ANALISA BIAYA KONSTRUKSI

PEKERJAAN PERSIAPAN

PA 6.1. 1 m' Pagar Sementara dari kayu tinggi 2 meter

6.1.1. Bahan
- Kayu Dolken 8-10/400 cm 1.250 Btg x Rp 19,250 = Rp 24,062.50
- Semen Portland 5.000 Kg x Rp 1,270 = Rp 6,350.00
- Pasir Beton 0.005 M3 x Rp 87,800 = Rp 439.00
- Koral Beton 0.009 M3 x Rp 170,900 = Rp 1,538.10
- Kayu 5/7 0.072 M3 x Rp 3,107,500 = Rp 223,740.00
- Paku Biasa 2" - 5" 0.060 Kg x Rp 14,520 = Rp 871.20
- Residu/colter 0.400 Lt x Rp 6,530 = Rp 2,612.00
Jumlah (1) = Rp 259,612.80

6.1.2. Tenaga
- Pekerja 0.400 Oh x Rp 52,500 = Rp 21,000.00
- Tukang Kayu 0.200 Oh x Rp 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp 91,900 = Rp 1,838.00
- Mandor 0.020 Oh x Rp 95,600 = Rp 1,912.00
Jumlah (2) = Rp 40,510.00
Jumlah (1) + (2) = Rp 300,122.80

PA 6.2. 1 m' Pagar sementara dari seng gelombang tinggi 2 meter

6.2.1. Bahan
- Kayu Dolken 8-10/400 cm 1.250 Btg x Rp 19,250 = Rp 24,062.50
- Semen Portland 2.500 Kg x Rp 1,270 = Rp 3,175.00
- Seng Gelombang 1.200 Lbr x Rp 59,640 = Rp 71,568.00
- Pasir beton 0.005 M3 x Rp 87,800 = Rp 439.00
- Koral beton 0.009 M3 x Rp 170,900 = Rp 1,538.10
- Kayu 5/7 0.012 M3 x Rp 3,107,500 = Rp 37,290.00
- Paku biasa 2" - 5" 0.060 Kg x Rp 14,520 = Rp 871.20
- Meni besi 0.450 Kg x Rp 25,410 = Rp 11,434.50
Jumlah (1) = Rp 150,378.30

6.2.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 52,500 = Rp 10,500.00
- Pekerja 0.400 Oh x Rp 78,800 = Rp 31,520.00
- Kepala tukang 0.020 Oh x Rp 91,900 = Rp 1,838.00
- Mandor 0.020 Oh x Rp 95,600 = Rp 1,912.00
Jumlah (2) = Rp 45,770.00
Jumlah (1) + (2) = Rp 196,148.30
PA 6.3 1 M' Pagar sementara dari kawat duri tinggi 1,8 meter

6.3.1. Bahan
- Kayu Dolken 8-10/400 cm 1.000 Btg x Rp 19,250 = Rp 19,250.00
- Semen Portland 2.000 Kg x Rp 1,270 = Rp 2,540.00
- Kawat duri 1.625 Kg x Rp 4,030 = Rp 6,548.75
- Pasir beton 0.005 M3 x Rp 87,800 = Rp 439.00
- Koral beton 0.009 M3 x Rp 170,900 = Rp 1,538.10
- Paku biasa 2" - 5" 0.060 Kg x Rp 14,520 = Rp 871.20
Jumlah (1) = Rp 31,187.05

6.3.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 52,500 = Rp 10,500.00
- Pekerja 0.400 Oh x Rp 78,800 = Rp 31,520.00
- Kepala tukang 0.020 Oh x Rp 91,900 = Rp 1,838.00
- Mandor 0.020 Oh x Rp 95,600 = Rp 1,912.00
Jumlah (2) = Rp 45,770.00
Jumlah (1) + (2) = Rp 76,957.05

PA 6.4 Pengukuran dan Pemasangan bouplank

6.4.1. Bahan
- Kayu 5/7 0.012 M3 x Rp 3,107,500 = Rp 37,290.00
- Paku biasa 2" - 5" 0.020 Kg x Rp 14,520 = Rp 290.40
- Kayu papan 3/20 0.007 M3 x Rp 3,107,500 = Rp 21,752.50
Jumlah (1) = Rp 59,332.90

6.4.2. Tenaga
- Tukang kayu 0.100 Oh x Rp 52,500 = Rp 5,250.00
- Pekerja 0.100 Oh x Rp 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp 91,900 = Rp 919.00
- Mandor 0.005 Oh x Rp 95,600 = Rp 478.00
Jumlah (2) = Rp 14,527.00
Jumlah (1) + (2) = Rp 73,859.90

PA 6.5 1 m2 Pembuatan Kantor Sementara dengan Lantai Plesteran

6.5.1. Bahan
- Kayu Dolken 8-10/400 cm 1.250 Btg x Rp 19,250 = Rp 24,062.50
- Kayu 0.180 M3 x Rp 37,400 = Rp 6,732.00
- Batu Belah/Kali 15 - 20 cm 0.850 Kg x Rp 125,900 = Rp 138,490.00
- Besi Strip 1.100 Kg x Rp 87,800 = Rp 3,073,000.00
- Semen Portland 35.000 Kg x Rp 1,270 = Rp 190.50
- Pasir pasang 0.150 M3 x Rp 150,200 = Rp 15,020.00
- Pasir beton 0.100 M3 x Rp 165,200 = Rp 24,780.00
- Koral beton 0.150 M3 x Rp 185,900 = Rp 5,577,000.00
- Bata merah 30.000 Bh x Rp 64,400 = Rp 16,100.00
- Seng plat 0.250 Lbr x Rp 4,180 = Rp 8,360.00
- Jendela nako 2.000 Bh x Rp 13,590 = Rp 1,087.20
- Kaca polos 0.080 M2 x Rp 145,200 = Rp 21,780.00
- Kunci tanam 0.150 Bh x Rp 170,900 = Rp 10,254.00
- Plywood 4 mm 0.060 Lbr x Rp 202,700 = Rp 0.00
Jumlah (1) = Rp 8,916,856.20
6.5.2. Tenaga
- Tukang kayu 2.000 Oh x Rp 52,500 = Rp 105,000.00
- Tukang batu 1.000 Oh x Rp 78,800 = Rp 78,800.00
- Pekerja 2.000 Oh x Rp 78,800 = Rp 157,600.00
- Kepala tukang 0.300 Oh x Rp 91,900 = Rp 27,570.00
- Mandor 0.050 Oh x Rp 95,600 = Rp 4,780.00
Jumlah (2) = Rp 373,750.00
Jumlah (1) + (2) = Rp 9,290,606.20

PA 6.6. 1 M Pembuatan gudang semen dan alat - alat

6.6.1. Bahan
- Kayu Dolken 8-10/400 cm 1.700 Btg x Rp 19,250 = Rp 32,725.00
- Kayu 0.210 M3 x Rp 37,400 = Rp 7,854.00
- Paku biasa 0.300 Kg x Rp 125,900 = Rp 37,770.00
- Semen Portland 10.500 Kg x Rp 1,270 = Rp 13,335.00
- Pasir beton 0.030 M3 x Rp 165,200 = Rp 4,956.00
- Koral beton 0.050 M3 x Rp 185,900 = Rp 9,295.00
- Seng gelombang bjls 20 - 7" 1.500 Lbr x Rp 59,640 = Rp 89,460.00
Jumlah (1) = Rp 195,395.00

6.2.2. Tenaga
- Tukang kayu 0.200 Oh x Rp 52,500 = Rp 10,500.00
- Pekerja 0.400 Oh x Rp 78,800 = Rp 31,520.00
- Kepala tukang 0.020 Oh x Rp 91,900 = Rp 1,838.00
- Mandor 0.020 Oh x Rp 95,600 = Rp 1,912.00
Jumlah (2) = Rp 45,770.00
Jumlah (1) + (2) = Rp 241,165.00

PA 6.7 1m Pembuatan rumah jaga / kontruksi kayu

6.7.1 Bahan
- Kayu Dolken 8-10/400 cm 3.000 Btg x Rp 19,250 = Rp 57,750.00
- Kayu 0.276 M x Rp 37,400 = Rp 10,322.40
- Paku biasa 0.700 Kg x Rp 125,900 = Rp 88,130.00
- Seng gelombang bjls 20 - 7" 1.500 Lbr x Rp 59,640 = Rp 89,460.00
Jumlah (1) = Rp 245,662.40

6.7.2 Tenaga
- Tukang kayu 1.500 Oh x Rp 52,500 = Rp 78,750.00
- Pekerja 1.000 Oh x Rp 78,800 = Rp 78,800.00
- Kepala Tukang 0.150 Oh x Rp 91,900 = Rp 13,785.00
- Mandor 0.050 Oh x Rp 95,600 = Rp 4,780.00
Jumlah (2) = Rp 176,115.00
Jumlah (1) + (2) = Rp 421,777.40

PA 6.8 1 m Membersihkan lapangan dan perataan

6.8.1 Tenaga
- Pekerja 0.100 Oh x Rp 78,800 = Rp 7,880.00
- Mandor 0.050 Oh x Rp 95,600 = Rp 4,780.00
Jumlah = Rp 12,660.00
PA 6.9 1 m Pembuatan bedeng buruh

6.9.1 Bahan
- Kayu Dolken 8-10/400 cm 1.250 Btg x Rp 19,250 = Rp 24,062.50
- Kayu 0.186 M x Rp 37,400 = Rp 6,956.40
- Paku biasa 0.300 Kg x Rp 125,900 = Rp 37,770.00
- Semen portland 18.000 Kg x Rp 1,270 = Rp 22,860.00
- Pasir beton 0.030 M x Rp 165,200 = Rp 4,956.00
- Koral beton 0.050 M x Rp 185,900 = Rp 9,295.00
- Seng gelombang bjls 20 - 7" 1.500 Lbr x Rp 59,640 = Rp 89,460.00
- Plywood 4mm 1.350 Lbr x Rp 202,700 = Rp 273,645.00
Jumlah (1) = Rp 469,004.90

6.9.2 Tenaga
- Tukang kayu 2.000 Oh x Rp 52,500 = Rp 105,000.00
- Pekerja 1.000 Oh x Rp 78,800 = Rp 78,800.00
- Kepala tukang 0.200 Oh x Rp 91,900 = Rp 18,380.00
- Mandor 0.050 Oh x Rp 95,600 = Rp 4,780.00
Jumlah (2) = Rp 206,960.00
Jumlah (1) + (2) = Rp 675,964.90

PA 6.10. 1 m Pembuatan bak adukan ukuran ( 40 x 50 x 20 ) cm

6.10.1. Bahan
- Waterfroof 0.036 M3 x Rp 52,300 = Rp 1,882.80
- Paku biasa 0.080 Kg x Rp 125,900 = Rp 10,072.00
- Kaso 5/7 1.000 Btg x Rp 1,270 = Rp 1,270.00
Jumlah (1) = Rp 13,224.80

6.10.2 Tenaga
- Tukang kayu 0.300 Oh x Rp 52,500 = Rp 15,750.00
- Mandor 0.002 Oh x Rp 95,600 = Rp 143.40
Jumlah (2) = Rp 15,893.40
Jumlah (1) + (2) = Rp 29,118.20

PA 6.11. 1 m Pembuatan Stegger dari bambu, ukuran ( 40 x 50 x 20 ) cm

6.11.1 Bahan
- Bambu 6 - 8 / 600 cm 1.000 Btg x Rp 62,900 = Rp 62,900.00
- Tali ijuk 0.250 Kg x Rp #REF! = Rp #REF!
Jumlah (1) = Rp #REF!

6.11.2 Tenaga
- Tukang kayu 0.017 Oh x Rp 52,500 = Rp 892.50
- Kepala tukang 0.002 Oh x Rp 91,900 = Rp 183.80
- Pekerja 0.250 Oh x Rp 78,800 = Rp 19,700.00
- Mandor 0.013 Oh x Rp 95,600 = Rp 1,242.80
Jumlah (2) = Rp 22,019.10
Jumlah (1) + (2) = Rp #REF!

PA 6.12 1 m Pembuatan jalan sementara

6. 12.1 Bahan
- Batu belah 15/20 0.150 M x Rp 125,900 = Rp 18,885.00
- Batu pecah 5/7 0.090 M x Rp 150,200 = Rp 13,518.00
- Pasir pasang 0.010 M x Rp 76,500 = Rp 765.00
Jumlah (1) = Rp 33,168.00

6.12.2 Tenaga
- Pekerja 1.000 Oh x Rp 78,800 = Rp 78,800.00
- Mandor 0.050 Oh x Rp 95,600 = Rp 4,780.00
Jumlah (2) = Rp 83,580.00
Jumlah (1) + (2) = Rp 116,748.00

PA 6.13 1 m Bongkaran beton betulang

6.13.1 Tenaga
- Pekerja 6.667 Oh x Rp 78,800 = Rp 525,359.60
- Mandor 0.333 Oh x Rp 95,600 = Rp 31,834.80
Jumlah = Rp 557,194.40

PA 6.14 1m Bongkaran dinding tembok bata merah

6.14.1 Tenaga
- Pekerja 5.000 Oh x Rp 78,800 = Rp 394,000.00
- Mandor 0.250 Oh x Rp 95,600 = Rp 23,900.00
Jumlah = Rp 417,900.00

PA 6.15 1m Pasangan pagar kawat jaring galvanis, tinggi 1.00 m

6.15.1 Bahan
- Kawat jaring galvanis/BRC 0.434 Lbr x Rp 235,950 = Rp 102,402.30
Jumlah (1) = Rp 102,402.30

6.15.2. Tenaga
- Pekerja 0.042 Oh x Rp 78,800 = Rp 3,309.60
- Kepala tukang 0.004 Oh x Rp 91,900 = Rp 367.60
- Tukang 0.042 Oh x Rp 52,500 = Rp 2,205.00
- Mandor 0.002 Oh x Rp 95,600 = Rp 191.20
Jumlah (2) = Rp 6,073.40
Jumlah (1) + (2) = Rp 108,475.70

PA 6.16 1 m' Pasang pagar beton pracetak (5 x 50 x 213) cm

6.16.1. Bahan
- Panel beton pracetak 0.986 Lbr x Rp 177,700 = Rp 175,212.20
- Kolom beton pracetak 0.525 Btg x Rp 0 = Rp 0.00
- Pasir beton 0.074 M x Rp 165,200 = Rp 12,224.80
- Koral 2/3 0.146 M x Rp 0 = Rp 0.00
- Batu Bata biasa 5x10x20 cm 45.000 Kg x Rp 1,270 = Rp 57,150.00
Jumlah (1) = Rp 244,587.00

6.16.2. Tenaga
- Pekerja 0.042 Oh x Rp 78,800 = Rp 3,309.60
- Kepala tukang 0.004 Oh x Rp 91,900 = Rp 367.60
- Tukang 0.042 Oh x Rp 52,500 = Rp 2,205.00
- Mandor 0.002 Oh x Rp 95,600 = Rp 191.20
Jumlah (2) = Rp 6,073.40
Jumlah (1) + (2) = Rp 250,660.40
ANALISA BIAYA KONSTRUKSI
PEKERJAAN TANAH

PT 6.1. 1 m Galian tanah biasa sedalam 1 meter

6.1.1. Tenaga
- Pekerja 0.400 Oh x Rp. 52,500 = Rp. 21,000.00
- Mandor 0.040 Oh x Rp. 95,600 = Rp. 3,824.00
Jumlah (1) = Rp. 24,824.00

PT 6.2. 1 m Galian tanah biasa sedalam 2 meter

6.2.1. Tenaga
- Pekerja 0.526 Oh x Rp. 52,500 = Rp. 27,615.00
- Mandor 0.0526 Oh x Rp. 95,600 = Rp. 5,028.56
Jumlah (1) = Rp. 32,643.56

PT 6.3. 1 m Galian tanah biasa sedalam 3 meter

6.3.1. Tenaga
- Pekerja 0.735 Oh x Rp. 52,500 = Rp. 38,587.50
- Mandor 0.0735 Oh x Rp. 95,600 = Rp. 7,026.60
Jumlah (1) = Rp. 45,614.10

PT 6.4. 1 m Galian tanah keras sedalam 1 meter

6.4. Tenaga
- Pekerja 0.625 Oh x Rp. 52,500 = Rp. 32,812.50
- Mandor 0.062 Oh x Rp. 95,600 = Rp. 5,927.20
Jumlah = Rp. 38,739.70

PT 6.5. 1 m Galian tanah cadas sedalam 1 meter

6.5.1. Tenaga
- Pekerja 1.250 Oh x Rp. 52,500 = Rp. 65,625.00
- Mandor 0.125 Oh x Rp. 95,600 = Rp. 11,950.00
Jumlah = Rp. 77,575.00

PT 6.6.. 1 m Galian tanah lumpur sedalam 1 meter

6.6.1. Tenaga
- Pekerja 0.823 Oh x Rp. 52,500 = Rp. 43,207.50
- Mandor 0.083 Oh x Rp. 95,600 = Rp. 7,934.80
Jumlah = Rp. 51,142.30

PT 6.7. 1 m Pekerjaan stripping setinggi 1 meter

6.7.1. Tenaga
- Pekerja 0.050 Oh x Rp. 52,500 = Rp. 2,625.00
- Mandor 0.005 Oh x Rp. 95,600 = Rp. 478.00
Jumlah (1) = Rp. 3,103.00

PT 6.8. 1 m Pembuangan tanah sejauh 150 meter

6.8.1. Tenaga
- Pekerja 0.515 Oh x Rp. 52,500 = Rp. 27,037.50
- Mandor 0.0515 Oh x Rp. 95,600 Rp. 4,923.40
Jumlah = Rp. 31,960.90
PT 6.9. 1 m Urugan kembali

6.9.1. Tenaga
- Pekerja 0.192 Oh x Rp. 52,500 = Rp. 10,080.00
- Mandor 0.019 Oh x Rp. 95,600 = Rp. 1,816.40
Jumlah = Rp. 11,896.40

PT 6.10. 1 m Pemadatan tanah

6.10.1. Tenaga
- Pekerja 0.500 Oh x Rp. 52,500 = Rp. 26,250.00
- Mandor 0.050 Oh x Rp. 95,600 = Rp. 4,780.00
Jumlah = Rp. 31,030.00

PT 6.11. 1 m Urugan pasir

6.11.1. Bahan
- Pasir urug 1.200 M x Rp. 64,400 = Rp. 77,280.00
Jumlah (1) = Rp. 77,280.00

6.11.2. Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp. 15,750.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp. 1,434.00
Jumlah (2) = Rp. 17,184.00
Jumlah (1) + (2) = Rp. 94,464.00
PT 6.12. 1 m Lapisan pudel campuran 1 Kp : 3 Ps : 7 TL

6.12.1. Bahan
- Pasir urug 0.330 M x Rp. 64,400 = Rp. 21,252.00
- Kapur padam 0.109 M x Rp. 1,840 = Rp. 200.56
- Tanah liat 0.763 M x Rp. 62,900 = Rp. 47,992.70
Jumlah (1) = Rp. 69,445.26

6.12.2. Tenaga
- Pekerja 0.500 Oh x Rp. 52,500 = Rp. 26,250.00
- Mandor 0.050 Oh x Rp. 95,600 = Rp. 4,780.00
Jumlah (2) = Rp. 31,030.00
Jumlah (1) + (2) = Rp. 100,475.26

PT 6.13. 1 m Lapisan pudel campuran 1 Kp : 5 TL

6.13.1. Bahan
- Kapur padam 0.200 M x Rp. 1,840 = Rp. 368.00
- Tanah liat 1.000 M x Rp. 62,900 = Rp. 62,900.00
Jumlah (1) = Rp. 63,268.00

6.13.2. Tenaga
- Pekerja 0.500 Oh x Rp. 52,500 = Rp. 26,250.00
- Mandor 0.050 Oh x Rp. 95,600 = Rp. 4,780.00
Jumlah (2) = Rp. 31,030.00
Jumlah (1) + (2) = Rp. 94,298.00

PT 6.16. 1 m Pembuatan jalan sementara, tebal 25 cm

6.16.1. Bahan
- Batu belah 10/15 0.275 M x Rp. 140,900 = Rp. 38,747.50
- Batu koral 5/7 0.030 M x Rp. 170,900 = Rp. 5,127.00
- Pasir pasang 0.050 M x Rp. 76,500 = Rp. 3,825.00
Jumlah (1) = Rp. 47,699.50

6.16.2. Tenaga

- Pekerja 0.500 Oh x Rp. 52,500 = Rp. 26,250.00


- Mandor 0.050 Oh x Rp. 95,600 = Rp. 4,780.00
Jumlah (2) = Rp. 31,030.00
Jumlah (1) + (2) = Rp. 78,729.50
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PONDASI

PP 6.1. 1 M Pasangan pondasi batu kali, 1 Pc : 1 Ps

6.1.1. Bahan :
- Batu belah 15/20 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 392.000 Kg x Rp. 1,270.00 = Rp. 497,840.00
- Pasir pasang 0.314 M x Rp. 76,500.00 = Rp. 24,021.00
Jumlah (1) = Rp. 660,351.00

6.1.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 138,714.00
Jumlah (1) + (2) = Rp. 799,065.00

PP 6.2. 1 M Pasang pondasi batu kali 1 Pc : 2 Ps

6.2.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 267.000 Kg x Rp. 1,270.00 = Rp. 339,090.00
- Pasir Pasang 0.427 M x Rp. 76,500.00 = Rp. 32,665.50
Jumlah (1) = Rp. 510,245.50

6.2.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 138,714.00
Jumlah (1) +(2) = Rp. 648,959.50

PP 6.3. 1 M Pasang pondasi batu kali, 1 Pc : 2,5 Ps

6.3.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 392.000 Kg x Rp. 1,270.00 = Rp. 497,840.00
- Pasir Pasang 0.314 M x Rp. 76,500.00 = Rp. 24,021.00
Jumlah (1) = Rp. 660,351.00

6.3.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 138,714.00
Jumlah (1) +(2) = Rp. 799,065.00
PP 6.4. 1 M Pasang pondasi batu kali, 1 Pc : 3 Ps

6.4.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 202.000 Kg x Rp. 1,270.00 = Rp. 256,540.00
- Pasir Pasang 0.485 M x Rp. 76,500.00 = Rp. 37,102.50
Jumlah (1) = Rp. 432,132.50

6.4.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 138,714.00
Jumlah (1) +(2) = Rp. 570,846.50
PP 6.5. 1 M Pasang pondasi batu kali, 1 Pc : 4 Ps.

6.5.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 163.000 Kg x Rp. 1,270.00 = Rp. 207,010.00
- Pasir Pasang 0.520 M x Rp. 76,500.00 = Rp. 39,780.00
Jumlah (1) = Rp. 385,280.00

6.5.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 138,714.00
Jumlah (1) +(2) = Rp. 523,994.00

PP 6.6. 1 M Pasang pondasi batu kali, 1 Pc : 5 Ps

6.6.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 136.000 Kg x Rp. 1,270.00 = Rp. 172,720.00
- Pasir Pasang 0.544 M x Rp. 76,500.00 = Rp. 41,616.00
Jumlah (1) = Rp. 352,826.00

6.6.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) 138,714.00
Jumlah (1) +(2) 491,540.00

PP 6.7. 1 M Pasang pondasi batu kali, 1 Pc : 6 Ps

6.7.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 117.000 Kg x Rp. 1,270.00 = Rp. 148,590.00
- Pasir Pasang 0.561 M x Rp. 76,500.00 = Rp. 42,916.50
Jumlah (1) = Rp. 329,996.50
6.7.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 138,714.00
Jumlah (1) +(2) = Rp. 468,710.50

PP 6.8. 1 M Pasang pondasi batu kali, Pc : 8 Ps

6.8.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Semen porland 91.000 Kg x Rp. 1,270.00 = Rp. 115,570.00
- Pasir Pasang 0.561 M x Rp. 76,500.00 = Rp. 42,916.50
Jumlah (1) = Rp. 296,976.50

6.8.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 138,714.00
Jumlah (1) +(2) = Rp. 435,690.50
PP 6.9. 1 M Pasang pondasi batu kali, 1 Kp : 1 Sm : 1 Ps

6.9.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Kapur pasang 0.229 Kg x Rp. 187,000.00 = Rp. 42,823.00
- Batu Bata biasa 5x10x20 cm 0.229 M x Rp. 25,080.00 = Rp. 5,743.32
- Pasir Pasang 0.544 M x Rp. 6,270.00 = Rp. 3,410.88
Jumlah (1) = Rp. 190,467.20

6.9.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 138,714.00
Jumlah (1) +(2) = Rp. 329,181.20

PP 6.10. 1 M Pasang pondasi batu kali, 1 Kp : 1 SM : 2 Ps

6.10.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Kapur pasang 0.170 Kg x Rp. 187,000.00 = Rp. 31,790.00
- Batu Bata biasa 5x10x20 cm 0.170 M x Rp. 25,080.00 = Rp. 4,263.60
- Pasir Pasang 0.340 M x Rp. 6,270.00 = Rp. 2,131.80
Jumlah (1) = Rp. 176,675.40

6.10.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 138,714.00
Jumlah (1) +(2) = Rp. 315,389.40
PP 6.11. 1 M Pasangan pondasi batu kali, 1 Pc : 1/4 Kp : 4 Ps

6.11.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Kayu Profil 4" 156.000 Kg x Rp. 25,080.00 = Rp. 3,912,480.00
- Kapur pasang 0.032 M x Rp. 187,000.00 = Rp. 5,984.00
- Pasir Pasang 0.584 M x Rp. 6,270.00 = Rp. 3,661.68
Jumlah (1) = Rp. 4,060,615.68

6.11.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 138,714.00
Jumlah (1) +(2) = Rp. 4,199,329.68

PP 6.12. 1 M Pasang pondasi batu kali, 1 Pc : 3 Kp : 10 Ps

6.12.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Kayu Profil 4" 61.000 Kg x Rp. 25,080.00 = Rp. 1,529,880.00
- Kapur pasang 0.147 M x Rp. 187,000.00 = Rp. 27,489.00
- Pasir Pasang 0.492 M x Rp. 6,270.00 = Rp. 3,084.84
Jumlah (1) = Rp. 1,698,943.84

6.12.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 138,714.00
Jumlah (1) +(2) = Rp. 1,837,657.84

PP 6.13. 1 M Pasang pondasi batu kali, 1/4 Pc : 1 Kp : 4 Ps

6.13.1. Bahan
- Batu belah 15/20 cm 1.100 M x Rp. 125,900.00 = Rp. 138,490.00
- Kayu Profil 4" 41.000 Kg x Rp. 25,080.00 = Rp. 1,028,280.00
- Kapur pasang 0.131 M x Rp. 187,000.00 = Rp. 24,497.00
- Pasir Pasang 0.523 M x Rp. 6,270.00 = Rp. 3,279.21
Jumlah (1) = Rp. 1,194,546.21

6.13.2. Tenaga
- Pekerja 1.500 Oh x Rp. 52,500.00 = Rp. 78,750.00
- Tukang batu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 138,714.00
Jumlah (1) +(2) = Rp. 1,333,260.21

PP 6.14. 1 M Pasang pondasi batu kosong

6.14.1. Bahan
- Batu belah 10/15 cm 1.200 M x Rp. 140,900.00 = Rp. 169,080.00
- Pasir pasang 0.300 M x Rp. 76,500.00 = Rp. 22,950.00
Jumlah (1) = Rp. 192,030.00
6.14.2. Tenaga
- Pekerja 0.780 Oh x Rp. 52,500.00 = Rp. 40,950.00
- Tukang batu 0.390 Oh x Rp. 78,800.00 = Rp. 30,732.00
- Kepala tukang 0.039 Oh x Rp. 91,900.00 = Rp. 3,584.10
- Mandor 0.039 Oh x Rp. 95,600.00 = Rp. 3,728.40
Jumlah (2) = Rp. 78,994.50
Jumlah (1) +(2) = Rp. 271,024.50
PP 6.15. 1 M Pasang pondasi siklop 40 % batu kali

6.15.1. Bahan
- Besi beton 75.000 Kg x Rp. 14,410.00 = Rp. 1,080,750.00
- Semen portland 202.000 Kg x Rp. 1,270.00 = Rp. 256,540.00
- Pasir beton 0.320 Kg x Rp. 87,800.00 = Rp. 28,096.00
- Koral beton 0.490 M x Rp. 185,900.00 = Rp. 91,091.00
- Kawat beton 0.800 Kg x Rp. 16,830.00 = Rp. 13,464.00
Jumlah (1) = Rp. 1,469,941.00

6.15.2. Tenaga
- Pekerja 3.000 Oh x Rp. 52,500.00 = Rp. 157,500.00
- Tukang batu 0.850 Oh x Rp. 78,800.00 = Rp. 66,980.00
- Kepala tukang 0.085 Oh x Rp. 91,900.00 = Rp. 7,811.50
- Mandor 0.150 Oh x Rp. 95,600.00 = Rp. 14,340.00
Jumlah (2) = Rp. 246,631.50
Jumlah (1) +(2) = Rp. 1,716,572.50

PP 6.16. 1 M Pasang pondasi sumuran diameter 100 Cm

6.16.1. Bahan
- Batu belah 15/20 cm 0.450 M x Rp. 125,900.00 = Rp. 56,655.00
- Semen portland 280.000 Kg x Rp. 1,270.00 = Rp. 355,600.00
- Pasir Pasang 0.670 M x Rp. 76,500.00 = Rp. 51,255.00
Jumlah (1) = Rp. 463,510.00

6.16.2. Tenaga
- Pekerja 2.380 Oh x Rp. 52,500.00 = Rp. 124,950.00
- Tukang batu 0.300 Oh x Rp. 78,800.00 = Rp. 23,640.00
- Kepala tukang 0.030 Oh x Rp. 91,900.00 = Rp. 2,757.00
- Mandor 0.080 Oh x Rp. 95,600.00 = Rp. 7,648.00
Jumlah (2) = Rp. 158,995.00
Jumlah (1) +(2) = Rp. 622,505.00

PP 6.17. 1 M Pembuatan tiang pancang (40 x 40) Cm, beton bertulang

6.17.1. Bahan
- Pasir urug darat 0.019 M x Rp. 64,400.00 = Rp. 1,223.60
- Pasir beton 0.094 M x Rp. 87,800.00 = Rp. 8,253.20
- Koral beton 0.150 M x Rp. 185,900.00 = Rp. 27,885.00
- Semen porland 60.500 Kg x Rp. 1,270.00 = Rp. 76,835.00
- Besi beton 45.000 Kg x Rp. 14,410.00 = Rp. 648,450.00
- Kawat beton 0.900 Kg x Rp. 16,830.00 = Rp. 15,147.00
- Kayu kaso 5/7 0.032 M x Rp. 3,107,500.00 = Rp. 99,440.00
- Paku 0.120 Kg x Rp. 14,520.00 = Rp. 1,742.40
- Minyak bekisting 0.090 Lt x Rp. 6,290.00 = Rp. 566.10
- Plamur tembok 0.240 Kg x Rp. 15,730.00 = Rp. 3,775.20
Jumlah (1) = Rp. 883,317.50
6.17.2. Tenaga
- Pekerja 1.000 Oh x Rp. 52,500.00 = Rp. 52,500.00
- Tukang batu 0.670 Oh x Rp. 78,800.00 = Rp. 52,796.00
- Kepala tukang 0.067 Oh x Rp. 91,900.00 = Rp. 6,157.30
- Mandor 0.050 Oh x Rp. 95,600.00 = Rp. 4,780.00
Jumlah (2) = Rp. 116,233.30
Jumlah (1) +(2) = Rp. 999,550.80
PP 6.18. 1 M Pembuatan tiang pancang (35 x 35) Cm, beton bertulang

6.18.1. Bahan
- Pasir urug darat 0.016 M x Rp. 64,400.00 = Rp. 1,030.40
- Pasir beton 0.080 M x Rp. 87,800.00 = Rp. 7,024.00
- Koral beton 0.125 M x Rp. 185,900.00 = Rp. 23,237.50
- Semen porland 49.000 Kg x Rp. 1,270.00 = Rp. 62,230.00
- Besi beton 34.500 Kg x Rp. 14,410.00 = Rp. 497,145.00
- Kawat beton 0.700 Kg x Rp. 16,830.00 = Rp. 11,781.00
- Kayu kaso 5/7 0.027 M x Rp. 3,107,500.00 = Rp. 83,902.50
- Paku 0.120 Kg x Rp. 14,520.00 = Rp. 1,742.40
- Minyak bekisting 0.090 Lt x Rp. 6,290.00 = Rp. 566.10
- Plamur tembok 0.200 Kg x Rp. 15,730.00 = Rp. 3,146.00
Jumlah (1) = Rp. 691,804.90

6.18.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang batu 0.500 Oh x Rp. 78,800.00 = Rp. 39,400.00
- Kepala tukang 0.050 Oh x Rp. 91,900.00 = Rp. 4,595.00
- Mandor 0.040 Oh x Rp. 95,600.00 = Rp. 3,824.00
Jumlah (2) = Rp. 89,819.00
Jumlah (1) +(2) = Rp. 781,623.90
ANALISA BIAYA KONSTRUKSI
PEKERJAAN DINDING

PD 6.1. 1 M Pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps

6.1.1. Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
- Semen portland 64.030 Kg x Rp. 1,270 = Rp 81,318.10
- Pasir pasang 0.059 M x Rp. 76,500 = Rp 4,513.50
Jumlah (1) = Rp 186,631.60

6.1.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 1,838.00
- Mandor 0.030 Oh x Rp. 95,600 = Rp 2,868.00
Jumlah (2) = Rp 54,591.00
Jumlah (1) + (2) = Rp 241,222.60

PD 6.2 1m Pasangan bata merah tebal 1 bata, 1Pc : 2 Ps

6.2.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
- Semen portland 43.500 Kg x Rp. 1,270 = Rp 55,245.00
- Pasir pasang 0.080 M x Rp. 76,500 = Rp 6,120.00
Jumlah (1) = Rp 162,165.00

6.2.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 1,838.00
- Mandor 0.030 Oh x Rp. 95,600 = Rp 2,868.00
Jumlah (2) = Rp 54,591.00
Jumlah (1) + (2) = Rp 216,756.00

PD 6.3 1 m Pasangan bata merah tebal 1 bata, 1Pc : 3 Ps

6.3.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
- Semen portland 32.950 Kg x Rp. 1,270 = Rp 41,846.50
- Pasir pasang 0.091 M x Rp. 76,500 = Rp 6,961.50
Jumlah (1) = Rp 149,608.00

6.3.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 1,838.00
- Mandor 0.030 Oh x Rp. 95,600 = Rp 2,868.00
Jumlah (2) = Rp 54,591.00
Jumlah (1) + (2) = Rp 204,199.00

PD 6.4 1 m Pasangan bata merah tebal 1 bata, 1Pc : 4 Ps

6.4.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
- Semen portland 26.550 Kg x Rp. 1,270 = Rp 33,718.50
- Pasir pasang 0.093 M x Rp. 76,500 = Rp 7,114.50
Jumlah (1) = Rp 141,633.00

6.4.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 1,838.00
- Mandor 0.030 Oh x Rp. 95,600 = Rp 34,125.00
Jumlah (2) = Rp 51,723.00
Jumlah (1) + (2) = Rp 193,356.00

PD 6.5 1 m Pasangan bata merah tebal 1 bata, 1Pc : 5 Ps

6.5.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
- Semen portland 22.200 Kg x Rp. 1,270 = Rp 28,194.00
- Pasir pasang 0.102 M x Rp. 76,500 = Rp 7,803.00
Jumlah (1) = Rp 136,797.00

6.5.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 0.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 0.00
- Mandor 0.030 Oh x Rp. 95,600 = Rp 2,868.00
Jumlah (2) = Rp 36,993.00
Jumlah (1) + (2) = Rp 173,790.00

PD 6.6 1 m Pasangan bata merah tebal 1 bata, 1Pc : 6 Ps

6.6.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
- Semen portland 22.200 Kg x Rp. 1,270 = Rp 28,194.00
- Pasir pasang 0.102 M x Rp. 76,500 = Rp 7,803.00
Jumlah (1) = Rp 136,797.00

6.6.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 1,838.00
- Mandor 0.030 Oh x Rp. 95,600 = Rp 2,868.00
Jumlah (2) = Rp 54,591.00
Jumlah (1) + (2) = Rp 191,388.00
PD 6.7 1 m Pasangan bata merah tebal 1 bata, 1Pc : 3 Kp : 10 Ps

6.7.1 Bahan
- Bata merah 5 x 10 x 20 cm 140.000 Bh x Rp. 720 = Rp 100,800.00
- Semen portland 10.080 Kg x Rp. 1,270 = Rp 12,801.60
- Pasir pasang 0.0925 M x Rp. 76,500 = Rp 7,076.25
Jumlah (1) = Rp 19,877.85

6.7.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp 34,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp 1,838.00
- Mandor 0.030 Oh x Rp. 95,600 = Rp 2,868.00
Jumlah (2) = Rp 54,591.00
Jumlah (1) + (2) = Rp 74,468.85

PD 6.8 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 1 Ps

6.8.1 Bahan
- Bata merah 5 x 10 x 20 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 27.800 Kg x Rp. 1,270 = Rp 35,306.00
- Pasir pasang 0.028 M x Rp. 76,500 = Rp 2,142.00
Jumlah (1) = Rp 87,848.00

6.8.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 27,033.00
Jumlah (1) + (2) = Rp 114,881.00

PD 6.9 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 2 Ps

6.9.1 Bahan
- Bata merah 5 x 10 x 20 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 18.950 Kg x Rp. 1,270 = Rp 24,066.50
- Pasir pasang 0.038 M x Rp. 76,500 = Rp 2,907.00
Jumlah (1) = Rp 77,373.50

6.9.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 27,033.00
Jumlah (1) + (2) = Rp 104,406.50
PD 6.10 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 3 Ps

6.10.1 Bahan
- Bata merah 5 x 10 x 20 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 14.370 Kg x Rp. 1,270 = Rp 18,249.90
- Pasir pasang 0.040 M x Rp. 76,500 = Rp 3,060.00
Jumlah (1) = Rp 71,709.90

6.10.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 27,033.00
Jumlah (1) + (2) = Rp 98,742.90

PD 6.11 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 4 Ps

6.11.1 Bahan
- Bata merah 5 x 10 x 20 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 11.500 Kg x Rp. 1,270 = Rp 14,605.00
- Pasir pasang 0.043 M x Rp. 76,500 = Rp 3,289.50
Jumlah (1) = Rp 68,294.50

6.11.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 27,033.00
Jumlah (1) + (2) = Rp 95,327.50

PD 6.12 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 5 Ps

6.12.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 9.680 Kg x Rp. 1,270 = Rp 12,293.60
- Pasir pasang 0.045 M x Rp. 76,500 = Rp 3,442.50
Jumlah (1) = Rp 66,136.10

6.12.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 27,033.00
Jumlah (1) + (2) = Rp 93,169.10
PD 6.13 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 6 Ps

6.13.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 8.320 Kg x Rp. 1,270 = Rp 10,566.40
- Pasir pasang 0.049 M x Rp. 76,500 = Rp 3,748.50
Jumlah (1) = Rp 64,714.90

6.13.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 27,033.00
Jumlah (1) + (2) = Rp 91,747.90

PD 6.14 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 8 Ps

6.14.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 6.500 Kg x Rp. 1,270 = Rp 8,255.00
- Pasir pasang 0.050 M x Rp. 76,500 = Rp 3,825.00
Jumlah (1) = Rp 62,480.00

6.14.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 27,033.00
Jumlah (1) + (2) = Rp 89,513.00

PD 6.15 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 3 Kp : 10 Ps

6.15.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Semen portland 4.500 Kg x Rp. 1,270 = Rp 5,715.00
- Pasir pasang 0.050 M x Rp. 76,500 = Rp 3,825.00
- Kapur pasang 0.015 M x Rp. 0 = Rp 0.00
Jumlah (1) = Rp 59,940.00

6.15.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 27,033.00
Jumlah (1) + (2) = Rp 86,973.00
PD 6.16 1 m Pasangan bata merah tebal 1/2 bata, 1Kp : 1 Sm : 1 Ps

6.16.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Kawat Duri 0.018 M x Rp. 4,030 = Rp 72.54
- Pasir pasang 0.018 M x Rp. 76,500 = Rp 1,377.00
- Kapur padam 0.018 M x Rp. 68,290 = Rp 1,229.22
Jumlah (1) = Rp 53,078.76

6.16.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 27,033.00
Jumlah (1) + (2) = Rp 80,111.76

PD 6.17 1 m Pasangan bata merah tebal 1/2 bata, 1Kp : 1 Sm : 2 Ps

6.17.1 Bahan
- Bata merah 5 x 11 x 22 cm 70.000 Bh x Rp. 720 = Rp 50,400.00
- Kawat Duri 0.014 Kg x Rp. 1,270 = Rp 17.78
- Pasir pasang 0.028 M x Rp. 76,500 = Rp 2,142.00
- Kapur padam 0.014 M x Rp. 68,290 = Rp 956.06
Jumlah (1) = Rp 53,515.84

6.17.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 27,033.00
Jumlah (1) + (2) = Rp 80,548.84

PD 6.18 1 m Pasangan dinding holowblock (HB.20)

6.18.1 Bahan
- Hollow block (HB.20) 12.500 Bh x Rp. 17,070 = Rp 213,375.00
- Semen portland 13.500 Kg x Rp. 1,270 = Rp 17,145.00
- Pasir pasang 0.048 M x Rp. 76,500 = Rp 3,672.00
- Besi beton polos 1.950 M x Rp. 168,250 = Rp 328,087.50
Jumlah (1) = Rp 562,279.50

6.18.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp 1,378.50
- Mandor 0.017 Oh x Rp. 95,600 = Rp 1,625.20
Jumlah (2) = Rp 31,623.70
Jumlah (1) + (2) = Rp 593,903.20
PD 6.19 1 m Pasangan dinding holowblock (HB.15)

6.19.1 Bahan
- Hollow block (HB.15) 12.500 Bh x Rp. 8,540 = Rp 106,750.00
- Semen portland 10.450 Kg x Rp. 1,270 = Rp 13,271.50
- Pasir pasang 0.038 M x Rp. 76,500 = Rp 2,907.00
- Besi beton polos 1.950 M x Rp. 168,250 = Rp 328,087.50
Jumlah (1) = Rp 451,016.00

6.19.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.120 Oh x Rp. 78,800 = Rp 9,456.00
- Kepala tukang 0.012 Oh x Rp. 91,900 = Rp 1,102.80
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 28,792.80
Jumlah (1) + (2) = Rp 479,808.80

PD 6.20 1 m Pasangan dinding holowblock (HB.10)

6.20.1 Bahan
- Hollow block (HB.10) 12.500 Bh x Rp. 17,330 = Rp 216,625.00
- Semen portland 7.500 Kg x Rp. 1,270 = Rp 9,525.00
- Pasir pasang 0.027 M x Rp. 76,500 = Rp 2,065.50
- Besi beton polos 1.950 M x Rp. 168,250 = Rp 328,087.50
Jumlah (1) = Rp 556,303.00

6.20.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 27,033.00
Jumlah (1) + (2) = Rp 583,336.00

PD 6.21 1 m Pasangan dinding conblock (CB.20)

6.21.1 Bahan
- Concrete block (CB 20) 12.500 Bh x Rp. 2,920 = Rp 36,500.00
- Semen portland 14.050 Kg x Rp. 1,270 = Rp 17,843.50
- Pasir beton 0.004 M x Rp. 87,800 = Rp 351.20
- Pasir pasang 0.042 M x Rp. 76,500 = Rp 3,213.00
- Besi beton polos 3.870 Bh x Rp. 14,410 = Rp 55,766.70
- Paku biasa 2" - 5" 0.006 Kg x Rp. 14,520 = Rp 87.12
- Kayu sembarang 0.001 M x Rp. 3,107,500 = Rp 3,107.50
- Kawat beton 0.030 M x Rp. 16,830 = Rp 504.90
- Koral beton 0.005 M x Rp. 185,900 = Rp 929.50
Jumlah (1) = Rp 118,303.42
6.21.2 Tenaga
- Pekerja 0.370 Oh x Rp. 52,500 = Rp 19,425.00
- Tukang batu 0.157 Oh x Rp. 78,800 = Rp 12,371.60
- Tukang besi 0.007 Oh x Rp. 78,800 = Rp 551.60
- Kepala tukang 0.0164 Oh x Rp. 91,900 = Rp 1,507.16
- Mandor 0.0185 Oh x Rp. 95,600 = Rp 1,768.60
Jumlah (2) = Rp 35,623.96
Jumlah (1) + (2) = Rp 153,927.38

PD 6.22 1 m Pasangan dinding Conblock (CB.15)

6.22.1 Bahan
- Concrete block (CB 15) 12.500 Bh x Rp. 1,600 = Rp 20,000.00
- Semen portland 10.460 Kg x Rp. 1,270 = Rp 13,284.20
- Pasir beton 0.003 M x Rp. 87,800 = Rp 263.40
- Pasir pasang 0.032 M x Rp. 76,500 = Rp 2,448.00
- Besi beton polos 8 mm 2.870 Bh x Rp. 14,410 = Rp 41,356.70
- Paku biasa 2" - 5" 0.004 Kg x Rp. 14,520 = Rp 58.08
- Kayu sembarang 0.001 M x Rp. 3,107,500 = Rp 3,107.50
- Kawat beton 0.020 M x Rp. 16,830 = Rp 336.60
- Koral beton 0.004 M x Rp. 185,900 = Rp 743.60
Jumlah (1) = Rp 81,598.08

