Anda di halaman 1dari 9

43 Demolition

T R Mills Ceng, MICE, FIDE


Chartered Engineer

Contents
43.1 Introduction 43/3 43.5 Demolition blasting 43/8

43.2 Organization and planning 43/3 43.6 Preferred methods of demolition 43/8
43.2.1 Insurance 43/3
43.2.2 Surveys and method statements 43/4 43.7 Salvage and recycling 43/9
43.2.3 Shoring 43/4
43.8 Health and safety 43/9
43.2.4 Weatherproofing 43/4
43.8.1 Fire and explosion risks 43/10
43.2.5 Hoardings 43/4
43.9 Environmental matters 43/10
43.3 Demolition by hand 43/5
43.3.1 Preweakening 43/5 43.10 Future developments 43/10
43.4 Mechanical demolition 43/5 References 43/10
43.4.1 Wire-rope pulling 43/6
43.4.2 Hydraulic excavators and tractor
shovels 43/6
43.4.3 Balling machines 43/6
43.4.4 Pusher arm 43/6
43.4.5 Impact breakers 43/7
43.4.6 Hydraulic shears 43/7
43.4.7 Heavy-duty grabs 43/7
43.4.8 Diamond drilling and sawing 43/7
43.4.9 Thermic lancing 43/7
43.4.10 Expanding cement 43/7
43.4.11 Cutting with water jets 43/7
43.4.12 Hydraulic bursting 43/8

This page has been reformatted by Knovel to provide easier navigation.


