INTRODUCTION
BIM has a database that contains necessary and accurate information about
the building. The information is highly accurate compared to the traditional
method and 3D Computer Aided Design (CAD). For instance, collision detection
in BIM is based on algorithms developed in gaming industry and computer
graphics procedures, which is unavailable in CAD and more efficient than the
traditional method which is based on overlapping designs. BIMs database
contains several variables necessary for analysis and assessment, such as
environmental protection and energy consumption, time scheduling, faster cost
estimation, facility management application, etc., all of which are manually and
separately done in traditional and CAD methods [3]. BIM has become a
revolutionary approach to the development in the architecture, engineering and
construction industries. A more efficient integrated design and construction
2
This chapter presents the different theories behind Building Science, Heating,
Ventilation, and Air Conditioning, Fire Protection, Plumbing, and Building
Information Modeling.
The concept phase defines the amount of work the project needs and the
conceived end result. This phase is crucial in properly defining what the client
needs and wants. This provides a basis for the design phase where
professionals, architects, and engineers provide the schematic plans and in
depth building specifications. Tendering phase is done to form contracts with
organizations willing to undertake the work specified by the designers. The Pre-
6
construction phase begins when the main contract has been awarded to the
selected contractor. This is the time allotted for the contractor to organize and
gather the necessary resources to begin construction. Construction begins when
site possession is given to the main contractor and ends when the project
reaches practical completion. Commissioning begins when principal is given the
liability for the facility. During this period the contractor is still under the defects
liability where remaining construction tasks is done, defects found are dealt with,
and service fixtures are properly inspected [12].
Extra Hazard 2. The standard automatic sprinkler system types and their main
characteristics are shown in Table2.2.
Type Characteristics
Wet pipe Has water under pressure at all times in the whole sprinkler system.
Usually used when freezing and special parameters are not present.
Dry pipe Does not contain water in its sprinkler system. Used when freezing is
possible and activation delay is not a grave concern.
Deluge Delivers water to the entire protected area in the least amount of time
possible, usually used on extra hazards.
Preaction Similar to the dry pipe but with more conditions to activate to prevent
accidental activation due to sensitivity of property protected.
Anti- Similar to the wet pipe but has an anti-freeze solution to prevent freezing
freeze in the system. Usually used as a subsystem of a wet pipe protecting an
area exposed to freezing temperatures.
sewer system conveys the waste water to proper disposal areas or treatment
plants. If a sewer system is unavailable, a septic system will be required [15].
Following the conservation of energy, decreasing the kinetic energy will result
in an increase in potential energy. Fluids also follow this rule when studying their
behavior at varying velocities; this is referred to as Bernoullis Principle. This is
useful when predicting the pressure of fluids following changes in elevation and
velocity. Due to friction losses and pump energy inputs energy loss and gain will
13
load analyzers are made by companies to eliminate the need for tedious
calculations [9].
Water Supply
Fixture Occupancy
Fixture Unit (wsfu)
Bathtub Private/Public 1.4/4.0
Bidet Private 2.0
Combination fixture Private 3.0
Dishwashing Private 1.4
machine
Drinking Fountain Offices, Etc. 0.25
Kitchen sink Private/Hotel, restaurant 1.4/4.0
Lavatory Private/Public 0.7/2.0
Service Sink Offices, Etc. 3.0
Shower Head Private/Public 1.4/10.0
Urinal Public 3.0
Water Closet Private/Public 2.2/5.0
digitize the designers drawings and import them into a cost estimating package,
or do manual estimates. This introduces possibility of human error [21].
Autodesk Revit. For time schedule, 71% use Autodesk Navisworks. Autodesk, as
one of the leading BIM solutions, has strengths that balance out the criteria for
BIM.
In the design phase, the input would consist of a finished architectural and
structural plan for the commercial building containing complete building
dimensions, and space allotment for different building activities. The mechanical
system to be designed will depend on the standards and laws that the local
building code requires. The clients preferences regarding budget and time limits
will be taken into consideration.
itself for the changes made. Once finished, the output would consist of data
generated from the model and simulation, such as the Analysis Data, Bill of
Materials, Construction Time Schedule as well as drawing sheets of the
schematic designs.
