Anda di halaman 1dari 18

CRONOGRAMA VALORIZADO DE OBRA

PROYECTO: MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL DE LOS PSJES: INCA GARCILAZO, JOSE SANTOS CHOCANO, LA GLOBALIZACION, LAS CALLES: LUIS PARDO, PEDRO PABLO PALACIOS Y DEL JR. LAUNION: LADO NORTE Y ULTIMA CUADRA EN SHANCAYAN - INDEPENDENCIA HUARAZ - ANCASH
LUGAR: SHANCAYAN - INDEPENDENCIA - HUARAZ - ANCASH
TIEMPO: 210 DIAS CALENDARIOS

Item Descripcin Und. Metrado Precio S/. Parcial S/. Mes 1 Mes 2 Mes 3 Mes 4 Mes 5

01 CONSTRUCCIONES PROVISIONALES 11,773.97


01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60mx2.40m und 1.00 608.36 608.36 S/. 608.36
01.02 ALMACEN, OFICINA Y GUARDIANIA mes 7.00 381.36 2,669.52 S/. 2,669.52
01.03 CERCO DE PROTECCION DE MALLA DE YUTE m 848.76 10.01 8,496.09 S/. 8,496.09
02 INSTALACION PROVISIONALES 2,654.84
02.01 AGUA PARA LA CONSTRUCCION GLB 1.00 677.97 677.97 S/. 96.85 S/. 96.85 S/. 96.85 S/. 96.85 S/. 96.85
02.02 CONSTRUCCION DE SERVICIO HIGIENICO GLB 1.00 1,129.41 1,129.41 S/. 1,129.41
02.03 ENERGIA ELECTRICA PROVISIONAL GLB 1.00 847.46 847.46 S/. 121.07 S/. 121.07 S/. 121.07 S/. 121.07 S/. 121.07
03 TRABAJOS PRELIMINARES 1,965.90
03.01 DEMOLICION MANUAL DE VEREDAS m2 26.84 21.55 578.40 S/. 578.40
03.02 DEMOLICION DE PAVIMENTO RIGIDO m2 27.14 23.90 648.65 S/. 648.65
03.03 ELIMINACIN DE MATERIAL EXCED C/ MAQUINARIA DE DESMONTES m3 11.36 20.28 230.38 S/. 230.38
03.04 MOVILIZACION DE EQUIPOS Y/O HERRAMIENTAS A OBRA GLB 1.00 508.47 508.47 S/. 508.47
04 SEGURIDAD Y SALUD 27,863.09
04.01 ELABORACION,IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO GLB 1.00 2,118.64 2,118.64 S/. 2,118.64
04.02 EQUIPOS DE PROTECCION INDIVIDUAL und 1.00 10,940.41 10,940.41 S/. 10,940.41
04.03 EQUIPOS DE PROTECCION COLECTIVA GLB 1.00 1,016.95 1,016.95 S/. 1,016.95
04.04 SEALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 2,838.00 2,838.00 S/. 2,838.00
04.05 CAPACITACION EN SEGURIDAD Y SALUD GLB 1.00 10,381.28 10,381.28 S/. 1,730.21 S/. 1,730.21 S/. 1,730.21 S/. 1,730.21 S/. 1,730.21
04.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO GLB 1.00 567.81 567.81 S/. 567.81
05 GRADERIAS 186,554.15
05.01 OBRAS PRELIMINARES 3,104.63
05.01.01 TRAZO NIVELACION Y REPLANTEO m2 727.08 1.90 1,381.45 S/. 1,381.45
05.01.02 CONTROL TOPOGRAFICO DURANTE LA EJECUCION m2 727.08 2.37 1,723.18 S/. 275.71 S/. 712.25 S/. 689.27 S/. 45.95
05.02 MOVIMIENTO DE TIERRAS 81,502.38
05.02.01 CORTE DE TERRENO MANUAL m3 688.22 41.36 28,464.78 S/. 22,771.82 S/. 5,692.96
05.02.02 PERFILADO Y COMPACTADO DE SUBRASANTE MANUAL m2 727.08 5.09 3,700.84 S/. 1,057.38 S/. 2,643.46
05.02.03 MATERIAL GRANULAR E=0.20 m EN CAPAS DE 0.10 m m2 727.08 23.25 16,904.61 S/. 16,904.61
05.02.04 ACARREO DE MATERIAL EXCEDENTE D=30M m3 894.68 17.23 15,415.34 S/. 15,415.34
05.02.05 ELIMINACIN DE MATERIAL EXCED C/ MAQUINARIA m3 894.68 19.02 17,016.81 S/. 10,210.09 S/. 6,806.72
05.03 CONCRETO DE GRADERIAS 101,947.14
05.03.01 ENCOFRADO Y DESENCOFRADO DE GRADERIAS m2 249.28 55.52 13,840.03 S/. 13,840.03
05.03.02 CONCRETO F'C=210 kg/cm2 PARA GRADERIAS m3 190.34 429.24 81,701.54 S/. 59,914.46 S/. 21,787.08
05.03.03 FROTACHADO DE LOSAS m2 727.08 7.54 5,482.18 S/. 4,020.27 S/. 1,461.91
05.03.04 CURADO DE CONCRETO m2 727.08 1.27 923.39 S/. 388.80 S/. 534.59
06 PAVIMENTO RIGIDO 343,963.45
06.01 OBRAS PRELIMINARES 10,008.67
06.01.01 TRAZO NIVELACION Y REPLANTEO m2 2,343.95 1.90 4,453.51 S/. 4,453.51
06.01.02 CONTROL TOPOGRAFICO DURANTE LA EJECUCION m2 2,343.95 2.37 5,555.16 S/. 962.89 S/. 2,296.13 S/. 2,222.06 S/. 74.08
06.02 MOVIMIENTO DE TIERRAS 115,735.42
06.02.01 CORTE DE TERRENO MANUAL m3 31.32 41.36 1,295.40 S/. 1,295.40
06.02.02 CORTE DE TERRENO NORMAL CON MAQUINARIA m3 1,265.06 6.89 8,716.26 S/. 5,810.84 S/. 2,905.42
06.02.03 PERFILADO Y COMPACTADO DE SUBRASANTE MANUAL m2 78.30 5.09 398.55 S/. 398.55
06.02.04 PERFILADO Y COMPACTADO DE LA SUBRASANTE m2 2,265.65 2.73 6,185.22 S/. 1,237.04 S/. 4,948.18
06.02.05 MATERIAL GRANULAR E=0.20 m EN CAPAS DE 0.10 m m2 78.30 23.25 1,820.48 S/. 1,820.48
06.02.06 SUB-BASE E=0.20 M. REND.= 2340 M2/DIA. m2 2,265.65 15.99 36,227.74 S/. 36,227.74
06.02.07 ACARREO DE MATERIAL EXCEDENTE D=30M m3 1,685.29 17.23 29,037.55 S/. 22,336.58 S/. 6,700.97
06.02.08 ELIMINACIN DE MATERIAL EXCED C/ MAQUINARIA m3 1,685.29 19.02 32,054.22 S/. 17,095.58 S/. 14,958.64
06.03 CONCRETO EN PAVIMENTO RIGIDO 200,991.22
06.03.01 ENCOFRADO Y DESENCOFRADO DE PAVIMENTO m2 588.35 38.98 22,933.88 S/. 19,493.80 S/. 3,440.08