43.1 Introduction Where original drawings exist an allowance must be made for
alterations and additions which have not been formally
The demolition industry has its origin among those small recorded.
contractors who specialized in the removal and resale of archi- Parts of the premises which are inaccessible should be care-
tectural items, building materials and structural components. In fully opened up. It should not be a prospective contractor's
the past, their operations were labour-intensive and time-con- responsibility to survey below the surface; indeed, the practi-
suming and often the salvaged items remained on their hands cality of a number of such contractors bringing equipment on to
for considerable periods. a site which is not formally in their responsibility normally
Development over the years has determined that demolition precludes this.
contractors organize their work and equip themselves to meet The likelihood of toxic or hazardous material either being
critical programmes. The size of firms undertaking demolition built in to the structure or arising from previous use should be
and associated fringe activities, such as excavation and tempor- assessed and the information forwarded to tenderers. It may be
ary works, varies from organizations offering a complete pack- prudent to decontaminate premises prior to the start of demoli-
age, through to small firms undertaking specialist works such as tion works or carefully phase a programme so that demolition
concrete-cutting or demolition blasting. does not produce a hazardous environment by scattering resi-
The capability of contractors varies from those thoroughly dues. The discovery of toxic and hazardous material at a late
organized with managerial and technical facilities backing up a stage can have the serious result of closing down work until
skilled labour force, down to those who work in excess of their residues are removed.
capacity to the detriment of their clients in particular and the The specification should state, and drawings should clearly
industry in general. indicate, the levels to which buildings are to be demolished. If
It is important that demolition contracts or the demolition ground slabs and foundations are to be removed, approximate
phase of major projects, should receive the same careful con- quantities with provisional sums for excesses, or a schedule of
sideration as those for rebuilding and civil engineering. rates, should be included for an item which is basically excava-
Much can be done to eliminate delays to works by ensuring tion. Any architectural features or sections of the building which
that obligations to third parties and statutory undertakings are are to be retained should be defined clearly and removed early in
negotiated before commencing work. the job if possible.
Details of the buildings or structures to be demolished or Once the decision to demolish has been taken, there are many
altered, together with a careful assessment of the restraints matters that can be put in hand alongside preparation of
imposed by location, should be discussed by clients and pros- contract documents.
pective contractors at an early stage to permit realistic and fair The so-called party wall awards, with their very specific
tendering. details of what can and cannot be done to adjacent properties,
'Demolition' embraces a wide spectrum of activities - from need considerable time for practical assessment and preparation
simple cottage demolition to the dismantling and removal of of documents. Whilst it may be impossible to agree fully the
industrial complexes. No broad boundaries are found between extent of the party wall award prior to opening up and exposing
demolition styles in different localities. Certain types of struc- an adjacent property, it is better to have made some progress,
ture lend themselves towards a preferred method, but of the thus allowing a demolition contractor to work normally and
many techniques available few can be applied individually and logically rather than be prohibited from approaching a site
most successful jobs employ a combination of one or more boundary.
methods. The removal of statutory undertakings' equipment should be
organized as soon as the premises become vacant, in order to
avoid delays to the works and accidents caused by live services.
43.2 Organization and planning Demolition work may involve the diversion or protection of
services where there is a wayleave across the site and such
The person inviting tenders or negotiating for demolition work matters should be considered early, as sometimes extremely
should ensure that it will be undertaken by experienced contrac- complex planning has to be done to avoid disconnecting adjoin-
tors who have an awareness of the problems likely to be ing premises.
encountered on and off the site. In industrial premises which have existed harmoniously with
Forms of contract normally used for building or civil engi- their neighbours, demolition, even over a short time, can cause
neering may consist of documentation made unnecessarily com- concern to residents, or hazards to adjoining premises. There
plex by alterations, omissions and additions. A simple form of needs to be liaison between the client and concerned neighbours
contract such as that published by the National Federation of in order that prospective contractors are aware of restraints
Demolition Contractors in London may be acceptable. upon their methods of work.
The specification should be as simple as possible while
adequately defining the work required. Items such as shoring,
weatherproofing and accommodation works may be impossible
to determine until parts of the redundant building or structure 43.2.1 Insurance
have been removed and assessments made with the professional Clients and their professional advisers should make certain that
adviser(s) appointed by owners of the adjoining premises. specified insurance requirements are adequate, but at the same
Where this is the case, 'provisional sums' should be included. time realistic, for the risks arising from their projects.
In partial demolition or refurbishment, the structural detail Policies on behalf of the client, the contractor and sometimes
may have a critical effect on the proposals. Even though original jointly, should be in force prior to commencement of the works.
drawings may exist, it is prudent to open up relevant parts of the The amount of cover required can vary considerably, depen-
superstructure to confirm what has, in fact, been built. This dent upon location. Demolition work on an active mainline rail
preliminary work will often be needed by the consulting engi- terminal, for example, would require considerably more cover
neers charged with modifying the structure, but in any event the than work on a remote and disused factory premises.
structural survey should be done prior to inviting tenders for Employer's liability insurance is a statutory requirement, the
demolition in order that prospective contractors may have the premium reflecting the hazardous nature of demolition work
benefit of seeing the structural detail. and the record of the contractor.
43.2.2 Surveys and method statements attendant difficulties of preparing the foundation block and
The object of a demolition survey is to establish sufficient detail handling the sections in confined spaces.
about the premises to allow a decision on the method of When a free area of land is required, and where there is a
demolition and to identify any restraints affecting proposed convenient support, a flying shore can be connected horizont-
activities on the site. ally to an adjacent and sufficiently robust premises, provided the
Problems may arise due to characteristics of the building or owner of the supporting building agrees.
structure, or to the previous use of the premises or the location. On flying shores of long spans a central prop may be
Drawings of the building are not always available, and even necessary and, although this to some extent defeats the object of
where they are, the survey should be comprehensive enough to obtaining a clear area, it can be less inconvenient in the centre of
determine the extent of alterations from, and additions to, the a site, where it may interfere only with floor construction, than
original plan. raking shores at the edge, interfering with walls.
The sequence of building or erection, together with an Raking and flying shores are inserted to prevent a sideways
assessment of any temporary works or equipment used, can be movement of a wall. It is sometimes necessary to effect vertical
usefully compared with the proposals for demolition. support to a wall, either because its foundations have failed, or
The need to provide shoring either on adjacent premises or it is to be underpinned, or is to have additional openings made
within the structure being demolished should emerge from the in it.
survey; also, the need for weatherproofing either temporary or In these circumstances, needle shores, in which short hori-
permanent (see sections 43.2.3 and 43.2.4). zontal members are placed through a wall and given their own
