2#2'4
ABSTRACT occurrence containing minimal quantities This paper outlines a design procedure
This paper describes the design of of other sulphides such as chalcopyrite, that drew on previously conducted
a molybdenite flotation circuit using pyrite, sphalerite and galena. testwork used to develop a suitable
FLEET technology applied to kinetics Molybdenite occurs mainly as process from laboratory and pilot plant
data produced from laboratory flotation coarse flakes with lesser amounts of work on a few samples of ore. It then
finer sized values. An optimum plant continued by testing forty drill core
testing and distributed across the
design was required to can achieve the samples by a standard technique that
blocks of a mine plan using a
predicted operating results, at a known allowed the determination of flotation
geostatistical approach. The geostatistics level of risk, while treating the variability kinetic parameters for each sample.
assigned the statistical error that arises inherent in the ore body. These parameters were then used
from having a limited amount of sample with the FLEET software program
testing data to the kinetics estimates of The traditional approach to flotation plant to scale-up to a plant design with an
each block of ore in the mine plan. The design involves the extensive testing optimum flowsheet and equipment
final design then included a quantification of a single large composite sample or selection suited to an orebody that
a small number of composite samples was described by an average of all
of risk based on the accuracy of the
that are reputed to represent the ore the samples tested. The variability
block flotation kinetics and model fitting.
body. Laboratory tests are conducted of expected plant results were then
The design made reference to the to establish a process with potential examined by applying the plant design
extensive technical reports describing flowsheets and reagent suites. The to the parameters of each of the
earlier metallurgical test work including process is then confirmed by pilot plant samples. The samples were widely
some pilot plant work over thirty years work on a large bulk sample or a few spaced across the resource, covered the
ago. samples. The size of equipment required expected proportions of each of the five
to achieve a specified throughput, major lithologies and had a wide range of
recovery and product grade is then molybdenite feed grade. Geostatistical
The testing involved conducting
calculated from one of a variety of scale- analysis of the flotation kinetics data was
MinnovEX Flotation Tests (MFT) to
up models. Since the test work has been conducted by identification of the
determine the rougher flotation kinetics extensive, it is accepted as being location of the sample points and
at the specified reagent conditions and reasonably precise in predicting results; comparison with the geological plan
rougher-cleaner tests to determine the however during the operation of the of the orebody, together with a mine
change in kinetics resulting from regrind. resulting plant the design is sometimes plan of the blocks to be mined during
These flotation kinetics were used found to be inadequate. It is then the proposed life of the mine. The
within FLEET simulations to create a suspected that the flaw in the design geostatistical analysis estimated kinetics
process lies in the samples not being parameters for each block and for the
full-scale flowsheet and plant design
sufficiently representative of the ore average values of each production year,
including recommended equipment sizes
body, since using only a single or small so that the FLEET program could be
and the forecast of operating results. number of composite samples used to predict the average flotation
Measurement of detailed flotation does not recognize the variability of results for each production year.
kinetics for a wide range of samples the flotation response of the ore, nor The statistical variability of the kinetics
allowed the effect of size of grind and does it allow for the lack of ore body of the forty samples was used with
efficiency of classification (i.e. width of representation used in the design. It had the FLEET program to determine the
size distribution) to be predicted for the not been possible to estimate the risk or precision of the expected average results
error in the expected results. of the selected plant design and the
whole ore body.
risk associated with that prediction.
INTRODUCTION
terms of feed rate (tph), feed grind were spatially well distributed across
FLEET SIMULATION SYSTEM (P80), head grade and flotation kinetic the ore body. Molybdenum content as
parameters at that grind. These reported from drill core assays on one
A brief description of FLEET software parameters are a description of each half of a core section did not always
is a pre-requisite to understanding the mineral species in terms of: compare well with that determined
whole design approach described in the ultimate recovery achievable by during the flotation test work on the
this paper. FLEET simulations were true flotation, Rmax (that is, flotation by other half of the core section, probably
used to investigate the performance of attachment only after the contribution due to sampling error when splitting
a full-scale flotation plant treating ore from hydraulic entrainment has been the core and in sample preparation of
represented by the Ruby Creek Project deducted) batches for flotation tests. However,
drill core samples with the reagent the average rate constant, kavg and there appears to be no bias between
conditions as tested in the laboratory. a measure of the rate constant the two measures as shown in Figure
FLEET was used in both flowsheet distribution, alpha. 1. Note that the higher grade samples
design and equipment size selection. Rmax and kavg are also expressed in (>0.13%Mo) proved harder to sample,
A FLEET system comprises three terms of any change with respect to a possibly due to the presence of large
components (Dobby et al, 2002): small change in grind, i.e. Rmax_slope and crystals (or rosettes) of molybdenite that
The Flowsheet, kavg_slope so that any change in P80 can be are occasionally seen in the drill core.