06.03.02 CONCRETO F'C=210 kg/cm2 PARA PAVIMENTOS e = 0.20 m m3 398.60 394.90 157,407.14 S/. 53,968.16 S/. 103,438.98
06.03.03 FROTACHADO DE LOSAS m2 2,343.95 7.54 17,673.38 S/. 6,059.44 S/. 11,613.94
06.03.04 CURADO DE CONCRETO m2 2,343.95 1.27 2,976.82 S/. 798.66 S/. 2,178.16
06.04 JUNTAS ASFALTICAS 17,228.14
06.04.01 JUNTAS DE DILATACION m 240.89 13.51 3,254.42 S/. 1,084.81
06.04.02 JUNTAS DE CONTRACCION m 569.49 5.79 3,297.35
06.04.03 JUNTAS LONGITUDINALES m 1,342.94 7.95 10,676.37
07 VEREDAS 190,822.92
07.01 OBRAS PRELIMINARES 6,660.95
07.01.01 TRAZO NIVELACION Y REPLANTEO m2 1,559.94 1.90 2,963.89 S/. 2,963.89
07.01.02 CONTROL TOPOGRAFICO DURANTE LA EJECUCION m2 1,559.94 2.37 3,697.06 S/. 1,478.82 S/. 2,218.24
07.02 MOVIMIENTO DE TIERRAS 70,474.33
07.02.01 CORTE DE TERRENO MANUAL m3 361.36 41.36 14,945.85 S/. 14,945.85
07.02.02 PERFILADO Y COMPACTADO DE SUBRASANTE MANUAL m2 1,559.94 5.09 7,940.09 S/. 7,940.09
07.02.03 MATERIAL GRANULAR E=0.10 m EN CAPAS DE 0.10 m m2 1,559.94 19.59 30,559.22 S/. 30,559.22
07.02.04 ACARREO DE MATERIAL EXCEDENTE D=30M m3 469.77 17.23 8,094.14 S/. 8,094.14
07.02.05 ELIMINACIN DE MATERIAL EXCED C/ MAQUINARIA m3 469.77 19.02 8,935.03 S/. 8,190.44 S/. 744.59
07.03 CONCRETO EN VEREDAS 106,975.66
07.03.01 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 620.93 42.92 26,650.32 S/. 2,961.15 S/. 23,689.17
07.03.02 CONCRETO F'C=175 kg/cm2 PARA VEREDAS m3 193.48 344.13 66,582.27 S/. 66,582.27
07.03.03 ACABADO PULIDO Y BRUADO DE VEREDA m2 1,559.94 7.54 11,761.95 S/. 11,761.95
07.03.04 CURADO DE CONCRETO m2 1,559.94 1.27 1,981.12 S/. 1,761.00 S/. 220.12
07.04 JUNTAS ASFALTICAS 6,711.98
07.04.01 JUNTAS DE DILATACION DE 1" m 518.70 12.94 6,711.98 S/. 6,711.98
08 MURO DE CONTENCIN DE CONCRETO ARMADO 235,135.94
08.01 OBRAS PRELIMINARES 485.89
08.01.01 TRAZO NIVELACION Y REPLANTEO m2 255.73 1.90 485.89 S/. 485.89
08.02 MOVIMIENTO DE TIERRAS 39,061.96
08.02.01 EXCAVACION MANUAL DE ZANJA m3 459.59 40.57 18,645.57 S/. 18,645.57
08.02.02 PERFILADO Y COMPACTADO DE FONDO DE ZANJA m2 255.73 7.46 1,907.75 S/. 1,907.75
08.02.03 RELLENO CON MATERIAL PROPIO m3 259.37 34.98 9,072.76 S/. 9,072.76
08.02.04 ACARREO DE MATERIAL EXCEDENTE D=30M m3 260.30 17.23 4,484.97 S/. 4,484.97
08.02.05 ELIMINACIN DE MATERIAL EXCED C/ MAQUINARIA m3 260.30 19.02 4,950.91 S/. 4,950.91
08.03 CONCRETO SIMPLE 7,226.93
08.03.01 SOLADO DE CONCRETO E=10cm m2 255.73 28.26 7,226.93 S/. 7,226.93
08.04 CONCRETO ARMADO 188,005.04
08.04.01 ENCOFRADO Y DESENCOFRADO DE MUROS m2 553.43 63.99 35,413.99 S/. 14,755.83 S/. 20,658.16
08.04.02 ACERO CORRUGADO FY=4200 Kg/cm2 kg 7,810.53 6.65 51,940.02 S/. 51,940.02
08.04.03 CONCRETO F'C=210 kg/cm2 PARA MUROS m3 215.61 463.56 99,948.17 S/. 49,974.09 S/. 49,974.08
08.04.04 CURADO DE CONCRETO m2 553.43 1.27 702.86 S/. 183.35 S/. 519.51
08.05 JUNTAS ASFALTICAS 356.12
08.05.01 JUNTA DE DILATACION e=1" m 58.00 6.14 356.12 S/. 356.12
09 MURO DE CONTENCION POR GRAVEDAD 54,569.57
09.01 OBRAS PRELIMINARES 331.47
09.01.01 TRAZO NIVELACION Y REPLANTEO m2 174.46 1.90 331.47 S/. 331.47
09.02 MOVIMIENTO DE TIERRAS 8,267.91
09.02.01 EXCAVACION MANUAL DE ZANJA m3 84.44 40.57 3,425.73 S/. 3,425.73
09.02.02 PERFILADO Y COMPACTADO DE FONDO DE ZANJA m2 174.46 7.46 1,301.47 S/. 1,301.47
09.02.03 RELLENO CON MATERIAL PROPIO m3 36.12 34.98 1,263.48 S/. 1,263.48
09.02.04 ACARREO DE MATERIAL EXCEDENTE D=30M m3 62.82 17.23 1,082.39 S/. 1,082.39
09.02.05 ELIMINACIN DE MATERIAL EXCED C/ MAQUINARIA m3 62.82 19.02 1,194.84 S/. 1,194.84
09.03 CONCRETO SIMPLE 45,970.19
09.03.01 ENCOFRADO Y DESENCOFRADO DE MUROS m2 381.91 63.99 24,438.42 S/. 24,438.42
09.03.02 CONCRETO f'c = 175 kg/cm2+ 70% P.M. m3 106.69 197.27 21,046.74 S/. 19,643.62 S/. 1,403.12
09.03.03 CURADO DE CONCRETO m2 381.91 1.27 485.03 S/. 280.81 S/. 204.22
10 DRENAJE PLUVIAL 324,295.23
10.01 OBRAS PRELIMINARES 1,710.65
10.01.01 TRAZO NIVELACION Y REPLANTEO m2 400.62 1.90 761.18 S/. 253.73 S/. 507.45
10.01.02 CONTROL TOPOGRAFICO DURANTE LA EJECUCION m2 400.62 2.37 949.47 S/. 949.47
10.02 MOVIMIENTO DE TIERRAS 24,901.71
10.02.01 EXCAVACION MANUAL DE ZANJA m3 249.88 40.57 10,137.63 S/. 10,137.63
10.02.02 PERFILADO Y COMPACTADO DE FONDO DE ZANJA m2 400.62 7.46 2,988.63 S/. 2,988.63
10.02.03 ACARREO DE MATERIAL EXCEDENTE D=30M m3 324.84 17.23 5,596.99 S/. 5,596.99
10.02.04 ELIMINACIN DE MATERIAL EXCED C/ MAQUINARIA m3 324.84 19.02 6,178.46 S/. 4,942.77 S/. 1,235.69
10.03 CONCRETO SIMPLE 11,321.52
10.03.01 SOLADO DE CONCRETO E=10cm m2 400.62 28.26 11,321.52 S/. 11,321.52
10.04 CONCRETO ARMADO 241,769.48
