Anda di halaman 1dari 69

Viaduct and bridge construction methods

adopted at MTR SIL(E) Contract 903

MTR SIL(E) 903 Viaduct Construction Team


28-8-2013

MTR Corporation
MTR CorporationLimited
Limited 2013/8/29
2013/8/29 Page11
Page
Content
1. About SIL(E) Contract 903

2. Viaduct Construction
2.1 Value Engineering for Viaduct
2.2 Viaduct construction by Pre-cast segmental method
2.3 Stakeholder Management

3. Aberdeen Channel Bridge (ACB) Construction


3.1 Value Engineering for Aberdeen Channel Bridge
3.2 Bridge construction by in-situ balance cantilever
3.3 Stakeholder Management

4. Q&A

MTR Corporation Limited 2013/8/29 Page 2


1. About SIL(E) Contract 903

MTR Corporation Limited 2013/8/29 Page 3


1. About SIL(E) Contract 903

ADM
Works Contract 901

Works Contract 902

WCH OCP

Works Contract 903


SOH
LET

Works Contract 904 Works Contract 907 / 908

MTR Corporation Limited 2013/8/29 Page 4


1. About SIL(E) Contract 903

Viaduct
Wong Chuk
Hang Station
Viaduct

Ocean Park
Nullah Works Station

Aberdeen Channel
Bridge

MTR Corporation Limited 2013/8/29 Page 5


1. About SIL(E) Contract 903

Ocean Park
Station

Viaduct B

Wong Chuk Ocean Park


Hang Station
Station

Viaduct C

MTR Corporation Limited 2013/8/29 Page 6


1. About SIL(E) Contract 903

Wong Chuk
Hang
Station

Viaduct D

Aberdeen Channel
Bridge
MTR Corporation Limited 2013/8/29 Page 7
1. About SIL(E) Contract 903

Beauty of Target Cost Contract

1. 2 Contractors can be selected at an early stage to help the Employer to identify


value engineering solutions

2. The selected Contractor will have more time to mobilise sufficient resources
and plan the works well before the actual commencement of the Contract.

3. The Employer and his construction team will be more proactive to help the
Contractor to use the cheapest method to complete the project.

4. This contract arrangement is beneficial to foster a genuine partnering


relationship between the Employer and the Contractor.

5. This form of contract facilities early identification of risks and allows these
risks to be better managed during the construction stage, thus increasing the
certainty of project delivery.

MTR Corporation Limited 2013/8/29 Page 8


1. About SIL(E) Contract 903

4 main benefits to use elevated railway for this section of SIL(E) are:

1. Less spoil will be generated from this Contract;

2. The passenger will be able to enjoy the beautiful scenery from Ocean Park to
Ap Lei Chau;

3. The connection details between the Ocean Park Station and the main railway
line will be much simpler and user friendly;

4. The elevated railway requires less land during construction compared to a


tunnel option, which addresses the lack of available land in Southern District;

MTR Corporation Limited 2013/8/29 Page 9


2. Viaduct Construction

MTR Corporation Limited 2013/8/29 Page 10


2. Key information of SIL(E) Viaduct

Key information of SIL(E) Viaduct


Length of the viaduct is approx. 2 km;
Viaduct height is approx. 10 to 25m subject to topographical condition;
There are 47 nos. of viaduct piers with span length from 21m to 50m; and
628 nos. of precast segments, 22-55 tonnes each.

Viaduct D
Viaduct C
Viaduct B

Wong Chuk Hang Station

Ocean Park Station


Segmental construction

casting in-situ construction

MTR Corporation Limited 2013/8/29 Page 11


Noise Barrier - Integrated Approach

Overhead Lines
Countershading
Coloured Translucent
Panels Where Required

Track-Side Ops 2m
Opaque Panels at
Absorptive Parapet
Barrier

Viaduct Pier

Proposed Noise Barrier - Perspective Proposed Noise Barrier - Section

MTR Corporation Limited 2013/8/29 Page 12


Typical Viaduct Section
4000

4000
Profiled Capital
13m

Rounded Piers
Consistent Approach
for Portal Piers
Planting at Bottom
Of Pier

Front Elevation Side Elevation Front Elevation at Portal

MTR Corporation Limited 2013/8/29 Page 13


2. Viaduct Construction

2.1 Value Engineering for Viaduct

MTR Corporation Limited 2013/8/29 Page 14


Viaduct B

Viaduct B

MTR Corporation Limited 2013/8/29 Page 15


2.1.1 Value Engineering for Viaduct B

Viaduct construction in the vicinity of the road with heavy traffic


MTR Corporation Limited 2013/8/29 Page 16
2.1.1 Value Engineering for Viaduct B

Change in piling design Use a large diameter pile to replace a group of smaller diameter piles