6.22.2 Tenaga
- Pekerja 0.340 Oh x Rp. 52,500 = Rp 17,850.00
- Tukang batu 0.130 Oh x Rp. 78,800 = Rp 10,244.00
- Tukang besi 0.007 Oh x Rp. 78,800 = Rp 551.60
- Kepala tukang 0.0137 Oh x Rp. 91,900 = Rp 1,259.03
- Mandor 0.017 Oh x Rp. 95,600 = Rp 1,625.20
Jumlah (2) = Rp 31,529.83
Jumlah (1) + (2) = Rp 113,127.91

PD 6.23 1 m Pasangan dinding Conblock (CB.10)

6.23.1 Bahan
- Concrete block (CB 10) 12.500 Bh x Rp. 740 = Rp 9,250.00
- Semen portland 7.200 Kg x Rp. 1,270 = Rp 9,144.00
- Pasir beton 0.002 M x Rp. 87,800 = Rp 175.60
- Pasir pasang 0.021 M x Rp. 76,500 = Rp 1,606.50
- Besi beton polos 2.540 Bh x Rp. 14,410 = Rp 36,601.40
- Paku biasa 2" - 5" 0.003 Kg x Rp. 14,520 = Rp 43.56
- Kayu sembarang 0.001 M x Rp. 3,107,500 = Rp 3,107.50
- Kawat beton 0.015 M x Rp. 16,830 = Rp 252.45
- Koral beton 0.003 M x Rp. 185,900 = Rp 557.70
Jumlah (1) = Rp 60,738.71

6.23.2 Tenaga
- Pekerja 0.340 Oh x Rp. 52,500 = Rp 17,850.00
- Tukang batu 0.107 Oh x Rp. 78,800 = Rp 8,431.60
- Tukang besi 0.007 Oh x Rp. 78,800 = Rp 551.60
- Kepala tukang 0.0114 Oh x Rp. 91,900 = Rp 1,047.66
- Mandor 0.017 Oh x Rp. 95,600 = Rp 1,625.20
Jumlah (2) = Rp 29,506.06
Jumlah (1) + (2) = Rp 90,244.77
PD 6.24 1 m Pasang dinding lantai

6.24.1 Bahan
- Bondbeam 40 x 20 x 20 cm 2.500 Bh x Rp. 30,250 = Rp 75,625.00
- Semen portland 5.100 Kg x Rp. 1,270 = Rp 6,477.00
- Pasir beton 0.080 M x Rp. 87,800 = Rp 7,024.00
- Besi beton polos 1.500 Kg x Rp. 14,410 = Rp 21,615.00
- Koral beton 0.150 M x Rp. 185,900 = Rp 27,885.00
Jumlah (1) = Rp 138,626.00

6.24.2 Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp 5,250.00
- Tukang batu 0.030 Oh x Rp. 78,800 = Rp 2,364.00
- Tukang besi 0.030 Oh x Rp. 78,800 = Rp 2,364.00
- Kepala tukang 0.006 Oh x Rp. 91,900 = Rp 551.40
- Mandor 0.005 Oh x Rp. 95,600 = Rp 478.00
Jumlah (2) = Rp 11,007.40
Jumlah (1) + (2) = Rp 149,633.40
PD 6.25 1 m Pasang dinding roster / terawang

6.25.1 Bahan
- Roster/terawang 36.000 Bh x Rp. 3,030 = Rp 109,080.00
- Semen portland 12.800 Kg x Rp. 1,270 = Rp 16,256.00
- Pasir pasang 0.035 M x Rp. 76,500 = Rp 2,677.50
Jumlah (1) = Rp 128,013.50

6.25.2 Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp 15,750.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 25,983.00
Jumlah (1) + (2) = Rp 153,996.50

PD 6.26 1 m Pasang bata berongga ukuran ( 5 x 10 x 20 ) cm

6.26.1 Bahan
- Batu berongga 80.000 Bh x Rp. 610 = Rp 48,800.00
- Semen portland 23.650 Kg x Rp. 1,270 = Rp 30,035.50
- Pasir pasang 0.570 M x Rp. 76,500 = Rp 43,605.00
Jumlah (1) = Rp 122,440.50

6.26.2 Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp 16,800.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp 1,378.50
- Mandor 0.015 Oh x Rp. 95,600 = Rp 1,434.00
Jumlah (2) = Rp 31,432.50
Jumlah (1) + (2) = Rp 153,873.00
PD 6.27 1 m Pasang dinding anyaman bambu, rangka kayu

6.27.1 Bahan
- Bilik bambu 1.500 M x Rp. 16,340 = Rp 24,510.00
- Kayu 5/7 0.014 M x Rp. 5,225,000 = Rp 73,150.00
- Paku 0.012 Kg x Rp. 14,520 = Rp 174.24
- List kayu 2/4 0.003 M x Rp. 5,225,000 = Rp 15,675.00
Jumlah (1) = Rp 113,509.24

6.27.2 Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp 5,250.00
- Tukang batu 0.050 Oh x Rp. 78,800 = Rp 3,940.00
- Kepala tukang 0.005 Oh x Rp. 91,900 = Rp 459.50
- Mandor 0.002 Oh x Rp. 95,600 = Rp 191.20
Jumlah (2) = Rp 9,840.70
Jumlah (1) + (2) = Rp 123,349.94
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PLESTERAN

PPL 6.1. 1 M Plesteran 1 Pc : 1 Ps, tebal 15 mm

6.1.1. Bahan
- Semen portland 12.920 Kg x Rp. 1,270 = Rp. 16,408.40
- Pasir pasang 0.013 M x Rp. 76,500 = Rp. 994.50
Jumlah (1) = Rp. 17,402.90
6.1.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 24,654.50
Jumlah (1) + (2) = Rp. 42,057.40

PPL 6.2. 1 M Plesteran 1 Pc : 2 Ps, tebal 15 mm

6.2.1. Bahan
- Semen portland 8.520 Kg x Rp. 1,270 = Rp. 10,820.40
- Pasir pasang 0.017 M x Rp. 76,500 = Rp. 1,300.50
Jumlah (1) = Rp. 12,120.90
6.2.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 24,654.50
Jumlah (1) + (2) = Rp. 36,775.40

PPL 6.3. 1 M Plesteran 1 Pc : 3 Ps, tebal 15 mm

6.3.1. Bahan
- Semen portland 6.480 Kg x Rp. 1,270 = Rp. 8,229.60
- Pasir pasang 0.019 M x Rp. 76,500 = Rp. 1,453.50
Jumlah (1) = Rp. 9,683.10
6.3.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 24,654.50
Jumlah (1) + (2) = Rp. 34,337.60

PPL 6.4. 1 M Plesteran 1 Pc : 4 Ps, tebal 15 mm

6.4.1. Bahan
- Semen portland 5.200 Kg x Rp. 1,270 = Rp. 6,604.00
- Pasir pasang 0.020 M x Rp. 76,500 = Rp. 1,530.00
Jumlah (1) = Rp. 8,134.00
6.4.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 24,654.50
Jumlah (1) + (2) = Rp. 32,788.50

PPL 6.5. 1 M Plesteran 1 Pc : 5 Ps, tebal 15 mm

6.5.1. Bahan
- Semen portland 4.320 Kg x Rp. 1,270 = Rp. 5,486.40
- Pasir pasang 0.022 M x Rp. 76,500 = Rp. 1,683.00
Jumlah (1) = Rp. 7,169.40
6.5.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 24,654.50
Jumlah (1) + (2) = Rp. 31,823.90

PPL 6.6. 1 M Plesteran 1 Pc : 6 Ps, tebal 15 mm

6.6.1. Bahan
- Semen portland 3.680 Kg x Rp. 1,270 = Rp. 4,673.60
- Pasir pasang 0.023 M x Rp. 76,500 = Rp. 1,759.50
Jumlah (1) = Rp. 6,433.10
6.6.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 24,654.50
Jumlah (1) + (2) = Rp. 31,087.60

PPL 6.7. 1 M Plesteran 1 Pc : 8 Ps, tebal 15 mm

6.7.1. Bahan
- Semen portland 2.880 Kg x Rp. 1,270 = Rp. 3,657.60
- Pasir pasang 0.024 M x Rp. 76,500 = Rp. 1,836.00
Jumlah (1) = Rp. 5,493.60
6.7.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 24,654.50
Jumlah (1) + (2) = Rp. 30,148.10
PPL 6.8. 1 M Plesteran 1 Pc : 0,5 Kp : 3 Ps, tebal 15 mm

6.8.1. Bahan
- Semen portland 5.760 Kg x Rp. 1,270 = Rp. 7,315.20
- Kapur padam 0.003 M x Rp. 8,470 = Rp. 25.41
- Pasir pasang 0.013 M x Rp. 76,500 = Rp. 994.50
Jumlah (1) = Rp. 8,335.11
6.8.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 24,654.50
Jumlah (1) + (2) = Rp. 32,989.61

PPL 6.9. 1 M Plesteran 1 Pc : 3 Kp : 10 Ps, tebal 15 mm

6.9.1. Bahan
- Semen portland 1.840 Kg x Rp. 1,270 = Rp. 2,336.80
- Kapur padam 0.006 M x Rp. 8,470 = Rp. 50.82
- Pasir pasang 0.014 M x Rp. 76,500 = Rp. 1,071.00
Jumlah (1) = Rp. 3,458.62
6.9.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 24,654.50
Jumlah (1) + (2) = Rp. 28,113.12

PPL 6.12. 1 M Plesteran 1 Kp : 1 Sm : 2 Ps, tebal 15 mm

6.12.1. Bahan
- Bingkai Naco Niki Hita 0.007 Kg x Rp. 1,270 = Rp. 8.89
- Kapur padam 0.007 M x Rp. 8,470 = Rp. 59.29
- Pasir pasang 0.015 M x Rp. 76,500 = Rp. 1,147.50
Jumlah (1) = Rp. 1,215.68
6.12.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 24,654.50
Jumlah (1) + (2) = Rp. 25,870.18

PPL 6.13. 1 M Plesteran 1 Pc : 2 Ps, tebal 20 mm

6.13.1. Bahan
- Semen Portland 14.280 Kg x Rp. 1,270 = Rp. 18,135.60
- Pasir pasang 0.023 M x Rp. 76,500 = Rp. 1,759.50
Jumlah (1) = Rp. 19,895.10
6.13.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.0125 Oh x Rp. 95,600 = Rp. 1,195.00
Jumlah (2) = Rp. 31,918.00
Jumlah (1) + (2) = Rp. 51,813.10

PPL 6.14. 1 M Plesteran 1 Pc : 3 Ps, tebal 20 mm

6.14.1. Bahan
- Semen Portland 10.800 Kg x Rp. 1,270 = Rp. 13,716.00
- Pasir pasang 0.026 M x Rp. 76,500 = Rp. 1,989.00
Jumlah (1) = Rp. 15,705.00
6.14.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.0125 Oh x Rp. 95,600 = Rp. 1,195.00
Jumlah (2) = Rp. 31,918.00
Jumlah (1) + (2) = Rp. 47,623.00

PPL 6.15. 1 M Plesteran 1 Pc : 4 Ps, tebal 20 mm

6.15.1. Bahan
- Semen Portland 8.680 Kg x Rp. 1,270 = Rp. 11,023.60
- Pasir pasang 0.028 M x Rp. 76,500 = Rp. 2,142.00
Jumlah (1) = Rp. 13,165.60
6.15.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.0125 Oh x Rp. 95,600 = Rp. 1,195.00
Jumlah (2) = Rp. 31,918.00
Jumlah (1) + (2) = Rp. 45,083.60

PPL 6.16. 1 M Plesteran 1 Pc : 5 Ps, tebal 20 mm

6.16.1. Bahan
- Semen Portland 7.290 Kg x Rp. 1,270 = Rp. 9,258.30
- Pasir pasang 0.028 M x Rp. 76,500 = Rp. 2,142.00
Jumlah (1) = Rp. 11,400.30
6.16.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.0125 Oh x Rp. 95,600 = Rp. 1,195.00
Jumlah (2) = Rp. 31,918.00
Jumlah (1) + (2) = Rp. 43,318.30

PPL 6.17. 1 M Plesteran 1 Pc : 6 Ps, tebal 20 mm

6.17.1. Bahan
- Semen Portland 6.240 Kg x Rp. 1,270 = Rp. 7,924.80
- Pasir pasang 0.030 M x Rp. 76,500 = Rp. 2,295.00
Jumlah (1) = Rp. 10,219.80

6.17.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.0125 Oh x Rp. 95,600 = Rp. 1,195.00
Jumlah (2) = Rp. 31,918.00
Jumlah (1) + (2) = Rp. 42,137.80

PPL 6.18. 1 M Plesteran 1 Kp : 1 Sm : 2 Ps, tebal 20 mm

6.18.1. Bahan
- Bingkai Naco Niki Hita 0.009 M x Rp. 1,270 = Rp. 11.43
- Kapur padam 0.009 M x Rp. 8,470 = Rp. 76.23
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
Jumlah (1) = Rp. 1,464.66
6.18.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.0125 Oh x Rp. 95,600 = Rp. 1,195.00
Jumlah (2) = Rp. 31,918.00
Jumlah (1) + (2) = Rp. 33,382.66

PPL 6.19. 1 M Plesteran 1 Pc : 2 Ps, tebal 25 mm

6.19.1. Bahan
- Semen Portland 15.500 Kg x Rp. 1,270 = Rp. 19,685.00
- Pasir pasang 0.013 M x Rp. 76,500 = Rp. 994.50
Jumlah (1) = Rp. 20,679.50
6.19.2. Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp. 15,750.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.013 Oh x Rp. 95,600 = Rp. 1,195.00
Jumlah (2) = Rp. 34,543.00
Jumlah (1) + (2) = Rp. 55,222.50

PPL 6.20. 1 M Plesteran 1 Pc : 3 Ps, tebal 25 mm

6.20.1. Bahan
- Semen Portland 11.750 Kg x Rp. 1,270 = Rp. 14,922.50
- Pasir pasang 0.035 M x Rp. 76,500 = Rp. 2,677.50
Jumlah (1) = Rp. 17,600.00
6.20.2. Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp. 15,750.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.013 Oh x Rp. 95,600 = Rp. 1,242.80
Jumlah (2) = Rp. 34,590.80
Jumlah (1) + (2) = Rp. 52,190.80

PPL 6.21. 1 M Plesteran 1 Pc : 4 Ps, tebal 25 mm


6.21.1. Bahan
- Semen Portland 9.480 Kg x Rp. 1,270 = Rp. 12,039.60
- Pasir pasang 0.038 M x Rp. 76,500 = Rp. 2,907.00
Jumlah (1) = Rp. 14,946.60
6.21.2. Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp. 15,750.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.013 Oh x Rp. 95,600 = Rp. 1,242.80
Jumlah (2) = Rp. 34,590.80
Jumlah (1) + (2) = Rp. 49,537.40

PPL 6.22. 1 M Plesteran 1 Pc : 5 Ps, tebal 25 mm

6.22.1. Bahan
- Semen Portland 7.940 Kg x Rp. 1,270 = Rp. 10,083.80
- Pasir pasang 0.039 M x Rp. 76,500 = Rp. 2,983.50
Jumlah (1) = Rp. 13,067.30
6.22.2. Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp. 15,750.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.013 Oh x Rp. 95,600 = Rp. 1,242.80
Jumlah (2) = Rp. 34,590.80
Jumlah (1) + (2) = Rp. 47,658.10

PPL 6.23. 1 M Plesteran 1 Pc : 2 Ps, tebal 30 mm

6.23.1. Bahan
- Semen Portland 18.650 Kg x Rp. 1,270 = Rp. 23,685.50
- Pasir pasang 0.035 M x Rp. 76,500 = Rp. 2,677.50
Jumlah (1) = Rp. 26,363.00
6.23.2. Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp. 16,800.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.015 Oh x Rp. 95,600 = Rp. 1,434.00
Jumlah (2) = Rp. 40,231.50
Jumlah (1) + (2) = Rp. 66,594.50

PPL 6.24. 1 M Plesteran 1 Pc : 3 Ps, tebal 30 mm

6.24.1. Bahan
- Semen Portland 14.150 Kg x Rp. 1,270 = Rp. 17,970.50
- Pasir pasang 0.039 M x Rp. 76,500 = Rp. 2,983.50
Jumlah (1) = Rp. 20,954.00
6.24.2. Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp. 16,800.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.015 Oh x Rp. 95,600 = Rp. 1,434.00
Jumlah (2) = Rp. 40,231.50
Jumlah (1) + (2) = Rp. 61,185.50

PPL 6.25. 1 M Plesteran 1 Pc : 4 Ps, tebal 30 mm

6.25.1. Bahan
- Semen Portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
Jumlah (1) = Rp. 17,665.60
6.25.2. Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp. 16,800.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.015 Oh x Rp. 95,600 = Rp. 1,434.00
Jumlah (2) = Rp. 40,231.50
Jumlah (1) + (2) = Rp. 57,897.10

PPL 6.26. 1 M Plesteran 1 Pc : 4 Ps, tebal 30 mm

6.26.1. Bahan
- Semen Portland 8.190 Kg x Rp. 1,270 = Rp. 10,401.30
- Pasir pasang 0.045 M x Rp. 76,500 = Rp. 3,442.50
Jumlah (1) = Rp. 13,843.80
6.26.2. Tenaga
- Pekerja 0.320 Oh x Rp. 52,500 = Rp. 16,800.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.015 Oh x Rp. 95,600 = Rp. 1,434.00
Jumlah (2) = Rp. 40,231.50
Jumlah (1) + (2) = Rp. 54,075.30

PPL 6.27. 1 M Berapen 1 Pc : 3 Ps, tebal 30 mm

6.27.1. Bahan
- Semen Portland 7.070 Kg x Rp. 1,270 = Rp. 8,978.90
- Pasir pasang 0.021 M x Rp. 76,500 = Rp. 1,606.50
Jumlah (1) = Rp. 10,585.40
6.27.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang batu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.008 Oh x Rp. 95,600 = Rp. 764.80
Jumlah (2) = Rp. 14,799.10
Jumlah (1) + (2) = Rp. 25,384.50

PPL 6.28. 1 M Berapen 1 Pc : 5 Ps, tebal 30 mm

6.28.1. Bahan
- Semen Portland 5.670 Kg x Rp. 1,270 = Rp. 7,200.90
- Pasir pasang 0.023 M x Rp. 76,500 = Rp. 1,759.50
Jumlah (1) = Rp. 8,960.40
6.28.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang batu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.008 Oh x Rp. 95,600 = Rp. 764.80
Jumlah (2) = Rp. 14,799.10
Jumlah (1) + (2) = Rp. 23,759.50
PPL 6.29. 1 M Plesteran Beton 1 Pc : 2 Ps, tebal 15 mm

6.29.1. Bahan
- Semen Portland 9.300 Kg x Rp. 1,270 = Rp. 11,811.00
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
Jumlah (1) = Rp. 13,188.00
6.29.2. Tenaga
- Pekerja 0.260 Oh x Rp. 52,500 = Rp. 13,650.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.013 Oh x Rp. 95,600 = Rp. 1,242.80
Jumlah (2) = Rp. 32,490.80
Jumlah (1) + (2) = Rp. 45,678.80

PPL 6.30. 1 M Plesteran Beton 1 Pc : 3 Ps, tebal 15 mm

6.30.1. Bahan
- Semen Portland 7.070 Kg x Rp. 1,270 = Rp. 8,978.90
- Pasir pasang 0.021 M x Rp. 76,500 = Rp. 1,606.50
Jumlah (1) = Rp. 10,585.40
6.30.2. Tenaga
- Pekerja 0.260 Oh x Rp. 52,500 = Rp. 13,650.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.013 Oh x Rp. 95,600 = Rp. 1,242.80
Jumlah (2) = Rp. 32,490.80
Jumlah (1) + (2) = Rp. 43,076.20

PPL 6.31. 1 M Plesteran Skoning 1 Pc : 2 Ps

6.31.1. Bahan
- Semen Portland 0.500 Kg x Rp. 1,270 = Rp. 635.00
- Pasir pasang 0.002 M x Rp. 76,500 = Rp. 153.00
Jumlah (1) = Rp. 788.00
6.31.2. Tenaga
- Pekerja 0.057 Oh x Rp. 52,500 = Rp. 2,992.50
- Tukang batu 0.038 Oh x Rp. 78,800 = Rp. 2,994.40
- Kepala tukang 0.038 Oh x Rp. 91,900 = Rp. 3,492.20
- Mandor 0.002 Oh x Rp. 95,600 = Rp. 191.20
Jumlah (2) = Rp. 9,670.30
Jumlah (1) + (2) = Rp. 10,458.30

PPL 6.32. 1 M Plesteran Granito, 1 Pc warna : 2 Granito, tebal 10 mm

6.32.1. Bahan
- PC warna 0.144 Kg x Rp. = Rp. 0.00
- Batu granito 15.000 Kg x Rp. = Rp. 0.00
Jumlah (1) = Rp. 0.00
6.32.2. Tenaga
- Pekerja 0.050 Oh x Rp. 52,500 = Rp. 2,625.00
- Tukang batu 0.020 Oh x Rp. 78,800 = Rp. 1,576.00
- Kepala tukang 0.002 Oh x Rp. 91,900 = Rp. 183.80
- Mandor 0.005 Oh x Rp. 95,600 = Rp. 478.00
Jumlah (2) = Rp. 4,862.80
Jumlah (1) + (2) = Rp. 4,862.80
PPL 6.33. 1 M Plesteran Teraso, 1 Pc warna : 2 Batu Teraso, tebal 10 mm

6.33.1. Bahan
- PC warna 0.440 Kg x Rp. = Rp. 0.00
- Batu teraso 11.500 Kg x Rp. = Rp. 0.00
Jumlah (1) = Rp. 0.00
6.33.2. Tenaga
- Pekerja 0.450 Oh x Rp. 52,500 = Rp. 23,625.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.025 Oh x Rp. 95,600 = Rp. 2,390.00
Jumlah (2) = Rp. 43,613.00
Jumlah (1) + (2) = Rp. 43,613.00

PPL 6.34. 1 M Plesteran Ciprat, 1 Pc : 2 Ps, tebal 10 mm

6.34.1. Bahan
- Semen portland 4.320 Kg x Rp. 1,270 = Rp. 5,486.40
- Pasir pasang 0.016 M x Rp. 76,500 = Rp. 1,224.00
Jumlah (1) = Rp. 6,710.40
6.34.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp. 1,434.00
Jumlah (2) = Rp. 23,358.00
Jumlah (1) + (2) = Rp. 30,068.40

PPL 6.35. 1 M Plesteran Siar adukan, 1 Pc : 2 Ps

6.35.1. Bahan
- Semen portland 4.320 Kg x Rp. 1,270 = Rp. 5,486.40
- Pasir pasang 0.016 M x Rp. 76,500 = Rp. 1,224.00
Jumlah (1) = Rp. 6,710.40
6.35.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang batu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.008 Oh x Rp. 95,600 = Rp. 764.80
Jumlah (2) = Rp. 14,799.10
Jumlah (1) + (2) = Rp. 21,509.50

PPL 6.36. 1 M Plesteran waterfroof bata cote 3 lapis

6.36.1. Bahan
- Semen portland 0.500 Kg x Rp. 1,270 = Rp. 635.00
- Kosen Pintu / Jendela 2.900 Kg x Rp. 66,550 = Rp. 192,995.00
- Pasir pasang 0.006 M x Rp. 76,500 = Rp. 459.00
Jumlah (1) = Rp. 194,089.00
6.36.2. Tenaga
- Pekerja 0.300 Oh x Rp. 52,500 = Rp. 15,750.00
- Tukang batu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.015 Oh x Rp. 95,600 = Rp. 1,434.00
Jumlah (2) = Rp. 34,782.00
Jumlah (1) + (2) = Rp. 228,871.00
ANALISA BIAYA KONSTRUKSI
PEKERJAAN KAYU

PK 6.1. 1 M Pasang kusen pintu dan jendela kayu jati :

6.1.1. Bahan
- Kayu jati, balok 1.100 M x Rp. 23,925,000.00 = Rp. 26,317,500.00
Jumlah (1) = Rp. 26,317,500.00

6.1.2. Tenaga
- Pekerja 6.000 Oh x Rp. 52,500.00 = Rp. 315,000.00
- Tukang kayu 20.000 Oh x Rp. 78,800.00 = Rp. 1,576,000.00
- Kepala tukang 2.000 Oh x Rp. 91,900.00 = Rp. 183,800.00
- Mandor 0.300 Oh x Rp. 95,600.00 = Rp. 28,680.00
Jumlah (2) = Rp. 2,103,480.00
Jumlah (1) +(2) = Rp. 28,420,980.00

PK 6.2. 1 M Pasang kusen pintu dan jendela kayu damar laut :

6.2.1. Bahan
- Kayu meranti, balok 1.200 M x Rp. 9,075,000.00 = Rp. 10,890,000.00
Jumlah (1) = Rp. 10,890,000.00

6.2.2. Tenaga
- Pekerja 6.000 Oh x Rp. 52,500.00 = Rp. 315,000.00
- Tukang kayu 18.000 Oh x Rp. 78,800.00 = Rp. 1,418,400.00
- Kepala tukang 2.000 Oh x Rp. 91,900.00 = Rp. 183,800.00
- Mandor 0.300 Oh x Rp. 95,600.00 = Rp. 28,680.00
Jumlah (2) = Rp. 1,945,880.00
Jumlah (1) +(2) = Rp. 12,835,880.00

PK 6.3. 1 M Pasang kusen pintu dan jendela kayu meranti :

6.3.1. Bahan
- Kayu kapur, balok 1.200 M x Rp. 6,490,000.00 = Rp. 7,788,000.00
Jumlah (1) = Rp. 7,788,000.00

6.3.2. Tenaga
- Pekerja 6.000 Oh x Rp. 52,500.00 = Rp. 315,000.00
- Tukang kayu 18.000 Oh x Rp. 78,800.00 = Rp. 1,418,400.00
- Kepala tukang 2.000 Oh x Rp. 91,900.00 = Rp. 183,800.00
- Mandor 0.300 Oh x Rp. 95,600.00 = Rp. 28,680.00
Jumlah (2) = Rp. 1,945,880.00
Jumlah (1) +(2) = Rp. 9,733,880.00

PK 6.4. 1 M Pasang kusen pintu dan jendela kayu damar laut :

6.4.1. Bahan
- Kayu damar laut, balok 1.200 M x Rp. 9,350,000.00 = Rp. 11,220,000.00
Jumlah (1) = Rp. 11,220,000.00

6.4.2. Tenaga
- Pekerja 6.000 Oh x Rp. 52,500.00 = Rp. 315,000.00
- Tukang kayu 18.000 Oh x Rp. 78,800.00 = Rp. 1,418,400.00
- Kepala tukang 2.000 Oh x Rp. 91,900.00 = Rp. 183,800.00
- Mandor 0.300 Oh x Rp. 95,600.00 = Rp. 28,680.00
Jumlah (2) = Rp. 1,945,880.00
Jumlah (1) +(2) = Rp. 13,165,880.00

PK 6.5. 1 M Pasang pintu klamp kayu meranti batu

6.5.1. Bahan
- Kayu meranti batu, papan 0.036 M x Rp. 9,375,000.00 = Rp. 337,500.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 14,520.00 = Rp. 726.00
Jumlah (1) = Rp. 338,226.00
6.5.2. Tenaga
- Pekerja 0.350 Oh x Rp. 52,500.00 = Rp. 18,375.00
- Tukang kayu 1.050 Oh x Rp. 78,800.00 = Rp. 82,740.00
- Kepala tukang 0.105 Oh x Rp. 91,900.00 = Rp. 9,649.50
- Mandor 0.018 Oh x Rp. 95,600.00 = Rp. 1,720.80
Jumlah (2) = Rp. 112,485.30
Jumlah (1) +(2) = Rp. 450,711.30

PK 6.6. 1 M Pasang pintu klamp kayu jati

6.6.1. Bahan
- Kayu jati, papan 0.036 M x Rp. 24,104,440.00 = Rp. 867,759.84
- Paku biasa 2" - 5" 0.050 Kg x Rp. 14,520.00 = Rp. 726.00
Jumlah (1) = Rp. 868,485.84
6.6.2. Tenaga
- Pekerja 0.350 Oh x Rp. 52,500.00 = Rp. 18,375.00
- Tukang kayu 1.050 Oh x Rp. 78,800.00 = Rp. 82,740.00
- Kepala tukang 0.105 Oh x Rp. 91,900.00 = Rp. 9,649.50
- Mandor 0.018 Oh x Rp. 95,600.00 = Rp. 1,720.80
Jumlah (2) = Rp. 112,485.30
Jumlah (1) +(2) = Rp. 980,971.14

PK 6.7. 1 M Pasang pintu panel kayu jati :

6.7.1. Bahan
- Kayu jati, papan 0.036 M x Rp. 24,104,440.00 = Rp. 867,759.84
Jumlah (1) 867,759.84
6.7.2. Tenaga
- Pekerja 1.000 Oh x Rp. 52,500.00 = Rp. 52,500.00
- Tukang kayu 2.500 Oh x Rp. 78,800.00 = Rp. 197,000.00
- Kepala tukang 0.250 Oh x Rp. 91,900.00 = Rp. 22,975.00
- Mandor 0.050 Oh x Rp. 95,600.00 = Rp. 4,780.00
Jumlah (2) = Rp. 277,255.00
Jumlah (1) +(2) = Rp. 1,145,014.84
PK 6.8. 1 M Pasang pintu panel kayu meranti batu

6.8.1. Bahan
- Kayu meranti batu, papan 0.040 M x Rp. 9,375,000.00 = Rp. 375,000.00
Jumlah (1) = Rp. 375,000.00
6.8.2. Tenaga
- Pekerja 1.000 Oh x Rp. 52,500.00 = Rp. 52,500.00
- Tukang kayu 2.500 Oh x Rp. 78,800.00 = Rp. 197,000.00
- Kepala tukang 0.250 Oh x Rp. 91,900.00 = Rp. 22,975.00
- Mandor 0.050 Oh x Rp. 95,600.00 = Rp. 4,780.00
Jumlah (2) = Rp. 277,255.00
Jumlah (1) +(2) = Rp. 652,255.00

PK 6.9. 1 M Pasang pintu dan jendela kaca panel kayu jati :

6.9.1. Bahan
- Kayu jati, papan 0.035 M x Rp. 24,104,440.00 = Rp. 843,655.40
- Kaca polos 5 mm 0.800 M x Rp. 145,200.00 = Rp. 116,160.00
Jumlah (1) = Rp. 959,815.40
6.9.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.040 Oh x Rp. 95,600.00 = Rp. 3,824.00
Jumlah (2) = Rp. 221,804.00
Jumlah (1) +(2) = Rp. 1,181,619.40

PK 6.10. 1 M Pasang pintu dan jendela kaca panel kayu meranti batu :

6.10.1. Bahan
- Kayu meranti batu, papan 0.035 M x Rp. 9,375,000.00 = Rp. 328,125.00
- Kaca polos 5 mm 0.800 M x Rp. 145,200.00 = Rp. 116,160.00
Jumlah (1) = Rp. 444,285.00
6.10.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.040 Oh x Rp. 95,600.00 = Rp. 3,824.00
Jumlah (2) = Rp. 221,804.00
Jumlah (1) +(2) = Rp. 666,089.00
PK 6.11. 1 M Pasang pintu dan jendela kaca panel kayu meranti :

6.11.1. Bahan
- Kayu meranti, papan 0.035 M x Rp. 5,475,000.00 = Rp. 191,625.00
- Kaca polos 5 mm 0.800 M x Rp. 145,200.00 = Rp. 116,160.00
Jumlah (1) = Rp. 307,785.00
6.11.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.040 Oh x Rp. 95,600.00 = Rp. 3,824.00
Jumlah (2) = Rp. 221,804.00
Jumlah (1) +(2) = Rp. 529,589.00

PK 6.12. 1 M Pasang pintu dan jendela jalusi kayu jati :

6.12.1. Bahan
- Kayu jati, papan 0.064 M x Rp. 24,104,440.00 = Rp. 1,542,684.16
Jumlah (1) = Rp. 1,542,684.16
6.12.2. Tenaga
- Pekerja 1.000 Oh x Rp. 52,500.00 = Rp. 52,500.00
- Tukang kayu 3.000 Oh x Rp. 78,800.00 = Rp. 236,400.00
- Kepala tukang 0.300 Oh x Rp. 91,900.00 = Rp. 27,570.00
- Mandor 0.300 Oh x Rp. 95,600.00 = Rp. 28,680.00
Jumlah (2) = Rp. 345,150.00
Jumlah (1) +(2) = Rp. 1,887,834.16

PK 6.13. 1 M Pasang pintu dan jendela jalusi kayu meranti batu :

6.13.1. Bahan
- Kayu meranti batu, papan 0.064 M x Rp. 9,375,000.00 = Rp. 600,000.00
Jumlah (1) = Rp. 600,000.00
6.13.2. Tenaga
- Pekerja 1.000 Oh x Rp. 52,500.00 = Rp. 52,500.00
- Tukang kayu 3.000 Oh x Rp. 78,800.00 = Rp. 236,400.00
- Kepala tukang 0.300 Oh x Rp. 91,900.00 = Rp. 27,570.00
- Mandor 0.500 Oh x Rp. 95,600.00 = Rp. 47,800.00
Jumlah (2) = Rp. 364,270.00
Jumlah (1) +(2) = Rp. 964,270.00

PK 6.14. 1 M Pasang pintu plywood rangka, rangka kayu jati :

6.14.1. Bahan
- Kayu jati, papan 0.0196 M x Rp. 24,104,440.00 = Rp. 472,447.02
- Paku biasa " - 1" 0.030 Kg x Rp. 16,940.00 = Rp. 508.20
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Playwood 4' x 3' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
Jumlah (1) = Rp. 536,095.22
6.14.2. Tenaga
- Pekerja 0.600 Oh x Rp. 52,500.00 = Rp. 31,500.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.030 Oh x Rp. 95,600.00 = Rp. 2,868.00
Jumlah (2) = Rp. 210,348.00
Jumlah (1) +(2) = Rp. 746,443.22

PK 6.15. 1 M Pasang pintu plywood rangka, rangka kayu meranti batu :

6.15.1. Bahan
- Kayu meranti batu, papan 0.0196 M x Rp. 9,375,000.00 = Rp. 183,750.00
- Paku biasa " - 1" 0.030 Kg x Rp. 16,940.00 = Rp. 508.20
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Playwood 4' x 3' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
Jumlah (1) = Rp. 247,398.20
6.15.2. Tenaga
- Pekerja 0.600 Oh x Rp. 52,500.00 = Rp. 31,500.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.030 Oh x Rp. 95,600.00 = Rp. 2,868.00
Jumlah (2) = Rp. 210,348.00
Jumlah (1) +(2) = Rp. 457,746.20

PK 6.16. 1 M Pasang jalusi mati kusen kayu jati :

6.16.1. Bahan
- Kayu jati, papan 0.060 M x Rp. 24,104,440.00 = Rp. 1,446,266.40
- Paku biasa " - 1" 0.150 Kg x Rp. 16,940.00 = Rp. 2,541.00
Jumlah (1) = Rp. 1,448,807.40
6.16.2. Tenaga
- Pekerja 0.500 Oh x Rp. 52,500.00 = Rp. 26,250.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.025 Oh x Rp. 95,600.00 = Rp. 2,390.00
Jumlah (2) = Rp. 204,620.00
Jumlah (1) +(2) = Rp. 1,653,427.40

PK 6.17. 1 M Pasang jalusi mati kusen kayu damar laut :

6.17.1. Bahan
- Kayu damar laut, papan 0.060 M x Rp. 9,650,000.00 = Rp. 579,000.00
- Paku biasa " - 1" 0.150 Kg x Rp. 16,940.00 = Rp. 2,541.00
Jumlah (1) = Rp. 581,541.00
6.17.2. Tenaga
- Pekerja 0.500 Oh x Rp. 52,500.00 = Rp. 26,250.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.025 Oh x Rp. 95,600.00 = Rp. 2,390.00
Jumlah (2) = Rp. 204,620.00
Jumlah (1) +(2) = Rp. 786,161.00
PK 6.18. 1 M Pasang pintu plywood rangka, rangka kayu meranti :

6.18.1. Bahan
- Kayu meranti, papan 0.0196 M x Rp. 5,475,000.00 = Rp. 107,310.00
- Paku biasa " - 1" 0.030 Kg x Rp. 16,940.00 = Rp. 508.20
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Playwood 4' x 3' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
Jumlah (1) = Rp. 63,140.00
6.18.2. Tenaga
- Pekerja 0.600 Oh x Rp. 52,500.00 = Rp. 31,500.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.030 Oh x Rp. 95,600.00 = Rp. 2,868.00
Jumlah (2) = Rp. 210,348.00
Jumlah (1) +(2) = Rp. 273,488.00

PK 6.19. 1 M Pasang pintu teakwood rangka, rangka kayu jati :

6.19.1. Bahan
- Kayu jati, papan 0.0196 M x Rp. 24,104,440.00 = Rp. 472,447.02
- Paku biasa " - 1" 0.300 Kg x Rp. 16,940.00 = Rp. 5,082.00
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Teakwood 4' x 8' x 4 mm 1.000 Lbr x Rp. 54,450.00 = Rp. 54,450.00
Jumlah (1) = Rp. 543,199.02
6.19.2. Tenaga
- Pekerja 0.600 Oh x Rp. 52,500.00 = Rp. 31,500.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.030 Oh x Rp. 95,600.00 = Rp. 2,868.00
Jumlah (2) = Rp. 210,348.00
Jumlah (1) +(2) = Rp. 753,547.02

PK 6.20. 1 M Pasang pintu teakwood rangka, rangka kayu meranti batu :

6.20.1. Bahan
- Kayu meranti batu, papan 0.0196 M x Rp. 9,375,000.00 = Rp. 183,750.00
- Paku biasa " - 1" 0.300 Kg x Rp. 16,940.00 = Rp. 5,082.00
- Lem kayu 0.300 Lt x Rp. 37,400.00 = Rp. 11,220.00
- Teakwood 4' x 8' x 4 mm 1.000 Lbr x Rp. 54,450.00 = Rp. 54,450.00
Jumlah (1) = Rp. 254,502.00
6.20.2. Tenaga
- Pekerja 0.600 Oh x Rp. 52,500.00 = Rp. 31,500.00
- Tukang kayu 2.000 Oh x Rp. 78,800.00 = Rp. 157,600.00
- Kepala tukang 0.200 Oh x Rp. 91,900.00 = Rp. 18,380.00
- Mandor 0.030 Oh x Rp. 95,600.00 = Rp. 2,868.00
Jumlah (2) = Rp. 210,348.00
Jumlah (1) +(2) = Rp. 464,850.00
PK 6.21. 1 M Pasang pintu plywood & formika, rangka kayu jati :

6.21.1. Bahan
- Kayu jati, papan 0.0196 M x Rp. 24,104,440.00 = Rp. 472,447.02
- Paku biasa " - 1" 0.300 Kg x Rp. 16,940.00 = Rp. 5,082.00
- Lem kayu 0.800 Lt x Rp. 37,400.00 = Rp. 29,920.00
- Plywood 4' x 8' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
- Formica 4' x 8' 1.000 Lbr x Rp. 74,250.00 = Rp. 74,250.00
Jumlah (1) = Rp. 633,619.02
6.21.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang kayu 2.500 Oh x Rp. 78,800.00 = Rp. 197,000.00
- Kepala tukang 0.250 Oh x Rp. 91,900.00 = Rp. 22,975.00
- Mandor 0.040 Oh x Rp. 95,600.00 = Rp. 3,824.00
Jumlah (2) = Rp. 265,799.00
Jumlah (1) +(2) = Rp. 899,418.02

PK 6.22. 1 M Pasang pintu plywood & formika, rangka kayu meranti batu :

6.22.1. Bahan
- Kayu meranti batu, papan 0.0196 M x Rp. 9,375,000.00 = Rp. 183,750.00
- Paku biasa " - 1" 0.300 Kg x Rp. 16,940.00 = Rp. 5,082.00
- Lem kayu 0.800 Lt x Rp. 37,400.00 = Rp. 29,920.00
- Plywood 4' x 8' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
- Formica 4' x 8' 1.000 Lbr x Rp. 74,250.00 = Rp. 74,250.00
Jumlah (1) = Rp. 344,922.00

6.22.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang kayu 2.500 Oh x Rp. 78,800.00 = Rp. 197,000.00
- Kepala tukang 0.250 Oh x Rp. 91,900.00 = Rp. 22,975.00
- Mandor 0.040 Oh x Rp. 95,600.00 = Rp. 3,824.00
Jumlah (2) = Rp. 265,799.00
Jumlah (1) +(2) = Rp. 610,721.00

PK 6.23. 1 M Pasang pintu plywood & formika, rangka kayu jati :

6.23.1. Bahan
- Kayu jati, papan 0.0196 M x Rp. 24,104,440.00 = Rp. 472,447.02
- Paku biasa " - 1" 0.300 Kg x Rp. 16,940.00 = Rp. 5,082.00
- Lem kayu 0.800 Lt x Rp. 37,400.00 = Rp. 29,920.00
- Teakwood 4' x 8' x 4 mm 1.000 Lbr x Rp. 54,450.00 = Rp. 54,450.00
- Formica 4' x 8' 1.000 Lbr x Rp. 74,250.00 = Rp. 74,250.00
Jumlah (1) = Rp. 636,149.02

6.23.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang kayu 2.500 Oh x Rp. 78,800.00 = Rp. 197,000.00
- Kepala tukang 0.250 Oh x Rp. 91,900.00 = Rp. 22,975.00
- Mandor 0.040 Oh x Rp. 95,600.00 = Rp. 3,824.00
Jumlah (2) = Rp. 265,799.00
Jumlah (1) +(2) = Rp. 901,948.02
PK 6.24. 1 M Pasang pintu plywood & formika, rangka kayu damar laut (divermis) :

6.24.1. Bahan
- Kayu meranti batu, papan 0.0196 M x Rp. 9,375,000.00 = Rp. 183,750.00
- Paku biasa " - 1" 0.300 Kg x Rp. 16,940.00 = Rp. 5,082.00
- Lem kayu 0.800 Lt x Rp. 37,400.00 = Rp. 29,920.00
- Teakwood 4' x 8' x 4 mm 0.500 Lbr x Rp. 54,450.00 = Rp. 27,225.00
- Vernis 0.500 Lt x Rp. 48,280.00 = Rp. 24,140.00
- Formica 4' x 8' 0.500 Lbr x Rp. 74,250.00 = Rp. 37,125.00
Jumlah (1) = Rp. 307,242.00

6.24.2. Tenaga
- Pekerja 0.800 Oh x Rp. 52,500.00 = Rp. 42,000.00
- Tukang kayu 2.500 Oh x Rp. 78,800.00 = Rp. 197,000.00
- Kepala tukang 0.250 Oh x Rp. 91,900.00 = Rp. 22,975.00
- Mandor 0.040 Oh x Rp. 95,600.00 = Rp. 3,824.00
Jumlah (2) = Rp. 265,799.00
Jumlah (1) +(2) = Rp. 573,041.00

PK 6.29. 1 M Pasang konstruksi kuda-kuda kayu damar laut :

6.29.1. Bahan
- Kayu damar laut, balok 1.1000 M x Rp. 9,350,000.00 = Rp. 10,285,000.00
- Besi strip 15.000 Kg x Rp. 11,880.00 = Rp. 178,200.00
- Paku biasa 2" - 5" 0.800 Kg x Rp. 16,940.00 = Rp. 13,552.00
Jumlah (1) = Rp. 10,476,752.00

6.29.2. Tenaga
- Pekerja 4.000 Oh x Rp. 52,500.00 = Rp. 210,000.00
- Tukang kayu 12.000 Oh x Rp. 78,800.00 = Rp. 945,600.00
- Kepala tukang 1.200 Oh x Rp. 91,900.00 = Rp. 110,280.00
- Mandor 0.200 Oh x Rp. 95,600.00 = Rp. 19,120.00
Jumlah (2) = Rp. 1,285,000.00
Jumlah (1) +(2) = Rp. 11,761,752.00

PK 6.30. 1 M Pasang konstruksi kuda-kuda kayu meranti :

6.30.1. Bahan
- Kayu meranti, balok 1.1000 M x Rp. 5,225,000.00 = Rp. 5,747,500.00
- Besi strip 15.000 Kg x Rp. 11,880.00 = Rp. 178,200.00
- Paku biasa 2" - 5" 0.800 Kg x Rp. 16,940.00 = Rp. 13,552.00
Jumlah (1) = Rp. 5,939,252.00

6.30.2. Tenaga
- Pekerja 4.000 Oh x Rp. 52,500.00 = Rp. 210,000.00
- Tukang kayu 12.000 Oh x Rp. 78,800.00 = Rp. 945,600.00
- Kepala tukang 1.200 Oh x Rp. 91,900.00 = Rp. 110,280.00
- Mandor 0.200 Oh x Rp. 95,600.00 = Rp. 19,120.00
Jumlah (2) = Rp. 1,285,000.00
Jumlah (1) +(2) = Rp. 7,224,252.00
PK 6.31. 1 M Pasang kaso + reng genteng kodok kayu meranti :

6.31.1. Bahan
- Kayu meranti, balok 0.012 M x Rp. 5,225,000.00 = Rp. 62,700.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 16,940.00 = Rp. 2,541.00
Jumlah (1) = Rp. 65,241.00
6.31.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500.00 = Rp. 5,250.00
- Tukang kayu 0.100 Oh x Rp. 78,800.00 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900.00 = Rp. 919.00
- Mandor 0.005 Oh x Rp. 95,600.00 = Rp. 478.00
Jumlah (2) = Rp. 14,527.00
Jumlah (1) +(2) = Rp. 79,768.00

PK 6.32. 1 M Pasang kaso + reng genteng kodok kayu damar laut :

6.32.1. Bahan
- Kayu damar laut, balok 0.012 M x Rp. 9,350,000.00 = Rp. 112,200.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 16,940.00 = Rp. 2,541.00
Jumlah (1) = Rp. 114,741.00

6.32.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500.00 = Rp. 5,250.00
- Tukang kayu 0.100 Oh x Rp. 78,800.00 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900.00 = Rp. 919.00
- Mandor 0.005 Oh x Rp. 95,600.00 = Rp. 478.00
Jumlah (2) = Rp. 14,527.00
Jumlah (1) +(2) = Rp. 129,268.00

PK 6.33. 1 M Pasang kaso + reng genteng monier kayu jati :

6.33.1. Bahan
- Kayu jati, balok 0.014 M x Rp. 23,925,000.00 = Rp. 334,950.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 16,940.00 = Rp. 2,541.00
Jumlah (1) = Rp. 337,491.00

6.33.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500.00 = Rp. 5,250.00
- Tukang kayu 0.100 Oh x Rp. 78,800.00 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900.00 = Rp. 919.00
- Mandor 0.005 Oh x Rp. 95,600.00 = Rp. 478.00
Jumlah (2) = Rp. 14,527.00
Jumlah (1) +(2) = Rp. 352,018.00

PK 6.34. 1 M Pasang kaso + reng genteng monier kayu damar laut :

6.34.1. Bahan
- Kayu damar laut, balok 0.014 M x Rp. 9,350,000.00 = Rp. 130,900.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 16,940.00 = Rp. 2,541.00
Jumlah (1) = Rp. 133,441.00
6.34.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500.00 = Rp. 5,250.00
- Tukang kayu 0.100 Oh x Rp. 78,800.00 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900.00 = Rp. 919.00
- Mandor 0.005 Oh x Rp. 95,600.00 = Rp. 478.00
Jumlah (2) = Rp. 14,527.00
Jumlah (1) +(2) = Rp. 147,968.00

PK 6.35. 1 M Pasang kaso + reng genteng beton kayu damar laut :

6.35.1. Bahan
- Kayu damar laut, balok 0.014 M x Rp. 9,350,000.00 = Rp. 130,900.00
- Paku biasa 2" - 5" 0.150 Kg x Rp. 16,940.00 = Rp. 2,541.00
Jumlah (1) = Rp. 133,441.00
6.35.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500.00 = Rp. 5,250.00
- Tukang kayu 0.100 Oh x Rp. 78,800.00 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900.00 = Rp. 919.00
- Mandor 0.005 Oh x Rp. 95,600.00 = Rp. 478.00
Jumlah (2) = Rp. 14,527.00
Jumlah (1) +(2) = Rp. 147,968.00

PK 6.36. 1 M Pasang kaso + reng atap sirap kayu damar laut :

6.36.1. Bahan
- Kayu damar laut, balok 0.165 M x Rp. 9,350,000.00 = Rp. 1,542,750.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 16,940.00 = Rp. 3,388.00
Jumlah (1) = Rp. 1,546,138.00

6.36.2. Tenaga
- Pekerja 0.120 Oh x Rp. 52,500.00 = Rp. 6,300.00
- Tukang kayu 0.120 Oh x Rp. 78,800.00 = Rp. 9,456.00
- Kepala tukang 0.012 Oh x Rp. 91,900.00 = Rp. 1,102.80
- Mandor 0.006 Oh x Rp. 95,600.00 = Rp. 573.60
Jumlah (2) = Rp. 17,432.40
Jumlah (1) +(2) = Rp. 1,563,570.40

PK 6.37. 1 M Pasang kaso + reng atap sirap kayu meranti :

6.37.1. Bahan
- Kayu meranti, balok 0.165 M x Rp. 5,225,000.00 = Rp. 862,125.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 16,940.00 = Rp. 3,388.00
Jumlah (1) = Rp. 865,513.00
6.37.2. Tenaga
- Pekerja 0.120 Oh x Rp. 52,500.00 = Rp. 6,300.00
- Tukang kayu 0.120 Oh x Rp. 78,800.00 = Rp. 9,456.00
- Kepala tukang 0.012 Oh x Rp. 91,900.00 = Rp. 1,102.80
- Mandor 0.006 Oh x Rp. 95,600.00 = Rp. 573.60
Jumlah (2) = Rp. 17,432.40
Jumlah (1) +(2) = Rp. 882,945.40
PK 6.38. 1 M Pasang rangka langit-langit (1.00 x 1.00) m, kayu jati :

6.38.1. Bahan
- Kayu jati, balok 0.012 M x Rp. 23,925,000.00 = Rp. 287,100.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 16,940.00 = Rp. 1,694.00
Jumlah (1) = Rp. 288,794.00
6.38.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500.00 = Rp. 7,875.00
- Tukang kayu 0.250 Oh x Rp. 78,800.00 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900.00 = Rp. 2,297.50
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 37,042.50
Jumlah (1) +(2) = Rp. 325,836.50

PK 6.38. A 1 M Pasang rangka langit-langit (1.00 x 1.00) m, damar laut :

6.38.1. Bahan
- Kayu damar laut, balok 0.012 M x Rp. 9,350,000.00 = Rp. 112,200.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 16,940.00 = Rp. 1,694.00
Jumlah (1) = Rp. 113,894.00
6.38.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500.00 = Rp. 7,875.00
- Tukang kayu 0.250 Oh x Rp. 78,800.00 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900.00 = Rp. 2,297.50
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 37,042.50
Jumlah (1) +(2) = Rp. 150,936.50

PK 6.38. B 1 M Pasang rangka langit-langit (1.00 x 1.00) m, Kayu meranti :

6.38.1. Bahan
- Kayu meranti, balok 0.012 M x Rp. 5,225,000.00 = Rp. 62,700.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 16,940.00 = Rp. 1,694.00
Jumlah (1) = Rp. 64,394.00
6.38.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500.00 = Rp. 7,875.00
- Tukang kayu 0.250 Oh x Rp. 78,800.00 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900.00 = Rp. 2,297.50
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 37,042.50
Jumlah (1) +(2) = Rp. 101,436.50
PK 6.44. 1 M Pasang rangka langit-langit (30 x 30) cm, kayu jati :

6.44.1. Bahan
- Kayu jati, balok 0.027 M x Rp. 23,925,000.00 = Rp. 645,975.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 16,940.00 = Rp. 3,388.00
Jumlah (1) = Rp. 649,363.00
6.44.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500.00 = Rp. 13,125.00
- Tukang kayu 0.350 Oh x Rp. 78,800.00 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900.00 = Rp. 3,216.50
- Mandor 0.0125 Oh x Rp. 95,600.00 = Rp. 1,195.00
Jumlah (2) = Rp. 45,116.50
Jumlah (1) +(2) = Rp. 694,479.50

PK 6.45. 1 M Pasang rangka langit-langit (30 x 30) cm, kayu damar laut :

6.45.1. Bahan
- Kayu damar laut, balok 0.027 M x Rp. 9,350,000.00 = Rp. 252,450.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 16,940.00 = Rp. 3,388.00
Jumlah (1) = Rp. 255,838.00
6.45.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500.00 = Rp. 13,125.00
- Tukang kayu 0.350 Oh x Rp. 78,800.00 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900.00 = Rp. 3,216.50
- Mandor 0.0125 Oh x Rp. 95,600.00 = Rp. 1,195.00
Jumlah (2) = Rp. 45,116.50
Jumlah (1) +(2) = Rp. 300,954.50

PK 6.46. 1 M Pasang rangka langit-langit (30 x 30) cm, kayu meranti :


6.46.1. Bahan
- Kayu meranti, balok 0.027 M x Rp. 5,225,000.00 = Rp. 141,075.00
- Paku biasa 2" - 5" 0.200 Kg x Rp. 16,940.00 = Rp. 3,388.00
Jumlah (1) = Rp. 144,463.00
6.46.2. Tenaga
- Pekerja 0.250 Oh x Rp. 52,500.00 = Rp. 13,125.00
- Tukang kayu 0.350 Oh x Rp. 78,800.00 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900.00 = Rp. 3,216.50
- Mandor 0.0125 Oh x Rp. 95,600.00 = Rp. 1,195.00
Jumlah (2) = Rp. 45,116.50
Jumlah (1) +(2) = Rp. 189,579.50
PK 6.47. 1 M Pasang lisplang ukuran (3 x 20) cm, kayu meranti :

6.47.1. Bahan
- Kayu meranti, papan 0.0072 M x Rp. 5,475,000.00 = Rp. 39,420.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 16,940.00 = Rp. 847.00
Jumlah (1) = Rp. 40,267.00
6.47.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500.00 = Rp. 5,250.00
- Tukang kayu 0.200 Oh x Rp. 78,800.00 = Rp. 15,760.00
- Kepala tukang 0.025 Oh x Rp. 91,900.00 = Rp. 2,297.50
- Mandor 0.005 Oh x Rp. 95,600.00 = Rp. 478.00
Jumlah (2) = Rp. 23,785.50
Jumlah (1) +(2) = Rp. 64,052.50

PK 6.48. 1 M Pasang lisplang ukuran (3 x 20) cm, kayu meranti batu :

6.48.1. Bahan
- Meranti batu, papan 0.0072 M x Rp. 9,375,000.00 = Rp. 67,500.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 16,940.00 = Rp. 847.00
Jumlah (1) = Rp. 68,347.00
6.48.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500.00 = Rp. 5,250.00
- Tukang kayu 0.200 Oh x Rp. 78,800.00 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900.00 = Rp. 1,838.00
- Mandor 0.005 Oh x Rp. 95,600.00 = Rp. 478.00
Jumlah (2) = Rp. 23,326.00
Jumlah (1) +(2) = Rp. 91,673.00

PK 6.49. 1 M Pasang lisplang ukuran (3 x 30) cm, kayu jati :

6.49.1. Bahan
- Kayu jati, papan 0.0110 M x Rp. 24,104,440.00 = Rp. 265,148.84
- Paku biasa 2" - 5" 0.050 Kg x Rp. 16,940.00 = Rp. 847.00
Jumlah (1) = Rp. 265,995.84
6.49.2. Tenaga
- Pekerja 0.110 Oh x Rp. 52,500.00 = Rp. 5,775.00
- Tukang kayu 0.220 Oh x Rp. 78,800.00 = Rp. 17,336.00
- Kepala tukang 0.022 Oh x Rp. 91,900.00 = Rp. 2,021.80
- Mandor 0.005 Oh x Rp. 95,600.00 = Rp. 478.00
Jumlah (2) = Rp. 25,610.80
Jumlah (1) +(2) = Rp. 291,606.64

PK 6.50. 1 M Pasang lisplang ukuran (3 x 30) cm, kayu meranti batu :

6.50.1. Bahan
- Meranti batu, papan 0.011 M x Rp. 9,375,000.00 = Rp. 103,125.00
- Paku biasa 2" - 5" 0.050 Kg x Rp. 16,940.00 = Rp. 847.00
Jumlah (1) = Rp. 103,972.00
6.50.2. Tenaga
- Pekerja 0.110 Oh x Rp. 52,500.00 = Rp. 5,775.00
- Tukang kayu 0.220 Oh x Rp. 78,800.00 = Rp. 17,336.00
- Kepala tukang 0.022 Oh x Rp. 91,900.00 = Rp. 2,021.80
- Mandor 0.005 Oh x Rp. 95,600.00 = Rp. 478.00
Jumlah (2) = Rp. 25,610.80
Jumlah (1) +(2) = Rp. 129,582.80

PK 6.51. 1 M Pasang lisplang ukuran 2 x (3 x 20) cm, kayu meranti batu :

6.51.1. Bahan
- Meranti batu, papan 0.0145 M x Rp. 9,375,000.00 = Rp. 135,937.50
- Paku biasa 2" - 5" 0.060 Kg x Rp. 16,940.00 = Rp. 1,016.40
Jumlah (1) = Rp. 136,953.90
6.51.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500.00 = Rp. 7,875.00
- Tukang kayu 0.250 Oh x Rp. 78,800.00 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900.00 = Rp. 2,297.50
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 37,042.50
Jumlah (1) +(2) = Rp. 173,996.40

PK 6.52. 1 M Pasang lisplang ukuran 2 x (2 x 20) cm, kayu meranti batu :

6.52.1. Bahan
- Meranti batu, papan 0.0086 M x Rp. 9,375,000.00 = Rp. 80,625.00
- Paku biasa 2" - 5" 0.060 Kg x Rp. 16,940.00 = Rp. 1,016.40
Jumlah (1) = Rp. 81,641.40
6.52.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500.00 = Rp. 5,250.00
- Tukang kayu 0.100 Oh x Rp. 78,800.00 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900.00 = Rp. 919.00
- Mandor 0.050 Oh x Rp. 95,600.00 = Rp. 4,780.00
Jumlah (2) = Rp. 18,829.00
Jumlah (1) +(2) = Rp. 100,470.40

PK 6.53. 1 M Pasang lisplang ukuran 2 x (2 x 20) cm, kayu meranti :

6.53.1. Bahan
- Kayu meranti,papan 0.0086 M x Rp. 5,475,000.00 = Rp. 47,085.00
- Paku biasa 2" - 5" 0.060 Kg x Rp. 16,940.00 = Rp. 1,016.40
Jumlah (1) = Rp. 48,101.40
6.53.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500.00 = Rp. 5,250.00
- Tukang kayu 0.100 Oh x Rp. 78,800.00 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900.00 = Rp. 919.00
- Mandor 0.050 Oh x Rp. 95,600.00 = Rp. 4,780.00
Jumlah (2) = Rp. 18,829.00
Jumlah (1) +(2) = Rp. 66,930.40
PK 6.54. 1 M Pasang rangka dinding pemisah, kayu damar laut :

6.54.1. Bahan
- Kayu damar laut, balok 0.0195 M x Rp. 9,350,000.00 = Rp. 182,325.00
- Meranti batu, papan 0.007 M x Rp. 9,375,000.00 = Rp. 65,625.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 16,940.00 = Rp. 1,694.00
Jumlah (1) = Rp. 249,644.00
6.54.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500.00 = Rp. 7,875.00
- Tukang kayu 0.450 Oh x Rp. 78,800.00 = Rp. 35,460.00
- Kepala tukang 0.045 Oh x Rp. 91,900.00 = Rp. 4,135.50
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 54,640.50
Jumlah (1) +(2) = Rp. 304,284.50

PK 6.55. 1 M Pasang rangka dinding pemisah, kayu meranti :

6.55.1. Bahan
- Kayu meranti, balok 0.0195 M x Rp. 5,225,000.00 = Rp. 101,887.50
- Kayu meranti, papan 0.007 M x Rp. 5,475,000.00 = Rp. 38,325.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 16,940.00 = Rp. 1,694.00
Jumlah (1) = Rp. 141,906.50
6.55.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500.00 = Rp. 7,875.00
- Tukang kayu 0.450 Oh x Rp. 78,800.00 = Rp. 35,460.00
- Kepala tukang 0.045 Oh x Rp. 91,900.00 = Rp. 4,135.50
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 54,640.50
Jumlah (1) +(2) = Rp. 196,547.00

PK 6.56. 1 M Pasang dinding pemisah teakwood rangka, rangka kayu damar laut :

6.56.1. Bahan
- Kayu damar laut, balok 0.0195 M x Rp. 9,350,000.00 = Rp. 182,325.00
- Teakwood 4' x 8' 1.000 M x Rp. 54,450.00 = Rp. 54,450.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 16,940.00 = Rp. 1,694.00
Jumlah (1) = Rp. 238,469.00
6.56.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500.00 = Rp. 7,875.00
- Tukang kayu 0.450 Oh x Rp. 78,800.00 = Rp. 35,460.00
- Kepala tukang 0.045 Oh x Rp. 91,900.00 = Rp. 4,135.50
- Mandor 0.075 Oh x Rp. 95,600.00 = Rp. 7,170.00
Jumlah (2) = Rp. 54,640.50
Jumlah (1) +(2) = Rp. 293,109.50

PK 6.57. 1 M Pasang dinding pemisah double plywood, rangka kayu damar laut :

6.57.1. Bahan
- Kayu damar laut, balok 0.0195 M x Rp. 9,350,000.00 = Rp. 182,325.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 16,940.00 = Rp. 1,694.00
- Lem kayu 0.560 Lt x Rp. 37,400.00 = Rp. 20,944.00
- Plywood 4' x 8' x 4 mm 1.000 Lbr x Rp. 51,920.00 = Rp. 51,920.00
Jumlah (1) = Rp. 256,883.00
6.57.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500.00 = Rp. 10,500.00
- Tukang kayu 0.600 Oh x Rp. 78,800.00 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900.00 = Rp. 5,514.00
- Mandor 0.010 Oh x Rp. 95,600.00 = Rp. 956.00
Jumlah (2) = Rp. 64,250.00
Jumlah (1) +(2) = Rp. 321,133.00

PK 6.58. 1 M Pasang dinding lambrizering dari papan meranti :

6.58.1. Bahan
- Kayu meranti, papan 0.0120 M x Rp. 5,475,000.00 = Rp. 65,700.00
- Paku biasa 2" - 5" 0.100 Kg x Rp. 16,940.00 = Rp. 1,694.00
- Paku skrup 3,5" 0.150 Lbr x Rp. 21,180.00 = Rp. 3,177.00
Jumlah (1) = Rp. 70,571.00
6.58.2. Tenaga
- Pekerja 0.600 Oh x Rp. 52,500.00 = Rp. 31,500.00
- Tukang kayu 1.800 Oh x Rp. 78,800.00 = Rp. 141,840.00
- Kepala tukang 0.180 Oh x Rp. 91,900.00 = Rp. 16,542.00
- Mandor 0.030 Oh x Rp. 95,600.00 = Rp. 2,868.00
Jumlah (2) = Rp. 192,750.00
Jumlah (1) +(2) = Rp. 263,321.00

PK 6.59. 1 M Pasang plywood tebal 4 mm, untuk dinding :

6.59.1. Bahan

- Plywood 4' x 8' x 4 mm 0.4000 Lbr x Rp. 51,920.00 = Rp. 20,768.00


- Paku biasa 2" - 5" 0.050 Kg x Rp. 16,940.00 = Rp. 847.00
Jumlah (1) = Rp. 21,615.00
6.59.2. Tenaga

- Pekerja 0.025 Oh x Rp. 52,500.00 = Rp. 1,312.50


- Tukang kayu 0.075 Oh x Rp. 78,800.00 = Rp. 5,910.00
- Kepala tukang 0.0075 Oh x Rp. 91,900.00 = Rp. 689.25
- Mandor 0.0013 Oh x Rp. 95,600.00 = Rp. 124.28
Jumlah (2) = Rp. 8,036.03
Jumlah (1) +(2) = Rp. 29,651.03

PK 6.60. 1 M' Pasang list plafond kayu profil :

6.60.1. Bahan

- Kayu profil 2" 1.050 M' x Rp. 12,540.00 = Rp. 13,167.00


Jumlah (1) = Rp. 13,167.00
6.60.2. Tenaga

- Pekerja 0.021 Oh x Rp. 52,500.00 = Rp. 1,102.50


- Tukang kayu 0.021 Oh x Rp. 78,800.00 = Rp. 1,654.80
- Kepala tukang 0.002 Oh x Rp. 91,900.00 = Rp. 183.80
- Mandor 0.001 Oh x Rp. 95,600.00 = Rp. 95.60
Jumlah (2) = Rp. 3,036.70
Jumlah (1) +(2) = Rp. 16,203.70
ANALISA BIAYA KONSTRUKSI
PEKERJAAN BETON

PB 6.1. 1 M Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr

6.1.1 Bahan
- Semen portland 218.000 Kg x Rp. 1,270 = Rp. 276,860.00
- Pasir beton 0.520 M x Rp. 87,800 = Rp. 45,656.00
- Koral beton 5/7 0.870 M x Rp. 170,900 = Rp. 148,683.00
Jumlah (1) = Rp. 471,199.00

6.1.2. Tenaga
- Pekerja 1.650 Oh x Rp. 52,500 = Rp. 86,625.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.080 Oh x Rp. 95,600 = Rp. 7,648.00
Jumlah (2) = Rp. 116,270.50
Jumlah (1) + (2) = Rp. 587,469.50
PB 6.2. 1 M Membuat beton tumbuk, 1 Pc : 3 Ps : 6 Kr

6.2.1 Bahan
- Semen portland 197.000 Kg x Rp. 1,270 = Rp. 250,190.00
- Pasir beton 0.470 M x Rp. 87,800 = Rp. 41,266.00
- Koral beton 5/7 0.940 M x Rp. 170,900 = Rp. 160,646.00
Jumlah (1) = Rp. 452,102.00

6.2.2. Tenaga
- Pekerja 1.650 Oh x Rp. 52,500 = Rp. 86,625.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.080 Oh x Rp. 95,600 = Rp. 7,648.00
Jumlah (2) = Rp. 116,270.50
Jumlah (1) + (2) = Rp. 568,372.50

PB 6.3. 1 M Membuat beton tumbuk, 1 Pc : 4 Ps : 6 Kr

6.3.1 Bahan
- Semen portland 173.000 Kg x Rp. 1,270 = Rp. 219,710.00
- Pasir beton 0.570 M x Rp. 87,800 = Rp. 50,046.00
- Koral beton 5/7 0.870 M x Rp. 170,900 = Rp. 148,683.00
Jumlah (1) = Rp. 418,439.00

6.3.2. Tenaga
- Pekerja 1.650 Oh x Rp. 52,500 = Rp. 86,625.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.080 Oh x Rp. 95,600 = Rp. 7,648.00
Jumlah (2) = Rp. 116,270.50
Jumlah (1) + (2) = Rp. 534,709.50

PB 6.4. 1 M Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr, Tebal 5 Cm

6.4.1 Bahan
- Semen portland 10.000 Kg x Rp. 1,270 = Rp. 12,700.00
- Pasir beton 0.026 M x Rp. 87,800 = Rp. 2,282.80
- Koral beton 5/7 0.044 M x Rp. 170,900 = Rp. 7,519.60
Jumlah (1) = Rp. 22,502.40
6.4.2. Tenaga
- Pekerja 0.165 Oh x Rp. 52,500 = Rp. 8,662.50
- Tukang batu 0.025 Oh x Rp. 78,800 = Rp. 1,970.00
- Kepala tukang 0.002 Oh x Rp. 91,900 = Rp. 183.80
- Mandor 0.006 Oh x Rp. 95,600 = Rp. 573.60
Jumlah (2) = Rp. 11,389.90
Jumlah (1) + (2) = Rp. 33,892.30

PB 6.5. 1 M Membuat beton 1 Pc : 2 Ps : 3 Kr

6.5.1. Bahan
- Semen portland 232.000 Kg x Rp. 1,270 = Rp. 294,640.00
- Pasir beton 0.520 M x Rp. 87,800 = Rp. 45,656.00
- Koral beton 5/7 0.780 M x Rp. 170,900 = Rp. 133,302.00
Jumlah (1) = Rp. 473,598.00
6.5.2. Tenaga
- Pekerja 1.650 Oh x Rp. 52,500 = Rp. 86,625.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.080 Oh x Rp. 95,600 = Rp. 7,648.00
Jumlah (2) = Rp. 116,270.50
Jumlah (1) + (2) = Rp. 589,868.50

PB 6.6. 1 M Membuat beton 1 Pc : 2 Ps : 4 Kr

6.6.1. Bahan
- Semen portland 280.000 Kg x Rp. 1,270 = Rp. 355,600.00
- Pasir beton 0.450 M x Rp. 87,800 = Rp. 39,510.00
- Koral beton 3/5 0.900 M x Rp. 185,900 = Rp. 167,310.00
Jumlah (1) = Rp. 562,420.00
6.6.2. Tenaga
- Pekerja 1.650 Oh x Rp. 52,500 = Rp. 86,625.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.080 Oh x Rp. 95,600 = Rp. 7,648.00
Jumlah (2) = Rp. 116,270.50
Jumlah (1) + (2) = Rp. 678,690.50

PB 6.7. 1 M Membuat beton 1 Pc : 2 Ps : 2,5 Kr

6.7.1. Bahan
- Semen portland 352.000 Kg x Rp. 1,270 = Rp. 447,040.00
- Pasir beton 0.560 M x Rp. 87,800 = Rp. 49,168.00
- Koral beton 3/5 0.700 M x Rp. 185,900 = Rp. 130,130.00
Jumlah (1) = Rp. 626,338.00
6.7.2. Tenaga
- Pekerja 1.650 Oh x Rp. 52,500 = Rp. 86,625.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.080 Oh x Rp. 95,600 = Rp. 7,648.00
Jumlah (2) = Rp. 116,270.50
Jumlah (1) + (2) = Rp. 742,608.50

PB 6.8. 1 M Membuat beton 1 Pc : 1,5 Ps : 3 Kr

6.8.1. Bahan
- Semen portland 357.000 Kg x Rp. 1,270 = Rp. 453,390.00
- Pasir beton 0.420 M x Rp. 87,800 = Rp. 36,876.00
- Koral beton 3/5 0.540 M x Rp. 185,900 = Rp. 100,386.00
Jumlah (1) = Rp. 590,652.00
6.8.2. Tenaga
- Pekerja 1.650 Oh x Rp. 52,500 = Rp. 86,625.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.080 Oh x Rp. 95,600 = Rp. 7,648.00
Jumlah (2) = Rp. 116,270.50
Jumlah (1) + (2) = Rp. 706,922.50

PB 6.9. 1 M Membuat beton 1 Pc : 1,5 Ps : 2,5 Kr

6.9.1. Bahan
- Semen portland 386.000 Kg x Rp. 1,270 = Rp. 490,220.00
- Pasir beton 0.470 M x Rp. 87,800 = Rp. 41,266.00
- Koral beton 3/5 0.780 M x Rp. 185,900 = Rp. 145,002.00
Jumlah (1) = Rp. 676,488.00
6.9.2. Tenaga
- Pekerja 1.650 Oh x Rp. 52,500 = Rp. 86,625.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.080 Oh x Rp. 95,600 = Rp. 7,648.00
Jumlah (2) = Rp. 116,270.50
Jumlah (1) + (2) = Rp. 792,758.50

PB 6.10. 1 M Membuat beton 1 Pc : 1 Ps : 2 Kr

6.10.1. Bahan
- Semen portland 479.000 Kg x Rp. 1,270 = Rp. 608,330.00
- Pasir beton 0.370 M x Rp. 87,800 = Rp. 32,486.00
- Koral beton 3/5 0.740 M x Rp. 185,900 = Rp. 137,566.00
Jumlah (1) = Rp. 778,382.00

6.10.2. Tenaga
- Pekerja 1.650 Oh x Rp. 52,500 = Rp. 86,625.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.080 Oh x Rp. 95,600 = Rp. 7,648.00
Jumlah (2) = Rp. 116,270.50
Jumlah (1) + (2) = Rp. 894,652.50

PB 6.11. 1 M Membuat tiang pancang prestressed beton

6.11.1. Bahan
- Semen portland 440.000 Kg x Rp. 1,270 = Rp. 558,800.00
- Pasir beton 0.500 M x Rp. 87,800 = Rp. 43,900.00
- Koral beton/batu pecah 2/3 0.800 M x Rp. 177,700 = Rp. 142,160.00
- Rapidrant 2.460 Gln x Rp. = Rp. 0.00
Jumlah (1) = Rp. 744,860.00
6.11.2. Tenaga
- Pekerja 1.650 Oh x Rp. 52,500 = Rp. 86,625.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.080 Oh x Rp. 95,600 = Rp. 7,648.00
Jumlah (2) = Rp. 116,270.50
Jumlah (1) + (2) = Rp. 861,130.50

PB 6.12. 1 M Membuat beton dengan puzzdith - 100 XR

6.12.1. Bahan
- Semen portland 336.000 Kg x Rp. 1,270 = Rp. 426,720.00
- Pasir beton 0.540 M x Rp. 87,800 = Rp. 47,412.00
- Koral beton 0.810 M x Rp. 185,900 = Rp. 150,579.00
- Puzzdith - 100 XR 1.000 Ltr x Rp. = Rp. 0.00
Jumlah (1) = Rp. 624,711.00
6.12.2. Tenaga
- Pekerja 1.650 Oh x Rp. 52,500 = Rp. 86,625.00
- Tukang batu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.080 Oh x Rp. 95,600 = Rp. 7,648.00
Jumlah (2) = Rp. 116,270.50
Jumlah (1) + (2) = Rp. 740,981.50

PB 6.13. 1 M Membuat beton 1 Pc : 2 Ps : 3 Kr

6.13.1. Bahan
- Semen portland 336.000 Kg x Rp. 1,270 = Rp. 426,720.00
- Pasir beton 0.540 M x Rp. 87,800 = Rp. 47,412.00
- Koral beton/batu pecah 2/3 0.810 M x Rp. 177,700 = Rp. 143,937.00
Jumlah (1) = Rp. 618,069.00
6.13.2. Tenaga
- Pekerja 2.000 Oh x Rp. 52,500 = Rp. 105,000.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 1.000 Oh x Rp. 95,600 = Rp. 95,600.00
Jumlah (2) = Rp. 231,396.50
Jumlah (1) + (2) = Rp. 849,465.50

PB 6.14. 1 M Membuat beton 1 Pc : 2 Ps : 4 Kr

6.14.1. Bahan
- Semen portland 291.000 Kg x Rp. 1,270 = Rp. 369,570.00
- Pasir beton 0.470 M x Rp. 87,800 = Rp. 41,266.00
- Koral beton/batu pecah 2/3 0.930 M x Rp. 177,700 = Rp. 165,261.00
Jumlah (1) = Rp. 576,097.00
6.14.2. Tenaga
- Pekerja 2.000 Oh x Rp. 52,500 = Rp. 105,000.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 1.000 Oh x Rp. 95,600 = Rp. 95,600.00
Jumlah (2) = Rp. 231,396.50
Jumlah (1) + (2) = Rp. 807,493.50

PB 6.15. 1 M Membuat beton 1 Pc : 1,5 Ps : 3 Kr

6.15.1. Bahan
- Semen portland 367.000 Kg x Rp. 1,270 = Rp. 466,090.00
- Pasir beton 0.440 M x Rp. 87,800 = Rp. 38,632.00
- Koral beton 2/3 0.880 M x Rp. 177,700 = Rp. 156,376.00
Jumlah (1) = Rp. 661,098.00

6.15.2. Tenaga

- Pekerja 2.000 Oh x Rp. 52,500 = Rp. 105,000.00


- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 1.000 Oh x Rp. 95,600 = Rp. 95,600.00
Jumlah (2) = Rp. 231,396.50
Jumlah (1) + (2) = Rp. 892,494.50

PB 6.16. 1 M Membuat beton 1 Pc : 1,5 Ps : 2,5 Kr

6.16.1. Bahan
- Semen portland 400.000 Kg x Rp. 1,270 = Rp. 508,000.00
- Pasir beton 0.480 M x Rp. 87,800 = Rp. 42,144.00
- Koral beton 2/3 0.880 M x Rp. 177,700 = Rp. 156,376.00
Jumlah (1) = Rp. 706,520.00
6.16.2. Tenaga
- Pekerja 2.000 Oh x Rp. 52,500 = Rp. 105,000.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 1.000 Oh x Rp. 95,600 = Rp. 95,600.00
Jumlah (2) = Rp. 231,396.50
Jumlah (1) + (2) = Rp. 937,916.50

PB 6.17. 1 M Membuat beton 1 Pc : 1 Ps : 1 Kr

6.17.1. Bahan
- Semen portland 615.000 Kg x Rp. 1,270 = Rp. 781,050.00
- Pasir beton 0.520 M x Rp. 87,800 = Rp. 45,656.00
- Koral beton 2/3 0.520 M x Rp. 177,700 = Rp. 92,404.00
Jumlah (1) = Rp. 919,110.00
6.17.2. Tenaga
- Pekerja 2.000 Oh x Rp. 75,000 = Rp. 150,000.00
- Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Kepala tukang 0.035 Oh x Rp. 125,000 = Rp. 4,375.00
- Mandor 1.000 Oh x Rp. 135,000 = Rp. 135,000.00
Jumlah (2) = Rp. 324,375.00
Jumlah (1) + (2) = Rp. 1,243,485.00

PB 6.18. 1 M Membuat beton kedap air dengan strorox - 100

6.18.1. Bahan
- Semen portland 400.000 Kg x Rp. 1,270 = Rp. 508,000.00
- Pasir beton 0.480 M x Rp. 87,800 = Rp. 42,144.00
- Koral beton 2/3 0.800 M x Rp. 177,700 = Rp. 142,160.00
- Strorox - 100 1.200 M x Rp. = Rp. 0.00
Jumlah (1) = Rp. 692,304.00

6.18.2. Tenaga
- Pekerja 2.000 Oh x Rp. 75,000 = Rp. 150,000.00
- Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Kepala tukang 0.035 Oh x Rp. 125,000 = Rp. 4,375.00
- Mandor 1.000 Oh x Rp. 135,000 = Rp. 135,000.00
Jumlah (2) = Rp. 324,375.00
Jumlah (1) + (2) = Rp. 1,016,679.00

PB 6.19. 1 M' Memasang PVC Waterstop lebar 150 mm

6.19.1. Bahan
- Waterstop lebar 150 mm 1.050 M' x Rp. = Rp. 0.00
Jumlah (1) = Rp. 0.00

6.19.2. Tenaga
- Pekerja 0.050 Oh x Rp. 75,000 = Rp. 3,750.00
- Tukang batu 0.030 Oh x Rp. 100,000 = Rp. 3,000.00
- Kepala tukang 0.003 Oh x Rp. 125,000 = Rp. 375.00
- Mandor 0.002 Oh x Rp. 135,000 = Rp. 270.00
Jumlah (2) = Rp. 7,395.00
Jumlah (1) + (2) = Rp. 7,395.00

PB 6.20. 1 M' Memasang PVC Waterstop lebar 200 mm

6.20.1. Bahan
- Waterstop lebar 200 mm 1.050 M' x Rp. = Rp. 0.00
Jumlah (1) = Rp. 0.00

6.20.2. Tenaga
- Pekerja 0.050 Oh x Rp. 75,000 = Rp. 3,750.00
- Tukang batu 0.035 Oh x Rp. 100,000 = Rp. 3,500.00
- Kepala tukang 0.0035 Oh x Rp. 125,000 = Rp. 437.50
- Mandor 0.002 Oh x Rp. 135,000 = Rp. 270.00
Jumlah (2) = Rp. 7,957.50
Jumlah (1) + (2) = Rp. 7,957.50

PB 6.21. 1 M' Memasang PVC Waterstop lebar 230 mm

6.21.1. Bahan
- Waterstop lebar 230 mm 1.050 M' x Rp. = Rp. 0.00
Jumlah (1) = Rp. 0.00
6.21.2. Tenaga
- Pekerja 0.550 Oh x Rp. 75,000 = Rp. 41,250.00
- Tukang batu 0.035 Oh x Rp. 100,000 = Rp. 3,500.00
- Mandor 0.002 Oh x Rp. 135,000 = Rp. 270.00
Jumlah (2) = Rp. 45,020.00
Jumlah (1) + (2) = Rp. 45,020.00

PB 6.22. 1 M' Memasang PVC Waterstop lebar 250 mm

6.22.1. Bahan
- Waterstop lebar 250 mm 1.050 M' x Rp. = Rp. 0.00
Jumlah (1) = Rp. 0.00

6.22.2. Tenaga
- Pekerja 0.550 Oh x Rp. 75,000 = Rp. 41,250.00
- Tukang batu 0.035 Oh x Rp. 100,000 = Rp. 3,500.00
- Mandor 0.003 Oh x Rp. 135,000 = Rp. 405.00
Jumlah (2) = Rp. 45,155.00
Jumlah (1) + (2) = Rp. 45,155.00

PB 6.23. 1 M' Memasang PVC Waterstop lebar 300 mm

6.23.1. Bahan
- Waterstop lebar 300 mm 1.050 M' x Rp. = Rp. 0.00
Jumlah (1) = Rp. 0.00

6.23.2. Tenaga
- Pekerja 0.300 Oh x Rp. 75,000 = Rp. 22,500.00
- Tukang batu 0.260 Oh x Rp. 100,000 = Rp. 26,000.00
- Kepala tukang 0.026 Oh x Rp. 125,000 = Rp. 3,250.00
- Mandor 0.005 Oh x Rp. 135,000 = Rp. 675.00
Jumlah (2) = Rp. 52,425.00
Jumlah (1) + (2) = Rp. 52,425.00

PB 6.25 1 Kg Pembesian dengan Besi polos

6.25.1 Bahan
Besi beton polos 1.050 Kg x Rp. 14,410 = Rp. 15,130.50
Kawat beton 0.015 Kg x Rp. 16,830 = Rp. 252.45
Jumlah (1) = Rp. 15,382.95

6.25.2 Tenaga
Pekerja 0.007 Oh x Rp. 75,000 = Rp. 525.00
Tukang besi 0.007 Oh x Rp. 78,800 = Rp. 551.60
Kepala tukang 0.007 Oh x Rp. 125,000 = Rp. 875.00
Mandor 0.003 Oh x Rp. 135,000 = Rp. 405.00
Jumlah (2) = Rp. 2,356.60
Jumlah (1) + (2) = Rp. 17,739.55

PB 6.26 1 M Kabel Presstressed polos / strands

6.26.1 Bahan
Besi Presstressed polos 1.050 Kg x Rp. 14,410 = Rp. 15,130.50
Kawat beton 0.010 Kg x Rp. 16,830 = Rp. 168.30
Jumlah (1) = Rp. 15,298.80

6.26.2 Tenaga
Pekerja 0.005 Oh x Rp. 75,000 = Rp. 375.00
Tukang besi 0.005 Oh x Rp. 78,800 = Rp. 394.00
Kepala tukang 0.005 Oh x Rp. 125,000 = Rp. 625.00
Mandor 0.003 Oh x Rp. 135,000 = Rp. 405.00
Jumlah (2) = Rp. 1,799.00
Jumlah (1) + (2) = Rp. 17,097.80

PB 6.28 1 M Pasang bekisting untuk pondasi

6.28.1 Bahan
Kayu sembarang 0.040 M x Rp. 3,107,500 = Rp. 124,300.00
Paku biasa 2" - 5" 0.300 Kg x Rp. 14,520 = Rp. 4,356.00
Minyak bekisting 0.100 Ltr x Rp. 6,290 = Rp. 629.00
Jumlah (1) = Rp. 129,285.00

6.28.2 Tenaga
Pekerja 0.300 Oh x Rp. 75,000 = Rp. 22,500.00
Tukang besi 0.260 Oh x Rp. 78,800 = Rp. 20,488.00
Kepala tukang 0.026 Oh x Rp. 125,000 = Rp. 3,250.00
Mandor 0.005 Oh x Rp. 135,000 = Rp. 675.00
Jumlah (2) = Rp. 46,913.00
Jumlah (1) + (2) = Rp. 176,198.00

PB 6.29. 1 M Pasang bekisting untuk sloof

6.29.1. Bahan
- Kayu sembarang 0.045 M x Rp. 3,107,500 = Rp. 139,837.50
- Paku biasa 2' - 5" 0.300 Kg x Rp. 14,520 = Rp. 4,356.00
- Minyak bekisting 0.100 Lt x Rp. 6,290 = Rp. 629.00
Jumlah (1) = Rp. 144,822.50

6.29.2. Tenaga
- Pekerja 0.300 Oh x Rp. 75,000 = Rp. 22,500.00
- Tukang batu 0.260 Oh x Rp. 100,000 = Rp. 26,000.00
- Kepala tukang 0.026 Oh x Rp. 125,000 = Rp. 3,250.00
- Mandor 0.005 Oh x Rp. 135,000 = Rp. 675.00
Jumlah (2) = Rp. 52,425.00
Jumlah (1) + (2) = Rp. 197,247.50
PB 6.30. 1 M Pasang bekisting untuk kolom

6.30.1. Bahan
- Kayu sembarang 0.040 M x Rp. 3,107,500 = Rp. 124,300.00
- Paku biasa 2' - 5" 0.400 Kg x Rp. 14,520 = Rp. 5,808.00
- Minyak bekisting 0.200 Lt x Rp. 6,290 = Rp. 1,258.00
- Balok kayu sembarang 0.015 M x Rp. 3,107,500 = Rp. 46,612.50
- Plywood tebal 9 mm 0.350 Lbr x Rp. 116,820 = Rp. 40,887.00
- Kayu dolken/Laut 3"-4"/4 m 2.000 Btg x Rp. 19,250 = Rp. 38,500.00
Jumlah (1) = Rp. 257,365.50

6.30.2. Tenaga
- Pekerja 0.300 Oh x Rp. 75,000 = Rp. 22,500.00
- Tukang batu 0.330 Oh x Rp. 100,000 = Rp. 33,000.00
- Kepala tukang 0.033 Oh x Rp. 125,000 = Rp. 4,125.00
- Mandor 0.006 Oh x Rp. 135,000 = Rp. 810.00
Jumlah (2) = Rp. 60,435.00
Jumlah (1) + (2) = Rp. 317,800.50

PB 6.31. 1 M Pasang bekisting untuk balok

6.31.1. Bahan
- Kayu sembarang 0.040 M x Rp. 3,107,500 = Rp. 124,300.00
- Paku biasa 2' - 5" 0.400 Kg x Rp. 14,520 = Rp. 5,808.00
- Minyak bekisting 0.200 Lt x Rp. 6,290 = Rp. 1,258.00
- Balok kayu sembarang 0.018 M x Rp. 3,107,500 = Rp. 55,935.00
- Plywood tebal 9 mm 0.350 Lbr x Rp. 116,820 = Rp. 40,887.00
- Kayu dolken/Laut 3"-4"/4 m 2.000 Btg x Rp. 19,250 = Rp. 38,500.00
Jumlah (1) = Rp. 266,688.00

6.31.2. Tenaga
- Pekerja 0.320 Oh x Rp. 75,000 = Rp. 24,000.00
- Tukang batu 0.330 Oh x Rp. 100,000 = Rp. 33,000.00
- Kepala tukang 0.033 Oh x Rp. 125,000 = Rp. 4,125.00
- Mandor 0.006 Oh x Rp. 135,000 = Rp. 810.00
Jumlah (2) = Rp. 61,935.00
Jumlah (1) + (2) = Rp. 328,623.00

PB 6.32. 1 M Pasang bekisting untuk lantai

6.32.1. Bahan
- Kayu sembarang 0.040 M x Rp. 3,107,500 = Rp. 124,300.00
- Paku biasa 2' - 5" 0.400 Kg x Rp. 14,520 = Rp. 5,808.00
- Minyak bekisting 0.200 Lt x Rp. 6,290 = Rp. 1,258.00
- Balok kayu sembarang 0.015 M x Rp. 3,107,500 = Rp. 46,612.50
- Plywood tebal 9 mm 0.350 Lbr x Rp. 116,820 = Rp. 40,887.00
- Kayu dolken/Laut 3"-4"/4 m 6.000 Btg x Rp. 19,250 = Rp. 115,500.00
Jumlah (1) = Rp. 334,365.50
6.32.2. Tenaga
- Pekerja 0.320 Oh x Rp. 75,000 = Rp. 24,000.00
- Tukang batu 0.330 Oh x Rp. 100,000 = Rp. 33,000.00
- Kepala tukang 0.033 Oh x Rp. 125,000 = Rp. 4,125.00
- Mandor 0.006 Oh x Rp. 135,000 = Rp. 810.00
Jumlah (2) = Rp. 61,935.00
Jumlah (1) + (2) = Rp. 396,300.50

PB 6.33. 1 M Pasang bekisting untuk dinding

6.33.1. Bahan
- Kayu sembarang 0.030 M x Rp. 3,107,500 = Rp. 93,225.00
- Paku biasa 2' - 5" 0.400 Kg x Rp. 14,520 = Rp. 5,808.00
- Minyak bekisting 0.200 Lt x Rp. 6,290 = Rp. 1,258.00
- Balok kayu sembarang 0.020 M x Rp. 3,107,500 = Rp. 62,150.00
- Plywood tebal 9 mm 0.350 Lbr x Rp. 116,820 = Rp. 40,887.00
- Kayu dolken/Laut 3"-4"/4 m 3.000 Btg x Rp. 19,250 = Rp. 57,750.00
- Formtie/penjaga jarak bekisting/spacer 4.000 Btg x Rp. 5,000 = Rp. 20,000.00
Jumlah (1) = Rp. 281,078.00

6.33.2. Tenaga
- Pekerja 0.320 Oh x Rp. 75,000 = Rp. 24,000.00
- Tukang batu 0.330 Oh x Rp. 100,000 = Rp. 33,000.00
- Kepala tukang 0.033 Oh x Rp. 125,000 = Rp. 4,125.00
- Mandor 0.006 Oh x Rp. 135,000 = Rp. 810.00
Jumlah (2) = Rp. 61,935.00
Jumlah (1) + (2) = Rp. 343,013.00

