocity could be estimated with
confidence down to a level of 10-7m/s.
7. Experimental thermal response tests were conducted, and the results analysed.
However, the estimated groundwater velocities deviated much from the test
values, with errors ranging from 10.54% to 160.01%. The uncontrollable
boundary temperature around the test rig was one of the major reasons for
this wide error range. The small size of the test tank also affected the
temperature profiles in the soil that should be obtained with the numerical
model having much larger grid boundaries. The estimated ground thermal
conductivities ranged from 2.391 to 2.602 W/mK, while the laboratory soil
thermal conductivity measurements yielded an upper limit of 3.731W/mK.
132
9. A new hybrid system, the ground-coupled liquid desiccant air conditioner
(GCLDAC), was designed where the fresh air was treated by the liquid
desiccant cycle in cooling mode, and the mixed air handled by a conventional
geothermal heat pump system. Only a single compressor was needed to
provide the necessary desiccant cooling/heating and air-conditioning load for
the supply air. A single-zone sample building was used to analyse the
dynamic performance of the new hybrid system. The room air conditioning
load profile was generated using the TRNSYS software package based on the
Hong Kong weather data from 1986 to 1995. Two cases were studied, the
first one with 10 occupants corresponding to a fresh air ratio 0.066 and the
second one with 20 occupants corresponding to a fresh air ratio 0.122. The
simulated results were compared with those using only the conventional
ground source heat pump (GSHP) system in terms of the required borehole
length and total energy input to the compressor at different groundwater flow
conditions.
10. With the new hybrid system, the borehole length was reduced by 10.11% on
average for Case 1, while a 14.31% saving was achieved for Case 2, as part
of condensing heat was transferred to the regenerative air stream of the liquid
desiccant loop. Hence, for a design requiring a higher fresh air ratio as in
Case 2, more beneficial results could be obtained. The total energy input to
the compressor was nearly the same for both systems, meaning that the new
hybrid system did not cause deterioration in the energy efficiency of the
conventional GSHP. The groundwater flow did not affect the borehole length
reduction significantly.
1. The present model assumes that the ground is homogeneous. In practice, the
soil may consist of several layers, each with its own physical properties. The
ground surface temperature also changes with time although the magnitude of
the annual fluctuation decreases rapidly with depth. To account for these
factors, modification of the present numerical scheme is required.
133
2. The groundwater may not always flow in the same direction if inhomogeneity
exists inside the ground. Indeed, the groundwater flow direction needs not
be horizontal, and that the difference in the groundwater temperature may
induce a buoyancy-driven flow in the vertical direction. A more precise
manipulation of the groundwater effect in the numerical model should be
made.
3. Piles are common for buildings in Hong Kong, and the embedding of the
ground heat exchangers into the piles can reduce the installation cost
substantially. To analyse the performance of energy piles, the present model
can be modified by considering the pipes as boreholes. However, the small
pipe size may result in convergence problem if the simulation time step is not
reduced. To compromise between stability and computation time, the present
methodology used to calculate the fully implicit scheme has to be modified.
134
Appendices
where Ruv can be evaluated from the formulae quoted from Hellstrom (1991) as
rb 2
Ruu =
1
ln + ln rb + R p (A.2)
2k b r 2 di 2
rpo b
buv
2 2
1 buv rb2 di 2
Ruv = ln + ln + (A.3)
2k b rb r2
b
r
b
kb k g
= (A.4)
kb + k g
buv is the centre-to-centre distance between tube u and v, and Rp is the thermal
resistance between the fluid and the grouting. Rp comprises the convective thermal
resistance between the fluid and the tube inner surface, and the conductive thermal
resistance through the tube wall, which can be calculated as
rpo
ln
r
Rp = +
pi 1
(A.5)
2k p 2hc , f rpi
where
kf
hc , f = 0.023 Re 0f.8 Pr f0.3 for cooling (A.6)
2rpi
kf
hc , f = 0.023 Re 0f.8 Pr f0.4 for heating (A.7)
2rpi
135
according to Dittus and Boelter (1930). To simplify the formulation, a mean value of
0.35 is used for the exponent of Prandtl number in the analysis. The same approach
was also adopted by Yavuzturk (1999). The fluid Reynolds and Prandtl numbers
are determined from Holman (1990) as
2m f
Re f = (A.8)
f rpi
cf f
Pr f = (A.9)
kf
[T fl ,u ]
Tb = Ruv [qt ,v ]
1
[
Ruv T fl ,v Tb = [qt ,u ]
]
1
By denoting Ruv = Ruv
[q ] = R [T ]
t ,u uv fl , v Tb (A.10)
Eq. (A.10) and Eq. (3.3) represent exactly the same thing. By comparing the
coefficients of T fl ,v (v u ) and Tb from the right hand sides of both equations,
1
Ruv =
for u v (A.11)
Ruv
1
Ruu = (A.12)
nt
R
v =1
uv
For the case with no fluid flow, Rp will contain only the thermal resistance from the
pipe wall. Hence,
rpo
ln
r
R p ,nf pi (A.13)
2k p
The derivation of Rnf ,uv is similar to Ruv except by replacing Rp with Rp,nf in Eq.
(A.2).
136
B. Algorithm for Calculating Condenser Coil Performance
Calculate initial estimation for cond , sat based on the following equation
mr h f g , cond
cond , sat = Minimum ,1 e NTU dh (B.1)
CL , dhi (Trs , cond TL , dhi )
, sat using the Eqs. (3.48&49).
Calculate initial guess for xcond
Calculate initial guess for TL ,dh 2 using Eq. (3.50), assuming TL ,dh1 = TL ,dhi .
, sh + xcond
If ( xcond , sat ) > 1 , no sub-cooling occurs
, sc = 0 and xcond
xcond , sat = 1 xcond
, sh
Else
, sc = 1 x cond
xcond , sh xcond
, sat .
If sub-cooling occurs,
Calculate new cond , sc based on Eqs. (3.52&53).
Else
137
set TL ,dh1 = TL ,dhi .
If no sub-cooling occurs,
If difference between TL ,dh1 and TL ,dhi is less than preset limit,
Proceed to step 4.
Else
, sh based on the difference between TL ,dh1 and
Revise xcond
TL ,dhi .
, sat .
Calculate new xcond
Go back to step 2.
Else
If difference between TL ,dh1 and TL ,dh1' is less than preset limit and
Proceed to step 4.
Else
, sh based on the difference between TL ,dh1 and
Revise xcond
TL ,dh1' .
h f ,cond .
Go back to step 2.
