Anda di halaman 1dari 201

A B C D E F G H I J K L M N O

1 UNIVERSITAS KATOLIK WIDYA MANDIRA KUPANG


2 FAKULTAS TEKNIK JURUSAN SIPIL
3 FORMULIR TUGAS MANAJEMEN KONSTRUKSI

4 REKAPITULASI
5 RENCANA ANGGARAN BIAYA
6
7 PROYEK : PEMB. AKSES PELABUHAN TERMINAL ANTARA BANGSA
8 LOKASI : KAB. TTU
9
10 JUMLAH HARGA
NO ITEM PEKERJAANA
11 Rp
12 1 GALIAN BIASA 229,784,
13 2 PENYIAPAN BADAN JALAN 89,059,
14 3 LAPIS PONDASI AGREGAT KELAS A 288,178,
15 4 LAPIS PONDASI AGREGAT KELAS B 373,549,
16 5 LAPIS RESAP PENGIKAT - ASPAL CAIR 124,526,
17 6 LASTON LAPIS ANTARA (AC - BC) 538,085,
18 7 BETON MUTU SEDANG (K - 250) 15,388,
19 8 BAJA TULANGAN BJ 24 POLOS 18,157,
20

21

22

23 A SUB JUMLAH 1,676,730,


24 B OVERHEAD + PROFIT (10% X A) 167673011.3
25 C SUB JUMAH (A+B) 1,844,403,
26 D PAJAK (10 % X C) 184440312.4
27 JUMLAH TOTAL (C+D) 2,028,843,
28

29

30

31
P Q R S T U V
1

5
6
AL ANTARA BANGSA
7
8
9
10JUMLAH HARGA
11 Rp
12 229,784,100.70
13 89,059,261.35
14 288,178,212.68
15 373,549,766.92
16 124,526,497.92
17 538,085,740.45
18 15,388,959.01
19 18,157,574.04
20

21

22

23 1,676,730,113.08
24 167673011.308016
25 1,844,403,124.39
26 184440312.438817
27 2,028,843,436.83
28

29

30

31
UNIVERSITAS KATOLIK WIDYA MANDIRA KUPANG
FAKULTAS TEKNIK JURUSAN SIPIL
FORMULIR TUGAS MANAJEMEN KONSTRUKSI

REKAPITULASI
RENCANA ANGGARAN BIAYA
PROYEK : PEMB. AKSES PELABUHAN TERMINAL ANTARA BANGSA
LOKASI : KAB. TTU

JUMLAH HARGA
NO ITEM PEKERJAANA
Rp

1 GALIAN BIASA 229,784,1

2 PENYIAPAN BADAN JALAN 89,059,2

3 LAPIS PONDASI AGREGAT KELAS A 288,178,2

4 LAPIS PONDASI AGREGAT KELAS B 373,549,7

5 LAPIS RESAP PENGIKAT - ASPAL CAIR 124,526,4

6 LASTON LAPIS ANTARA (AC - BC) 538,085,7

7 BETON MUTU SEDANG (K - 250) 15,388,9

8 BAJA TULANGAN BJ 24 POLOS 18,157,5

A SUB JUMLAH 1,676,730,1

B OVERHEAD + PROFIT (10% X A) 167673011.3

C SUB JUMAH (A+B) 1,844,403,1

D PAJAK (10 % X C) 184440312.4

JUMLAH TOTAL (C+D) 2,028,843,4


Form 1a

ANTARA BANGSA

JUMLAH HARGA
Rp

229,784,100.70

89,059,261.35

288,178,212.68

373,549,766.92

124,526,497.92

538,085,740.45

15,388,959.01

18,157,574.04

1,676,730,113.08

167673011.308016

1,844,403,124.39

184440312.438817

2,028,843,436.83
UNIVERSITAS KATOLIK WIDYA MANDIRA KUPANG
FAKULTAS TEKNIK JURUSAN SIPIL
FORMULIR TUGAS MANAJEMEN KONSTRUKSI

REKAPITULASI
RENCANA ANGGARAN BIAYA

PROYEK : PEMB. AKSES PELABUHAN TERMINAL ANTARA BANGSA


LOKASI : KAB. TTU

NO ITEM PEKERJAAN SATUAN

1 GALIAN BIASA m3
2 PENYIAPAN BADAN JALAN m2
3 LAPIS PONDASI AGREGAT KELAS A m3
4 LAPIS PONDASI AGREGAT KELAS B m3
5 LAPIS RESAP PENGIKAT - ASPAL CAIR Ltr
6 LASTON LAPIS ANTARA (AC - BC) Ton
7 BETON MUTU SEDANG (K - 250) m3
8 BAJA TULANGAN BJ 24 POLOS kg
TERMINAL ANTARA BANGSA

HARGA SATUAN JUMLAH HARGA


VOLUME
(Rp) (Rp)
2,800.00 82,065.75 229,784,100.70
53,120.00 1,676.57 89,059,261.35
540.00 533,663.36 288,178,212.68
800.00 466,937.21 373,549,766.92
8,000.00 15,565.81 124,526,497.92
391.44 1,374,631.46 538,085,740.45
10.08 1,526,682.44 15,388,959.01
1,203.06 15,092.83 18,157,574.04
UNIVERSITAS KATOLIK WIDYA MANDIRA KUPANG
FAKULTAS TEKNIK JURUSAN SIPIL
FORMULIR TUGAS MANAJEMEN KONSTRUKSI

