Anda di halaman 1dari 15

LINING TECHNOLOGY

Segmental linings:
a vision for the future
In the Oct/Nov issue of Tunneling Journal North America[1] the
authors, Anthony Harding and Malcolm Chappell described
the current state of the art in segmental linings. Following
this, they explore some of the areas they think segmental
linings are likely to develop over the next decade.

WHILE TUNNEL LININGS have been getting bigger (see box), the
thickness of linings has been going in the opposite direction in an Figure 1: Hexagonal lining erection sequence
effort to save cost and excavated volumes. The authors have seen
contractors consider a lining thickness of 240mm for a 6m Metro Erect Thrust Erect Thrust
tunnel, but settle on slightly higher thicknesses having examined
risks associated with fragility of such thin linings, particularly the
imposed loads and deformations at cross passage openings. It
therefore appears likely that we are approaching the practical lower
limit for lining thickness in many parts of the world.
The largest rings still tend to use traditional rectangular segment
designs. However, at smaller diameters rectangular segments are
increasingly being replaced with trapezoidal and parallelogram Step 1: thrust from shaded rams and retract other rams
shapes (often called the universal ring). These rings typically build to erect the segments outlined
more quickly, more easily, and more accurately than their straight
sided counterparts. It is likely that they will continue to be used at Thrust Erect Thrust Erect
ever higher diameters until they are the geometry of choice except
where particular project requirements dictate otherwise.
However, the geometry that warrants real development over the
next decade is the hexagonal lining. Hexagonal linings offer
significant productivity benefits over the traditional tapered ring, as
the TBM can thrust from half of the ring while the other half is
being erected (see Figure 1). In their current form they suffer from
gaps that open due to imperfect ring plane (see Figure 2). These
Step 2: thrust from shaded rams onto segments just erected
gaps tend to concentrate the hoop loads in just one half of the ring and retract other rams to erect remainder of ring
unless the gap is grouted with a high strength mortar. The gaps can
also pose problems with waterproofing
gaskets. For this reason their use has been the load transfer through the remaining
confined to: Figure 2: Gaps due to ring plane lining. While this would require additional
rock tunnels where water ingress and loss in hexagonal linings reinforcement in the segments around the
ground loads are not an issue opening, it could eliminate the requirement
projects in Japan where high tolerance for internal propping.
moulds and bespoke steel connectors
Gap
have been employed to limit loss of plane Allowance for internal structures
and ensure a good fit As more and more tunnels are constructed
However, if a simple and cost-effective with internal structures, particularly where
method for early identification and intermediate decks are required, cost
correction of ring plane can be identified Offset effective solutions for the construction of
(due to plane loss)
then it is possible that these linings could the internal structures will be required. Such
become an attractive alternative to normal solutions will need to:
tapered rings. connect to the lining in a cost effective
An additional benefit of hexagonal and buildable way
segments is that it is possible to create accommodate all the movements that
openings by simply removing a segment or might occur to the lining over its design
pattern of segments in a way that allows life (including seismic)

TUNNELLING JOURNAL 31
LINING TECHNOLOGY

Are tunnel linings getting bigger?


It seems that barely a few years passes
Figure 3: Comparison of twin bore and single bore stacked configurations before the latest world record TBM is
of a three lane tunnel surpassed by another tunnel of even
larger diameter. This has been driven by a
combination of tunnel function and
constrained urban environments. Where
corridors are narrow (for example due to
the presence of tall buildings either side
Twin bore of a street), there may not be enough
room for a twin bore tunnel. This problem
becomes even more apparent at the
portals, where significant excavated space
outside the TBM perimeter is required. So
what do you do if you dont have enough
width? One option is to stack the
roadways within a single bore as
illustrated in Figure 3, to obtain a lower
overall width.
This has been successfully implemented
in a number of tunnels, including the
SMART tunnel in Kuala Lumpur and the
Socatop Tunnel in Paris. A three lane
tunnel with full height traffic lanes would
require a world record size TBM, as was
envisaged for the Orlovski project in St
Single bore Petersburg.
Such solutions also offer benefits in
eliminating cross passages as
communication between roadways can be
provided with internal structures, and
equipment and ventilation spaces
provided to either side of the roadway.
Removing the requirement to hand mine
cross passages may be a significant

be easy to build without impeding TBM geopolymer can achieve equivalent or geopolymer requires almost no curing,
logistics better structural, durability and fire eliminating the requirement for steam
The authors are hopeful that this will performance than traditional OPC. This curing
generate some innovative solutions that technology is sufficiently mature to be geopolymer is less vulnerable to early
improve significantly on the traditional adopted on a tunnel project. Critically, their thermal cracking
method of drilling and fixing large numbers research showed that the CO2 required to improved fire performance may save on
of anchors into the lining. produce and deliver the segments would be micro-synthetic polypropylene fibres
70% less than the OPC equivalents. These cost savings will be of interest to
Materials The major barrier to the widespread contractors while the reduced carbon
The predominant material in segmental uptake of geopolymer has been that high footprint will be a concern to all in the
linings is concrete that uses Ordinary volumes of concrete are required to make industry and a major selling point to clients.
Portland Cement (OPC) as a binder, and is the cost of setting up a supply chain and Therefore as soon as a trial project has
reinforced either with steel or steel fibres. manufacturing facilities economically successfully demonstrated the effectiveness
However, the authors view is that there will viable. However, a typical metro tunnel of this technology, it is likely that there will
be an increasing trend towards lower contains at least 1,000m of precast be a proliferation of projects that use
carbon, non-ferrous linings. concrete per route kilometre in the tunnel geopolymer concrete in place of OPC.
One way that carbon footprints will be lining alone, and would easily provide
reduced is by the replacement of OPC with sufficient concrete volume to make for a Fibres
geopolymer, a product that uses slag and viable the business case for geopolymer. As well as changing the concrete binder, the
fly ash in place of cement, activated by Indeed, geopolymer binder could even be authors also see macro-synthetic fibres
admixtures to produce comparable strength cheaper, particularly if the geopolymer was becoming a frequently employed alternative
and strength gain rates to conventional to be used for other concrete on the to steel fibres. There is currently much
OPC. Wimpenny and Chappell[2] have project. debate in the industry as to whether steel
presented research into the use of fibre As well as material cost, geopolymer can fibres or macro-synthetic fibres are superior
reinforced geopolymer concrete for tunnel also save money in the manufacturing for the reinforcement of concrete segments.
segments that demonstrates that plant: Both have limitations when compared to

32 TUNNELLING JOURNAL
LINING TECHNOLOGY

Figure 4: Double
deck construction in a single
tunnel from Barcelona Line 9

project benefit in some ground


conditions. The single bore option does
reduce schedule flexibility somewhat but
this can usually be managed. Therefore
where space is tight we can expect more
mega-TBMs.

Will conventional tunnels get bigger?