138
C. Determination of Mean Refrigerant Density along Saturated
Region in Counter-flow Condenser/Evaporator
UA
dT f = (Tr T f )dl
Cf
UA
By setting NTU = and re-arranging,
Cf
dT f
= NTUdl
Tr T f
T T f ,in
ln r = NTU l
T T
r f
T f = Tr (Tr T f ,in )e NTU l (C.1)
mr h f g
dT f = d (C.2)
Cf
where is the quality of the refrigerant. Combining Eqs. (C.1) and (C.2),
mr h f g
d = NTU (Tr T f ,in )e NTU l dl
Cf
139
(Tr T f ,in )C f
where = (C.4)
mr h f g
where f g = f g .
The mean refrigerant density can be determined by integrating Eq. (C.6) by dl from
0 to 1. Thus,
1
r = r dl
0
1
g f
= dl
0
f g e NTU L
1
l 1
= g f + ln( f g e NTU l )
NTU 0
1 1 f g e NTU
= g f + ln (C.8)
NTU f g
140
D. Algorithm for Calculating Evaporator Coil Performance
, sat = 1 .
Calculate hr , suc based on Eq. (3.63), assuming xevap
hr , suc hg , evap
, sh =
xevap (D.1)
hr , suc hr , ei
Continue to step 2.
Proceed to Step 4.
Else
141
, sh based on the difference between hr ,dc1 and hg , evap .
Revise xevap
Go back to step 2.
142
E. Algorithm for Calculating Air Cooler Performance Based on
Approximate Iterative Method
Calculate Tsa using algorithm E.1 based on dry conditions for the entire air
cooler.
If (Tsa > Tadp , aci ) , no condensation occurs
sa = a , dci .
Proceed to step 4.
Else
, wet from the following equation
Calculate initial estimation of x ac
Tsa + 10
xac , wet = 1 (E.1)
Tadp , aci + 10
Continue to step 2.
Calculate Tr ,ac1 using algorithm E.1 based on wet conditions for the wet
partial coil.
Calculate new Tadp ,dci using algorithm E.1 based on dry conditions for the dry
partial coil.
143
Step 3 - Check of convergence
If difference between new Tadp ,dci and true Tadp ,dci less than preset limit
Proceed to Step 4.
Else
Revise x ac , wet based on the difference between new Tadp ,dci and true
Tadp ,dci .
Go back to step 2.
144
F. Modified Numerical Integration Method Used for FLSM
From Eq. (2.33), the determination of the ground temperature rise requires
the evaluation of a definite integral. The integrand reaches a maximum when s z ,
and drops rapidly when s differs from z like a needle hill, as shown in Figure F.1.
The integration of such kind of function can lead to a wrong result if non-uniform
step is used as is found when trying to determine Eq. (2.25) without specifying a
fixed integration step and the integration starts at the lower integration limit. A small
integration step ensures accuracy but at the expense of long computation time.
Hence, a compromise must be found.
Integrand of Eq. (2.33)
s'
0 d z H
Figure F.1 Variation of integrand of Eq. (2.33) with s
145
G. Modified Numerical Integration Method Used for LSMGA
16 a
2 2
= g
2
( x V ' ) 2 + y 2
4 a g V ' 2 2 + 4ag ( x 2 + y 2 )
= e = t t' (G.1)
4a g 3
1 R12 1 R12
16 1 R12 16
2e
2 2e 1 R12
16 16 1 R2 1
= =e
3 1 2 (G.2)
4 2 2 32 2
The value of * and * where and reach the maximum can be found by setting
Eqs. (G.1&2) to zero. Hence,
V '2 *2 + 4a g * ( x 2 + y 2 ) = 0
2a g + 4a g2 + V ' 2 ( x 2 + y 2 )
=
*
for V' 0 (G.3)
V '2
R12 *2 + 16 * 16 = 0
8(1 + 1 + R12 / 4 )
=
*
for R1 0 (G.4)
R12
The minimum integration time step and lower integration limit for Eq. (2.35) are
both set to 1, and those for Eq. (2.37) being 0.00001. The integration time step
multiplier is 1.01 for both equations.
146
H. Borehole Thermal Interference Based on FLSMGA
The temperature rise due to an instantaneous finite line source with insulated depth d
and effective length H below ground level is given by integrating Eq. (H.1) by ds '
from d to H. To maintain no temperature change at ground level, a negative strength
mirror finite line source is to be added above the ground level. The overall
temperature rise due to an instantaneous moving finite line source becomes
d + H [( x V t ) + y ' + ( z s ) ] [( z V t ) + y + ( z + s ) ]
' ' 2 2 ' 2 ' ' 2 2 ' 2
d +H
qb dt ' '
8 g cg (a g t ' )3 / 2 d d
4ag t '
inst , flsmga =
4ag t '
e dz e dz
be rewritten as
[( x V ' t ' ) 2 + y 2 ]
qb dt ' 4ag t ' zd erf z d H
inst , flsmga = e erf 4a t '
8k g t ' 4ag t
'
g
z+d +H + erf z + d
erf (H.3)
4a g t '
'
4a g t
The temperature rise due to a continuous moving finite line source of constant load
qb at time t is then given as
{[ x V ' ( t t ' )] 2 + y 2 }
4 a g (t t ' )
zd erf z d H
t
q e
flsmga = b erf
8k g 0 t t' ' 4a (t t ' )
4a g (t t ) g
147
z+d +H z+d dt '
erf + erf
(H.4)
4a g (t t ' )
4 a (t t '
)
g
z+d +H
erf + erf z + d d (H.5)
4ag 4ag
d +H
4 a g zd
qb te
erf erf z d H
8k g H d 0
flsmga ,inf =
4ag 4ag
z+d +H z + d
erf + erf d dz
4a g
(H.6)
4a g
or in terms of g function as
[( x1 V ) + y12 ]
' 2
1 d + H t e
4 a g zd
erf erf z d H
4 H d 0
g flsmga ,inf =
4ag 4ag
z+d +H
erf + erf z + d d dz (H.7)
4a g 4a g
Eqs. (H.6&7) require the evaluation of a double integral, which is very time
consuming. To simplify, a weighted average is used as
[( x1 V ) + y12 ]
' 2
nz bore 1
t e 4 a g z d
qb
erf i erf zi d H
flsmga ,inf =
8k g H
4ag 4a g
i =1 0
148
z +d +H
erf i + erf zi + d d dz (H.8)
4a g 4a g i
[( x1 V ) + y12 ]
' 2
nz bore 1
t e 4 a g z d
1
erf i erf zi d H
flsmga ,inf =
4H
4ag 4ag
i =1 0
z +d +H
erf i + erf zi + d d dz (H.9)
4a g 4a g i
where z i are the mid-depths of vertical segments discretised in the same way as the
present numerical model. The trends of the integrands are similar to that for Eq.