10.04.01 ENCOFRADO Y DESENCOFRADO DE DRENAJE PLUVIAL m2 1,335.40 54.64 72,966.26 S/. 29,186.50 S/. 43,779.76
10.04.02 ACERO CORRUGADO FY=4200 Kg/cm2 kg 11,908.69 6.65 79,192.79 S/. 79,192.79
10.04.03 CONCRETO F'C=210 kg/cm2 PARA DRENAJE PLUVIAL m3 207.58 429.24 89,101.64 S/. 21,780.40 S/. 61,381.13 S/. 5,940.11
10.04.04 CURADO DE CONCRETO m2 400.62 1.27 508.79 S/. 49.88 S/. 309.26 S/. 149.65
10.05 REJILLAS METALICAS 44,591.87
10.05.01 REJILLAS DE TOMAS LATERALES m 61.50 669.64 41,182.86 S/. 41,182.86
TAPA DE CONCRETO ARMADO PREFABRICADO und 17.00 200.53 3,409.01 S/. 3,409.01
11 SARDINELES 68,682.41
11.01 OBRAS PRELIMINARES 139.08
11.01.01 TRAZO NIVELACION Y REPLANTEO m2 73.20 1.90 139.08 S/. 139.08
11.02 CONCRETO EN SARDINELES 62,870.00
11.02.01 ENCOFRADO Y DESENCOFRADO DE SARDINELES m2 552.00 76.29 42,112.08 S/. 42,112.08
11.02.02 CONCRETO F'C=175 Kg/cm2 EN SARDINELES m3 60.32 344.13 20,757.92 S/. 20,757.92
11.03 REVOQUES Y ACABADOS 5,673.33
11.03.01 TARRAJEO CON MORTERO 1:5 (C:A) E = 1.5 cm m2 185.95 30.51 5,673.33 S/. 5,673.33
12 SISTEMA DE AGUA POTABLE 71,599.87
12.01 OBRAS PRELIMINARES 857.64
12.01.01 TRAZO NIVELACION Y REPLANTEO m2 451.39 1.90 857.64 S/. 857.64
12.02 MOVIMIENTO DE TIERRAS 25,207.21
12.02.01 EXCAVACION MANUAL DE ZANJAS m3 212.73 34.47 7,332.80 S/. 4,583.00 S/. 2,749.80
12.02.02 PERFILADO Y COMPACTADO DE FONDO DE ZANJA m2 451.39 7.46 3,367.37 S/. 1,496.61 S/. 1,870.76
12.02.03 RELLENO CON MATERIAL PROPIO m3 166.76 34.98 5,833.26 S/. 5,833.26
12.02.04 CAMA DE APOYO e = 0.10 m, PARA AGUA m 1,123.27 6.71 7,537.14 S/. 1,884.29 S/. 5,652.85
12.02.05 ELIMINACIN DE MATERIAL EXCED C/ MAQUINARIA m3 59.76 19.02 1,136.64 S/. 1,136.64
12.03 SUMINISTRO E INSTALACION DE TUBERIAS 9,861.47
12.03.01 SUMINISTRO E INSTALACION DE TUBERIA P.V.C SAP 1" C-10 m 593.57 8.44 5,009.73 S/. 5,009.73
12.03.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP 2" C-10 m 189.65 9.09 1,723.92 S/. 1,723.92
12.03.03 SUMINISTRO E INSTALACION DE TUBERIA P.V.C. SAP 3/4" C-10 m 124.05 8.10 1,004.81 S/. 1,004.81
12.03.04 PRUEBA HIDRAULICA m 907.27 2.34 2,123.01 S/. 2,123.01
12.04 RECONEXION DOMICILARIA 30,754.80
12.04.01 INSTALACION A DOMICILIO INC./CAJA DE REGISTRO pto 180.00 170.86 30,754.80 S/. 30,754.80
12.05 CAJAS DE CONTROL 0.40 x 0.40 m 4,871.72
12.05.01 CAJA DE CONTROL 0.40 x 0.40 CON VALVULA COMPUERTA DE 2" und 3.00 366.79 1,100.37 S/. 1,100.37
12.05.02 CAJA DE CONTROL 0.40 x 0.40 CON VALVULA COMPUERTA DE 1" und 7.00 335.79 2,350.53 S/. 2,350.53
12.05.03 CAJA DE CONTROL 0.40 x 0.40 CON VALVULA COMPUERTA DE 3/4" und 2.00 323.29 646.58 S/. 646.58
12.05.04 TAPA DE CONCRETO ARMADO 0.35 X 0.35 und 12.00 64.52 774.24 S/. 774.24
12.06 ACCESORIOS 47.03
12.06.01 ACCESORIOS PARA AGUA POTABLE GLB 1.00 47.03 47.03 S/. 47.03
13 SISTEMA DE DESAGUE 175,762.00
13.01 OBRAS PRELIMINARES 1,615.23
13.01.01 TRAZO NIVELACION Y REPLANTEO m2 850.12 1.90 1,615.23 S/. 1,615.23
13.02 MOVIMIENTO DE TIERRAS 66,939.39
13.02.01 EXCAVACION MANUAL DE ZANJAS m3 716.51 34.47 24,698.10 S/. 24,698.10
13.02.02 PERFILADO Y COMPACTADO DE FONDO DE ZANJA m2 850.12 7.46 6,341.90 S/. 6,341.90
13.02.03 RELLENO CON MATERIAL PROPIO m3 623.02 34.98 21,793.24 S/. 6,537.97 S/. 15,255.27
13.02.04 CAMA DE APOYO e = 0.10 m, PARA DESAGUE m 1,116.90 10.56 11,794.46 S/. 11,794.46
13.02.05 ELIMINACIN DE MATERIAL EXCED C/ MAQUINARIA m3 121.54 19.02 2,311.69 S/. 2,311.69
13.03 SUMINISTRO E INSTALACION DE TUBERIAS 32,749.62
13.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC-U D=160 mm, S-25 m 846.90 36.86 31,216.73 S/. 16,648.92 S/. 14,567.81
13.03.02 PRUEBA HIDRAULICA PARA DESAGUE m 846.90 1.81 1,532.89 S/. 1,532.89
13.04 REPOSICION Y REHABILITACION DE BUZONES 44,210.56
13.04.01 BUZON TIPO I TERR.NORMAL H= 1.50 A 2.00 und 37.00 1,194.88 44,210.56 S/. 44,210.56
13.05 RECONEXION DOMICILIARIA 30,247.20
13.05.01 INSTALACION A DOMICILIO DESAGE INC./CAJA DE REGISTRO pto 180.00 168.04 30,247.20 S/. 30,247.20
14 OBRAS COMPLEMENTARIAS 53,912.39
14.01 PINTURA 21,859.18
14.01.01 PINTURA TRAFICO EN VEREDAS m 1,415.75 15.44 21,859.18
14.02 CARPINTERIA METALICA 25,273.55
14.02.01 BARANDA METALICA DE TUBO FO. GDO DE 2" Y 3" m 150.25 144.64 21,732.16
CRONOGRAMA VALORIZADO DE OBRA
PROYECTO: MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL DE LOS PSJES: INCA GARCILAZO, JOSE SANTOS CHOCANO, LA GLOBALIZACION, LAS CALLES: LUIS PARDO, PEDRO PABLO PALACIOS Y DEL JR. LAUNION: LADO NORTE Y ULTIMA CUADRA EN SHANCAYAN - INDEPENDENCIA HUARAZ - ANCASH
LUGAR: SHANCAYAN - INDEPENDENCIA - HUARAZ - ANCASH
TIEMPO: 210 DIAS CALENDARIOS