CHAPTER III
REVIEW OF RELATED LITERATURE
3.4 Comparison Between Traditional CAD vs. BIM in the Design Phase
Traditional CAD and BIM are two entirely different methods. They cover
several differences particularly in the design phase. For instance, CAD can be a
2D or 3D representation of a model but it does not contain intelligent information.
In traditional CAD separate, independent documents are used to explain a
building. Whereas in BIM, all information such as schedules, quantity take-offs
and analyses are assembled in one database, thus it contains intelligent
information [33]. In terms of visualization, section, plan, elevation, and 3D views
are each manually created in Traditional CAD. In BIM, a created 2D plan can
already generate different views [22]. Table 3.1 shows more differences of the
two methods.
23
In traditional CAD design, project team members have to wait for each other s
design completion before exchanging information. However, in BIM, the
integrated designs allow earlier and timelier exchange of information between
members, which is necessary for design adjustments and modifications. Apart
from that, BIM minimizes idle times and unwanted delays of waiting for designs,
unlike in CAD where complete information is still waited. Reworks are very
normal in design phase. When this occurs in traditional CAD, any adjustment of a
certain concept or a drawing perspective has to be reflected in all other
disciplines and views. However, in BIM, one modification in a view automatically
modifies other views, which saves time and prevents cost overruns [34].
The Return of Investments of BIM of the four projects of the midsized general
contractor labeled Company X (for confidentiality) were estimated. Projects A and
B were commercial warehouses were comparable in terms of size, scope,
contract value, delivery method, and construction type. Projects C and D were
condominiums which were also comparable. The estimated ROIs for Projects A
and C were based on the BIM-preventable time overrun issues, mainly design
conflicts, with associated direct and indirect costs. For Projects B and D, ROIs
were based on indirect costs saved from early completion and delays. Table
showed the summary of the project details with their corresponding ROI. It was
concluded that great ROI was achieved on larger projects, however, savings
were still realized regardless of the project size. The usage of BIM also
completed the project schedule on or ahead of time [36].
As BIM had been expanding globally, many countries had reported positive
ROI on their investment on BIM. Figureure showed the percentage of contractors
from the 10 BIM-adopting countries who reported positive ROI for BIM. It clearly
showed that Japan, France and Germany report top ROI on BIM investments,
while South Korea, UK and US trailed [32].
100%
50% 97% 97% 97% 87% 85% 78% 74% 59%
0% 48%
Center project was also used to study the application of BIM for 3D coordination,
construction planning, prefabrication, visualization, and record model. In
conclusion, the visualization is the simplest use of BIM. The 3D coordination was
used for clash and conflict detection. Better construction planning has resulted
from BIM based time scheduling which helped in understanding of the
construction mechanisms and scheduling [22].
Current AEC industry process as being fragmented and the paper based
communication is considered to be the primary reason behind this. Additionally,
the study discloses that the application of BIM on a project level requires
comprehensive planning by facility owners and project participants to provide
successful transition from a traditional approach to integrate this recent
technology into the project workflow. This factor is vital when attempting to adapt
BIM because it cannot operate if building data is limited to paper and digital
copies are unavailable. This might be a reason for the slow adaptation of BIM
[40].
CHAPTER IV
METHODOLOGY
Construction time schedule was created and linked to the model. Further
refinements were done when necessary.
The Gantt Chart shows estimated duration of tasks necessary for designing
mechanical systems using the BIM approach. The study was estimated to
complete in 93 days.
This chapter contains the findings of the study conducted. Details regarding
the prominent differences of traditional designing and BIM, and the cost and time
benefits are discussed in this chapter.
diffuser
3. Input diffuser specification
4. Adjust placement accordingly
Routing of The routing is Autodesk Revit show multiple solution
ducts drafted manually on proposals which is user selected.
Autodesk CAD Steps in Autodesk Revit are the ff:
1. Select create ducting system to
start routing process
2. Select equipment involved in the
system to be routed.
