Gas Treating Unit 3

TUR Contractors:

1) Hadi Hammam
Stage Date Crew Note
1 03/26/2017 -1 Supervisor Day Only
04/06/2017 -4 pipe fitter

2 04/07/2017 -1 Supervisors Day Only


04/09/2017 - 9 Pipe fitters

3 -2 Supervisors. Day
-25 pipe Fitters.
-1 Forklift Operator.
04/10/2017
05/08/2017 - 2 Supervisors. Night
- 20 Pipe fitter.
- 1 Fork lift operator.

4 05/09/2017 -2 Supervisors Day


05/13/2017 -18 pipe Fitters
-2 supervisors. Night
-15 Pipe fitter.
5 5/14/2017 -1 Supervisor. Day Only
5/20/2017 -8 Pipe fitters

2) Arabian Fal (Hydrojetting)


Stage Date Crew Note
1 04/13/2017 - 3 Hydrojetting crew. Day & Night
04/15/2017 - 2 Super Sucker Crew.
2 04/16/2017 -5 Hydrojetting Crew. Day & Night
05/07/2017 -3 Liquid Super Sucker.
3 04/23/2017 -1 Dry Super Sucker Day & Night
05/12/2017
4 05/08/2017 - 3 Hydrojetting crew. Day & Night
05/12/2017 - 2 Super Sucker Crew.

Other Contractors:

1) Grit Blasting & Coating (Qualified Techention)


Moblization date (Apr.21.2017)

2) Insulation (BinZagr)
Mobilization date (Mar.26.2017)

3) Torquing (Cooper Heat)


Monilization Date (Apr.12.2017)
4) Tube Bundle Removal (Osama Zainy)

E-305:
1st Removal (Apr.17.2017)
2nd Installion (Apr.29.2017)
3rd Removal (Mar.02.2017)
4th installion (Mar.04.2017)

Others:
Removal:
E-302 (Apr.17.2017)

Installion:
E-302 (Apr.17.2017)

5) Chemical Cleaning (Khushaim)


Mobilization date (Apr.25.2017)

6) Machining & Lapping (SAECO)


Upon Requist

7) Post Weld Heat Treatment (TCR Arabia)


Upon Requist

8) Remove Wasted Material (Bal Hareth)


Mobilization Date (Apr.14.2017)

9) Cladding Repair (Zamil)


Mobilization Date (Apr.17.2017)

10) Civil repairs:


Upon Requist

11) Scaffoldings (SGB Dabal)


Mobilization Date (Mar.26.2017)
Stand by 2 Crews Day & Night starting From (04/07/2017)

-END-