(2.35). Unfortunately, an explicit expression for * cannot be made. Thus, the
integration will start at the lower integration limit (set as 10) with fixed time step (set
as 1) until the integrand starts to decrease. Then a multiplier of 1.01 for the
integration time step will be used for all subsequent integration steps.
149
I. Calibration Curves for Measuring Instruments Used in Laboratory
Tests
40
38
Set temperature (degC)
36
34
32
30
28
26
24
22
20
21 26 31 36 41
30
Set temperature (degC)
28
26
24
22
20
19 21 23 25 27 29 31
150
Calculation curves for thermocouples
T _heater T _ambient
50
40
35
30
28 33 38 43 48
50
Power analyser reading (V)
45
40
35
30
25
20
15
10
5
0 10 20 30 40 50 60
0.5
Power analyser reading (A)
0.45
0.4
0.35
0.3
0.25
0.2
0.15
0.1
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4 0.45
151
J. Detailed Performance Curves at Different Groundwater Directions
and Load Profiles for Various Borefields
Tbf,f,out - To (K)
Tbf,f,out - To (K)
16.5 14.4
1 year 1 year
16 14.2
2 years 2 years
15.5 14
5 years 5 years
15 13.8
14.5 10 years 13.6 10 years
14 13.4
13.5 13.2
13 13
0 10 20 30 40 50 0 10 20 30 40 50
Figure J.1 Performance of 2x2 borefield with Figure J.2 Performance of 2x2 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 1 groundwater directions under load profile 1
10.7 7.5
1 year DV=1E-6
10.6 7
2 years DV=2E-6
10.5 6.5
5 years DV=5E-6
10.4 6
10.3 10 years DV=1E-5
5.5
10.2 5
10.1 4.5
10 4
0 10 20 30 40 50 0 10 20 30 40 50
Figure J.3 Performance of 2x2 borefield with Figure J.4 Performance of 2x2 borefield with high
groundwater velocity 5x10-7m/s at different groundwater velocity after 2 years at different
groundwater directions under load profile 1 groundwater directions under load profile 1
Tbf,f,out - To (K)
9.2
1 year 1 year
10 9.1
2 years 2 years
9
5 years 5 years
9.5 8.9
10 years 8.8 10 years
9 8.7
8.6
8.5 8.5
0 10 20 30 40 50 0 10 20 30 40 50
Figure J.5 Performance of 2x2 borefield with Figure J.6 Performance of 2x2 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 2 groundwater directions under load profile 2
152
Leaving fluid temperature rise Leaving fluid temperature rise
at DV=5E-7 after two years
8 7
7.9
6.5
7.8
Tbf,f,out - To (K)
Tbf,f,out - To (K)
7.7
1 year 6 DV=1E-6
7.6
2 years DV=2E-6
7.5 5.5
5 years DV=5E-6
7.4
7.3 10 years 5 DV=1E-5
7.2
4.5
7.1
7 4
0 10 20 30 40 50 0 10 20 30 40 50
Figure J.7 Performance of 2x2 borefield with Figure J.8 Performance of 2x2 borefield with high
groundwater velocity 5x10-7m/s at different groundwater velocity after 2 years at different
groundwater directions under load profile 2 groundwater directions under load profile 2
Tbf,f,out - To (K)
Tbf,f,out - To (K)
8.4 7.85
1 year 1 year
8.2 7.8
2 years 2 years
8 7.75
5 years 5 years
7.8 7.7
7.6 10 years 7.65 10 years
7.4 7.6
7.2 7.55
7 7.5
0 10 20 30 40 50 0 10 20 30 40 50
Figure J.9 Performance of 2x2 borefield with Figure J.10 Performance of 2x2 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 3 groundwater directions under load profile 3
7.35 6
1 year DV=1E-6
7.3
2 years DV=2E-6
7.25 5.5
5 years DV=5E-6
7.2
10 years 5 DV=1E-5
7.15
7.1
4.5
7.05
7 4
0 10 20 30 40 50 0 10 20 30 40 50
Figure J.11 Performance of 2x2 borefield with Figure J.12 Performance of 2x2 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at
groundwater directions under load profile 3 different groundwater directions under load
profile 3
153
Leaving fluid temperature rise Leaving fluid temperature rise
at DV=1E-7 at DV=2E-7
8.4 8
7.9
8.2
7.8
Tbf,f,out - To (K)
Tbf,f,out - To (K)
8 7.7
1 year 1 year
7.8 7.6
2 years 2 years
7.5
7.6 5 years 5 years
7.4
10 years 10 years
7.4 7.3
7.2
7.2
7.1
7 7
0 10 20 30 40 50 0 10 20 30 40 50
Groundwater direction (deg) Groundwater direction (deg)
Figure J.13 Performance of 2x2 borefield with Figure J.14 Performance of 2x2 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 4 groundwater directions under load profile 4
Tbf,f,out - To (K)
7.2
1 year 6 DV=1E-6
7.1
2 years DV=2E-6
7 5.5
5 years DV=5E-6
6.9
6.8 10 years 5 DV=1E-5
6.7
4.5
6.6
6.5 4
0 10 20 30 40 50 0 10 20 30 40 50
Groundwater direction (deg) Groundwater direction (deg)
Figure J.15 Performance of 2x2 borefield with Figure J.16 Performance of 2x2 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at different
groundwater directions under load profile 4 groundwater directions under load profile 4
Tbf,f,out - To (K)
22 1 year 1 year
17.5
21 2 years 2 years
17
20 5 years 5 years
19 16.5
10 years 10 years
18 16
17 15.5
16 15
0 10 20 30 40 50 0 10 20 30 40 50
Groundwater direction (deg) Groundwater direction (deg)
Figure J.17 Performance of 3x3 borefield with Figure J.18 Performance of 3x3 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 1 groundwater directions under load profile 1
154
Leaving fluid temperature rise Leaving fluid temperature rise
at DV=5E-7 after two years
13 10
12.9
12.8 9
Tbf,f,out - To (K)
Tbf,f,out - To (K)
12.7
1 year 8 DV=1E-6
12.6
2 years DV=2E-6
12.5 7
5 years DV=5E-6
12.4
12.3 10 years 6 DV=1E-5
12.2
5
12.1
12 4
0 10 20 30 40 50 0 10 20 30 40 50
Figure J.19 Performance of 3x3 borefield with Figure J.20 Performance of 3x3 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at
groundwater directions under load profile 1 different groundwater directions under load
profile 1
Figure J.21 Performance of 3x3 borefield with Figure J.22 Performance of 3x3 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 2 groundwater directions under load profile 2
8.35
1 year DV=1E-6
8.3 6.5
2 years DV=2E-6
8.25 6
5 years DV=5E-6
8.2 5.5
8.15 10 years DV=1E-5
5
8.1
8.05 4.5
8 4
0 10 20 30 40 50 0 10 20 30 40 50
Figure J.23 Performance of 3x3 borefield with Figure J.24 Performance of 3x3 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at
groundwater directions under load profile 2 different groundwater directions under load