REKAPITULASI
RENCANA ANGGARAN BIAYA

PROYEK : PEMB. AKSES PELABUHAN TERMINAL ANTARA BANGSA


ITEM PEKERJAAN : GALIAN BIASA

LOKASI : KAB. TTU

VOLUME : 2,800.00 m3
HARGA SATUAN
NO ITEM PEKERJAAN SATUAN KOEFISIEN
(Rp)

A TENAGA KERJA

1 Pekerja Jam 0.3375 7,650.00

2 Mandor Jam 0.1125 11,000.00

SUB JUMLAH A

B MATERIAL

1 - - - -

SUB JUMLAH B

C PERALATAN

1 Exavator Jam 0.1125 522,901.00

2 Dump Truck Jam 0.0460 257,815.00

3 Alat Bantu Ls 1.0000 100.00

SUB JUMLAH C

JUMLAH TOTAL (A+B+C

BIAYA UMUM DAN KEUNTUNGAN =10% x D

HARGA SATUAN = (D+E


ITEM PEKERJAAN : PENYIAPAN BADAN JALAN

VOLUME : 53,120.00 m2
HARGA SATUAN
NO ITEM PEKERJAAN SATUAN KOEFISIEN
(Rp)

A TENAGA KERJA

1 Pekerja Jam 0.0071 7,650.00

2 Mandor Jam 0.0018 11,000.00

SUB JUMLAH A

B MATERIAL

1 - - - -

SUB JUMLAH B

C PERALATAN

1 Motor Grader Jam 0.0005 388,598.0

2 Vibrator Roller Jam 0.0018 334,399.0

3 Water Tank Jam 0.0028 215,650.0

4 Alat Bantu Ls 1.0000 50.0

SUB JUMLAH C

JUMLAH TOTAL (A+B+C

BIAYA UMUM DAN KEUNTUNGAN =10% x D

HARGA SATUAN = (D+E


ITEM PEKERJAAN : LAPIS PONDASI AGREGAT KELAS A

VOLUME : 540.00 m3
HARGA SATUAN
NO ITEM PEKERJAAN SATUAN KOEFISIEN
(RP)

A TENAGA KERJA

1 Pekerja Jam 0.3125 7,650.00

2 Mandor Jam 0.0625 11,000.00

SUB JUMLAH A

B MATERIAL

1 Material Agregat Kelas A M3 1.2000 321,568.0

SUB JUMLAH B

C PERALATAN

1 Wheal Loader Jam 0.0625 337,643.0

2 Dump Truck Jam 0.2301 257,815.0

3 Motor Grader Jam 0.0208 388,598.0

4 Vibrator Roller Jam 0.0162 334,399.0

5 Water Tank Jam 0.0104 215,650.0

6 Alat Bantu Ls 1.0000 20.0

SUB JUMLAH C

JUMLAH TOTAL (A+B+C

BIAYA UMUM DAN KEUNTUNGAN =10% x D

HARGA SATUAN = (D+E


ITEM PEKERJAAN : LAPIS PONDASI AGREGAT KELAS B

VOLUME : 800.00 m3
HARGA SATUAN
NO ITEM PEKERJAAN SATUAN KOEFISIEN
(RP)

A TENAGA KERJA

1 Pekerja Jam 0.1563 7,650.00

2 Mandor Jam 0.0313 11,000.00

SUB JUMLAH A

B MATERIAL

1 Material Pilihan M3 1.200 280,439.00

SUB JUMLAH B

C PERALATAN

1 Wheal Loader Jam 0.0313 337,643.00

2 Dump Truck Jam 0.2651 257,815.00

3 Motor Grader Jam 0.0052 388,598.00

4 Vibro Roller Jam 0.0091 334,399.00

5 Water Tanker Jam 0.0104 215,659.00

6 Alat Bantu Ls 1.0000 200.00

SUB JUMLAH C

JUMLAH TOTAL (A+B+C

BIAYA UMUM DAN KEUNTUNGAN =10% x D

HARGA SATUAN = (D+E


ITEM PEKERJAAN : LAPIS RESAP PENGIKAT - ASPAL CAIR

VOLUME : 8,000.00 ltr


HARGA SATUAN
NO ITEM PEKERJAAN SATUAN KOEFISIEN
(Rp)

A TENAGA KERJA

1 Pekerja Jam 0.0032 7,650.00

2 Mandor Jam 0.0003 11,000.00

3 SUB JUMLAH A

B MATERIAL

1 Aspal kg 0.6922 13,250.00

2 Kerosin Ltr 0.3780 12,000.00

SUB JUMLAH B

C PERALATAN

1 Asphalt Distributor Jam 0.0003 252,493.00

2 Air Compresor Jam 0.0023 147,635.00

SUB JUMLAH C

JUMLAH TOTAL (A+B+C

BIAYA UMUM DAN KEUNTUNGAN =10% x D

HARGA SATUAN = (D+E


ITEM PEKERJAAN : LASTON LAPIS ANTARA (AC - BC)