While the mega-projects grab the
headlines, the workhorses of the
tunnelling industry are much smaller
tunnels: metro tunnels at around 6m,
cable tunnels at 2-4m, and water tunnels
varying from the very smallest tunnels up
to diameters over 10m. One might think
that this blend of sizes might remain.
However, even for normal tunnels there
may be upward pressure on diameter. In
metro projects the solutions developed
for Barcelona Line 9 (see Figure 4), which
place both tracks on separate decks
within the same tunnel, offer a number
of benefits outlined in Table 1. The impact
of these benefits will vary from project to
Table 1: Comparison of single metro tunnel to twin bore. project, but it is likely that this kind of
scheme will be the best solution for some
Element Conventional twin bore Single tunnel projects.
Tunnel 2x 6m tunnel Single 12m tunnel There may be other circumstances
Footprint 18m wide 12m wide where we can add genuine value to
Cross passages Every 250m approx. Not required projects by making space for more
Crossovers Cut and cover box ~200m long Constructed within tunnel infrastructure inside the tunnel. This will
Stations Cut and cover box ~150m long Driven by patronage, but could be as small as one 30m diameter shaft
also put upward pressure on the average
Sidings Separate tunnel required Within tunnel.
size of segmental linings.

the other, but the authors believe that the Plain concrete??? to limit damage to steel fibre reinforced
limitations can generally be designed for Another potential area of development is the segments. The success of such systems is
and there will be many circumstances where use of plain, unreinforced concrete. This may that they ensure that the segments are not
both materials could meet the required at first appear to be a retrograde step back cracked by the handling activities. Given that
criteria. to the earliest segmental linings, many of the fibres only provide additional strength
A further development that is relevant to which were not reinforced at all[3]. However, after the formation of the crack, it could be
both fibre types, however, is increased the problem with plain concrete segments argued that the systems could also limit
concrete strengths and a desire to make was that they proved very prone to damage damage to plain concrete segments even at
steel fibres work at ever higher diameters during handling, even at low aspect ratios high aspect ratios.
and more heavily loaded linings. At larger (ratio of circumferential length to thickness). The key differences between fibre
diameters the higher hoop loads and higher In recent years aspect ratios have been reinforced and plain concrete are:
TBM ram thrusts give rise to high bursting increasing in order to have fewer segments Fibre reinforced concrete provides
stresses on the longitudinal and in the ring, with the consequent cost and toughness against impacts that plain
circumferential joints. While steel fibres schedule benefits. So it would appear that concrete does not.
have been shown to increase the post-crack modern requirements make plain concrete In the event of a flexural failure the fibres
strength of concrete joints in bursting, the even more problematic. However there are will hold the segment together and
strength of the joints is still fundamentally two important recent developments that provide residual resistance. Plain concrete
tied to the strength of the concrete. may put plain concrete back in the frame. segments could break into two or more
However, the authors are aware that at Firstly, increased concrete strengths and pieces.
least one of the latest steel fibre types offers qualities mean that in many tunnels the Where these obstacles can be overcome (and
increased concrete splitting strengths at low reinforcement is not required for the tunnel ground loads allow) plain concrete linings
dosages. This, paired with high strength in its constructed state. The hoop force in may become more common.
fibres that perform well with high and very many tunnels provides sufficient resistance
high strength concretes, make the for the expected bending moments. Connecting
possibility of solely fibre reinforced rings at Secondly, handling systems that limit As well as reducing or even eliminating steel
higher diameters a realistic possibility. damage have become widespread, primarily from the main body of the segments, the

TUNNELLING JOURNAL 33
APAC TUNNELS &
ORGANISED BY:

BRIDGES 2015
15 -16 April 2015 | Kuala Lumpur, Malaysia

CO - HOST:

SUPPORTING ASSOCIATION

ASIAS
RENOWNED EXCLUSIVE MEDIA PARTNER
PROJECTS UNDER ONE ROOF
The one platform bringing together
industrys prominent design, construction
and maintenance experts SUPPORTING MEDIA PARTNER
to deliver insights and help you build an

EFFICIENT INTERCONNECTED
TOMORROW
Phone: +603 2027 4767
REGISTER Email: roohi.taragi@eminggulf.com
TODAY Website: http://bit.ly/1w9lcG7
LINING TECHNOLOGY

authors also expect that steel bolts will of segmental linings and TBM performance turning, marking, and craneage. In this area
become less and less common. Push-fit is subject to quality of workmanship. automation is already developing in a
plastic dowels have already replaced steel Automation of the tunnelling operation has piecemeal way as automation of various
bolts on the circumferential joint in many the potential to remove operatives from the aspects becomes cost-effective, and this
parts of the world, and there are projects tunnel, while maintaining or improving process is likely to continue.
where guiding rods have been used in place quality and productivity.
of steel bolts on the longitudinal joint. Bolts The items required to fully automate the Quality control
are often included in designs simply tunnelling process are listed in Table 2. It is The automation of segment manufacture,
because they have always been used, interesting to note that the only technology transport and erection can also bring
without regard for whether they are actually
required[4]. However, resistance to the
removal of bolts will continue to be eroded Table 2: Components of tunnelling automation.
as more projects demonstrate that bolts are Excavation and advance Either from a TBM operators cabin located at the surface or completely automated
not required in normal circumstances. Segment erection Robotic controlled erector arm. All segment connectors are pre-installed push fit type.
Where tension across the joint must be Segment identification Bar code or more durable cast in system to uniquely identify each segment.
resisted bolts could continue to be required. Grouting Automated two component type grout fed by pipes on self-extending system.
However, installing bolts can add time to TBM consumables supply Either by robotic processing of cars delivered by automated train or by self-extending supply lines
Segment supply Automated trains with robotically controlled transfer station to place segments on segment feeder.
the erection process and providing long
Muck handling Self-extending conveyors.
term protection against corrosion is difficult.
Survey for TBM guidance Access for survey could be targeted mainly at routine maintenance
The authors have been working with one Routine maintenance Systems designed for lower levels of routine maintenance to limit personnel entry into tunnel
supplier to develop a push-fit plastic
alternative to bolts in order to provide
alternatives for some current projects, and that has not been implemented successfully benefits to quality control/quality assurance.
have some promising ideas. Other suppliers is the offloading of TBM consumables, and In normal practice each segment is
are also looking to develop systems. even this appears straightforward when equipped with a unique identifier, often
Therefore in ten years time it appears likely compared to systems employed in other simply a number sprayed onto a segment.
that there will be no need to use ferrous industries. This number is usually manually entered
elements of any kind to connect the Automation requires a lot of up-front into a database, and then tied to data such
segments. investment, but saves in the cost of as date cast, batch number, etc. However
operatives, so the cost-benefit is likely to be with an automated system this information
Grouting and sealing most apparent in long tunnels in locations could be automatically entered. A bar code
The recent and welcome adoption of cast-in could be affixed to the segment
gaskets is likely to turn into widespread immediately upon demoulding.
usage in the next ten years. While it may be Automation requires Alternatively, a barcode or other binary
difficult to see any big developments in the system could be cast into the segment.
seals incorporated into the segments, the a lot of up-front If all handling steps could record the
first line of defence is usually the grouting. investment, but specific item that they were handling then a
Tail shield grouting is very widely adopted, database could be created which linked
but still needs very careful control to ensure saves in the cost of records of all inspection and test steps. If
effective filling of the annulus. Poor filling operatives, so the such steps were recorded electronically in
can easily occur and requires significant wireless devices (such as tablets) then paper
secondary grouting to mitigate if detected cost-benefit is likely entry could be almost eliminated and fail
at all. Even where tail shield grouting
operation is good some check grouting is
to be most apparent safes used that prevent unchecked
segments proceeding to the next stage.
required to verify the continued in long tunnels in Much of this technology already exists and
performance. Check and secondary has been applied to a few projects.
grouting activities require additional crews
locations where However, tying the quality control system
handling highly alkaline materials, and can wages are high. into an automated segment delivery and
often slow progress of the TBM. erection system could allow the full history
Therefore if an alternative can be found of the segment to be recorded, from mould
that provides an assured filling of the void where wages are high. However, the system cleaning and preparation through to the
(such as a low strength expandable must have a high degree of reliability. time, location, and orientation of
material cast into the outside of the Downtime will increase if the operatives placement. This could free up time for the
segments, for example), then these required to rectify the problem are not actual quality control activities that require
activities and the associated risks of already on site, so the incidence of failures human inspection, improving quality and
material handling could be eliminated. A must be minimised if an automated system freeing up staff for more productive
void filling material that is expanded could is to achieve performance that is as good as activities.
also be useful in squeezing ground if the or better than current practice.
material could absorb inward movements In addition to the tunnel, there are also Intelligent segments
without overloading the lining. potential benefits to automating other parts Another area that may see significant
of the segment manufacture and supply changes over the coming years is intelligent
Automation process. Automation at pit top could easily segments: segments that monitor their
The drive to improve both productivity and tie in with the automatic trains operating in performance over their life span or some
tunnel safety must be maintained if we are the tunnel. Meanwhile there are many portion of it. A recently developed small
to push the industry forward. The gold aspects of the manufacturing plant that can device known as Utterberry can locate itself
standard for safety is to remove operatives be automated such as reinforcement relative to other devices very accurately and
from the work area. Meanwhile the quality welding, automatic batching, segment communicate wirelessly, and has already