Conforming design Alternative design

Wong Chuk Wong Chuk Wong Chuk Wong Chuk


Hang Road Hang Road Hang Road Hang Road

3 nos of 1.5m Single 2.8m Dia.


dia piles Bored Pile

MTR Corporation Limited 2013/8/29 Page 17


2.1.1 Value Engineering for Viaduct B

Change in Pilecap Design Use a smaller rectangular pilecap to replace a larger irregular pilecap

Legend
B3 Piles
R oad Pile cap
h u k Hang
C
Wong Traffic flow
Carriageway

B3
Conforming design ad
hu k Hang Ro
W ong C

Extent of works area required was greatly


reduced
Less impact on road traffic

Alternative design
MTR Corporation Limited 2013/8/29 Page 18
2.1.1 Value Engineering for Viaduct B

Change in Pilecap Design Use a smaller rectangular pilecap to replace a larger irregular pilecap

Minimize the conflict with the existing utilities

Existing 132 kV
HEC cables

Original Pile
Cap
Existing 132 kV
Conforming design HEC cables

Revised Pile
Cap

Alternative design
MTR Corporation Limited 2013/8/29 Page 19
2.1.1 Value Engineering for Viaduct B

Comparison between conforming design and alternative design

Conforming design Alternative design


Number of bored piles
18 9

Size of bored piles


1.5 m 2.0 m to 2.8 m

Pile caps 1) Volume of pile cap - Approx. 480 m3 1) Volume of pile cap - Approx. 320 m3
2) More construction and ELS required 2) Less construction and ELS required

Advantages of the 1) Extent of works area required was greatly reduced


alternative design over 2) Less impact on the road traffic
the conforming design 3) Minimize the conflict with the existing utilities
4) Cheaper and faster to construct the piling and pilecap works

MTR Corporation Limited 2013/8/29 Page 20


Viaduct C

Nullah

Viaduct C

MTR Corporation Limited 2013/8/29 Page 21


2.1.2 Value Engineering for Viaduct C

Viaduct construction over nullah


MTR Corporation Limited 2013/8/29 Page 22
2.1.2 Value Engineering for Viaduct C

1. Reduce the number of portal from 11 to 8


2. Change in piling design Use a large diameter pile to replace a group of smaller diameter piles

Conforming design

Alternative design
MTR Corporation Limited 2013/8/29 Page 23
2.1.2 Value Engineering for Viaduct C

Comparison between conforming design and alternative design

Conforming design Alternative design


Number of bored piles 56 28
Size of bored piles 1.5 m (C1, C2 and C13 Piers) 1.8 m (C1, C2 and C11 Piers)
1.8 m or 2.2 m (Portals) 2.0 m (Portals)
Number of portals 11 8
Span length Approx. 35 m Approx. 50 m
Advantages of the 1) Reduce construction time for bored piles and portals
alternative design over the 2) Minimize construction activities inside the nullah - critical to programme
conforming design 3) Less visual impact with wider spacing of portal structures
4) Minimize the conflicts with the existing utilities

MTR Corporation Limited 2013/8/29 Page 24


Viaduct D

Viaduct D

MTR Corporation Limited 2013/8/29 Page 25


2.1.3 Value Engineering for Viaduct D (from D13 to D18)

Viaduct construction in hilly area


MTR Corporation Limited 2013/8/29 Page 26
2.1.3 Value Engineering for Viaduct D (from D13 to D18)

Change in Foundation Design Replace bored pile by spread footing

Conforming Design Alternatives Design

Inferred
Rockhead Spread
Footing
found on
Rock
3 nos of 1.5m Rock
dia piles Dowels

