End Area End Area Distance Vol of Vol.

of Strip cut Strip Fill


Stations Cut (sf) Fill (sf) (L) Cut (bcy) Fill (ccy) (bcy) (ccy)
1 2 3 4 5 6 7
0+00 1,583.0 - - - - - -
0+15 1,335.0 0 15 811 0 0 0
0+30 1,128.7 0 15 684 0 0 0
0+45 1,232.0 0 15 656 0 0 0
0+60 795.7 0 15 563 0 0 0
0+75 742.5 0 15 427 0 0 0
0+95 493.5 0 20 458 0 0 0

Mass Diagram
Total Cut Total Fill Adj. Sum Mass
(bcy) (ccy) Fill(bcy) (bcy) Ordinate
8 9 10 11 12 Total Exavation Volume: (s
- - - - - Cross haul/dozer work within Project: (
811 0 0 811 811
684 0 0 684 1495
656 0 0 656 2151
563 0 0 563 2714
427 0 0 427 3141
458 0 0 458 3599

m
Exavation Volume: (sum 8) 3599 cft
work within Project: (11-8) 0 cft