A. S. ODEH
MEMBER AIME SOCONY MOBIL OIL CO., INC.
F. SELIG DALLAS, TEX.
I
t
where it is assumed that the q - t curve was divided into
Q= q(T) dT n equal time intervals each of 60t length.
o For a drill-stem test the rate of flow as a function of
and time is usually not known. The pressure as a function of
_ tJ-
t
q T () -
,' .;~c
4/,(t-T) d
time during the flow periods is known. With a reasonable
p, - P - 47rkh t - e (5) degree of accuracy, Eq. 9 could be written (see Appendix
of
T T
B) as
n-l
where Pi is the reservoir pressure at t = O.
t* ~ 2 [ "i,[(P'i+1 -- Pt.) (f'+l + t,)] ]
In the case of an infinite reservoir with the well located t - 1/2 _0 n 1 (12)
at r = 0, and if the well is flowed for time t and then
"i, (Pt, - Pi)
shut in for time 0, and if r" (the well radius) can be o
approximated by zero, and ignoring the effects of after- Po represents the pressure at the start of the first flow
production, the sand-face shut-in pressure at time t + 0 is period, i.e., at t = O. Pn is the pressure at the end of the
given by second flow period prior to shutting-in the well for the
_ ft [It+8 q (T ) - t+~T d
final pressure build-up, i.e., at tn.
Pi - P - 47rkh t + (J _ T e T
o APPLICATION
EXAMPLE 1
. :-- d'l Data
A production test was conducted on a well according
=--
tJ-
47rkh
I+ f
t
q(T)
(J - T
e - t+~-T d T
(6)
to the schedule shown in Table 1. After nine hours, the
well was shut in and the sand-face pressure was recorded,
as shown in Table 2. The problem is to calculate the
o
_ rw'<ptJ- c reservoir pressure and the average kh of the field.
where A-~
Solution
It is desirable to approximate Eq. 6, so as to put it 1':' as given by Eq. 11 is equal to
in a workable form. This can be done by introducing a
modified rate, q* = constant, and a modified time t*, 2(9 _ 478.5 X 1.5 + 319 X 4.5 + 159.5 X 7.5)~
such that the integration at the right-hand side of Eq. 6 478.5 + 319 + 159.5 3
can be carried out analytically. q* and t* have to be
= II hours.
chosen in such a way that
+
319 X 3 + 159.5 X 3) 24
~ q* A) (478.5 X 3
I
o
t
t +
q(T)
(J - T
e- t+':-T dT [
-
E' (
I - t* +0
q* (Eq. 10)
24 X 11
= 260.9 reservoir BID.
Extrapolation of the straight-line portion which is given
(7)
t* + 0
approximately by 2 > --0- ;;;, 1 (Fig. 1) gives an ini-
ao
where -Ei (-x) = Ie~v duo tial pressure of 3,000 psi.
x kh = 162.6q*tJ- = 97 md-ft where tJ- = 0.6 cp, and
By the proper expansion of the Ei functions and the 111
integral in Eq. 7, one arrives at (see Appendix A) 111is the slope of the straight line = 263 psi/cycle. For
162.6,M* t* + (J comparison, the same example was worked out using
Pi - P = kh log,o - ( J - (8) Horner's method, Fig. 1. It resulted in an initial pressure
where of 3,005 psi and a kh of 77 md-ft. A simulated case on
an R-C network electric analyzer resulted in an initial
pressure of 3,000 psi and a kh of 100 md-ft.
t* -- (9)
and TABLE I-SCHEDULE FOR CONDUCTING PRODUCTION TEST
~
Time Interval Average Production Rate Production per 3-Hour
q* = (10) (hours) (res. BID) Interval (res. bbl)
0-3 478.5 59.8
Eq. 8 holds only when both t and t* are less than 0, a 3-6 319.0 39.9
6-9 159.5 19.9
condition necessary for the validity of Eqs. A-4 and A-7
of Appendix A. This condition could be obtained easily TABLE 2-SAND-FACE PRESSURE
in drill-stem tests and short production tests. V is the Shut-in Time Pressure Shut in Time Pressure
volume of the fluid produced from time t = 0 until the (hours) ~ (hours) ~
well is shut in. Eqs. 8, 9 and 10 are given in practical 2 2812.5 11 2919
3 2838 13 2929.5
engineering units. 5 2872.5 15 2935
7 2895 17 2942
During a short production test, the rate of flow as a 9 2910
3000
'" 2000
iii
a.
!: 2900
w w
c:
::>
<I>
'"~ 1800
<I> <I>
W w
2800~
c:
a.
g: 1700
!
THE "r'" oJ.)oI. METHOD ,,- THE t*q* METHOD
,. HORNER'S METHOD 1600 t.l. - t IS THE SECOND FLOW
PERIOD TIME
2700L-----------~------~----~--~--~~~~~ [500!
I 10 10
MOGIFIED TIME + SHUT-IN TIME MODIFIED TIME + SHUT-IN TIME
SHUT-IN TIME SHUT-IN TIME
FIG. I-DETER;\ll],;ATION OF ORIGINAL RESERVOIR PRESSlJRE A"D FrG. 2-DE'l'EH:I'II],;ATION OF ORIGIl(AL RESERVOIR PHESSt:HE A"D
AVERAGE FLOW CAPACITy-ExAMPLE 1. AVERAGE FLOW CAPACITY-EXA~lPLE 2.
ACKNOWLEDGMENT
R. H. Barham, M. E. Brewer and W. H. Wilson ran the
a,~ - HA + t ~ T)q(T) dT + c/' (t~' + At':')
simulated case on the analyzer. The authors are grateful (A-9)
for their help. The authors would like also to thank the
ftr
management of Socony Mobil Oil Co., Inc., for permis- A'
a,~ (t~Tr+2A(t~T)+ 2 ] 1(T)dT
sion to publish this paper.
o
REFERENCES r:"
~q*
1. Horner, D. R.: "Pressure BuildUp in Wells", Proc., Third
[ -3 (A-IO)
f
Solids, Second Ed. (1959). t
3. Dolan, J. P., Einarsen, C. A. and Hill, G. A.: "Special Appli q*t':, = q(T)dT = V (A-ll )
cation of DrillStem Test Pressure Data", Trans., AIME
(1957) 210, 318. o
4. Johnston Testers, Inc.: Practical DrillStem Test Manual. Setting a, = 0 yields
5. Ammann, C. B.: "Case Histories of Analysis of Characteristics
of Reservoir Rock from Drill-Stem Tests", Jour. Pet. Tech.
(May, 1960) XII, No.5, 27.
AV + tV ~ J:q( T) T ciT = V;':' + A V, (A-12)
6. Zak, A. J., Jr. and Griffin, Phil, III: "Evaluating DST Data", or
Oil and Gas Jour. (April 15, April 29 and May 13, 1957).
APPENDIX A (A-13 )
DERrv ATION OF EQS. 8, 9 AND 10
If the production rate q( T) is plotted vs t, the teo-ordinate
The introduction of a modified production rate q':' and of the center of gravity, t" is given by
a modified time t* has to be performed in such a way
that the difference r~(T)TdT
6. ='ft q(T)
t+8~T
e,:o-TdT ~ q':' [Ei(-~)
8
t'=J-~-
oq(T)dT
, (A-14)
o
and we obtain the final form of the solution
~Ei(~~A
(':' + 8 )] (A-I)
t* = 2(t ~ t,), q':' =
V
7' (A-IS)
tends toward zero for large values of 8. We will write 6. The coefficient a3 can be expressed in the form
as a power series in 8-' in the form