The circuit Input parameters, and investigated. This comparison highlights the sampling
The Dataset difficulties and the potential ore body
The dataset can be a single line estimation errors.
describing the feed to a flotation circuit
The FLEET Flowsheet
at one particular time (e.g. a single
In the FLEET Flowsheet component,
the configuration of the circuit and the
equipment specifications, e.g. number
of cells, type, dimensions, are defined.
Various flowsheets are then simulated to
determine an optimum.
Kinetic parameter extraction procedure Figure 2: Typical Mo recovery (Rmax) versus size data
Pulp kinetic parameters for each test are Rmax values. As a comparison, copper The average Mo Rmax value increased
derived for each mineral species from porphyry ore may exhibit NSG Rmax of 4 by almost 5% when changing from
the sizing and chemical analyses of the to 8%. m value of 0.7 to 1.0, indicating the
feed, individual concentrates, combined advantage that would be gained from
concentrate and tailings samples (Dobby The molybdenite recovery was generally achieving the narrowest possible size
and Savassi, 2005) for use in the FLEET poor under the standard size conditions distribution for feed to the flotation
dataset. It is also possible to calculate with P80 of 210 microns and m of 0.7, circuit. This could be achieved by 2-stage
the effect on the kinetics of changing with an average Rmax of only 84.8% cycloning of mill discharge to minimise
the feed size distribution, the m value for the forty samples tested. All the the quantity of misplaced coarse material
of the Rosin-Rammler distribution. data were recalculated at two further that exits the grinding circuit. Reducing
It is possible to simulate a feed size standards: an m value of 1.0 ; and a P80 the P80 from 210 to 180 microns will
distribution similar to that expected in of 180 microns. The results are shown in improve the average Mo Rmax by 1.5%.
a full-scale operation rather than the Table 1. Any decision regarding the change of
narrow distribution produced in typical size can now be made by comparing the
laboratory mills. In this case the m cost of the extra grinding against the
value of the Rosin-Rammler distribution
Table 1: Summary of kinetics results from the 40 samples.
was about 1.0 in the laboratory ball
Grind (microns) P80= 210 P80= 210 P80= 180
mill, whereas a value of 0.7 to 0.8 may
be more likely in a plant distribution R-R slope m= 0.7 m= 1.0 m= 1.0
containing more slimes and coarse Moly NSG Moly NSG Moly NSG
material (typical of single stage plant Average 84.8 0.6 89.6 0.7 91.1 0.7
cycloning where the P80 is 200 microns)
while maintaining the P80 at the same
value. All of the data was converted to a
standard m of 0.7 for plant design.
Results
Figure 5: FLEET flowsheet used to simulate laboratory rougher-cleaner tests with a 2 stages of regrind.
Note the water addition point, and M (circled) that refers to a modification of the kinetic parameters, in
this case as a consequence of the regrind.
NSG - 0.05 to 0.4
that is recovered by true flotation Figure 7: Overall Circuit Grade/Recovery
performance with single regrind
(attached to molybdenite) into the Again there is a trend that a lower NSG
rougher concentrate. The more that the Rmax multiplier can be used in the stages using column cells.
gangue is attached at the rougher feed 2nd regrind to counter a higher Rmax
stage, the more is available for liberation multiplier in the 1st regrind (i.e. better The FLEET output suggests that
and the lower the multiplier needed for liberation in the 2nd regrind if there is performance can be improved up to a
FLEET to account for cleaning as shown more attachment remaining after the first limit of four columns, i.e. five cleaner
in Figure 6, i.e. the less the liberation regrind). NSG Rmax multiplier figures of stages (see Figure 7). The results of
at the rougher stage, the greater the 0.05 and 0.3 were selected as constant multiple stages of cleaning are limited
benefit achieved by the regrind. There is inputs for the 1st and 2nd regrinds by the extent of the liberation achieved
obviously a lower limit for the multiplier respectively for FLEET simulations in the in the regrinding up to the limit of about
and it can be assumed to be in the design of a full scale plant. 85% MoS2 recovery at a concentrate
region of 0.05 to 0.1 (at adequate grind grade of 90% MoS2 (54%Mo) from the
size) for material with higher Rmax in the FLEET SIMULATION RESULTS average feed grade.
