Doc No: RAPID-P0003-HXCC-CVS-JHA-0001-0007

JOB HAZARDS ANALYSIS


Rev. A

Date: 16/02/2017
JOB HAZARDS ANALYSIS FOR SURVEY WORKS

CLIENT PETRONAS-RAPID IPMT CONTRACT NO. 0226025010


PROJECT TITLE RAPID PACKAGE 3 PROJECT NO. 00260

ASSESSORS NAME DESIGNATION DATE SIGNATURE


Tang Jin Construction Manager
Li Bin Construction Supervisor

NAME DATE SIGNATURE


Liu Yang
Prepared by
Civil Engineer, HXCC
Sundramohan
Checked by
HSSE Manager, HXCC
Diego G. Bucchi
Verified by
Construction Manager, TR
Dileep Prabakaran
Verified by
Deputy HSSE Manager, TR
Jerry Gumbang
Review by
HSE Lead, PMC
Mark Reynolds
Approved by
HSE Manager, PMC
Section 1
SUBCONTRACTO
ACTIVITY SURVEY WORKS ZHONGHE HUAXING DEVEMLOPMENT (M) SDN BHD
R
ASSESSMENT DETAILS
Assessed By Position Page Number Page 2 of 3
Tang Jin Construction Manager Assessment No.
Li Bin Construction Supervisor Assessment Date
Risk Assessment Rev. A
Section 1
RISK ACTION/
RISK RISK
RATING RISK RESPONSIBLE
ACTIVITY RISKS CONTROL MEASURE RATING (RR) CATEGORY
(RR) CATEGORY PERSON(S)
S L RR S L RR

Hand pinch 2 D D2 MEDIUM - Wear hand gloves 2 C C2 LOW

- Ensure the equipment are in good condition


Setting up for survey
1 Survey equipment fall 2 D D2 MEDIUM - Follow safe manual handling 2 C C2 LOW
equipment
- Wear appropriate PPE
Li Bin
(Site Supervisor, HXCC)

Eye injury 3 C C3 MEDIUM - Wear safety glass 2 C C2 LOW Lu Xinquan


(Site Supervisor, HXCC)

Fall from different level - Working behind the excavation barricade Zhou Bin
(working on excavation 3 D D3 HIGH - Wear additional PPE (Full Body Harness) if the 2 C C2 LOW (Site Supervisor, HXCC)
trench) excavation trench more than 1.5 meter
Hu Hai Liang
(Site Supervisor, HXCC)
Soil collapse - Ensure the trench are in good sloping
Searching marking point (working in the 3 D D3 HIGH - Trench must be cover with the plastic sheet 2 C C2 LOW Liu Yiping
2 near to excavation excavation) - Wear appropriate PPE (Site Supervisor, HXCC)
trench

- Provide cool water in the workplace and


encourage worker to drink.
Heat stress 3 C C3 MEDIUM - Implement a buddy system where workers 2 C C2 LOW
observe each other for signs of heat
intolerance.

Notes: S=Severity of injury L=Likelihood of Occurrence Risk Rating score(RR)=S * L


Section 1
SUBCONTRACTO
ACTIVITY SURVEY WORKS ZHONGHE HUAXING DEVEMLOPMENT (M) SDN BHD
R
ASSESSMENT DETAILS
Assessed By Position Page Number Page 3 of 3
Tang Jin Construction Manager Assessment No.
Li Bin Construction Supervisor Assessment Date
Risk Assessment Rev. A
Section 1
RISK ACTION/
RISK RISK
RATING RISK RESPONSIBLE
ACTIVITY RISKS CONTROL MEASURE RATING (RR) CATEGORY
(RR) CATEGORY PERSON(S)
S L RR S L RR

3 Marking point Hand Injury 3 C C3 MEDIUM -

Notes: S=Severity of injury L=Likelihood of Occurrence Risk Rating score(RR)=S * L