Practicum Report
by
Tamanna Amin Rini
ID# 12306032
Program: BSCE
Practicum Report
by
Tamanna Amin Rini
ID# 12306022
Program: BSCE
Supervisor
Prof. Dr. Tarekh Rasul
Examination Committee
This practicum report is done for the partial fulfilment of requirements for the Bachalor of Science degree at the
International University of Business Agriculture and Technology, Dhaka, Bangladesh.
Dhaka
31 March 2017
1
Letter of Transmittal
31 March 2017
Prof. Dr. Md. Monirul Islam
Chair and Course Coordinate, Department of Civil Engineering
International University of Business Agriculture and Technology (IUBAT University)
4 Embankment Drive Road, Sector 10,Uttara Model Town,
Dhaka 1230, Bangladesh
Dear Sir,
This is a great opportunity & immense for me to submit my internship report on Study on the
Construction Process of a Ten Storied Residential Building at Holy Homes Sagor Saikat. I have got the
opportunity to work in Holy Homes Sagor Saikot for my internship program, which is an essential part of
my academic program.
I have tried my level best to prepare this report to the required standard. It was certainly a great
opportunity for me to work on this report to actualize my theoretical knowledge in the practical arena.
I express my heart full gratitude to you to go through this report and make your valuable comments. It
would be very kind of you, if you please evaluate my performance regarding this report.
Thanking you,
Sincerely Yours,
..
Tamanna Amin Rini
2
Recommendation Letter
3
Student Declaration
I am declaring that this internship report on Study on the Construction Process of a Ten Storied
Residential Building at Holy Homes Sagor Saikat has only been prepared for the partial fulfilment
of the degree Bachelor of Science in Civil Engineering (BSCE).
It has not been prepared for any other purpose, reward, or presentation and has not been submitted by
me for any Degree, Diploma, Title or Recognition before.
..
Tamnanna Amin Rini
Program: BSCE
ID # 12306032
4
Executive Summery
My practicum report titled Study on the construction Process of a seven storied residential
Building at Holy Homes sagor saikat is made based on the three month practical works in a
construction project with Holy Homes. I have observed project name is Holy Homes sagor saikat.
located at college road Gazipur, Dhaka. As a civil engineering student, I had only the theoretical
knowledge, when I started as a practicum student from then I have gathered some practical knowledge
about the civil construction work. The main focus was on the superstructure part of the project and I
have gathered some practical knowledge about the column, stair, and beam and slab construction
procedure when I was monitoring this work. Brick wall measurement is described. I can read any
structural drawings and now I am able to monitor the super structural constructional work according to
the drawings. This is a significant job to ensure the construction work according to the design and to
maintain the preferred quality in this report on construction process. The First chapter is introduction
arranged with the background and objectives of the study and others. Second chapter describes about
Company Profile, and all running all projects Holy Homes sagor saikat. The Third chapter is about
construction work of all design and specification. In fourth chapter describes about construction work
of Brick wall measurement. In Chapter five is discussed about the staircase. Chapter six about column
and chapter eight is Slab and Beam. And facing some problems and given solution. Lastly discuss
contains the conclusion and recommendation. Overall, in this way here monitoring of a construction
building has been explained that I performed during my internship. I visited another three project by
EXIN Group so; maximum construction work sees this internship and its lots of opportunity for me.
Here, I tried to learn all the practical work in a construction site. It was a great opportunity to work and
learn in Holy Homes sagor saikat.
5
Acknowledgements
At first I remember all praise and thanks to Almighty who helped me to complete the research work
and the practicum report, leading to Bachelor of Science in Civil Engineering. In the process of
completion of my practicum and preparing this practicum report, I would like to pay my gratitude to
some persons for their immense help and enormous cooperation.
At First I would like to show my gratitude to the university authority to permit me to do my practicum.
In this respect, I would like to mention the name of Dr. M A Hannan, the Honourable Registrar of
IUBAT University.
I would like to pay my gratitude to the honourable Vice-Chancellor and Founder of International
University of Business Agriculture and Technology (IUBAT University), Professor Dr. M Alimullah
Miyanfor his enormous contribution to establish a non-government university in this country
otherwise many of us like me could not get the opportunity to become an engineer.
I wish to express my sincere and deepest sense of gratitude to my reverend teacher Professor Dr. Md.
Monirul Islam, Chair, Department of Civil Engineering, International University of Business
Agriculture and Technology (IUBAT University), and my mentor Prof. Dr. Tarekh Rasul,
Professor, Department of Civil Engineering for his keen interest, continuous support, painstaking
guidance and constant inspiration throughout the last four months of my graduation period.
Last but not the least persons whom I should extend my warmest appreciation and thanks are
Supervisor Engr. Md. Mohidul Islam Mison, Project engineer of for his valuable suggestions and
heartiest cooperation during the last four months of my practicum and for his continuous direction in
preparing the practicum report. It was really impossible for me to submit the practicum report without
the cooperation and help of any of the above mentioned.
6
Table of Contents
1. CHAPTER 1 Introduction
12
1.1. General
1.2. Objectives of the study
1.3. Responsibilities:
Figure 7.3 a) Attaching wooden Planks b) Checking depth of Beam c) Checking Depth
of Beam................................................................................................................
CHAPTER 1 INTRODUCTION
1.1. General
In civil engineering construction it is one of the biggest challenges to ensure quality and
standard practice in the real life. In order to overcome such a challenge one should earn sound
knowledge with the help of experienced engineer before supervising any engineering project
independently. And, to get an experienced and cooperative minded engineer is another
challenge in this learning paradigm. As a result, it is always challenging to learn problem
based solutions rather learned by the experience. Sometimes, the problems are so different
from each other spatially that one solution might not be directly applicable for the other.
Therefore, a fresh graduate gets this unique opportunity to involve himself/herself for a short
time through the practicum period where at least few of the basic terminologies are learned:
those are very often used to interact labours or the contractors at the construction site.
To learn how to lead and maintain harmony within different groups in a construction
site
To learn how to work under an extreme environmental condition at the construction
site
1.3. Responsibilities:
Supervise the whole construction work
Estimation of required materials
Implementation of design in practical field
Assuring quality of construction work
Monitoring the labour work.
CHAPTER 2 COMPANY OVERVIEW
1.4. Introduction
ADDRESS:
Holy Homes Real Estate Ltd. is a property development company with operations primarily at
Tongi College Road which is known as the Heart of Gazipur district. The Company owns,
operates, develops, acquires, and rehabilitates apartment communities. We adhere to a simple
and straightforward business plan in our effort to provide investors with dependable financial
returns that exceed those of comparable investments. Our communities generate excellent
financial results through physical improvements and exhibit an unwavering commitment to
customer service. Holy Homes Real Estate Ltd is creating and preserving value in multifamily
apartment complex.
1.5. Our Mission for our Valued Clients and Commitment to residents:
Our mission is to maximize long-term shareholder value by acquiring, repositioning,
developing, and managing market-rate apartment communities while enhancing the quality of
life for our residents and providing employees with opportunities for growth and
accomplishment.
Managing Director
General Manager
Project Director
Project Engineer
Supervisor
Security Guard
Project Location : 23 SHAKIL SARANI, AUCH PARA, COLLEGE ROAD, TONGI, GAZIPUR
Level : Basement+G+9
No.of Apt. : 36
HOLY HOMES ROKEYA MANJIL
Level : G+5
No.of Apt. : 10
Level:
No.of Apt.
Level: G+9
No.of Apt. : 45
Fig: Cement
Concrete Aggregate
Fine Aggregates :
i) 100% Sylhet sand of FM 2.5 for Column ii) 75% sylhet sand & 25% local sand of F.M. 2.5
for Beam, Slab, Stair & others
Coarse Aggregates : i) 3/4" downsize well graded stone chips for Column
ii) 3/4" downsize well graded brick chips for Beam, Slab, Stair & others
2.2. Equipments
Tan Bolts: It is used for fixing column formwork. It keeps column formwork vertically
Nuts: It is used for adding two steel formworks
Screw: It used with screw
Steel Props: It is also used for fixing column formwork
Jute Tape: It used in steel board join
Steel shutter
Steel props
Nut
Bolts
Plum bob
Screw
Jutes gaskets
Trowel
Range
Bamboo
Measurement tape
Wood
Nails
Steel nails
24 gauge wire
MS rod
Plain Sheet
2.3. Procedure
For Staircase:
Reinforcement was placed over the wooden plank according to the drawing
After placing all reinforcement the labors were created tread and riser of stair
The stair was kept riser height 6"and tread height was 10"
For Column:
Generally the main purpose of kicker construction was maintained the vertical
alignment of column
Before construction column kicker all the alignment was corrected
This figure is brick wall plan of this project, its separately two unit, unit A= 1170sft and unit B=
1165sft. Unit A include one master room with veranda, two bed room, also a drawing and dining room
same as Unit B. Each unit have one kitchen room and three toilets, one is attached in master bed, one is
attached in bed room and another is beside the kitchen room.
Indicates the all lintel and false slab of this floor. Basically engineer follow the designer plan
but owner if he wants to change of brick wall then should be lintel will be change. This layout
plan we can see all red colours line is lintel, after reaching 7 ft of height, there was a need to
prepare shuttering for the lintel. The thickness of the lintel was 6 At the same time, the slab of the
toilets and kitchens were given a false slab with a 3thickness in order to create a room for the sanitary
traps and as storage facility for the dwellers.