profile 2
155
Leaving fluid temperature rise Leaving fluid temperature rise
at DV=1E-7 at DV=2E-7
10.5 9
8.9
10 8.8
Tbf,f,out - To (K)
Tbf,f,out - To (K)
8.7
1 year 1 year
9.5 8.6
2 years 2 years
8.5
5 years 5 years
9 8.4
10 years 10 years
8.3
8.5 8.2
8.1
8 8
0 10 20 30 40 50 0 10 20 30 40 50
Figure J.25 Performance of 3x3 borefield with Figure J.26 Performance of 3x3 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 3 groundwater directions under load profile 3
Tbf,f,out - To (K)
7.7
1 year 6 DV=1E-6
7.6
2 years DV=2E-6
7.5 5.5
5 years DV=5E-6
7.4
10 years 5 DV=1E-5
7.3
7.2
4.5
7.1
7 4
0 10 20 30 40 50 0 10 20 30 40 50
Figure J.27 Performance of 3x3 borefield with Figure J.28 Performance of 3x3 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at
groundwater directions under load profile 3 different groundwater directions under load
profile 3
Tbf,f,out - To (K)
8.9 8.2
1 year 1 year
8.7 8.1
2 years 2 years
8.5 8
5 years 5 years
8.3 7.9
10 years 10 years
8.1 7.8
7.9 7.7
7.7 7.6
7.5 7.5
0 10 20 30 40 50 0 10 20 30 40 50
Groundwater direction (deg) Groundwater direction (deg)
Figure J.29 Performance of 3x3 borefield with Figure J.30 Performance of 3x3 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 4 groundwater directions under load profile 4
156
Leaving fluid temperature rise Leaving fluid temperature rise
at DV=5E-7 after two years
7.6 7
7.5 6.5
Tbf,f,out - To (K)
Tbf,f,out - To (K)
7.4 1 year 6 DV=1E-6
2 years DV=2E-6
7.3 5.5
5 years DV=5E-6
7.2 10 years 5 DV=1E-5
7.1 4.5
7 4
0 10 20 30 40 50 0 10 20 30 40 50
Figure J.31 Performance of 3x3 borefield with Figure J.32 Performance of 3x3 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at
groundwater directions under load profile 4 different groundwater directions under load
profile 4
13.5 12
Tbf,f,out - To (K)
Tbf,fout - To (K)
11.5 11.2
11 11
0 20 40 60 80 100 0 20 40 60 80 100
Figure J.33 Performance of 1x2 borefield with Figure J.34 Performance of 1x2 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 1 groundwater directions under load profile 1
Figure J.35 Performance of 1x2 borefield with Figure J.36 Performance of 1x2 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at
groundwater directions under load profile 1 different groundwater directions under load
profile 1
157
Leaving fluid temperature rise Leaving fluid temperature rise
at DV=1E-7 at DV=2E-7
9 8.5
8.9 8.4
8.8 8.3
Tbf,f,out - To (K)
Tbf,f,out - To (K)
8.7 8.2
1 year 1 year
8.6 8.1
2 years 2 years
8.5 8
5 years 5 years
8.4 7.9
8.3 10 years 7.8 10 years
8.2 7.7
8.1 7.6
8 7.5
0 20 40 60 80 100 0 20 40 60 80 100
Figure J.37 Performance of 1x2 borefield with Figure J.38 Performance of 1x2 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 2 groundwater directions under load profile 2
Tbf,f,out - To (K)
7.2
1 year 6 DV=1E-6
7.1
2 years DV=2E-6
7 5.5
5 years DV=5E-6
6.9
6.8 10 years 5 DV=1E-5
6.7
4.5
6.6
6.5 4
0 20 40 60 80 100 0 20 40 60 80 100
Groundwater direction (deg) Groundwater direction (deg)
Figure J.39 Performance of 1x2 borefield with Figure J.40 Performance of 1x2 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at
groundwater directions under load profile 2 different groundwater directions under load
profile 2
Tbf,f,out - To (K)
7.7 7.35
1 year 1 year
7.6 7.3
2 years 2 years
7.5 7.25
5 years 5 years
7.4 7.2
7.3 10 years 10 years
7.15
7.2 7.1
7.1 7.05
7 7
0 20 40 60 80 100 0 20 40 60 80 100
Groundwater direction (deg) Groundwater direction (deg)
Figure J.41 Performance of 1x2 borefield with Figure J.42 Performance of 1x2 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 3 groundwater directions under load profile 3
158
Leaving fluid temperature rise Leaving fluid temperature rise
at DV=5E-7 after two years
7 7
6.95
6.9 6.5
Tbf,f,out - To (K)
Tbf,f,out - To (K)
6.85
1 year 6 DV=1E-6
6.8
2 years DV=2E-6
6.75 5.5
5 years DV=5E-6
6.7
6.65 10 years 5 DV=1E-5
6.6
4.5
6.55
6.5 4
0 20 40 60 80 100 0 20 40 60 80 100
Groundwater direction (deg) Groundwater direction (deg)
Figure J.43 Performance of 1x2 borefield with Figure J.44 Performance of 1x2 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at different
groundwater directions under load profile 3 groundwater directions under load profile 3
7.5 7.25
Tbf,f,out - To (K)
Tbf,f,out - To (K)
7.4 1 year 7.2 1 year
2 years 2 years
7.3 7.15
5 years 5 years
7.2 10 years 7.1 10 years
7.1 7.05
7 7
0 20 40 60 80 100 0 20 40 60 80 100
Groundwater direction (deg) Groundwater direction (deg)
Figure J.45 Performance of 1x2 borefield with Figure J.46 Performance of 1x2 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 4 groundwater directions under load profile 4
Tbf,f,out - To (K)
6.85
1 year 6 DV=1E-6
6.8
2 years DV=2E-6
6.75 5.5
5 years DV=5E-6
6.7
6.65 10 years 5 DV=1E-5
6.6
4.5
6.55
6.5 4
0 20 40 60 80 100 0 20 40 60 80 100
Groundwater direction (deg) Groundwater direction (deg)
Figure J.47 Performance of 1x2 borefield with Figure J.48 Performance of 1x2 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at
groundwater directions under load profile 4 different groundwater directions under load
profile 4
159
Leaving fluid temperature rise Leaving fluid temperature rise
at DV=1E-7 at DV=2E-7
16 14
15.5
13.5
15
Tbf,f,out - To (K)
Tbf,f,out - To (K)
1 year 13 1 year
14.5
2 years 2 years
14 12.5
5 years 5 years
13.5
10 years 12 10 years
13
11.5
12.5
12 11
0 20 40 60 80 100 0 20 40 60 80 100
Figure J.49 Performance of 1x3 borefield with Figure J.50 Performance of 1x3 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 1 groundwater directions under load profile 1
Tbf,f,out - To (K)
10.4
1 year 8 DV=1E-6
10.2
2 years DV=2E-6
10 7
5 years DV=5E-6
9.8
9.6 10 years 6 DV=1E-5
9.4
5
9.2
9 4
0 20 40 60 80 100 0 20 40 60 80 100
Groundwater direction (deg) Groundwater direction (deg)
