KARNATAKA POWER TRANSMISSION CORPORATION LIMITED

Estimate No: AE/TEL/2016-17/02 Date: 07.12.2016


Regularization of tentative work order for Replacement of flashed over 66KV CTs
for 20MVA power Transformer No-1, T & R make at 66/11KV Telecom layout
MUSS, Bangaluru-40.

T.W.O. 1)TWO/G-8/NRS/74.110/339 Dt.24.11.2016


T.W.O. 2)TWO/G-16/NRS/16.200/1102 Dt.24.11.2016

PART-A: MATERIAL PORTION.

Sl.No Particulars Unit Qty Rate Amount


66KV Class, 400-200/1-1-1A Current
Transformers with 0.2 accuracy class & 30VA
1 Burden. As per MWSR-2016 , Part-I, page No- Nos 3 95000.00 285000.00
3, Sl.no.01 C( 7 ).

Drake ACSR Conductor. As per MWSR-2016 ,


2 Part-I, Page No-12, Sl.no-7( c ). Km 0.02 242000.00 4840.00

Solid core Insulator for 66kV. As per MWSR-


3 2016, Part-I, Page No-12, Sl.no-8( c ). Nos 2 4685.25 9370.50

4 TOTAL 299210.50
Rounded of Rs. 299211.00
PART-B: LABOUR PORTION.

Sl.No Particulars Unit Qty Rate Amount


Erection of CTs and wiring including movement
from the point of unloading to the point of
erection. As per MWSR-2016, Part-II,Page.No- Set
1 64,Sl.no-19 of item no(a). 1 3322.00 3322.00
(3 Nos)

Fixing of solid core insulators. As per MWSR-


2 2016, Part-II,Page.No-65,Sl.no-23. Per stack 2 198.00 396.00

Supply of 12mm iron sheet of 2' X 1 1/2' (3Nos)


includes welding, cutting, providing holes,
3 connecting GI flats to existing groundings. As per bill supplied by LEC 10400.00

3 TOTAL 14118.00

PART-C: DISMANTLING LABOUR


Releasing of 66KV CTs. As per MWSR-2013 , Set
1 1 2491.5 2492
Part-II,,Page.No-73,Sl.no-43(iv). (3 Nos)

2 Releasing of 66KV Solid core Insulators. As per Nos 2 148.5 297


MWSR-2013 , Part-II,,Page.No-73,Sl.no-43(iv).
TOTAL 2789

Dismantling charges is 75% of erection charges in general


ABSTRACT:-

1 299210.50
PART-A: MATERIAL PORTION.

2 14118.00
PART-B: LABOUR PORTION.
3 PART-C : DISMANTLING LABOUR. 2788.50

4 316117.00
GRAND TOTAL

CREDIT/ 7th Schedule

Sl.No Particulars Unit Qty Rate Amount Remarks

CT Details:-
Ratio: 400-200/1-1-1A. B-phase 1 No CT
Burden: 30VA, Make:Indian transformers flashed over &
com(P) Ltd 2Nos CTs are
1 D.O.C: 26-12-2005 , YOM-2004. Nos 3 6240.00 18720.00
insulation failure
Sl.Nos: R Phase-6725-01, Y Phase-6725-18, B (As per RT report
Phase-6725-16 for TR-1 20MVA. (SCRAP) enclosed.)

2 Nos 2 5.00 10.00 Scrap


Solid core insulators

Certificate:

Certified that I have personally visited the spot and prepared estimate using current Schedule of rates -2016 at
most economical and safe execution of work.
Report:
This estimate for Rs 3,15,424.00( Three Lakhs fifteen Thousand four hundred and twenty four Only) has been
prepared to Regularization of tentative work order for Replacement of flashed over 66KV ( 20MVA power Transformer side ) 3
Nos CT's at 66/11KV Telecom layout MUSS. Out of this one CT was flashed over on 23.11.2016 and the other 2Nos CT's
were tested for Tan-delta by RT staff & found the values below the permissible limit. Therefore all the CT's were replaced &
tested for all values found ok.

It is also proposed to replace two number limbs of 66kV transformer GOS which were flashed over into pieces. The
line clear No-454 was availed to replace the CT's & GOS limbs on 25.11.2016 & line clear was returned on 27.11.2016 at
19:15hours & load was normalized.Two numbers of Solid core insulators are broken into pieces, since cannot be return to store
and also no valve. Hence this estimate may kindly be sanctioned.