PB 6.34. 1 M Pasang bekisting untuk tangga

6.34.1. Bahan
- Kayu sembarang 0.030 M x Rp. 3,107,500 = Rp. 93,225.00
- Paku biasa 2' - 5" 0.400 Kg x Rp. 14,520 = Rp. 5,808.00
- Minyak bekisting 0.150 Lt x Rp. 6,290 = Rp. 943.50
- Balok kayu sembarang 0.015 M x Rp. 3,107,500 = Rp. 46,612.50
- Plywood tebal 9 mm 0.350 Lbr x Rp. 116,820 = Rp. 40,887.00
- Kayu dolken/Laut 3"-4"/4 m 2.000 Btg x Rp. 19,250 = Rp. 38,500.00
Jumlah (1) = Rp. 225,976.00

6.34.2. Tenaga
- Pekerja 0.320 Oh x Rp. 75,000 = Rp. 24,000.00
- Tukang batu 0.330 Oh x Rp. 100,000 = Rp. 33,000.00
- Kepala tukang 0.033 Oh x Rp. 125,000 = Rp. 4,125.00
- Mandor 0.006 Oh x Rp. 135,000 = Rp. 810.00
Jumlah (2) = Rp. 61,935.00
Jumlah (1) + (2) = Rp. 287,911.00
PB 6.35. 1 M Pasang beton dengan mutu K 225

6.35.1. Bahan
- Semen portland 388.000 Kg x Rp. 1,270 = Rp. 492,760.00
- Pasir beton 0.650 M x Rp. 87,800 = Rp. 57,070.00
- Batu pecah 0.650 M x Rp. 190,200 = Rp. 123,630.00
Jumlah (1) = Rp. 673,460.00

6.35.2. Tenaga
- Pekerja 6.000 Oh x Rp. 75,000 = Rp. 450,000.00
- Tukang batu 1.000 Oh x Rp. 100,000 = Rp. 100,000.00
- Kepala tukang 0.100 Oh x Rp. 125,000 = Rp. 12,500.00
- Mandor 0.300 Oh x Rp. 135,000 = Rp. 40,500.00
Jumlah (2) = Rp. 603,000.00
Jumlah (1) + (2) = Rp. 1,276,460.00

PB 6.36. 1 M Pasang beton dengan mutu K 275

6.36.1. Bahan
- Semen portland 400.000 Kg x Rp. 1,270 = Rp. 508,000.00
- Pasir beton 0.400 M x Rp. 87,800 = Rp. 35,120.00
- Koral beton 0.820 M x Rp. 190,200 = Rp. 155,964.00
Jumlah (1) = Rp. 699,084.00

6.36.2. Tenaga
- Pekerja 6.000 Oh x Rp. 75,000 = Rp. 450,000.00
- Tukang batu 1.000 Oh x Rp. 100,000 = Rp. 100,000.00
- Kepala tukang 0.100 Oh x Rp. 125,000 = Rp. 12,500.00
- Mandor 0.300 Oh x Rp. 135,000 = Rp. 40,500.00
Jumlah (2) = Rp. 603,000.00
Jumlah (1) + (2) = Rp. 1,302,084.00

PB 6.37. 1 M Pasang jembatan cor

6.37.1. Bahan
- Kayu sembarang 0.0264 M x Rp. 3,107,500 = Rp. 82,038.00
- Paku biasa 2" - 5 " 0.600 Kg x Rp. 14,520 = Rp. 8,712.00
- Kayu dolken/Laut 3"-4"/4 m 0.500 Btg x Rp. 19,250 = Rp. 9,625.00
Jumlah (1) = Rp. 100,375.00

6.37.2. Tenaga
- Pekerja 0.150 Oh x Rp. 75,000 = Rp. 11,250.00
- Tukang batu 0.050 Oh x Rp. 100,000 = Rp. 5,000.00
- Kepala tukang 0.005 Oh x Rp. 125,000 = Rp. 625.00
- Mandor 0.007 Oh x Rp. 135,000 = Rp. 945.00
Jumlah (2) = Rp. 17,820.00
Jumlah (1) + (2) = Rp. 118,195.00
PB 6.38. 1 M Membuat pondasi beton bertulang (150 kg besi + bekisting)

6.38.1. Bahan
- Kayu sembarang 0.2000 M x Rp. 3,107,500 = Rp. 621,500.00
- Paku biasa 2" - 5 " 1.500 Kg x Rp. 14,520 = Rp. 21,780.00
- Minyak bekisting 0.400 Lt x Rp. 6,290 = Rp. 2,516.00
- Besi beton polos 150.000 Kg x Rp. 14,410 = Rp. 2,161,500.00
- Kawat beton 2.250 Kg x Rp. 16,830 = Rp. 37,867.50
- Semen portland 323.000 Kg x Rp. 1,270 = Rp. 410,210.00
- Pasir beton 0.520 M x Rp. 87,800 = Rp. 45,656.00
- Koral beton 0.780 M x Rp. 190,200 = Rp. 148,356.00
Jumlah (1) = Rp. 3,449,385.50

6.38.2. Tenaga
- Pekerja 3.900 Oh x Rp. 75,000 = Rp. 292,500.00
- Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Tukang kayu 1.040 Oh x Rp. 100,000 = Rp. 104,000.00
- Tukang besi 1.050 Oh x Rp. 100,000 = Rp. 105,000.00
- Kepala tukang 0.245 Oh x Rp. 125,000 = Rp. 30,625.00
- Mandor 0.165 Oh x Rp. 135,000 = Rp. 22,275.00
Jumlah (2) = Rp. 589,400.00
Jumlah (1) + (2) = Rp. 4,038,785.50

PB 6.39. 1 M Membuat sloof beton bertulang (200 kg besi + bekisting)

6.39.1. Bahan
- Kayu sembarang 0.2700 M x Rp. 3,107,500 = Rp. 839,025.00
- Paku biasa 2" - 5 " 2.000 Kg x Rp. 14,520 = Rp. 29,040.00
- Minyak bekisting 0.600 Lt x Rp. 6,290 = Rp. 3,774.00
- Besi beton polos 200.000 Kg x Rp. 14,410 = Rp. 2,882,000.00
- Kawat beton 3.000 Kg x Rp. 16,830 = Rp. 50,490.00
- Semen portland 323.000 Kg x Rp. 1,270 = Rp. 410,210.00
- Pasir beton 0.520 M x Rp. 87,800 = Rp. 45,656.00
- Koral beton 0.780 M x Rp. 190,200 = Rp. 148,356.00
Jumlah (1) = Rp. 4,408,551.00

6.39.2. Tenaga
- Pekerja 4.850 Oh x Rp. 75,000 = Rp. 363,750.00
- Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Tukang kayu 1.560 Oh x Rp. 100,000 = Rp. 156,000.00
- Tukang besi 1.400 Oh x Rp. 100,000 = Rp. 140,000.00
- Kepala tukang 0.331 Oh x Rp. 125,000 = Rp. 41,375.00
- Mandor 0.170 Oh x Rp. 135,000 = Rp. 22,950.00
Jumlah (2) = Rp. 759,075.00
Jumlah (1) + (2) = Rp. 5,167,626.00
PB 6.40. 1 M Membuat kolom beton bertulang (300 kg besi + bekisting)

6.40.1. Bahan
- Kayu sembarang 0.4000 M x Rp. 3,107,500 = Rp. 1,243,000.00
- Paku biasa 2" - 5 " 4.000 Kg x Rp. 14,520 = Rp. 58,080.00
- Minyak bekisting 2.000 Lt x Rp. 6,290 = Rp. 12,580.00
- Besi beton polos 300.000 Kg x Rp. 14,410 = Rp. 4,323,000.00
- Kawat beton 4.500 Kg x Rp. 16,830 = Rp. 75,735.00
- Semen portland 323.000 Kg x Rp. 1,270 = Rp. 410,210.00
- Pasir beton 0.520 M x Rp. 87,800 = Rp. 45,656.00
- Koral beton 0.780 M x Rp. 190,200 = Rp. 148,356.00
- Kayu sembarang balok 0.150 M x Rp. 3,107,500 = Rp. 466,125.00
- Plywood 9 mm 3.500 Lbr x Rp. 116,820 = Rp. 408,870.00
- Kayu dolken/Laut 3"-4"/4 m 20.000 Btg x Rp. 19,250 = Rp. 385,000.00
Jumlah (1) = Rp. 7,576,612.00

6.40.2. Tenaga
- Pekerja 7.300 Oh x Rp. 75,000 = Rp. 547,500.00
- Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Tukang kayu 3.300 Oh x Rp. 100,000 = Rp. 330,000.00
- Tukang besi 2.100 Oh x Rp. 100,000 = Rp. 210,000.00
- Kepala tukang 0.570 Oh x Rp. 125,000 = Rp. 71,250.00
- Mandor 0.250 Oh x Rp. 135,000 = Rp. 33,750.00
Jumlah (2) = Rp. 1,227,500.00
Jumlah (1) + (2) = Rp. 8,804,112.00

PB 6.41. 1 M Membuat balok beton bertulang (200 kg besi + bekisting)

6.41.1. Bahan
- Kayu sembarang 0.3200 M x Rp. 3,107,500 = Rp. 994,400.00
- Paku biasa 2" - 5 " 3.200 Kg x Rp. 14,520 = Rp. 46,464.00
- Minyak bekisting 1.600 Lt x Rp. 6,290 = Rp. 10,064.00
- Besi beton polos 200.000 Kg x Rp. 14,410 = Rp. 2,882,000.00
- Kawat beton 3.000 Kg x Rp. 16,830 = Rp. 50,490.00
- Semen portland 323.000 Kg x Rp. 1,270 = Rp. 410,210.00
- Pasir beton 0.520 M x Rp. 87,800 = Rp. 45,656.00
- Koral beton 0.780 M x Rp. 190,200 = Rp. 148,356.00
- Kayu sembarang balok 0.140 M x Rp. 3,107,500 = Rp. 435,050.00
- Plywood 9 mm 2.800 Lbr x Rp. 116,820 = Rp. 327,096.00
- Kayu dolken/Laut 3"-4"/4 m 16.000 Btg x Rp. 19,250 = Rp. 308,000.00
Jumlah (1) = Rp. 5,657,786.00

6.41.2. Tenaga
- Pekerja 5.960 Oh x Rp. 75,000 = Rp. 447,000.00
- Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Tukang kayu 2.800 Oh x Rp. 100,000 = Rp. 280,000.00
- Tukang besi 1.400 Oh x Rp. 100,000 = Rp. 140,000.00
- Kepala tukang 0.455 Oh x Rp. 125,000 = Rp. 56,875.00
- Mandor 0.208 Oh x Rp. 135,000 = Rp. 28,080.00
Jumlah (2) = Rp. 986,955.00
Jumlah (1) + (2) = Rp. 6,644,741.00

PB 6.42. 1 M Membuat balok beton bertulang (150 kg besi + bekisting)

6.42.1. Bahan
- Kayu sembarang 0.320 M x Rp. 3,107,500 = Rp. 994,400.00
- Paku biasa 2" - 5 " 3.200 Kg x Rp. 14,520 = Rp. 46,464.00
- Minyak bekisting 1.600 Lt x Rp. 6,290 = Rp. 10,064.00
- Besi beton polos 150.000 Kg x Rp. 14,410 = Rp. 2,161,500.00
- Kawat beton 2.250 Kg x Rp. 16,830 = Rp. 37,867.50
- Semen portland 323.000 Kg x Rp. 1,270 = Rp. 410,210.00
- Pasir beton 0.520 M x Rp. 87,800 = Rp. 45,656.00
- Koral beton 0.780 M x Rp. 190,200 = Rp. 148,356.00
- Kayu sembarang balok 0.120 M x Rp. 3,107,500 = Rp. 372,900.00
- Plywood 9 mm 2.800 Lbr x Rp. 116,820 = Rp. 327,096.00
- Kayu dolken/Laut 3"-4"/4 m 32.000 Btg x Rp. 19,250 = Rp. 616,000.00
Jumlah (1) = Rp. 5,170,513.50
6.42.2. Tenaga
- Pekerja 5.800 Oh x Rp. 75,000 = Rp. 435,000.00
- Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Tukang kayu 2.800 Oh x Rp. 100,000 = Rp. 280,000.00
- Tukang besi 1.050 Oh x Rp. 100,000 = Rp. 105,000.00
- Kepala tukang 0.420 Oh x Rp. 125,000 = Rp. 52,500.00
- Mandor 0.185 Oh x Rp. 135,000 = Rp. 24,975.00
Jumlah (2) = Rp. 932,475.00
Jumlah (1) + (2) = Rp. 6,102,988.50

PB 6.43. 1 M Membuat dinding beton bertulang (150 kg besi + bekisting)

6.43.1. Bahan
- Kayu sembarang 0.240 M x Rp. 3,107,500 = Rp. 745,800.00
- Paku biasa 2" - 5 " 3.200 Kg x Rp. 14,520 = Rp. 46,464.00
- Minyak bekisting 1.600 Lt x Rp. 6,290 = Rp. 10,064.00
- Besi beton polos 150.000 Kg x Rp. 14,410 = Rp. 2,161,500.00
- Kawat beton 2.250 Kg x Rp. 16,830 = Rp. 37,867.50
- Semen portland 323.000 Kg x Rp. 1,270 = Rp. 410,210.00
- Pasir beton 0.520 M x Rp. 87,800 = Rp. 45,656.00
- Koral beton 0.780 M x Rp. 190,200 = Rp. 148,356.00
- Kayu sembarang balok 0.160 M x Rp. 3,107,500 = Rp. 497,200.00
- Plywood 9 mm 2.800 Lbr x Rp. 116,820 = Rp. 327,096.00
- Kayu dolken/Laut 3"-4"/4 m 24.000 Btg x Rp. 19,250 = Rp. 462,000.00
Jumlah (1) = Rp. 4,892,213.50

6.43.2. Tenaga
- Pekerja 5.600 Oh x Rp. 75,000 = Rp. 420,000.00
- Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Tukang kayu 2.640 Oh x Rp. 100,000 = Rp. 264,000.00
- Tukang besi 1.050 Oh x Rp. 100,000 = Rp. 105,000.00
- Kepala tukang 0.400 Oh x Rp. 125,000 = Rp. 50,000.00
- Mandor 0.193 Oh x Rp. 135,000 = Rp. 26,055.00
Jumlah (2) = Rp. 900,055.00
Jumlah (1) + (2) = Rp. 5,792,268.50

PB 6.44. 1 M Membuat tangga beton bertulang (150 kg besi + bekisting)

6.44.1. Bahan
- Kayu sembarang 0.250 M x Rp. 3,107,500 = Rp. 776,875.00
- Paku biasa 2" - 5 " 3.000 Kg x Rp. 14,520 = Rp. 43,560.00
- Minyak bekisting 1.200 Lt x Rp. 6,290 = Rp. 7,548.00
- Besi beton polos 200.000 Kg x Rp. 14,410 = Rp. 2,882,000.00
- Kawat beton 3.000 Kg x Rp. 16,830 = Rp. 50,490.00
- Semen portland 323.000 Kg x Rp. 1,270 = Rp. 410,210.00
- Pasir beton 0.520 M x Rp. 87,800 = Rp. 45,656.00
- Koral beton 0.780 M x Rp. 190,200 = Rp. 148,356.00
- Kayu sembarang balok 0.105 M x Rp. 3,107,500 = Rp. 326,287.50
- Plywood 9 mm 2.500 Lbr x Rp. 116,820 = Rp. 292,050.00
- Kayu dolken/Laut 3"-4"/4 m 14.000 Btg x Rp. 19,250 = Rp. 269,500.00
Jumlah (1) = Rp. 5,252,532.50

6.44.2. Tenaga
- Pekerja 5.600 Oh x Rp. 75,000 = Rp. 420,000.00
- Tukang batu 0.350 Oh x Rp. 100,000 = Rp. 35,000.00
- Tukang kayu 2.300 Oh x Rp. 100,000 = Rp. 230,000.00
- Tukang besi 1.400 Oh x Rp. 100,000 = Rp. 140,000.00
- Kepala tukang 0.405 Oh x Rp. 125,000 = Rp. 50,625.00
- Mandor 0.202 Oh x Rp. 135,000 = Rp. 27,270.00
Jumlah (2) = Rp. 902,895.00
Jumlah (1) + (2) = Rp. 6,155,427.50

PB 6.45. 1 M' Membuat kolom penguat beton bertulang (11 x 11) cm

6.45.1. Bahan
- Kayu sembarang 0.002 M x Rp. 3,107,500 = Rp. 6,215.00
- Paku biasa 2" - 5 " 0.010 Kg x Rp. 14,520 = Rp. 145.20
- Besi beton polos 3.000 Kg x Rp. 14,410 = Rp. 43,230.00
- Kawat beton 0.450 Kg x Rp. 16,830 = Rp. 7,573.50
- Semen portland 4.000 Kg x Rp. 1,270 = Rp. 5,080.00
- Pasir beton 0.006 M x Rp. 87,800 = Rp. 526.80
- Koral beton 0.009 M x Rp. 190,200 = Rp. 1,711.80
Jumlah (1) = Rp. 64,482.30

6.45.2. Tenaga
- Pekerja 0.060 Oh x Rp. 75,000 = Rp. 4,500.00
- Tukang batu 0.020 Oh x Rp. 100,000 = Rp. 2,000.00
- Tukang kayu 0.020 Oh x Rp. 100,000 = Rp. 2,000.00
- Tukang besi 0.020 Oh x Rp. 100,000 = Rp. 2,000.00
- Kepala tukang 0.006 Oh x Rp. 125,000 = Rp. 750.00
- Mandor 0.003 Oh x Rp. 135,000 = Rp. 405.00
Jumlah (2) = Rp. 11,655.00
Jumlah (1) + (2) = Rp. 76,137.30

PB 6.46. 1 M' Membuat ring balok beton bertulang (10 x 15) cm

6.46.1. Bahan
- Kayu sembarang 0.003 M x Rp. 3,107,500 = Rp. 9,322.50
- Paku biasa 2" - 5 " 0.020 Kg x Rp. 14,520 = Rp. 290.40
- Besi beton polos 3.600 Kg x Rp. 14,410 = Rp. 51,876.00
- Kawat beton 0.050 Kg x Rp. 16,830 = Rp. 841.50
- Semen portland 5.500 Kg x Rp. 1,270 = Rp. 6,985.00
- Pasir beton 0.009 M x Rp. 87,800 = Rp. 790.20
- Koral beton 0.015 M x Rp. 190,200 = Rp. 2,853.00
Jumlah (1) = Rp. 72,958.60

6.46.2. Tenaga
- Pekerja 0.100 Oh x Rp. 75,000 = Rp. 7,500.00
- Tukang batu 0.033 Oh x Rp. 100,000 = Rp. 3,300.00
- Tukang kayu 0.033 Oh x Rp. 100,000 = Rp. 3,300.00
- Tukang besi 0.033 Oh x Rp. 100,000 = Rp. 3,300.00
- Kepala tukang 0.010 Oh x Rp. 125,000 = Rp. 1,250.00
- Mandor 0.005 Oh x Rp. 135,000 = Rp. 675.00
Jumlah (2) = Rp. 19,325.00
Jumlah (1) + (2) = Rp. 92,283.60
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PENUTUP ATAP

PPA 6.1 1 M Pasang atap genteng palentong kecil

6.1.1 Bahan
- Genteng Palentong 25.000 Buah x Rp. 1,670 = Rp. 41,750.00
Jumlah (1) = Rp. 41,750.00
6.1.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang Kayu 0.075 Oh x Rp. 78,800 = Rp. 5,910.00
- Kepala Tukang 0.008 Oh x Rp. 91,900 = Rp. 735.20
- Mandor 0.008 Oh x Rp. 95,600 = Rp. 764.80
Jumlah (2) = Rp. 15,285.00
Jumlah (1) + (2) = Rp. 57,035.00

PPA 6.2 1 M Pasang atap genteng kodok / glazzur

6.2.1 Bahan
- Genteng Kodok 25.000 Buah x Rp. 2,170 = Rp. 54,250.00
Jumlah (1) = Rp. 54,250.00
6.2.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang Kayu 0.075 Oh x Rp. 78,800 = Rp. 5,910.00
- Kepala Tukang 0.008 Oh x Rp. 91,900 = Rp. 735.20
- Mandor 0.008 Oh x Rp. 95,600 = Rp. 764.80
Jumlah (2) = Rp. 15,285.00
Jumlah (1) + (2) = Rp. 69,535.00

PPA 6.3 1 M Pasang atap genteng palentong super / besar

6.3.1 Bahan
- Genteng Palentong super 12.000 Buah x Rp. 3,980 = Rp. 47,760.00
Jumlah (1) = Rp. 47,760.00
6.3.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang Kayu 0.060 Oh x Rp. 78,800 = Rp. 4,728.00
- Kepala Tukang 0.006 Oh x Rp. 91,900 = Rp. 551.40
- Mandor 0.008 Oh x Rp. 95,600 = Rp. 764.80
Jumlah (2) = Rp. 13,919.20
Jumlah (1) + (2) = Rp. 61,679.20

PPA 6.4 1 M Pasang genteng bubung palentong

6.4.1 Bahan
- Bubung geneteng palentong 5.000 Buah x Rp. 9,350 = Rp. 46,750.00
- Semen portland 8.000 Kg x Rp. 1,270 = Rp. 10,160.00
- Pasir Pasang 0.032 M x Rp. 76,500 = Rp. 2,448.00
Jumlah (1) = Rp. 59,358.00
6.4.2 Tenaga
- Pekerja 0.400 Oh x Rp. 52,500 = Rp. 21,000.00
- Tukang Kayu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala Tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.002 Oh x Rp. 95,600 = Rp. 191.20
Jumlah (2) = Rp. 38,789.20
Jumlah (1) + (2) = Rp. 98,147.20

PPA 6.5 1 M' Pasang bubung genteng kodok glazzuur

6.5.1 Bahan
- Bubung genteng kodok 5.000 Buah x Rp. 9,560 = Rp. 47,800.00
- Semen portland 8.000 Kg x Rp. 1,270 = Rp. 10,160.00
- Pasir Pasang 0.032 M x Rp. 76,500 = Rp. 2,448.00
Jumlah (1) = Rp. 60,408.00
6.5.2 Tenaga
- Pekerja 0.400 Oh x Rp. 52,500 = Rp. 21,000.00
- Tukang Kayu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala Tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.002 Oh x Rp. 95,600 = Rp. 191.20
Jumlah (2) = Rp. 38,789.20
Jumlah (1) + (2) = Rp. 99,197.20
PPA 6.6 1 M' Pasang bubung genteng palentong besar

6.6.1 Bahan
- Bubung genteng palentong super 4.000 Buah x Rp. 12,740 = Rp. 50,960.00
- Semen portland 8.000 Kg x Rp. 1,270 = Rp. 10,160.00
- Pasir Pasang 0.032 M x Rp. 76,500 = Rp. 2,448.00
Jumlah (1) = Rp. 63,568.00
6.6.2 Tenaga
- Pekerja 0.400 Oh x Rp. 52,500 = Rp. 21,000.00
- Tukang Kayu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala Tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.002 Oh x Rp. 95,600 = Rp. 191.20
Jumlah (2) = Rp. 38,789.20
Jumlah (1) + (2) = Rp. 102,357.20

PPA 6.7 1 M Pasang roof light fiberglass ( 180 x 90 ) cm

6.7.1 Bahan
- Roof light fibreglass 0.600 Lbr x Rp. 46,390 = Rp. 27,834.00
- Paku biasa " - 1" 0.050 Kg x Rp. 16,940 = Rp. 847.00
Jumlah (1) = Rp. 28,681.00
6.7.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.067 Oh x Rp. 78,800 = Rp. 5,279.60
- Kepala Tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.007 Oh x Rp. 95,600 = Rp. 669.20
Jumlah (2) = Rp. 13,942.10
Jumlah (1) + (2) = Rp. 42,623.10

PPA 6.8 1 M Pasang atap asbes gelombang ( 2,70 x 0,92 m ) x 5 mm

6.8.1 Bahan
- Atap asbes gelombang 0.450 Lbr x Rp. 106,810 = Rp. 48,064.50
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 50,506.50
6.8.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.075 Oh x Rp. 78,800 = Rp. 5,910.00
- Kepala Tukang 0.008 Oh x Rp. 91,900 = Rp. 735.20
- Mandor 0.008 Oh x Rp. 95,600 = Rp. 764.80
Jumlah (2) = Rp. 14,760.00
Jumlah (1) + (2) = Rp. 65,266.50

PPA 6.9 1 M Pasang atap asbes gelombang ( 2,40 x 0,92 m ) x 5 mm

6.9.1 Bahan
- Atap asbes gelombang 0.500 Lbr x Rp. 97,020 = Rp. 48,510.00
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 50,952.00
6.9.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.075 Oh x Rp. 78,800 = Rp. 5,910.00
- Kepala Tukang 0.008 Oh x Rp. 91,900 = Rp. 735.20
- Mandor 0.008 Oh x Rp. 95,600 = Rp. 764.80
Jumlah (2) = Rp. 14,760.00
Jumlah (1) + (2) = Rp. 65,712.00

PPA 6.10 1 M Pasang atap asbes gelombang ( 2,10 x 0,92 m ) x 5 mm

6.10.1 Bahan
- Atap asbes gelombang 0.600 Lbr x Rp. 88,770 = Rp. 53,262.00
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 55,704.00
6.10.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.075 Oh x Rp. 78,800 = Rp. 5,910.00
- Kepala Tukang 0.008 Oh x Rp. 91,900 = Rp. 735.20
- Mandor 0.008 Oh x Rp. 95,600 = Rp. 764.80
Jumlah (2) = Rp. 14,760.00
Jumlah (1) + (2) = Rp. 70,464.00
PPA 6.11 1 M Pasang atap asbes gelombang ( 1,80 x 0,92 m ) x 5 mm

6.11.1 Bahan
- Atap asbes gelombang 0.750 Lbr x Rp. 70,950 = Rp. 53,212.50
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 55,654.50
6.11.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala Tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.007 Oh x Rp. 95,600 = Rp. 669.20
Jumlah (2) = Rp. 14,178.50
Jumlah (1) + (2) = Rp. 69,833.00

PPA 6.12 1 M Pasang atap asbes gelombang ( 2,40 x 1,05 m ) x 4 mm

6.12.1 Bahan
- Atap asbes gelombang 0.450 Lbr x Rp. 108,130 = Rp. 48,658.50
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 51,100.50
6.12.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala Tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.007 Oh x Rp. 95,600 = Rp. 669.20
Jumlah (2) = Rp. 14,178.50
Jumlah (1) + (2) = Rp. 65,279.00

PPA 6.13 1 M Pasang atap asbes gelombang ( 2,10 x 1,05 m ) x 4 mm

6.13.1 Bahan
- Atap asbes gelombang 0.500 Lbr x Rp. 93,170 = Rp. 46,585.00
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 49,027.00
6.13.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala Tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.007 Oh x Rp. 95,600 = Rp. 669.20
Jumlah (2) = Rp. 14,178.50
Jumlah (1) + (2) = Rp. 63,205.50

PPA 6.14 1 M Pasang atap asbes gelombang ( 1,80 x 1,05 m ) x 4 mm

6.14.1 Bahan
- Atap asbes gelombang 0.600 Lbr x Rp. 59,380 = Rp. 35,628.00
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 38,070.00
6.14.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.067 Oh x Rp. 78,800 = Rp. 5,279.60
- Kepala Tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.007 Oh x Rp. 95,600 = Rp. 669.20
Jumlah (2) = Rp. 13,942.10
Jumlah (1) + (2) = Rp. 52,012.10

PPA 6.15 1 M Pasang atap asbes gelombang ( 2,10 x 1,05 m ) x 4 mm

6.15.1 Bahan
- Atap asbes gelombang 0.510 Lbr x Rp. 59,380 = Rp. 30,283.80
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 32,725.80
6.15.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.067 Oh x Rp. 78,800 = Rp. 5,279.60
- Kepala Tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.007 Oh x Rp. 95,600 = Rp. 669.20
Jumlah (2) = Rp. 13,942.10
Jumlah (1) + (2) = Rp. 46,667.90
PPA 6.16 1 M Pasang atap asbes gelombang ( 1,5 x 1,05 m ) x 4 mm

6.16.1 Bahan
- Atap asbes gelombang 0.800 Lbr x Rp. 59,380 = Rp. 47,504.00
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 49,946.00
6.16.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.067 Oh x Rp. 78,800 = Rp. 5,279.60
- Kepala Tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.007 Oh x Rp. 95,600 = Rp. 669.20
Jumlah (2) = Rp. 13,942.10
Jumlah (1) + (2) = Rp. 63,888.10

PPA 6.17 1 M Pasang atap asbes gelombang ( 3,00 x 1,08 m ) x 6 mm

6.17.1 Bahan
- Atap asbes gelombang 0.370 Lbr x Rp. 59,380 = Rp. 21,970.60
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 24,412.60
6.17.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.067 Oh x Rp. 78,800 = Rp. 5,279.60
- Kepala Tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.007 Oh x Rp. 95,600 = Rp. 669.20
Jumlah (2) = Rp. 13,942.10
Jumlah (1) + (2) = Rp. 38,354.70

PPA 6.18 1 M Pasang atap asbes gelombang ( 2,70 x 1,08 m ) x 6 mm

6.18.1 Bahan
- Atap asbes gelombang 0.380 Lbr x Rp. 155,430 = Rp. 59,063.40
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 61,505.40
6.18.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.067 Oh x Rp. 78,800 = Rp. 5,279.60
- Kepala Tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.007 Oh x Rp. 95,600 = Rp. 669.20
Jumlah (2) = Rp. 13,942.10
Jumlah (1) + (2) = Rp. 75,447.50

PPA 6.19 1 M Pasang atap asbes gelombang ( 2,4 x 1,08 m ) x 6 mm

6.19.1 Bahan
- Atap asbes gelombang 0.450 Lbr x Rp. 128,370 = Rp. 57,766.50
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 60,208.50
6.19.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.067 Oh x Rp. 78,800 = Rp. 5,279.60
- Kepala Tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.007 Oh x Rp. 95,600 = Rp. 669.20
Jumlah (2) = Rp. 13,942.10
Jumlah (1) + (2) = Rp. 74,150.60

PPA 6.20 1 M Pasang atap asbes gelombang ( 2,1 x 1,08 m ) x 6 mm

6.20.1 Bahan
- Atap asbes gelombang 0.490 Lbr x Rp. 120,450 = Rp. 59,020.50
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 61,462.50
6.16.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.067 Oh x Rp. 78,800 = Rp. 5,279.60
- Kepala Tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.007 Oh x Rp. 95,600 = Rp. 669.20
Jumlah (2) = Rp. 13,942.10
Jumlah (1) + (2) = Rp. 75,404.60

PPA 6.21 1 M Pasang atap asbes gelombang ( 1,80 x 1,08 m ) x 6 mm

6.21.1 Bahan
- Atap asbes gelombang 0.570 Lbr x Rp. 103,620 = Rp. 59,063.40
- Paku seng 0.120 Kg x Rp. 20,350 = Rp. 2,442.00
Jumlah (1) = Rp. 61,505.40
6.21.2 Tenaga
- Pekerja 0.140 Oh x Rp. 52,500 = Rp. 7,350.00
- Tukang Kayu 0.067 Oh x Rp. 78,800 = Rp. 5,279.60
- Kepala Tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.007 Oh x Rp. 95,600 = Rp. 669.20
Jumlah (2) = Rp. 13,942.10
Jumlah (1) + (2) = Rp. 75,447.50

PPA 6.22 1 M' Pasang bubung stel gelombang 0,92 m

6.22.1 Bahan
- Bubung stel gelombang 2.400 Lbr x Rp. 19,590 = Rp. 47,016.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 49,476.00
6.22.2 Tenaga
- Pekerja 0.084 Oh x Rp. 52,500 = Rp. 4,410.00
- Tukang Kayu 0.125 Oh x Rp. 78,800 = Rp. 9,850.00
- Kepala Tukang 0.013 Oh x Rp. 91,900 = Rp. 1,194.70
- Mandor 0.004 Oh x Rp. 95,600 = Rp. 382.40
Jumlah (2) = Rp. 15,837.10
Jumlah (1) + (2) = Rp. 65,313.10

PPA 6.23 1 M' Pasang nok stel gelombang 1,05 m

6.23.1 Bahan
- Bubung stel gelombang 2.100 Lbr x Rp. 25,990 = Rp. 54,579.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 57,039.00

6.23.2 Tenaga
- Pekerja 0.084 Oh x Rp. 52,500 = Rp. 4,410.00
- Tukang Kayu 0.125 Oh x Rp. 78,800 = Rp. 9,850.00
- Kepala Tukang 0.013 Oh x Rp. 91,900 = Rp. 1,194.70
- Mandor 0.004 Oh x Rp. 95,600 = Rp. 382.40
Jumlah (2) = Rp. 15,837.10
Jumlah (1) + (2) = Rp. 72,876.10

PPA 6.24 1 M' Pasang nok stel gelombang 1,08 m

6.24.1 Bahan
- Bubung stel gelombang 2.050 Lbr x Rp. 28,510 = Rp. 58,445.50
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 60,905.50
6.24.2 Tenaga
- Pekerja 0.084 Oh x Rp. 52,500 = Rp. 4,410.00
- Tukang Kayu 0.125 Oh x Rp. 78,800 = Rp. 9,850.00
- Kepala Tukang 0.013 Oh x Rp. 91,900 = Rp. 1,194.70
- Mandor 0.004 Oh x Rp. 95,600 = Rp. 382.40
Jumlah (2) = Rp. 15,837.10
Jumlah (1) + (2) = Rp. 76,742.60

PPA 6.25 1 M' Pasang nok paten 1,05 m

6.25.1 Bahan
- Nok paten 5 mm 1.200 Lbr x Rp. 36,810 = Rp. 44,172.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 46,632.00
6.25.2 Tenaga
- Pekerja 0.084 Oh x Rp. 52,500 = Rp. 4,410.00
- Tukang Kayu 0.125 Oh x Rp. 78,800 = Rp. 9,850.00
- Kepala Tukang 0.013 Oh x Rp. 91,900 = Rp. 1,194.70
- Mandor 0.004 Oh x Rp. 95,600 = Rp. 382.40
Jumlah (2) = Rp. 15,837.10
Jumlah (1) + (2) = Rp. 62,469.10

PPA 6.26 1 M' Pasang nok paten 1,05 m

6.26.1 Bahan
- Nok paten 4 mm 1.200 Lbr x Rp. 30,950 = Rp. 37,140.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 39,600.00
6.26.2 Tenaga
- Pekerja 0.084 Oh x Rp. 52,500 = Rp. 4,410.00
- Tukang Kayu 0.125 Oh x Rp. 78,800 = Rp. 9,850.00
- Kepala Tukang 0.013 Oh x Rp. 91,900 = Rp. 1,194.70
- Mandor 0.004 Oh x Rp. 95,600 = Rp. 382.40
Jumlah (2) = Rp. 15,837.10
Jumlah (1) + (2) = Rp. 55,437.10

PPA 6.27 1 M' Pasang nok paten 1,08 m

6.27.1 Bahan
- Nok paten 6 mm 1.200 Lbr x Rp. 42,960 = Rp. 51,552.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 54,012.00
6.27.2 Tenaga
- Pekerja 0.084 Oh x Rp. 52,500 = Rp. 4,410.00
- Tukang Kayu 0.125 Oh x Rp. 78,800 = Rp. 9,850.00
- Kepala Tukang 0.013 Oh x Rp. 91,900 = Rp. 1,194.70
- Mandor 0.004 Oh x Rp. 95,600 = Rp. 382.40
Jumlah (2) = Rp. 15,837.10
Jumlah (1) + (2) = Rp. 69,849.10

PPA 6.28 1 M' Pasang nok stel rata 0,92 m

6.28.1 Bahan
- Nok stel rata 5 mm 1.100 Lbr x Rp. 36,080 = Rp. 39,688.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 42,148.00
6.28.2 Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp. 5,250.00
- Tukang Kayu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala Tukang 0.013 Oh x Rp. 91,900 = Rp. 1,194.70
- Mandor 0.004 Oh x Rp. 95,600 = Rp. 382.40
Jumlah (2) = Rp. 18,647.10
Jumlah (1) + (2) = Rp. 60,795.10

PPA 6.29 1 M' Pasang nok stel rata 1,05 m

6.29.1 Bahan
- Nok stel rata 4 mm 1.100 Lbr x Rp. 30,250 = Rp. 33,275.00
- Paku seng 6.000 Bh x Rp. 410 = Rp. 2,460.00
Jumlah (1) = Rp. 35,735.00
6.29.2 Tenaga
- Pekerja 0.084 Oh x Rp. 52,500 = Rp. 4,410.00
- Tukang Kayu 0.125 Oh x Rp. 78,800 = Rp. 9,850.00
- Kepala Tukang 0.013 Oh x Rp. 91,900 = Rp. 1,194.70
- Mandor 0.004 Oh x Rp. 95,600 = Rp. 382.40
Jumlah (2) = Rp. 15,837.10
Jumlah (1) + (2) = Rp. 51,572.10

PPA 6.30 1 M Pasang atap genteng beton

6.30.1 Bahan
- Atap genteng beton 11.000 Bh x Rp. 5,970 = Rp. 65,670.00
- Paku biasa 2" - 5" 0.030 Kg x Rp. 14,520 = Rp. 435.60
Jumlah (1) = Rp. 66,105.60
6.30.2 Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang Kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala Tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 20,255.00
Jumlah (1) + (2) = Rp. 86,360.60

PPA 6.31 1 M Pasang atap genteng aspal

6.31.1 Bahan
- Nok genteng aspal 6.900 Lbr x Rp. 11,320 = Rp. 78,108.00
- Plywood 4" x 8" x 6 mm 0.350 Lbr x Rp. 77,880 = Rp. 27,258.00
- Paku biasa " - 1" 0.030 Kg x Rp. 16,940 = Rp. 508.20
- Plastic aerator 0.500 Bh x Rp. 27,500 = Rp. 13,750.00
Jumlah (1) = Rp. 119,624.20
6.31.2 Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang Kayu 0.300 Oh x Rp. 78,800 = Rp. 23,640.00
- Kepala Tukang 0.003 Oh x Rp. 91,900 = Rp. 275.70
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 35,371.70
Jumlah (1) + (2) = Rp. 154,995.90

PPA 6.32 1 M Pasang atap genteng metal / multi roof

6.32.1 Bahan
- Atap genteng metal 1.020 Bh x Rp. 64,130 = Rp. 65,412.60
- Paku biasa 2" - 5" 0.200 Kg x Rp. 14,520 = Rp. 2,904.00
Jumlah (1) = Rp. 68,316.60
6.32.2 Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang Kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala Tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 20,255.00
Jumlah (1) + (2) = Rp. 88,571.60

PPA 6.33 1 M Pasang atap sirap

6.33.1 Bahan
- Atap sirap 60.000 Bh x Rp. 1,030 = Rp. 61,800.00
- Paku biasa " - 1" 0.200 Kg x Rp. 16,940 = Rp. 3,388.00
Jumlah (1) = Rp. 65,188.00
6.33.2 Tenaga
- Pekerja 0.166 Oh x Rp. 52,500 = Rp. 8,715.00
- Tukang Kayu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala Tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.008 Oh x Rp. 95,600 = Rp. 764.80
Jumlah (2) = Rp. 31,477.30
Jumlah (1) + (2) = Rp. 96,665.30

PPA 6.34 1 M' Pasang nok genteng beton

6.34.1 Bahan
- Nok atap genteng beton 3.500 Bh x Rp. 13,440 = Rp. 47,040.00
- Paku biasa 2" x 5" 0.050 Kg x Rp. 14,520 = Rp. 726.00
- Semen PC 10.800 Kg x Rp. 1,270 = Rp. 13,716.00
- Pasir pasang 0.032 M x Rp. 76,500 = Rp. 2,448.00
- Semen warna 1.000 Kg x Rp. 2,500 = Rp. 2,500.00
Jumlah (1) = Rp. 66,430.00
6.34.2 Tenaga
- Pekerja 0.400 Oh x Rp. 52,500 = Rp. 21,000.00
- Tukang Kayu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala Tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.020 Oh x Rp. 95,600 = Rp. 1,912.00
Jumlah (2) = Rp. 40,510.00
Jumlah (1) + (2) = Rp. 106,940.00

PPA 6.35 1 M' Pasang nok genteng aspal

6.35.1 Bahan
- Nok genteng aspal 2.000 Bh x Rp. 11,320 = Rp. 22,640.00
- Paku biasa " - 1" 0.050 Kg x Rp. 16,940 = Rp. 847.00
- Kayu papan 0.0035 M x Rp. 9,650,000 = Rp. 33,775.00
Jumlah (1) = Rp. 57,262.00
6.35.2 Tenaga
- Pekerja 0.125 Oh x Rp. 52,500 = Rp. 6,562.50
- Tukang Kayu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala Tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.006 Oh x Rp. 95,600 = Rp. 573.60
Jumlah (2) = Rp. 29,133.60
Jumlah (1) + (2) = Rp. 86,395.60

PPA 6.36 1 M' Pasang nok genteng metal

6.36.1 Bahan
- Nok genteng decra bond 1.100 Bh x Rp. 41,140 = Rp. 45,254.00
- Paku biasa " - 1" 0.050 Kg x Rp. 16,940 = Rp. 847.00
Jumlah (1) = Rp. 46,101.00
6.36.2 Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang Kayu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala Tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.013 Oh x Rp. 95,600 = Rp. 1,242.80
Jumlah (2) = Rp. 27,566.30
Jumlah (1) + (2) = Rp. 73,667.30

PPA 6.37 1 M' Pasang nok sirap

6.37.1 Bahan
- Seng plat 3" x 6" BJLS 35 0.400 Lbr x Rp. 115,500 = Rp. 46,200.00
- Paku biasa " - 1" 0.060 Kg x Rp. 16,940 = Rp. 1,016.40
- Paku biasa 2" - 5" 0.050 Kg x Rp. 14,520 = Rp. 726.00
- Kayu papan tbl. 3 cm 0.004 M x Rp. 9,650,000 = Rp. 38,600.00
Jumlah (1) = Rp. 86,542.40
6.37.2 Tenaga
- Pekerja 0.125 Oh x Rp. 52,500 = Rp. 6,562.50
- Tukang Kayu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala Tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.006 Oh x Rp. 95,600 = Rp. 573.60
Jumlah (2) = Rp. 29,133.60
Jumlah (1) + (2) = Rp. 115,676.00

PPA 6.38 1 M' Pasang atap seng gelombang

6.38.1 Bahan
- Seng gelombang 3" x 6" BJLS 30 0.700 Lbr x Rp. 59,640 = Rp. 41,748.00
- Paku seng 0.040 Kg x Rp. 20,350 = Rp. 814.00
Jumlah (1) = Rp. 42,562.00
6.38.2 Tenaga
- Pekerja 0.120 Oh x Rp. 52,500 = Rp. 6,300.00
- Tukang Kayu 0.060 Oh x Rp. 78,800 = Rp. 4,728.00
- Kepala Tukang 0.006 Oh x Rp. 91,900 = Rp. 551.40
- Mandor 0.006 Oh x Rp. 95,600 = Rp. 573.60
Jumlah (2) = Rp. 12,153.00
Jumlah (1) + (2) = Rp. 54,715.00

PPA 6.39 1 M' Pasang atap nok seng

6.39.1 Bahan
- Seng plat 3" x 6" BJLS 35 0.300 Bh x Rp. 115,500 = Rp. 34,650.00
- Paku seng 0.020 Kg x Rp. 20,350 = Rp. 407.00
Jumlah (1) = Rp. 35,057.00
6.39.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang Kayu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala Tukang 0.008 Oh x Rp. 91,900 = Rp. 735.20
- Mandor 0.006 Oh x Rp. 95,600 = Rp. 573.60
Jumlah (2) = Rp. 14,699.80
Jumlah (1) + (2) = Rp. 49,756.80

PPA 6.40 1 M' Pasang atap aluminium

6.40.1 Bahan
- Atap aluminium gelombang 0,55 1.050 Bh x Rp. 98,180 = Rp. 103,089.00
- Paku hak panjang 15 cm 0.020 Kg x Rp. 30,530 = Rp. 610.60
Jumlah (1) = Rp. 103,699.60
6.40.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang Kayu 0.075 Oh x Rp. 78,800 = Rp. 5,910.00
- Kepala Tukang 0.008 Oh x Rp. 91,900 = Rp. 735.20
- Mandor 0.006 Oh x Rp. 95,600 = Rp. 573.60
Jumlah (2) = Rp. 15,093.80
Jumlah (1) + (2) = Rp. 118,793.40

PPA 6.41 1 M' Pasang nok aluminium

6.41.1 Bahan
- Nok standard 40 cm 18 SWG 22 1.200 Bh x Rp. 47,890 = Rp. 57,468.00
- Paku hak panjang 15 cm 0.040 Kg x Rp. 30,530 = Rp. 1,221.20
Jumlah (1) = Rp. 58,689.20
6.41.2 Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp. 5,250.00
- Tukang Kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala Tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 15,005.00
Jumlah (1) + (2) = Rp. 73,694.20

PPA 6.42 1 M' Pasang aluminium foil / sisalation

6.42.1 Bahan
- Sisalation / Aluminium foil 1.050 M x Rp. 77,200 = Rp. 81,060.00
Jumlah (1) = Rp. 81,060.00
6.42.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang Kayu 0.050 Oh x Rp. 78,800 = Rp. 3,940.00
- Kepala Tukang 0.005 Oh x Rp. 91,900 = Rp. 459.50
- Mandor 0.008 Oh x Rp. 95,600 = Rp. 764.80
Jumlah (2) = Rp. 13,039.30
Jumlah (1) + (2) = Rp. 94,099.30
ANALISA BIAYA KONSTRUKSI
PEKERJAAN PENUTUP LANTAI