feed. FOR FULL SCALE PLANT
DESIGNS The results of including a 2nd regrind
Multipliers for the 2nd regrind stage with five cleaner stages re
established from these tests are in the Average dataset In this design study an shown in the form of grade-recovery
region: average dataset was used to describe relationships compared with
2nd Regrind Rmax multipliers: the resource as a composite of all performance with only one regrind in
Mo - 1.0 the samples tested and simulations were Figure 8. Also included in Figure 8 is the
conducted to develop the most suitable recovery benefit determined by FLEET of
flowsheet. After that a complete enlarging the rougher cells from 100m3
dataset comprising all the individual to 130m3.
samples was produced and run with the
preferred flowsheet to see the variation
in possible results. The kinetics
Table 2. Average dataset used for the FLEET simulations of the full-scale circuit.
FEED FINAL MO
%MOS2 CONC % RECOVERY
MOS2 %
Figure 9: Plant flowsheet with two regrinds and five cleaning stages Average 0.144 88.2 88.1
Std dev. 0.110 7.6 7.1
The recommended flowsheet shown in Minimum 0.033 54.7 61.6
Figure 9 includes:
Maximum 0.568 98.0 96.7
8 rougher cells of 130m3 each
a regrind of the rougher concentrate to
P80 = 40 microns Table 3: Overall Circuit Grade/Recovery performance for the preferred flowsheet on the Average dataset
5 cleaner cells of 5m3 each produced at different feed sizes.
5 cleaner-scavenger cells of 5m3 each P80 MICRONS m VALUE MOLY Rmax NSG Rmax %MOLY CONC %
secondary regrind of the 1st cleaner RECOVERY MOLY
concentrate to P80 = 40 microns
210 1 89.6 1.1 88.7 90
4 further stages of columns with
210 0.7 84.8 0.9 83.9 91.3
diameters deceasing in size (2.2m, 2m,
1.6m and 1.3m) at each stage. 180 1 91.1 1.1 90.1 90.1
MINERALS TECHNICAL BULLETIN 7
GEOMETALLURGICAL
DISTRIBUTION OF DATA ON
THE MINE PLAN
estimation of flotation response at any the relative value of 25% is quite high concentration within any specific area.
block in the mine plan. (reflecting the sampling problems There is 95% confidence that Mo Rmax
described earlier) and results in a lack of a block will lie within +/-2 standard
Estimation of block values was made of precision in the estimates of block errors of the best estimated value. Since
using the geostatistical distance values. In this study, three samples the Mo Rmax for most blocks is in the
weighting method known as Kriging with abnormally low Rmax values were region of 90% and one standard error is
(Preece, 2006) i.e. weighting available excluded from the variogram data in typically 5%, the Mo Rmax of any block
sample data according to their distance order to obtain a reasonable nugget lies somewhere between 80 and 100%.
to the block in such a way that samples value for the remainder of the ore body. This situation is untenable for production
close to the block have more influence It was assumed that these three had planning and more flotation tests are
on the block estimate than other some localised geological effect, e.g. necessary for mill feed that is expected
samples further away. The spacing of faulting causing increased alteration, that in the first operating years to improve
the samples was adequate for this is not typical of the whole ore body. the prediction.
since at least 75% of the blocks had a
sample within 100m. Kriging requires the The samples were identified as six Since blocks have been identified by year
construction of geostatistical main lithologies further split into a total on the mining plan, the geostatistical
variograms for Rmax by plotting the semi- of eleven sub-types and into three ore analysis also allows the determination
variance of differences in the value of types. Statistical analysis indicated no of annual average grindability values
pairs of samples of equal distance apart significant Rmax differences could be and their precision by the same Kriging
against that distance. The correlogram determined between types; hence a technique, making it possible to predict
(i.e. 1 minus the correlation single variogram was developed for all the throughput in each production year. It
coefficient of pairs of samples) for Rmax is samples so that a block of any one type is also possible to extend the analysis to
plotted as a variogram in Figure 10. was interpolated using samples from any calculate how many more samples need
other type. to be tested from within the range of
The establishment of a model for the the blocks mined in a production year in
variogram allows for the estimation Since we have no determined correlation order to improve the precision to
of the Rmax and the precision of each of Rmax with %Mo grade, the %Mo grade any desired level.