On any type of building or structure, the condition can, to a support, are used. Vertical support is referred to as 'dead
greater or lesser extent, determine the method of demolition to shoring'.
be used. The loading on the shoring must be assessed and the system
Traditional brick, masonry and timber structures left unat- designed and detailed in a manner which takes into account the
tended and open to the atmosphere, may have deteriorated to circumstances of its erection and later dismantling.
the extent that they cannot be relied upon to provide safe access. Shoring was traditionally of timber, but examples from
Industrial uses producing corrosive atmospheres and long- scaffold tubes and fittings, and from fabricated steelwork are
term lack of maintenance may have affected structural steel- more common today, with the use of traditional carpentry skills
work, particularly connections, to the extent that preweakening becoming uneconomical.
of a structure would be hazardous. For dealing with dangerous structures, say a building which
Persons undertaking demolition surveys should be aware of, has been hit by a vehicle or suffered a severe fire, shores made
and experienced in, finding such conditions. from scaffolding are normally used, often erected not by the
In addition to surveying the building, the adjoining buildings demolition contractor but by scaffolding companies who have
should be assessed in terms of structure and equipment con- arrangements with the authorities for rapid turnout to deal with
tained to determine any restraints. For example, in urban areas such emergencies.
the increase in use of computers, which are very sensitive to For retaining facades, scaffolds may be used, but fabricated
vibration, has added to the problems traditionally arising from steelwork providing quick erection and a compact design is
dust and vibration. popular, particularly in congested city areas.
Following the demolition survey, a detailed method state-
ment should be prepared prior to the start of work. 43.2.4 Weatherproofing
The presentation of this statement has been widely debated:
BS 6187:1982 Code of practice for demolition* recommends that Walls previously protected by buildings which are being demol-
a programme should be drawn up in which the proposed ished, will quickly absorb moisture and deteriorate if weather-
sequence and the method of operation is indicated clearly. The proofing is not provided.
Health and Safety Executive Guidance Note GS29/12 goes Walls exposed on a long-term basis can be rendered or
further by advising that a detailed method statement should skimmed with brickwork if this is desirable from a visual
identify problems and their solutions and form a reference for viewpoint. Walls in good condition can be treated with water-
site supervision. repellent compounds.
The degree of difficulty in the work must determine the detail It is more usual for bitumen or polythene sheeting to be used
on the method statement, but in any event, it must be in terms on a temporary basis to stand until the new adjacent walls
that can be understood by the supervisor and labour force. It provide protection. Such sheeting must be fixed to the wall with
may be written with annotated drawings, or instructions may be vertical and horizontal battens in a regular pattern and in a
painted on to the structure. workmanlike manner if it is not to be torn by the wind and
become ineffective. It is both annoying and costly to have to
return to repair small areas of weatherproofing as the access
from the original building may not be available and scaffolds or
43.2.3 Shoring
elevating platforms will have to be obtained. The sheeting must
The need for shoring-up adjacent buildings or, on occasions, the be overlapped and horizontal faces must be weatherproofed to
temporary shoring of the structure being demolished, should be ensure that the arrangement is completely watertight.
investigated prior to the start of demolition. In cases where this
is not possible a procedure for checking the requirements as the
job progresses should be formalized. 43.2.5 Hoardings
The simplest approach is to leave parts of adjacent walls or It is usual for the contractor to provide a hoarding, sometimes
part of the structural frame as buttresses if they are in an to his own design, sometimes to that of others.
acceptable condition - provided their retention would not As a precaution against trespassers, it is in the contractor's
hinder subsequent building. best interests to secure the site at all times, but this may not be
If it is decided that raking shores are necessary, it is some- practicable, particularly during the early stages of work.
times acceptable to erect them after demolition, but if the The provision of a hoarding can be a substantial item.
durability of the exposed wall is suspect in the short term, the Erection should be done by experienced personnel in order to
shores may have to be inserted prior to demolition, with all the ensure that it will resist overturning by the wind, and be robust
enough to resist the ravages of subsequent building activity explosive needed or to form 'hinges' to encourage structures to
where it will be cut about to complete sight lines or have panels collapse in a predictable manner, thus allowing economic re-
removed to give access for materials. moval of debris.
Hoardings should not go across manholes and valve covers. There is argument about the relationship between the need
Any openings or doors which are at ground level should not for expert engineering advice and reliance on experience and
open on to open basements or trial holes. intuition to decide the style of preweakening.
It is accepted that most structures, when relieved of sheeting,
industrial plant and bulk material, can be considerably pre-
43.3 Demolition by hand weakened. Most engineered solutions use simplifications of the
structure to arrive at the selected procedures.
Hand demolition involves workmen using pneumatic or hand There is a school of thought which encourages the retention
tools to remove part of a building or structure prior to comple- of loads at height in order to provoke movement once the
tion by mechanical means (Figure 43.1), or all of the structure structure is, by whatever means, made unstable. This method
where mechanical means cannot be used. requires very careful analysis and supervision.
This work may involve opening up floors to allow debris to be Notwithstanding an empirical or an engineered approach
dropped to the lowest hard level. Opening up must not be after any surplus load has been removed, a number of cuts will
allowed to make the building unstable and material must be be made to finally preweaken the structure.
cleared to avoid lateral pressure on lower walls. Cuts that allow members to 'sit', or 'hinge', have characteris-
If material is being dropped inside, it will be deflected a tic styles, but great care is required to monitor movement as
considerable distance if it hits other parts of the structure. preweakening progresses to ensure that the structure is behaving
Windows and apertures should be boarded up, or sheeting as intended and not about to collapse prematurely from inbuilt
erected, to prevent debris being ejected outside. stresses, wind or impact.
Suitable working platforms must be provided where work Failure of structures to respond to the final drama of remov-
cannot be done safely from the structure. These can be formed ing the key parts can produce extremely complex problems
from scaffolding or the use of man-riding skips or hydraulic involving time and expense.
elevating platforms.
Scaffolds should be sheeted and fans provided over adjacent
public areas. As the height of the building is reduced the scaffold
should follow; ties should not be removed because this would
render the scaffold unsafe. 43.4 Mechanical demolition
It is normally preferable to demolish floor by floor. To
preserve adjacent properties, shoring may have to be built either There are comparatively few machines which are specifically
before or during demolition. The removal of roofs will normally designed for demolition, equipment generally being obtained
be done by hand prior to other activities. through the normal plant markets. With few exceptions, demoli-
tion attachments to base machines designed primarily for exca-
vation and material handling are used.
43.3.1 Preweakening Demolition duties impose considerable wear and tear on
Preweakening is the removal, cutting or partial cutting of machinery. Good maintenance procedures therefore need to be
structural members as an activity prior to final collapse being provided if the machinery is not to deterioriate until it becomes
achieved by some other means. unsafe and beyond economic repair.
The preweakening of structures has for many years been a Some contractors elect to improve the durability of their
preliminary to wire-rope-pulling, but more recently the use of machinery by fitting heavy-duty buckets and protection to cabs
explosives has involved preweakening to reduce the amount of and engines to guard against damage by debris.

