Contract Title: Construction of Interchange Bridges at Shareh Al-Mina & By-pass (Phase-1)
Contract No.: PIC R-7507
NTP Date: 05 Jan 2015
EOC Date: 04 Feb 2017
Date: 4 Feb 2015 Time: 1:30 Page: 1 of 3
.
Place: Jabriah 8 Site Office - Conference Room File No.
_____________________________________________________________________________________
CHEC shall provide all contractual requirement and deliverables as shown in specification
During specific date. Next meeting contractor should have a plan for all submittal.
The next Coordination Meeting to be held at RC residential section conference room as determined
during this meeting.
PREPARED BY : _________________
Engr. Yasser AL-BOGAMI
Coordinator