TUNNELLING JOURNAL 35
LINING TECHNOLOGY

been deployed successfully in an


underground context[5].
Figure 6: Internal lining/gasket detail on Herrenknecht combi-segments
Paired with the development of other
technologies such distributed glass fibre
monitoring it is entirely feasible that at least
some segments in the tunnel may be
intelligent able to assess their
performance against what they were
designed for. Over the next decade it is
reasonable to assume that the cost of such
systems will come down significantly. The
potential benefits of would be many, but
one that the authors consider most
significant is for critical infrastructure where
creating downtime for inspection and
maintenance is problematic, as the
additional cost of the system could be many
times less than the cost of just a single
inspection.

Special circumstances
As well as he more routine segment
designs, there will continue to be one-off
designs that fulfil a particular need. These
have the potential to provide new
technologies that push the industry in
different directions. A few such
circumstances are discussed below.

One-pass pressurised tunnels


The traditional approach to pressurised projects in both Switzerland and Japan. This have been sought is in sewer tunnels,
tunnels is to use the segmental lining to solution has much merit insofar as it keeps where protection from the aggressive
provide a primary lining that resists external the concrete and the gaskets between the environment is required. Systems with an
ground and water loads during segments in compression under tensile integral internal plastic protection have
construction, and then to provide a service loads, thereby enhancing durability been developed. Such solutions may use
secondary lining (of reinforced concrete, (by minimising cracking) and minimising welding or gaskets to ensure continuity of
steel or other material) that provides the leakage. However, the cable is hard to the protection (Figure 6). However, a
resistance to the tensile hoop forces assure for the 100 year design life often frequent objection to the solution is that
generated by the internal pressure. If this required, and it can be difficult to install. the plastic can mask the deterioration of
can be achieved in a one-pass system then However, if a robust and cost effective the concrete behind, and significant levels
the cost and schedule benefits are self- solution to these issues can be found then of degradation may be required before it is
evident. it is likely that such solutions will spotted. This is less of an issue for a grout
One solution is to thread post-tensioning proliferate. annulus or secondary lining as they are
cables through ducts specially cast into the A second solution is to design the lining easier to repair than the primary lining that
segments, and then use the cables to to take the tension. This can be achieved by provides grout support. If a solution to this
compress the entire ring, as used in recent systems that span the longitudinal joint, objection can be found then integrally
such as bolts, or protected one-pass solutions could become
across the the preferred option.
Figure 5: Dowels transferring tension loads around a joint
circumferential joint
by dowels (Figure 5). Heat recovery
A system has also Another area that is likely to receive
been developed in increased attention is to enhance return on
Japan where a the capital investment by utilising the tunnel
profiled for a secondary use.
circumferential joint One such idea that has been proposed is
interlocks with the to recover energy through a series of pipes
segments in the cast into the tunnel lining. These are inter-
adjacent ring, connected to form a continuous circuit
allowing the tension through each ring of the lining which are
to be transferred then in turn fed into a main to circulate
1. Opening created by segments between rings in the water to a surface heat exchanger. This can
moving apart circumferentially same manner as be used as a very effective heat sink or
2. Segments moving apart circumferentially dowels. source of heat, providing a very economic
resisted by two dowels on each joint on both sides source of energy for heating and cooling.
Integral protection The energy that is able to be captured can
3. Path of tensile forces across opening
Another area where be quite staggering.
one-pass solutions The authors are convinced that there