Item Descripcin Und. Metrado Precio S/. Parcial S/. Mes 1 Mes 2 Mes 3 Mes 4 Mes 5
14.02.02 PINTURA EN BARANDAS METALICAS m 150.25 23.57 3,541.39
JARDINERIA
14.03 6,779.66
14.03.01 TRABAJOS DE JARDINERIA GLB 1.00 6,779.66 6,779.66
MITIGACION DE IMPACTO AMBIENTAL
15 4,237.29
15.01 MITIGACION DE IMPACTO AMBIENTAL GLB 1.00 4,237.29 4,237.29
VARIOS
16 4,661.02
16.01 LIMPIEZA FINAL DE OBRA GLB 1.00 1,694.92 1,694.92
16.02 CAPACITACION DE USUARIOS GLB 1.00 2,966.10 2,966.10
COSTO DIRECTO #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
AVANCE MENSUAL (%) 1,758,454.04 #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
AVANCE ACUMULADO (%) #VALUE! #VALUE! #VALUE! #VALUE! #VALUE!
Mes 6 Mes 7

S/. 96.85 S/. 96.85

S/. 121.07 S/. 121.07

S/. 1,730.21

S/. 2,169.61
S/. 3,297.35
S/. 10,676.37

S/. 21,859.18

S/. 21,732.16
Mes 6 Mes 7
S/. 3,541.39

S/. 1,355.93 S/. 5,423.73

S/. 4,237.29

S/. 1,694.92
S/. 2,966.10
#VALUE! #VALUE!
#VALUE! #VALUE!
#VALUE! #VALUE!
CRONOGRAMA VALO

Item Descripcin

PROYECTO
01 OBRAS PROVISIONALES Y PRELIMINARES
01.01 CARTEL DE OBRA
01.02 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS
01.03 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL
01.04 TRAZO , NIVELACION Y REPLANTEO
01.05 TRAZO , NIVELACION Y REPLANTEO DE OBRAS DE ARTE
02 MOVIMIENTO DE TIERRAS
02.01 DESBROCE Y LIMPIEZA DEL TERRENO
02.02 CORTE EN MATERIAL SUELTO
02.03 CORTE EN ROCA SUELTA
02.04 CORTE EN ROCA FIJA
02.05 RELLENO COMPACTADO CON MATERIAL PROPIO
02.06 PERFILADO, NIVELACION Y COMPACTACION DE SUBRASANTES
03 AFIRMADO
03.01 AFIRMADO GRANULAR e= 20 cm
04 OBRAS DE ARTE Y DRENAJE
04.01 CUNETAS
04.01.01 CUNETA TRIANGULAR DE TIERRA
04.01.01.01 CONFORMACION Y PERFILADO DE CUNETAS
0.4.02 ALCANTARILLAS TMC
04.02.01 ALCANTARILLAS DE ALIVIO
04.02.01.01 ALCANTARILLAS DE TMC D=36"
04.02.01.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS
04.02.01.01.02 ALCANTARILLA DE TUBERIA METALICA CORRUGADA TMC 36"
04.02.01.01.03 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO
04.02.01.01.04 ENCOFRADO Y DESENCOFRADO
04.02.01.01.05 CONCRETO f'c=175 kg/cm2
04.02.01.01.06 EMBOQUILLADO DE PIEDRA CON MORTERO DE CONCRETO C/A 1:4
04.02.01.01.07 ELIMINACION DE MATERIAL EXCEDENTE DIST/PROM= 30 m
04.02.02.02 ALCANTARILLAS DE TMC D=36"
04.02.01.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS
04.02.01.02.02 ALCANTARILLA DE TUBERIA METALICA CORRUGADA TMC 60"
04.02.01.02.03 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO
04.02.01.02.04 ENCOFRADO Y DESENCOFRADO
04.02.01.02.05 CONCRETO f'c=175 kg/cm2
04.02.01.02.06 EMBOQUILLADO DE PIEDRA CON MORTERO DE CONCRETO C/A 1:4
04.02.01.02.07 ELIMINACION DE MATERIAL EXCEDENTE DIST/PROM= 30 m
04.02.03.03 ALCANTARILLAS DE TMC D=36"
04.02.01.03.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS
04.02.01.03.02 ALCANTARILLA DE TUBERIA METALICA CORRUGADA TMC 72"
04.02.01.03.03 RELLENO PARA ESTRUCTURAS CON MATERIAL PROPIO
04.02.01.03.04 ENCOFRADO Y DESENCOFRADO
04.02.01.03.05 CONCRETO f'c=175 kg/cm2
04.02.01.03.06 EMBOQUILLADO DE PIEDRA CON MORTERO DE CONCRETO C/A 1:4
04.02.01.03.07 ELIMINACION DE MATERIAL EXCEDENTE DIST/PROM= 30 m
05 TRANSPORTE
05.01 TRANSPORTE DE MATERIAL GRANULAR PARA D<1KM
05.02 TRANSPORTE DE MATERIAL GRANULAR PARA D>1KM
05.03 TRANSPORTE DE MATERIAL EXCEDENTE PARA D<1KM
05.04 TRANSPORTE DE MATERIAL EXCEDENTE PARA D>1km
06 SEALIZACION
06.01 SEALES INFORMATIVAS
06.02 SEALES REGLAMENTARIAS
06.03 SEALES PREVENTIVAS
06.04 HITOS KILOMETRICOS
07 MITIGACION DE IMPACTO AMBIENTAL
07.01 EDUCACION AMBIENTAL A TRABAJADORES Y POBLADORES
07.02 RESTAURACION DE CAMPAMENTO Y PATIO DE MAQUINAS
07.03 RESTAURACION DE CANTERAS
07.04 ACONDICIONAMIENTO DE BOTADEROS
CRONOGRAMA VALORIZADO DE OBRA

