REPORT ON COORDINATION MEETING No.

3 BETWEEN ROYAL
COMMISSION (RC)
AND CHINA HARBOUR ENGINEEING ARABIA CO. LTD. (CHEC)

Contract Title: Construction of Interchange Bridges at Shareh Al-Mina & By-pass (Phase-1)
Contract No.: PIC R-7507
NTP Date: 05 Jan 2015

EOC Date: 04 Feb 2017

Date: 27 May 2015 Time: 13:30 Page: 1 of 3

Place: Jabriah 8 Site Office - Conference Room File No.: 4.3

ATTENDEES :

Royal Commission CHEC/Contractor

1. Engr. Basil Saghorchi - SRCM 1. Yang Junjia PM


2. Engr. Rodolfo C. Suaco RCE (Civil) 2. Wang Xu HSE
3. Engr. Jawed Saghir - RCE (Electrical) 3. Ziehow HSE Engineer
4. Engr. Mohammed Khan RC-Safety group 4. Fan Zhi - Planner
5.Qiao Peiming Civil Engr.
6. Bushra Adam QC Manager
_____________________________________________________________________________________

PARTICULARS ACTION BY TARGET COMPL.


DATE/REMARKS
1. Health ,Safety and Environment Issues

1.1. Submission of CVS Contractor safety CHEC For Info


representative ( Safety Manager, Safety engineer,
Scaffolding inspector, safety officer) are approved
1.2. Project signboard and safety signages lay-out CHEC For info
are submitted including the installation of
remaining sign board.
1.3. Personal protective equipment (PPE) CHEC As Always
1.4. Submission of RFI on safety inspection CHEC As Required
1.5. House Keeping to be an everyday affair CHEC As Always
1.6. Submission of certification documents for power CHEC As Required
and heavy equipment operators submitted.
However, RC Safety has reminded CHEC that
heavy equipment operators must secure
a Saudi License as per Saudi Government
requirements before to operate equipment.
1.7. Detour plan to be provided by warning sign and CHEC As Required
Safety barricade for precaution.
1.8 CHEC must always to sprinkling water the site area to CHEC As Always
control or eliminate the dust.
REPORT ON COORDINATION MEETING No. 3 BETWEEN ROYAL
COMMISSION (RC)
AND CHINA HARBOUR ENGINEEING ARABIA CO. LTD. (CHEC)

2. Contractually Required/Administrative/Non-Technical Submittals

2.1 Submission of organizational chart & CVs of key CHEC 28 May 2015
Personnel are already submitted and approved.
CHEC to submit the organizational chart with approved
names of key personnels on key positions

2.2. List of Requirement:

submitte Not
Item / Description Remarks
d Submitted
To provide w/in 10 days of NTA
Performance security Article 9 & SC-36
Yanbu chamber of commerce SC-50
membership
Not less than 10 days before commencing of work
Insurance certificates Approved
To provide w/in 10 days after NTP
Accommodations & Messing SC-43
To provide w/in 30 days after NTP
Safety Plan Approved
Fire Protection & Prevention Approved
Plan
First Aid Plan Under Review of Health Service
Program
Sanitation Plan Under Review of RC-Sanitation
Dep.
Security Plan Approved
Monthly progress report Month of May under preparation
Fixed Price Breakdown for Approved
Payments
Saudi Air Usage For RC Record
Preliminary Schedule Approved with minor comments
Product Listing Approved
Expediting Plan Under CSG Review
To provide w/in 45 days after NTP
Procedures Manual Approved
To provide w/in 60 days after NTP
Inspection and test plan SC-21, Submission In Progress
Schedule of Shop Drawing 1340, Submission In Progress
Submittal
Resubmission of QC/QA Plan Approved
& Reports
Logistics Plan 1610, Approved
Independent testing laboratory Approved
Cash flow plan 1033, Submitted
REPORT ON COORDINATION MEETING No. 3 BETWEEN ROYAL
COMMISSION (RC)
AND CHINA HARBOUR ENGINEEING ARABIA CO. LTD. (CHEC)
Contract Schedule 1030, Under PMD Review
To provide w/in 90 days after NTP
List of employees (Saudis) Submitted
Cross Check between IFC and Under review if RC Engineering
P-2 table

CHEC shall submit all contractual requirement and deliverables as shown in the specification on specific
date. Contractor should follow the specific schedule and plan of all the submittals to avoid delay in project
schedule and progress .

3.0 Material and Equipment Technical Submittals/Shop Drawings:


3.1 Civil / Structural Works
3.1.1 Shop drawing for structural/ Civil drawing under CHEC As Required
Preparation and submission
3.1.2 Bar bending schedule under preparation CHEC As Required
3.1.3 Soil inspection reports and recommendations RC For Info
under review. RC to follow up
3.2 Electrical Works
3.2.1 Personnel for training of authorized permit CHEC As Required
receiver is approved, Materials submittal
medium and low voltage cable is under
preparation
- General for all discipline: CHEC must secure CHEC As Required
approval of ITPs for each discipline individually.
This is a prerequisite for commencing the work

4.0 Project Schedule Issues

a. Monthly Schedule Target : 7.20% Actual Accomplishment : 5.50%

b. Manpower On site.

Key personnel = 14 Nos. Saudi National = 0 Nos. Skilled workers = 45 Nos.

TOTAL MANPOWER = 59 Nos.

5.0 Issues Concern, Problems and Resolutions


5.1 Shop drawing for new detour plan was reviewed CHEC As Required
by RC Engineering and acceptable with comments,
CHEC to submit permit to Road Department in
phase by phase request as agreed during joint
meeting with Road department. CHEC reported
that phase 1 is already signed by Industrial safety
and security department
5.2 Request for the latest drawings with signature For Record
and stamp has already been transmitted
CHEC
5.3 Cross checking of imported filling materials RC As Required
REPORT ON COORDINATION MEETING No. 3 BETWEEN ROYAL
COMMISSION (RC)
AND CHINA HARBOUR ENGINEEING ARABIA CO. LTD. (CHEC)
quantity is under RC Engineering review. RC
construction to follow up
5.4 The Royal Commission had informed CHEC CHEC As Required
that use of excavated surplus materials
as fill materials where such material meets
specified criteria for intended use shall not
be considered as imported filling. RC advised
CHEC not to include the volume of excavated
materials used as fill materials to the volume
of imported fill materials in their calculation.
This was clearly specified in pay item 2.01
(Excavation to lower grade levels).
CHEC to study.
5.5 RC has reminded CHEC that the remaining CHEC As Required
RC field office requirements i.e. RC field office,
ten (10) slots parking sunshade stated in Section
01590 are part of the contract and CHEC must
provide. RC will provide information for the
location of RC field office/parking shade later.
5.6 Relocation of existing fire hydrant already submitted CHEC As Required
to MARAFIQ for approval. RC to follow up
5.7 Existing Sewer Manhole are to be disposed by CHEC As Required
CHEC in approved designated areas by RC.

6.0 On Site Activities


6.1 CHEC to submit on next meeting

7.0 Ongoing/Planned/Look Ahead Activities

- 3 Weeks Look Ahead Schedule to be submitted in the next meeting.

The next Coordination Meeting will be held on 10 June 2015 (Wednesday) at 14:00 at Haii Al Jabriah
8 project Site Office.

PREPARED BY: _____________________


Engr. Rodolfo C. Suaco
RCE Civil/Structural

REPORT CONCURRED BY:

______________________ __________________
Engr. Basil Saghorchi Engr. Yang Junjia
Senior Resident Construction Manager CHEC Project Manager

cc: All attendees


Manager, Residential Section
CA (PIC R-7507)
File No 4.3