Figure J.51 Performance of 1x3 borefield with Figure J.52 Performance of 1x3 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at different
groundwater directions under load profile 1 groundwater directions under load profile 1
9.4 8.7
1 year 1 year
9.2 8.6
2 years 2 years
9 8.5
5 years 5 years
8.8 8.4
10 years 8.3 10 years
8.6
8.4 8.2
8.2 8.1
8 8
0 20 40 60 80 100 0 20 40 60 80 100
Figure J.53 Performance of 1x3 borefield with Figure J.54 Performance of 1x3 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 2 groundwater directions under load profile 2
160
Leaving fluid temperature rise Leaving fluid temperature rise
at DV=5E-7 after two years
7.6 7
7.5
7.4 6.5
Tbf,f,out - To (K)
Tbf,f,out - To (K)
7.3
1 year 6 DV=1E-6
7.2
2 years DV=2E-6
7.1 5.5
5 years DV=5E-6
7
6.9 10 years 5 DV=1E-5
6.8
4.5
6.7
6.6 4
0 20 40 60 80 100 0 20 40 60 80 100
Groundwater direction (deg) Groundwater direction (deg)
Figure J.55 Performance of 1x3 borefield with Figure J.56 Performance of 1x3 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at
groundwater directions under load profile 2 different groundwater directions under load
profile 2
Figure J.57 Performance of 1x3 borefield with Figure J.58 Performance of 1x3 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 3 groundwater directions under load profile 3
7.1 6.5
Tbf,f,out - To (K)
Tbf,f,out - To (K)
7 1 year 6 DV=1E-6
2 years DV=2E-6
6.9 5.5
5 years DV=5E-6
6.8 10 years 5 DV=1E-5
6.7 4.5
6.6 4
0 20 40 60 80 100 0 20 40 60 80 100
Figure J.59 Performance of 1x3 borefield with Figure J.60 Performance of 1x3 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at
groundwater directions under load profile 3 different groundwater directions under load
profile 3
161
Leaving fluid temperature rise Leaving fluid temperature rise
at DV=1E-7 at DV=2E-7
7.8 7.4
7.7
7.35
7.6
Tbf,f,out - To (K)
Tbf,f,out - To (K)
1 year 7.3 1 year
7.5
2 years 2 years
7.4 7.25
5 years 5 years
7.3
10 years 7.2 10 years
7.2
7.1 7.15
7 7.1
0 20 40 60 80 100 0 20 40 60 80 100
Groundwater direction (deg) Groundwater direction (deg)
Figure J.61 Performance of 1x3 borefield with Figure J.62 Performance of 1x3 borefield with
groundwater velocity 10-7m/s at different groundwater velocity 2x10-7m/s at different
groundwater directions under load profile 4 groundwater directions under load profile 4
Tbf,f,out - To (K)
6.95
1 year 6 DV=1E-6
6.9
2 years DV=2E-6
6.85 5.5
5 years DV=5E-6
6.8
10 years 5 DV=1E-5
6.75
6.7
4.5
6.65
6.6 4
0 20 40 60 80 100 0 20 40 60 80 100
Groundwater direction (deg) Groundwater direction (deg)
Figure J.63 Performance of 1x3 borefield with Figure J.64 Performance of 1x3 borefield with
groundwater velocity 5x10-7m/s at different high groundwater velocity after 2 years at
groundwater directions under load profile 4 different groundwater directions under load
profile 4
162
K. Parameter Estimation Results with Specified Groundwater Flow
Using LSMGA on Generated TRT Data for 5 Days at Different
Groundwater Velocities
Table K.1 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 5 days with groundwater velocity 10-8m/s
Table K.2 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 5 days with groundwater velocity 2x10-8m/s
163
Table K.3 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 5 days with groundwater velocity 5x10-8m/s
Table K.4 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 5 days with groundwater velocity 10-7m/s
164
Table K.5 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 5 days with groundwater velocity 5x10-7m/s
165
L. Parameter Estimation Results with Specified Groundwater Flow
Using LSMGA on Generated TRT Data for 30 Days at Different
Groundwater Velocities
Table L.1 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 30 days without groundwater flow
Table L.2 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 30 days with groundwater velocity 10-8m/s
166
Table L.3 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 30 days with groundwater velocity 10-7m/s
Table L.4 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 30 days with groundwater velocity 2x10-7m/s
167
Table L.5 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 30 days with groundwater velocity 5x10-7m/s
Table L.6 Parameter estimation results with specified groundwater flow using
LSMGA on generated TRT data for 30 days with groundwater velocity 10-6m/s
168
M. Parameter (Including Groundwater Velocity) Estimation Results
Using LSMGA on Generated TRT Data Using LSMGA for 5
Days at Different Groundwater Velocities
169
Table M.4 Parameter (including groundwater velocity) estimation results using
LSMGA on generated TRT data for 5 days with groundwater velocity 5x10-7m/s
170
N. Parameter (Including Groundwater Velocity) Estimation Results
Using LSMGA on Generated TRT Data Using LSMGA for 30
Days at Different Groundwater Velocities
171
Table N.4 Parameter (including groundwater velocity) estimation results using
LSMGA on generated TRT data for 30 days with groundwater velocity 2x10-7m/s
172
O. Logged Temperature Profiles in Experimental Thermal Response
Tests
45
Temperature (degC)
40
35
30
25
20
0 20 40 60 80 1 00
40
Temperature (degC)
35
30
25
20
0 20 40 60 80 1 00
40
Temperature (degC)
35
30
25
20
0 20 40 60 80 1 00
173
Temperature profiles in Test D
Borehole Room Circulating water
40
Temperature (degC)
35
30
25
20
0 20 40 60 80 1 00
45
Temperature (degC)
40
35
30
25
20
0 20 40 60 80 1 00
40
Temperature (degC)
35
30
25
20
0 20 40 60 80 1 00
174
P. Dynamic Simulation Results of GCLDAC/GSHP with
Groundwater Flow
175
Table P.4 Simulation results of GSHP/GCLDAC with Darcy velocity 10-7m/s of
groundwater flow for Case 2
176
References
Arundel, A.V., E.M. Sterling, J.H. Biggin and T.D. Sterling (1992). Indirect health
effects of relative humidity in indoor environments, Desiccant Cooling and
Dehumidification, Atlanta: AHSRAE, 3-12.
