ESTIMATING

BRICKWORK
BY

ASSOC. PROF. SETI MARIAM AYOP


UNIVERISIT TEKNOLOGI MARA
MALAYSIA
CALCULATION EXAMPLES
1. Calculate the cost/m of half-brick wall
laid in 1:3 cement mortar which is mixed in
1m diameter mixer (5/3 type).

Price of bricks/piece = RM0.25


Bricklayer rate/day = RM60
Price of cement/bag of 50kg = RM10.50
Price of sand/m = RM30
Rental of mixer = RM300/month with
working days/month is 20
Labour rate/day = RM40
CALCULATION EXAMPLES
2. Build up a unit rate for one-brick wall laid
in 1:1:6 cement-lime mortar which is mixed
by hand.

Price of bricks/piece = RM0.25


Bricklayer rate/day = RM60
Price of cement/bag of 50kg = RM10.50
Price of sand/m = RM30
Price of lime/bag of 10kg = RM4
Labour rate/day = RM40
CALCULATION EXAMPLES
3. Ditto but mixed using a 5/3 mixer.

Price of bricks/piece = RM0.25


Bricklayer rate/day = RM60
Price of cement/bag of 50kg = RM10.50
Price of sand/m = RM30
Price of lime/bag of 10kg = RM4
Rental of mixer = RM300/month with
working days per month = 30
Labour rate/day = RM40
BRICKWORK FACINGS
In laying facing bricks, the
bricklayer lays less facing than
ordinary bricks per hour.

Brickwork facings are billed as


EXTRA OVER ordinary brickwork.

Examples of the descriptions of


brickwork facings in the BQ are as
follows:
BRICKWORK FACINGS
1. Extra over ordinary brickwork in lime-
mortar for facings as specified and laid
in English bond.

2. Extra over ordinary brickwork in


cement mortar laid in stretching bond
for facing with facing bricks as
specified.

3. Extra to facing bricks as specified over


ordinary brickwork to outer walls of
hollow brickwalls.
BRICKWORK FACINGS
This EXTRA OVER or additional coat is
made up of:

1. The additional cost of the facing


bricks over and above the cost of
ordinary bricks.
2. Any additional labour cost involved in
selecting of hand-picking the facing
bricks.
3. The additional bricklayer and labourer
hours taken in laying the facing bricks.
BRICKWORK FACINGS
CALCULATION EXAMPLES
1. Calculate the Extra Over cost/m
facings over ordinary brickwork and laid
in English bond, single-faced.

Price of facing brick/piece = RM0.45


Price of ordinary brick/piece = RM0.25
Bricklayer rate/day = RM60
Labour rate/day = RM40
BRICKWORK FACINGS
CALCULATION EXAMPLES
2. Calculate the Extra Over cost/m
facings over ordinary brickwork and
laid in English bond, double-faced.

Price of facing brick/piece = RM0.45


Price of ordinary brick/piece = RM0.25
Bricklayer rate/day = RM60
Labour rate/day = RM40
POINTING BRICKWORK
Pointing the brickwork can be done in 2
ways:
1. As the laying brickwork proceeds the
joints are flushed or raked as the
bricks are laid.

2. The pointing work is done as a


separate operation before the mortar
has set this way is quite expensive
and seldom practiced.
POINTING BRICKWORK
CALCULATION EXAMPLES

A small quantity of cement mortar or


cement-lime mortar, plain or coloured is
required for the pointing work.
1. Calculate the cost per m of pointing
brickwork as the work proceed in
English bond laid in 1:3 cement
mortar.

2. Ditto but done as a separate operation


and laid in 1:1:6 cement-lime mortar.
POINTING BRICKWORK
CALCULATION EXAMPLES

Price of facing brick/piece = RM0.45


Price of ordinary brick/piece = RM0.25
Bricklayer rate/day = RM60
Labour rate/day = RM40
WORK ELEMENT

ESTIMATING SHEET NO. ______

Material Cost Equipment Cost Labour Cost


Item No. Descriptions Calculations Unit Total Quantity Unit Rate (RM) Total Cost (RM)
(RM) (RM) (RM)

A Main Item:

A1 Materials:

A2 Equipment:

A3 Labour:

Sub-total Direct Costs (RM)

A4 Indirect Costs:

Insurance

Overhead Expenses

Sub-total Indirect Costs (RM)

Total direct and indirect costs (RM)

A5 Add-ons:

Contigencies - 5%

Profit - 10%

GRAND TOTAL COST (RM)