PPL 6.9 1 M Pasang lantai ubin granito ukuran 40 x 40 cm


6.9.1 Bahan
- Ubin granito 40 x 40 cm 6.930 Bh x Rp. 46,590 = Rp. 322,868.70
- Semen portland 9.800 Kg x Rp. 1,270 = Rp. 12,446.00
- Pasir pasang 0.0215 M x Rp. 76,500 = Rp. 1,644.75
- Semen warna 1.300 Kg x Rp. 2,500 = Rp. 3,250.00
Jumlah (1) = Rp. 340,209.45
6.9.2 Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.120 Oh x Rp. 78,800 = Rp. 9,456.00
- Kepala tukang 0.012 Oh x Rp. 91,900 = Rp. 1,102.80
- Mandor 0.0125 Oh x Rp. 95,600 = Rp. 1,195.00
Jumlah (2) = Rp. 24,878.80
Jumlah (1) + (2) = Rp. 365,088.25

PPL 6.10 1 M Pasang lantai ubin granito ukuran 30 x 30 cm

6.10.1 Bahan
- Ubin granito 30 x 30 cm 11.870 Bh x Rp. 26,260 = Rp. 311,706.20
- Semen portland 10.000 Kg x Rp. 1,270 = Rp. 12,700.00
- Pasir pasang 0.0215 M x Rp. 76,500 = Rp. 1,644.75
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 329,800.95
6.10.2 Tenaga
- Pekerja 0.260 Oh x Rp. 52,500 = Rp. 13,650.00
- Tukang batu 0.125 Oh x Rp. 78,800 = Rp. 9,850.00
- Kepala tukang 0.0125 Oh x Rp. 91,900 = Rp. 1,148.75
- Mandor 0.013 Oh x Rp. 95,600 = Rp. 1,242.80
Jumlah (2) = Rp. 25,891.55
Jumlah (1) + (2) = Rp. 355,692.50

PPL 6.13 1 M Pasang lantai ubin teralux marmer ukuran 60 x 60 cm

6.13.1 Bahan
- Ubin marmer 60 x 60 cm 2.780 Bh x Rp. 109,510 = Rp. 304,437.80
- Semen portland 8.190 Kg x Rp. 1,270 = Rp. 10,401.30
- Pasir pasang 0.0215 M x Rp. 76,500 = Rp. 1,644.75
- Semen warna 1.000 Kg x Rp. 2,500 = Rp. 2,500.00
Jumlah (1) = Rp. 318,983.85
6.13.2 Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang batu 0.120 Oh x Rp. 78,800 = Rp. 9,456.00
- Kepala tukang 0.012 Oh x Rp. 91,900 = Rp. 1,102.80
- Mandor 0.0125 Oh x Rp. 95,600 = Rp. 1,195.00
Jumlah (2) = Rp. 24,878.80
Jumlah (1) + (2) = Rp. 343,862.65

PPL 6.14 1 M Pasang lantai ubin teralux marmer ukuran 40 x 40 cm

6.14.1 Bahan
- ubin marmer 40 x 40 cm 6.250 Bh x Rp. 48,400 = Rp. 302,500.00
- Semen portland 8.800 Kg x Rp. 1,270 = Rp. 11,176.00
- Pasir pasang 0.0215 M x Rp. 76,500 = Rp. 1,644.75
- Semen warna 1.300 Kg x Rp. 2,500 = Rp. 3,250.00
Jumlah (1) = Rp. 318,570.75
6.14.2 Tenaga
- Pekerja 0.672 Oh x Rp. 52,500 = Rp. 35,280.00
- Tukang batu 0.224 Oh x Rp. 78,800 = Rp. 17,651.20
- Kepala tukang 0.022 Oh x Rp. 91,900 = Rp. 2,021.80
- Mandor 0.034 Oh x Rp. 95,600 = Rp. 3,250.40
Jumlah (2) = Rp. 58,203.40
Jumlah (1) + (2) = Rp. 376,774.15

PPL 6.15 1 M Pasang lantai ubin teralux marmer ukuran 30 x 30 cm

6.15.1 Bahan
- Ubin marmer 30 x 30 cm 11.870 Bh x Rp. 27,230 = Rp. 323,220.10
- Semen portland 10.000 Kg x Rp. 1,270 = Rp. 12,700.00
- Pasir pasang 0.0215 M x Rp. 76,500 = Rp. 1,644.75
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 341,314.85
6.15.2 Tenaga
- Pekerja 0.700 Oh x Rp. 52,500 = Rp. 36,750.00
- Tukang batu 0.340 Oh x Rp. 78,800 = Rp. 26,792.00
- Kepala tukang 0.034 Oh x Rp. 91,900 = Rp. 3,124.60
- Mandor 0.035 Oh x Rp. 95,600 = Rp. 3,346.00
Jumlah (2) = Rp. 70,012.60
Jumlah (1) + (2) = Rp. 411,327.45

PPL 6.24 1 M' Pasang plint ubin granito ukuran 10 x 40 cm

6.24.1 Bahan
- Plint ubin granito 10 x 40 cm 2.650 Bh x Rp. 62,800 = Rp. 166,420.00
- Semen portland 1.200 Kg x Rp. 1,270 = Rp. 1,524.00
- Pasir pasang 0.0032 M x Rp. 76,500 = Rp. 244.80
- Semen warna 0.100 Kg x Rp. 2,500 = Rp. 250.00
Jumlah (1) = Rp. 168,438.80
6.24.2 Tenaga
- Pekerja 0.600 Oh x Rp. 52,500 = Rp. 31,500.00
- Tukang batu 0.030 Oh x Rp. 78,800 = Rp. 2,364.00
- Kepala tukang 0.003 Oh x Rp. 91,900 = Rp. 275.70
- Mandor 0.003 Oh x Rp. 95,600 = Rp. 286.80
Jumlah (2) = Rp. 34,426.50
Jumlah (1) + (2) = Rp. 202,865.30

PPL 6.25 1 M' Pasang plint ubin granito ukuran 10 x 30 cm

6.25.1 Bahan
- Plint ubin granito 10 x 30 cm 3.330 Bh x Rp. 27,950 = Rp. 93,073.50
- Semen portland 1.650 Kg x Rp. 1,270 = Rp. 2,095.50
- Pasir pasang 0.0032 M x Rp. 76,500 = Rp. 244.80
- Semen warna 0.100 Kg x Rp. 2,500 = Rp. 250.00
Jumlah (1) = Rp. 95,663.80
6.25.2 Tenaga
- Pekerja 0.900 Oh x Rp. 52,500 = Rp. 47,250.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.0045 Oh x Rp. 95,600 = Rp. 430.20
Jumlah (2) = Rp. 55,599.30
Jumlah (1) + (2) = Rp. 151,263.10

PPL 6.28 1 M' Pasang plint ubin teralux marmer ukuran 10 x 60 cm

6.28.1 Bahan
- Plint ubin marmer 10 x 60 cm 1.700 Bh x Rp. 65,700 = Rp. 111,690.00
- Semen portland 1.650 Kg x Rp. 1,270 = Rp. 2,095.50
- Pasir pasang 0.0032 M x Rp. 76,500 = Rp. 244.80
- Semen warna 0.100 Kg x Rp. 2,500 = Rp. 250.00
Jumlah (1) = Rp. 114,280.30

6.28.2 Tenaga
- Pekerja 0.900 Oh x Rp. 52,500 = Rp. 47,250.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.0045 Oh x Rp. 95,600 = Rp. 430.20
Jumlah (2) = Rp. 55,599.30
Jumlah (1) + (2) = Rp. 169,879.60

PPL 6.29 1 M' Pasang plint ubin teralux marmer ukuran 10 x 40 cm

6.29.1 Bahan
- Plint ubin marmer 10 x 40 cm 2.500 Bh x Rp. 29,040 = Rp. 72,600.00
- Semen portland 1.650 Kg x Rp. 1,270 = Rp. 2,095.50
- Pasir pasang 0.0032 M x Rp. 76,500 = Rp. 244.80
- Semen warna 0.100 Kg x Rp. 2,500 = Rp. 250.00
Jumlah (1) = Rp. 75,190.30

6.29.2 Tenaga
- Pekerja 0.900 Oh x Rp. 52,500 = Rp. 47,250.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.0045 Oh x Rp. 95,600 = Rp. 430.20
Jumlah (2) = Rp. 55,599.30
Jumlah (1) + (2) = Rp. 130,789.60

PPL 6.30 1 M' Pasang plint ubin teralux marmer ukuran 10 x 30 cm

6.30.1 Bahan
- Plint ubin marmer 10 x 30 cm 3.330 Bh x Rp. 16,340 = Rp. 54,412.20
- Semen portland 1.650 Kg x Rp. 1,270 = Rp. 2,095.50
- Pasir pasang 0.0032 M x Rp. 76,500 = Rp. 244.80
- Semen warna 0.100 Kg x Rp. 2,500 = Rp. 250.00
Jumlah (1) = Rp. 57,002.50

6.30.2 Tenaga
- Pekerja 0.900 Oh x Rp. 52,500 = Rp. 47,250.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.0045 Oh x Rp. 95,600 = Rp. 430.20
Jumlah (2) = Rp. 55,599.30
Jumlah (1) + (2) = Rp. 112,601.80

PPL 6.34 1 M Pasang lantai keramik artistik 10 x 20 cm

6.34.1 Bahan
- Keramik artistik 10 x 20 cm 50.000 Bh x Rp. 1,760 = Rp. 88,000.00
- Semen portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 109,415.60

6.34.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 175,630.10

PPL 6.35 1 M Pasang lantai keramik artistik 10 x 10 cm

6.35.1 Bahan
- Keramik artistik 10 x 10 cm 50.000 Bh x Rp. 910 = Rp. 45,500.00
- Semen portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
- Semen warna 2.000 Kg x Rp. 2,500 = Rp. 5,000.00
Jumlah (1) = Rp. 68,165.60

6.35.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 134,380.10

PPL 6.36 1 M Pasang lantai keramik artistik ukuran 5 x 20 cm

6.36.1 Bahan
- Keramik artistik 5 x 20 cm 100.000 Bh x Rp. 910 = Rp. 91,000.00
- Semen portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 112,415.60
6.36.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 178,630.10

PPL 6.37 1 M' Pasang plint keramik artistik ukuran 10 x 20 cm

6.37.1 Bahan
- keramik artistik 10 x 20 cm 5.000 Bh x Rp. 1,760 = Rp. 8,800.00
- Semen portland 1.650 Kg x Rp. 1,270 = Rp. 2,095.50
- Pasir pasang 0.0032 M x Rp. 76,500 = Rp. 244.80
- Semen warna 0.100 Kg x Rp. 2,500 = Rp. 250.00
Jumlah (1) = Rp. 11,390.30
6.37.2 Tenaga
- Pekerja 0.090 Oh x Rp. 52,500 = Rp. 4,725.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.0045 Oh x Rp. 95,600 = Rp. 430.20
Jumlah (2) = Rp. 13,074.30
Jumlah (1) + (2) = Rp. 24,464.60

PPL 6.38 1 M' Pasang plint keramik artistik ukuran 10 x 10 cm

6.38.1 Bahan
- keramik artistik 10 x 10 cm 10.000 Bh x Rp. 910 = Rp. 9,100.00
- Semen portland 1.650 Kg x Rp. 1,270 = Rp. 2,095.50
- Pasir pasang 0.0032 M x Rp. 76,500 = Rp. 244.80
- Semen warna 0.120 Kg x Rp. 2,500 = Rp. 300.00
Jumlah (1) = Rp. 11,740.30

6.38.2 Tenaga
- Pekerja 0.090 Oh x Rp. 52,500 = Rp. 4,725.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.0045 Oh x Rp. 95,600 = Rp. 430.20
Jumlah (2) = Rp. 13,074.30
Jumlah (1) + (2) = Rp. 24,814.60

PPL 6.39.A 1 M' Pasang plint keramik ukuran 10 x 20 cm

6.39.1 Bahan
- Keramik 10 x 20 cm 5.000 Bh x Rp. 1,210 = Rp. 6,050.00
- Semen portland 0.850 Kg x Rp. 1,270 = Rp. 1,079.50
- Pasir pasang 0.0032 M x Rp. 76,500 = Rp. 244.80
- Semen warna 0.080 Kg x Rp. 2,500 = Rp. 200.00
Jumlah (1) = Rp. 7,574.30
6.39.2 Tenaga
- Pekerja 0.090 Oh x Rp. 52,500 = Rp. 4,725.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.0045 Oh x Rp. 95,600 = Rp. 430.20
Jumlah (2) = Rp. 13,074.30
Jumlah (1) + (2) = Rp. 20,648.60

PPL 6.39.B 1 M' Pasang plint keramik ukuran 10 x 30 cm

6.39.1 Bahan
- Keramik 10 x 30 cm 3.340 Bh x Rp. 4,110 = Rp. 13,727.40
- Semen portland 0.850 Kg x Rp. 1,270 = Rp. 1,079.50
- Pasir pasang 0.0032 M x Rp. 76,500 = Rp. 244.80
- Semen warna 0.080 Kg x Rp. 2,500 = Rp. 200.00
Jumlah (1) = Rp. 15,251.70

6.39.2 Tenaga
- Pekerja 0.090 Oh x Rp. 52,500 = Rp. 4,725.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.0045 Oh x Rp. 95,600 = Rp. 430.20
Jumlah (2) = Rp. 13,074.30
Jumlah (1) + (2) = Rp. 28,326.00

PPL 6.39.C 1 M' Pasang plint keramik ukuran 10 x 40 cm

6.39.1 Bahan
- Keramik 10 x 40 cm 2.500 Bh x Rp. 5,690 = Rp. 14,225.00
- Semen portland 0.850 Kg x Rp. 1,270 = Rp. 1,079.50
- Pasir pasang 0.0032 M x Rp. 76,500 = Rp. 244.80
- Semen warna 0.080 Kg x Rp. 2,500 = Rp. 200.00
Jumlah (1) = Rp. 15,749.30

6.39.2 Tenaga
- Pekerja 0.090 Oh x Rp. 52,500 = Rp. 4,725.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.0045 Oh x Rp. 95,600 = Rp. 430.20
Jumlah (2) = Rp. 13,074.30
Jumlah (1) + (2) = Rp. 28,823.60

PPL 6.41 1 M' Pasang plint vinyil tanpa adukan

6.41.1 Bahan
- Vinyl 30 x 30 cm 3.500 Bh x Rp. 8,230 = Rp. 28,805.00
- Lem vinyl 0.080 Kg x Rp. 44,900 = Rp. 3,592.00
Jumlah (1) = Rp. 32,397.00
6.41.2 Tenaga
- Pekerja 0.080 Oh x Rp. 52,500 = Rp. 4,200.00
- Tukang batu 0.080 Oh x Rp. 78,800 = Rp. 6,304.00
- Kepala tukang 0.008 Oh x Rp. 91,900 = Rp. 735.20
- Mandor 0.004 Oh x Rp. 95,600 = Rp. 382.40
Jumlah (2) = Rp. 11,621.60
Jumlah (1) + (2) = Rp. 44,018.60
PPL 6.42 1 M Pasang lantai keramik 10 x 20 cm

6.42.1 Bahan
- Ubin keramik 10 x 20 cm 50.000 Bh x Rp. 1,210 = Rp. 60,500.00
- Semen portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 81,915.60
6.42.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 148,130.10

PPL 6.43 1 M Pasang lantai keramik 15 x 15 cm

6.43.1 Bahan
- Ubin keramik 15 x 15 cm 44.000 Bh x Rp. 1,400 = Rp. 61,600.00
- Semen portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 83,015.60
6.43.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 149,230.10

PPL 6.44 1 M Pasang lantai keramik 20 x 20 cm

6.44.1 Bahan
- Ubin keramik 20 x 20 cm 25.000 Bh x Rp. 2,490 = Rp. 62,250.00
- Semen portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 83,665.60

6.44.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 149,880.10

PPL 6.45 1 M Pasang lantai keramik 20 x 25 cm

6.45.1 Bahan
- Ubin keramik 20 x 25 cm 20.000 Bh x Rp. 3,150 = Rp. 63,000.00
- Semen portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 84,415.60

6.45.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 150,630.10

PPL 6.46 1 M Pasang lantai keramik 25 x 25 cm

6.46.1 Bahan
- Ubin keramik 25 x 25 cm 16.000 Bh x Rp. 3,870 = Rp. 61,920.00
- Semen portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 83,335.60

6.46.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 149,550.10

PPL 6.47 1 M Pasang lantai keramik 30 x 30 cm

6.47.1 Bahan
- Ubin keramik 30 x 30 cm 11.120 Bh x Rp. 5,570 = Rp. 61,938.40
- Semen portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 83,354.00
6.47.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 149,568.50

PPL 6.48 1 M Pasang lantai keramik 30 x 30 cm anti slip

6.48.1 Bahan
- Ubin keramik 30 x 30 cm anti slip 11.120 Bh x Rp. 6,290 = Rp. 69,944.80
- Semen portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 91,360.40
6.48.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 157,574.90

PPL 6.49 1 M Pasang lantai keramik 40 x 40 cm

6.49.1 Bahan
- Ubin keramik 40 x 40 cm 6.250 Bh x Rp. 9,680 = Rp. 60,500.00
- Semen portland 11.380 Kg x Rp. 1,270 = Rp. 14,452.60
- Pasir pasang 0.042 M x Rp. 76,500 = Rp. 3,213.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 81,915.60
6.49.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 148,130.10

PPL 6.50 1 M Pasang lantai mosaik 30 x 30 cm, ex lokal

6.50.1 Bahan
- Mosaik 30 x 30 cm 12.000 Bh x Rp. 13,920 = Rp. 167,040.00
- Semen portland 14.150 Kg x Rp. 1,270 = Rp. 17,970.50
- Pasir pasang 0.039 M x Rp. 76,500 = Rp. 2,983.50
- Semen warna 2.000 Kg x Rp. 2,500 = Rp. 5,000.00
Jumlah (1) = Rp. 192,994.00
6.50.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 259,208.50

PPL 6.51 1 M Pasang lantai marmer

6.51.1 Bahan
- Marmer 1.052 Bh x Rp. 261,970 = Rp. 275,592.44
- Semen portland 14.150 Kg x Rp. 1,270 = Rp. 17,970.50
- Pasir pasang 0.039 M x Rp. 76,500 = Rp. 2,983.50
- Semen warna 2.000 Kg x Rp. 2,500 = Rp. 5,000.00
Jumlah (1) = Rp. 301,546.44
6.51.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 367,760.94

PPL 6.52 1 M Pasang lantai karpet 100% wool

6.52.1 Bahan
- Karpet wool 1.050 M x Rp. 85,250 = Rp. 89,512.50
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 105,227.50
6.52.2 Tenaga
- Pekerja 0.170 Oh x Rp. 52,500 = Rp. 8,925.00
- Tukang 0.170 Oh x Rp. 78,800 = Rp. 13,396.00
- Kepala tukang 0.017 Oh x Rp. 91,900 = Rp. 1,562.30
- Mandor 0.0085 Oh x Rp. 95,600 = Rp. 812.60
Jumlah (2) = Rp. 24,695.90
Jumlah (1) + (2) = Rp. 129,923.40

PPL 6.53 1 M Pasang lantai karpet 80% wool, 20% nylon

6.53.1 Bahan
- Karpet wool + nylon 1.050 M x Rp. 87,450 = Rp. 91,822.50
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 107,537.50

6.53.2 Tenaga
- Pekerja 0.170 Oh x Rp. 52,500 = Rp. 8,925.00
- Tukang 0.170 Oh x Rp. 78,800 = Rp. 13,396.00
- Kepala tukang 0.017 Oh x Rp. 91,900 = Rp. 1,562.30
- Mandor 0.0085 Oh x Rp. 95,600 = Rp. 812.60
Jumlah (2) = Rp. 24,695.90
Jumlah (1) + (2) = Rp. 132,233.40

PPL 6.55 1 M Pasang lantai karpet

6.55.1 Bahan
- Carpet 1.050 M x Rp. 90,750 = Rp. 95,287.50
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 111,002.50
6.55.2 Tenaga
- Pekerja 0.170 Oh x Rp. 52,500 = Rp. 8,925.00
- Tukang 0.170 Oh x Rp. 78,800 = Rp. 13,396.00
- Kepala tukang 0.017 Oh x Rp. 91,900 = Rp. 1,562.30
- Mandor 0.0085 Oh x Rp. 95,600 = Rp. 812.60
Jumlah (2) = Rp. 24,695.90
Jumlah (1) + (2) = Rp. 135,698.40

PPL 6.56 1 M Pasang lantai parquet jati

6.56.1 Bahan
- Perquet jati 1.050 M x Rp. 368,500 = Rp. 386,925.00
- Lem vinyl 0.600 Kg x Rp. 44,900 = Rp. 26,940.00
Jumlah (1) = Rp. 413,865.00
6.56.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp. 34,125.00
- Tukang 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.0325 Oh x Rp. 95,600 = Rp. 3,107.00
Jumlah (2) = Rp. 68,028.50
Jumlah (1) + (2) = Rp. 481,893.50

PPL 6.58 1 M Pasang dinding porselin 11 x 11 cm, putih

6.58.1 Bahan
- Porselin 11 x 11 cm 83.000 Bh x Rp. 1,210 = Rp. 100,430.00
- Semen portland 9.300 Kg x Rp. 1,270 = Rp. 11,811.00
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 117,368.00

6.58.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.500 Oh x Rp. 78,800 = Rp. 39,400.00
- Kepala tukang 0.050 Oh x Rp. 91,900 = Rp. 4,595.00
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 79,413.00
Jumlah (1) + (2) = Rp. 196,781.00

PPL 6.59 1 M Pasang dinding porselin 11 x 11 cm, warna

6.59.1 Bahan
- Porselin 11 x 11 cm warna 83.000 Bh x Rp. 145 = Rp. 12,035.00
- Semen portland 9.300 Kg x Rp. 1,270 = Rp. 11,811.00
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 28,973.00

6.59.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.500 Oh x Rp. 78,800 = Rp. 39,400.00
- Kepala tukang 0.050 Oh x Rp. 91,900 = Rp. 4,595.00
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 79,413.00
Jumlah (1) + (2) = Rp. 108,386.00
PPL 6.60 1 M Pasang dinding porselin 15 x 15 cm, putih

6.60.1 Bahan
- Porselin 15 x 15 cm putih 45.000 Bh x Rp. 2,300 = Rp. 103,500.00
- Semen portland 9.300 Kg x Rp. 1,270 = Rp. 11,811.00
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 120,438.00
6.60.2 Tenaga
- Pekerja 0.600 Oh x Rp. 52,500 = Rp. 31,500.00
- Tukang batu 0.450 Oh x Rp. 78,800 = Rp. 35,460.00
- Kepala tukang 0.045 Oh x Rp. 91,900 = Rp. 4,135.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 73,963.50
Jumlah (1) + (2) = Rp. 194,401.50

PPL 6.61 1 M Pasang dinding porselin 15 x 15 cm, warna

6.61.1 Bahan
- Porselin 15 x 15 cm warna 45.000 Bh x Rp. 2,540 = Rp. 114,300.00
- Semen portland 9.300 Kg x Rp. 1,270 = Rp. 11,811.00
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 131,238.00
6.61.2 Tenaga
- Pekerja 0.600 Oh x Rp. 52,500 = Rp. 31,500.00
- Tukang batu 0.450 Oh x Rp. 78,800 = Rp. 35,460.00
- Kepala tukang 0.045 Oh x Rp. 91,900 = Rp. 4,135.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 73,963.50
Jumlah (1) + (2) = Rp. 205,201.50

PPL 6.64 1 M Pasang dinding keramik artistik 10 x 20 cm

6.64.1 Bahan
- Keramik artistik 10 x 20 cm 100.000 Bh x Rp. 1,760 = Rp. 176,000.00
- Semen portland 9.300 Kg x Rp. 1,270 = Rp. 11,811.00
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 192,938.00

6.64.2 Tenaga
- Pekerja 0.600 Oh x Rp. 52,500 = Rp. 31,500.00
- Tukang batu 0.450 Oh x Rp. 78,800 = Rp. 35,460.00
- Kepala tukang 0.045 Oh x Rp. 91,900 = Rp. 4,135.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 73,963.50
Jumlah (1) + (2) = Rp. 266,901.50

PPL 6.65 1 M Pasang dinding keramik artistik 5 x 20 cm

6.65.1 Bahan
- Keramik artistik 5 x 20 cm 100.000 Bh x Rp. 910 = Rp. 91,000.00
- Semen portland 9.300 Kg x Rp. 1,270 = Rp. 11,811.00
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 107,938.00
6.65.2 Tenaga
- Pekerja 0.600 Oh x Rp. 52,500 = Rp. 31,500.00
- Tukang batu 0.450 Oh x Rp. 78,800 = Rp. 35,460.00
- Kepala tukang 0.045 Oh x Rp. 91,900 = Rp. 4,135.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 73,963.50
Jumlah (1) + (2) = Rp. 181,901.50
PPL 6.66 1 M Pasang dinding keramik 10 x 20 cm

6.66.1 Bahan
- Keramik 10 x 20 cm 50.000 Bh x Rp. 1,210 = Rp. 60,500.00
- Semen portland 9.300 Kg x Rp. 1,270 = Rp. 11,811.00
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 77,438.00
6.66.2 Tenaga
- Pekerja 0.600 Oh x Rp. 52,500 = Rp. 31,500.00
- Tukang batu 0.450 Oh x Rp. 78,800 = Rp. 35,460.00
- Kepala tukang 0.045 Oh x Rp. 91,900 = Rp. 4,135.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 73,963.50
Jumlah (1) + (2) = Rp. 151,401.50

PPL 6.67 1 M Pasang dinding keramik 15 x 15 cm

6.67.1 Bahan
- Keramik 15 x 15 cm 45.000 Bh x Rp. 1,400 = Rp. 63,000.00
- Semen portland 9.300 Kg x Rp. 1,270 = Rp. 11,811.00
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 79,938.00
6.67.2 Tenaga
- Pekerja 0.600 Oh x Rp. 52,500 = Rp. 31,500.00
- Tukang batu 0.450 Oh x Rp. 78,800 = Rp. 35,460.00
- Kepala tukang 0.045 Oh x Rp. 91,900 = Rp. 4,135.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 73,963.50
Jumlah (1) + (2) = Rp. 153,901.50

PPL 6.68 1 M Pasang dinding keramik 20 x 20 cm

6.68.1 Bahan
- Keramik 20 x 20 cm 25.000 Bh x Rp. 2,490 = Rp. 62,250.00
- Semen portland 9.300 Kg x Rp. 1,270 = Rp. 11,811.00
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 79,188.00
6.68.2 Tenaga
- Pekerja 0.600 Oh x Rp. 52,500 = Rp. 31,500.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.045 Oh x Rp. 91,900 = Rp. 4,135.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 46,383.50
Jumlah (1) + (2) = Rp. 125,571.50

PPL 6.69 1 M Pasang dinding keramik 20 x 25 cm

6.69.1 Bahan
- Keramik 20 x 25 cm 20.000 Bh x Rp. 3,150 = Rp. 63,000.00
- Semen portland 9.300 Kg x Rp. 1,270 = Rp. 11,811.00
- Pasir pasang 0.018 M x Rp. 76,500 = Rp. 1,377.00
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 79,938.00
6.69.2 Tenaga
- Pekerja 0.600 Oh x Rp. 52,500 = Rp. 31,500.00
- Tukang batu 0.450 Oh x Rp. 78,800 = Rp. 35,460.00
- Kepala tukang 0.0450 Oh x Rp. 91,900 = Rp. 4,135.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 73,963.50
Jumlah (1) + (2) = Rp. 153,901.50
PPL 6.70 1 M Pasang dinding marmer

6.70.1 Bahan
- Marmer 1.020 M x Rp. 261,970 = Rp. 267,209.40
- Paku pancing 2.000 Bh x Rp. 720 = Rp. 1,440.00
- Semen portland 12.440 Kg x Rp. 1,270 = Rp. 15,798.80
- Pasir pasang 0.025 M x Rp. 76,500 = Rp. 1,912.50
- Semen warna 1.500 Kg x Rp. 2,500 = Rp. 3,750.00
Jumlah (1) = Rp. 290,110.70
6.70.2 Tenaga
- Pekerja 0.720 Oh x Rp. 52,500 = Rp. 37,800.00
- Tukang batu 0.650 Oh x Rp. 78,800 = Rp. 51,220.00
- Kepala tukang 0.065 Oh x Rp. 91,900 = Rp. 5,973.50
- Mandor 0.035 Oh x Rp. 95,600 = Rp. 3,346.00
Jumlah (2) = Rp. 98,339.50
Jumlah (1) + (2) = Rp. 388,450.20

PPL 6.71 1 M Pasang dinding bata pelapis 7 x 3 x 20 cm

6.71.1 Bahan
- Bata pelapis dinding 60.000 Bh x Rp. 2,040 = Rp. 122,400.00
- Semen portland 12.440 Kg x Rp. 1,270 = Rp. 15,798.80
- Pasir pasang 0.025 M x Rp. 76,500 = Rp. 1,912.50
Jumlah (1) = Rp. 140,111.30
6.71.2 Tenaga
- Pekerja 0.650 Oh x Rp. 52,500 = Rp. 34,125.00
- Tukang batu 0.500 Oh x Rp. 78,800 = Rp. 39,400.00
- Kepala tukang 0.050 Oh x Rp. 91,900 = Rp. 4,595.00
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 80,988.00
Jumlah (1) + (2) = Rp. 221,099.30

PPL 6.73 1 M Pasang dinding batu poros

6.73.1 Bahan
- Batu poros 1.050 M x Rp. 114,680 = Rp. 120,414.00
- Semen portland 11.750 Kg x Rp. 1,270 = Rp. 14,922.50
- Pasir pasang 0.035 M x Rp. 76,500 = Rp. 2,677.50
Jumlah (1) = Rp. 138,014.00
6.73.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 204,228.50

PPL 6.74 1 M Pasang dinding batu tempel hitam

6.74.1 Bahan
- Batu tempel hitam 1.050 M x Rp. 104,500 = Rp. 109,725.00
- Semen portland 11.750 Kg x Rp. 1,270 = Rp. 14,922.50
- Pasir pasang 0.035 M x Rp. 76,500 = Rp. 2,677.50
Jumlah (1) = Rp. 127,325.00
6.74.2 Tenaga
- Pekerja 0.620 Oh x Rp. 52,500 = Rp. 32,550.00
- Tukang batu 0.350 Oh x Rp. 78,800 = Rp. 27,580.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.030 Oh x Rp. 95,600 = Rp. 2,868.00
Jumlah (2) = Rp. 66,214.50
Jumlah (1) + (2) = Rp. 193,539.50
PPL 6.75 1 M Pasang lantai vinyl karet 30 x 30 cm KL I

6.75.1 Bahan
- Vinyl karet 11.050 Bh x Rp. 9,800 = Rp. 108,290.00
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 124,005.00
6.75.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.0075 Oh x Rp. 95,600 = Rp. 717.00
Jumlah (2) = Rp. 21,790.50
Jumlah (1) + (2) = Rp. 145,795.50

PPL 6.76 1 M Pasang lantai vinyl karet 30 x 30 cm KL II

6.76.1 Bahan
- Vinyl karet 11.050 Bh x Rp. 9,080 = Rp. 100,334.00
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 116,049.00
6.76.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.0075 Oh x Rp. 95,600 = Rp. 717.00
Jumlah (2) = Rp. 21,790.50
Jumlah (1) + (2) = Rp. 137,839.50

PPL 6.77 1 M Pasang lantai vinyl asbes 30 x 30 cm

6.77.1 Bahan
- Vinyl asbes 30 x 30 cm 11.050 Bh x Rp. 8,230 = Rp. 90,941.50
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 106,656.50
6.77.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.0075 Oh x Rp. 95,600 = Rp. 717.00
Jumlah (2) = Rp. 21,790.50
Jumlah (1) + (2) = Rp. 128,447.00

PPL 6.78 1 M Pasang lantai vinyl motif kembang 30 x 30 cm

6.78.1 Bahan
- Vinyl motif kembang 11.050 Bh x Rp. 9,440 = Rp. 104,312.00
- Lem vinyl 0.350 Kg x Rp. 44,900 = Rp. 15,715.00
Jumlah (1) = Rp. 120,027.00
6.78.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang batu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.0075 Oh x Rp. 95,600 = Rp. 717.00
Jumlah (2) = Rp. 21,790.50
Jumlah (1) + (2) = Rp. 141,817.50
PPL 6.79 1 M Pasang wall corvering lebar 50 cm

6.79.1 Bahan
- Corvering L.50 cm 1.100 M x Rp. 63,250 = Rp. 69,575.00
- Lem 0.250 Kg x Rp. 44,900 = Rp. 11,225.00
Jumlah (1) = Rp. 80,800.00
6.79.2 Tenaga
- Pekerja 0.750 Oh x Rp. 52,500 = Rp. 39,375.00
- Tukang batu 0.170 Oh x Rp. 78,800 = Rp. 13,396.00
- Kepala tukang 0.017 Oh x Rp. 91,900 = Rp. 1,562.30
- Mandor 0.0085 Oh x Rp. 95,600 = Rp. 812.60
Jumlah (2) = Rp. 55,145.90
Jumlah (1) + (2) = Rp. 135,945.90

PPL 6.82 1 M Plint kayu Jati 2 x 10 cm

6.82.1 Bahan
- Kayu jati papan 0.0024 M x Rp. 24,104,440 = Rp. 57,850.66
- Paku skrup 3,5" 0.050 Kg x Rp. 20,350 = Rp. 1,017.50
Jumlah (1) = Rp. 58,868.16
6.82.2 Tenaga
- Pekerja 0.120 Oh x Rp. 52,500 = Rp. 6,300.00
- Tukang kayu 0.120 Oh x Rp. 78,800 = Rp. 9,456.00
- Kepala tukang 0.012 Oh x Rp. 91,900 = Rp. 1,102.80
- Mandor 0.006 Oh x Rp. 95,600 = Rp. 573.60
Jumlah (2) = Rp. 17,432.40
Jumlah (1) + (2) = Rp. 76,300.56

PPL 6.82.A 1 M Plint kayu Meranti batu 2 x 10 cm

6.82.1 Bahan
- Kayu meranti batu, papan 0.0024 M x Rp. 9,375,000 = Rp. 22,500.00
- Paku skrup 3,5" 0.050 Kg x Rp. 20,350 = Rp. 1,017.50
Jumlah (1) = Rp. 23,517.50
6.82.2 Tenaga
- Pekerja 0.120 Oh x Rp. 52,500 = Rp. 6,300.00
- Tukang kayu 0.120 Oh x Rp. 78,800 = Rp. 9,456.00
- Kepala tukang 0.012 Oh x Rp. 91,900 = Rp. 1,102.80
- Mandor 0.006 Oh x Rp. 95,600 = Rp. 573.60
Jumlah (2) = Rp. 17,432.40
Jumlah (1) + (2) = Rp. 40,949.90
ANALISA BIAYA KONSTRUKSI
PEKERJAAN KUNCI DAN KACA

PKK 6.1 1 buah pasang kunci tanam antik


6.1.1 Bahan
- Kunci tanam antik 1.000 Bh x Rp. 214,500 = Rp. 214,500.00
Jumlah (1) = Rp. 214,500.00
6.1.2 Tenaga
- Pekerja 0.060 Oh x Rp. 52,500 = Rp. 3,150.00
- Tukang Kayu 0.600 Oh x Rp. 78,800 = Rp. 47,280.00
- Kepala Tukang 0.060 Oh x Rp. 91,900 = Rp. 5,514.00
- Mandor 0.003 Oh x Rp. 95,600 = Rp. 286.80
Jumlah (2) = Rp. 56,230.80
Jumlah (1) + (2) = Rp. 270,730.80

PKK 6.2 1 buah pasang kunci tanam biasa


6.2.1 Bahan
- Kunci tanam biasa 1.000 Bh x Rp. 90,020 = Rp. 90,020.00
Jumlah (1) = Rp. 90,020.00
6.1.2 Tenaga
- Pekerja 0.010 Oh x Rp. 52,500 = Rp. 525.00
- Tukang Kayu 0.500 Oh x Rp. 78,800 = Rp. 39,400.00
- Kepala Tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.005 Oh x Rp. 95,600 = Rp. 478.00
Jumlah (2) = Rp. 41,322.00
Jumlah (1) + (2) = Rp. 131,342.00

PKK 6.3 1 buah pasang kunci tanam kamar mandi


6.3.1 Bahan
- Kunci tanam kamar mandi 1.000 Bh x Rp. 54,690 = Rp. 54,690.00
Jumlah (1) = Rp. 54,690.00
6.3.2 Tenaga
- Pekerja 0.005 Oh x Rp. 52,500 = Rp. 262.50
- Tukang Kayu 0.500 Oh x Rp. 78,800 = Rp. 39,400.00
- Kepala Tukang 0.005 Oh x Rp. 91,900 = Rp. 459.50
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 40,361.00
Jumlah (1) + (2) = Rp. 95,051.00

PKK 6.4 1 buah pasang kunci silinder


6.4.1 Bahan
- Kunci silinder 1.000 Bh x Rp. 34,490 = Rp. 34,490.00
Jumlah (1) = Rp. 34,490.00
6.4.2 Tenaga
- Pekerja 0.005 Oh x Rp. 52,500 = Rp. 262.50
- Tukang Kayu 0.500 Oh x Rp. 78,800 = Rp. 39,400.00
- Kepala Tukang 0.005 Oh x Rp. 91,900 = Rp. 459.50
- Mandor 0.00025 Oh x Rp. 95,600 = Rp. 23.90
Jumlah (2) = Rp. 40,145.90
Jumlah (1) + (2) = Rp. 74,635.90

PKK 6.5 1 buah pasang engsel pintu


6.5.1 Bahan
- engsel pintu 1.000 Bh x Rp. 15,130 = Rp. 15,130.00
Jumlah (1) = Rp. 15,130.00
6.5.2 Tenaga
- Pekerja 0.015 Oh x Rp. 52,500 = Rp. 787.50
- Tukang Kayu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala Tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.00075 Oh x Rp. 95,600 = Rp. 71.70
Jumlah (2) = Rp. 14,057.70
Jumlah (1) + (2) = Rp. 29,187.70
PKK 6.6 1 buah pasang engsel jendela kupu-kupu
6.6.1 Bahan
- Engsel jendela 1.000 Bh x Rp. 15,730 = Rp. 15,730.00
Jumlah (1) = Rp. 15,730.00
6.6.2 Tenaga
- Pekerja 0.010 Oh x Rp. 52,500 = Rp. 525.00
- Tukang Kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala Tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.0005 Oh x Rp. 95,600 = Rp. 47.80
Jumlah (2) = Rp. 9,371.80
Jumlah (1) + (2) = Rp. 25,101.80

PKK 6.7 1 buah pasang engsel angin

6.7.1 Bahan
- Engsel angin 1.000 Bh x Rp. 25,050 = Rp. 25,050.00
Jumlah (1) = Rp. 25,050.00
6.7.2 Tenaga
- Pekerja 0.020 Oh x Rp. 52,500 = Rp. 1,050.00
- Tukang Kayu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala Tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 19,604.00
Jumlah (1) + (2) = Rp. 44,654.00

PKK 6.8 1 buah pasang spring knip

6.8.1 Bahan
- Spring knip 1.000 Bh x Rp. 9,080 = Rp. 9,080.00
Jumlah (1) = Rp. 9,080.00
6.8.2 Tenaga
- Pekerja 0.015 Oh x Rp. 52,500 = Rp. 787.50
- Tukang Kayu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala Tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.00075 Oh x Rp. 95,600 = Rp. 71.70
Jumlah (2) = Rp. 14,057.70
Jumlah (1) + (2) = Rp. 23,137.70

PKK 6.9 1 buah pasang kait angin


6.9.1 Bahan
- Kait angin 1.000 Bh x Rp. 19,120 = Rp. 19,120.00
Jumlah (1) = Rp. 19,120.00
6.9.2 Tenaga
- Pekerja 0.015 Oh x Rp. 52,500 = Rp. 787.50
- Tukang Kayu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala Tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.00075 Oh x Rp. 95,600 = Rp. 71.70
Jumlah (2) = Rp. 14,057.70
Jumlah (1) + (2) = Rp. 33,177.70

PKK 6.10 1 buah pasang door closer


6.10.1 Bahan
- Door closer 1.000 Bh x Rp. 109,750 = Rp. 109,750.00
Jumlah (1) = Rp. 109,750.00
6.10.2 Tenaga
- Pekerja 0.050 Oh x Rp. 52,500 = Rp. 2,625.00
- Tukang Kayu 0.500 Oh x Rp. 78,800 = Rp. 39,400.00
- Kepala Tukang 0.050 Oh x Rp. 91,900 = Rp. 4,595.00
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 46,859.00
Jumlah (1) + (2) = Rp. 156,609.00
PKK 6.11 1 buah pasang kunci selot
6.11.1 Bahan
- Kunci selot 1.000 Bh x Rp. 27,230 = Rp. 27,230.00
Jumlah (1) = Rp. 27,230.00
6.11.2 Tenaga
- Pekerja 0.020 Oh x Rp. 52,500 = Rp. 1,050.00
- Tukang Kayu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala Tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.001 Oh x Rp. 95,600 = Rp. 95.60
Jumlah (2) = Rp. 18,743.60
Jumlah (1) + (2) = Rp. 45,973.60

PKK 6.12 1 buah pasang pegangan pintu / door holder


6.12.1 Bahan
- Pegangan pintu / door holder 1.000 Bh x Rp. 113,010 = Rp. 113,010.00
Jumlah (1) = Rp. 113,010.00
6.12.2 Tenaga
- Pekerja 0.050 Oh x Rp. 52,500 = Rp. 2,625.00
- Tukang Kayu 0.500 Oh x Rp. 78,800 = Rp. 39,400.00
- Kepala Tukang 0.050 Oh x Rp. 91,900 = Rp. 4,595.00
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 46,859.00
Jumlah (1) + (2) = Rp. 159,869.00

PKK 6.13 1 buah pasang door stop

6.13.1 Bahan
- Door stop 1.000 Bh x Rp. 38,120 = Rp. 38,120.00
Jumlah (1) = Rp. 38,120.00
6.13.2 Tenaga
- Pekerja 0.010 Oh x Rp. 52,500 = Rp. 525.00
- Tukang Kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala Tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.0005 Oh x Rp. 95,600 = Rp. 47.80
Jumlah (2) = Rp. 9,371.80
Jumlah (1) + (2) = Rp. 47,491.80

PKK 6.14 1 buah pasang rel pintu dorong


6.14.1 Bahan
- Rel pintu dorong 1.000 Bh x Rp. 160,330 = Rp. 160,330.00
Jumlah (1) = Rp. 160,330.00
6.14.2 Tenaga
- Pekerja 0.060 Oh x Rp. 52,500 = Rp. 3,150.00
- Tukang Kayu 0.600 Oh x Rp. 78,800 = Rp. 47,280.00
- Kepala Tukang 0.060 Oh x Rp. 91,900 = Rp. 5,514.00
- Mandor 0.003 Oh x Rp. 95,600 = Rp. 286.80
Jumlah (2) = Rp. 56,230.80
Jumlah (1) + (2) = Rp. 216,560.80

PKK 6.15 1 buah pasang kunci lemari

6.15.1 Bahan
- Kunci lemari 1.000 Bh x Rp. 12,340 = Rp. 12,340.00
Jumlah (1) = Rp. 12,340.00
6.15.2 Tenaga
- Pekerja 0.025 Oh x Rp. 52,500 = Rp. 1,312.50
- Tukang Kayu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala Tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.00125 Oh x Rp. 95,600 = Rp. 119.50
Jumlah (2) = Rp. 23,429.50
Jumlah (1) + (2) = Rp. 35,769.50
PKK 6.16 1 M pasang kaca, tebal 3 mm
6.16.1 Bahan
- Kaca 1.100 M x Rp. 87,120 = Rp. 95,832.00
Jumlah (1) = Rp. 95,832.00
6.16.2 Tenaga
- Pekerja 0.015 Oh x Rp. 52,500 = Rp. 787.50
- Tukang Kayu 0.150 Oh x Rp. 78,800 = Rp. 11,820.00
- Kepala Tukang 0.015 Oh x Rp. 91,900 = Rp. 1,378.50
- Mandor 0.00075 Oh x Rp. 95,600 = Rp. 71.70
Jumlah (2) = Rp. 14,057.70
Jumlah (1) + (2) = Rp. 109,889.70

PKK 6.17 1 M pasang kaca, tebal 5 mm


6.17.1 Bahan
- Kaca 1.100 M x Rp. 145,200 = Rp. 159,720.00
Jumlah (1) = Rp. 159,720.00
6.17.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 52,500 = Rp. 813.75
- Tukang Kayu 0.1550 Oh x Rp. 78,800 = Rp. 12,214.00
- Kepala Tukang 0.0155 Oh x Rp. 91,900 = Rp. 1,424.45
- Mandor 0.00075 Oh x Rp. 95,600 = Rp. 71.70
Jumlah (2) = Rp. 14,523.90
Jumlah (1) + (2) = Rp. 174,243.90