MTR Corporation Limited 2013/8/29 Page 27


2.1.3 Value Engineering for Viaduct D (from D13 to D18)

Change in viaduct design - Replace precast segmental deck by in-situ deck

Hilly area
Segmental construction

Replace precast segmental deck by in-situ deck

Precast segmental deck In-situ Deck

- Better quality control in casting yard


Advantage - Environmental friendly - steel mould replace timber - More timber formworks
formwork

- Difficult access at hilly area for erection of precast - Construction is relatively simple and
Limitation
segment faster with the use of a tower crane

MTR Corporation Limited 2013/8/29 Page 28


2.1.3 Value Engineering for Viaduct D (from D13 to D18)

Comparison between conforming design and alternative design

Conforming design Alternative design


Type of pile per column 3 nos of 1.5m dia piles per Spread footing found on rock with
column rock dowels per column

Viaduct type Precast segmental deck In-situ deck

Advantages of the 1) No heavy piling plant is required in the hilly area


alternative design over
the conforming design 2) Less time to complete the foundation works as footing can be
constructed simultaneously

3) The size of the haul road and the ELS works required can be
reduced

4) The delivery of materials are relatively simple with the use of a


tower crane or a mobile crane

MTR Corporation Limited 2013/8/29 Page 29


2. Viaduct Construction

2.2 Viaduct Construction by Pre-cast Segmental Method

MTR Corporation Limited 2013/8/29 Page 30


2.2 Pre-cast segmental method

Two erection methods are being adopted:

2.2.1 Erection by Crane 2.2.2 Erection by Beam-and-


Winch

MTR Corporation Limited 2013/8/29 Page 31


2.2.1 Erection by Crane
B4 B5
B4

Step 1 Step 2

MTR Corporation Limited 2013/8/29 Page 32


2.2.1 Erection by Crane

B4 B5 B4 B5
Closure
beams

Step 3 Step 4
MTR Corporation Limited 2013/8/29 Page 33
2.2.2 Erection by Beam-and-Winch
Beam-and-Winch technology was introduced in the SIL(E) project to enhance the merits of
precast segment erection method
B4 B5
B4 B5

Step 1 Step 2
MTR Corporation Limited 2013/8/29 Page 34
2.2.2 Erection by Beam-and-Winch

B4 B5 B4 B5
Closure
beams

Step 3 Step 4
MTR Corporation Limited 2013/8/29 Page 35
2.2.2 Erection by Beam-and-Winch

MTR Corporation Limited 2013/8/29 Page 36


2.2.3 Beam-and-Winch and Launching Gantry

Beam-and-Winch Launching Gantry


Scale Approx. 8m in length and 10m Approx. 100m in length and 10m wide
wide More than 10 times larger than Beam-
and-Winch equipment in size

Time required for Approx. a week Approx. one month


machine assembly

Beam-and-Winch Launching gantry


MTR Corporation Limited 2013/8/29 Page 37
2.2.3 Beam-and-Winch and Launching Gantry
Advantage and Limitation of Beam-and-Winch
Advantage of Beam-and-Winch over Launching Gantry
Less road space required, less disturbance to the traffic
Less construction time required
More flexibility and efficiency in works arrangement

Limitation of Beam-and-Winch
Allowance in Permanent Works Design
Mobile Crane required for mobilization from pier to pier.

MTR Corporation Limited 2013/8/29 Page 38


2.2.4 Safety Measures

Independent checking system for segment erection

Checklist of segment erection Checklist of B&W operation

MTR Corporation Limited 2013/8/29 Page 39


2.2.5 Measures to minimize impacts on Road Traffic

Key measures to minimize impacts on road traffic:


1. Adopt Pre-cast segmental method
2. Use Beam-and-Winch
3. Night-time erection to minimize traffic impact on the public

1) Pre-cast segmental method 2) Beam-and-Winch 3) Night time erection

MTR Corporation Limited 2013/8/29 Page 40


2. Viaduct Construction

2.3 Stakeholder Management

MTR Corporation Limited 2013/8/29 Page 41


2.3.1 Major Stakeholders around the Viaduct B & C

TWGHs Wong Chuk


Hang Complex

Aberdeen Tunnel

uct
ad
Vi San Wai Village
Bus Depot

a rk
P
an ion
e t
Oc Sta

Viaduc
t
Police College Ocean Park

MTR Corporation Limited 2013/8/29 Page 42


2.3.2 Major Stakeholders around the Viaduct D

h u k Hang
gC
Won Station
NLSR
Tai Wong Ye Cooked Food
ct Temple
Viadu Market

Jockey Club
Holy Spirit Rehabilitatio Little Sisters of
Seminary n Centre the Poor
St. Marys
Home for the
Aged

MTR Corporation Limited 2013/8/29 Page 43


2.3.3 Stakeholder Engagement

Community Liaison Group Meeting Visit to the TWGHs Wong Chuk Painting activity in Little Sisters of
Hang Complex the Poor

JCRC visit and regular meeting Allowance for Tai Wong Ye


Temples Yu Lam Festival event Football Match with Police College

MTR Corporation Limited 2013/8/29 Page 44


MTR Corporation Limited 2013/8/29 Page 45
3. Aberdeen Channel Bridge Construction

MTR Corporation Limited 2013/8/29 Page 46


3. Aberdeen Channel Bridge

Aberdeen Channel

Existing Ap Lei Chau Bridge

m
73
A
Max

5m 7m
11
A

SIL(E) Aberdeen Channel


m
58 Bridge

Total Length = 250m Section A

MTR Corporation Limited 2013/8/29 Page 47


3. Aberdeen Channel Bridge

Aberdeen Channel Bridge (as of June 2013)

Photomontage of Aberdeen Channel Bridge

MTR Corporation Limited 2013/8/29 Page 48


3. Aberdeen Channel Bridge Construction

3.1 Value Engineering for Aberdeen Channel Bridge

MTR Corporation Limited 2013/8/29 Page 49


3.1 Value Engineering for Aberdeen Channel Bridge
E4 E3 E2 E1
Conforming Arrangement

16 pairs segments (~3.5m long) 16 pairs segments (~3.5m long) Hill

12m insitu end span on


falsework

E3
E2 Temporary pier bracing
Temporary pier bracing

Alternative Arrangement Longer cantilever length for


segment construction
10 pairs segments (~4.3m long) 14 pairs segments (~4.3m long) Hill

Falsework eliminated

One unbalanced cantilever


E3 E2 Temporary pier bracing
segment

MTR Corporation Limited 2013/8/29 Page 50


3.1 Value Engineering for Aberdeen Channel Bridge

Comparison between conforming design and alternative design

Conforming design Alternative design


Number of segments 32 pairs 24 pairs
Period for segment construction ~ 50 weeks ~ 40 weeks

Max. cantilever length 60 m 65 m


Max. segment weight 130 tons 160 tons
Number of strands per cantilever
12 19
tendons
Remark: 1) Segment weight in alternative design is heavier
2) One set of form traveller instead of two sets of form traveller
is required to meet the programme
3) Temporary bracing at E3 pier eliminated
4) Scaffolding for end span near E1 eliminated
5) Advantage to construction programme
6) The alternative design can provide early access for P-way
construction

MTR Corporation Limited 2013/8/29 Page 51


3. Aberdeen Channel Bridge Construction

3.2 Bridge construction by in-situ balance cantilever

MTR Corporation Limited 2013/8/29 Page 52


3.2 ACB Comparison of different construction methods

Cast in-situ segments by Pre-cast segmental method Cast in-situ span by span
balanced cantilever
(Selected option)

Description Cast in-situ segments by Segment pre-cast and Cast bridge span by span
balanced cantilever method erection with the support by
with form traveller falsework

Advantage Advantage Disadvantage Disadvantage


and 1) Only one set of form 1)Barge for segment 1) Falsework cannot be
disadvantage traveller is required erection is too large to erected across the
2) Without affecting the gain access to the bridge Aberdeen Channel
marine traffic underneath 2) Segment (max 160T) too
the bridge heavy for lifting
3) No heavy lifting involved 3) Disruption to Navigation
4) Cheapest and fastest Channel during segment
way to build this bridge erection