36 TUNNELLING JOURNAL
LINING TECHNOLOGY

could be other beneficial applications that Intelligent segments monitor tunnel benefits to the industry and society as a
could be applied if entrepreneurs\inventors performance remotely, reducing the whole. This will require commitment to
were given the challenge. requirement for inspection and communication and genuine problem
maintenance solving from clients, contractors, and
Conclusions Void filling assured by an expanding designers alike. Surely we can manage that?
Precast concrete segmental tunnel linings material cast into the outside face of the
may appear to be a mature technology that segment that actuates on exit from the ACKNOWLEDGEMENTS
has changed little over the years. However, tail shield
in their previous article[1] the authors showed Database that allows the QC and as-built The authors would like to acknowledge the
how the technology has changed records of every segment on the job to be following people for their contributions to this
significantly over the last 20 years. In this easily called up. article: Chris Smith of CRS consultants,
article the authors have shown how there is This may appear a panacea, but the authors Rolando Justa Camara, Director of Tunnels
plenty of scope for the technology to are convinced that if we work together as and Marine Works Department of Acciona
continue to develop over the next decade an industry it can become a reality that Infraestructuras SA.
and beyond. In some areas, such as offers cost, safety, and environmental
geopolymer concrete and non-ferrous
linings, the authors have been able to REFERENCES
pinpoint what the solutions might look like.
In others the authors have merely been able 1. Harding and Chappell, 2014. State of the art precast linings. North American Tunneling Journal,
to highlight the problems and the benefits Oct/Nov issue, TGS Media, Tunbridge Wells, UK
of solving them. However, if the authors 2. Wimpenny, D; Chappell, M; 2013. Fiber-reinforced geopolymer concretean innovative material
were asked what the ideal lining might look for tunnel segments. In Rapid Excavation and Tunneling Conference. Washington DC, USA, 23-26
like in ten years time they would offer the Jun 2013. Englewood, Colorado, USA: Society for Mining, Metallurgy, and Exploration. 810-819.
following: 3. Craig, R N; Muir-Wood, A M; 978. A Review of Tunnel Lining Practice in the United Kingdom; TRRL
Geopolymer concrete lining with macro- Supplementary Report 335, Transport and Road Research Laboratory, Crowthorne, UK
synthetic fibre reinforcement. 4. Harding and Chappell, 2014. Myth and Reality: Bolts in Modern Concrete Segmental Tunnel
Non-ferrous connections on longitudinal Linings. North American Tunnelling Conference, Los Angeles, 22-25 June 2014, Englewood,
and radial joints Colorado, USA: Society for Mining, Metallurgy, and Exploration. pp66-75
Hexagonal segments to allow continuous 5. UtterBerry sensor scoops award for industry. 2014. http://www-
mining smartinfrastructure.eng.cam.ac.uk/20141022-UtterBerry-innovation-award
Ability to resist internal tension loading

Scan to find out more


THE SYNTHETIC FIBRE EXPE
EXPERTS
ERTS
Get total synthetic fibre reinf o
orcement
reinforcement Concrrete.
solutions with Elasto Plastic Concrete.
Expert Shotcre
Shotcrete
ete and Concrete Advice
Expert Synthet
Synthetic
ic Fibre Reinf
Reinforcement
orcement Advice
Eng
Engineered
ineered and
and Finite Element Anal
Analysis
ysis Designs

Used in the Spra


Sprayed
yed Lining of Ryfast Subsea Tunnel
Tunnell - The longest subsea
tunnel in the world

FEEA Anal
FEA ysis and Life of Asset Testing
Analysis Testing
e

EPCS BARCHIP FIBRE BEN


BENEFITS
EFITS
Increased Dura
Durability
b - Corrosion Free
bility
Ductility
Increased Ducti lity Usedd in Cast In-Situ Linings Used in Segmental
S Linings
Increased Post Crack Flexural CaCapacity
pacity (toughness)
Up to 80% redu
reduction
uction in transport, handling and stora
storage
ge cos
costs
sts EPC are the Gold Sponsors ffor
or WTC 2015.
20115.
15 Contact uss to arrange
a priva te presentation
private presentatioon during the conference.
Reduced Ma teriial and La
Material bour Costs
Labour europe@elastoplastic.com
e
Increased safetyy on site
70% reduction in carbon ffootprint
ootprint vs steel reinforcement
reinforcement
Reduces mainte enance of equipment
maintenance

WHEN PERFORMA
PERFORMANCE
NCE MATTERS, CHOOSE ELASTO PLASTIC
PLASTTIC CONCRETE

TUNNELLING JOURNAL 37
LINING TECHNOLOGY

3, 6 and 9 oclock positions in Figure 1.

Segmental But if they were rotated 45, then the


joints would have no effect. When a ring
has 4 joints, the orientation of the joints
makes a huge difference, but this effect
decreases as the number of joints
increases. Hefny & Chua (2006) compared

lining joints Muir Woods equation to analyses using


continuum finite element models and
found that as the number of joints
increases beyond 6 joints, the influence of
joint orientation becomes negligible.
Muir Woods equation also assumes
In this article, Dr Benot Jones, Director of that an individual rings deformation is
unimpeded by the adjacent rings, which
the Tunnelling and Underground Space would only be the case if the
MSc at the University of Warwick, UK, circumferential joint had no shear keys,
dowels or friction, or if the radial joints
looks at recent developments in the design were all aligned down the length of the
tunnel (Klappers et al., 2006). Usual
of segmental lining joints. practice, however, is to stagger joints and
to encourage shear resistance, so this
THERE HAVE BEEN SIGNIFICANT as a separate check from the service loads. assumption is unrealistic.
ADVANCES in our understanding of But recent studies have found that Another problem with continuum
segmental lining behaviour in the last 15 ringbuilding and jacking loads remain in analytical solutions is that the smearing of
years from instrumented rings in actual the lining permanently.
tunnels, full scale or reduced scale Virtually all the cracking and damage to
laboratory tests and 3D numerical segmental linings occurs during
Another problem
modelling. This article will attempt to construction. Once the rings are in place with continuum
summarise this work, with particular and the grout has hardened, it is rare for
reference to the behaviour of the joints in them to experience any further distress. analytical solutions
a segmental lining.
Segmental tunnel linings have
This should indicate to us that although
we are probably quite good at designing
is that the smearing
traditionally been designed in two for the earth and water pressures in of the effect of the
dimensions using quite simple models. For service, the worst design loads occur
instance, the International Tunnelling during construction and we need to
joints allows
Associations Working Group No.2 Report improve our methods of estimating them. calculation of
in 2000 (ITA, 2000) recommended the use
of analytical solutions, such as the Curtis- Introduction previous state of the art average bending
Muir Wood solution (Curtis, 1974; Muir circa 2000 moments, but in
Wood, 1975), or bedded beam models, In the case of the continuum analytical
where each segment is modelled by a 1D solutions, which are referred to in ITA reality, bending
beam element and the ground is modelled (2000) as the elastic equation method,
by springs. In addition, simple methods the material properties of the lining and
moments near to the
were used to estimate construction loads the ground are assumed elastic and the joints will have a
due to handling, storage, ringbuilding and effect of joints is smeared by reducing
jacking forces, and these were performed the moment of inertia of the whole lining. different value
The boundary conditions are shown in (usually higher) than
Figure 1.
Figure 1: Curtis-Muir Wood solution Muir Wood (1975) proposed the bending moments
boundary conditions following equation to reduce the moment
of inertia of a ring to take account of
mid-segment and
v
joints: will depend on the
joint geometry, bolt
details, packer and
This smears the effect of joints by
reducing the moment of inertia of the gasket.
whole ring. The equation is based on the
h h
assumption that there is no resistance to the effect of the joints allows calculation
r0
rotation at the joints, except that provided of average bending moments, but in
by ground reaction to the rings ellipsoidal reality, bending moments near to the
t deformation. The equation is only valid if joints will have a different value (usually
there are more than 4 joints. In reality a higher) than bending moments mid-
ring can deform with 4 joints if the joints segment and will depend on the joint
v
are aligned with the principal stress geometry, bolt details, packer and gasket.
directions in the ground, i.e. joints at 12, One way to fudge this is to assume a

38 TUNNELLING JOURNAL
LINING TECHNOLOGY

Restraint from the shield, and in


Figure 2: From left to right: aligned radial joints, staggered radial joints, particular the tailseal brushes
monolithic rings (from Fei et al., 2014). What happens when radial joints are not
parallel to the axis of the tunnel, e.g.
when trapezoidal or hexagonal segments
are used.
In this article I will discuss staggered radial
joints, packers, joint geometry, rotation
and misalignment of joints. Next issue I will
discuss jacking forces, grout pressures and
longitudinal effects.