Figure 3.2 Staircase Section Plan
In this projects three fight of staircase, fight 1 = 8 row, fight 2= 8 row and fight 3=4 row.
10mm&12mm bar was used in stair 10mm dia bar was used 8" c/c as binder bar12mm dia bar was
used 4" c/c as main bar. After placing all reinforcement the labors were created tread and riser of
stair.The stair was kept riser height 6"and tread height was 10".
Figure 3.3 Column Layout
There are 22 column in this project, this picture including all column size, there are eight
categories of column schedule first one is C1= 15*21 ,C2= 15*23, C3= 15*23, C4=
15*25,C5= 15*25, C6 (lift column)= 10*15*15, C7= 12*18 and C8= 15*25
And mixing ratio is 1:1.5:3 (using stone for column)
Figure 3.4 Column Schedule
Figure 3.5 Beam and slab Layout(Top Bar)
Figure 3.6 Beam and slab layout( Bottom bar)
This is floor outline plan, its tropical part and as well as follow the section 1-1 and A-A,
respectively for shuttering and using of this for cantering. This is floor slab reinforcement
details of these projects. In section A and B both are using reinforcement 10mm 6c/c, for
line 1 -10mm extra top bar, line 2- 2 10mm extra top bar
Line 3- one extra top bar 12mm and line 4- two extra top bar 12mm and 10mm in middle
portion 8 c/c in temperature, slab thickness is 5.
Its outline of beam this project here 13 types of beam used (B1-B13) and for casting followed
by reinforcement fy =70,0000 psi and fc = 2500 psi
Mixing ratio of concrete is : 1.2.4
Coarse aggregate brick chips to be used
Clear covering block 1.5
CHAPTER 3 CONSTRUCTION WORK
3.1.1. General
The slab provides a horizontal surface and is usually supported by columns, beams, of walls.
Slabs may be defined as those structural elements that are subjected to distribute loads
primarily in a plane transverse to the plane of slab. It is supported by reinforced concrete
beams. There are two types of slab.
One-Way Slab
One way slabs are normally used when the length to breadth ratio of the room is greater than
2 and the short span does not exceed 3.5m.
When the length to width ratio of an opening (room etc) is less than 2 the slab is design
considering two-way slab.
In my project I worked with two way slab
Fig4.1 : Slab Reinforcements details
Wood
Nails
Steel nails
24 gauge wire
MS rod
Plain Sheet
Short direction bar was used at bottom bar and it is a main bar of slab
Long direction bar was used at top and it is a binder bar of slab
After completing the beam formwork, the slab shuttering was started. At first the runner was placed after that
the props were placed under the runner. After props placing the horizontal Shuttering wood was placed. After
complete of lying wood, the steel sheet was placed on the surface of wood. The diameter of the bamboo was
not less than 3 in. Minimum thickness of the Shuttering wood was 1.25 in. The width of the shuttering wood
was 6 in. The distance between the shuttering wood was 6 in. Plane sheet was be neat and clean. The runner
size 3 in x 2 in.
Figure 4.10 Prepare For Plain Sheet
Figure 4.11 Plain Sheet joining
After that I observed the steel sheet placement and found it was neat and clean
Finally I checked the leakage on the steel sheet and didnt found any leakage or unexpected gaps
between the sheet
One of the major works I found that is the vertical and horizontal levelling of beam and slab I
checked the levelling and the level marked on column reinforcement.
Crank rod should be used for bending moment in both way of slab and placed by 10 mm dia
crank rod in different distance from floor beam in various slab. Extra top bar:- Extra top bar
are to be used on every crank reinforcement actually on floor beam horizontally and placed
by 10 mm. After that I checked the main bars spacing and I observed the arrangement was ok.
Again I observed the top layer reinforcement placing as well as the extra top bar arrangement
Then I checked the top bars spacing and also checked the cranked bar length
3.2. Construction of Beam
Beam is the horizontal member of a structure carrying transverse loads. Beam carries load
from the floor or the roof slab and transfers all the loads inclining its self-weight to the
columns or walls. Beams are the horizontal parts of the structure which transfer the dead and live
loads to the vertical members of the structures. Beams are often used to support slabs, which are
mostly cast with monolithic construction. Beams should withstand the whole load of slab & other live
loads on the slab. This chapter includes the formwork of the beam, casting of the beam and describe
the related problems & solutions.