3. Select generate layout to produce
the proposed solutions
4. Select desired layout
5. Adjust the routing accordingly
Sizing of ducts Duct dimensions Revit has a built in sizing feature that
are selected sizes the ducts accordingly. Steps in
manually using Autodesk Revit are the ff:
1. Select ducts to size
different methods of
2. Select duct sizing button
sizing. 3. Choose the desired method of
sizing
4. Adjust the sizes accordingly
tab
2. Click Schedules/Quantities button
3. Click costs category
4. Input corresponding cost of material
Title block Manual drafting in Automatic creation of sections
1. Open the 3-D model
making Autodesk CAD.
2. Select the view desired
3. Hide components that should not
be included
Estimated Time of
Estimated Time of
Accomplishment using
Task Accomplishment using
Conventional Method
BIM (labor hours)
(labor hours)
Plumbing System Design 84 48
Fire Protection System 48 36
Design
HVAC Design 64 72
46
Consolidation 36 -
Clash Detection 36 -
Information Extraction 36 12
304 168
Total
Total Time Benefit 136
Revit contains System Inspector tool which simulates the flow direction of the
system. It also shows the flow rate and pressure information of the section of
duct and piping systems. A sample screenshot of this feature is shown in Figure
5.11.
act as the basis for the automated features. Proper management of information is
essential for effective implementation.
The computers that were used in the designing were the MacBookPro11, and
the Lenovo 80RU. These computers were capable of modelling our sample
building. We are not able to provide a guide for selecting computer specifications
depending on the anticipated project sizes.
typically have their tasks specialized. The actual number of hours spent on
conducting the study was not kept on track. This fault caused the study to be
unable to provide a concrete time-benefit analysis.
CHAPTER VI
CONCLUSION AND RECOMMENDATION
This chapter will discuss the conclusion of the study and recommendations
that would have improved the data gathered.
6.1 Conclusion
The duration it took to finish the mechanical systems design took
approximately 100 days from start to finish, including days where the study was
not being worked on. A number of factors were considered to have great effect
on the result of the study.
It was found that BIM provides construction firms a much more organized,
accurate, and convenient process to conduct construction project designing for
54
even for small to medium scale buildings, however, the time and cost efficiency
of BIM conducted in this study was inconclusive due to the manner the study was
conducted. Better planning and preparations should have yielded better results.
6.2 Recommendations
The study recognized factors that affected the data only during the execution
of the study. This section will discuss how to properly address the factors in order
to acquire more accurate and conclusive data representing actual work
conditions.
Bibliography
[3] I. Czmoch and A. Pekala, "Traditional Design versus BIM Based Design,"
Elsevier Ltd., Warsaw: Warsaw University of Technology, 2014.
[4] "Frequently asked questions about the national bim standard-united states,"
National Building Information Model Standard Project, 2016. [Online].
Available: https://www.nationalbimstandard.org/faqs#faq1.
[7] W. Ocfemia, "Philippines should adopt BIM technology in infra projects", The
Market Monitor, 2016.
[9] M. Bjork Lof and I. Kojadinovic, "Possible Utilization of BIM in the Production
Phase of Construction Projects: BIM in work preparation at Skanska
Sweden AB," Stockholm, 2012.
[15] ASHRAE Inc., 2016 ASHRAE Handbook - Heating, Ventilating, and Air-
Conditioning Systems and Equipment (SI Edition), American Society of
Heating, Refrigerating and Air-Conditioning Engineers, Inc, 2016.
[18] NFPA 13: Standard for the Installation of Sprinkler Systems, NFPA, 2016.
[19] P. Simmonds, ASHRAE Design Guid for Tall, Supertall, and Megatall
Building SYstems., American Society of Heating, Refrigerationg and Air-
Conditioning Engineers, Inc., 2015.
57
[23] M. K. Khan, Fluid Mechanics and Machinery, Oxford University Press, 2015.
[28] P. Stelth, "Projects' Analysis Through CPM (Critical Path Method)," vol. 1,
2009.
[29] S. Azhar, "Building Information Modelling (BIM): Trends, Benefits, Risks, and
Challenges for the AEC Industry," 2011.