Staggering of radial joints


Staggering the radial joints has the effect
of reducing deformations and increasing
bending stiffness of the rings. Fei et al.
(2014) used small scale physical models
(Figure 2) to show that by staggering the
joints an overall stiffness is achieved that is
Figure 3: Effect of ignoring circumferential joint shear resistance ('uncoupled',
somewhere between that of aligned radial
left) and modelling circumferential joint shear resistance (coupled, right) (from
joints and that of monolithic rings (with no
Klappers et al., 2006)
radial joints).
By increasing the circumferential joint bolt
forces in their model, Fei et al. (2014) also
showed that a higher longitudinal axial force

Figure 5: Behaviour of elastomeric


and bituminous packers - 3 loading
cycles under simple compression
(from Cavalaro & Aguado, 2012)

(a) Line 9 in Barcelona - Rubber


21
Normal stress (MPa)

18 Load cycle 1
15 Load cycle 2
Load cycle 3
12
9
joint rotation based on the maximum 6
specified ovalisation and then to use the Figure 4: Eccentricity of hoop thrust 3
joint geometry and packer properties to caused by joint rotation 0
calculate the eccentricity of the hoop force 0 20 40 60 80
Strain (mm/m)
and hence a bending moment. The
designer can then use the greater of the (b) Line 9 in Barcelona - Bitumenous
Resultant 21
average and this local value for design, Joint
Normal stress (MPa)

Intrados hoop force Extrados 18 Load cycle 1


and this approach should be conservative. contact
pressure 15 Load cycle 2
From experience I know that this approach Load cycle 3
12
is not commonplace and often only the
9
average values are used for design. Joint
Packer rotation 6
When a bedded beam model is used, the
3
radial joints may be modelled by rotational
0
hinges, which is a slight improvement on Eccentricity
0 45 90 135 180 225 270
the continuum analytical solutions. If a Strain (mm/m)
finite element or frame analysis program is
used, then these hinges can be assigned a
rotational stiffness. However, knowing them in a very simplistic way (Blom et al., across the circumferential joints increases
what this rotational stiffness should be is 1999; Molins & Arnau, 2011): bending rigidity. This is illustrated by the
not straightforward. De Waal (2000) Staggering of joints in adjacent rings exaggerated deformed mesh plots from a
showed that the results will always be Packing material in the joints 3D numerical analysis by Klappers et al.
between the two limiting situations of a Grout pressure and grout hardening (2006), showing how coupling of rings by
monolithic ring with no joints and a ring The type of joints and their rotational introducing longitudinal axial force and
with free (or pin) joints. Lee et al. (2001) stiffness shear resistance in the circumferential joint
estimated that it is between 1/10 and 1/4 Redistribution of moments via shear harmonises deformations. This effect was
of the segment stiffness. stress across the circumferential joint to found to occur even at quite low values of
The bedded beam models and analytical adjacent rings longitudinal axial force, so it is likely that
solutions, prevalent circa 2000, usually The effect of longitudinal compression in even residual axial forces left behind by the
ignored the following factors or dealt with the tunnel caused by the TBM jacks TBM shove rams would be sufficient.