Figure 43.1 Manual demolition work using pneumatic breakers


on a city centre roof
43.4.1 Wire-rope pulling steelwork, trunking and fittings) which is unsaleable and which
This apparently simple and effective method of demolition may need sorting prior to dumping.
requires careful planning and organization if it is to be success-
ful, especially when used on tall structures. 43.4.3 Balling machines
Static winches or vehicle recovery trucks may be used to effect
the pull, as may the drag rope of an excavator or a winch 'dozer. This well-publicized method is popular with demolition contrac-
The distances available must be such that there is no risk of tors because it is economic, quick and safe, provided certain
the resultant debris falling or being projected on to the winch or simple precautions are taken.
pulling vehicle. Balling machines need space in which to operate and should
The pulling ropes must be of steel wire, be in good condition be outside rather than within the confines of the building being
and have proper fittings at their ends. demolished (Figure 43.2).
It may be necessary to remove roofs by hand prior to balling,
Workmen and spectators must be well clear of the area in
which a breaking rope may whip. and it is sometimes necessary to remove storeys to bring a
More than one rope should be attached in advance, in order building within the capacity of a balling machine. Areas of
to avoid the risk of approaching the structure which may be floors may need to be removed to facilitate the dropping of
unstable or partially collapsed after the first pull. debris.
The load should be applied gradually, and it will become If vibration is likely to be a problem, a split should be made
between the building being demolished and adjacent properties.
apparent at an early stage if the equipment has sufficient pulling
capacity. The demolition ball should generally not be allowed to swing
free on the hoist rope, but should at all times be tethered by a
In the event that it has been decided to preweaken the
structure in advance of ordering final collapse by pulling, expert drag-rope. In order to bring the ball into contact with the
building, it may be dropped, pulled and released in line with the
engineering advice may be necessary to ensure that structural
jib, or slewed. Slewing the jib is particularly hazardous as an
stability is retained. An unsuccessful pull may weaken a struc-
ture. excessive slew angle, rotational acceleration, and braking can
impose excessive stresses encouraging jib failures.
Balling at heights in excess of 30 m, known as 'high balling' is
now undertaken regularly. Great skill and experience is required
43.4.2 Hydraulic excavators and tractor shovels
for this work, and it does not follow that a good crane driver is a
Most demolition sites will eventually reach the stage where a good balling-machine operator.
hydraulic excavator or a tractor shovel will be used for digging It is important to ensure that the ball does not become
out basements or loading debris. trapped or that the machine becomes overloaded by sudden
These machines may be used successfully for pulling or collapse of large parts of the structure. A technique of 'little-
pushing over low-level buildings by using their buckets. Brick and-often' is preferred.
and masonry structures will collapse readily, but steelwork may Many recommendations concerning the use of balling
need some preweakening if the section resists the capacity of the machines and other mechanical methods are given in BS
machine. 6187:1982.'
A Ripper tooth attachment can be used to drag down low-
level steelwork and industrial plant.
When adopting this approach, there is a tendency to start on 43.4.4 Pusher arm
the structure before the building has been properly stripped out, These devices were formally rigid arms fitted to hydraulic
the result being mixed debris (containing brickwork, masonry, excavators which exerted a horizontal thrust to demolish walls