PKK 6.18 1 M pasang kaca, tebal 8 mm


6.18.1 Bahan
- Kaca polos 1.100 M x Rp. 232,320 = Rp. 255,552.00
Jumlah (1) = Rp. 255,552.00
6.18.2 Tenaga
- Pekerja 0.0165 Oh x Rp. 52,500 = Rp. 866.25
- Tukang Kayu 0.165 Oh x Rp. 78,800 = Rp. 13,002.00
- Kepala Tukang 0.0165 Oh x Rp. 91,900 = Rp. 1,516.35
- Mandor 0.0008 Oh x Rp. 95,600 = Rp. 76.48
Jumlah (2) = Rp. 15,461.08
Jumlah (1) + (2) = Rp. 271,013.08

PKK 6.19 1 M pasang kaca buram, tebal 5 mm

6.19.1 Bahan
- Kaca buram 1.100 M x Rp. 111,320 = Rp. 122,452.00
- Sealent 0.050 Kg x Rp. 39,330 = Rp. 1,966.50
Jumlah (1) = Rp. 124,418.50
6.19.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 52,500 = Rp. 813.75
- Tukang Kayu 0.1550 Oh x Rp. 78,800 = Rp. 12,214.00
- Kepala Tukang 0.0155 Oh x Rp. 91,900 = Rp. 1,424.45
- Mandor 0.00075 Oh x Rp. 95,600 = Rp. 71.70
Jumlah (2) = Rp. 14,523.90
Jumlah (1) + (2) = Rp. 138,942.40

PKK 6.20 1 M pasang kaca cermin, tebal 5 mm

6.20.1 Bahan
- Kaca cermin 1.100 M x Rp. 161,700 = Rp. 177,870.00
Jumlah (1) = Rp. 177,870.00
6.20.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 52,500 = Rp. 813.75
- Tukang Kayu 0.1550 Oh x Rp. 78,800 = Rp. 12,214.00
- Kepala Tukang 0.0155 Oh x Rp. 91,900 = Rp. 1,424.45
- Mandor 0.00075 Oh x Rp. 95,600 = Rp. 71.70
Jumlah (2) = Rp. 14,523.90
Jumlah (1) + (2) = Rp. 192,393.90
PKK 6.21 1 M pasang kaca cermin, tebal 8 mm

6.21.1 Bahan
- Kaca cermin 1.100 M x Rp. 258,720 = Rp. 284,592.00
Jumlah (1) = Rp. 284,592.00
6.21.2 Tenaga
- Pekerja 0.0165 Oh x Rp. 52,500 = Rp. 866.25
- Tukang Kayu 0.165 Oh x Rp. 78,800 = Rp. 13,002.00
- Kepala Tukang 0.0165 Oh x Rp. 91,900 = Rp. 1,516.35
- Mandor 0.0008 Oh x Rp. 95,600 = Rp. 76.48
Jumlah (2) = Rp. 15,461.08
Jumlah (1) + (2) = Rp. 300,053.08

PKK 6.23 1 M pasang kaca "wireglass" , tebal 5 mm

6.23.1 Bahan
- Kaca wireglass 1.100 M x Rp. 151,250 = Rp. 166,375.00
Jumlah (1) = Rp. 166,375.00
6.23.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 52,500 = Rp. 813.75
- Tukang Kayu 0.1550 Oh x Rp. 78,800 = Rp. 12,214.00
- Kepala Tukang 0.0155 Oh x Rp. 91,900 = Rp. 1,424.45
- Mandor 0.00075 Oh x Rp. 95,600 = Rp. 71.70
Jumlah (2) = Rp. 14,523.90
Jumlah (1) + (2) = Rp. 180,898.90

PKK 6.24 1 M pasang kaca patri, tebal 5 mm


6.24.1 Bahan
- Kaca patri 1.100 M x Rp. 169,400 = Rp. 186,340.00
Jumlah (1) = Rp. 186,340.00
6.24.2 Tenaga
- Pekerja 0.0250 Oh x Rp. 52,500 = Rp. 1,312.50
- Tukang Kayu 0.2500 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala Tukang 0.0250 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.00125 Oh x Rp. 95,600 = Rp. 119.50
Jumlah (2) = Rp. 23,429.50
Jumlah (1) + (2) = Rp. 209,769.50

PKK 6.24.A 1 M pasang kaca Reyben, tebal 5 mm

6.24.1 Bahan
- Kaca reyben 1.100 M x Rp. 193,120 = Rp. 212,432.00
Jumlah (1) = Rp. 212,432.00
6.24.2 Tenaga
- Pekerja 0.0155 Oh x Rp. 52,500 = Rp. 813.75
- Tukang Kayu 0.1550 Oh x Rp. 78,800 = Rp. 12,214.00
- Kepala Tukang 0.0155 Oh x Rp. 91,900 = Rp. 1,424.45
- Mandor 0.00075 Oh x Rp. 95,600 = Rp. 71.70
Jumlah (2) = Rp. 14,523.90
Jumlah (1) + (2) = Rp. 226,955.90
ANALISA BIAYA KONTRUKSI
PEKERJAAN PENGECATAN

PC 6.1 1M Mengikis/ mengerok permukaan cat tembok lama


6.1.1 Bahan
- Soda api 0.050 Kg x Rp. 12,100 = Rp. 605.00
Jumlah (1) = Rp. 605.00
6.1.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 8,114.00
Jumlah (1) + (2) = Rp. 8,719.00

PC 6.2. 1M Mencuci bidang permukaan tembok yang pernah di cat


6.2.1 Bahan
- Sabun 0.050 Kg x Rp. 10,290 = Rp. 514.50
Jumlah (1) = Rp. 514.50
6.2.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 8,114.00
Jumlah (1) + (2) = Rp. 8,628.50

PC 6.3. 1M Mengerok karat cat lama permukaan baja dengan cara manual
6.3 .1 Bahan
- Sabun 0.050 Kg x Rp. 10,290 = Rp. 514.50
Jumlah (1) = Rp. 514.50
6.3.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 8,114.00
Jumlah (1) + (2) = Rp. 8,628.50

PC 6.4 1M Menyabun permukaan tembok lama


6.4 .1 Bahan
- Sabun 0.050 Kg x Rp. 10,290 = Rp. 514.50
Jumlah (1) = Rp. 514.50
6.4.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 8,114.00
Jumlah (1) + (2) = Rp. 8,628.50

PC 6.6 1M Mendempul dan menggosok kayu

6.4 .1 Bahan
- Dempul jadi 0.080 Kg x Rp. 11,860 = Rp. 948.80
- Minyak cat 0.020 Kg x Rp. 11,010 = Rp. 220.20
- Amplas 0.100 Lbr x Rp. 1,820 = Rp. 182.00
Jumlah (1) = Rp. 1,351.00
6.4.2 Tenaga
- Pekerja 0.040 Oh x Rp. 52,500 = Rp. 2,100.00
- Tukang cat 0.040 Oh x Rp. 78,800 = Rp. 3,152.00
- Kepala tukang 0.040 Oh x Rp. 91,900 = Rp. 3,676.00
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 9,167.00
Jumlah (1) + (2) = Rp. 10,518.00
PC 6.7 1M Pengecatan bidang kayu lama

6.7.1 Bahan
- Plamir 0.150 Kg x Rp. 15,730 = Rp. 2,359.50
- Minyak Cat 0.170 Kg x Rp. 11,010 = Rp. 1,871.70
- Cat Minyak 0.170 Kg x Rp. 35,700 = Rp. 6,069.00
Jumlah (1) = Rp. 10,300.20
6.7.2 Tenaga
- Pekerja 0.070 Oh x Rp. 52,500 = Rp. 3,675.00
- Tukang cat 0.075 Oh x Rp. 78,800 = Rp. 5,910.00
- Kepala tukang 0.0075 Oh x Rp. 91,900 = Rp. 689.25
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 10,513.25
Jumlah (1) + (2) = Rp. 20,813.45

PC 6.8 1M Pengecatan bidang kayu baru 1 lps plamir, 1 lps cat dasar, 2 lps cat minyak
6.8.1 Bahan
- Cat menie kayu 0.200 Kg x Rp. 20,570 = Rp. 4,114.00
- Plamir 0.150 Kg x Rp. 15,730 = Rp. 2,359.50
- Cat dasar 0.170 Kg x Rp. 15,730 = Rp. 2,674.10
- Cat Minyak 0.260 Kg x Rp. 35,700 = Rp. 9,282.00
Jumlah (1) = Rp. 18,429.60
6.8.2 Tenaga
- Pekerja 0.070 Oh x Rp. 52,500 = Rp. 3,675.00
- Tukang cat 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.0090 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 11,833.10
Jumlah (1) + (2) = Rp. 30,262.70

PC 6.9 1M Pengecatan bidang kayu baru 1 lps plamir, 1 lps cat dasar, 3lps cat minyak
6.9.1 Bahan
- Cat menie kayu 0.200 Kg x Rp. 20,570 = Rp. 4,114.00
- Plamir 0.150 Kg x Rp. 15,730 = Rp. 2,359.50
- Minyak Cat 0.170 Kg x Rp. 11,010 = Rp. 1,871.70
- Cat Minyak 0.350 Kg x Rp. 35,700 = Rp. 12,495.00
Jumlah (1) = Rp. 20,840.20
6.9.2 Tenaga
- Pekerja 0.070 Oh x Rp. 52,500 = Rp. 3,675.00
- Tukang cat 0.105 Oh x Rp. 78,800 = Rp. 8,274.00
- Kepala tukang 0.0105 Oh x Rp. 91,900 = Rp. 964.95
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 13,152.95
Jumlah (1) + (2) = Rp. 33,993.15

PC 6.11 1M Peleburan kayu dengan politur


6.11.1 Bahan
- Minyak politur 0.150 Kg x Rp. 11,010 = Rp. 1,651.50
- Politur Jadi / vernis 0.372 Kg x Rp. 48,280 = Rp. 17,960.16
- Amplas 2.000 Kg x Rp. 1,820 = Rp. 3,640.00
Jumlah (1) = Rp. 23,251.66
6.11.2 Tenaga
- Pekerja 0.040 Oh x Rp. 52,500 = Rp. 2,100.00
- Tukang cat 0.060 Oh x Rp. 78,800 = Rp. 4,728.00
- Kepala tukang 0.0160 Oh x Rp. 91,900 = Rp. 1,470.40
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 8,537.40
Jumlah (1) + (2) = Rp. 31,789.06
PC 6.12 1M Peleburan kayu dengan residu
6.12.1 Bahan
- Residu 0.350 Kg x Rp. 6,530 = Rp. 2,285.50
Jumlah (1) = Rp. 2,285.50
6.12.2 Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp. 5,250.00
- Mandor 0.006 Oh x Rp. 95,600 = Rp. 573.60
Jumlah (2) = Rp. 5,823.60
Jumlah (1) + (2) = Rp. 8,109.10

PC 6.13 1M Peleburan bidang kayu dan vernis

6.13.1 Bahan
- Vernis 0.150 Ltr x Rp. 48,280 = Rp. 7,242.00
- Dempul 0.050 Kg x Rp. 11,860 = Rp. 593.00
- Ampelas 0.100 Lbr x Rp. 1,820 = Rp. 182.00
- Kuas 0.010 bh x Rp. 7,870 = Rp. 78.70
Jumlah (1) = Rp. 8,095.70
6.13.2 Tenaga
- Pekerja 0.160 Oh x Rp. 52,500 = Rp. 8,400.00
- Tukang cat 0.160 Oh x Rp. 78,800 = Rp. 12,608.00
- Kepala tukang 0.016 Oh x Rp. 91,900 = Rp. 1,470.40
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 22,717.40
Jumlah (1) + (2) = Rp. 30,813.10

PC 6.14 1M Pengecatan tembok baru ( 1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup )

6.14.1 Bahan
- Plamir 0.120 Kg x Rp. 15,730 = Rp. 1,887.60
- Cat dasar 0.120 Kg x Rp. 15,730 = Rp. 1,887.60
- Cat tembok 2 x 0.260 Kg x Rp. 19,360 = Rp. 5,033.60
Jumlah (1) = Rp. 8,808.80
6.14.2 Tenaga
- Pekerja 0.040 Oh x Rp. 52,500 = Rp. 2,100.00
- Tukang cat 0.120 Oh x Rp. 78,800 = Rp. 9,456.00
- Kepala tukang 0.0120 Oh x Rp. 91,900 = Rp. 1,102.80
- Mandor 0.002 Oh x Rp. 95,600 = Rp. 191.20
Jumlah (2) = Rp. 12,850.00
Jumlah (1) + (2) = Rp. 21,658.80

PC 6.15 1M Pengecatan tembok lama ( 1 lapis cat dasar, 2 lapis cat penutup )

6.15.1 Bahan
- Cat dasar 0.120 Kg x Rp. 15,730 = Rp. 1,887.60
- Cat tembok 2 x 0.260 Kg x Rp. 19,360 = Rp. 5,033.60
Jumlah (1) = Rp. 6,921.20
6.15.2 Tenaga
- Pekerja 0.030 Oh x Rp. 52,500 = Rp. 1,575.00
- Tukang cat 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.0090 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.0015 Oh x Rp. 95,600 = Rp. 143.40
Jumlah (2) = Rp. 9,637.50
Jumlah (1) + (2) = Rp. 16,558.70
PC 6.19 1M Pemasangan wall paper

6.19.1 Bahan
- wall paper 1.200 M x Rp. 30,610 = Rp. 36,732.00
- Perekat lem karet 0.200 Kg x Rp. 44,900 = Rp. 8,980.00
Jumlah (1) = Rp. 45,712.00
6.19.2 Tenaga
- Pekerja 0.020 Oh x Rp. 52,500 = Rp. 1,050.00
- Tukang cat 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.002 Oh x Rp. 91,900 = Rp. 183.80
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 17,232.80
Jumlah (1) + (2) = Rp. 62,944.80

PC 6.20 1M Pengecatan permukaan baja dengan meni besi

6.20.1 Bahan
- Meni besi 0.100 Kg x Rp. 25,410 = Rp. 2,541.00
- Kuas 0.010 Bh x Rp. 7,870 = Rp. 78.70
Jumlah (1) = Rp. 2,619.70
6.20.2 Tenaga
- Pekerja 0.020 Oh x Rp. 52,500 = Rp. 1,050.00
- Tukang cat 0.020 Oh x Rp. 78,800 = Rp. 1,576.00
- Kepala tukang 0.02 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.01 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 5,420.00
Jumlah (1) + (2) = Rp. 8,039.70

PC 6.21. 1M Pengecatan permukaan baja dengan meni besi dan perancah

6.21.1 Bahan
- Meni besi 0.100 Kg x Rp. 25,410 = Rp. 2,541.00
- Kuas 0.010 Bh x Rp. 7,870 = Rp. 78.70
- Peranca kayu 0.002 M x Rp. 3,107,500 = Rp. 6,215.00
Jumlah (1) = Rp. 8,834.70
6.21.2 Tenaga
- Pekerja 0.250 Oh x Rp. 52,500 = Rp. 13,125.00
- Tukang cat 0.225 Oh x Rp. 78,800 = Rp. 17,730.00
- Kepala tukang 0.0225 Oh x Rp. 91,900 = Rp. 2,067.75
- Mandor 0.0075 Oh x Rp. 95,600 = Rp. 717.00
Jumlah (2) = Rp. 33,639.75
Jumlah (1) + (2) = Rp. 42,474.45

PC 6.23. 1M Pengecatan permukaan baja lapis seng (galbani) secara manual


sistem 1 lapis cat konvensional dengan tebal 200 um.

6.23.1 Bahan
- Cat Minyak besi 0.300 Kg x Rp. 39,330 = Rp. 11,799.00
Jumlah (1) = Rp. 11,799.00
6.23.2 Tenaga
- Pekerja 0.060 Oh x Rp. 52,500 = Rp. 3,150.00
- Tukang cat 0.060 Oh x Rp. 78,800 = Rp. 4,728.00
- Kepala tukang 0.1200 Oh x Rp. 91,900 = Rp. 11,028.00
- Mandor 0.006 Oh x Rp. 95,600 = Rp. 573.60
Jumlah (2) = Rp. 19,479.60
Jumlah (1) + (2) = Rp. 31,278.60

PC 6.24. 1M Pengecatan permukaan baja lapis seng (galbani) secara manual


sistem 3 lapis cat konvensional dengan tebal 200 um.

6.24.1 Bahan
- Cat dasar 0.110 Kg x Rp. 15,730 = Rp. 1,730.30
- Cat menie besi 0.170 Kg x Rp. 25,410 = Rp. 4,319.70
- Cat minyak besi 0.080 Kg x Rp. 39,330 = Rp. 3,146.40
Jumlah (1) = Rp. 9,196.40
6.24.2 Tenaga
- Pekerja 0.500 Oh x Rp. 52,500 = Rp. 26,250.00
- Tukang cat 0.800 Oh x Rp. 78,800 = Rp. 63,040.00
- Kepala tukang 0.300 Oh x Rp. 91,900 = Rp. 27,570.00
- Mandor 0.200 Oh x Rp. 95,600 = Rp. 19,120.00
Jumlah (2) = Rp. 135,980.00
Jumlah (1) + (2) = Rp. 145,176.40

PC 6.25. 1M Pengecatan permukaan baja lapis seng (galbani) secara semprot


(airless spray) dengan sistem 1 lapis cat konvensional dengan tebal 200 um.

6.25.1 Bahan
- Cat dasar 0.300 Kg x Rp. 15,730 = Rp. 4,719.00
Jumlah (1) = Rp. 4,719.00
6.25.2 Tenaga
- Pekerja 0.400 Oh x Rp. 52,500 = Rp. 21,000.00
- Tukang cat 0.700 Oh x Rp. 78,800 = Rp. 55,160.00
- Kepala tukang 0.200 Oh x Rp. 91,900 = Rp. 18,380.00
- Mandor 0.200 Oh x Rp. 95,600 = Rp. 19,120.00
Jumlah (2) = Rp. 113,660.00
Jumlah (1) + (2) = Rp. 118,379.00
ANALISA BIAYA KONSTRUKSI
PEKERJAAN SANITASI

PS 6.1. Memasang 1 buah kloset duduk/monoblok

6.1.1. Bahan
- Klosed duduk/monoblok 1.000 Bh x Rp. 1,931,600 = Rp. 1,931,600.00
- Perlengkapan 6% harga klosed x Rp. 1,931,600 = Rp. 115,896.00
Jumlah (1) = Rp. 2,047,496.00
6.1.2. Tenaga
- Pekerja 3.300 Oh x Rp. 52,500 = Rp. 173,250.00
- Tukang batu 1.500 Oh x Rp. 78,800 = Rp. 118,200.00
- Kepala tukang 0.150 Oh x Rp. 91,900 = Rp. 13,785.00
- Mandor 0.160 Oh x Rp. 95,600 = Rp. 15,296.00
Jumlah (2) = Rp. 320,531.00
Jumlah (1) +(2) = Rp. 2,368,027.00

PS 6.2. Memasang 1 buah kloset jongkok porselen

6.2.1. Bahan
- Klosed jongkok porselin 1.000 Bh x Rp. 225,280 = Rp. 225,280.00
- Semen portland 6.000 Kg x Rp. 1,270 = Rp. 7,620.00
- Pasir pasang 0.010 M x Rp. 76,500 = Rp. 765.00
Jumlah (1) = Rp. 233,665.00
6.2.2. Tenaga
- Pekerja 1.100 Oh x Rp. 52,500 = Rp. 57,750.00
- Tukang batu 1.500 Oh x Rp. 78,800 = Rp. 118,200.00
- Kepala tukang 0.150 Oh x Rp. 91,900 = Rp. 13,785.00
- Mandor 0.110 Oh x Rp. 95,600 = Rp. 10,516.00
Jumlah (2) = Rp. 200,251.00
Jumlah (1) +(2) = Rp. 433,916.00

PS 6.3. Memasang 1 buah kloset jongkok teraso

6.3.1. Bahan
- Klosed jongkok teraso 1.000 Bh x Rp. 526,350 = Rp. 526,350.00
- Bata merah 5x10x20 cm 7.000 Bh x Rp. 610 = Rp. 4,270.00
- Semen portland 6.000 Kg x Rp. 1,270 = Rp. 7,620.00
- Pasir pasang 0.010 M x Rp. 76,500 = Rp. 765.00
Jumlah (1) = Rp. 539,005.00
6.3.2. Tenaga
- Pekerja 1.000 Oh x Rp. 52,500 = Rp. 52,500.00
- Tukang batu 1.500 Oh x Rp. 78,800 = Rp. 118,200.00
- Kepala tukang 0.150 Oh x Rp. 91,900 = Rp. 13,785.00
- Mandor 0.100 Oh x Rp. 95,600 = Rp. 9,560.00
Jumlah (2) = Rp. 194,045.00
Jumlah (1) +(2) = Rp. 733,050.00
PS 6.4 Memasang 1 buah urinoir

6.4.1. Bahan
- Urinoir 1.000 Bh x Rp. 557,480 = Rp. 557,480.00
- Perlengkapan 15% harga urinoir x Rp. 557,480 = Rp. 83,622.00
- Semen portland 6.000 Kg x Rp. 1,270 = Rp. 7,620.00
- Pasir pasang 0.010 M x Rp. 76,500 = Rp. 765.00
Jumlah (1) = Rp. 649,487.00
6.4.2. Tenaga
- Pekerja 1.000 Oh x Rp. 52,500 = Rp. 52,500.00
- Tukang batu 1.000 Oh x Rp. 78,800 = Rp. 78,800.00
- Kepala tukang 0.100 Oh x Rp. 91,900 = Rp. 9,190.00
- Mandor 0.100 Oh x Rp. 95,600 = Rp. 9,560.00
Jumlah (2) = Rp. 150,050.00
Jumlah (1) +(2) = Rp. 799,537.00

PS 6.5 Memasang 1 buah wastafel

6.5.1. Bahan
- Wastafel 1.000 Bh x Rp. 526,350 = Rp. 526,350.00
- Perlengkapan 12% harga wastafel x Rp. 526,350 = Rp. 63,162.00
- Semen portland 6.000 Kg x Rp. 1,270 = Rp. 7,620.00
- Pasir pasang 0.010 M x Rp. 76,500 = Rp. 765.00
Jumlah (1) = Rp. 597,897.00
6.5.2. Tenaga
- Pekerja 1.200 Oh x Rp. 52,500 = Rp. 63,000.00
- Tukang batu 1.450 Oh x Rp. 78,800 = Rp. 114,260.00
- Kepala tukang 0.150 Oh x Rp. 91,900 = Rp. 13,785.00
- Mandor 0.100 Oh x Rp. 95,600 = Rp. 9,560.00
Jumlah (2) = Rp. 200,605.00
Jumlah (1) +(2) = Rp. 798,502.00

PS 6.6. Memasang 1 buah bak mandi teraso volume 0,30 m

6.6.1. Bahan
- Bak teraso 1.000 Bh x Rp. 181,500 = Rp. 181,500.00
- Semen portland 6.000 Kg x Rp. 1,270 = Rp. 7,620.00
- Pasir pasang 0.010 M x Rp. 76,500 = Rp. 765.00
Jumlah (1) = Rp. 189,885.00
6.6.2. Tenaga
- Pekerja 2.100 Oh x Rp. 52,500 = Rp. 110,250.00
- Tukang batu 0.750 Oh x Rp. 78,800 = Rp. 59,100.00
- Kepala tukang 0.075 Oh x Rp. 91,900 = Rp. 6,892.50
- Mandor 0.110 Oh x Rp. 95,600 = Rp. 10,516.00
Jumlah (2) = Rp. 186,758.50
Jumlah (1) +(2) = Rp. 376,643.50
PS 6.7. Memasang 1 buah bak mandi fibreglass volume 0,30 m

6.7.1. Bahan
- Bak fibreglass 1.000 Bh x Rp. 181,500 = Rp. 181,500.00
- Perlengkapan 18% Harga bak x Rp. 181,500 = Rp. 32,670.00
Jumlah (1) = Rp. 214,170.00
6.7.2. Tenaga
- Pembantu tukang 1.800 Oh x Rp. 52,500 = Rp. 94,500.00
- Tukang batu 0.540 Oh x Rp. 78,800 = Rp. 42,552.00
- Kepala tukang 0.054 Oh x Rp. 91,900 = Rp. 4,962.60
- Mandor 0.110 Oh x Rp. 95,600 = Rp. 10,516.00
Jumlah (2) = Rp. 152,530.60
Jumlah (1) +(2) = Rp. 366,700.60
0.35129

PS 6.8. Memasang 1 buah bak mandi batu bata volume 0,30 m

6.8.1. Bahan
- Batu bata 44.000 M x Rp. 720 = Rp. 31,680.00
- Semen portland 120.000 Kg x Rp. 1,270 = Rp. 152,400.00
- Pasir pasang 0.300 M x Rp. 76,500 = Rp. 22,950.00
- Porselin (11x11) cm 360.000 Bh x Rp. 145 = Rp. 52,200.00
- Semen putih 6.000 Kg x Rp. 2,500 = Rp. 15,000.00
Jumlah (1) = Rp. 274,230.00
6.8.2. Tenaga
- Pekerja 3.000 Oh x Rp. 52,500 = Rp. 157,500.00
- Tukang batu 3.000 Oh x Rp. 78,800 = Rp. 236,400.00
- Kepala tukang 0.300 Oh x Rp. 91,900 = Rp. 27,570.00
- Mandor 0.300 Oh x Rp. 95,600 = Rp. 28,680.00
Jumlah (2) = Rp. 450,150.00
Jumlah (1) +(2) = Rp. 724,380.00

PS 6.9. Memasang 1 buah badkip porselin

6.9.1. Bahan
- Badkip 1.000 Bh x Rp. 3,025,000 = Rp. 3,025,000.00
- Perlengkapan 20% Harga badkip x Rp. 3,025,000 = Rp. 605,000.00
Jumlah (1) = Rp. 3,630,000.00
6.9.2. Tenaga
- Pekerja 2.500 Oh x Rp. 52,500 = Rp. 131,250.00
- Tukang batu 0.750 Oh x Rp. 78,800 = Rp. 59,100.00
- Kepala tukang 0.075 Oh x Rp. 91,900 = Rp. 6,892.50
- Mandor 0.250 Oh x Rp. 95,600 = Rp. 23,900.00
Jumlah (2) = Rp. 221,142.50
Jumlah (1) +(2) = Rp. 3,851,142.50
PS 6.10. Memasang 1 buah bak mandi beton volume 1 m air

6.10.1 Bahan
- Beton 1 : 1 : 2 0.900 M x Rp. 12,500 = Rp. 11,250.00
- Besi beton 180.000 Kg x Rp. 14,410 = Rp. 2,593,800.00
- Kayu cetakan 0.096 M x Rp. 3,107,500 = Rp. 298,320.00
- Ubin porselin 420.000 M x Rp. 145 = Rp. 60,900.00
- Perlengkapan 10% Hrg total bahan x Rp. 2,964,270 = Rp. 296,427.00
Jumlah (1) = Rp. 3,260,697.00

6.10.2 Tenaga
- Pekerja 3.500 Oh x Rp. 52,500 = Rp. 183,750.00
- Tukang batu 4.500 Oh x Rp. 78,800 = Rp. 354,600.00
- Kepala tukang 0.900 Oh x Rp. 91,900 = Rp. 82,710.00
- Mandor 0.900 Oh x Rp. 95,600 = Rp. 86,040.00
Jumlah (2) = Rp. 707,100.00
Jumlah (1) +(2) = Rp. 3,967,797.00

PS 6.11. Memasang 1 buah bak fibreglass volume 1 m air

6.11.1.Bahan
- Bak fibreglass 1.000 Bh x Rp. 181,500 = Rp. 181,500.00
- Perlengkapan 12% Harga bak x Rp. 181,500 = Rp. 21,780.00
Jumlah (1) = Rp. 203,280.00
6.11.2.Tenaga
- Pekerja 3.000 Oh x Rp. 52,500 = Rp. 157,500.00
- Tukang batu 4.500 Oh x Rp. 78,800 = Rp. 354,600.00
- Kepala tukang 0.900 Oh x Rp. 91,900 = Rp. 82,710.00
- Mandor 0.900 Oh x Rp. 95,600 = Rp. 86,040.00
Jumlah (2) = Rp. 680,850.00
Jumlah (1) +(2) = Rp. 884,130.00

PS 6.15. Memasang 1 m' pipa beton, diameter 30 cm - 100 cm

6.15.1 Bahan
- Pipa beton 1.100 Bh x Rp. 56,270 = Rp. 61,897.00
- Batu bata 55.000 Bh x Rp. 720 = Rp. 39,600.00
- Semen portland 10.300 Kg x Rp. 1,270 = Rp. 13,081.00
- Pasir pasang 0.061 M x Rp. 76,500 = Rp. 4,666.50
- Pasir urug 0.069 M x Rp. 64,400 = Rp. 4,443.60
Jumlah (1) = Rp. 123,688.10
6.15.2 Tenaga
- Pekerja 0.380 Oh x Rp. 52,500 = Rp. 19,950.00
- Tukang batu 0.190 Oh x Rp. 78,800 = Rp. 14,972.00
- Kepala tukang 0.019 Oh x Rp. 91,900 = Rp. 1,746.10
- Mandor 0.019 Oh x Rp. 95,600 = Rp. 1,816.40
Jumlah (2) = Rp. 38,484.50
Jumlah (1) +(2) = Rp. 162,172.60
PS 6.16. Memasang 1 buah bak kontrol pasangan batu bata ukuran (30 x 30) cm
tinggi 35 cm

6.16.1 Bahan
- Batu bata 145.000 Bh x Rp. 720 = Rp. 104,400.00
- Semen portland 44.000 Kg x Rp. 1,270 = Rp. 55,880.00
- Pasir pasang 0.070 M x Rp. 76,500 = Rp. 5,355.00
- Batu kerikil 0.070 M x Rp. 185,900 = Rp. 13,013.00
- Besi beton 1.600 Kg x Rp. 14,410 = Rp. 23,056.00
- Pasir beton 0.060 M x Rp. 87,800 = Rp. 5,268.00
Jumlah (1) = Rp. 206,972.00
6.16.2 Tenaga
- Pekerja 3.200 Oh x Rp. 52,500 = Rp. 168,000.00
- Tukang batu 1.015 Oh x Rp. 78,800 = Rp. 79,982.00
- Kepala tukang 0.0015 Oh x Rp. 91,900 = Rp. 137.85
- Mandor 0.016 Oh x Rp. 95,600 = Rp. 1,529.60
Jumlah (2) = Rp. 249,649.45
Jumlah (1) +(2) = Rp. 456,621.45

PS 6.17. Memasang 1 buah bak kontrol pasangan batu bata ukuran (45 x 45) cm
tinggi 50 cm

6.17.1 Bahan
- Batu bata 250.000 Bh x Rp. 720 = Rp. 180,000.00
- Semen portland 77.000 Kg x Rp. 1,270 = Rp. 97,790.00
- Pasir pasang 0.130 M x Rp. 76,500 = Rp. 9,945.00
- Batu kerikil 0.020 M x Rp. 185,900 = Rp. 3,718.00
- Besi beton 2.600 Kg x Rp. 14,410 = Rp. 37,466.00
- Pasir beton 0.090 M x Rp. 87,800 = Rp. 7,902.00
Jumlah (1) = Rp. 336,821.00
6.17.2 Tenaga
- Pekerja 1.420 Oh x Rp. 52,500 = Rp. 74,550.00
- Tukang batu 0.473 Oh x Rp. 78,800 = Rp. 37,272.40
- Kepala tukang 0.047 Oh x Rp. 91,900 = Rp. 4,319.30
- Mandor 0.071 Oh x Rp. 95,600 = Rp. 6,787.60
Jumlah (2) = Rp. 122,929.30
Jumlah (1) +(2) = Rp. 459,750.30

PS 6.18. Memasang 1 buah bak kontrol pasangan batu bata ukuran (60 x 60) cm
tinggi 65 cm

6.18.1 Bahan
- Batu bata 371.000 Bh x Rp. 720 = Rp. 267,120.00
- Semen portland 114.000 Kg x Rp. 1,270 = Rp. 144,780.00
- Pasir pasang 0.184 M x Rp. 76,500 = Rp. 14,076.00
- Batu koral 0.033 M x Rp. 185,900 = Rp. 6,134.70
- Besi beton 4.850 Kg x Rp. 14,410 = Rp. 69,888.50
- Pasir beton 0.120 M x Rp. 87,800 = Rp. 10,536.00
Jumlah (1) = Rp. 512,535.20
6.18.2 Tenaga
- Pekerja 2.160 Oh x Rp. 52,500 = Rp. 113,400.00
- Tukang batu 0.720 Oh x Rp. 78,800 = Rp. 56,736.00
- Kepala tukang 0.072 Oh x Rp. 91,900 = Rp. 6,616.80
- Mandor 0.108 Oh x Rp. 95,600 = Rp. 10,324.80
- Tukang gali 0.100 Oh x Rp. 52,500 = Rp. 5,250.00
Jumlah (2) = Rp. 192,327.60
Jumlah (1) +(2) = Rp. 704,862.80
PS 6.19. Memasang 1 m' pipa galvanis diameter "

6.19.1 Bahan
- Pipa galvanis 1.200 M x Rp. 14,770 = Rp. 17,724.00
- Perlengkapan 35% harga pipa x Rp. 14,770 = Rp. 5,169.50
Jumlah (1) = Rp. 22,893.50

6.19.2 Tenaga
- Pekerja 0.054 Oh x Rp. 52,500 = Rp. 2,835.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.027 Oh x Rp. 95,600 = Rp. 2,581.20
Jumlah (2) = Rp. 13,335.30
Jumlah (1) +(2) = Rp. 36,228.80

PS 6.20. Memasang 1 m' pipa galvanis diameter 3/4"

6.20.1 Bahan
- Pipa galvanis 1.200 M x Rp. 20,140 = Rp. 24,168.00
- Perlengkapan 35% harga pipa x Rp. 20,140 = Rp. 7,049.00
Jumlah (1) = Rp. 31,217.00
6.20.2 Tenaga
- Pekerja 0.054 Oh x Rp. 52,500 = Rp. 2,835.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.027 Oh x Rp. 95,600 = Rp. 2,581.20
Jumlah (2) = Rp. 13,335.30
Jumlah (1) +(2) = Rp. 44,552.30

PS 6.21. Memasang 1 m' pipa galvanis diameter 1"

6.21.1 Bahan
- Pipa galvanis 1.200 M x Rp. 29,520 = Rp. 35,424.00
- Perlengkapan 35% harga pipa x Rp. 29,520 = Rp. 10,332.00
Jumlah (1) = Rp. 45,756.00
6.21.2 Tenaga
- Pekerja 0.054 Oh x Rp. 52,500 = Rp. 2,835.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.027 Oh x Rp. 95,600 = Rp. 2,581.20
Jumlah (2) = Rp. 13,335.30
Jumlah (1) +(2) = Rp. 59,091.30
PS 6.22. Memasang 1 m' pipa galvanis diameter 1 "

6.22.1 Bahan
- Pipa galvanis 1.200 M x Rp. 37,580 = Rp. 45,096.00
- Perlengkapan 35% harga pipa x Rp. 37,580 = Rp. 13,153.00
Jumlah (1) = Rp. 58,249.00
6.22.2 Tenaga
- Pekerja 0.108 Oh x Rp. 52,500 = Rp. 5,670.00
- Tukang batu 0.180 Oh x Rp. 78,800 = Rp. 14,184.00
- Kepala tukang 0.018 Oh x Rp. 91,900 = Rp. 1,654.20
- Mandor 0.0054 Oh x Rp. 95,600 = Rp. 516.24
Jumlah (2) = Rp. 22,024.44
Jumlah (1) +(2) = Rp. 80,273.44
PS 6.23. Memasang 1 m' pipa galvanis diameter 2"

6.23.1 Bahan
- Pipa galvanis 1.200 M x Rp. 47,600 = Rp. 57,120.00
- Perlengkapan 35% harga pipa x Rp. 47,600 = Rp. 16,660.00
Jumlah (1) = Rp. 73,780.00
6.23.2 Tenaga
- Pekerja 0.108 Oh x Rp. 52,500 = Rp. 5,670.00
- Tukang batu 0.180 Oh x Rp. 78,800 = Rp. 14,184.00
- Kepala tukang 0.018 Oh x Rp. 91,900 = Rp. 1,654.20
- Mandor 0.0054 Oh x Rp. 95,600 = Rp. 516.24
Jumlah (2) = Rp. 22,024.44
Jumlah (1) +(2) = Rp. 95,804.44

PS 6.24. Memasang 1 m' pipa galvanis diameter 3"

6.24.1 Bahan
- Pipa galvanis 1.200 M x Rp. 52,440 = Rp. 62,928.00
- Perlengkapan 35% harga pipa x Rp. 52,440 = Rp. 18,354.00
Jumlah (1) = Rp. 81,282.00
6.24.2 Tenaga
- Pekerja 0.135 Oh x Rp. 52,500 = Rp. 7,087.50
- Tukang batu 0.225 Oh x Rp. 78,800 = Rp. 17,730.00
- Kepala tukang 0.0225 Oh x Rp. 91,900 = Rp. 2,067.75
- Mandor 0.0068 Oh x Rp. 95,600 = Rp. 650.08
Jumlah (2) = Rp. 27,535.33
Jumlah (1) +(2) = Rp. 108,817.33

PS 6.25. Memasang 1 m' pipa PVC tipe AW diameter "

6.25.1 Bahan
- Pipa PVC 1.200 M x Rp. 5,540 = Rp. 6,648.00
- Perlengkapan 35% harga pipa x Rp. 5,540 = Rp. 1,939.00
Jumlah (1) = Rp. 8,587.00
6.25.2 Tenaga
- Pekerja 0.036 Oh x Rp. 52,500 = Rp. 1,890.00
- Tukang batu 0.060 Oh x Rp. 78,800 = Rp. 4,728.00
- Kepala tukang 0.006 Oh x Rp. 91,900 = Rp. 551.40
- Mandor 0.0018 Oh x Rp. 95,600 = Rp. 172.08
Jumlah (2) = Rp. 7,341.48
Jumlah (1) +(2) = Rp. 15,928.48

PS 6.26. Memasang 1 m' pipa PVC tipe AW diameter "

6.26.1 Bahan
- Pipa PVC 1.200 M x Rp. 7,440 = Rp. 8,928.00
- Perlengkapan 35% harga pipa x Rp. 7,440 = Rp. 2,604.00
Jumlah (1) = Rp. 11,532.00
6.26.2 Tenaga
- Pekerja 0.036 Oh x Rp. 52,500 = Rp. 1,890.00
- Tukang batu 0.060 Oh x Rp. 78,800 = Rp. 4,728.00
- Kepala tukang 0.006 Oh x Rp. 91,900 = Rp. 551.40
- Mandor 0.0018 Oh x Rp. 95,600 = Rp. 172.08
Jumlah (2) = Rp. 7,341.48
Jumlah (1) +(2) = Rp. 18,873.48
PS 6.27. Memasang 1 m' pipa PVC tipe AW diameter 1"

6.27.1 Bahan
- Pipa PVC 1.200 M x Rp. 13,620 = Rp. 16,344.00
- Perlengkapan 35% harga pipa x Rp. 13,620 = Rp. 4,767.00
Jumlah (1) = Rp. 21,111.00
6.27.2 Tenaga
- Pekerja 0.036 Oh x Rp. 52,500 = Rp. 1,890.00
- Tukang batu 0.060 Oh x Rp. 78,800 = Rp. 4,728.00
- Kepala tukang 0.006 Oh x Rp. 91,900 = Rp. 551.40
- Mandor 0.0018 Oh x Rp. 95,600 = Rp. 172.08
Jumlah (2) = Rp. 7,341.48
Jumlah (1) +(2) = Rp. 28,452.48
PS 6.28. Memasang 1 m' pipa PVC tipe AW diameter 1 "
6.28.1 Bahan
- Pipa PVC 1.200 M x Rp. 19,670 = Rp. 23,604.00
- Perlengkapan 35% harga pipa x Rp. 19,670 = Rp. 6,884.50
Jumlah (1) = Rp. 30,488.50
6.28.2 Tenaga
- Pekerja 0.036 Oh x Rp. 52,500 = Rp. 1,890.00
- Tukang batu 0.060 Oh x Rp. 78,800 = Rp. 4,728.00
- Kepala tukang 0.006 Oh x Rp. 91,900 = Rp. 551.40
- Mandor 0.0018 Oh x Rp. 95,600 = Rp. 172.08
Jumlah (2) = Rp. 7,341.48
Jumlah (1) +(2) = Rp. 37,829.98
PS 6.29. Memasang 1 m' pipa PVC tipe AW diameter 2"

6.29.1 Bahan
- Pipa PVC 1.200 M x Rp. 23,190 = Rp. 27,828.00
- Perlengkapan 35% harga pipa x Rp. 23,190 = Rp. 8,116.50
Jumlah (1) = Rp. 35,944.50
6.29.2 Tenaga
- Pekerja 0.054 Oh x Rp. 52,500 = Rp. 2,835.00
- Tukang batu 0.090 Oh x Rp. 78,800 = Rp. 7,092.00
- Kepala tukang 0.009 Oh x Rp. 91,900 = Rp. 827.10
- Mandor 0.0027 Oh x Rp. 95,600 = Rp. 258.12
Jumlah (2) = Rp. 11,012.22
Jumlah (1) +(2) = Rp. 46,956.72

PS 6.30. Memasang 1 m' pipa PVC tipe AW diameter 2 "

6.30.1 Bahan
- Pipa PVC 1.200 M x Rp. 26,620 = Rp. 31,944.00
- Perlengkapan 35% harga pipa x Rp. 26,620 = Rp. 9,317.00
Jumlah (1) = Rp. 41,261.00
6.30.2 Tenaga
- Pekerja 0.036 Oh x Rp. 52,500 = Rp. 1,890.00
- Tukang batu 0.060 Oh x Rp. 78,800 = Rp. 4,728.00
- Kepala tukang 0.006 Oh x Rp. 91,900 = Rp. 551.40
- Mandor 0.0018 Oh x Rp. 95,600 = Rp. 172.08
Jumlah (2) = Rp. 7,341.48
Jumlah (1) +(2) = Rp. 48,602.48
PS 6.31. Memasang 1 m' pipa PVC tipe AW diameter 3"

6.31.1 Bahan
- Pipa PVC 1.200 M x Rp. 29,840 = Rp. 35,808.00
- Perlengkapan 35% harga pipa x Rp. 29,840 = Rp. 10,444.00
Jumlah (1) = Rp. 46,252.00
6.31.2 Tenaga
- Pekerja 0.081 Oh x Rp. 52,500 = Rp. 4,252.50
- Tukang batu 0.135 Oh x Rp. 78,800 = Rp. 10,638.00
- Kepala tukang 0.0135 Oh x Rp. 91,900 = Rp. 1,240.65
- Mandor 0.0041 Oh x Rp. 95,600 = Rp. 391.96
Jumlah (2) = Rp. 16,523.11
Jumlah (1) +(2) = Rp. 62,775.11

PS 6.32. Memasang 1 m' pipa PVC tipe AW diameter 4"


6.32.1 Bahan
- Pipa PVC 1.200 M x Rp. 49,920 = Rp. 59,904.00
- Perlengkapan 35% harga pipa x Rp. 49,920 = Rp. 17,472.00
Jumlah (1) = Rp. 77,376.00
6.32.2 Tenaga
- Pekerja 0.081 Oh x Rp. 52,500 = Rp. 4,252.50
- Tukang batu 0.135 Oh x Rp. 78,800 = Rp. 10,638.00
- Kepala tukang 0.0135 Oh x Rp. 91,900 = Rp. 1,240.65
- Mandor 0.0041 Oh x Rp. 95,600 = Rp. 391.96
Jumlah (2) = Rp. 16,523.11
Jumlah (1) +(2) = Rp. 93,899.11
PS 6.33. Memasang 1 bh bak cuci piring stainles steel
6.33.1 Bahan
- Bak cuci stainless steel 1.000 Bh x Rp. 466,700 = Rp. 466,700.00
- Water drain asesories 1.000 Set x Rp. 15,000 = Rp. 15,000.00
Jumlah (1) = Rp. 481,700.00
6.33.2 Tenaga
- Pekerja 0.030 Oh x Rp. 52,500 = Rp. 1,575.00
- Tukang batu 0.300 Oh x Rp. 78,800 = Rp. 23,640.00
- Kepala tukang 0.030 Oh x Rp. 91,900 = Rp. 2,757.00
- Mandor 0.0015 Oh x Rp. 95,600 = Rp. 143.40
Jumlah (2) = Rp. 28,115.40
Jumlah (1) +(2) = Rp. 509,815.40

PS 6.34. Memasang 1 bh bak cuci piring teraso

6.34.1 Bahan
- Bak cuci teraso 1.000 Bh x Rp. 272,250 = Rp. 272,250.00
- Water drain + asesories 1.000 Bh x Rp. 15,000 = Rp. 15,000.00
- Semen portland 20.000 Kg x Rp. 1,270 = Rp. 25,400.00
- Pasir 0.050 M x Rp. 76,500 = Rp. 3,825.00
Jumlah (1) = Rp. 316,475.00
6.34.2 Tenaga
- Pekerja 0.050 Oh x Rp. 52,500 = Rp. 2,625.00
- Tukang batu 0.500 Oh x Rp. 78,800 = Rp. 39,400.00
- Kepala tukang 0.050 Oh x Rp. 91,900 = Rp. 4,595.00
- Mandor 0.0025 Oh x Rp. 95,600 = Rp. 239.00
Jumlah (2) = Rp. 46,859.00
Jumlah (1) +(2) = Rp. 363,334.00
PS 6.35. Memasang 1 bh kran diameter " atau "

