This document provides examples of estimating costs for various brickwork tasks. It includes calculating costs for half-brick walls, one-brick walls, brickwork facings, pointing brickwork, and includes considerations like the cost of materials, equipment rental, and labor rates. An estimating sheet template is also presented to help organize cost calculations for individual work elements.
This document provides examples of estimating costs for various brickwork tasks. It includes calculating costs for half-brick walls, one-brick walls, brickwork facings, pointing brickwork, and includes considerations like the cost of materials, equipment rental, and labor rates. An estimating sheet template is also presented to help organize cost calculations for individual work elements.
This document provides examples of estimating costs for various brickwork tasks. It includes calculating costs for half-brick walls, one-brick walls, brickwork facings, pointing brickwork, and includes considerations like the cost of materials, equipment rental, and labor rates. An estimating sheet template is also presented to help organize cost calculations for individual work elements.
UNIVERISIT TEKNOLOGI MARA MALAYSIA CALCULATION EXAMPLES 1. Calculate the cost/m of half-brick wall laid in 1:3 cement mortar which is mixed in 1m diameter mixer (5/3 type).
Price of bricks/piece = RM0.25
Bricklayer rate/day = RM60 Price of cement/bag of 50kg = RM10.50 Price of sand/m = RM30 Rental of mixer = RM300/month with working days/month is 20 Labour rate/day = RM40 CALCULATION EXAMPLES 2. Build up a unit rate for one-brick wall laid in 1:1:6 cement-lime mortar which is mixed by hand.
Price of bricks/piece = RM0.25
Bricklayer rate/day = RM60 Price of cement/bag of 50kg = RM10.50 Price of sand/m = RM30 Price of lime/bag of 10kg = RM4 Labour rate/day = RM40 CALCULATION EXAMPLES 3. Ditto but mixed using a 5/3 mixer.
Price of bricks/piece = RM0.25
Bricklayer rate/day = RM60 Price of cement/bag of 50kg = RM10.50 Price of sand/m = RM30 Price of lime/bag of 10kg = RM4 Rental of mixer = RM300/month with working days per month = 30 Labour rate/day = RM40 BRICKWORK FACINGS In laying facing bricks, the bricklayer lays less facing than ordinary bricks per hour.
Brickwork facings are billed as
EXTRA OVER ordinary brickwork.
Examples of the descriptions of
brickwork facings in the BQ are as follows: BRICKWORK FACINGS 1. Extra over ordinary brickwork in lime- mortar for facings as specified and laid in English bond.
2. Extra over ordinary brickwork in
cement mortar laid in stretching bond for facing with facing bricks as specified.
3. Extra to facing bricks as specified over
ordinary brickwork to outer walls of hollow brickwalls. BRICKWORK FACINGS This EXTRA OVER or additional coat is made up of:
1. The additional cost of the facing
bricks over and above the cost of ordinary bricks. 2. Any additional labour cost involved in selecting of hand-picking the facing bricks. 3. The additional bricklayer and labourer hours taken in laying the facing bricks. BRICKWORK FACINGS CALCULATION EXAMPLES 1. Calculate the Extra Over cost/m facings over ordinary brickwork and laid in English bond, single-faced.
Price of facing brick/piece = RM0.45
Price of ordinary brick/piece = RM0.25 Bricklayer rate/day = RM60 Labour rate/day = RM40 BRICKWORK FACINGS CALCULATION EXAMPLES 2. Calculate the Extra Over cost/m facings over ordinary brickwork and laid in English bond, double-faced.
Price of facing brick/piece = RM0.45
Price of ordinary brick/piece = RM0.25 Bricklayer rate/day = RM60 Labour rate/day = RM40 POINTING BRICKWORK Pointing the brickwork can be done in 2 ways: 1. As the laying brickwork proceeds the joints are flushed or raked as the bricks are laid.
2. The pointing work is done as a
separate operation before the mortar has set this way is quite expensive and seldom practiced. POINTING BRICKWORK CALCULATION EXAMPLES
A small quantity of cement mortar or
cement-lime mortar, plain or coloured is required for the pointing work. 1. Calculate the cost per m of pointing brickwork as the work proceed in English bond laid in 1:3 cement mortar.
2. Ditto but done as a separate operation
and laid in 1:1:6 cement-lime mortar. POINTING BRICKWORK CALCULATION EXAMPLES
Price of facing brick/piece = RM0.45
Price of ordinary brick/piece = RM0.25 Bricklayer rate/day = RM60 Labour rate/day = RM40 WORK ELEMENT
ESTIMATING SHEET NO. ______
Material Cost Equipment Cost Labour Cost
Item No. Descriptions Calculations Unit Total Quantity Unit Rate (RM) Total Cost (RM) (RM) (RM) (RM)