177
Bejan, A. (1993). Heat Transfer, Wiley.
Bennet, J., J. Claesson and G. Hellstrom (1987). Multipole method to compute the
conductive heat flows to and between pipes in a composite cylinder, Notes on
Heat Transfer 3-1987, Department of Building Physics and Mathematical
Physics, Lund Institute of Technology, Lund, Sweden.
Bernier, M.A. (2000). A review of the cylindrical heat source method for the design
and analysis of vertical ground-coupled heat pump systems, Fourth
International Conference on Heat Pumps in Cold climates, Aylmer, Quebec.
Bernier, M.A., P. Pinel, R. Labib and R. Paillot (2004). A multiple load aggregation
algorithm for annual hourly simulations of GCHP systems, HVAC&R
Research, 10(4), 471-487.
Bose, J.E., J.D. Parker and F.C. McQuiston (1985). Design/Data Manual for Closed-
Loop Ground-Coupled Heat Pump Systems, Altanta, ASHRAE.
Bose, J.E., M.D. Smith and J.D. Spitler (2002). Advances in ground source heat
pump systems - an international overview, Proceedings of the Seventh
International Energy Agency Heat Pump Conference, Beijing, 313-324.
178
Cane, R.L.D., and D.A. Forgas (1991). Modeling of ground source heat pump
performance, ASHRAE Transactions, 97(1), 909-925.
Carslaw, H.S., and J.C. Jaeger (1959). Conduction of Heat in Solids, Oxford:
Claremore Press.
Cecchini, C., and D. Marchal (1991). A simulation model of refrigerant and air-
conditioning equipment based on experimental data, ASHRAE Transactions,
97(2), 388-393.
Chiasson, A.D., S.J. Rees and J.D. Spitler (2000). A preliminary assessment of the
effects of groundwater flow on closed-loop ground-source heat pump systems,
ASHRAE Transactions, 106(1), 380-393.
Chung, T.W., T.K. Ghosh and A.L. Hines (1996). Comparison between random and
structured packings for dehumidification of air by lithium chloride solutions
in a packed column and their heat and mass transfer correlations, Industrial
and Engineering Chemistry Research, 35(1), 192-198.
Claesson, J., and G. Hellstrom (1987). Thermal Resistances to and between Pipes in
a Composite Cylinder, Department of Mathematical Physics and Building
Technology, University of Lund, Lund, Sweden.
Claesson, J., and G. Hellstrom (2000). Analytical studies of the influence of regional
groundwater flow on the performance of borehole heat exchangers,
Proceedings of the 8th international Conference on Thermal Energy Storage,
Terrastock 2000, Stuttgart, Germany, 195-200.
179
Cooper, L.Y. (1976). Heating of a cylindrical cavity; International Journal of Heat
and Mass Transfer, 19(7), 575-577.
Deerman, J.D., and S.P. Kavanaugh (1991). Simulation of vertical U-tube ground
coupled heat pump systems using the cylindrical heat source solution,
ASHRAE Transactions, 97(1), 287-295.
Diao, N., Q. Li and Z. Fang (2004). Heat transfer in ground heat exchangers with
groundwater advection, International Journal of Thermal Sciences, 43(12),
1203-1211.
Diao, N.R., H.Y. Zeng and Z.H. Fang (2004). Improvement in modeling of heat
transfer in vertical ground heat exchangers, HVAC&R Research, 10(4), 459-
470.
Dittus, F.W., and L.M.K. Boelter (1930). University of California (Berkeley) Pub.
Eng., 2, 443.
Dobson, M.K., D.L. O'Neal and W. Aldred (1995). A modified analytical method for
simulating cyclic operation of vertical U-tube ground-coupled heat pumps,
Proceedings of the 1995 ASME/JSME/JSES International Solar Energy
Conference, 1, 69-76.
Domanski, P., and D. Didion (1984). Mathematical model of an air-to-air heat pump
equipped with a capillary tube, International Journal of Refrigeration, 7(4),
249-255.
Eklof, C., and S. Gehlin (1996). TED - a mobile equipment for thermal response test,
Masters Thesis, Lulea University of Technology, Sweden.
180
Elsarrag, E., E.E.M. Magzoub and S. Jain (2004). Mass-transfer correlations for
dehumidification of air by triethylene glycol in a structured packed column,
Industrial and Engineering Chemistry Research, 43(23), 7676-7681.
Eskilson, P., and J. Claesson (1988). Simulation model for thermally interacting heat
extraction boreholes, Numerical Heat Transfer, 13, 149-165.
Fromentin, A., D. Pahud and G. Sarlos (1998). Heating and cooling systems with
heat exchanger piles, Proceedings of the International Conference on Energy
and Environment, ICEE, 230-234.
Fujii, H., R. Itoi, and T. Ishikami (2004a). Improvements on analytical modeling for
vertical U-tube ground heat exchangers, Geothermal Resources Council
Transactions, 28, August 29 September 1, 73-77.
Fujii, H., R. Itoi, J. Fujii, Y. Uchida and T. Ishikami (2004b). Numerical simulation
of large-scale GCHP systems in the presence of groundwater flow,
Geothermal Resources Council Transaction, 28, August 29 September 1,
79-84.
181
Fumo, N., and D.Y. Goswami (2002). Study of an aqueous lithium chloride desiccant
system: air dehumidification and desiccant regeneration, Solar Energy, 72(4),
351-361.
Gandhidasan, P., C.F. Kettleborough and M.R. Ullah (1986). Calculation of heat and
mass transfer coefficients in a packed tower operating with a desiccant-air
contact system, Transactions of the ASME Journal of Solar Energy
Engineering, 108, 123-128.
Gasparella, A., G.A. Longo and R. Marra (2005). Combination of ground source
heat pumps with chemical dehumidification of air, Applied Thermal
Engineering, 25(2-3), 295-308.
Gehlin, S.E.A., and G. Hellstrom (2003a). Comparison of four models for thermal
response test evaluation, ASHRAE Transactions, 109(1), 131-142.
Georgiev, A., A. Busso and P. Roth (2006). Shallow borehole heat exchange:
Response test and charging-discharging test with solar collectors, Renewable
Energy, 31(7), 971-985.