TUNNELLING JOURNAL 39
LINING TECHNOLOGY

Joint geometry and packers


In reality, bending moments at the joints
Joint geometry and packer properties
depend on the geometry of the joint and are crucial to the design of a segmental
the properties of any packer. As joints
rotate, the line of thrust across the joint lining, because the eccentricity of the
moves and this eccentricity of the thrust
transfers moment to the adjacent segment
hoop force across the joint determines
(Figure 4). The moment is equal to the the bending moment induced, the
hoop force multiplied by the eccentricity.
In addition, as eccentricity increases and
bursting stress and the shear capacity.
the hoop force gets closer to the edge, the
shearing resistance of the corner reduces tests are shown in Figure 5. The first Conclusions
as the potential shear plane reduces in loading cycle also shows a much softer Virtually all the cracking and damage to
length. This could result in damage to the response this is known as the Mullins segmental linings occurs during
edges of the joints. If this occurs on the effect. construction. Once the rings are in place
Sometimes radial joints are designed and the grout has hardened, it is rare for
with curved surfaces, and in theory curved them to experience any further distress.
Figure 6: Effect of misalignment on joints have a lower rotational stiffness This should indicate to us that although
eccentricity than flat joints. This is because when flat we are probably quite good at designing
joint surfaces rotate relative to each other, for the earth and water pressures in
they will quickly generate a larger service, the worst design loads occur
eccentricity by tending to hinge about the during construction and we need to
Resultant
Intrados hoop force Extrados edge of the contact area. As curved joints improve our methods of estimating them.
rotate, the line of thrust stays closer to the Continuum analytical solutions smear
centreline of the segment. Another feature the effect of joints and therefore provide
is that as flat joints in a ring rotate, the average bending moments. In reality,
Misalignment Eccentricity perimeter of the ring increases. As far as I bending moments vary a lot within each
e = /2 know, no-one has researched this effect, segment.
but it should be expected to slightly Where staggered radial joints are used,
increase the hoop force. If curved joints it is important to model more than one
have a radius approximately equal to one ring. In the simplest possible model, 3
half the arc length of a segment, then the rings need to be modelled in 3D.
perimeter does not change. Joint geometry and packer properties
intrados, it will require repair. If a shear Eccentricity in radial joints is also caused are crucial to the design of a segmental
failure occurs on the extrados it cannot be by lipping, where segments are misaligned lining, because the eccentricity of the
repaired, and it may also compromise the and have a step between them. In this hoop force across the joint determines the
watertightness of the gasket. Therefore, case the eccentricity is equal to half the bending moment induced, the bursting
designing to minimise eccentricity is misalignment, as shown in Figure 6. stress and the shear capacity.
important.
The properties of the packer have a big REFERENCES
influence on the eccentricity of the hoop
force. A packer that is too thin or too Blom, C.B.M., van der Horst, E.J. & Jovanovic, P.S. (1999). Three-dimensional structural analyses of the
compressible will result in a concrete to shield-driven green heart tunnel of the high-speed line south. Tunnelling and Underground Space
concrete contact and a high stress Technology 14 (2), 217224.
concentration. A packer that is too stiff Cavalaro, S. H. P. & Aguado, A. (2012). Packer behavior under simple and coupled stresses. Tunnelling
will also generate a large eccentricity as and Underground Space Technology 28, 159173.
stress is mobilised at the edge of the Curtis, D. J. (1974). Visco-elastic tunnel analysis. Tunnels & Tunnelling, November, 38-39.
packer first. Understanding the stress- De Waal (1999). R.G.A. (2000). Steel Fibre Reinforced Tunnel Segments for the Application in Shield
strain behaviour of a packer and how it Driven Tunnel Linings. PhD Thesis. Technische Universiteit Delft.
interacts with joint rotation is absolutely Fei, Y., Chang-fei, G., Hai-dong, S., Yan-peng, L., Yong-xu, X. & Zhuo, Z. (2014). Model test study on
essential. effective ratio of segment transverse bending rigidity of shield tunnel. Tunnelling and Underground
Cavalaro & Aguado (2012) performed Space Technology 41, 193205.
simple compression and simultaneous Hefny, A. M. & Chua, H. - C. (2006). An investigation into the behaviour of jointed tunnel lining.
compression and shear tests on Proceedings of the ITA-AITES 2006 World Tunnel Congress Safety in the Underground Space, Seoul,
elastomeric and bituminous packers for Korea, 2227 April 2006.
several tunnelling projects in Spain, testing Klappers, C., Grbl, F., Ostermeier, B. (2006). Structural analyses of segmental lining coupled beam
the packer between both concrete blocks and spring analyses versus 3D-FEM calculations with shell elements. Proceedings of the ITA-AITES
and steel plates. Using steel plates resulted 2006 World Tunnel Congress Safety in the Underground Space, Seoul, Korea, 2227 April 2006.
in a more repeatable test, because even ITA (2000). Guidelines for the design of shield tunnel lining. Tunnelling & Underground Space
concrete cast to tight tolerances has small Technology 15, No.3, 303-331.
asperities that can cause stress Lee, K.M., Ge, X.W. (2001). The equivalence of a jointed shield-driven tunnel lining to a continuous
concentrations. Bituminous packers were ring structure. Canadian Geotechnical Journal 38, 461483.
found to have a softer response than Molins, C. & Arnau, O. (2011). Experimental and analytical study of the structural response of
elastomeric packers, but both have an segmental tunnel linings based on an in situ loading test. Part 1: Test configuration and execution.
exponential behaviour; they become stiffer Tunnelling and Underground Space Technology 26, 764777.
as strain increases, due to densification Muir Wood, A. M. (1975). The circular tunnel in elastic ground. Gotechnique 25, No.1, 115-117.
(Cavalaro & Aguado, 2012). Two of their

40 TUNNELLING JOURNAL
ITA CROATIA
Croatian Association for
ASSOCIATION
INTERNATIONALE DES TUNNELS
ET DE LESPACE SOUTERRAIN
ITA
INTERNATIONAL TUNNELLING
Tunnels and Underground
Structures AITES AND UNDERGROUND SPACE
ASSOCIATION

41st General Assembly and Congress of


International Tunnelling and Underground
Space Association ITA-AITES

SEE
TUNNEL
PROMOTING TUNNELLING IN SEE REGION
LACROMA VALAMAR CONGRESS CENTER MAY 22-28,2015
DUBROVNIK, CROATIA

www.wtc15.com
MACRO-SYNTHETICS

In-service performance
of Macro Synthetic
FRC in tunnel linings Left: The North Strathfield Rail Underpass
tunnel in Sydney, Australia, incorporated a
single pass macro-synthetic fibre reinforced
permanent sprayed concrete lining[3].

considerations with the aim of summarising


the latest research and industry thinking as well
as presenting instances where MSFRC will
deliver a distinct advantage to the finished
product.

Durability
The durability of a tunnel concrete lining
encompasses a number of factors including the
permeability of the concrete, concrete strength,
reinforcement and control of cracks. The
durability of the concrete matrix in FRC is
affected by the same parameters governing
R. Winterberg, G. Sedgman of Elasto Plastic plain concrete when subject to the exposure
conditions typical of an underground
Concrete state the case for the use of Macro environment. When macro-synthetic fibres are
Synthetic Fibres in tunnel linings. used in concrete (in the absence of steel bars),
there is no need to be concerned about
chloride ion penetration, carbonation, and to a
lesser degree, water impermeability, since there
MACRO-SYNTHETIC FIBRE REINFORCED fibre reinforcement meets the strict is no steel within the concrete which could be
CONCRETE or shotcrete (MSFRC or MSFRS) is performance criteria. This is a consequence of subject to corrosion. This frees the designer
a technology that is becoming an accepted the highly performance-based nature of the from the difficulties of trying to satisfy multiple
form of reinforcement in the construction industry in which engineers constantly monitor performance requirements related to corrosion
community and is seen by many design lining behaviour and adapt design and resistance thereby allowing greater flexibility in
engineers as offering a viable alternative to construction methods to achieve improvements design. The designer can therefore focus on
steel fibre and steel bar reinforcement in in outcomes. This research combined with a strength gain, shrinkage, sulphate resistance,
applications such as tunnel linings. The number of major tunnel lining projects recently and post-crack performance without the
technology is now common place in completed using macro synthetic fibre complications of trying to satisfy other
applications such as shotcrete for primary and reinforcement sees the future of this type of parameters such as crack width control, which
secondary ground support in both mining and reinforcement looking extremely bright. largely governs traditional design approaches
civil tunnel applications. For example it has For civil tunnel lining applications there are a for the sake of protecting the incorporated
become the standard form of reinforcement in number of factors design engineers must steel against corrosion.
the Australian mining industry, where 2014 consider when determining which
marked the end of steel fibre reinforcement reinforcement product can meet the design Corrosion
use in shotcrete[1]. Additionally, an increasing performance criteria. These include structural If steel bars or fibres are included within a
number of tunnels are adopting permanent capacity, durability, corrosion, crack width, tunnel lining, the mix design becomes more
sprayed concrete linings using macro synthetic creep and embrittlement to name a few. It is challenging and compromises must be made
fibres, examples of which include the A3 always important for a designer and the client to satisfy concerns over durability. Chloride ion
Hindhead tunnel near Guildford in the UK and to understand the benefits of adding any type penetration and carbonation depth need to be
the North Strathfield Rail Underpass in Sydney, of reinforcement to the concrete - in order to considered thereby restricting the design of the
Australia[2,3]. assess value for money. What are the benefits mix. Maximum allowable crack widths are
Applications such as permanent tunnel in terms of durability or extended asset life much smaller when using steel bars or steel
linings have required further research and because of the use of macro synthetic fibre? fibres since cracks, should they occur, act as
investigation to confirm that macro synthetic This article examines a number of these key points of rapid salt ingress to the