Figure 43.2 A balling machine working in a confined area


or structures. More recently, a telescopic demolition arm allow-
ing a pushing or pulling motion has become available, consider-
ably extending the adaptability of this method.
Some preparation may be necessary, either in removing the
roof, reducing the height or isolating the building from adjacent
premises. The building should be attacked in a logical manner
without leaving slender sections free-standing. Walls should not
be pushed more than 600 mm below their top level and, once
again, a 'little-and-often' technique is required both to bring the
building down safely and avoid the necessity of breaking-up
large slabs of brickwork or masonry as a secondary operation.
Pusher arms are not effective against steel-framed or heavily
reinforced concrete structures although they may be used to
remove infill panels or sheeting.

43.4.5 Impact breakers


This tool is essentially a larger development of the traditional
'jack hammer'. It may be pneumatic, but is more regularly
hydraulically operated from the power pack of the excavator on Figure 43.3 A small 'skidsteer' rubber-tyred loader working on an
which it is mounted. These devices will achieve considerably intermediate floor
better and more economical output than hand-held tools.
Large impact breakers are normally used for breaking mass
concrete or old foundations. When used on reinforced concrete, methods, which would produce a nuisance through dust, noise
it is sometimes necessary to cut manually the reinforcement or vibration, are not acceptable. It should always be borne in
enabling the pick of the impact breaker to remove the fractured mind, however, that if mains power is not available, diesel prime
concrete prior to restarting work on a fresh area. movers in themselves produce noise and exhaust fumes.
Alongside the development of small and mini hydraulic Tipped-core drills can be used to stitch drill, i.e. form overlap-
excavators has been the development of the so-called mini ping holes around a section to be moved, be it horizontal or
breaker. These machines can be lifted or manoeuvred into vertical, but it is necessary to ensure that there is no movement
buildings for breaking floors or be placed in confined areas for before the work is complete, as this may stop the core.
breaking basements and foundations, which would previously Cores may have to be taken out at the start and finish of
have required handwork. sawcut lines to accommodate the crescent left by the circular
blade.
43.4.6 Hydraulic shears Great care and experience is required to ensure that prema-
ture movement of parts being cut away does not stop the
Large hydraulic shears mounted on the boom of an excavator rotating sawblades.
and powered from the machine can be used instead of manual Accurate work with some judicious angle cutting is necessary
cutting methods. These machines have the advantage of reduc- to ensure that a piece, especially the first one of a pattern, will
ing the risks associated with hot cutting, be it of fire or risks to move clear without jamming once the cutting is complete. For
health by lead fumes from paint or heated chemicals. large blocks or slabs inside buildings, complex systems for
Some shears have the ability to both elevate and swivel moving pieces both vertically and horizontally may be needed.
allowing them to be used for cutting down structures rather
than simply reducing to pieces the structures that have been
felled by other methods. 43.4.9 Thermic lancing
When working on areas of steelwork, it is important to Thermic lancing is a process in which a reaction between oxygen
establish a sequence which maintains the stability of the struc- and iron is used to generate an intense heat at the point of a
ture by leaving braced bays in position until a collapse can be lance which is used to cut through, for example, heavy sections
engineered and the shear used to complete cutting at ground of concrete, and is useful where noise and vibration are pro-
level. hibited. The volume of fumes given off in confined spaces can be
The shears should always be worked in an attitude which a problem, as can the heat and the need for the slag to be
allows cut sections to fall free without overloading the base drained away without causing a fire hazard. In the open,
machine. The shears can, by careful manipulation, pick and however, it is used regularly where time is 'of the essence', e.g. in
load cut sections directly into skips or vehicles. an alteration to busy public areas during nights or at weekends.

