DOCUMENT NUMBER

ISSUED REV

8/3/2017 WRK-01-ADR-002 0
PREPARED BY CHECKED BY CHECKED BY

DW
UPGRADE JETTY K1

INITIAL
Rev

DATE
Rev-0
Rev-1

METHOD STATEMENT FOR


FORMWORK
Rev-2
Rev-3
Rev-4

SITE MANAGER
ENGINEERING

SUPERVISOR

Review
QC
Date :

Date :
Date :

Date :
COPIES

Date :
1

1
METHOD STATEMENT FOR
GENERAL FORMWORK INSTALLATION

1. General
The concrete structure of building foundation for Upgrade Jetty K1 Project is
necessary to make a method statement of general formwork installation. This
method statement covers formwork for building foundations. It shall be
designed to produce hardened concrete having the shape, lines, grade
and dimensions indicated to approved drawings.

2. Purpose
The purpose of this method is to make produce of installation formwork to
be carried out at jobs site. The formwork comprises conventional formwork.
The scope of work for formwork installation covers the supply, assembling,
and fabrication of formwork that made of plywood, and either materials,
including shutter oil, form tie, chamfering, nalls, supports, and shoring,
cutting in vertical and horizontal position and any other nwcwssary materials
for execution of the work.

3. Type of Formwork
All the surface of foundation using from PERI SYSTEM (PERI GT
24 GIRDER).

And In Exposed Concrete using Phenolic Film Faced.

4. Implementation
The implementation of formwork installation for building foundations at
site to be carried out is as follows:

- Site preparation
- Lean concrete
- Fabrication of side and bottom form
- Rebar installation
- Formwork installation
- Cleaning and treatment of formwork
- Surveying
- Concrete placing
Page 2
- Removal of formwork

4.1.Site Preparation
Site preparation for installation of formwork consist of:
Prepare engine pump for drying water at formwork location.
Excavate the soil for place of fromwork using excavator or by
hand.
Trim/form the slope of soil for slope protection to prevent
collapse of the soil using excavator or using manual.

4.2.Fabrication of side and bottom form


Formwork assembling will be done at outside of job site of pouring
concrete work consist of:
The timber frame are set at regular intervals to distribute the
load from the side and bottom form.
The plywood sheets are fixed on the assembly timber frame.
Mark all connection points using permanent marker to indicate
the line of connection of each side of form.
Mark the level on which the concrete will be placed up to.

4.3.Rebar Installation
Reinforcing bar shall be installed as per method statement for
concrete.

4.4.Formwork Installation
The formwork installation at site consist of :
Mobilization of all formwork components and other formwork
support to the installation location.
Assembly of side and/or bottom form.
Setting of shoring pipe to the assembled panel of side and
bottom form. Make sure the formwork elements are properly tied
at the joint, precisely aligned and tensioned, without spilling out
of place.
Each panel of formwork shall be connected using overlapping
timber beam for connection of formwork panel.
Champer wood as per drawing.

Page 3
Distance between form panel shall be maintained using
separator rod. The rod is set into the hole prepared previously.

4.5.Cleaning and Treatment of Formwork


No concrete shall be placed in any portion of the work until the forms
for the position have been completed and confirmed by the owner.
All the rubbish shall be removed from the interior of forrm before the
concrete is placed.

The faces of the forms in contact with the concrete shall be clear
treated with a suitable release agent. Forms that are to be used for
forming concrete surface on which fill adhesive, paint, epoxies,
masonry coatings, or release agents that leaves residues on the
surface that leaves residues on the surface at the concrete.

4.6.Formwork Removal
It is very important to ensure that fresh concrete is well supported
before it is self supporting. Theformwork removal shall be executed
as per following: - Columns walls : 2 days
Side form of column : 2 days
Side form of beam : 2 days
Bottom form of beam : 14 days
Side form of slab : 2 days

5. Flowchart
The flowchart for formwork installation is as follows:

Page 4
Page 5
6. Inspection Form The inspection form for fomwork installation
is attached on Appendix-1.

0. S afet y P ro ced ure The safety procedure for forwork installation


is attached on Appendix-2.

Appendix-1
Inspection Form

Page 6
Page 7
Appendix-2
Safety Hazard Identification and Risk Analysis

Page 8