estimate to be made for each block. The estimated in each block could not be
range of influence is determined by the used to improve the estimation of the The average Mo Rmax for the blocks in
shortest distance apart for pairs having Rmax of Mo for that block (with some each year of the mining plan are plotted
attained the maximum variance. In this form of co-Kriging). in Figure 11. The results indicate a
study the range for Rmax values was possible period of low Rmax at about 88%
100m. The value where the curve cuts The resultant standard error (uncertainty) for the first 2 years, rising to about
the y-axis is referred to as the nugget in the estimate of Rmax is very high at 90% from the fourth year onwards. This
effect and is a measure of the inherent about 5% for all mine blocks, since the is because the samples that exhibited
errors in sampling and measurement nugget effect is high and the samples lower Rmax values are in the area of the
of individual data points. In this case were widely distributed with no pit that is to be mined in the early years.
MINERALS TECHNICAL BULLETIN 8
Possibly this is a mineralogical effect; of the statistical error in the projected to determine the potential error in that
perhaps an occurrence of molybdenum results is of value in estimating the best estimate. The statistical variability
oxides or high alteration in the near-to- associated risks of not collecting more of flotation kinetics (at a standard grind
surface ore. It must be remembered data. A best estimation of the average of P80 = 210 microns and m value =
that there is also an uncertainty in the results for life-of-mine has been based 1.0) are presented in Table 5. Table 5
average annual data (that is lower on single tests on forty samples selected includes the results of FLEET simulations
than the uncertainty for individual blocks, to cover a wide range of locations within using kinetics parameters for the
due to the greater number of samples the resource, the lithology and feed average dataset and those at the 95%
used in calculating average data), so the grade. No correlation could be found confidence limits about the average
change with time may be more or less between maximum achievable (mean) i.e. +/-2 standard errors.
than it appears from Figure 11. However, molybdenite recovery (Mo Rmax) and
this confirms that more flotation tests lithology or feed grade. Perhaps this Definitions of items in the table:
should be conducted on mill feed that is not surprising given the sampling 95% of the sample data falls within +/-
lies within the first operating years to problems of such low grade ore (as 2 standard deviations.
refine expectations before plant start up. illustrated in Figure 1) when the Standard error of the mean = Standard
deviation of the samples / Square root
of the number of samples
There is a 95% confidence that the
true value of the mean falls with +/- 2
standard errors of the best estimate
for the average dataset, i.e. within the
range of minimum to maximum in the
table.
Table 5: Statistical variability of kinetics and expected plant results first two years will be about 2% lower
Moly MOLY NSG NSG %MOLY CONC % than average for the resource as a
Rmax kav Rmax kav RECOVERY MOLY whole. The precision of this estimate
should be improved by testing more
'Average dataset' 89.6 0.9 1.1 0.25 88.7 90.0
samples from this period since there
Standard deviation 5.4 0.3 1.0 0.14 will be an impact on expected metal
of samples recovery and project economics.
Standard error of 0.9 0.05 0.15 0.02
mean It is estimated that the expected average
Range of mean - 87.8 0.8 0.8 0.21 86.6 88.4 life-of-mine results are accurate to +/-
minimum 2% in terms of recovery and +/-1.5%
Range of mean - 91.4 1.0 104 0.29 90.7 91.9 in terms of grade at a 95% confidence
maximum level, i.e. there is a 2.5% risk that
the results will be worse than the lower
established a recommended grind, Use the variability of the sample
limit. Enlargement of the plant will not
reagent suit and flowsheet. kinetics to determine the precision of
compensate for the possibility of lower
Select forty samples that were the predicted average plant results for
recovery since the uncertainty lies in the
geographically spread over the ore body the ore body as a whole.
average value for Mo Rmax. The precision
and represent the variability in lithology
can be improved and the risk reduced
and feed grade. Simulation using an average dataset
by further tests to check some of the
Conduct standardized rougher flotation with feed grade of 0.086%Mo
existing data and add more information.