43.4.7 Heavy-duty grabs 43.4.10 Expanding cement


Heavy-duty multi-reeved rope-operated grabs are normally The drilling of holes, filling them with a cement which expands
used for rehandling debris at ground level. They can be used on setting - thus breaking off pieces of concrete - is sometimes
directly to remove brick and masonry structures, but this advocated as a method of demolition. It is used regularly in
method is not popular in the UK. The rate of production is quarrying and rock excavation, but has not found favour with
often determined by the availability of transport which, particu- demolition contractors in the UK.
larly in urban locations, can be unreliable.
43.4.11 Cutting with water jets
43.4.8 Diamond drilling and sawing
The cutting of concrete using high-pressure water jets is offered
Diamond drilling and sawing or a combination of both may as a service by a small number of specialist firms, but it has not
have to be used to remove parts of structures where other been seen in general use alongside more traditional methods.
43.4.12 Hydraulic bursting arches which, if demolished by hand, should be in strips parallel
to the rings forming the span of the arch. Likewise, reinforced
Mass or lightly reinforced concrete can be broken by drilling a
concrete floors should be demolished in strips parallel to the
series of holes near an open face and inserting a burster from
main reinforcement.
which plungers are forced out by hydraulic pressure, thus
When working on a filler joist floor, it should be tackled
cracking the concrete.
progressively by releasing individual filler joists, whilst ensuring
A more recent application of this technique is the removal of
that the workmen have the protection of a well-secured tempor-
a core into which a small hydraulic jack is placed. When the jack
ary deck spanning the main floor beams.
is operated, the concrete will crack from the core to the open
The principle of removing as much deadload as possible also
face.
should be applied to bridges, bearing in mind that temporary
Bursting techniques are relatively quiet, but tend to be slow. support may be necessary to support the skeleton before re-
In an effort to speed the process, large areas of concrete may be moval by crane or dropping on to a prepared area.
broken out, but their subsequent removal, particularly if in The procedures for demolishing chimneys by explosives re-
awkward areas inside the building, may be a problem. volve around leaving the chimney standing on pillars created by
taking 'windows' out of the base in a pattern arranged to
encourage a particular direction of fall when the pillars are
43.5 Demolition blasting blasted clear. If chimneys are to be demolished by hand, access
must be provided to the top. This is normally by a laddered
The use of explosives for demolition attracts a great deal of scaffold on the outside. It is normal for material to be dropped
publicity, but it should be considered as another demolition inside the chimney and removed through a doorway cut in the
method requiring careful selection based on suitability, location, side of the base. The debris must be cleared to avoid pressure on
competent practitioners and careful planning. the walls of the chimney, and regular checks must be made to
For all demolition blasting, good protection and carefully ensure that material has not arched inside the flue.
selected clear zones must be achieved. Brick, masonry or mass Brick or reinforced concrete chimneys can be treated as
concrete, when drilled and charged with explosive, will rupture described, but in prestressed and post-tensioned structures,
or disintegrate when detonated. The effect will vary and be expert advice from engineers should be sought to deal with the
dependent upon the amount and type of explosive, the weight of particular problems.
material charged in relation to the amount of explosive, the On sites in confined spaces it will be necessary to dismantle
pattern and position of the charges in relation to open faces and pylons and masts by hand, but in open areas, these can be felled
the integrity of the material. accurately by preweakening the legs against the direction of fall,
Taking these many variables into account, successful blasts cutting the rear legs and pulling over the structure with a
can be achieved and used to remove key parts to fell structures previously secured steel-wire rope.
or simply fracture banks of material to allow removal by For steel flues, the guylines at 45 on plan against the line of
mechanical excavation. fall should be maintained or, if absent, provided and made taut
With reinforced concrete, the problem becomes more com- prior to cutting the remote guys and severing the base of the flue
plex. It is easy enough to disintegrate the concrete but bursting in a pattern which allows it to hinge over.
open the steel and thus allowing the debris to disperse is not Above ground, storage tanks must be free of fire and explo-
quite so simple. The firing of test shots may be necessary, and sion risks before structural dismantling takes place. If the tank is
the manual cutting of reinforcement will (subject to advice from too large for the roof to be lifted clear as one piece, then the
engineers) assist towards a successful demolition. plates should be removed exposing the structural steel 'spider'
Recent years have seen more use of explosives on the demoli- which should be removed in a regular pattern until a simple
tion of steel structures. The cutting of steelwork was done cruciform exists which finally can be cut down.
traditionally by using substantial charges to blast a section apart Some tanks have roofs which float on the contents. Such
a procedure which tended to have a limited application due roofs should be lowered to their supports and removed once the
to noise and the risk of shrapnel. However, the development of tank shell has been dealt with. Tank shells should be removed in
linear or cutting charges, previously well established for military horizontal bands rather than vertical strips as the behaviour of