Asst.Executive Engineer (Ele.) Assistant Engineer (Ele.)


KPTCL Ring Mains Sub-Division-II 66/11KV Telecom layout MUSS.
Chandra Layout, Bangaluru-40 Bangaluru-40
Executive Engineer (Ele)
KPTCL , 220/66KV R/S
Rajajinagar , Bangaluru-10.
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED

Estimate No: AE/TEL/2016-17/05 Date: .02.2017


Estimate for Replacement of faulty 66KV CTs of 20MVA power Transformer No-2
at 66/11kV Telecom layout MUSS, Bangaluru-40.

PART-A: MATERIAL PORTION.

Sl.No Particulars Unit Qty Rate Amount


66KV Class, 400-200/1-1-1A Current
Transformers with 0.2 accuracy class & 30VA
1 Burden. As per MWSR-2016 , Part-I, page No- Nos 3 95000.00 285000.00
3, Sl.no.01 C( 7 ).

Drake ACSR Conductor. As per MWSR-2016 ,


2 Part-I, Page No-12, Sl.no-7( c ). Km 0.02 242000.00 4840.00

4 TOTAL 289840.00

PART-B: LABOUR PORTION.

Sl.No Particulars Unit Qty Rate Amount


Erection of CTs and wiring including movement
from the point of unloading to the point of
erection. As per MWSR-2016, Part-II,Page.No- Set
1 64,Sl.no-19 of item no(a). 1 3322.00 3322.00
(3 Nos)

Supply of 12mm iron sheet of 2' X 1 1/2' (3Nos)


includes welding, cutting, providing holes,
3 connecting GI flats to existing groundings. As per bill supplied by LEC 10400.00

3 TOTAL 13722.00
PART-C: DISMANTLING LABOUR

Set
1 Releasing of 66KV CTs. As per MWSR-2013 , 1 2491.5 2491.50
(3 Nos)
Part-II,,Page.No-73,Sl.no-43(iv).
TOTAL 2492
Dismantling charges is 75% of erection charges in general
ABSTRACT:-

1 289840.00
PART-A: MATERIAL PORTION.

2 13722.00
PART-B: LABOUR PORTION.
3 PART-C : DISMANTLING LABOUR. 2491.50

4 306053.50
GRAND TOTAL
Rounded of Rs. 306054
CREDIT/ 7th Schedule

Sl.No Particulars Unit Qty Rate Amount

CT Details:-
Ratio: 400-200/1-1-1A.
Burden: 30VA, Make:Indian transformers
com(P) Ltd
1 D.O.C: 26-12-2005 , YOM-2004. Nos 3
Sl.Nos: R Phase-6725-14, Y Phase-6725-13, B
Phase-6725-17 of 20MVA power
transformerNo-2 .(SCRAP)

Certificate:
Certified that I have personally visited the spot and prepared estimate using current Schedule of rates of
MWSR -2016 at most economical and safe execution of work.
Report:
This estimate for Rs 3,06,054.00( Three Lakhs six Thousand and fifty four Only) has been
prepared for Replacement of 66KV ( 20MVA power Transformer-2 side ) 3 Nos CT's at 66/11KV
Telecom layout MUSS. RT staff visited the sub-station on 23.02.2017 and conducted Capacitance &
tan-delta test on 3Nos CT's of power transformer No-2, the results are found above the permissible
limits and suggested for immediate replacement to prevent further damage to the station
equipments. The provision for materials and labour is made in this estimate considering the rates of
MWSR-2016. Hence this estimate may kindly be sanctioned at the earliest.
Asst.Executive Engineer (Ele.) Assistant Engineer (Ele.)
KPTCL Ring Mains Sub-Division-II 66/11KV Telecom layout MUSS.
Chandra Layout, Bangaluru-40 Bangaluru-40

Executive Engineer (Ele)


KPTCL , 220/66KV R/S
Rajajinagar , Bangaluru-10.
TED
Remarks

3Nos CTs are


insulation failure
(As per RT report
enclosed.)

rrent Schedule of rates of

y four Only) has been


Nos CT's at 66/11KV
ducted Capacitance &
above the permissible
mage to the station
onsidering the rates of

er (Ele.)
ayout MUSS.