42 TUNNELLING JOURNAL
MACRO-SYNTHETICS

Left: Spraying concrete, but is also related to the elastic


of MSFRS at modulus and composition of the paste. For this
the Helsinki reason, satisfactory performance at early ages
West Metro (around 28 days) is not a guarantee of
Extension acceptable performance at late ages for steel
project FRC. The performance of steel FRC at crack
widths in excess of 1.0mm can fall by as much
Below: Macro- as 50% compared to the optimum exhibited at
synthetic fibre early ages, thus a performance reduction factor
reinforced cast should be applied to the long-term flexural
in situ in the resistance of steel FRC[5,12]
final lining of Macro-synthetic FRC is largely unaffected by
the Oliola this phenomenon since changes in paste
water tunnel, hardness make little difference to the
Spain[9]. behaviour of the fibre within the composite
beyond the first few days of
reinforcement. Maximum acceptable crack hardening. The performance of
widths are about 0.15mm for steel bar macro-synthetic FRC evident at 28
reinforcement, and recent in-field tests by days can therefore be relied upon
Kaufmann[4] and Bernard[5], supported by earlier to be retained with age. Thus,
research by Nordstrom[6,7], all indicate a designers can be more confident
maximum acceptable crack width of only about the long-term retention of
0.10mm for steel FRC. This places very post-crack performance.
stringent requirements on crack control when
steel reinforcement is used, especially for steel Crack width control
fibres since crack width control is much more An investigation into the potential
difficult and unpredictable for steel fibres than use of BarChip macro-synthetic
for steel bar reinforcement. fibres was undertaken to
In contrast, crack widths are not a concern determine whether these fibres
when macro-synthetic FRC is used since there is were effective in reducing mean
then no corrodible material present within the crack widths generated in
lining. Crack width limits are therefore conventionally reinforced concrete
governed by other considerations, such as members as a result of flexural
water-tightness. However, if significant in-plane loading[13]. Use of macro-synthetic
compressive loads are present in the lining designs often contain large proportions of fibres to reduce maximum crack widths in
(which is almost always the case) flexural cracks pozzolanic binders, which in turn can show reinforced concrete flexural members subject to
will not penetrate through more than a small significant post-hardening of the concrete with aggressive environmental exposure is more
fraction of the total lining thickness so water age. This leads to embrittlement of the fibre rational than the use of steel fibres because the
ingress to the tunnel is unlikely to occur concrete matrix, which is responsible for post- latter are more sensitive to the corrosive effects
through unplanned cracks. crack performance loss when using steel fibres. of environmental exposure at cracks. The fibre
Examples of where corrosion has been seen was an experimental variant of a standard
as a potential problem are the subsea tunnels Embrittlement of FRC BarChip fibre that has been developed for
in Norway and Finland. Research on durability Embrittlement of concrete or shotcrete with crack width control purposes.
in these aggressive environments, due to the age due to post-hardening and its detrimental In this first part of the research, the focus
saline water peculating through the rock to the effect on the post-crack performance of steel was on the effect of the presence of special
tunnel lining, has brought about a complete FRC, has been known for nearly 20 years. macro-synthetic fibres on the cracking
ban on steel fibre in these constructions and Numerous investigations have indicated that development and the developing crack
the use of macro synthetic fibres for all aging can lead to a significant loss of post- spacings. Through a set of experimental trials
shotcrete reinforcement[8]. crack performance for steel FRC[10,11,12]. involving 32 beams reinforced with normal
The Ryfast Subsea tunnel, currently under The change in behaviour with age is due to a levels of steel bar reinforcement, and between
construction (the longest subsea tunnel in the change from a high-energy pull-out mode of 0 and 6kg/m3 of BarChip macro-synthetic crack
world) near Stavanger, is a current example of post-crack fibre behaviour to a brittle low- width control fibres, it has been demonstrated
this as is the Helsinki West Metro Extension. energy rupture mode. This leads to rupturing that these fibres are indeed capable of
Another example of the successful of steel fibres at crack widths in excess of the reducing mean crack spacings by up to 30%
application of macro-synthetic fibres in this elongation capacity of the fibre. Thus, the compared to plain reinforced concrete
regard is the 4.47km Oliola water tunnel in performance degradation primarily affects members.
North Eastern Spain, which has now been in resistance to late-age load conditions such as This result is useful in the field because,
service for 5 years and was constructed using a nearby underground construction, seismic unlike steel fibres, macro-synthetic fibres are
BarChip fibre reinforced secondary concrete loading, or changes in groundwater pressure. entirely immune to the effects of corrosion and
lining to eliminate the risk of corrosion in this Extensive research into post-crack behaviour thus their potential location close to the surface
environment[9]. of steel fibres, strand, and bar in concrete of a member (in a crack or otherwise) will not
Most concrete or shotcrete mix designs focus suggests that rupture is caused by excessively compromise durability. Inclusion of up to
on durability and corrosion protection to high friction between the steel and 6kg/m3 of BarChip crack width control fibres
provide high resistance against chemical attack cementitious paste that is more closely related may therefore prove a useful tool for reducing
over their service life, which in tunnelling is to the hardness of the binder paste. Paste maximum crack widths in RC members in
typically 120 years. To achieve this, the mix hardness increases with the strength of the aggressive environments where maximum