or underwater operations, with the proviso that proprietary platesxcut down vertically is unpredictable.
products are available, has meant that such charges, coupled British Standard 6187:1982' includes a guide to typical meth-
with the careful use of delay detonators and propellant charges ods of demolition from which it can be noted that on the more
to shift cut sections, are now regularly used to fell substantial widely found buildings and structures, more than one method
steel structures. may be applied successfully.
With all types of demolition blasting, no matter what type of There is little experience to date with the demolition of
structure, it is essential that those personnel involved under- prestressed concrete. There is, however, a recognition that
stand or have access to advice concerning the 'mechanism of uncontrolled release of stressed wires, cables or bars may
collapse'. A structure which has failed to respond to the use of provoke the ejection of anchorages, particularly if the stressed
explosives, or has partly collapsed, can be extremely dangerous member is unbonded or the bonding is faulty.
with all the attendant problems of safe access for completion of Pretensioned members are rarely a problem during demoli-
the task. tion. This is not the case with post-tensioned members, which
are sometimes incrementally tensioned as successive loading is
applied. Most post-tensioned members are bonded by grouting,
but some unbonded examples must remain and it is difficult to
43.6 Preferred methods of demolition identify the difference other than by physically exposing the
stressing wires. Expert engineering advice should be sought
Some types of structures lend themselves to particular methods when dealing with such members, as uncontrollable release of
of demolition, subject, of course, to local restraints. The basis of the tension can lead to catastrophic collapse and/or ejection of
these methods is that the sequence of work retains the stability debris from anchorages which will fly a considerable distance at
of the remaining part of the structure. great speed.
Simple examples of preferred demolition methods concern Incorrect unloading of incrementally tensioned beams with-
Figure 43.4 Example of temporary steelwork supporting a
five-storey fagade
out partial release of the stressing can lead to hogging and/or 43.8 Health and safety
bursting with unpredictable results.
The technology for dealing with prestressed concrete exists, For the demolition industry, the risks to health and safety range
but it is important to recognize the problem at the outset. It is from those generally associated with construction through to
also important to realize that, complex as the problems may be, chemical hazards normally found on manufacturing plants.
the actual method for destressing and removing prestressed Logical work planning, an analysis of the structural condition
concrete beams, say, may pall into insignificance in comparison of buildings or structures as they are being dismantled, and the
with the problems posed by their location (which is likely to be provision of good access and working platforms can greatly
permanently encapsulated in working structures). reduce the risks from premature collapse, falling materials and
falls from heights. Such measures are specified for particular
circumstances in UK legislation.
43.7 Salvage and recycling Items needed in ensuring personal protection against physical
injury such as safety helmets, goggles, ear muffs and dust and
On some premises, particularly those of historic interest, archi- fume respirators are, in many circumstances, required by legisla-
tectural items, such as weathercocks, clocks, door porticos and tion. However, no matter how rigidly the use of such equipment
boundary marks may have to be recovered ahead of the is enforced, much needs to be done to improve its design.
demolition work for restoration and later repositioning. Although it may prove satisfactory in manufacturing con-
Internal fittings, staircases and banisters may also be of ditions, it very quickly becomes uncomfortable when used for
interest, particularly in listed buildings. The demolition contrac- the manual tasks and long duration of use associated with the
tor has traditionally been interested in metal, be it nonferrous or work.
ferrous scrap. During demolition, these will need to be graded The standard of respiratory protection during burning of
into type and size for marketing to processors for resmelting or lead-painted steelwork or cleaning of lead dust will depend on
export. The removal and resale of builders' items, doors, the natural ventilation around the workman. The use of an auri-
window frames, flooring and china is no longer attractive as it is nasal mask may be sufficient in the open air, whereas a full
time-consuming and prohibited by tight schedules. facepiece with a high-efficiency filter or even airline breathing
The practice of recycling debris to produce a single-size apparatus may be needed indoors. The difference in comfort
crushed concrete or an all-in material has developed in recent and visibility is apparent, and workmen have a tendency to
years. Although it has proved difficult to maintain a specific discard uncomfortable equipment.
grading because of the variable raw material, these materials are The shrouding of work areas, the full respiratory protection
often acceptable as backfill, subgrade for estate roads or car and the decontamination procedures required for asbestos
parks. removal have to be maintained stringently; most workmen take
Research aimed at producing a specification for crushed seriously the publicity given to the risks from this material.
concrete and subsequently a wider acceptance of its use is Apart from these two well-documented hazards, the demoli-
currently being undertaken. In the UK this is at an early stage, tion contractor often encounters others associated with the