tests on each of these samples and (0.14%MoS2) produced an overall plant
extract kinetics parameters for each recovery of 88.7% at a final concentrate
ACKNOWLEDGEMENTS
mineral species (molybdenite and grade of 90% MoS2 from an average at a
gangue) that were used in scale-up grind P80 = 210 microns with m value
John Fisher and staff at Adanac Moly
calculations by the FLEET program. = 1.0. The recovery increases to 90.1%
Corp for access to the 30 year old
Conduct rougher-cleaner flotation tests at P80 = 180 microns.
test work reports from Kerr-Addison
on several samples to determine the
and Placer Developments and for co-
regrinding needed to achieve specified The width of the size distribution curve
operation in the design and permission
concentrate grade and the numerical of flotation feed (m value) significantly
to publish this paper Michel Dagbert
modifiers to kinetics parameters that affects the recovery in rougher flotation
and staff at Geostats International for
allowed the effect of cleaner flotation to and must be considered when the
geostatistical study of the flotation
be described in the FLEET program. grinding circuit is designed. A change
kinetics parameter data and support in
With an average dataset for the forty from m value of 1.0 to 0.7 (typical for
understanding the technology
sets of parameters, use FLEET to some plants with single stage cyclone
Orivaldo Savassi and Catherine McInnes
investigate flotation circuit flowsheets classification at P80 = 210 microns)
at SGS-Minnovex for numerous hours
and equipment sizing to achieve reduces the estimated plant recovery
without complaint working with the data.
optimum results at a grind P80 of 210 by almost 5%. Hence a 2-stage cyclone
microns with an m value for the classification system is recommended
Rosin-Rammler size distribution of 1.0 for the grinding circuit.
for the ore body as a whole.
Examine the change in results that The geostatistical study indicated that:
arise from changes to P80 and m in The samples were well spaced around
the average dataset. the resource for best representation.
Examine the variability of the results There was no correlation between
from using this plant design by applying Mo Rmax and feed grade or lithology.
it to the kinetics parameters from each Some of the variability may be due
of the forty samples. to sampling error because of the low
Use the location of the sample grade nuggety material. None of the
points and the geological and mining data has been checked by duplicate
plans of the ore body to conduct a sampling and testing.
geostatistical analysis that estimated The Mo Rmax values have limited spatial
grindability values for each mine block correlation; there is a big nugget effect,
and production year with a technique meaning that a best estimate of the
that allowed the determination of the value for any block can be made from
precision of the estimates. the values of the nearest samples, but
Predict the throughput for this plant the precision of that estimate is very
design in each production year using low.
the average kinetics parameters for that There is an indication that the average
year. Mo Rmax for blocks mined during the
MINERALS TECHNICAL BULLETIN 10
REFERENCES
Bulled, D., McInnes, C., Flotation plant design and production planning through
Geometallurgical modelling; Centenary of flotation conference, Brisbane, 2006
Dobby, G, Kosick, G and Amelunxen, R, A focus on Variability within the ore body for
improved design of flotation plants: Annual Canadian Mineral Processors Conference,
Ottawa, Ontario 2002
Dobby, G and Savassi O, 2005 An advanced modelling technique for scale-up of batch
flotation results to plant metallurgical performance, Proc. Centenary of Flotation
(Australasian Institute of Mining and Metallurgy) Melbourne
Dobby, G. et al., Geometallurgical Modeling - The New Approach To Plant Design and
Production Forecasting/Planning, and Mine/Mill Optimization; Annual Canadian
Mineral Processors Conference, Ottawa, Ontario 2004
Kosick, G., Bennett, C., Dobby, G., Managing Company Risk by Incorporating the Mine
Resource Model into Design and Optimization of Mineral Processing Plants; CIM
2002, Vancouver, British Columbia MinnovEX Technologies, 2004: MinnovEX Flotation
Test; Standard Procedure and Parameter extraction. Available at www.minnovex.com
Preece, R., Use of point samples to estimate spatial distribution of hardness in the
Escondida Porphyry copper deposit, Chile; SAG 2006, Vancouver, British Columbia
CONTACT INFORMATION 2011 SGS. All rights reserved. The information contained
herein is provided as is and SGS does not warrant that it
will be error-free or will meet any particular criteria of per-
formance or quality. Do not quote or refer any information
Email us at minerals@sgs.com herein without SGS prior written consent. Any unautho-
rized alteration, forgery or falsification of the content or
www.sgs.com/minerals appearance of this document is unlawful and offenders
may be prosecuted to the fullest extent of the law.