50% of the countrys total energy needs are met through natural
gas.
The existing FSRU has a spare capacity for 400 MMCFD in year 1 (i.e.
upto March 2016) and 200 MMCFD in years 2 till 15. The cost for
re-gasification will depend on what M/s. EETPL offers to the third party,
who is interested in bringing in their own LNG. The base-line for the
price may be taken as USD 0.06/MMBtu.
Under the LNG policy 2011, a business concern may take up LNG
business under:
M/s. EETPL has acquired FSRU named Exquisite from M/s. Excelerate
Energy on time-charter basis for a period of 15 years. The storage
capacity of FSRU is 150,900 m3 out of which only 143,335 m3 can be
re-gasified, the remaining amount being heel, which is kept in the LNG
storage tanks to maintain cryogenic temperature.
1 m3 = 35.31 ft3
LNG is measured in cubic meters (m3). Since the volume of natural gas
reduces by 600 times, when it changes phase from gas to liquid.
The flow rate of gas pipelines and gas send-out rate of FSRU is
measured in MMCFD (million cubic feet per day). 1 MMCFD is equal to
11.57 ft3/sec.
Natural gas and LNG
To convert: B m3 B ft3 MM MM T MM
TOE tons Btu BOE
LNG
9. Cost of FSRU
The cost of FSRU ranges between USD 330 - 500 million depending on
the LNG storage capacity and gas send-out (i.e. Re-gasified LNG
produced).
Starting from now, LNG developer can establish first FSRU based LNG
terminal in a time frame of 8 - 12 months (May 2016 - September
2016 can go upto December 2016) to add 400 MMCFD supply in the
42" dia. X 358 km pipeline by SSGC.
In the interim period i.e. from today till December 2016, LNG Buyer
may contract with EETPL for utilizing additional terminal capacity
available in FSRU. This will materialize upto December 2015, after
which SSGC will be able to transport 240 MMCFD gas to SNGPL and
has a demand for 240 MMCFD for its own consumption.
11. Envisioned transmission capacity
The GoP/MP&NR are also pursuing other pipeline projects 42" Dia X
1,100 km pipeline from Karachi to Lahore to be laid by Russia
(expected completion by February 2017). Another pipeline project will
be executed by China for transport of 690 MMCFD RLNG from GWadar
to Nawabshah (expected completion by February 2017).
Clearances required:
The capital cost of floating storage unit is USD 1,000/tons per annum.
For fulfilling the 2 BCFD shortfall, 20 -30 MMPTA floating storage unit
will be required. This will cost around USD 20 - 30 million and $
0.18/MMBtu (upto USD 138 - 276 million) as operating cost.
a. LNG Buyer with its own LNG FSO(floating storage unit) and contract
with M/s. EETPL for excess capacity of 200 MMCFD (constrained by
SSGC transmission capability if gas is to be transported to SNGPL
network)
b. LNG developer (constrained by SSGC transmission capability if gas is
to be transported to SNGPL network)
16. Qmax Carriers required for bridging the demand gap of 2 Bcfd
Under the existing set-up, there are two constraints: FSRU send-out
capacity and transmission capacity. For 2 Bcfd gas demand, 2 similar
size FSRUs (gas send-out capacity of 690 MMCFD) in addition to the
existing FSRU will be required. The total gas send-out (at 95% of
designed send-out rate) for three FSRUs will be 1,966 MMCFD. This
will require LNG volume of 430,005 m 3, i.e. a Qmax ship after every two
days.
The existing LSA (LNG Services agreement) between SSGC and Engro
Elengy Terminal Pvt. Ltd. is for a term of 15 years. The salient features
of the agreement are as under: