Project Title: Proposed warehouse renovation

Location: Reparo road, Caloocan City


Owner: Mr. Micheal Siytauco

Breakdown of Cost of Work

ITEM QTY UNIT

I. SITE PREPARATION
a. Demolish wall partition 125.67 sq. m
b. Demolish stairs 12.83 sq. m

II. STEEL WORKS


a. Mezzanine Framing 191.36 sq. m
b. Steel Matting wall partition 162.72 sq. m
c. Stairs 7.90 sq. m
d. Steel Ramp 11.25 sq. m
e. Steel sliding gate 84.40 sq. m

III. MASONRY WORKS


a. 100mm thk CHB 60.33 sq. m
b. 150mm thk CHB 11.73 sq. m
c. 10mm X 6.00m Reinforcement 38.00 pcs
d. Plastering 144.12 sq. m

IV. DOORS
a. PVC Door 4.00 pcs
b. Glass Door 1.00 pcs

V. GLASS WORKS
a. Glass wall partition 8.91 sq. m

VI. FINISHING WORKS


a. Interior wall surface 120.66 sq. m
b. Exterior wall surface 23.46 sq.m
c. Ceiling 16.84 sq.m
d. Floor tile 16.84 sq.m
e. Wall tile 38.28 sq.m

VII. ROOFING
a. GA. 24 pre-painted roofing 142.11 sq. m
b. Polycarbonate roofing 62.60 sq.m

VIII. ELECTRICAL WORKS as per actual


IX. PLUMBING WORKS
a. Plumbing Layout 19.05 unit
b. Fixture Fittings 19.05 unit
c. Urinal fixture unit 3.00 pcs
d. Lavatory fixture unit 4.00 pcs
e. Watercloset fixture unit 5.00 pcs
f. Kitchen Sink fixture unit 2.00 pcs
Project Title: CAFE RENOVATION
Location: FEU RECTO

Breakdown of Cost of Work

ITEM QTY UNIT COST SUB-TOTAL AMOUNT

I. GENERAL REQUIREMENTS
a. Permits 1 lot AS PER OWNER
b. Mobilization 1 lot 25,000.00 25,000.00
c. Supervision 1 lot 25,000.00 25,000.00
d. Power & Water 1 lot

II. SITE PREPARATION


a. Clearing & Hauling of Debris 5.00 trucks 1,300.00 6,500.00

III FINISHING WORKS


a. Interior wall paint 430.22 sq. m 230.00 98,950.60

IV ELECTRICAL WORKS as per actual

V DEMOBILIZATION
a. General cleaning & clearing 1.00 lot 15,000.00 15,000.00
b. Hauling 1.00 lot 15,000.00 15,000.00

SUBTOTAL COST 185,450.60


LABOR COST 55,635.18

TOTAL COST 241,085.78