ABRIL MES
ENERO MES 1 FEBRERO MES 2 MARZO MES 3 MAYO MES 5
4

### ### ### ### ###


S/. 16,041.07 S/. 18,370.41 S/. 21,942.54 S/. 10,059.43 S/. 9,223.31
S/. 925.78
S/. 4,744.47 S/. 5,807.44 S/. 6,429.67 S/. 6,222.26 S/. 5,625.96
S/. 2,925.84 S/. 3,581.36 S/. 3,965.08 S/. 3,837.17 S/. 3,597.35
S/. 7,444.98
S/. 8,981.61 S/. 11,547.79
S/. 38,131.11 ### ### ###
S/. 9,055.41
S/. 29,075.70 S/. 63,232.58 S/. 70,007.50 S/. 18,348.74
S/. 27,550.35
S/. 86,485.22
S/. 5,486.19 S/. 194,367.74 S/. 50,943.16
S/. 43,145.22 S/. 65,853.24
### ###
S/. 238,233.92 S/. 463,929.22
### S/. 64,184.22 S/. 11,096.60
S/. 11,096.60
S/. 11,096.60
S/. 11,096.60
### S/. 64,184.22
### S/. 64,184.22
###
S/. 3,346.42
S/. 23,021.28
S/. 2,312.13
S/. 21,020.89
S/. 34,080.06
S/. 16,596.88
S/. 3,687.22
S/. 9,600.01 S/. 52,406.81
S/. 1,806.35
S/. 7,793.66 S/. 4,676.20
S/. 1,124.82
S/. 8,176.78
S/. 15,840.03
S/. 20,728.47
S/. 1,860.51
S/. 11,777.41
S/. 301.01
S/. 2,238.18
S/. 187.47
S/. 1,362.80
S/. 2,640.00
S/. 4,737.94
S/. 310.01
S/. 84,924.23 ### ### S/. 98,686.50 S/. 87,813.73
S/. 14,457.63 S/. 28,154.34
S/. 30,635.91 S/. 59,659.39
S/. 58,378.99 S/. 126,960.13 S/. 140,563.00 S/. 36,841.11
S/. 26,545.24 S/. 57,729.45 S/. 63,914.75 S/. 16,751.85
S/. 18,114.12
S/. 1,851.52
S/. 2,320.56
S/. 13,942.04

S/. 2,953.61 S/. 3,835.05 ### S/. 1,500.00


S/. 2,953.61 S/. 3,835.05 S/. 3,711.34 S/. 1,500.00

S/. 102,800.00
JUNIO MES 6 TOTAL

S/. 73,638.76 ###


S/. 75,636.76
S/. 925.78
S/. 28,829.80
S/. 17,906.80
S/. 7,444.98
S/. 20,529.40
S/. 663,551.05
S/. 9,055.41
S/. 180,664.52
S/. 27,550.35
S/. 86,485.22
S/. 250,797.09
S/. 108,998.46
S/. 702,163.14
S/. 702,163.14
S/. 188,945.71
S/. 11,096.60
S/. 11,096.60
S/. 11,096.60
S/. 177,849.11
S/. 177,849.11
S/. 104,064.88
S/. 3,346.42
S/. 23,021.28
S/. 2,312.13
S/. 21,020.89
S/. 34,080.06
S/. 16,596.88
S/. 3,687.22
S/. 62,006.82
S/. 1,806.35
S/. 12,469.86
S/. 1,124.82
S/. 8,176.78
S/. 15,840.03
S/. 20,728.47
S/. 1,860.51
S/. 11,777.41
S/. 301.01
S/. 2,238.18
S/. 187.47
S/. 1,362.80
S/. 2,640.00
S/. 4,737.94
S/. 310.01
S/. 660,591.79
S/. 42,611.97
S/. 90,295.30
S/. 362,743.23
S/. 164,941.29
S/. 16,286.70 S/. 34,400.82
S/. 1,851.52
S/. 2,320.56
S/. 14,841.52 S/. 28,783.56
S/. 1,445.18 S/. 1,445.18
S/. 57,352.06 S/. 172,152.06
S/. 12,000.00
S/. 2,029.82 S/. 2,029.82
S/. 55,322.24 S/. 55,322.24
S/. 102,800.00
CALENDARIO DE AVANCE DE OBRA - CALENDARIZADO
OBRA : MEJORAMIENTO DEL SERVICIO DE EDUCACION PRIMARIA EN LA I. E. 821213 - SUCCHAPAMPA

LUGAR: CORTEGANA - CELENDIN - CAJAMARCA

PLAZO 180 DIAS CALENDARIOS

VAL 01 VAL 02 VAL 03 VAL 04 VAL 05 VAL 06 VAL 07 VAL 08 VAL 09


Item Descripcin Parcial S/.
11.12.2013 01.01.2014 01.02.2014 01.03.2014 20.05.2014 01.06.2014 01.07.2014 01.08.2014 01.09.2014 01.10.2014
31.12.2013 31.01.2014 28.02.2014 31.03.2014 31.05.2014 30.06.2014 31.07.2014 31.08.2014 30.09.2014 31.10.2014