Ghaddar, N., K. Ghali and A. Najm (2003). Performance of solar-assisted hybrid air-
conditioning liquid desiccant system in Beirut, Proceedings of Energy and
the Environment 2003, Halkidiki, Greece, 241-251.
Goulburn, J.R., and J. Fearon (1983). Domestic heat pump with deep hole ground
source evaporator, Applied Energy, 14(2), 99-113.
182
Griffiths, W.C. (1992). Use of liquid sorption dehumidification to improve energy
utilisation of air systems, Desiccant Cooling and Dehumidification, Atlanta:
AHSRAE, 33-39.
Gu, Y., and D.L. O'Neal (1995). An analytical solution to transient heat conduction
in a composite region with a cylindrical heat source, Transactions of the
ASME Journal of Solar Energy Engineering, 117, 242-248.
Gu, Y., and D.L. O'Neal (1998a). Development of an equivalent diameter expression
for vertical U-tubes used in ground-coupled heat pumps, ASHRAE
Transactions, 104(2), 347-355.
Gu, Y., and D.L. O'Neal (1998b). Modeling the effect of backfills on U-tube ground
coil performance, ASHRAE Transactions, 104(2), 356-365.
Hart, D.P., and R. Couvillion (1986). Earth Coupled Heat Transfer, Prepared for the
National Water Well Association, Dublin.
He, M.M. (2007). Analysis of Underground Thermal Energy Storage Systems with
Ground Water Advection in Subtropical Regions, Master Thesis, Department
of Mechanical Engineering, University of Hong Kong.
Hellstrom, G. (1989). Duct Ground Heat Storage Model, Manual for Computer Code,
Department of Mechanical Physics, University of Lund, Sweden.
183
Hellstrom, G., L. Mazzarella and D. Pahud (1996). Duct Ground Heat Storage
Model, Lund DST TRNSYS13.1 Version January 1996, Department of
Mathematical Physics, University of Lund, Sweden.
Hellstrom, G., and B. Sanner (2000). Earth Energy Designer, User Manual, Version
2.0.
Hepbasli, A., and O. Akdemir (2004). Energy and exergy analysis of a ground source
(geothermal) heat pump system, Energy Conversion and Management, 45(5),
737-753.
Ingersoll, L.R., O.J. Zobel and A.C. Ingersoll (1954). Heat Conduction: with
Engineering, Geological and Other Applications, Madison: University of
Wisconsin Press.
Jin, H., and J.D. Spitler (2002). A parameter estimation based model of water-to-
water heat pumps for use in energy calculation programs, ASHRAE
Transactions, 108(1), 3-17.
Jung, D., C. Park and B. Park (1999). Capillary tube selection for HCFC22
alternatives, International Journal of Refrigeration, 22(7), 604-614.
184
Kavanaugh, S.P. (1992). Simulation of ground-coupled heat pumps with an
analytical solution, ASME-JSES-KSES International Solar Energy
Conference, 395-400.
Kavanaugh, S.P. (1995). A design method for commercial ground-coupled heat
pumps, ASHRAE Transactions, 101(2), 1088-1094.
Kavanaugh, S.P. (1998). A design method for hybrid ground-source heat pumps,
ASHRAE Transactions, 104(2), 691-698.
Khan, A.Y., and H.D. Ball (1992). Development of a generalised model for
performance evaluation of packed-type liquid sorbent dehumidifiers and
regenerators, ASHRAE Transactions, 98(1), 525-533.
Kasuda, T., and P.R. Archenbach (1965). Earth temperature and thermal diffusivity
at selected stations in the United States, ASHRAE Transactions, 71(1), 61-75.
Kyriakis, N., A. Michopoulos and K. Pattas (2006). On the maximum thermal load of
ground heat exchangers; Energy and Buildings, 38(1), 25-29.
Laloui, L., M. Nuth and L. Vulliet (2006). Experimental and numerical investigations
of the behaviour of a heat exchanger pile, International Journal for
Numerical and Analytical Methods in Geomechanics, 30(8), 763-781.
Lam, H.N., and H.M. Wong (2005). Geothermal heat pump system for air
conditioning in Hong Kong, Proceedings of World Geothermal Congress
2005, Antalya, Turkey, article no. 1475.
185
Lau, K.F., and M.T. Suen (2003). Geothermal heat pump air-conditioning system for
the Hong Kong International Wetland Park, Proceedings of Shandong-Hong
Kong Joint Symposium 2003, A1-A9.
Lamarche, L., and B. Beauchamp (2007). A new contribution to the finite line-source
model for geothermal boreholes, Energy and Buildings, 39(2), 188-198.
Lazzarin, R.M., and F. Castellotti (2007). A new heat pump desiccant dehumidifier
for supermarket application, Energy and Buildings, 39(1), 59-65.
Li, X., J. Zhao and Q. Zhou (2005). Inner heat source model with heat and moisture
transfer in soil around the underground heat exchanger, Applied Thermal
Enginering, 25(10), 1565-1577.
Li, X., Z. Chen and J. Zhao (2006). Simulation and experiment on the thermal
performance of U-vertical ground coupled heat exchanger, Applied Thermal
Engineering, 26(14-15), 1564-1571.
Liu, X.H., K.Y. Qu and Y. Jiang (2006). Empirical correlations to predict the
performance of the dehumidifier using liquid desiccant in heat and mass
transfer, Renewable Energy, 31(10), 1627-1639.
Lund, J.W. (2003). Direct-use of geothermal energy in the USA, Applied Energy,
74(1-2), 33-42.
Mago, P.J., L. Chamra and G. Steele (2006). A simulation model for the performance
of a hybrid liquid desiccant system during cooling and dehumidification,
International Journal of Energy Research, 30(1), 51-66.
186
Martin, V., and D.Y. Goswami (2000). Effectiveness of heat and mass transfer
processes in a packed bed liquid desiccant dehumidifier/regenerator,
HVAC&R Research, 6(1), 21-39.
Mei, V.C. (1988). Heat pump ground coil analysis with thermal interference,
Transactions of the ASME Journal of Solar Energy Engineering, 110, 69-73.
Mei, V.C. (1991). Heat transfer of buried pipe for heat pump application,
Transactions of the ASME Journal of Solar Energy Engineering, 113, 51-55.
Mogensen, P. (1983). Fluid to duct wall heat transfer in duct system heat storages,
Proceedings of the International Conference on Subsurface Heat Storage in
Theory and Practice, Stockholm, Sweden, 652-657.
Morino, K., and T. Oka (1994). Study on heat exchanged in soil by circulating water
in a steel pile, Energy and Buildings, 21(1), 65-78.
