Penawaran Harga Hydrant Ciawi Dan Lembur Situ
Penawaran Harga Hydrant Ciawi Dan Lembur Situ
I PEKERJAAN PERSIAPAN
1. Survey dan Pengukuran ls 1 875,000 - 875,000 875,000
2. Mobilisasi dan Demobilisasi ls 1 3,750,000 - 3,750,000 3,750,000
II INSTALASI HYDRANT
1. Pekerjaan Galian Tanah
- Galian Tanah m3 13.5 24,000 - 324,000 324,000
- Lapisan Pasir t.10 cm m3 1.8 210,000 25,000 378,000 45,000 423,000
- Urugan Tanah Kembali dan Pemadatan m3 11.7 17,000 - 198,900 198,900
2. Pekerjaan Pemipaan
- Pipa d.4" SCH 40 (Welded Joint) m' 36 339,744 125,000 12,230,769 4,500,000 16,730,769
- Long Elbow d.4" (welded) bh 2 225,000 95,000 450,000 190,000 640,000
- Short Elbow (Welded) bh 1 185,000 55,000 185,000 55,000 240,000
- Flange d.4" (Welded) bh 4 125,000 75,000 500,000 300,000 800,000
- Stut Bolt 16x80mm set 16 26,500 12,500 424,000 200,000 624,000
- Gasket bh 2 17,500 12,500 35,000 25,000 60,000
- Pengecatan Pipa m' 36 24,000 17,500 864,000 630,000 1,494,000
I PEKERJAAN PERSIAPAN
1. Survey dan Pengukuran ls 1 875,000 - 875,000 875,000
2. Mobilisasi dan Demobilisasi ls 1 3,750,000 - 3,750,000 3,750,000
II INSTALASI HYDRANT
1. Pekerjaan Galian Tanah
- Galian Tanah m3 4.875 24,000 - 117,000 117,000
- Lapisan Pasir t.10 cm m3 0.65 210,000 25,000 136,500 16,250 152,750
- Urugan Tanah Kembali dan Pemadatan m3 4.225 17,000 - 71,825 71,825
2. Pekerjaan Pemipaan
- Pipa d.4" SCH 40 (Welded Joint) m' 13 339,744 125,000 4,416,667 1,625,000 6,041,667
- Long Elbow d.4" (welded) bh 2 225,000 95,000 450,000 190,000 640,000
- Short Elbow (Welded) bh 1 185,000 55,000 185,000 55,000 240,000
- Flange d.4" (Welded) bh 4 125,000 75,000 500,000 300,000 800,000
- Stut Bolt 16x80mm set 16 26,500 12,500 424,000 200,000 624,000
- Gasket bh 2 17,500 12,500 35,000 25,000 60,000
- Pengecatan Pipa m' 13 24,000 17,500 312,000 227,500 539,500