01 04 AULAS (02) NIVELES 337,259.69 25,817.37 76,500.49 65,645.43 39,219.67 24,770.31 43,910.63 4,725.57 4,725.57 23,004.43 28,940.24
01.01 TRABAJOS PROVISIONALES 1,847.19 1,847.19 - ### - - - - - ### -
01.02 OBRAS PRELIMINARES 30,778.37 15,389.19 15,389.19 - - - - - ### -
01.03 MOVIMIENTO DE TIERRAS 17,161.98 8,580.99 8,580.99 - - - - - ### -
01.04 OBRAS DE CONCRETO SIMPLE 30,462.53 - 30,462.53 - - - - - ### -
01.05 OBRAS DE CONCRETO ARMADO 113,876.04 - 22,067.78 57,770.16 20,862.06 13,176.04 - - - -
01.05.01 ZAPATAS 14,270.85 - 14,270.85 - - - - - ### -
01.05.02 VIGA DE CIMENTACION 7,796.93 - 7,796.93 - - - - - ### -
01.05.03 COLUMNAS 25,292.35 - - 25,292.35 - - - - ### -
01.05.04 VIGAS 32,477.81 - - 32,477.81 - - - - ### -
01.05.05 LOSAS ALIGERADAS 34,038.10 - - ### 20,862.06 13,176.04 - - ### -
01.06 ESCALERA DE CIRCULACION 3,061.64 - - ### 1,876.49 1,185.15 - - ### -
01.07 MUROS Y TABIQUES DE ALBAILERIA 15,750.54 - - 7,875.27 4,826.78 3,048.49 - - ### -
01.08 REVOQUES ENLUCIDOS Y MOLDURAS 19,127.68 - - ### 5,861.71 3,702.13 9,563.84 - ### -
01.09 PISOS Y PAVIMENTOS 47,255.67 - - ### 5,792.63 3,658.50 18,902.27 4,725.57 4,725.57 4,725.57 4,725.57
01.10 ZOCALOS Y CONTRAZOCALOS 5,978.10 - - ### - - - 5,978.10
01.11 CUBIERTAS 8,417.29 - - ### - - 8,417.29 - ### -
01.12 CARPINTERIA DE MADERA 18,248.52 - - ### - - 9,124.26 9,124.26
01.13 CARPINTERIA METALICA 3,176.50 - - ### - - - 3,176.50 -
01.14 CERRAJERIA 724.15 - - ### - - - - 724.15
01.15 VIDRIOS, CRISTALES Y SIMILARES 4,379.75 - - ### - - - - 4,379.75
01.16 PINTURA 9,986.51 - - ### - - - - 9,986.51
01.17 INSTALACIONES ELECTRICAS 5,704.85 - - ### - - 5,704.85 - ### -
01.18 INSTALACIONES SANITARIAS 1,322.38 - - ### - - 1,322.38 - ### -
02 02 AULAS - BIBLIOTECA - SALA DE LECTURA 273,433.99 8,789.30 60,626.38 65,058.83 35,316.03 22,304.85 32,693.58 - - 21,012.34 27,632.68
02.01 OBRAS PRELIMINARES 384.14 384.14 - ### - - - - ### -
02.02 MOVIMIENTO DE TIERRAS 16,810.32 8,405.16 8,405.16 - - - - - ### -
02.03 OBRAS DE CONCRETO SIMPLE 30,153.44 - 30,153.44 - - - - - ### -
02.04 OBRAS DE CONCRETO ARMADO 113,876.04 - 22,067.78 57,770.16 20,862.06 13,176.04 - - - -
02.04.01 ZAPATAS 14,270.85 - 14,270.85 - - - - - ### -
02.04.02 VIGA DE CIMENTACION 7,796.93 - 7,796.93 - - - - - ### -
02.04.03 COLUMNAS 25,292.35 - - 25,292.35 - - - - ### -
02.04.04 VIGAS 32,477.81 - - 32,477.81 - - - - ### -
02.04.05 LOSAS ALIGERADAS 34,038.10 - - ### 20,862.06 13,176.04 - - ### -
02.05 ESCALERA DE CIRCULACION 3,008.64 - - ### 1,844.01 1,164.63 - - ### -
02.06 MUROS Y TABIQUES DE ALBAILERIA 14,577.34 - - 7,288.67 4,467.25 2,821.42 - - ### -
02.07 REVOQUES ENLUCIDOS Y MOLDURAS 18,643.76 - - ### 5,713.41 3,608.47 9,321.88 - ### -
02.08 PISOS Y PAVIMENTOS 19,817.96 - - ### 2,429.30 1,534.29 7,927.18 3,963.59 3,963.59
02.09 ZOCALOS Y CONTRAZOCALOS 5,978.10 - - ### - - - 5,978.10
02.10 CUBIERTAS 8,417.29 - - ### - - 8,417.29 - ### -
02.11 CARPINTERIA DE MADERA 18,279.19 - - ### - - 9,139.60 9,139.60
02.12 CARPINTERIA METALICA 1,931.05 - - ### - - - 1,931.05
02.13 CERRAJERIA 724.15 - - ### - - - - 724.15
02.14 VIDRIOS, CRISTALES Y SIMILARES 4,111.97 - - ### - - - - 4,111.97
02.15 PINTURA 9,693.37 - - ### - - - - 9,693.37
02.16 INSTALACIONES ELECTRICAS 5,704.85 - - ### - - 5,704.85 - ### -
02.17 INSTALACIONES SANITARIAS 1,322.38 - - ### - - 1,322.38 - ### -
03 ADMINISTRACION - SALA DE COMPUTO - SALA MULTIUSOS 281,449.78 9,425.51 62,555.57 66,355.84 36,590.63 23,109.88 33,592.05 5,978.10 - 15,453.25 28,388.95
03.01 OBRAS PRELIMINARES 384.14 384.14 - ### - - - - ### -
03.02 MOVIMIENTO DE TIERRAS 18,082.73 9,041.37 9,041.37 - - - - - ### -
03.03 OBRAS DE CONCRETO SIMPLE 31,446.42 - 31,446.42 - - - - - ### -
03.04 OBRAS DE CONCRETO ARMADO 113,876.04 - 22,067.78 57,770.16 20,862.06 13,176.04 - - - -
03.04.01 ZAPATAS 14,270.85 - 14,270.85 - - - - - ### -
03.04.02 VIGA DE CIMENTACION 7,796.93 - 7,796.93 - - - - - ### -
03.04.03 COLUMNAS 25,292.35 - - 25,292.35 - - - - ### -
03.04.04 VIGAS 32,477.81 - - 32,477.81 - - - - ### -
03.04.05 LOSAS ALIGERADAS 34,038.10 - - ### 20,862.06 13,176.04 - - ### -
CALENDARIO DE AVANCE DE OBRA - CALENDARIZADO
OBRA : MEJORAMIENTO DEL SERVICIO DE EDUCACION PRIMARIA EN LA I. E. 821213 - SUCCHAPAMPA

