Timesheet Heavy Equipment

Heavy Equipment Working Hours


No Operator Name Date Location
Type Start Finish
1 Marlon Sinaga Excavator 22-Sep-16 8:00 17:00 SM-A Wellpad
2 Andrian Excavator 22-Sep-16 8:00 17:00 SM-E Wellpad
3 Margono Dump Truck 22-Sep-16 8:00 17:00 SM-E Wellpad
4 Buldozer 22-Sep-16 8:00 17:00 SM-E Wellpad
Vibro 22-Sep-16 8:00 17:00 SM-A Wellpad
5
6 Backho loader 22-Sep-16 8:00 17:00 SM-A Wellpad
Note:
1. Mobilization Excavator carried out last night, but there were stopped by local residents.
2. Regulation of compensation for the local residents, waiting for instructions from PT. SMGP.

Documentation
Base Camp Area

Excavator Stand By at SM-A Wellpad

Diketahui Oleh: Disetujui Oleh:


PT. CIPTA BANGUN NUSANTARA PT. SORIK MARAPI GEOTHERMAL P
Dicky Aditriya Agus Suwito Aristeo Jabola/Syamsul Muis
Project Control Project Manager Civil Construction
Remarks

Stand By
Supporting Earthwork at SM-E
Stand By
Stand By
Supporting Spreading and leveling basecourse for enguin top dri
Supporting Spreading and leveling basecourse for enguin top dri

Disetujui Oleh:
SORIK MARAPI GEOTHERMAL POWER
Aristeo Jabola/Syamsul Muis
Civil Construction