Martin Hursey is structural staff en- One of the elements that can ex-
Guesswork in gineer for the Pulp and Paper pedite connection design and
Connection Design Division of CRS Sirrine Engineers,
Inc. in Greenville, South Carolina,
detailing is for the fabricator to have
all the information needed to com-
- The Role of the where he is responsible for the ap- plete the task. Design engineers
proval of all structural steel design generate the information needed
Design Engineer in the division. During his 28 years by the fabricator and can provide
with Sirrine Mr. Hursey has been the information with their design if
involved in the design and checking a systematic approach is used.
of structures and their connections, This paper recognizes what is
in addition to developing design needed and presents a method for
aids and procedures. He is respon- the building design engineer to
sible for: purchasing steel, check- communicate to the fabricator
ing shop drawings, fabricator's design forces that were initially
connection design and expediting overlooked and difficult to retrieve
of fabricator's detailing. when needed by the fabricator.
Mr. Hursey attended Clemson
University and is a registered
professional engineer.
Martin Hursey
12-1
M. E. Hursey, P.E
Staff Engineer
CRSS Sirrine Engineers, Inc.
Greenville, SC
INTRODUCTION
For years fabricators' engineers have labored over which of the axial forces shown on
design drawings are transferred through the connection. If the design engineer directs
the fabricator to design for the larger forces shown, who then should pay for the costs of
these over-designed connections? When using this philosophy the connection will
sometimes be under-designed, as shown later in this paper. If the design engineer does
respond with the actual force to be used, it is usually after a time-consuming search. It
is less costly for the designer to recognize the force during design and to note it on the
drawings.
When the building design is electronically transferred from the design engineer to the
fabricator, the program should be written to recognize this phenomenon.
The purpose of this paper is to identify the building joints that need clarification and a
method of indicating the actual forces for which the connections must be designed.
FIGURE 1
Figure 1A, indicates a plan truss with south to north forces. The end diagonal is the
same for the truss in Figure 1B, with east to west forces. The reaction for the truss in
Figure 1B, is shown in Section A-A, where it is integrated into the vertical bracing
system at Elevation E. Preferably the truss diagonal and chord forces should be
indicated in plan and the truss reaction shown in elevation. Combining the two trusses
and indicating the larger member force as it would be on the design drawing, Figure 1C,
results in joints that cannot be balanced without knowing all the forces. Therefore, the
actual axial force to be incorporated into the connection design should be indicated as a
transfer force (TF). It need only point to the end of one of the two members on
opposite sides of the supporting column or beam so as not to clutter the drawing.
12-3
FIGURE 2
This is a simple illustration of how confusing the forces can become at a joint when they
are introduced from four directions and the structure is braced on only three sides,
Figure 2A. The combination of forces and of those combined at Column J-6 is shown in
Figure 2B.
FIGURE 3
When concrete forms are placed under the top beam flange all the beams together are
used to transfer the diaphragm forces to the steel. However, when form-deck is used the
method of transferring the forces from concrete to steel can be done in many different
ways. Figure 3A uses the concrete compressing on the columns, and Figure 3B uses
studs to make the transfer. Whichever avenue the design engineer chooses to transfer
diaphragm forces to the steel, it should be made clear with member forces and
connection transfer forces.
The transfer forces in Figure 3A are different on opposite sides of the column. Most are
the same on both sides of a support element (Figures 1C, 2B, and 3B). Additionally,
column web shear, yielding, crippling, and buckling at line 10 must be checked in Figure
3A, if the web is in the plane of the paper. The same column web may have to be
stiffened if the web is perpendicular to the paper's plane as shown.
FIGURE 4
The fabricator would not have difficulty in determining that 180 kips divided by four
column bases will result in each having 45 kips of shear. However, in more complicated
bracing schemes it is reassuring to know that the math is confirmed by the transfer
forces. Figure 4D indicates one method of utilizing the transfer force to determine the
weld needed from gusset to base plate.
12-4
2003 by American Institute of Steel Construction, Inc. All rights reserved.
This publication or any part thereof must not be reproduced in any form without permission of the publisher.
FIGURE 5
Also note that a heavier column section can be spliced-in at the top replacing the
original column section, if found to be less expensive than adding needed reinforcing.
12-5
2003 by American Institute of Steel Construction, Inc. All rights reserved.
This publication or any part thereof must not be reproduced in any form without permission of the publisher.
SOUTH TO NORTH FORCES
SECTION "A-A"
FIGURE 1A
12-6
2003 by American Institute of Steel Construction, Inc. All rights reserved.
This publication or any part thereof must not be reproduced in any form without permission of the publisher.
EAST TO WEST FORCES
SECTION "A-A"
FIGURE 1B
12-7
2003 by American Institute of Steel Construction, Inc. All rights reserved.
This publication or any part thereof must not be reproduced in any form without permission of the publisher.
COMBINED FORCES
PARTIAL PLAN @ ELEVATION "E"
SECTION "A-A"
FIGURE 1C
12-8
2003 by American Institute of Steel Construction, Inc. All rights reserved.
This publication or any part thereof must not be reproduced in any form without permission of the publisher.
COLUMN A-2
FIGURE 1D
12-9
2003 by American Institute of Steel Construction, Inc. All rights reserved.
This publication or any part thereof must not be reproduced in any form without permission of the publisher.
FIGURE 2A
12-10
2003 by American Institute of Steel Construction, Inc. All rights reserved.
This publication or any part thereof must not be reproduced in any form without permission of the publisher.
EAST TO WEST FORCES WEST TO EAST FORCES
COMBINED FORCES
COLUMN J-6
FIGURE 2B
12-11
2003 by American Institute of Steel Construction, Inc. All rights reserved.
This publication or any part thereof must not be reproduced in any form without permission of the publisher.
RIGHT TO LEFT FORCES
FIGURE 3A
12-12
2003 by American Institute of Steel Construction, Inc. All rights reserved.
This publication or any part thereof must not be reproduced in any form without permission of the publisher.
LEFT TO RIGHT FORCES
FIGURE 4A
12-13
2003 by American Institute of Steel Construction, Inc. All rights reserved.
This publication or any part thereof must not be reproduced in any form without permission of the publisher.
COMBINED FORCES
FIGURE 4C
FIGURE 4D
12-14
2003 by American Institute of Steel Construction, Inc. All rights reserved.
This publication or any part thereof must not be reproduced in any form without permission of the publisher.
FIGURE 5
12-15
2003 by American Institute of Steel Construction, Inc. All rights reserved.
This publication or any part thereof must not be reproduced in any form without permission of the publisher.