MTR Corporation Limited 2013/8/29 Page 53


3.2.1 ACB Construction Sequence

Stage 1 Pier Table construction at E2

Stage 2 Pier Table construction at E3


- Erect form traveller at E2

MTR Corporation Limited 2013/8/29 Page 54


3.2.1 ACB Construction Sequence

Stage 3 Complete cantilever span at E2 by


insitu balanced cantilever method

Stage 4 Launch back form traveller &


remove tower crane from E2

MTR Corporation Limited 2013/8/29 Page 55


3.2.1 ACB Construction Sequence

Stage 5 Tower Crane & form traveller removed from E2

Stage 6 Erect tower crane & form traveller at E3

MTR Corporation Limited 2013/8/29 Page 56


3.2.1 ACB Construction Sequence

Stage 7 Complete E3 cantilever span by


insitu balanced cantilever method

Stage 8 Cast Mid-span stitch

MTR Corporation Limited 2013/8/29 Page 57


3.2.1 ACB Construction Sequence

Stage 9 Cast unbalanced segment at E4

Stage 10 Cast End-span stitch at E4

MTR Corporation Limited 2013/8/29 Page 58


3.2.2 Modular Form Traveller (MFT)
Modular Form Traveller Formwork system
Main Frame x 2 Inner Form
Major component: Front Transverse Truss x 1 Outer Form
Rear Transverse Truss x 1 Bottom Form
Rear Anchorage x 2
Rail Beam x 2

MTR Corporation Limited 2013/8/29 Page 59


3.2.2 Modular Form Traveller (MFT)
General characteristics of Modular Form Traveller:
Bridge alignment Segment geometry
Gradient of +/-5% Maximum length of 5m
Cross-fall of +/-5% Maximum weight of 180 tons (with 2
Minimum curve in plan of 500m main frames)
radius Single or multiple cells
Vertical or inclined webs

Load test could be carried out


prior to assembly
System capacity: 180 tons
MTR Corporation Limited 2013/8/29 Page 60
3.2.2 Modular Form Traveller (MFT)
Main frames

Front truss Wall Form

Rear
truss

Bottom Form

MTR Corporation Limited 2013/8/29 Page 61


3.2.2 Modular Form Traveller (MFT)

MTR Corporation Limited 2013/8/29 Page 62


3. Aberdeen Channel Bridge Construction

3.3 Stakeholder Management

MTR Corporation Limited 2013/8/29 Page 63


3.3.1 Stakeholders around Aberdeen Channel Bridge

Aberdeen
Channel
Bridge

Dragon Boat
Association
Kaito

Aberdeen Sham Wan


Channel Jumbo
Restaurant

Marine Police Aberdeen Boat


Port Club

Tai Shue Wan

MTR Corporation Limited 2013/8/29 Page 64


3.3.2 Minimize impact on Marine Traffic

Key measures to minimize marine traffic impact:


1. Use cast-insitu balanced cantilever method

2. Maintain navigation channel

3. Advance notice to all marine users about the construction works

4. Use of guard boat

1. Cast-insitu balanced cantilever method

2. Navigation Channel

14 m min. high

40m min. wide


MTR Corporation Limited 2013/8/29 Page 65
3.3.2 Minimize impact on Marine Traffic

3. Early notice to all marine users about the 4. Use of guard boat
construction works

MTR Corporation Limited 2013/8/29 Page 66


3.3.3 Minimize impact on Marine Environment

Key measures to minimize marine environment impact:

1. Use of silt curtain


2. Use of temporary steel formwork for pile cap construction

Use of silt curtain Use of temporary steel formwork for


pile cap construction

MTR Corporation Limited 2013/8/29 Page 67


3.3.4 Entertain the need of Dragon Boat Association

Relocate the existing dragon boats to the new permanent storage area for the Dragon Boat
Association before the commencement of the construction on site

Aberdeen Channel Bridge

Existing storage area for dragon boat


New permanent storage area for before bridge construction
dragon boat

MTR Corporation Limited 2013/8/29 Page 68


Q&A

MTR Corporation Limited 2013/8/29 Page 73

Anda mungkin juga menyukai