6.35.1 Bahan
- Kran air 1.000 Bh x Rp. 27,350 = Rp. 27,350.00
- Seal tape 0.025 Bh x Rp. 92,570 = Rp. 2,314.25
Jumlah (1) = Rp. 29,664.25

6.35.2 Tenaga
- Pekerja 0.010 Oh x Rp. 52,500 = Rp. 525.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.005 Oh x Rp. 95,600 = Rp. 478.00
Jumlah (2) 9,802.00
Jumlah (1) +(2) 39,466.25

PS 6.36. Memasang 1 bh Floor drain

6.36.1 Bahan
- Floor drain 1.000 Bh x Rp. 15,000 = Rp. 15,000.00
Jumlah (1) = Rp. 15,000.00

6.36.2 Tenaga
- Pekerja 0.010 Oh x Rp. 52,500 = Rp. 525.00
- Tukang batu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.005 Oh x Rp. 95,600 = Rp. 478.00
Jumlah (2) 9,802.00
Jumlah (1) +(2) 24,802.00
ANALISA BIAYA KONSTRUKSI
PEKERJAAN BESI DAN ALUMINIUM

PBA 6.1 1 Kg Pasang rangka atap baja

6.1.1 Bahan
- Besi profil WF 1.100 Kg x Rp. 15,950 = Rp. 17,545.00
- Meni besi 0.080 Kg x Rp. 25,410 = Rp. 2,032.80
Jumlah (1) = Rp. 19,577.80
6.1.2. Tenaga
- Tukang besi 0.006 Oh x Rp. 78,800 = Rp. 472.80
- Pekerja 0.060 Oh x Rp. 52,500 = Rp. 3,150.00
- Kepala tukang 0.006 Oh x Rp. 91,900 = Rp. 551.40
- Mandor 0.0003 Oh x Rp. 95,600 = Rp. 28.68
Jumlah (2) = Rp. 4,202.88
Jumlah (1) +(2) = Rp. 23,780.68

PBA 6.2 1 M Pasang pintu besi baja

6.2.1 Bahan
- Pintu besi baja 1.000 M x Rp. 816,750 = Rp. 816,750.00
Jumlah (1) = Rp. 816,750.00
6.2.2. Tenaga
- Tukang besi konstruksi 0.650 Oh x Rp. 78,800 = Rp. 51,220.00
- Pekerja 0.650 Oh x Rp. 52,500 = Rp. 34,125.00
- Kepala tukang 0.065 Oh x Rp. 91,900 = Rp. 5,973.50
- Mandor 0.032 Oh x Rp. 95,600 = Rp. 3,059.20
Jumlah (2) = Rp. 94,377.70
Jumlah (1) +(2) = Rp. 911,127.70

PBA 6.3 1 M Pasang jendela besi


6.3.1 Bahan
- Jendela besi 1.000 M x Rp. 347,270 = Rp. 347,270.00
Jumlah (1) = Rp. 347,270.00
6.3.2. Tenaga
- Tukang besi konstruksi 1.050 Oh x Rp. 78,800 = Rp. 82,740.00
- Pekerja 1.050 Oh x Rp. 52,500 = Rp. 55,125.00
- Kepala tukang 0.105 Oh x Rp. 91,900 = Rp. 9,649.50
- Mandor 0.00525 Oh x Rp. 95,600 = Rp. 501.90
Jumlah (2) = Rp. 148,016.40
Jumlah (1) +(2) = Rp. 495,286.40

PBA 6.5 1 M Pasang pintu gulung besi


6.5.1 Bahan
- Pintu gulung besi 1.000 M x Rp. 828,850 = Rp. 828,850.00
Jumlah (1) = Rp. 828,850.00
6.5.2. Tenaga
- Tukang besi konstruksi 1.200 Oh x Rp. 78,800 = Rp. 94,560.00
- Pekerja 1.200 Oh x Rp. 52,500 = Rp. 63,000.00
- Kepala tukang 0.120 Oh x Rp. 91,900 = Rp. 11,028.00
- Mandor 0.006 Oh x Rp. 95,600 = Rp. 573.60
Jumlah (2) = Rp. 169,161.60
Jumlah (1) +(2) = Rp. 998,011.60

PBA 6.6 1 M Pasang pintu lipat

6.6.1 Bahan
- Pintu lipat 1.000 M x Rp. 837,320 = Rp. 837,320.00
Jumlah (1) = Rp. 837,320.00
6.6.2. Tenaga
- Tukang besi konstruksi 1.050 Oh x Rp. 78,800 = Rp. 82,740.00
- Pekerja 1.050 Oh x Rp. 52,500 = Rp. 55,125.00
- Kepala tukang 0.105 Oh x Rp. 91,900 = Rp. 9,649.50
- Mandor 0.0052 Oh x Rp. 95,600 = Rp. 497.12
Jumlah (2) = Rp. 148,011.62
Jumlah (1) +(2) = Rp. 985,331.62
PBA 6.7 1 M Pasang pintu Sunscreen alluminium

6.7.1 Bahan
- Sunscreen alluminium 1.000 M x Rp. 287,380 = Rp. 287,380.00
Jumlah (1) = Rp. 287,380.00
6.7.2. Tenaga
- Tukang besi konstruksi 0.800 Oh x Rp. 78,800 = Rp. 63,040.00
- Pekerja 0.080 Oh x Rp. 52,500 = Rp. 4,200.00
- Kepala tukang 0.080 Oh x Rp. 91,900 = Rp. 7,352.00
- Mandor 0.004 Oh x Rp. 95,600 = Rp. 382.40
Jumlah (2) = Rp. 74,974.40
Jumlah (1) +(2) = Rp. 362,354.40

PBA 6.8 1 M Pasang Rolling door

6.8.1 Bahan
- Roll door 1.000 M x Rp. 465,850 = Rp. 465,850.00
Jumlah (1) = Rp. 465,850.00
6.8.2. Tenaga
- Tukang besi konstruksi 1.500 Oh x Rp. 78,800 = Rp. 118,200.00
- Pekerja 1.050 Oh x Rp. 52,500 = Rp. 55,125.00
- Kepala tukang 0.105 Oh x Rp. 91,900 = Rp. 9,649.50
- Mandor 0.0052 Oh x Rp. 95,600 = Rp. 497.12
Jumlah (2) = Rp. 183,471.62
Jumlah (1) +(2) = Rp. 649,321.62

PBA 6.9 1 M Pasang pintu alluminium

6.9.1 Bahan
- Pintu alluminium 1.000 M x Rp. 405,350 = Rp. 405,350.00
Jumlah (1) = Rp. 405,350.00

6.9.2. Tenaga
- Tukang besi konstruksi 1.050 Oh x Rp. 78,800 = Rp. 82,740.00
- Pekerja 1.050 Oh x Rp. 52,500 = Rp. 55,125.00
- Kepala tukang 0.105 Oh x Rp. 91,900 = Rp. 9,649.50
- Mandor 0.0052 Oh x Rp. 95,600 = Rp. 497.12
Jumlah (2) = Rp. 148,011.62
Jumlah (1) +(2) = Rp. 553,361.62

PBA 6.10 1 M Pasang Venetions blinds

6.10.1 Bahan
- Venetions blinds 1.000 M x Rp. 163,350 = Rp. 163,350.00
Jumlah (1) = Rp. 163,350.00

6.10.2. Tenaga
- Tukang kayu 0.350 Oh x Rp. 61,775 = Rp. 21,621.25
- Pekerja 0.350 Oh x Rp. 52,500 = Rp. 18,375.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.00175 Oh x Rp. 95,600 = Rp. 167.30
Jumlah (2) = Rp. 43,380.05
Jumlah (1) +(2) = Rp. 206,730.05

PBA 6.11 1 M Pasang Vertikals blinds

6.11.1 Bahan
- Vertikals blinds 1.000 M x Rp. 175,450 = Rp. 175,450.00
Jumlah (1) = Rp. 175,450.00

6.11.2. Tenaga
- Tukang kayu 0.350 Oh x Rp. 61,775 = Rp. 21,621.25
- Pekerja 0.350 Oh x Rp. 52,500 = Rp. 18,375.00
- Kepala tukang 0.035 Oh x Rp. 91,900 = Rp. 3,216.50
- Mandor 0.00175 Oh x Rp. 95,600 = Rp. 167.30
Jumlah (2) = Rp. 43,380.05
Jumlah (1) +(2) = Rp. 218,830.05

PBA 6.12 1 M Pasang terali besi

6.12.1 Bahan
- Besi strip 2 x 3 11.500 M' x Rp. 11,880 = Rp. 136,620.00
Jumlah (1) = Rp. 136,620.00
6.12.2. Tenaga
- Tukang las 1.200 Oh x Rp. 61,775 = Rp. 74,130.00
- Pekerja 1.200 Oh x Rp. 52,500 = Rp. 63,000.00
- Kepala tukang 0.012 Oh x Rp. 91,900 = Rp. 1,102.80
- Mandor 0.0006 Oh x Rp. 95,600 = Rp. 57.36
Jumlah (2) = Rp. 138,290.16
Jumlah (1) +(2) = Rp. 274,910.16

PBA 6.13 1 M Pasang kawat harmonika

6.13.1 Bahan
- Kawat harmonika 1.100 M x Rp. 23,600 = Rp. 25,960.00
- Paku biasa " - 1" 0.020 Kg x Rp. 16,940 = Rp. 338.80
- Kayu meranti 0.0018 M x Rp. 5,225,000 = Rp. 9,405.00
Jumlah (1) = Rp. 35,703.80
6.13.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp. 5,250.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.0005 Oh x Rp. 95,600 = Rp. 47.80
Jumlah (2) = Rp. 14,096.80
Jumlah (1) +(2) = Rp. 49,800.60

PBA 6.14 1 M Pasang kawat nyamuk

6.14.1 Bahan
- Kawat nyamuk 1.100 M x Rp. 11,980 = Rp. 13,178.00
- Paku biasa " - 1" 0.020 Kg x Rp. 16,940 = Rp. 338.80
- Kayu meranti 0.0018 M x Rp. 5,225,000 = Rp. 9,405.00
Jumlah (1) = Rp. 22,921.80
6.14.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp. 5,250.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.0005 Oh x Rp. 95,600 = Rp. 47.80
Jumlah (2) = Rp. 14,096.80
Jumlah (1) +(2) = Rp. 37,018.60

PBA 6.15 1 M Pasang kawat kassa

6.15.1 Bahan
- Kawat kassa 1.100 M x Rp. 13,920 = Rp. 15,312.00
- Paku biasa " - 1" 0.020 Kg x Rp. 16,940 = Rp. 338.80
- Kayu meranti 0.0018 M x Rp. 5,225,000 = Rp. 9,405.00
Jumlah (1) = Rp. 25,055.80

6.15.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp. 5,250.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.0005 Oh x Rp. 95,600 = Rp. 47.80
Jumlah (2) = Rp. 14,096.80
Jumlah (1) +(2) = Rp. 39,152.60

PBA 6.16 1 M Pasang kawat burung

6.15.1 Bahan
- Kawat burung 1.100 M x Rp. 12,710 = Rp. 13,981.00
- Paku biasa " - 1" 0.020 Kg x Rp. 16,940 = Rp. 338.80
- Kayu meranti 0.0018 M x Rp. 5,225,000 = Rp. 9,405.00
Jumlah (1) = Rp. 23,724.80

6.15.2. Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp. 5,250.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.0005 Oh x Rp. 95,600 = Rp. 47.80
Jumlah (2) = Rp. 14,096.80
Jumlah (1) +(2) = Rp. 37,821.60
PBA 6.17 1 M Pasang jendela nako dan tralis

6.17.1 Bahan
- Jendela nako 1.100 M x Rp. 201,660 = Rp. 221,826.00
- Paku biasa " - 1" atau skrup 0.020 Kg x Rp. 16,940 = Rp. 338.80
- Besi strip # 12 mm 1.500 M x Rp. 11,880 = Rp. 17,820.00
Jumlah (1) = Rp. 239,984.80

6.17.2. Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang kayu 0.200 Oh x Rp. 78,800 = Rp. 15,760.00
- Kepala tukang 0.020 Oh x Rp. 91,900 = Rp. 1,838.00
- Mandor 0.001 Oh x Rp. 95,600 = Rp. 95.60
Jumlah (2) = Rp. 28,193.60
Jumlah (1) +(2) = Rp. 268,178.40
PBA 6.18 1 M' Pasang talang datar, seng bjls 35

6.18.1 Bahan
- Seng plat 3' x 6' bjls 35 0.500 Lbr x Rp. 115,500 = Rp. 57,750.00
- Paku biasa " - 1" atau skrup 0.015 Kg x Rp. 16,940 = Rp. 254.10
- Kayu meranti 0.0096 M x Rp. 5,225,000 = Rp. 50,160.00
- Flincote / meni besi 0.250 Kg x Rp. 25,410 = Rp. 6,352.50
Jumlah (1) = Rp. 114,516.60
6.18.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang kayu 0.400 Oh x Rp. 78,800 = Rp. 31,520.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.00125 Oh x Rp. 95,600 = Rp. 119.50
Jumlah (2) = Rp. 41,812.00
Jumlah (1) +(2) = Rp. 156,328.60
PBA 6.19 1 M' Pasang talang miring, seng bjls 35

6.19.1 Bahan
- Seng plat 3' x 6' bjls 35 0.500 Lbr x Rp. 115,500 = Rp. 57,750.00
- Paku biasa " - 1" atau skrup 0.015 Kg x Rp. 16,940 = Rp. 254.10
- Kayu meranti 0.019 M x Rp. 5,225,000 = Rp. 99,275.00
- Flincote / meni besi 0.300 Kg x Rp. 25,410 = Rp. 7,623.00
Jumlah (1) = Rp. 164,902.10
6.19.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang kayu 0.400 Oh x Rp. 78,800 = Rp. 31,520.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.00125 Oh x Rp. 95,600 = Rp. 119.50
Jumlah (2) = Rp. 41,812.00
Jumlah (1) +(2) = Rp. 206,714.10

PBA 6.20 1 M' Pasang talang lingkaran D-10 cm, seng bjls 35

6.20.1 Bahan
- Seng plat 3' x 6' bjls 35 0.300 Lbr x Rp. 115,500 = Rp. 34,650.00
- Paku biasa " - 1" atau skrup 0.100 Kg x Rp. 16,940 = Rp. 1,694.00
- Kayu meranti 0.019 M x Rp. 5,225,000 = Rp. 99,275.00
- Besi strip 0.500 Kg x Rp. 11,880 = Rp. 5,940.00
Jumlah (1) = Rp. 141,559.00
6.20.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang kayu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.00125 Oh x Rp. 95,600 = Rp. 119.50
Jumlah (2) = Rp. 29,992.00
Jumlah (1) +(2) = Rp. 171,551.00

PBA 6.21 1 M' Pasang talang lingkaran D-10 cm, seng bjls 30

6.21.1 Bahan
- Seng plat 3' x 6' bjls 30 0.300 Lbr x Rp. 103,950 = Rp. 31,185.00
- Paku biasa " - 1" atau skrup 0.100 Kg x Rp. 16,940 = Rp. 1,694.00
- Kayu meranti 0.019 M x Rp. 5,225,000 = Rp. 99,275.00
- Besi strip 0.500 Kg x Rp. 11,880 = Rp. 5,940.00
Jumlah (1) = Rp. 138,094.00
6.21.2. Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang kayu 0.250 Oh x Rp. 78,800 = Rp. 19,700.00
- Kepala tukang 0.025 Oh x Rp. 91,900 = Rp. 2,297.50
- Mandor 0.00125 Oh x Rp. 95,600 = Rp. 119.50
Jumlah (2) = Rp. 29,992.00
Jumlah (1) +(2) = Rp. 168,086.00
ANALISA BIAYA KONSTRUKSI
PEKERJAAN LANGIT - LANGIT

PLL 6.1 1 M langit - langit asbes ( 1,00 x 1,00 ) m tebal 6 mm

6.1.1 Bahan
- Pelat asbes tebal 6 mm 1.100 Lbr x Rp. 17,330 = Rp. 19,063.00
- Paku 0.010 Kg x Rp. 16,940 = Rp. 169.40
Jumlah (1) = Rp. 19,232.40
6.1.2 Tenaga
- Pekerja 0.030 Oh x Rp. 52,500 = Rp. 1,575.00
- Tukang kayu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.0015 Oh x Rp. 95,600 = Rp. 143.40
Jumlah (2) = Rp. 7,877.70
Jumlah (1) +(2) = Rp. 27,110.10

PLL 6.2 1 M langit - langit asbes ( 1,00 x 1,00 ) m tebal 5 mm

6.2.1 Bahan
- Pelat asbes tebal 5 mm 1.100 Lbr x Rp. 14,440 = Rp. 15,884.00
- Paku 0.010 Kg x Rp. 16,940 = Rp. 169.40
Jumlah (1) = Rp. 16,053.40
6.2.2 Tenaga
- Pekerja 0.030 Oh x Rp. 52,500 = Rp. 1,575.00
- Tukang kayu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.0015 Oh x Rp. 95,600 = Rp. 143.40
Jumlah (2) = Rp. 7,877.70
Jumlah (1) +(2) = Rp. 23,931.10

PLL 6.3 1 M langit - langit asbes ( 1,00 x 1,00 ) m tebal 4 mm

6.3.1 Bahan
- Pelat asbes tebal 4 mm 1.100 Lbr x Rp. 11,550 = Rp. 12,705.00
- Paku 0.010 Kg x Rp. 16,940 = Rp. 169.40
Jumlah (1) = Rp. 12,874.40
6.3.2 Tenaga
- Pekerja 0.030 Oh x Rp. 52,500 = Rp. 1,575.00
- Tukang kayu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.0015 Oh x Rp. 95,600 = Rp. 143.40
Jumlah (2) = Rp. 7,877.70
Jumlah (1) +(2) = Rp. 20,752.10

PLL 6.4 1 M langit - langit asbes ( 1,00 x 1,00 ) m tebal 3,5 mm


6.4.1 Bahan
- Pelat asbes tebal 3,5 mm 1.100 Lbr x Rp. 9,350 = Rp. 10,285.00
- Paku 0.010 Kg x Rp. 16,940 = Rp. 169.40
Jumlah (1) = Rp. 10,454.40

6.4.2 Tenaga
- Pekerja 0.030 Oh x Rp. 52,500 = Rp. 1,575.00
- Tukang kayu 0.070 Oh x Rp. 78,800 = Rp. 5,516.00
- Kepala tukang 0.007 Oh x Rp. 91,900 = Rp. 643.30
- Mandor 0.0015 Oh x Rp. 95,600 = Rp. 143.40
Jumlah (2) = Rp. 7,877.70
Jumlah (1) +(2) = Rp. 18,332.10
PLL 6.5 1 M Langit - langit akustik ( 30 x 30 ) cm

6.5.1 Bahan
- Akustik ukuran 30 x 30 cm 11.500 Lbr x Rp. 8,540 = Rp. 98,210.00
- Paku 0.050 Kg x Rp. 16,940 = Rp. 847.00
Jumlah (1) = Rp. 99,057.00
6.5.2 Tenaga
- Pekerja 0.060 Oh x Rp. 52,500 = Rp. 3,150.00
- Tukang kayu 0.120 Oh x Rp. 78,800 = Rp. 9,456.00
- Kepala tukang 0.012 Oh x Rp. 91,900 = Rp. 1,102.80
- Mandor 0.003 Oh x Rp. 95,600 = Rp. 286.80
Jumlah (2) = Rp. 13,995.60
Jumlah (1) +(2) = Rp. 113,052.60

PLL 6.6 1 M Langit - langit akustik ( 30 x 60 ) cm

6.6.1 Bahan
- Akustik ukuran 30 x 60 cm 5.800 Lbr x Rp. 17,070 = Rp. 99,006.00
- Paku 0.050 Kg x Rp. 16,940 = Rp. 847.00
Jumlah (1) = Rp. 99,853.00
6.6.2 Tenaga
- Pekerja 0.060 Oh x Rp. 52,500 = Rp. 3,150.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.003 Oh x Rp. 95,600 = Rp. 286.80
Jumlah (2) = Rp. 12,235.80
Jumlah (1) +(2) = Rp. 112,088.80

PLL 6.7 1 M Langit - langit akustik ( 60 x 120 ) cm

6.7.1 Bahan
- Akustik arm strong ukuran 60 x 120 cm 1.500 Lbr x Rp. 68,290 = Rp. 102,435.00
- Paku 0.050 Kg x Rp. 16,940 = Rp. 847.00
Jumlah (1) = Rp. 103,282.00
6.7.2 Tenaga
- Pekerja 0.060 Oh x Rp. 52,500 = Rp. 3,150.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.003 Oh x Rp. 95,600 = Rp. 286.80
Jumlah (2) = Rp. 12,235.80
Jumlah (1) +(2) = Rp. 115,517.80

PLL 6.8 1 M Langit - langit plywood ( 30 x 60 ) cm, tebal 4 mm

6.8.1 Bahan
- Plywood 4' x 8' x 4 mm 0.360 Lbr x Rp. 51,920 = Rp. 18,691.20
- Paku 0.030 Kg x Rp. 16,940 = Rp. 508.20
Jumlah (1) = Rp. 19,199.40
6.8.2 Tenaga
- Pekerja 0.070 Oh x Rp. 52,500 = Rp. 3,675.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.0035 Oh x Rp. 95,600 = Rp. 334.60
Jumlah (2) = Rp. 12,808.60
Jumlah (1) +(2) = Rp. 32,008.00

PLL 6.9 1 M Langit - langit plywood ( 30 x 60 ) cm, tebal 6 mm


6.9.1 Bahan
- Plywood 4' x 8' x 6 mm 0.360 Lbr x Rp. 77,880 = Rp. 28,036.80
- Paku 0.030 Kg x Rp. 16,940 = Rp. 508.20
Jumlah (1) = Rp. 28,545.00
6.9.2 Tenaga
- Pekerja 0.070 Oh x Rp. 52,500 = Rp. 3,675.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.0035 Oh x Rp. 95,600 = Rp. 334.60
Jumlah (2) = Rp. 12,808.60
Jumlah (1) +(2) = Rp. 41,353.60
PLL 6.10 1 M Langit - langit plywood ( 60 x 120 ) cm, tebal 4 mm

6.10.1 Bahan
- Plywood 4' x 8' x 4 mm 0.375 Lbr x Rp. 51,920 = Rp. 19,470.00
- Paku 0.030 Kg x Rp. 16,940 = Rp. 508.20
Jumlah (1) = Rp. 19,978.20
6.10.2 Tenaga
- Pekerja 0.070 Oh x Rp. 52,500 = Rp. 3,675.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.0035 Oh x Rp. 95,600 = Rp. 334.60
Jumlah (2) = Rp. 12,808.60
Jumlah (1) +(2) = Rp. 32,786.80

PLL 6.11 1 M Langit - langit plywood ( 60 x 120 ) cm, tebal 6 mm


6.11.1 Bahan
- Plywood 4' x 8' x 6 mm 0.375 Lbr x Rp. 77,880 = Rp. 29,205.00
- Paku 0.030 Kg x Rp. 16,940 = Rp. 508.20
Jumlah (1) = Rp. 29,713.20
6.11.2 Tenaga
- Pekerja 0.070 Oh x Rp. 52,500 = Rp. 3,675.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.0035 Oh x Rp. 95,600 = Rp. 334.60
Jumlah (2) = Rp. 12,808.60
Jumlah (1) +(2) = Rp. 42,521.80

PLL 6.12 1 M Langit - langit teakwood ( 30 x 60 ) cm, tebal 4 mm

6.12.1 Bahan
- Teakwood 4' x 8' x 4 mm 0.360 Lbr x Rp. 54,450 = Rp. 19,602.00
- Paku 0.030 Kg x Rp. 16,940 = Rp. 508.20
Jumlah (1) = Rp. 20,110.20
6.12.2 Tenaga
- Pekerja 0.070 Oh x Rp. 52,500 = Rp. 3,675.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.0035 Oh x Rp. 95,600 = Rp. 334.60
Jumlah (2) = Rp. 12,808.60
Jumlah (1) +(2) = Rp. 32,918.80

PLL 6.13 1 M Langit - langit teakwood ( 60 x 120 ) cm, tebal 4 mm

6.13.1 Bahan
- Teakwood 4' x 8' x 4 mm 0.375 Lbr x Rp. 54,450 = Rp. 20,418.75
- Paku 0.030 Kg x Rp. 16,940 = Rp. 508.20
Jumlah (1) = Rp. 20,926.95
6.13.2 Tenaga
- Pekerja 0.070 Oh x Rp. 52,500 = Rp. 3,675.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.0035 Oh x Rp. 95,600 = Rp. 334.60
Jumlah (2) = Rp. 12,808.60
Jumlah (1) +(2) = Rp. 33,735.55

PLL 6.14 1 M Langit - langit lat kayu jati


6.14.1 Bahan
- Kayu jati, papan 0.024 M x Rp. 24,104,440 = Rp. 578,506.56
- Paku 0.010 Kg x Rp. 16,940 = Rp. 169.40
- Paku sekrup 0.050 Kg x Rp. 21,180 = Rp. 1,059.00
Jumlah (1) = Rp. 579,734.96
6.14.2 Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang kayu 0.600 Oh x Rp. 78,800 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900 = Rp. 5,514.00
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 64,250.00
Jumlah (1) +(2) = Rp. 643,984.96

PLL 6.16 1 M Langit - langit lat papan rider


6.16.1 Bahan
- Papan rider 1.000 Lbr x Rp. 225,000 = Rp. 225,000.00
- Paku 0.010 Kg x Rp. 16,940 = Rp. 169.40
- Paku sekrup 0.050 Kg x Rp. 21,180 = Rp. 1,059.00
Jumlah (1) = Rp. 226,228.40
6.16.2 Tenaga
- Pekerja 0.200 Oh x Rp. 52,500 = Rp. 10,500.00
- Tukang kayu 0.600 Oh x Rp. 78,800 = Rp. 47,280.00
- Kepala tukang 0.060 Oh x Rp. 91,900 = Rp. 5,514.00
- Mandor 0.010 Oh x Rp. 95,600 = Rp. 956.00
Jumlah (2) = Rp. 64,250.00
Jumlah (1) +(2) = Rp. 290,478.40

PLL 6.17 1 M Langit - langit soft board


6.17.1 Bahan
- Soft board 4' x 8' x 4 mm 0.350 Lbr x Rp. 55,990 = Rp. 19,596.50
- Paku biasa 0.030 Kg x Rp. 16,940 = Rp. 508.20
Jumlah (1) = Rp. 20,104.70
6.17.2 Tenaga
- Pekerja 0.600 Oh x Rp. 52,500 = Rp. 31,500.00
- Tukang kayu 0.100 Oh x Rp. 78,800 = Rp. 7,880.00
- Kepala tukang 0.010 Oh x Rp. 91,900 = Rp. 919.00
- Mandor 0.003 Oh x Rp. 95,600 = Rp. 286.80
Jumlah (2) = Rp. 40,585.80
Jumlah (1) +(2) = Rp. 60,690.50

PLL 6.18 1 M Langit - langit akustik 60 x 120 cm + rangka alluminium

6.18.1 Bahan
- Profil alluminium "T" 3.600 M' x Rp. 8,470 = Rp. 30,492.00
- Kawat seng polos 0.150 Kg x Rp. 22,530 = Rp. 3,379.50
- Ramset/dina bolt 1.000 Bh x Rp. 720 = Rp. 720.00
- Akustik arm strong 60 x 120 cm 1.500 Lbr x Rp. 68,290 = Rp. 102,435.00
Jumlah (1) = Rp. 137,026.50
6.18.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang kayu 0.500 Oh x Rp. 78,800 = Rp. 39,400.00
- Kepala tukang 0.050 Oh x Rp. 91,900 = Rp. 4,595.00
- Mandor 0.0075 Oh x Rp. 95,600 = Rp. 717.00
Jumlah (2) = Rp. 52,587.00
Jumlah (1) +(2) = Rp. 189,613.50

PLL 6.19 1 M' List Langit - langit Kayu profil 3"


6.19.1 Bahan
- List kayu profil 1.100 M' x Rp. 18,810 = Rp. 20,691.00
- Paku 0.010 Kg x Rp. 16,940 = Rp. 169.40
Jumlah (1) = Rp. 20,860.40
6.19.2 Tenaga
- Pekerja 0.050 Oh x Rp. 52,500 = Rp. 2,625.00
- Tukang kayu 0.050 Oh x Rp. 78,800 = Rp. 3,940.00
- Kepala tukang 0.005 Oh x Rp. 91,900 = Rp. 459.50
- Mandor 0.003 Oh x Rp. 95,600 = Rp. 286.80
Jumlah (2) = Rp. 7,311.30
Jumlah (1) +(2) = Rp. 28,171.70
PLL 6.20 1 M Langit - langit asbes (1,00 x 1,00) m, rangka kayu meranti

6.20.1 Bahan
- Kayu meranti 0.012 M x Rp. 5,225,000 = Rp. 62,700.00
- Paku 0.060 Kg x Rp. 16,940 = Rp. 1,016.40
- Asbes 1,00 x 1,00 m 1.100 Lbr x Rp. 11,550 = Rp. 12,705.00
Jumlah (1) = Rp. 76,421.40
6.20.2 Tenaga
- Pekerja 0.180 Oh x Rp. 52,500 = Rp. 9,450.00
- Tukang kayu 0.320 Oh x Rp. 78,800 = Rp. 25,216.00
- Kepala tukang 0.032 Oh x Rp. 91,900 = Rp. 2,940.80
- Mandor 0.009 Oh x Rp. 95,600 = Rp. 860.40
Jumlah (2) = Rp. 38,467.20
Jumlah (1) +(2) = Rp. 114,888.60

PLL 6.21 1 M Langit - langit plywood 4 mm + rangka kayu meranti

6.21.1 Bahan
- Kayu meranti 0.013 M x Rp. 5,225,000 = Rp. 67,925.00
- Paku biasa 2" - 5" 0.060 Kg x Rp. 16,940 = Rp. 1,016.40
- Plywood 4' x 8' x 4 mm 0.390 Lbr x Rp. 51,920 = Rp. 20,248.80
Jumlah (1) = Rp. 89,190.20
6.21.2 Tenaga
- Pekerja 0.270 Oh x Rp. 52,500 = Rp. 14,175.00
- Tukang kayu 0.400 Oh x Rp. 78,800 = Rp. 31,520.00
- Kepala tukang 0.040 Oh x Rp. 91,900 = Rp. 3,676.00
- Mandor 0.0135 Oh x Rp. 95,600 = Rp. 1,290.60
Jumlah (2) = Rp. 50,661.60
Jumlah (1) +(2) = Rp. 139,851.80

PLL 6.22 1 M Langit - langit akustik ( 30 x 60 ) cm + rangka kayu meranti

6.22.1 Bahan
- Kayu meranti 0.013 M x Rp. 5,225,000 = Rp. 67,925.00
- Paku 0.060 Kg x Rp. 16,940 = Rp. 1,016.40
- Akustik 30 x 60 cm 5.800 Lbr x Rp. 17,070 = Rp. 99,006.00
Jumlah (1) = Rp. 167,947.40
6.22.2 Tenaga
- Pekerja 0.260 Oh x Rp. 52,500 = Rp. 13,650.00
- Tukang kayu 0.400 Oh x Rp. 78,800 = Rp. 31,520.00
- Kepala tukang 0.040 Oh x Rp. 91,900 = Rp. 3,676.00
- Mandor 0.013 Oh x Rp. 95,600 = Rp. 1,242.80
Jumlah (2) = Rp. 50,088.80
Jumlah (1) +(2) = Rp. 218,036.20

PLL 6.23 1 M Langit - langit akustik ( 30 x 30 ) cm + rangka kayu borneo

6.23.1 Bahan
- Kayu meranti 0.013 M x Rp. 5,225,000 = Rp. 67,925.00
- Paku 0.060 Kg x Rp. 16,940 = Rp. 1,016.40
- Akustik 30 x 30 cm 11.500 Lbr x Rp. 8,540 = Rp. 98,210.00
Jumlah (1) = Rp. 167,151.40
6.23.2 Tenaga
- Pekerja 0.310 Oh x Rp. 52,500 = Rp. 16,275.00
- Tukang kayu 0.470 Oh x Rp. 78,800 = Rp. 37,036.00
- Kepala tukang 0.047 Oh x Rp. 91,900 = Rp. 4,319.30
- Mandor 0.0155 Oh x Rp. 95,600 = Rp. 1,481.80
Jumlah (2) = Rp. 59,112.10
Jumlah (1) +(2) = Rp. 226,263.50
PLL 6.24 1 M Langit - langit gypsum board, tebal 9 mm

6.24.1 Bahan
- Gypsum board (120 x 240 x 9) mm 0.364 Lbr x Rp. 71,500 = Rp. 26,026.00
- Paku sekrup 0.110 Kg x Rp. 21,180 = Rp. 2,329.80
Jumlah (1) = Rp. 28,355.80

6.24.2 Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp. 5,250.00
- Tukang kayu 0.050 Oh x Rp. 78,800 = Rp. 3,940.00
- Kepala tukang 0.005 Oh x Rp. 91,900 = Rp. 459.50
- Mandor 0.005 Oh x Rp. 95,600 = Rp. 478.00
Jumlah (2) = Rp. 10,127.50
Jumlah (1) +(2) = Rp. 38,483.30

PLL 6.24A 1 M Langit - langit gypsum board, tebal 6 mm

6.24.1 Bahan
- Gypsum board (120 x 240 x 6) mm 0.364 Lbr x Rp. 59,950 = Rp. 21,821.80
- Paku sekrup 0.110 Kg x Rp. 21,180 = Rp. 2,329.80
Jumlah (1) = Rp. 24,151.60

6.24.2 Tenaga
- Pekerja 0.100 Oh x Rp. 52,500 = Rp. 5,250.00
- Tukang kayu 0.050 Oh x Rp. 78,800 = Rp. 3,940.00
- Kepala tukang 0.005 Oh x Rp. 91,900 = Rp. 459.50
- Mandor 0.005 Oh x Rp. 95,600 = Rp. 478.00
Jumlah (2) = Rp. 10,127.50
Jumlah (1) +(2) = Rp. 34,279.10

PLL 6.24B 1 M Langit - langit gypsum board, tebal 12 mm

6.24.1 Bahan
- Gypsum board (120 x 240 x 12) mm 0.364 Lbr x Rp. 93,500 = Rp. 34,034.00
- Paku sekrup 0.110 Kg x Rp. 21,180 = Rp. 2,329.80
Jumlah (1) = Rp. 36,363.80

6.24.2 Tenaga
- Pekerja 0.150 Oh x Rp. 52,500 = Rp. 7,875.00
- Tukang kayu 0.080 Oh x Rp. 78,800 = Rp. 6,304.00
- Kepala tukang 0.0075 Oh x Rp. 91,900 = Rp. 689.25
- Mandor 0.0075 Oh x Rp. 95,600 = Rp. 717.00
Jumlah (2) = Rp. 15,585.25
Jumlah (1) +(2) = Rp. 51,949.05
DAFTAR HARGA SATUAN UPAH DAN BAHAN
PEKERJAAN PEMBANGUNAN GEDUNG NEGARA
TAHUN ANGGARAN 2010

NO. URAIAN HARGA UPAH HARGA SATUAN

1 2 3 4

1 Pekerja @Rp. 52,500.00 / Org/Hari


2 Mandor @Rp. 95,600.00 / OH
3 Tukang Batu @Rp. 78,800.00 / OH
4 Tukang Kayu @Rp. 78,800.00 / OH
5 Tukang Besi @Rp. 78,800.00 / OH
6 Tukang Keramik @Rp. 78,800.00 / OH
7 Tukang Plafond @Rp. 78,800.00 / OH
8 Tukang Pasang Pipa @Rp. 78,800.00 / OH
9 Tukang Cat @Rp. 78,800.00 / OH
10 Kepala Tukang @Rp. 91,900.00 / OH
11 Jaga Malam @Rp. 42,000.00 / OM

NO. URAIAN HARGA BAHAN HARGA SATUAN

1 2 3 4

A TIMBUNAN / GALIAN
1 Tanah Timbun/Merah @Rp. 62,900.00 / M3
2 Pasir Timbun / Urug @Rp. 64,400.00 / M3
3 Pasir Pasang @Rp. 76,500.00 / M3
4 Pasir beton @Rp. 87,800.00 / M3
5 Sirtu @Rp. 87,800.00 / M3
6 Tanah Humus @Rp. 71,500.00 / M3

B BAHAN PEREKAT
1 Portland Cement (PC) @Rp. 1,270.00 / Kg
2 Cement Putih @Rp. 2,500.00 / Kg
3 Lem Kayu @Rp. 37,400.00 / Kg
4 Lem Vinyl / Karet @Rp. 44,900.00 / Kg
5 Perekat Kaca @Rp. 76,500.00 / Kg
6 Waterfroof @Rp. 52,300.00 / Kg

C BATU / BATU CETAKAN


1 Batu Krikil / Koral 3 - 5 cm @Rp. 185,900.00 / M3
2 Batu Krikil / Koral 5 - 7 cm @Rp. 170,900.00 / M3
3 Batu Krikil / Koral 7 - 10 cm @Rp. 155,900.00 / M3
4 Batu Belah/Kali 10 - 15 cm @Rp. 140,900.00 / M3
5 Batu Belah/Kali 15 - 20 cm @Rp. 125,900.00 / M3
6 Batu Pecah 1 - 2 cm @Rp. 190,200.00 / M3
7 Batu Pecah 2 - 3 cm @Rp. 177,700.00 / M3
8 Batu Pecah 3 - 5 cm @Rp. 165,200.00 / M3
9 Batu Pecah 5 - 7 cm @Rp. 150,200.00 / M3
10 Batu Kacang /jagung 0,5 - 1 cm @Rp. 202,700.00 / M3
11 Batu Splyt @Rp. 212,700.00 / M3
12 Batu Bata biasa 5x10x20 cm @Rp. 610.00 / Bh
13 Batu Bata Mesin 5x10x20 cm @Rp. 720.00 / Bh
14 Batu Bataco 6x12x24 cm @Rp. 4,180.00 / Bh
15 Batu Krawang 10x10x20 cm @Rp. 3,030.00 / Bh
16 Batu Krawang 10x15x15 cm @Rp. 3,470.00 / Bh
17 Batu Krawang 10x20x20 cm @Rp. 3,740.00 / Bh
18 Concrete Block (CB) 10 @Rp. 740.00 / Bh
19 Concrete Block (CB) 15 @Rp. 1,600.00 / Bh
20 Concrete Block (CB) 20 @Rp. 2,920.00 / Bh
21 Bondbeam 40x20x20 cm @Rp. 30,250.00 / Bh
22 Con Block warna type Holland tb 6 cm @Rp. 1,720.00 / Bh
23 Con Block warna type Uni pave tb 6 cm @Rp. 1,600.00 / Bh
24 Con Block warna type Dosex Six tb 6 cm @Rp. 1,840.00 / Bh
25 Con Block warna type Hexagon tb 6 cm @Rp. 1,710.00 / Bh
26 Con Block K 125 @Rp. 1,750.00 / Bh
27 Con Block K 175 @Rp. 2,700.00 / Bh
1 2 3 4

D KAYU / LANGIT - LANGIT


1 Balok Kayu Jati @Rp. 23,925,000.00 / M3
2 Papan Kayu Jati @Rp. 24,104,440.00 / M3
3 Balok Kayu Damar Laut @Rp. 9,350,000.00 / M3
4 Papan Kayu Damar Laut @Rp. 9,650,000.00 / M3
5 Balok Kayu Meranti Batu @Rp. 9,075,000.00 / M3
6 Papan Kayu Meranti Batu @Rp. 9,375,000.00 / M3
7 Balok Kayu Kapur @Rp. 6,490,000.00 / M3
8 Papan kayu Kapur @Rp. 6,790,000.00 / M3
9 Balok Kayu Meranti Kls I @Rp. 5,225,000.00 / M3
10 Papan Kayu Meranti Kls I @Rp. 5,475,000.00 / M3
11 Kayu Sembarang/Bekisting @Rp. 3,107,500.00 / M3
12 Kayu Bakar @Rp. 187,000.00 / M3
13 Papan Lambersering/Rider @Rp. 225,000.00 / M2
14 Kayu Lat Asbes 5x30x400 mm @Rp. 7,430.00 / Btg
15 Kayu Kaso 5 - 7 /400 cm @Rp. 87,780.00 / Btg
16 Kayu Dolken / Kayu Laut 7,5 - 10 / 400 cm @Rp. 19,250.00 / Btg
17 Bambu 6 - 8 /600 cm @Rp. 13,750.00 / Btg
18 Bilik Bambu @Rp. 16,340.00 / M2
19 Kayu Profil 1" @Rp. 6,270.00 / M'
20 Kayu Profil 2" @Rp. 12,540.00 / M'
21 Kayu Profil 3" @Rp. 18,810.00 / M'
22 Kayu Profil 4" @Rp. 25,080.00 / M'
23 Profil Gypsum 2" @Rp. 4,600.00 / M'
24 Profil Gypsum 3" @Rp. 5,450.00 / M'
25 Profil Gypsum 4" @Rp. 6,660.00 / M'
26 Profil Gypsum 6" @Rp. 7,870.00 / M'
27 Plywood 120x240 tbl. 18 mm @Rp. 233,640.00 / Lbr
28 Plywood 120x240 tbl. 12 mm @Rp. 155,760.00 / Lbr
29 Plywood 120x240 tbl. 9 mm @Rp. 116,820.00 / Lbr
30 Plywood 120x240 tbl. 6 mm @Rp. 77,880.00 / Lbr
31 Plywood 120x240 tbl. 4 mm @Rp. 51,920.00 / Lbr
32 Teakwood 120x240 tbl. 3 mm @Rp. 54,450.00 / Lbr
33 Triplek Jati 120x240 tbl. 3 mm @Rp. 85,250.00 / Lbr
34 Triplek Sungkai 120x240 tbl. 3 mm @Rp. 79,750.00 / Lbr
35 Formika 120x240 @Rp. 74,250.00 / Lbr
36 Soft Board 120x240 tbl. 4 mm @Rp. 55,990.00 / Lbr
37 Soft Board 120x240 tbl. 6 mm @Rp. 84,150.00 / Lbr
38 Soft Board 120x240 tbl. 9 mm @Rp. 126,230.00 / Lbr
39 Soft Board 120x240 tbl. 12 mm @Rp. 168,250.00 / Lbr
40 Gypsum 120x240 tbl. 6 mm @Rp. 59,950.00 / Lbr
41 Gypsum 120x240 tbl. 9 mm @Rp. 71,500.00 / Lbr
42 Gypsum 120x240 tbl. 12 mm @Rp. 93,500.00 / Lbr
43 Asbes Lokal 100x100 cm @Rp. 9,350.00 / Lbr
44 Asbes Atrisco 100x100 cm t= 4 mm @Rp. 11,550.00 / Lbr
45 Asbes Atrisco 100x100 cm t= 5 mm @Rp. 14,440.00 / Lbr
46 Asbes Atrisco 100x100 cm t= 6 mm @Rp. 17,330.00 / Lbr
47 Akustik 30x30 cm @Rp. 8,540.00 / Lbr
48 Akustik 30x60 cm @Rp. 17,070.00 / Lbr
49 Akustik 60x120 cm @Rp. 68,290.00 / Lbr
50 Rangka Furing Ceiling Gypsum @Rp. 52,250.00 / M2
51 Rangka Furing Dinding Gypsum @Rp. 63,800.00 / M2
52 Tepung Dempul @Rp. 10,450.00 / Kg
53 Kain kasa/Paper Tape @Rp. 57,750.00 / Roll
1 2 3 4