but in Europe it is more advanced, boosted in part by a lack of structure or its previous use. Timber used for building may be
acceptable landfill sites and in some areas by a lack of roadmak- treated with preservative requiring its removal to a licensed tip,
ing aggregate. as burning will produce a toxic smoke. Heavy metals such as
The recycling of timber as a fuel has been developed in The cadmium or mercury may be found engrained in slabs or even
Netherlands where charcoal is obtained with some gas produc- the subsoil of factory premises. Sometimes these contaminants
tion. Such plants are extremely expensive and do not, as yet, surface from processes used many years prior to the final use of
exist in the UK. the premises.
43.8.1 Fire and explosion risks Vibration may be impossible to avoid; indeed, efforts to
Flame-cutting through structures and within buildings can eradicate it by changing methods may produce other problems.
create a serious fire hazard if precautions are not taken to isolate However, the intermittent use of a demolition ball may be more
areas and clear burnable debris from underneath working areas. acceptable to neighbours than the constant noise of pneumatic
When bonfires are lit they should be carefully sited, of modest breakers.
size and be extinguished before the end of the shift. The demolition method quite obviously must take into ac-
At the other end of the scale is the devastation caused by count the susceptibility of adjacent or neighbouring structures
explosions due to the ignition of vapours from small quantities to damage from vibration, and the increasing use of sophisti-
of residues in closed vessels. cated office equipment - which is highly susceptible to vibration
Residues in petroleum, oil, gas or chemical tanks, pipes and - means that work must be organized to provide as early as
vessels remain almost indefinitely after the tanks have been possible a gap between occupied buildings and the building
drained and abandoned. Even when containers have been being demolished. Even then, there may be a problem if office
degassed, pockets of residues may remain and vaporize. equipment is in basements, picking up vibration from falling
If it is proposed to dismantle such containers using flame- debris or moving plant and vehicles.
cutters or tools which produce sparks, such as abrasive disc The major problem is dust. Sheeting and dampening down
cutters, the contents must be made inert. can reduce the inconvenience but not eliminate it completely.
Water can be used to fill a tank to exclude vapour, but it does Contractors face an increasing number of complaints about
not render the contents inert; indeed, flammable liquid may blocked filters which purify the air circulation to computer
float on top of the water. Nitrogen, an inert gas, is recom- rooms; air-conditioning units are also affected. Much can be
mended in BS 6187:1982' for purging tanks. Nitrogen is, how- done to relieve this problem if the contractor allows for the time
ever, an asphyxiant and should be handled carefully by special- and cost of additional sheeting or occasionally the use of a
ists. 'Dry ice' - frozen carbon dioxide - can also be used as an prefilter at the installation.
inhibitor. In general, the contractor can do much to prevent environ-
As well as the problems of neutralizing fuel tanks, contractors mental difficulties by good housekeeping around his sites,
are increasingly involved with the dismantling of factories which responding to complaints from the authorities and individuals,
have used chemicals in their working processes. On some and keeping local people informed of the reasons for temporary
occasions, the plants which produce or convert such chemicals inconviences.
are themselves demolished.
Notwithstanding the operator may have purged the process
equipment, pipework, tanks and vessels, they may nevertheless 43.10 Future developments
have accumulated volatile residues over a considerable period
which present health risks from toxicity or irritants. The demolition industry, as conservative as any section of the
These problems will be anticipated by experienced contrac- construction industry, watches new techniques and machinery
tors who will know where to seek the necessary expert advice. with interest as it continues to move toward greater mechaniza-
tion, encouraged both by economics and legislation, effectively
bringing about methods which allow a reduced workforce.
On a broader front, contractors recognize that their manager-
43.9 Environmental matters ial and supervisory skills will be assessed thoroughly prior to
obtaining a share of the markets becoming available, e.g.
The demolition contractor's activities will attract the attention decommissioning offshore oil installations and nuclear power
of the authorities required to look after the interests of the stations. Many governmental policy decisions will affect the
public both physically and environmentally. Local authorities procedures.
will be concerned particularly about: (1) noise; (2) vibration;
and (3) dust.
Restrictions on working hours, e.g. placing limits on early References
starts or imposing early finishes, or the enforcement of silent
periods through the day, can seriously affect site production. 1 British Standards Institution (1982) Code of practice for demolition,
The level of noise acceptable at a site boundary may be settled BS 6187. BSI, Milton Keynes.
in advance by agreement with the local authority, but few 2 Health and Safety Executive, Health and safety in demolition work,
developers opt for this procedure, preferring to leave the nego- Part I: 'Preparation and planning'. Guidance note, GS29/1, HSE,
tiations to the contractor once the job has started. London.
The careful siting of diesel-driven plant, shielding of static
items and use of electrically driven equipment (if mains power is
available) can reduce noise considerably. Good maintenance of
engines and bodywork, and the avoidance of unnecessary
dropping when loading, can also contribute to this.

Anda mungkin juga menyukai