COMMENTS
File:\/opt/scribd/conversion/tmp/scratch2718/36997697.doc
NEWMONT GHANA GOLD LIMITED
OPERATION SERVICES DEPARTMENT - AHAFO SITE
TABLE OF CONTENTS
1.0BACKGROUND ...................................................................................2
2.0SCOPE OF WORK...............................................................................2
3.0ENGINEERING DELIVERABLES ........................................................4
4.0ASSUMPTIONS ...................................................................................6
5.0PROJECT MILESTONES ....................................................................6
6.0ATTACHMENTS...................................................................................6
1
File:\/opt/scribd/conversion/tmp/scratch2718/36997697.doc
NEWMONT GHANA GOLD LIMITED
OPERATION SERVICES DEPARTMENT - AHAFO SITE
1.0 BACKGROUND
The project will be in two phases; Scope 1 and 2. This Scope of Works
specifically spells out details of Scope 1 which involves the design of a
facility to pump water from the boreholes into a ground seated water
storage tank (The water will be used to serve the fire hydrants and the fire
tender).
2
File:\/opt/scribd/conversion/tmp/scratch2718/36997697.doc
NEWMONT GHANA GOLD LIMITED
OPERATION SERVICES DEPARTMENT - AHAFO SITE
• Design a concrete pad for the ground seated water storage tank.
• Design a flow meter and the accessories between the borehole and
water storage tank.
• Design a steel pipe stand with its support and accessories for
discharging fire water into the fire tender.
3
File:\/opt/scribd/conversion/tmp/scratch2718/36997697.doc
NEWMONT GHANA GOLD LIMITED
OPERATION SERVICES DEPARTMENT - AHAFO SITE
• Design Report
The report must include the following items, but not limited to
5
File:\/opt/scribd/conversion/tmp/scratch2718/36997697.doc
NEWMONT GHANA GOLD LIMITED
OPERATION SERVICES DEPARTMENT - AHAFO SITE
4.0 ASSUMPTIONS
The following Project Milestone Dates are part of this Scope of Work:
Deliverable Deadline
Engineering Contract award Week 0 (W0)
Kick off meeting and site visit W1
Preliminary Engineering design W2
Detailed Engineering design & Report W5
Budget estimate, BOQ & Scope of Works W6
6.0 ATTACHMENTS
Attachment A
– Concept Drawings
– Specifications and Data Sheet
6
File:\/opt/scribd/conversion/tmp/scratch2718/36997697.doc
NEWMONT GHANA GOLD LIMITED
OPERATION SERVICES DEPARTMENT - AHAFO SITE
ATTACHMENT A
A.1.1 Drawings
7
File:\/opt/scribd/conversion/tmp/scratch2718/36997697.doc