3 BETWEEN ROYAL
COMMISSION (RC)
AND CHINA HARBOUR ENGINEEING ARABIA CO. LTD. (CHEC)
Contract Title: Construction of Interchange Bridges at Shareh Al-Mina & By-pass (Phase-1)
Contract No.: PIC R-7507
NTP Date: 05 Jan 2015
ATTENDEES :
2.1 Submission of organizational chart & CVs of key CHEC 28 May 2015
Personnel are already submitted and approved.
CHEC to submit the organizational chart with approved
names of key personnels on key positions
submitte Not
Item / Description Remarks
d Submitted
To provide w/in 10 days of NTA
Performance security Article 9 & SC-36
Yanbu chamber of commerce SC-50
membership
Not less than 10 days before commencing of work
Insurance certificates Approved
To provide w/in 10 days after NTP
Accommodations & Messing SC-43
To provide w/in 30 days after NTP
Safety Plan Approved
Fire Protection & Prevention Approved
Plan
First Aid Plan Under Review of Health Service
Program
Sanitation Plan Under Review of RC-Sanitation
Dep.
Security Plan Approved
Monthly progress report Month of May under preparation
Fixed Price Breakdown for Approved
Payments
Saudi Air Usage For RC Record
Preliminary Schedule Approved with minor comments
Product Listing Approved
Expediting Plan Under CSG Review
To provide w/in 45 days after NTP
Procedures Manual Approved
To provide w/in 60 days after NTP
Inspection and test plan SC-21, Submission In Progress
Schedule of Shop Drawing 1340, Submission In Progress
Submittal
Resubmission of QC/QA Plan Approved
& Reports
Logistics Plan 1610, Approved
Independent testing laboratory Approved
Cash flow plan 1033, Submitted
REPORT ON COORDINATION MEETING No. 3 BETWEEN ROYAL
COMMISSION (RC)
AND CHINA HARBOUR ENGINEEING ARABIA CO. LTD. (CHEC)
Contract Schedule 1030, Under PMD Review
To provide w/in 90 days after NTP
List of employees (Saudis) Submitted
Cross Check between IFC and Under review if RC Engineering
P-2 table
CHEC shall submit all contractual requirement and deliverables as shown in the specification on specific
date. Contractor should follow the specific schedule and plan of all the submittals to avoid delay in project
schedule and progress .
b. Manpower On site.
The next Coordination Meeting will be held on 10 June 2015 (Wednesday) at 14:00 at Haii Al Jabriah
8 project Site Office.
______________________ __________________
Engr. Basil Saghorchi Engr. Yang Junjia
Senior Resident Construction Manager CHEC Project Manager