E BESI / ALUMINIUM
1 Besi Beton polos @Rp. 14,410.00 / Kg
2 Besi Beton Ulir @Rp. 14,580.00 / Kg
3 Besi Profil WF/INP @Rp. 15,950.00 / Kg
4 Besi siku @Rp. 11,990.00 / Kg
5 Besi CNP @Rp. 13,090.00 / Kg
6 Besi Plat Strip @Rp. 11,880.00 / Kg
7 Besi Plat Polos @Rp. 13,630.00 / Kg
8 Kawat Besi Beton @Rp. 16,830.00 / Kg
9 Kawat Licin / Seng Polos @Rp. 22,530.00 / Kg
10 Kawat Duri @Rp. 4,030.00 / M'
11 Kawat Nyamuk @Rp. 11,980.00 / M2
12 Kawat Kasa @Rp. 13,920.00 / M2
13 Kawat Harmonika # 1" @Rp. 23,600.00 / M2
14 Kawat Burung @Rp. 12,710.00 / M2
15 Pagar kawat BRC 120 Polos @Rp. 235,950.00 / Lbr
16 Pintu Besi @Rp. 816,750.00 / M2
17 Pintu gulung Besi @Rp. 828,850.00 / M2
18 Pintu Lipat Besi @Rp. 837,320.00 / M2
19 Pintu Rolling Door @Rp. 465,850.00 / M2
20 Jerajak besi Bermotif @Rp. 347,270.00 / M2
21 Jerajak Besi Strip @Rp. 312,180.00 / M2
22 Rangka Baja Ringan @Rp. 177,870.00 / M2
23 Kosen Pintu Aluminium (80 x 210) Coklat @Rp. 405,350.00 / Bh
24 Kosen Pintu Aluminium (80 x 210) Putih @Rp. 371,470.00 / Bh
25 Kosen Jendela aluminium (120x60) Coklat @Rp. 287,380.00 / Bh
26 Kosen Jendela aluminium (120x60) Putih @Rp. 248,050.00 / Bh
27 Pintu Aluminium ( 80 x 210) Coklat @Rp. 711,480.00 / Bh
28 Pintu Aluminium ( 80 x 210) Putih @Rp. 609,840.00 / Bh
29 Jendela Aluminium + Kaca 5 mm (120 x 60) Coklat @Rp. 304,920.00 / Bh
30 Jendela Aluminium + Kaca 5 mm (120 x 60) Putih @Rp. 261,360.00 / Bh
31 Kosen Pintu / Jendela Aluminium Coklat @Rp. 78,650.00 / M'
32 Kosen Pintu / Jendela Aluminium Putih @Rp. 66,550.00 / M'
33 Daun Jendela Aluminium Coklat @Rp. 54,450.00 / M'
34 Daun Jendela Aluminium Putih @Rp. 48,400.00 / M'
35 Profil Aluminium T @Rp. 8,470.00 / M'
36 Ventions Blinds @Rp. 163,350.00 / M2
37 Verticals Blinds @Rp. 175,450.00 / M2
38 Bingkai Naco Niki Hitam @Rp. 201,660.00 / M2
39 Bingkai Naco Niki Putih @Rp. 168,060.00 / M2
40 Paku Beton 0,5 - 2" @Rp. 310.00 / Bh
41 Paku Beton 2" - 5" @Rp. 530.00 / Bh
42 Paku Biasa 0,5 - 2" @Rp. 16,940.00 / Kg
43 Paku Biasa 2" - 5" @Rp. 14,520.00 / Kg
44 Sekrup macam ukuran @Rp. 21,180.00 / Kg
45 Sekrup 0,5 - 2" @Rp. 420.00 / Bh
46 Sekrup fisher @Rp. 360.00 / Bh
47 Baut 5/8" - 8" @Rp. 19,970.00 / Bh
48 Baut Angker 3/4" - 10" @Rp. 45,380.00 / Bh
49 Baut Ramset / Dina Bolt @Rp. 720.00 / Bh
50 Rangka Atap Twin light @Rp. 302,500.00 / M2
1 2 3 4

F PENUTUP LANTAI DAN DINDING


1 Ubin Granito 30 x 30 cm @Rp. 26,260.00 / Bh
2 Ubin Granito 40 x 40 cm @Rp. 46,590.00 / Bh
3 Ubin Granito 60 x 60 cm @Rp. 104,670.00 / Bh
4 Ubin Mosaik 30 x 30 cm @Rp. 13,920.00 / Bh
5 Ubin Marmer Ex. DN @Rp. 261,970.00 / M2
6 Ubin teralux marmer 30 x 30 cm @Rp. 27,230.00 / Bh
7 Ubin teralux marmer 40 x 40 cm @Rp. 48,400.00 / Bh
8 Ubin teralux marmer 60 x 60 cm @Rp. 109,510.00 / Bh
9 Ubin keramik 10 x 20 cm @Rp. 1,210.00 / Bh
10 Ubin keramik 15 x 15 cm @Rp. 1,400.00 / Bh
11 Ubin keramik 20 x 20 cm @Rp. 2,490.00 / Bh
12 Ubin keramik 20 x 25 cm @Rp. 3,150.00 / Bh
13 Ubin keramik 25 x 25 cm @Rp. 3,870.00 / Bh
14 Ubin keramik 30 x 30 cm @Rp. 5,570.00 / Bh
15 Ubin keramik 30 x 30 cm anti slip @Rp. 6,290.00 / Bh
16 Ubin keramik 40 x 40 cm @Rp. 9,680.00 / Bh
17 Ubin keramik artistik 5 x 20 cm @Rp. 910.00 / Bh
18 Ubin keramik artistik 10 x 10 cm @Rp. 910.00 / Bh
19 Ubin keramik artistik 10 x 20 cm @Rp. 1,760.00 / Bh
20 Ubin keramik Essenza 30 x 30 cm @Rp. 21,180.00 / Bh
21 Ubin keramik Essenza 40 x 40 cm @Rp. 37,630.00 / Bh
22 Porselin 11 x 11 cm Putih @Rp. 1,210.00 / Bh
23 Porselin 11 x 11 cm, warna @Rp. 145.00 / Bh
24 Porselin 15 x 15 cm, putih @Rp. 2,300.00 / Bh
25 Porselin 15 x 15 cm, warna @Rp. 2,540.00 / Bh
26 Plint ubin teralux marmer 10 x 30 cm @Rp. 16,340.00 / Bh
27 Plint ubin teralux marmer 10 x 40 cm @Rp. 29,040.00 / Bh
28 Plint ubin teralux marmer 10 x 60 cm @Rp. 65,700.00 / Bh
29 Plint ubin granito 10 x 30 cm @Rp. 27,950.00 / Bh
30 Plint ubin granito 10 x 40 cm @Rp. 62,800.00 / Bh
31 Plint ubin granito 10 x 60 cm @Rp. 157,180.00 / Bh
32 Plint ubin keramik 10 x 30 cm @Rp. 4,110.00 / Bh
33 Plint ubin keramik 10 x 40 cm @Rp. 5,690.00 / Bh
34 Plint ubin keramik 10 x 60 cm @Rp. 8,110.00 / Bh
35 Plint ubin keramik 15 x 30 cm @Rp. 5,810.00 / Bh
36 Plint ubin keramik 15 x 40 cm @Rp. 7,740.00 / Bh
37 Plint ubin keramik 15 x 60 cm @Rp. 11,620.00 / Bh
38 Batu Lapis Dinding 7x3x24 @Rp. 2,040.00 / Bh
39 Batu Tempel Hitam @Rp. 104,500.00 / M2
40 Batu Poros @Rp. 114,680.00 / M2
41 Carpet @Rp. 90,750.00 / M2
42 Carpet 80 % wool, 20 % nylon @Rp. 87,450.00 / M2
43 Feltex carpet 100 % wool-T-21 @Rp. 85,250.00 / M2
44 Underlyer tebal 6 mm / rubber corrugated @Rp. 104,500.00 / M2
45 Vynil asbes 30 x 30 cm @Rp. 8,230.00 / Bh
46 Vynil karet 30 x 30 cm KL I @Rp. 9,800.00 / Bh
47 Vynil karet 30 x 30 cm KL II @Rp. 9,080.00 / Bh
48 Vynil motif kembang ex DN 30 x 30 cm @Rp. 9,440.00 / Bh
49 Vynil wall covering lebar 50 cm @Rp. 63,250.00 / M2
50 Perquet Jati @Rp. 368,500.00 / M2
51 Gymfloor @Rp. 79,750.00 / M2
52 Paku Pancing 60 - 230 @Rp. 720.00 / Bh
53 Sekrup 3,5" @Rp. 410.00 / Kg
54 Sekrup 3,5" @Rp. 20,350.00 / Kg
1 2 3 4

G PENUTUP ATAP
1 Atap Genteng Palentong @Rp. 1,670.00 / Bh
2 Atap Genteng Palentong super @Rp. 3,980.00 / Bh
3 Atap Genteng Kodok @Rp. 2,170.00 / Bh
4 Atap Genteng Beton @Rp. 5,970.00 / Bh
5 Atap Genteng Keramik @Rp. 11,390.00 / Bh
6 Atap Genteng Aspal @Rp. 11,320.00 / Lbr
7 Atap Genteng Metal/Multi Roof 35 @Rp. 64,130.00 / M2
8 Atap Genteng Asbes cement 0,35 @Rp. 66,790.00 / Lbr
9 Atap Sirap @Rp. 1,030.00 / Bh
10 Atap Aluminium gelombang tebal 0,55 @Rp. 98,180.00 / Lbr
11 Atap seng Gelombang 3' x 6' bjls 35 @Rp. 59,640.00 / Lbr
12 Atap seng Super Deck 3' x 6' tbl 0,30 @Rp. 68,750.00 / Lbr
13 Roof light fibreglass gelombang @Rp. 46,390.00 / Lbr
14 Atap Asbes Gelombang 1,8 x 1,05 tbl.4 mm @Rp. 59,380.00 / Lbr
15 Atap Asbes Gelombang 2,1 x 1,05 tbl.4 mm @Rp. 93,170.00 / Lbr
16 Atap Asbes Gelombang 2,4 x 1,05 tbl.4 mm @Rp. 108,130.00 / Lbr
17 Atap Asbes Gelombang 2,7 x 1,05 tbl.4 mm @Rp. 113,300.00 / Lbr
18 Atap Asbes Gelombang 1,8 x 0,92 tbl.5 mm @Rp. 70,950.00 / Lbr
19 Atap Asbes Gelombang 2,1 x 0,92 tbl.5 mm @Rp. 88,770.00 / Lbr
20 Atap Asbes Gelombang 2,4 x 0,92 tbl.5 mm @Rp. 97,020.00 / Lbr
21 Atap Asbes Gelombang 2,7 x 0,92 tbl.5 mm @Rp. 106,810.00 / Lbr
22 Atap Asbes Gelombang 1,8 x 1,08 tbl.6 mm @Rp. 103,620.00 / Lbr
23 Atap Asbes Gelombang 2,1 x 1,08 tbl.6 mm @Rp. 120,450.00 / Lbr
24 Atap Asbes Gelombang 2,4 x 1,08 tbl.6 mm @Rp. 128,370.00 / Lbr
25 Atap Asbes Gelombang 2,7 x 1,08 tbl.6 mm @Rp. 155,430.00 / Lbr
26 Genteng bubung palentong @Rp. 9,350.00 / Bh
27 Genteng bubung palentong super @Rp. 12,740.00 / Bh
28 Genteng bubung kodok @Rp. 9,560.00 / Bh
29 Nok genteng beton @Rp. 13,440.00 / Bh
30 Nok genteng keramik @Rp. 15,040.00 / Bh
31 Nok Genteng Aspal @Rp. 29,350.00 / Bh
32 Nok Genteng Metal/Multi Roof (decra bond) @Rp. 41,140.00 / Bh
33 Nok Genteng Asbes cement 0,35 @Rp. 33,770.00 / Lbr
34 Nok Aluminium standard 40 cm 18 swg22 @Rp. 47,890.00 / M2
35 Bubung/Nok Stel Gelombang 0,92 m' tbl.5 mm @Rp. 19,590.00 / Lbr
36 Bubung/Nok Stel Gelombang 1,05 m' tbl.4 mm @Rp. 25,990.00 / Lbr
37 Bubung/Nok Stel Gelombang 1,08 m' tbl.6 mm @Rp. 28,510.00 / Lbr
38 Bubung/Nok Paten 0,92 m' tbl.5 mm @Rp. 36,810.00 / Lbr
39 Bubung/Nok Paten 1,05 m' tbl.4 mm @Rp. 30,950.00 / Lbr
40 Bubung/Nok Paten 1,08 m' tbl.6 mm @Rp. 42,960.00 / Lbr
41 Bubung/Nok Stel Rata 0,92 m' tbl.5 mm @Rp. 36,080.00 / Lbr
42 Bubung/Nok Stel Rata 1,05 m' tbl.4 mm @Rp. 30,250.00 / Lbr
43 Bubung/Nok Stel Rata 1,08 m' tbl.6 mm @Rp. 40,600.00 / Lbr
44 Seng Plat 3" x 6" bjls 35 @Rp. 115,500.00 / Lbr
45 Seng Plat 3" x 6" bjls 30 @Rp. 103,950.00 / Lbr
46 Plastic aerator @Rp. 27,500.00 / Bh
47 Sisalation / aluminium foil @Rp. 77,200.00 / M2
48 Paku seng + Ring karet @Rp. 20,350.00 / Kg
49 Paku seng + Ring karet @Rp. 410.00 / Bh
50 Paku hak panjang 15 cm @Rp. 30,530.00 / Kg
51 Atap Seng Alumi Zinc warna 0,35 @Rp. 62,040.00 / M2
52 Atap Twin light @Rp. 74,250.00 / M2
1 2 3 4

H KUNCI DAN KACA


1 Kunci tanam antik @Rp. 214,500.00 / Bh
2 Kunci tanam biasa @Rp. 90,020.00 / Bh
3 Kunci tanam kamar mandi @Rp. 54,690.00 / Bh
4 Kunci silinder @Rp. 34,490.00 / Bh
5 Kunci selot @Rp. 27,230.00 / Bh
6 Kunci lemari @Rp. 12,340.00 / Bh
7 Engsel pintu 4" @Rp. 15,130.00 / Bh
8 Engsel jendela 3" @Rp. 11,250.00 / Bh
9 Engsel angin @Rp. 25,050.00 / Bh
10 Kait angin @Rp. 19,120.00 / Bh
11 Rel pintu dorong @Rp. 160,330.00 / Bh
12 Sealent @Rp. 39,330.00 / Kg
13 Spring Knip @Rp. 9,080.00 / Bh
14 Door closer @Rp. 109,750.00 / Bh
15 Door handle @Rp. 113,010.00 / Bh
16 Door stoop @Rp. 38,120.00 / Bh
17 Espanyolet @Rp. 88,450.00 / Bh
18 Kaca Block 20 x 20 cm @Rp. 26,020.00 / Bh
19 Kaca polos tbl.3 mm @Rp. 87,120.00 / M2
20 Kaca polos tbl.5 mm @Rp. 145,200.00 / M2
21 Kaca polos tbl.8 mm @Rp. 232,320.00 / M2
22 Kaca Reyben tbl.5 mm @Rp. 193,120.00 / M2
23 Kaca Reyben tbl.8 mm @Rp. 308,980.00 / M2
24 Kaca Buram tbl.3 mm @Rp. 72,600.00 / M2
25 Kaca Buram tbl.5 mm @Rp. 111,320.00 / M2
26 Kaca buram tbl.8 mm @Rp. 193,600.00 / M2
27 Kaca cermin tbl.5 mm @Rp. 161,700.00 / M2
28 Kaca cermin tbl.6 mm @Rp. 194,040.00 / M2
29 Kaca cermin tbl.8 mm @Rp. 258,720.00 / M2
30 Kaca patri @Rp. 169,400.00 / M2
31 Kaca Wireglass @Rp. 151,250.00 / M2
32 Kaca Reyben Naco 30 x 60 cm tbl.5 mm @Rp. 13,590.00 / Lbr
33 Kaca Bening Naco 30 x 60 cm tbl.5 mm @Rp. 10,730.00 / Lbr

I CAT / MINYAK
1 Cat dasar @Rp. 15,730.00 / Kg
2 Cat Tembok setara Vinilex @Rp. 19,360.00 / Kg
3 Cat Minyak untuk kayu @Rp. 35,700.00 / Kg
4 Cat Minyak untuk Besi @Rp. 39,330.00 / Kg
5 Cat Menie kayu @Rp. 20,570.00 / Kg
6 Cat Menie besi @Rp. 25,410.00 / Kg
7 Cat sending @Rp. 54,450.00 / Kg
8 Cat Melamix @Rp. 59,290.00 / Kg
9 Cat Vernis Jadi @Rp. 48,280.00 / Kg
10 Plamir @Rp. 15,730.00 / Kg
11 Dempul gypsum @Rp. 10,410.00 / Kg
12 Dempul Cat @Rp. 11,860.00 / Kg
13 Minyak Cat @Rp. 11,010.00 / Kg
14 Minyak Bekisting @Rp. 6,290.00 / Ltr
15 Residu / Kolter @Rp. 6,530.00 / Ltr
16 Soda api @Rp. 12,100.00 / Kg
17 Sabun @Rp. 10,290.00 / Kg
18 Kuas @Rp. 7,870.00 / Bh
19 Ampelas / Kertas pasir @Rp. 1,820.00 / Lbr
20 Wall paper @Rp. 30,610.00 / M2
1 2 3 4

J SANITASI / PIPA
1 Kloset duduk / monoblok lengkap tangki @Rp. 1,931,600.00 / Bh
2 Kloset duduk / monoblok tanpa tangki @Rp. 1,391,500.00 / Bh
3 Kloset jongkok porselin @Rp. 225,280.00 / Bh
4 Bakkif Porselin @Rp. 3,025,000.00 / Bh
5 Wastafel @Rp. 526,350.00 / Bh
6 Urinoir @Rp. 557,480.00 / Bh
7 Kran air 1/2" - 3/4" @Rp. 27,350.00 / Bh
8 Kran air leher angsa 1/2" @Rp. 77,200.00 / Bh
9 Kran shower @Rp. 92,570.00 / Bh
10 Kran Cebok @Rp. 72,240.00 / Bh
11 Bak fibreglass 0,3 M3 @Rp. 181,500.00 / Bh
12 Bak fibreglass 1 M3 @Rp. 522,720.00 / Bh
13 Bak cuci piring stainless 2 lobang @Rp. 466,700.00 / Bh
14 Bak cuci piring teraso 2 lobang @Rp. 272,250.00 / Bh
15 Tempat sabun keramik @Rp. 56,270.00 / Bh
16 Floor drain 4" steinless @Rp. 15,000.00 / Bh
17 Stop kran 3/4" @Rp. 27,500.00 / Bh
18 Tutup bak air 1" Kuningan @Rp. 12,500.00 / Bh
19 Instalasi air bersih @Rp. 100,000.00 / Ttk
20 Instalasi air kotor/limbah @Rp. 125,000.00 / Ttk
21 Buis Beton 1/2 15 cm @Rp. 11,250.00 / M'
22 Buis Beton 1/2 20 cm @Rp. 17,790.00 / M'
23 Buis Beton 1/2 30 cm @Rp. 20,090.00 / M'
24 Buis Beton 15 cm @Rp. 19,240.00 / M'
25 Buis Beton 20 cm @Rp. 27,350.00 / M'
26 Buis Beton 30 cm @Rp. 56,270.00 / M'
27 Buis Beton 40 cm @Rp. 63,400.00 / M'
28 Buis Beton 50 cm @Rp. 95,950.00 / M'
29 Buis Beton 60 cm @Rp. 136,000.00 / M'
30 Buis Beton 80 cm @Rp. 201,100.00 / M'
31 Buis Beton 100 cm @Rp. 345,820.00 / M'
32 Pipa PVC Tipe AW 1/2" @Rp. 25,300.00 / Btg
33 Pipa PVC Tipe AW 3/4" @Rp. 7,440.00 / Btg
34 Pipa PVC Tipe AW 1" @Rp. 13,620.00 / Btg
35 Pipa PVC Tipe AW 1 1/2" @Rp. 19,670.00 / Btg
36 Pipa PVC Tipe AW 2" @Rp. 23,190.00 / Btg
37 Pipa PVC Tipe AW 2 1/2" @Rp. 26,620.00 / Btg
38 Pipa PVC Tipe AW 3" @Rp. 29,840.00 / Btg
39 Pipa PVC Tipe AW 4" @Rp. 49,920.00 / Btg
40 Pipa Besi Hitam 1/2" @Rp. 14,770.00 / Btg
41 Pipa Besi Hitam 3/4" @Rp. 20,140.00 / Btg
42 Pipa Besi Hitam 1" @Rp. 29,520.00 / Btg
43 Pipa Besi Hitam 1 1/2" @Rp. 37,580.00 / Btg
44 Pipa Besi Hitam 2" @Rp. 47,600.00 / Btg
45 Pipa Besi Hitam 2 1/2" @Rp. 50,220.00 / Btg
46 Pipa Galvanis 1/2" @Rp. 14,770.00 / Btg
47 Pipa Galvanis 3/4" @Rp. 20,140.00 / Btg
48 Pipa Galvanis 1" @Rp. 29,520.00 / Btg
49 Pipa Galvanis 1 1/4" @Rp. 33,560.00 / Btg
50 Pipa Galvanis 1 1/2" @Rp. 37,580.00 / Btg
51 Pipa Galvanis 2" @Rp. 47,600.00 / Btg
52 Pipa Galvanis 2 1/2" @Rp. 52,440.00 / Btg
53 Fitting Pipa AW 1" @Rp. /
54 Knee AW 1" @Rp. 5,230.00 / Bh
55 Tee AW 1" @Rp. 7,150.00 / Bh
56 Socht AW 1" @Rp. 4,680.00 / Bh
57 F-Knee 1" @Rp. / Bh
58 F-Tee 1" @Rp. 11,500.00 / Bh
59 Bocht LL-D 1" @Rp. 24,750.00 / Bh
60 Union Socht 1" @Rp. 7,430.00 / Bh
61 D-Nipple 1" @Rp. 18,150.00 / Bh
62 Water Moer 1" @Rp. 29,500.00 / Bh

1 2 3 4

J SANITASI / PIPA
1 Kloset duduk / monoblok lengkap tangki @Rp. 1,931,600.00 / Bh
2 Kloset duduk / monoblok tanpa tangki @Rp. 1,391,500.00 / Bh
3 Kloset jongkok porselin @Rp. 225,280.00 / Bh
4 Bakkif Porselin @Rp. 3,025,000.00 / Bh
5 Wastafel @Rp. 526,350.00 / Bh
6 Urinoir @Rp. 557,480.00 / Bh
7 Kran air 1/2" - 3/4" @Rp. 27,350.00 / Bh
8 Kran air leher angsa 1/2" @Rp. 77,200.00 / Bh
9 Kran shower @Rp. 92,570.00 / Bh
10 Kran Cebok @Rp. 72,240.00 / Bh
11 Bak fibreglass 0,3 M3 @Rp. 181,500.00 / Bh
12 Bak fibreglass 1 M3 @Rp. 522,720.00 / Bh
13 Bak cuci piring stainless 2 lobang @Rp. 466,700.00 / Bh
14 Bak cuci piring teraso 2 lobang @Rp. 272,250.00 / Bh
15 Tempat sabun keramik @Rp. 56,270.00 / Bh
16 Floor drain 4" steinless @Rp. 15,000.00 / Bh
17 Stop kran 3/4" @Rp. 27,500.00 / Bh
18 Tutup bak air 1" Kuningan @Rp. 12,500.00 / Bh
19 Instalasi air bersih @Rp. 100,000.00 / Ttk
20 Instalasi air kotor/limbah @Rp. 125,000.00 / Ttk
21 Buis Beton 1/2 15 cm @Rp. 11,250.00 / M'
22 Buis Beton 1/2 20 cm @Rp. 17,790.00 / M'
23 Buis Beton 1/2 30 cm @Rp. 20,090.00 / M'
24 Buis Beton 15 cm @Rp. 19,240.00 / M'
25 Buis Beton 20 cm @Rp. 27,350.00 / M'
26 Buis Beton 30 cm @Rp. 56,270.00 / M'
27 Buis Beton 40 cm @Rp. 63,400.00 / M'
28 Buis Beton 50 cm @Rp. 95,950.00 / M'
29 Buis Beton 60 cm @Rp. 136,000.00 / M'
30 Buis Beton 80 cm @Rp. 201,100.00 / M'
31 Buis Beton 100 cm @Rp. 345,820.00 / M'
32 Bodeam 30 x 60 cm @Rp. 25,300.00 / Bh
33 Pipa PVC Tipe AW 1/2" @Rp. 5,540.00 / M'
34 Pipa PVC Tipe AW 3/4" @Rp. 7,440.00 / M'
35 Pipa PVC Tipe AW 1" @Rp. 13,620.00 / M'
36 Pipa PVC Tipe AW 1 1/2" @Rp. 19,670.00 / M'
37 Pipa PVC Tipe AW 2" @Rp. 23,190.00 / M'
38 Pipa PVC Tipe AW 2 1/2" @Rp. 26,620.00 / M'
39 Pipa PVC Tipe AW 3" @Rp. 29,840.00 / M'
40 Pipa PVC Tipe AW 4" @Rp. 49,920.00 / M'
41 Pipa Besi Hitam 1/2" @Rp. 14,770.00 / M'
42 Pipa Besi Hitam 3/4" @Rp. 20,140.00 / M'
43 Pipa Besi Hitam 1" @Rp. 29,520.00 / M'
44 Pipa Besi Hitam 1 1/2" @Rp. 37,580.00 / M'
45 Pipa Besi Hitam 2" @Rp. 47,600.00 / M'
46 Pipa Besi Hitam 2 1/2" @Rp. 50,220.00 / M'
47 Pipa Galvanis 1/2" @Rp. 14,770.00 / M'
48 Pipa Galvanis 3/4" @Rp. 20,140.00 / M'
49 Pipa Galvanis 1" @Rp. 29,520.00 / M'
50 Pipa Galvanis 1 1/4" @Rp. 33,560.00 / M'
51 Pipa Galvanis 1 1/2" @Rp. 37,580.00 / M'
52 Pipa Galvanis 2" @Rp. 47,600.00 / M'
53 Pipa Galvanis 2 1/2" @Rp. 52,440.00 / M'
Fitting Pipa AW 1" yang terdiri dari : @Rp. /
54 Fitting Knee AW 1" @Rp. 5,230.00 / Bh
55 Fitting Tee AW 1" @Rp. 7,150.00 / Bh
56 Fitting Socht AW 1" @Rp. 4,680.00 / Bh
57 Bocht LL-D 1" @Rp. 24,750.00 / Bh
58 Union Socht 1" @Rp. 7,430.00 / Bh
59 D-Nipple 1" @Rp. 18,150.00 / Bh

1 2 3 4

K LISTRIK / ACSESORIES
1 Lampu TL 1 x 20 W Lengkap Kotak @Rp. 54,450.00 / Set
2 Lampu TL 1 x 40 W Lengkap Kotak @Rp. 60,500.00 / Set
3 Lampu TL 2 x 20 W Lengkap Kotak @Rp. 163,350.00 / Set
4 Lampu TL 2 x 40 W Lengkap Kotak @Rp. 183,920.00 / Set
5 Lampu TL Bambu 1 x 20 W Lengkap @Rp. 108,900.00 / Set
6 Lampu TL Bambu 1 x 40 W Lengkap @Rp. 123,420.00 / Set
7 Lampu XL 5 W + Fitting @Rp. 25,410.00 / Set
8 Lampu XL 8 W + Fitting @Rp. 27,230.00 / Set
9 Lampu XL 10 W + Fitting @Rp. 29,040.00 / Set
10 Lampu XL 14 W + Fitting @Rp. 33,280.00 / Set
11 Lampu XL 18 W + Fitting @Rp. 33,880.00 / Set
12 Lampu XL 24 W + Fitting @Rp. 38,720.00 / Set
13 Lampu Downlight 5 W lengkap @Rp. 54,450.00 / Set
14 Lampu Pijar 5 w + Fitting @Rp. 8,250.00 / Set
15 Lampu Pijar 10 w + Fitting @Rp. 8,800.00 / Set
16 Lampu Pijar 15 w + Fitting @Rp. 9,350.00 / Set
17 Lampu Pijar 20 w + Fitting @Rp. 9,900.00 / Set
18 Lampu Pijar 25 w + Fitting @Rp. 10,450.00 / Set
19 Lampu Pijar 40 w + Fitting @Rp. 11,550.00 / Set
20 Stop Kontak tanam @Rp. 10,290.00 / Bh
21 Saklar tunggal @Rp. 14,520.00 / Bh
22 Saklar ganda @Rp. 15,730.00 / Bh
23 Saklar Triple @Rp. 18,150.00 / Bh
24 Zekring box 1 grup @Rp. 26,620.00 / Unit
25 Zekring box 2 grup @Rp. 31,350.00 / Unit
26 Zekring box 3 grup @Rp. 38,500.00 / Unit
27 Zekring box 4 grup @Rp. 46,200.00 / Unit
28 MCB 2 Ampere @Rp. 35,200.00 / Unit
29 MCB 4 Ampere @Rp. 42,900.00 / Unit
30 MCB 6 Ampere @Rp. 67,760.00 / Unit
31 MCB 8 Ampere @Rp. 99,220.00 / Unit
32 Kabel Listrik NYA 1,5 mm @Rp. 1,120.00 / M'
33 Kabel Listrik NYA 2,5 mm @Rp. 1,930.00 / M'
34 Kabel Listrik NYA 4 mm @Rp. 8,250.00 / M'
35 Kabel Listrik NYM 2 1,5 mm @Rp. 4,020.00 / M'
36 Kabel Listrik NYM 2 2,5 mm @Rp. 9,900.00 / M'
37 Kabel Listrik NYM 2 4 mm @Rp. 15,970.00 / M'
38 Instalasi Listrik titik api / Lampu nyala @Rp. 101,750.00 / Ttk

Medan, Maret 2008

Diketahui Oleh : Dibuat oleh : TIM TEKNIS


Kepala Dinas Penataan Ruang dan 1. Ir. Jeremias Sinaga, MAP (.)
Permukiman Prov. Sumatera Utara
2. Ir. Herimas (.)

3. H. Sugiarto Bharata, ST (.)

4. Ali Muhar, ST (.)


Ir. H. Syafruddin Siregar, MSi
Pembina Utama Muda 5. Sekula Karokaro, ST (.)
NIP. 400025884
6. Ebenser Saragih, SE (.)

7. Sahat Hasudungan, ST (.)

8. Ir. Tanogara Siahaan (.)

9. Ali Fauzen, ST (.)

10. Naimul Ahmad R. ST (.)

11. Chandra, ST (.)


DAFTAR ANALISA
PEKERJAAN PEMBANGUNAN GEDUNG NEGARA

NO ANALISA URAIAN HARGA

Pekerjaan Persiapan
1 Anl. 6.1 1 M' Pagar sementara dari kayu tinggi 2 meter Rp.
2 Anl. 6.2 1 M' Pagar sementara dari seng gelombang tinggi 2 meter Rp.
3 Anl. 6.3 1 M' Pagar sementara dari kawat duri tinggi 1,8 meter Rp.
4 Anl. 6.4 1 M' Pengukuran dan pemasangan bouwlank Rp.
5 Anl. 6.5 1 M Pembuatan kantor sementara dengan lantai plesteran Rp.
6 Anl. 6.6 1 M Pembuatan gudang semen dan alat - alat Rp.
7 Anl. 6.7 1 M Pembuatan rumah jaga/ konstruksi kayu Rp.
8 Anl. 6.8 1 M Membersihkan Lapangan dan peralatan Rp.
9 Anl. 6.9 1 M Pembuatan bedeng buruh Rp.
10 Anl. 6.10 1 M Pembuatan bak adukan ukuran (40 x 50 x 20) cm Rp.
11 Anl. 6.11 1 M Pembuatan Stegger dari bambu ukuran (40 x 50 x 20) cm Rp.
12 Anl. 6.12 1 M Pembuatan jalan sementara Rp.
13 Anl. 6.13 1 M Bongkaran beton bertulang Rp.
14 Anl. 6.14 1 M Bongkaran dinding tembok bata merah Rp.
15 Anl. 6.15 1 M' Pasang pagar kawat jaring galvanis, tinggi 1,00 m Rp.
16 Anl. 6.16 1 M' Pasang pagar beton pracetak (5 x 50 x 213) cm Rp.

Pekerjaan Tanah
17 Anl. 6.1 1 M Galian tanah biasa sedalam 1 meter Rp.
18 Anl. 6.2 1 M Galian tanah biasa sedalam 2 meter Rp.
19 Anl. 6.3 1 M Galian tanah biasa sedalam 3 meter Rp.
20 Anl. 6.4 1 M Galian tanah keras sedalam 1 meter Rp.
21 Anl. 6.5 1 M Galian tanah cadas sedalam 1 meter Rp.
22 Anl. 6.6 1 M Galian tanah lumpur sedalam 1 meter Rp.
23 Anl. 6.7 1 M Pekerjaan Stripping setinggi 1 meter Rp.
24 Anl. 6.8 1 M Pembuangan tanah sejauh 150 meter Rp.
25 Anl. 6.9 1 M Urugan kembali Rp.
26 Anl. 6.10 1 M Pemadatan tanah Rp.
27 Anl. 6.11 1 M Urugan pasir Rp.
28 Anl. 6.12 1 M Lapisan pudel campuran 1 Kp : 3 Ps : 7 TL Rp.
29 Anl. 6.13 1 M Lapisan pudel campuran 1 Kp : 5 TL Rp.
30 Anl. 6.14 1 M Pemasangan lapisan ijuk Rp.
31 Anl. 6.15 1 M Urugan sirtu Rp.
32 Anl. 6.16 1 M Pembuatan jalan sementara, tebal 25 cm Rp.

Pekerjaan Pondasi
33 Anl. 6.1 1 M Pasangan pondasi batu kali, 1 Pc : 1 Ps Rp.
34 Anl. 6.2 1 M Pasang pondasi batu kali 1 Pc : 2 Ps Rp.
35 Anl. 6.3 1 M Pasang pondasi batu kali, 1 Pc : 2,5 Ps Rp.
36 Anl. 6.4 1 M Pasang pondasi batu kali, Pc : 3 Ps Rp.
37 Anl. 6.5 1 M Pasang pondasi batu kali, 1 Pc : 4 Ps. Rp.
38 Anl. 6.6 1 M Pasang pondasi batu kali, 1 Pc : 5 Ps Rp.
39 Anl. 6.7 1 M Pasang pondasi batu kali, 1 Pc : 6 Ps Rp.
40 Anl. 6.8 1 M Pasang pondasi batu kali, Pc : 8 Ps Rp.
41 Anl. 6.9 1 M Pasang pondasi batu kali, 1 Kp : 1 Sm : 1 Ps Rp.
42 Anl. 6.10 1 M Pasang pondasi batu kali, 1 Kp : 1 SM : 2 Ps Rp.

NO ANALISA URAIAN HARGA

43 Anl. 6.11 1 M Pasangan pondasi batu kali, 1 Pc : 1/4 Kp : 4 Ps Rp.


44 Anl. 6.12 1 M Pasang pondasi batu kali, 1 Pc : 3 Kp : 10 Ps Rp.
45 Anl. 6.13 1 M Pasang pondasi batu kali, 1/4 Pc : 1 Kp : 4 Ps Rp.
46 Anl. 6.14 1 M Pasang pondasi batu kosong Rp.
47 Anl. 6.15 1 M Pasang pondasi siklop 40 % batu kali Rp.
48 Anl. 6.16 1 M Pasang pondasi sumuran diameter 100 Cm Rp.
49 Anl. 6.17 1 M Pembuatan tiang pancang (40 x 40) Cm, beton bertulang Rp.
50 Anl. 6.18 1 M Pembuatan tiang pancang (35 x 35) Cm, beton bertulang Rp.

Pekerjaan Dinding
51 Anl. 6.1 1 m Pasangan bata merah tebal 1 bata, 1 Pc : 1 Ps Rp.
52 Anl. 6.2 1 m Pasangan bata merah tebal 1 bata, 1Pc : 2 Ps Rp.
53 Anl. 6.3 1 m Pasangan bata merah tebal 1 bata, 1Pc : 3 Ps Rp.
54 Anl. 6.4 1 m Pasangan bata merah tebal 1 bata, 1Pc : 4 Ps Rp.
55 Anl. 6.5 1 m Pasangan bata merah tebal 1 bata, 1Pc : 5 Ps Rp.
56 Anl. 6.6 1 m Pasangan bata merah tebal 1 bata, 1Pc : 6 Ps Rp.
57 Anl. 6.7 1 m Pasangan bata merah tebal 1 bata, 1Pc : 3 Kp : 10 Ps Rp.
58 Anl. 6.8 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 1 Ps Rp.
59 Anl. 6.9 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 2 Ps Rp.
60 Anl. 6.10 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 3 Ps Rp.
61 Anl. 6.11 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 4 Ps Rp.
62 Anl. 6.12 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 5 Ps Rp.
63 Anl. 6.13 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 6 Ps Rp.
64 Anl. 6.14 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 8 Ps Rp.
65 Anl. 6.15 1 m Pasangan bata merah tebal 1/2 bata, 1Pc : 3 Kp : 10 Ps Rp.
66 Anl. 6.16 1 m Pasangan bata merah tebal 1/2 bata, 1Kp : 1 Sm : 1 Ps Rp.
67 Anl. 6.17 1 m Pasangan bata merah tebal 1/2 bata, 1Kp : 1 Sm : 2 Ps Rp.
68 Anl. 6.18 1 m Pasangan dinding holowblock (HB.20) Rp.
69 Anl. 6.19 1 m Pasangan dinding holowblock (HB.15) Rp.
70 Anl. 6.20 1 m Pasangan dinding holowblock (HB.10) Rp.
71 Anl. 6.21 1 m Pasangan dinding holowblock (HB.10) Rp.
72 Anl. 6.22 1 m Pasangan dinding Conblock (CB.15) Rp.
73 Anl. 6.23 1 m Pasangan dinding Conblock (CB.10) Rp.
74 Anl. 6.24 1 m Pasang dinding lantai Rp.
75 Anl. 6.25 1 m Pasang dinding lantai Rp.
76 Anl. 6.26 1 m Pasang bata berongga ukuran ( 5 x 11 x 24 ) cm Rp.
77 Anl. 6.27 1 m Pasang dinding anyaman bambu, rangka kayu Rp.

Pekerjaan Plesteran
78 Anl. 6.1 1 M Plesteran 1 Pc : 1 Ps, tebal 15 mm Rp.
79 Anl. 6.2 Rp.
80 Anl. 6.3 Rp.
81 Anl. 6.4 Rp.
82 Anl. 6.5 Rp.
83 Anl. 6.6 Rp.
84 Anl. 6.7 Rp.
85 Anl. 6.8 Rp.
86 Anl. 6.9 Rp.
87 Anl. 6.10 Rp.
88 Anl. 6.11 Rp.
89 Anl. 6.12 Rp.
90 Anl. 6.13 Rp.

NO ANALISA URAIAN HARGA

91 Anl. 6.14 Rp.


92 Anl. 6.15 Rp.
93 Anl. 6.16 Rp.
94 Anl. 6.17 Rp.
95 Anl. 6.18 Rp.
96 Anl. 6.19 Rp.
97 Anl. 6.20 Rp.
98 Anl. 6.21 Rp.
99 Anl. 6.22 Rp.
100 Anl. 6.23 Rp.
101 Anl. 6.24 Rp.
102 Anl. 6.25 Rp.
103 Anl. 6.26 Rp.
104 Anl. 6.27 Rp.
105 Anl. 6.28 Rp.
106 Anl. 6.29 Rp.
107 Anl. 6.30 Rp.
108 Anl. 6.31 Rp.
109 Anl. 6.32 Rp.
110 Anl 6.33 Rp.
111 Anl 6.34 Rp.
112 Anl 6.35 Rp.
113 Anl 6.36 Rp.

Pekerjaan Kayu
114 Anl 6.1 Rp.
115 Anl 6.2 Rp.
116 Anl 6.3 Rp.
117 Anl 6.4 Rp.
118 Anl 6.5 Rp.
119 Anl 6.6 Rp.
120 Anl 6.7 Rp.
121 Anl 6.8 Rp.
122 Anl 6.9 Rp.
123 Anl 6.10 Rp.
124 Anl 6.11 Rp.
125 Anl 6.12 Rp.
126 Anl 6.13 Rp.
127 Anl 6.14 Rp.
128 Anl 6.15 Rp.
129 Anl 6.16 Rp.
130 Anl 6.17 Rp.
131 Anl 6.18 Rp.
132 Anl 6.19 Rp.
133 Anl 6.20 Rp.
134 Anl 6.21 Rp.
135 Anl 6.22 Rp.
136 Anl 6.23 Rp.
137 Anl 6.24 Rp.
138 Anl 6.25 Rp.
139 Anl 6.26 Rp.
140 Anl 6.27 Rp.

NO ANALISA URAIAN HARGA

141 Anl 6.28 Rp.


142 Anl 6.29 Rp.
143 Anl 6.30 Rp.
144 Anl 6.31 Rp.
145 Anl 6.32 Rp.
146 Anl 6.33 Rp.
147 Anl 6.34 Rp.
148 Anl 6.35 Rp.
149 Anl 6.36 Rp.
150 Anl 6.37 Rp.
151 Anl 6.38 Rp.
152 Anl 6.39 Rp.
153 Anl 6.40 Rp.
154 Anl 6.41 Rp.
155 Anl 6.42 Rp.
156 Anl 6.43 Rp.
157 Anl 6.44 Rp.
158 Anl 6.45 Rp.
159 Anl 6.46 Rp.
160 Anl 6.47 Rp.
161 Anl 6.48 Rp.
162 Anl 6.49 Rp.
163 Anl 6.50 Rp.
164 Anl 6.51 Rp.
165 Anl 6.52 Rp.
166 Anl 6.53 Rp.
167 Anl 6.54 Rp.
168 Anl 6.55 Rp.
169 Anl 6.56 Rp.
170 Anl 6.57 Rp.
171 Anl 6.58 Rp.
172 Anl 6.59 Rp.
173 Anl 6.60 Rp.

Pekerjaan Beton
174 Anl 6.1 1 M Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr Rp. 587,469.50
175 Anl 6.2 1 M Membuat beton tumbuk, 1 Pc : 3 Ps : 6 Kr Rp. 568,372.50
176 Anl 6.3 1 M Membuat beton tumbuk, 1 Pc : 4 Ps : 6 Kr Rp. 534,709.50
177 Anl 6.4 1 M Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr, Tebal 5 Cm Rp. 33,892.30
178 Anl 6.5 1 M Membuat beton 1 Pc : 2 Ps : 3 Kr Rp. 589,868.50
179 Anl 6.6 1 M Membuat beton 1 Pc : 2 Ps : 4 Kr Rp. 678,690.50
180 Anl 6.7 1 M Membuat beton 1 Pc : 2 Ps : 2,5 Kr Rp. 742,608.50
181 Anl 6.8 1 M Membuat beton 1 Pc : 1,5 Ps : 3 Kr Rp. 706,922.50
182 Anl 6.9 1 M Membuat beton 1 Pc : 1,5 Ps : 2,5 Kr Rp. 792,758.50
183 Anl 6.10 1 M Membuat beton 1 Pc : 1 Ps : 2 Kr Rp. 894,652.50
184 Anl 6.11 1 M Membuat tiang pancang prestressed beton Rp. 861,130.50
185 Anl 6.12 1 M Membuat beton dengan puzzdith - 100 XR Rp. 740,981.50
186 Anl 6.13 1 M Membuat beton 1 Pc : 2 Ps : 3 Kr Rp. 849,465.50
187 Anl 6.14 1 M Membuat beton 1 Pc : 2 Ps : 4 Kr Rp. 807,493.50
188 Anl 6.15 1 M Membuat beton 1 Pc : 1,5 Ps : 3 Kr Rp. 892,494.50
189 Anl 6.16 1 M Membuat beton 1 Pc : 1,5 Ps : 2,5 Kr Rp. 937,916.50
190 Anl 6.17 1 M Membuat beton 1 Pc : 1 Ps : 1 Kr Rp. 1,243,485.00

NO ANALISA URAIAN HARGA

191 Anl 6.18 1 M Membuat beton kedap air dengan strorox - 100 Rp. 1,016,679.00
192 Anl 6.19 1 M' Memasang PVC Waterstop lebar 150 mm Rp. 7,395.00
193 Anl 6.20 1 M' Memasang PVC Waterstop lebar 200 mm Rp. 7,957.50
194 Anl 6.21 1 M' Memasang PVC Waterstop lebar 230 mm Rp. 45,020.00
195 Anl 6.22 1 M' Memasang PVC Waterstop lebar 250 mm Rp. 45,155.00
196 Anl 6.23 1 M' Memasang PVC Waterstop lebar 300 mm Rp. 52,425.00
197 Anl 6.24 Rp.
198 Anl 6.25 Rp.
199 Anl 6.26 Rp.
200 Anl 6.27 Rp.
201 Anl 6.28 Rp.
202 Anl 6.29 1 M Pasang bekisting untuk sloof Rp. 197,247.50
203 Anl 6.30 1 M Pasang bekisting untuk kolom Rp. 317,800.50
204 Anl 6.31 1 M Pasang bekisting untuk balok Rp. 328,623.00
205 Anl 6.32 1 M Pasang bekisting untuk lantai Rp. 396,300.50
206 Anl 6.33 1 M Pasang bekisting untuk dinding Rp. 343,013.00
207 Anl 6.34 1 M Pasang bekisting untuk tangga Rp. 287,911.00
208 Anl 6.35 1 M Pasang beton dengan mutu K 225 Rp. 1,276,460.00
209 Anl 6.36 1 M Pasang beton dengan mutu K 275 Rp. 1,302,084.00
210 Anl 6.37 1 M Pasang jembatan cor Rp. 118,195.00
211 Anl 6.38 1 M Membuat pondasi beton bertulang (150 kg besi + bekisting) Rp. 4,038,785.50
212 Anl 6.39 1 M Membuat sloof beton bertulang (200 kg besi + bekisting) Rp. 5,167,626.00
213 Anl 6.40 1 M Membuat kolom beton bertulang (300 kg besi + bekisting) Rp. 8,804,112.00
214 Anl 6.41 1 M Membuat balok beton bertulang (200 kg besi + bekisting) Rp. 6,644,741.00
215 Anl 6.42 1 M Membuat balok beton bertulang (150 kg besi + bekisting) Rp. 6,102,988.50
216 Anl 6.43 1 M Membuat dinding beton bertulang (150 kg besi + bekisting) Rp. 5,792,268.50
217 Anl 6.44 1 M Membuat tangga beton bertulang (150 kg besi + bekisting) Rp. 6,155,427.50
218 Anl 6.45 1 M' Membuat kolom penguat beton bertulang (11 x 11) cm Rp. 76,137.30
219 Anl 6.46 1 M' Membuat ring balok beton bertulang (10 x 15) cm Rp. 92,283.60