LUGAR: CORTEGANA - CELENDIN - CAJAMARCA

PLAZO 180 DIAS CALENDARIOS

VAL 01 VAL 02 VAL 03 VAL 04 VAL 05 VAL 06 VAL 07 VAL 08 VAL 09


Item Descripcin Parcial S/.
03.05 ESCALERA DE CIRCULACION 2,980.99 - - ### 1,827.06 1,153.93 - - ### -
03.06 MUROS Y TABIQUES DE ALBAILERIA 17,171.36 - - 8,585.68 5,262.19 3,323.49 - - ### -
03.07 REVOQUES ENLUCIDOS Y MOLDURAS 20,087.90 - - ### 6,155.97 3,887.98 10,043.95 - ### -
03.08 PISOS Y PAVIMENTOS 20,258.96 - - ### 2,483.35 1,568.44 8,103.58 4,051.79 4,051.79
03.09 ZOCALOS Y CONTRAZOCALOS 5,978.10 - - ### - - - 5,978.10
03.10 CUBIERTAS 8,417.29 - - ### - - 8,417.29 - ### -
03.11 CARPINTERIA DE MADERA 18,309.86 - - ### - - 9,154.93 9,154.93
03.12 CARPINTERIA METALICA 2,246.53 - - ### - - - 2,246.53 -
03.13 CERRAJERIA 1,013.81 - - ### - - - - 1,013.81
03.14 VIDRIOS, CRISTALES Y SIMILARES 3,844.18 - - ### - - - - 3,844.18
03.15 PINTURA 10,324.24 - - ### - - - - 10,324.24
03.16 INSTALACIONES ELECTRICAS 5,704.85 - - ### - - 5,704.85 - ### -
03.17 INSTALACIONES SANITARIAS 1,322.38 - - ### - - 1,322.38 - ### -
04 COCINA - COMEDOR - IMPRESIONES 132,782.20 4,427.31 32,396.30 28,503.43 18,379.29 11,607.98 17,883.87 - 5,666.25 6,315.50 7,602.28
04.01 OBRAS PRELIMINARES 273.60 273.60 - ### - - - - ### -
04.02 MOVIMIENTO DE TIERRAS 8,307.41 4,153.71 4,153.71 - - - - - ### -
04.03 OBRAS DE CONCRETO SIMPLE 19,620.52 - 19,620.52 - - - - - ### -
04.04 OBRAS DE CONCRETO ARMADO 57,165.26 - 8,622.07 26,168.94 13,713.25 8,661.00 - - - -
04.04.01 ZAPATAS 4,658.41 - 4,658.41 - - - - - ### -
04.04.02 VIGA DE CIMENTACION 3,963.66 - 3,963.66 - - - - - ### -
04.04.03 COLUMNAS 13,043.79 - - 13,043.79 - - - - ### -
04.04.04 VIGAS 13,125.15 - - 13,125.15 - - - - ### -
04.04.05 LOSAS ALIGERADAS 22,374.25 - - ### 13,713.25 8,661.00 - - ### -
04.05 MUROS Y TABIQUES DE ALBAILERIA 4,668.98 - - 2,334.49 1,430.82 903.67 - - ### -
04.06 REVOQUES ENLUCIDOS Y MOLDURAS 6,527.60 - - ### 2,000.39 1,263.41 3,263.80 - ### -
04.07 PISOS Y PAVIMENTOS 10,073.65 - - ### 1,234.83 779.90 4,029.46 2,014.73 2,014.73
04.08 ZOCALOS Y CONTRAZOCALOS 1,286.78 - - ### - - - 1,286.78
04.09 CUBIERTAS 5,198.30 - - ### - - 5,198.30 - ### -
04.10 CARPINTERIA DE MADERA 8,601.54 - - ### - - 4,300.77 4,300.77
04.11 CERRAJERIA 846.72 - - ### - - - 846.72 - -
04.12 VIDRIOS, CRISTALES Y SIMILARES 1,472.50 - - ### - - - 1,472.50 - -
04.13 PINTURA 3,347.03 - - ### - - - 3,347.03 - -
04.14 INSTALACIONES ELECTRICAS 4,414.95 - - ### - - 4,414.95 - ### -
04.15 INSTALACIONES SANITARIAS 977.36 - - ### - - 977.36 - ### -
05 SERVICIOS HIGIENICOS 46,033.83 1,145.80 20,916.42 7,922.27 2,066.90 1,305.41 4,804.42 - 1,912.63 3,405.69 2,554.29
05.01 OBRAS PRELIMINARES 72.78 72.78 - ### - - - - ### -
05.02 MOVIMIENTO DE TIERRAS 2,146.04 1,073.02 1,073.02 - - - - - ### -
05.03 OBRAS DE CONCRETO SIMPLE 8,876.29 - 8,876.29 - - - - - ### -
05.04 OBRAS DE CONCRETO ARMADO 10,246.02 - 6,591.15 3,654.87 - - - - - -
05.04.02 VIGA DE CIMENTACION 1,509.67 - 1,509.67 - - - - - ### -
05.04.03 COLUMNAS 1,883.49 - 1,883.49 - - - - - ### -
05.04.04 VIGAS 3,197.99 - 3,197.99 - - - - - ### -
05.04.05 LOSAS ALIGERADAS 3,654.87 - - 3,654.87 - - - - ### -
05.05 MUROS Y TABIQUES DE ALBAILERIA 3,576.08 - 3,576.08 - - - - - ### -
05.06 REVOQUES ENLUCIDOS Y MOLDURAS 3,467.52 - - 3,467.52 - - - - ### -
05.07 PISOS Y PAVIMENTOS 1,599.76 - 799.88 799.88 - - - - ### -
05.08 ZOCALOS Y CONTRAZOCALOS 1,835.59 - - ### 1,125.04 710.55 - - ### -
05.09 CUBIERTAS 1,536.72 - - ### 941.86 594.86 - - ### -
05.10 CARPINTERIA DE MADERA 3,825.26 - - ### 1,912.63 1,172.26 740.37
05.11 CERRAJERIA 622.64 - - ### - - 381.62 241.02
05.12 VIDRIOS, CRISTALES Y SIMILARES 389.93 - - ### - - - - 389.93
05.13 PINTURA 1,182.97 - - ### - - - - 1,182.97
05.14 INSTALACIONES ELECTRICAS 1,867.22 - - ### - - 1,867.22 - ### -
05.15 INSTALACIONES SANITARIAS 4,789.01 - - - - - 2,937.20 - 1,851.81 -
05.16 APARATOS Y ACCESORIOS SANITARIOS 1,851.81 - - ### - - - 1,851.81 -
05.17 INSTALACIONES SANITARIAS 1,267.39 - - ### - - 1,267.39 - ### -
05.18 SISTEMA DE AGUA FRIA Y CONTRAINCENDIO 1,669.81 - - ### - - 1,669.81 - ### -
CALENDARIO DE AVANCE DE OBRA - CALENDARIZADO
OBRA : MEJORAMIENTO DEL SERVICIO DE EDUCACION PRIMARIA EN LA I. E. 821213 - SUCCHAPAMPA

LUGAR: CORTEGANA - CELENDIN - CAJAMARCA

PLAZO 180 DIAS CALENDARIOS

VAL 01 VAL 02 VAL 03 VAL 04 VAL 05 VAL 06 VAL 07 VAL 08 VAL 09


Item Descripcin Parcial S/.
06 MURO PERIMETRICO (L=82.40 m) 53,686.71 - - - 1,704.36 1,076.44 - - - 3,594.80 47,311.11
06.01 OBRAS PRELIMINARES 167.27 - - ### 102.52 64.75 - - ### -
06.02 MOVIMIENTO DE TIERRAS 2,613.53 - - ### 1,601.84 1,011.69 - - ### -
06.03 OBRAS DE CONCRETO SIMPLE 10,005.29 - - ### - - ### 10,005.29
06.04 OBRAS DE CONCRETO ARMADO 8,647.82 - - - - - 8,647.82
06.04.01 COLUMNAS 5,144.49 - - ### - ### 5,144.49
06.04.02 VIGAS 3,503.33 - - ### - ### 3,503.33
06.05 MUROS Y TABIQUES DE ALBAILERIA 13,205.19 - - ### - ### 13,205.19
06.06 REVOQUES ENLUCIDOS Y MOLDURAS 7,970.78 - - ### - - 7,970.78
06.07 ZOCALOS Y CONTRAZOCALOS 819.39 - - ### - - 819.39
06.08 CARPINTERIA METALICA 3,594.80 - - ### - - - 3,594.80
06.09 PINTURA 6,662.64 - - ### - - - 6,662.64
07 CISTERNA - TANQUE ELEVADO 9,763.51 - - - 2,645.99 1,671.15 4,005.51 259.40 - - 1,181.46
07.01 OBRAS PRELIMINARES 26.27 - - ### 16.1 10.17 - - ### -
07.02 MOVIMIENTO DE TIERRAS 579.45 - - ### 355.15 224.30 - - ### -
07.03 OBRAS DE CONCRETO ARMADO 4,381.53 - - - 2,274.74 1,436.68 410.71 259.40 -
07.04 CARPINTERIA METALICA 3,594.80 - - ### - - 3,594.80 - ### -
07.05 PINTURA 223.46 - - ### - - - 223.46
07.06 LI MPIEZA GENERAL 958.00 - - ### - - - - 958.00
08 MOBILIARIO Y EQUIPAMIENTO 153,482.70 - - - - - - 30,696.54 76,741.35 46,044.81 -
08.01 MOBILIARIO DE AULAS 18,954.60 - - 3,790.92 9,477.30 5,686.38
08.02 BIBLIOTECA Y SALA DE LECTURA 3,643.60 - - 728.72 1,821.80 1,093.08
08.03 SALA DE COMPUTO 85,335.60 - - 17,067.12 42,667.80 25,600.68
08.04 SALA DE PROFESORES 6,089.05 - - 1,217.81 3,044.53 1,826.72
08.05 SALA DE USOS MULTIPLES 24,141.75 - - 4,828.35 12,070.88 7,242.53
08.06 DIRECCION, SUBDIRECCION Y SECRETARIA 15,318.10 - - 3,063.62 7,659.05 4,595.43
09 CAPACITACION DOCENTE 21,120.00 - - - 4,314.84 2,725.16 7,040.00 7,040.00 - - -
09.01 CAPACITACION AL PERSONAL DOCENTE 21,120.00 - - ### 4,314.84 2,725.16 7,040.00 7,040.00
MITIGACION AMBIENTAL
10 11,778.82 1,092.22 1,092.22 1,092.22 669.43 422.79 1,092.22 1,092.22 - 3,265.00 1,960.50
10.01 ASPERSION DE AGUA PARA EVITAR EL POLVO 6,553.32 1,092.22 1,092.22 1,092.22 669.43 422.79 1,092.22 1,092.22
10.02 ACONDICIONAMIENTO DE BOTADERO 3,265.00 - - ### - - - 3,265.00 -
10.03 REFORESTACION DE AREAS VERDES 1,960.50 - - ### - - - - 1,960.50
11 FLETE TERRESTRE 24,000.00 4,000.00 4,000.00 4,000.00 2,451.61 1,548.39 4,000.00 4,000.00 - - -
11.01 FLETE TERRESTRE 24,000.00 4,000.00 4,000.00 4,000.00 2,451.61 1,548.39 4,000.00 4,000.00
COSTO DIRECTO 54,697.50 258,087.37 238,578.02 143,358.76 90,542.36 149,022.29 53,791.83 89,045.80 122,095.82 145,571.51
AVANCE MENSUAL (%) 1,344,791.23 4.07% 19.19% 17.74% 10.66% 6.73% 11.08% 4.00% 6.62% 9.08% 10.82%
AVANCE ACUMULADO (%) 4.07% 23.26% 41.00% 51.66% 58.39% 69.47% 73.47% 80.10% 89.18% 100.00%

