DEPARTMENT OF TRANSPORTATION
SPECIAL PROVISION
FOR
CONTRACTOR FURNISHED MIX DESIGNS
FOR PCC PAVEMENT
This work consists of establishing the mix design requirements and acceptance
criteria for Portland Cement Concrete Pavement (PCCP).
Make the following changes to the Standard Specifications for Roads and
Bridges:
Section 380.3 A Page 139 and 140 Delete this section and replace with the
following:
The mix design process shall produce a mix design that will plot within the
limits listed in Chart A. The mix design shall also meet the following
requirements when plotted on the 0.45 power chart. The best fit line
plotted on the 0.45 power chart shall use a top size of 1 (25 mm)
aggregate for jointed concrete pavement and 1.5 (37.5 mm) aggregates
for Continuously Reinforced Concrete Pavements (CRCP). The combined
gradation when plotted on the 0.45 power chart should fit within the limits
as defined in Chart B for jointed concrete pavement or Chart C for CRCP.
CRCP mix designs shall retain a minimum of 11.5% of the total aggregate
above the 1 (25mm) sieve.
b. Fly ash: Fly ash shall be included in the concrete mixture. Fly ash
shall constitute 20% of the cementitious material (at a 1:1 ratio), by
weight.
The air content for all concrete trial mixes shall have an entrained air
content of 7.0% - 8.0.
All mix designs shall be based off of Saturated Surface Dry (SSD)
condition & Aggregate specific gravity at SSD.
A minimum of 3 cylinders at each age, for each trial shall be tested for
compressive strength at 7, 14, and 28 days. All 9 cylinders must be
made from the same batch of concrete. The cylinders must be
consolidated by the rodding method.
The results of the trial mixes including all batched weights, aggregate
moisture contents, fresh concrete results (initial and 20 minute slump,
initial air content, initial unit weight, and initial temperature), actual
water/cementitious material ratio, compressive strengths, aggregate
gradations (including production tests) and aggregate quality results
shall be furnished by the Contractor to the Engineer at the time the
proposed mix design is submitted for verification.
i. Laboratory Trial Batch Verification: Mix design data and test results
shall be recorded on a DOT Form 24 and submitted to the Engineer,
along with all necessary supporting documentation. Approval of mix
designs shall not relieve the Contractor from the responsibility for
furnishing a concrete mix that meets specification and workability
requirements.
Mix design verification by the Department shall not commence until the
Department has received all of the necessary samples and information
from lab trials and aggregate tests. The Contractors mix design lab
trial must also obtain 4000 psi (28MPa) at 7 days. The Department will
require 40 days prior to production to complete mix design verification.
A concrete mix design that previously has been allowed for use under
this provision will be considered for approval if all proportions are
unchanged from those previously used, and current aggregate
samples show the materials to be used are the same as those used for
the original mix design, and the previous projects test results were
satisfactory for strength, workability, and performance. Aggregate
samples for gradation checks shall be submitted along with the request
to use a previously approved mix design a minimum of 40 days prior to
the anticipated use.
The Department will verify one of the submitted mix design trails. The
Departments verification can be no more than 10% less than the
Contractors submitted strength. If the Departments verification does
not match the Contractors submittal the first time, the Department will
do a second verification at the Contractors request. The costs involved
with any further mix design verifications will be at the Contractors
expense.
a. Slump: The slump range for pavements placed by the slipform paving
method shall be 0-2 (0-50 mm) at the time of placement. Concrete
placed by the stationary side form method shall have a slump range of
1-3 (0-75 mm) at the time of placement.
The allowable tolerance from target values shall be +1.0% and -1.5%.
If the average core compressive strength is more than 500 psi (3.5
Mpa) below the specified 28 day compressive strength, the
concrete represented by the cylinders shall be removed and
replaced, unless Area Engineer approves other corrective
measures.
If the average core compressive strength is more than 500 psi (3.5
Mpa) below the specified 28 day compressive strength, the
concrete represented by the cylinders shall be removed and
replaced, unless the Area Engineer approves other corrective
measures.
The average compressive strength of the cores will prevail over all
other compressive strength determination methods.
Section 820.2 D Page 442 Delete this section and replace with the
following:
General Notes:
The samples of all materials to be used by both the testing firm and the
Central Laboratory shall be taken at the same time and split
proportionately. Material from proposed aggregate sources must be
submitted when a new or modified mix is required or desired. The
following quantities are required to be submitted for each mix design:
Notes:
* A complete certified Chemical Analysis and Physical Test Report
are required for cement other than Dacotah Brand
Quality and other special tests on aggregates that require equipment not
available at the Region Materials Laboratory and field labs shall be made
in the Central Laboratories on samples representing:
a) The first 31,500 yd3 (24,084 m3) taken at the start of production.
b) Each 31,500 yd3 (24,084 m3) thereafter.
The sample sizes for all fine and coarse aggregate Quality tests
require 60 lbs (27.2 kg) of material.
Chart A
WORKABILITY CHART
50
(45,44.5)
Sandy
45
smaller
W, WORKABILITY FACTOR
(79,41)
agg. mix
40
Optimum
35
Larger
agg. mix (45,32.5
30
(75,29) Rocky
W = % Passing #8 25
C = % retained above 3/8" X 100
% retained above #8
20
90 80 70 60 50 40 30
C, COARSENESS FACTOR
100
95
90
85
80
75
70
65 Upper Low er
60 Seive Limit Limit
55 1" 100 92
50 3/4" 96 80
45 1/2" 81 65
40 3/8" 72 56
35 #4 55 39
30 #8 42 26
25 #16 33 17
20
#30 27 11
15
10
5
0
#200
#100
#50
#30
#16
#8
#4
3/8
1/2
3/4
1
Chart C
#30
#50
*****