DIMENSIONS
S.NO DESCRIPTION OF WORK NO L B D QUANTITIES UNITS RATE PER AMOUNT
Excavation for foundation including cost and
conveyance of materials is to site and all labour
1 4 1 1 1.5 6 cu.m 500 Rs/cu.m 3000
charge for digging, laying &etc.. complete
complying with standard specifications.
Sand filling done with fine river sand without dirts
including cost and conveyance of sand to site and
all labour charge for laying complete complying
with standard specifications.
2
column 4 1 1 0.6 2.4
flooring 1 8 2.5 0.3 6
pavement 1 22.5 4.8 0.1 10.8
deduct 1 8 2.5 0.1 2
total 18 cu.m 1000 Rs/cu.m 18000
Cement concrete 1:4:8 mix using 40mmsize hard
broken granite stone jelly including cost and
conveyance of materials is to site and all labour
charge for mixing, laying & curing etc.. complete
3 complying with standard specifications.
PCC 1:2:4 the concrete base of 100mm thick is to 1 22.5 4.8 - 108
be laid using 20 mm down graded hard broken 1 8 2.5 - 20
blue granite stone jelly. Floor finishingof 25 mm
Total 88 sqm 160 Rs/sqm 14080
thick is to be laid while the base concrete is wet
for proper bond, the bottom 15 mm thick consists
of one part ofcementandone part of 6 mm
downgraded hard broken blue granite stone chips
(the proportion being by volume) and the top
10mm finish with hardening compound of
12 proportion one part of hardonite (ironite or
equivalent) 4 parts of cement and 8 parts of 6mm
downgraded hard broken blue granite stone chips
(the proportion being by weight). Rate to include
cost of 100mm thick base PCC 1:2:4 and top finish
PCC 1:2:4 the concrete base of 100mm thick is to
be laid using 20 mm down graded hard broken
blue granite stone jelly. Floor finishingof 25 mm
thick is to be laid while the base concrete is wet
for proper bond, the bottom 15 mm thick consists
of one part ofcementandone part of 6 mm
downgraded hard broken blue granite stone chips
(the proportion being by volume) and the top
10mm finish with hardening compound of
12 proportion one part of hardonite (ironite or
equivalent) 4 parts of cement and 8 parts of 6mm
downgraded hard broken blue granite stone chips
(the proportion being by weight). Rate to include
cost of 100mm thick base PCC 1:2:4 and top finish
of 25 mm thick granolithic flooring including cost
of materials, form work, finishing labour, cruring
etc. complete as per standard specifications
plain Cement concrete hard broken granite stone 1 22.5 4.8 0.08 8.64
jelly including cost and conveyance of materials is 1 8 2.5 0.08 1.6
13 to site and all labour charge for mixing, laying &
curing etc.. complete complying with standard Total 8 cu.m 3900 Rs/cu.m 31200
specifications.
providing urinals Vitreous Chinaware urinal stall
of 11p type as specified in the material schedule.
5 litre capacity C.I automatic flushing cistern
withallaccessories. 32mm Chromium plated brass
waste coupling. 12 mm dia C.P. brass, flush pipe.
14 7 - - - - - 1000 Rs/no 7000
Suitable supporting arrangement using Rawl plugs
with C.P. brass screws used for fixing the urinal
.All other necessary work for satisfactory working.
AMOUNT Rs 454605