Beam Size is: 10"*16" and 12"*24"
Depth= 16
Width=10
There are two types of main bar is used, one is 16 mm and another is 20 mm bar
Main bar was different for individual beam as well as the extra top bar also different
3.2.4. Spacing:
In the corner section of each beam, that is L/4 length, stirrup spacing was 5 c/c and the middle section
of the beam that is L/2 length, it was 7 c/c.
Top = 1.5
Bottom = 1.5
Side = 1.5
And it insured by using Block ( 1.5 x 1 x 1)
For beam bottom bar, lap should not be provided at middle third zone 58of the span
For beam top bar, lap may be provided at middle third zone of the span
Not more than 50% of the bars shall be spliced at one place
Lap length for the tension zone = 60*dia and for compression zone = 40*dia
3.2.7. Shattering of Beam
Shuttering or form work is the term used for temporary timber, plywood, metal or other
material used to provide support to wet concrete mix till it gets strength for self support. It
provides supports to horizontal, vertical and inclined surfaces or also provides support to cast
concrete according to required shape and size.
The form work also produces desired finish concrete surface. Some procedure given below:
First steps were cutting the wooden planks, bamboos and runners in proper size. (Planks
size usually 5 1.5 and Runners size usually 3" 2")
Bamboo has been used as props in my project
Beam bottom shutter wooden plank was placed according to beam layout
3.2.9. Checking
At first the labors were cutting reinforcement according to design specification before
Reinforcement placing into the beam and slab
Second steps were placing the beam reinforcement
Stirrup was arranged according to the design
Stirrup was tied up with the top and bottom reinforcement bar
Stirrup was banded top and bottom layer
Stirrup was used 10 mm bar
Matum dimension was 6"
Extra top and bottom were provided according to drawing demand
Extra top 1-20mm bar middle position &2-20mm bar has been used
Decorated this reinforcement and distribute these stirrups at every beam support portion and middle
portion of the beam. Advised him for every beam top bar reinforcement lapping at middle portion
and bottom bar lapping near the support portion. Binding wire not above 24G galvanized irons
wire.
Column is vital part of the structure, which transfers the load of the structure such as beam
and slab to the base of footing. Column forms a very important component of a structure.
Columns support beams which in turn support walls and slabs. It should be realized that the
failure of a column results in the collapse of the structure. Placement and right construction
process will enhance the column durability and strength so everyone needs special
consideration about the column construction.
Tan Bolts: It is used for fixing column formwork. It keeps column formwork vertically
Nuts: It is used for adding two steel formworks
Screw: It used with screw
Steel Props: It is also used for fixing column formwork
Jute Tape: It used in steel board join
In R M Future Garden 22 types of column, all columns reinforcement used 20mm in every
corner and middle position using 16mm reinforcement and 10mm using for binding.
3.3.8. My Role during Reinforcement Placing and Steel Shutter
This figure ties spacing check for finding all reinforcement portion accurate or not and tie
are providing on the outer face of column bar. All tie bar reinforcement provides 10 mm
dia and all tie bar spacing middle parson 7 and another portion 5 c/c.
3.3.11. Formwork:
Its very important to check the preparation of formwork. The shuttering should not permit leakage of
cement grouting. The centring was truly vertical and should not be placed at an angle. The level of the
formwork should be checked they should be as per the drawings. There should not be gap before
concrete is placed. The joints of the formwork should be tight and close enough to prevent the
squeezing out of grouting or sucking in of air during vibration. The formwork should be set accurately
to the desired line levels should have plane surface. It should be as light as possible as well as clean
and oiled.
Figure 6.26 Column Shattering
there are four parts of steel shutter two parts were attached together before setting in the
column
Column shutter was installed around the kicker
Jute fiber gaskets were used at the time of attaching two shutters together with column
Steel shutter
Steel props
Nut
Bolts
Plum bob
Screw
Jutes gaskets
Trowel
Range
Bamboo
Measurement tape
before column casting inner sides of the shutter was wetted by water
Concrete was placed inside the column shutter
At first I checked the materials, the mortar mixture machine and the vibrator was ready
Then I checked the labour was ready for casting
During casting I checked the mortar mixture ratio and it was 1: 1.5: 3
Then I checked the vibrator using and I suggested them proper vibrating
Its very important role on strength development and durability of concrete, curing take place
immediately after concrete placing and finishing and involves maintenance of desired moisture and
temperatureColumn curing was done by wrapping moist jute fabric and sprinkling by hose pipe
frequently Curing was continued up to 28 days within three times in day.
Curing example shown in the figure:
.
3.4. CONSTRUCTION OF STAIRCASE
3.4.1. General
The staircases have always been an apparent architectural element of any architectural style. At first
it was a primitive stone and wooden stairs. Later in course of development of technology of wood,
stone, and metal processing the staircases