Moujaes, S.F. (1990). Cyclic simulation of a model describing heat transfer from a
ground-coupled water source heat pump, considering transient effects on both
soil and water sides, International Journal of Refrigeration, 13(5), 330-335.
Muraya, N.K., D.L. O'Neal and W.M. Heffington (1996). Thermal interference of
adjacent legs in a vertical U-tube heat exchanger for a ground-coupled heat
pump, ASHRAE Transactions, 102(2), 12-21.
Nelder, J.A., and R. Mead (1965). A simplex method for function minimization,
Computer Journal, 7(1), 308-313.
Niibori, Y., Y. Iwata, S. Ichinose and G. Fukaya (2005). Design of the BHP system
considering the heat transport of groundwater flow, Proceedings of World
Geothermal Congress 2005, Antalya, Turkey, article no. 1422.
187
Ozgener, O., and A. Hepbasli (2006). An economical analysis on a solar greenhouse
integrated solar assisted geothermal heat pump system, Journal of Energy
Resources Technology, Transactions of the ASME, 128(1), 28-34.
Pahud, D., A. Fromentin and J.C. Hadorn (1996). The Duct Ground Heat Storage
Model (DST) for TRNSYS Used for the Simulation of Heat Exchanger Piles.
User Manual, December 1996 Version, Internal Report, Laboratory of
Energy Systems (LASEN), Swiss Federal Institute of Technology (EPFL),
Lausanne, Switzerland.
Pahud, D., and G. Hellstrom (1996). The new duct ground heat model for TRNSYS,
Proceedings of Eurotherm Seminar No49, Eindhoven, The Netherlands, 27-
136.
Pahud, D., A. Formentin and M. Hubbuch (1999). Heat Exchanger Pile System of the
Dock Midfield at the Zurich Airport - Detailed Simulation and Optimization
of the Installation, Final report, Swiss Federal Office of Energy, Switzerland.
Pahud, D., and B. Mathey (2001). Comparison of the thermal performance of double
U-pipe borehole heat exchangers measured in situ, Energy and Buildings,
33(5), 503-507.
188
Patek, J., and J. Klomfar (2006). A computationally effective formulation of the
thermodynamic properties of LiBr-H2O solutions from 273 to 500K over full
composition range, International Journal of Refrigeration, 29(4), 556-578.
Petit, P.J., and J.P. Meyer (1998). Economic potential of vertical ground-source heat
pumps compared to air-source air conditioners in South Africa, Energy, 23(2),
137-143.
Ren, C., Y. Jiang and Y. Zhang (2006). Simplified analysis of coupled heat and mass
transfer processes in packed bed liquid desiccant-air contact system, Solar
Energy, 80(1), 121-131.
Rottmayer, S.P., W.A Beckman and J.W. Mitchell (1997). Simulation of a single
vertical U-tube ground heat exchanger in an infinite medium, ASHRAE
Transactions, 103(2), 651-659.
Sachs, H.M. (2002). Geology and Drilling Methods for Ground-Source Heat Pump
System Installations: An Introduction for Engineers, Atlanta: ASHRAE.
Smith, M.D., R.L. Perry and W.A. Holloway (1999). Development of a system for
verification of transient in-situ testing models and development of a testing
standard, Research Update Report for the Department of Energy, Oklahoma
State University, Division of Engineering Technology.
189
Shonder, J.A., and J.V. Beck (1999). Determining effective soil formation thermal
properties from field data using a parameter estimation technique, ASHRAE
Transactions, 105(1), 458-466.
Sliwa, T., and J. Kotyza (2003). Application of existing wells as ground heat source
for heat pumps in Poland, Applied Energy, 74(1-2), 3-8.
Sliwa, T., and A. Gonet (2005). Theoretical model of borehole heat exchanger,
Transactions of the ASME Journal of Energy Resources Technology, 127(2),
142-148.
Spiegel, M.R., and J. Liu (1999). Mathematical Handbook of Formulas and Tables,
New York: McGraw-Hill.
Spitler, J.D. (2000). GLHEPRO - A design tool for commercial building ground loop
heat exchangers, Proceedings of the Fourth International Heat Pumps in
Cold Climates Conference, Aylmer, Quebec.
Spitler, J.D., S.J. Rees and C. Yavuzturk (2000b). Recent developments in ground
source heat pump system design, modeling and application, Proceedings of
CIBSE/ASHRAE joint conference "20 20 Vision", Dublin, Session 9a, paper
A28.
Spitler, J.D. (2005). Ground-source heat pump system research-past, present and
future, HVAC&R Research, 11(2), 165-167.
190
Spitler, J.D. (2006). Private communication.
Stoecker, W.F., and J.W. Jones. (1982). Refrigeration and Air-Conditioning, New
York: McGraw-Hill.
Sutton, M.G., R.J. Couvillion, D.W. Nutter and R.K. Davis (2002). An algorithm for
approximating the performance of vertical bore heat exchangers installed in a
stratified geological regime, ASHRAE Transactions, 108(2), 177-184.
Thornton, J.W., T.P. McDowell and P.J. Hughes (1997a). Comparison of practical
vertical ground heat exchanger sizing methods to a Fort Polk data/model
benchmark, ASHRAE Transactions, 103(2), 675-683.
Thornton, J.W., T.P. McDowell, J.A. Shonder, P.J. Hughes, D. Pahud and G.A. J
Hellstrom (1997b). Residential vertical geothermal heat pump system
models: Calibration to data, ASHRAE Transactions, 103(2), 660-674.
Treybal, R.E. (1969). Adiabatic gas absorption and stripping in packed towers,
Industrial and Engineering Chemistry, 61(7), 36-41.
191
Wagner R., and C. Clauser (2005). Evaluating thermal response tests using
parameter estimation for thermal conductivity and thermal capacity, Journal
of Geophysics and Engineering, 2(4), 349-356.
Young, T.R. (2004). Development, Verification, and Design Analysis of the Borehole
Fluid Thermal Mass Model for Approximating Short Term Borehole Thermal
Response, Master Thesis, Oklahoma State University.
Yuan, Y.J., and V. Alberce (2004). Gas heat and mass transfer method based on
self-microcirculation of caloric infinitesimal liquid, China Patent
PRC200410015955.
Zeng, H.Y., N.R. Diao and Z.H. Fang (2002). A finite line-source model for
boreholes in geothermal heat exchangers, Heat Transfer - Asian Research,
31(7), 558-567.
Zeng, H., N. Diao and Z. Fang (2003). Heat transfer analysis of boreholes in vertical
ground heat exchangers, International Journal of Heat and Mass Transfer,
46(23), 4467-4481.
192