GASTOS GENERALES (8%) 107,650.00 4,375.80 20,646.99 19,086.24 11,468.70 7,243.39 11,921.78 4,303.35 7,123.66 9,767.67 11,645.72
UTILIDAD (8%) 107,650.00 4,375.80 20,646.99 19,086.24 11,468.70 7,243.39 11,921.78 4,303.35 7,123.66 9,767.67 11,645.72
SUBTOTAL 1,560,091.23 63,449.09 299,381.34 276,750.50 166,296.16 105,029.14 172,865.85 62,398.52 103,293.12 141,631.15 168,862.95
I.G.V (18%) 280,816.42 11,420.84 53,888.64 49,815.09 29,933.31 18,905.24 31,115.85 11,231.73 18,592.76 25,493.61 30,395.33
TOTAL PRESUPUESTADO 1,840,907.65 74,869.93 353,269.99 326,565.59 196,229.47 123,934.38 203,981.71 73,630.25 121,885.89 167,124.75 199,258.28
CALENDARIO DE AVANCE DE OBRA - RESUMEN
OBRA : MEJORAMIENTO DEL SERVICIO DE EDUCACION PRIMARIA EN LA I. E. 821213 - SUCCHAPAMPA

LUGAR: CORTEGANA - CELENDIN - CAJAMARCA

PLAZO 180 DIAS CALENDARIOS

VAL 01 VAL 02 VAL 03 VAL 04 VAL 05 VAL 06 VAL 07 VAL 08 VAL 09


Item Descripcin Parcial S/.
11.12.2013 01.01.2014 01.02.2014 01.03.2014 20.05.2014 01.06.2014 01.07.2014 01.08.2014 01.09.2014 01.10.2014
31.12.2013 31.01.2014 28.02.2014 31.03.2014 31.05.2014 30.06.2014 31.07.2014 31.08.2014 30.09.2014 31.10.2014

01 04 AULAS (02) NIVELES 337,259.69 25,817.37 76,500.49 65,645.43 39,219.67 24,770.31 43,910.63 4,725.57 4,725.57 23,004.43 28,940.24
02 02 AULAS - BIBLIOTECA - SALA DE LECTURA 273,433.99 8,789.30 60,626.38 65,058.83 35,316.03 22,304.85 32,693.58 - - 21,012.34 27,632.68
03 ADMINISTRACION - SALA DE COMPUTO - SALA MULTIUSOS 281,449.78 9,425.51 62,555.57 66,355.84 36,590.63 23,109.88 33,592.05 5,978.10 - 15,453.25 28,388.95
04 COCINA - COMEDOR - IMPRESIONES 132,782.20 4,427.31 32,396.30 28,503.43 18,379.29 11,607.98 17,883.87 - 5,666.25 6,315.50 7,602.28
05 SERVICIOS HIGIENICOS 46,033.83 1,145.80 20,916.42 7,922.27 2,066.90 1,305.41 4,804.42 - 1,912.63 3,405.69 2,554.29
06 MURO PERIMETRICO (L=82.40 m) 53,686.71 - - - 1,704.36 1,076.44 - - - 3,594.80 47,311.11
07 CISTERNA - TANQUE ELEVADO 9,763.51 - - - 2,645.99 1,671.15 4,005.51 259.40 - - 1,181.46
08 MOBILIARIO Y EQUIPAMIENTO 153,482.70 - - - - - - 30,696.54 76,741.35 46,044.81 -
09 CAPACITACION DOCENTE 21,120.00 - - - 4,314.84 2,725.16 7,040.00 7,040.00 - - -
MITIGACION AMBIENTAL
10 11,778.82 1,092.22 1,092.22 1,092.22 669.43 422.79 1,092.22 1,092.22 - 3,265.00 1,960.50
11 FLETE TERRESTRE 24,000.00 4,000.00 4,000.00 4,000.00 2,451.61 1,548.39 4,000.00 4,000.00 - - -
COSTO DIRECTO 54,697.50 258,087.37 238,578.02 143,358.76 90,542.36 149,022.29 53,791.83 89,045.80 122,095.82 145,571.51
AVANCE MENSUAL (%) 1,344,791.23 4.07% 19.19% 17.74% 10.66% 6.73% 11.08% 4.00% 6.62% 9.08% 10.82%
AVANCE ACUMULADO (%) 4.07% 23.26% 41.00% 51.66% 58.39% 69.47% 73.47% 80.10% 89.18% 100.00%

GASTOS GENERALES (8%) 107,650.00 4,375.80 20,646.99 19,086.24 11,468.70 7,243.39 11,921.78 4,303.35 7,123.66 9,767.67 11,645.72
UTILIDAD (8%) 107,650.00 4,375.80 20,646.99 19,086.24 11,468.70 7,243.39 11,921.78 4,303.35 7,123.66 9,767.67 11,645.72
SUBTOTAL 1,560,091.23 63,449.09 299,381.34 276,750.50 166,296.16 105,029.14 172,865.85 62,398.52 103,293.12 141,631.15 168,862.95
I.G.V (18%) 280,816.42 11,420.84 53,888.64 49,815.09 29,933.31 18,905.24 31,115.85 11,231.73 18,592.76 25,493.61 30,395.33
TOTAL PRESUPUESTADO 1,840,907.65 74,869.93 353,269.99 326,565.59 196,229.47 123,934.38 203,981.71 73,630.25 121,885.89 167,124.75 199,258.28

Anda mungkin juga menyukai