TUNNELLING JOURNAL 43
MACRO-SYNTHETICS

acceptable crack widths of about 0.10- fibres in respect of creep and the associated The physical properties of different macro-
0.15mm must be achieved. consequences for crack width development synthetic fibres vary greatly and for the majority
The reduced crack widths will offer higher with time under sustained flexural loads. To of the research and the completed projects
durability and therefore longer asset life and address these concerns, a method to presented in this article only highly engineered
less maintenance over the design life. Malaga determine the effects of creep and shrinkage macro synthetic fibres with a tensile strength of
on the time-dependent > 600MPa and a Modulus of Elasticity of
behaviour of cracked, >10GPa has been used. These fibre
macro-synthetic fibre characteristics are required to achieve and
reinforced concrete cross- maintain the presented performance
sections containing outcomes.
conventional bar
reinforcement subjected to a Conclusions
sustained bending moment Highly engineered macro-synthetic fibres prove
and axial force has been to be effective in reducing crack widths in RC
developed[14]. The results of members and therefore significantly add to a
this analysis show that the tunnel linings durability.
inclusion of macro-synthetic The inherent isolated creep properties of
fibres in the concrete has macro-synthetic fibre reinforcement play a
only a minor effect on the subordinate role in the long-term performance
flexural strength of the of tunnel linings where compression forces
cross-section, but the fibres typically govern.
Above: Malaga Airport High Speed Rail segmental lining used a reduce time-dependent in- High-performance macro-synthetic fibre
combination of steel cage and macro-synthetic fibre reinforcement service deformations and reinforcement is ideal for aggressive exposure
significantly reduce conditions and guarantees durable
Airport High Speed Rail was a project which maximum crack widths when used in performance over the design life cycle without
benefited from this type of reinforcement. combination with conventional reinforcing suffering matrix embrittlement and
Macro synthetic fibre was used in combination bars. This research work will be presented at performance loss with age.
with the traditional reinforcement cage. The the World Tunnelling Congress (WTC 2015) in making it an ideal construction material
addition of macro-synthetic fibre was able to Dubrovnik, Croatia this year in May. for tunnel linings.
assist in keeping crack widths, which may have
been produced from either the TBM rams or in REFERENCE
service loads, much smaller than if there was
no fibre. This design reduced repair and [1] E. Stefan Bernard, Matthew J.K. Clements, Shotcrete: Engineering Developments, Bernard
maintenance costs and increased asset life in Stephen B. Duffield, and D. Rusty Morgan, 2014. (ed.), pp213-217, Swets & Zeitlinger, Lisse.
the long term. Development of macro-synthetic fibre reinforced [8] Hagelia, P. 2008, Deterioration mechanisms
shotcrete in Australia, 7th International and durability of sprayed concrete in Norwegian
Creep considerations Symposium on Sprayed Concrete Modern Use tunnels, Fifth International Symposium on
Creep has always been a question for designers of Wet Mix Sprayed Concrete for Underground Sprayed Concrete, Lillehammar, Norway, 21-24
as they see the material properties between Support Sandefjord, Norway, 16. 19. June April, pp180-197.
steel and macro synthetic fibre as very different. 2014 [9] Spains synthetic reinforcement, Tunnels and
However, in segmental linings hoop [2] Ireland, T.J., Stephenson, S., 2010. Design Tunnelling International, April 2009, pp 25-27
compression forces typically govern the and construction of a permanent shotcrete lining [10] Bjontegaard, O., Myren, S.A., Klemtsrud, K.,
occurring stresses and tensile stresses are The A3 Hindhead Project, UK, Shotcrete: More and Kompen, R., 2014. Fibre Reinforced Sprayed
minimal after installation and grouting to the Engineering Developments, Bernard (ed.), pp143- Concrete (FRSC): Energy Absorption Capacity
substrate. Potential cracks, which have 152 from 2 days age to One Year, Seventh
developed during hauling, handling and [3] Gonzalez, M., Kitson, M., Mares, D., Muir, B., International Symposium on Sprayed Concrete,
installation of the segments, or during TBM Nye, E., Schroeter, T., 2014. The North Strathfield Sandefjord, Norway, 16-19 June, pp 88-97.
propulsion, are expected to close over time due Rail Underpass Driven Tunnel Design and [11] Kaufmann, J.P., 2014. Durability
to the natural creep of concrete under high Construction, 15th Australian Tunnelling performance of fiber reinforced shotcrete in
compressive forces. The creep of the type of Conference 2014, Sydney, 17-19 September, pp aggressive environment, World Tunnelling
reinforcement plays a negligible role herein. 369-374. Congress 2014, (Ed. Negro, Cecilio and Bilfinger),
The particular requirement for long-term [4] Kaufmann, J. P., 2014. Durability performance Iguassu Falls Brazil, p279.
testing of macro-synthetic FRC is only necessary of fiber reinforced shotcrete in aggressive [12] Bernard, E.S., 2014. Age-dependent
when long-term tensile stress is expected to be environment, Proceedings of the World Tunnel Changes in Post-cracking Performance of Fibre-
imposed on a cracked section in service. This Congress 2014 Tunnels for a better Life. Foz do Reinforced Concrete for Tunnel Segments, 15th
almost never occurs in reality as the section is Iguau, Brazil. Australian Tunnelling Conference 2014, Sydney,
typically under compression due to high axial [5] Bernard, E.S. 2008. Embrittlement of Fiber 17-19 September, pp229-235.
forces from surrounding groundwater and Reinforced Shotcrete, Shotcrete, Vol. 10, No. 3, [13 Bernard, E.S., 2015. Investigation of Crack
earth pressure. In service, the tensile behaviour pp16-21, American Shotcrete Association Width Control Using Barchip Fibres in Reinforced
is not as significant as during production and [6] Nordstrm, E., 1999. Durability of steel fibre Concrete Beams, TSE Report 248, Penrith, NSW,
transient stages. If transitory tensile stresses are reinforced sprayed concrete with regard to Australia, January 2015
expected, then there is no need for long-term corrosion, Proceedings, 3rd Int. Symposium on [14] Gilbert, R. I. and Bernard, E. S., 2015. Time-
test data because macro-synthetic FRC Sprayed Concrete, Gol, Norway, 26-29 dependent Analysis of Macro-synthetic FRC
performs very similarly to steel FRC in the short September. Sections with Conventional Bar Reinforcement, (in
term. [7] Nordstrm, E., 2001. Durability of steel fibre press) World Tunnelling Congress (WTC 2015) in
However, concerns have been raised about reinforced shotcrete with regard to corrosion, Dubrovnik, Croatia, May 2015
the long-term performance of macro-synthetic

44 TUNNELLING JOURNAL
TJ_0215_ADS_045_revised_page.qxd:Feature 16/2/15 23:21 Page 45

HPC Products
Supplying Specialist Products to
Mining, Tunnelling and Industry

Alvenius Steel Pipe Systems ; Belloli Rockbolt Systems


CBE-APS Precast Concrete Moulds ; Cogemacoustic Tunnel Fans
Condat Lubricants, Greases and Oils ; LVC Knifegate Valves
Mat Hellas Ventilation Ducting
Metalliance Underground Vehicles
NFM Tunnel Boring Machines ; RBL-REI Conveyor Systems

World Class Tunnel Contact


Contact
Alan
KeithBozeat
Prebble+44
+44(0)
(0)1202
Fire Protection 587750
1202 587750
www.hpcproducts.com

Hunter Personnel
Promat are the worlds largest dedicated manufacturer of passive Recruiting For Your Industry
re protection materials and global leaders in the Fire Protection
of Tunnels, providing re protection solutions to many of the
worlds largest tunnel projects.  Specialists in Tunnelling and Infrastructure
Recruitment over the past 30 years
Since the 1960s Promat materials have protected more than
190 tunnels using PROMATECT boards. More than 1.4 million m2 of  Supplying personnel of all nationalities for
tunnel linings have been protected using our spray applied systems.
UK and International Projects
www.promat-tunnel.com
Contact
David Kellett +44 (0) 1202 298322
www.hunterpersonnel.com

TUNNELLING JOURNAL 45

Anda mungkin juga menyukai