AGENDA COORDINATION MEETING NO.

02 BETWEEN ROYAL COMMISSION (RC)


AND CHINA HARBOUR ENGINEEING ARABIA CO. LTD. (CHEC)

Contract Title: Construction of Interchange Bridges at Shareh Al-Mina & By-pass (Phase-1)
Contract No.: PIC R-7507
NTP Date: 05 Jan 2015
EOC Date: 04 Feb 2017
Date: 4 Feb 2015 Time: 1:30 Page: 1 of 3
.
Place: Jabriah 8 Site Office - Conference Room File No.

_____________________________________________________________________________________

PARTICULARS ACTION BY TARGET COMPL.


DATE/REMARKS

1. Health ,Safety and Environment Issues

1.1. Submission of CVS Contractor safety CHEC Not acceptable. To be re-submitted


representative ( Safety engineer,
Scaffolding inspector, safety officer) dedicated.
1.2. Submit fencing layout. CHEC To be submitted
1.3. Submit project signboard and safety signages lay-out CHEC To be submitted
1.4. Personal protective equipment (PPE) CHEC Information
1.5. Submission of RFI on safety inspection CHEC As Required
1.6. Submission of certification documents for power CHEC To be submitted
and heavy equip. operators

2. Contractually Required/Administrative/Non Technical


Submittals
2.1 Submission of organizational chart & CVs of key CHEC Not acceptable. To be re-submitted
and discipline personal for Structural/Civil, Mechanical,
Electrical, Architectural, QA/QC
2.2. List of Requirement :

Item / Description submitted Not Submitted Remarks


To provide w/in 10 days of NTA
Performance security Article 9 & SC-36
Yanbu chamber of commerce membership SC-50
Not less than 10 days before commencing of work
Insurance certificates SC-42
To provide w/in 10 days after NTP
Accommodations & Messing SC-43
To provide w/in 30 days after NTP
Safety Plan For approval by RC-Safety Group
Fire Protection & Prevention Plan For approval by RC-Safety
First Aid Plan For approval by RC-HPD
Sanitation Plan For approval by RC-Sanitation Dep.
Security Plan For approval by RC-Safety
Monthly progress report 1033
Fixed Price Breakdown for Payments For approval by RC-F&B Dep.
Saudi Air Usage For approval by CSG
Preliminary Schedule 1033
Product Listing 1610
Expediting Plan 1610
To provide w/in 45 days after NTP
Procedures Manual 1030
To provide w/in 60 days after NTP
Inspection and test plan SC-21
Schedule of Shop Drawing Submittal 1340
Resubmission of QC/QA Plan & Reports For approval by CSG
Logistics Plan 1610
Independent testing laboratory Approved
Cash flow plan 1033
Contract Schedule 1030
To provide w/in 90 days after NTP
List of employees (Saudis) Ministry of labor decision No. 6773
Cross Check between IFC and P-2 table

CHEC shall provide all contractual requirement and deliverables as shown in specification
During specific date. Next meeting contractor should have a plan for all submittal.

3.0 Material and Equipment Technical Submittals/Shop Drawings:


3.1 Civil / Structural Works
3.1.1 shop drawing for structural/ Civil drawing. CHEC before commencing of work
3.1.2 par bending schedule CHEC
3.2 Electrical Works
3.2.1 Revise drawing will issued for transformer RC
and revised Specs for medium voltage.
3.2.2 personal for training for authorized permit receiver. CHEC
- General for all discipline: CHEC must take approval
ITP for each discipline separately. CHEC before commencing of work

4.0 Issues Concern, Problems and Resolutions


4.1. Shop drawing for new detour plan.
4.1.1 RC Const. submitted shop drawing to Engineering Dep. RC
for review and approval.
4.2 Request for the latest drawings with signature and stamp RC
4.2.1 RC Const. submit letter to Engineering Dep.
to signature and stamp it .However, this issues
is not stop CHEC to start.
4.3 Request for the as-built drawing of existing utilities. RC
4.3.1 RC Const. submit letter to Urban planning Dep.
to provide the as-built drawing to use.
4.3 Status of CHEC Excavation Permit. CHEC
4.4 Accommodation request for Management, Staff & Labor CHEC

The next Coordination Meeting to be held at RC residential section conference room as determined
during this meeting.

PREPARED BY : _________________
Engr. Yasser AL-BOGAMI
Coordinator