VOLUME : 391.44 ton


HARGA SATUAN
NO ITEM PEKERJAAN SATUAN KOEFISIEN
(RP)

A TENAGA KERJA

1 Pekerja Jam 0.1961 7,650.00

2 Mandor Jam 0.0196 11,000.00

SUB JUMLAH A

B MATERIAL

1 Agregat 5-10 & 10-15 m3 0.3910 346,478.00

2 Agregat 0-5 m3 0.2729 380,643.00

3 Filler kg 10.5000 1,450.00

4 Aspal cair kg 58.7100 13,250.00

SUB JUMLAH B

C PERALATAN

1 Wheel Loader Jam 0.0106 337,643.00

2 AMP Jam 0.0196 6,548,792.00

3 Genset Jam 0.0196 324,283.00

4 Dump Truck Jam 0.2402 257,815.00

5 Asphalt Finisher Jam 0.0095 611,868.00

6 Tandem Roller Jam 0.0093 329,304.00

7 P. Tire Roller Jam 0.0040 343,152.00

8 Alat Bantu LS 1.0000 5,000.00

SUB JUMLAH C

JUMLAH TOTAL (A+B+C

BIAYA UMUM DAN KEUNTUNGAN =10% x D

HARGA SATUAN = (D+E


ITEM PEKERJAAN : BETON MUTU SEDANG (K - 250)

VOLUME : 10.08 m3
HARGA SATUAN
NO ITEM PEKERJAAN SATUAN KOEFISIEN
(Rp)

A TENAGA KERJA

1 Pekerja Jam 12.5000 7,650.00

2 Mandor Jam 1.0417 11,000.00

3 Tukang Jam 4.1667 9,500.00

SUB JUMLAH A

B MATERIAL

1 Batu Pecah m3 0.8883 310,659.00

2 Semen Kg 481.7500 1,450.00

3 Pasir m3 0.4215 90,000.00

4 Kayu Perancah Ls 0.1500 1,500,000.00

5 Paku kg 1.8000 7,500.00

SUB JUMLAH B

C PERALATAN

1 Concrete Mixer Jam 1.0417 57,377.0

2 Concrete Vibrator Jam 1.0417 42,027.0

3 Water Tank Jam 0.1147 215,650.0

4 Alat Bantu Ls 1.0000 800.0

SUB JUMLAH C

JUMLAH TOTAL (A+B+C

BIAYA UMUM DAN KEUNTUNGAN =10% x D

HARGA SATUAN = (D+E


ITEM PEKERJAAN : BAJA TULANGAN BJ 24 POLOS

VOLUME : 1,203.06 kg
HARGA SATUAN
NO ITEM PEKERJAAN SATUAN KOEFISIEN
(Rp)

A TENAGA KERJA

1 Pekerja Jam 0.1050 7,650.00

2 Mandor Jam 0.0350 11,000.00

3 Tukang Jam 0.0350 9,500.00

SUB JUMLAH A

B MATERIAL

1 Besi Beton kg 1.1000 1050

2 Kawat Baja kg 0.0200 2000

SUB JUMLAH B

C PERALATAN

3 Alat Bantu Ls 1.0000 250.00

SUB JUMLAH C

JUMLAH TOTAL (A+B+C

BIAYA UMUM DAN KEUNTUNGAN =10% x D

HARGA SATUAN = (D+E


INAL ANTARA BANGSA

HARGA SATUAN JUMLAH HARGA


(Rp) (Rp)

7,650.00 2,581.88

11,000.00 1,237.50

SUB JUMLAH A 3,819.38

- -

SUB JUMLAH B 0.00

522,901.00 58,826.36

257,815.00 11,859.49

100.00 100.00

SUB JUMLAH C 70,785.85

JUMLAH TOTAL (A+B+C) 74,605.23

UMUM DAN KEUNTUNGAN =10% x D 7,460.52

HARGA SATUAN = (D+E) 82,065.75


HARGA SATUAN JUMLAH HARGA
(Rp) (Rp)

7,650.00 54.32

11,000.00 19.80

SUB JUMLAH A 74.12

- -

SUB JUMLAH B 0.00

388,598.00 194.30

334,399.00 601.92

215,650.00 603.82

50.00 50.00

SUB JUMLAH C 1,450.04

JUMLAH TOTAL (A+B+C) 1,524.15

UMUM DAN KEUNTUNGAN =10% x D 152.42

HARGA SATUAN = (D+E) 1,676.57


HARGA SATUAN JUMLAH HARGA
(RP) (Rp)

7,650.00 2,390.63

11,000.00 687.50

SUB JUMLAH A 3,078.13

321,568.00 385,881.60

SUB JUMLAH B 385,881.60

337,643.00 21,102.69

257,815.00 59,323.23

388,598.00 8,082.84

334,399.00 5,417.26

215,650.00 2,242.76

20.00 20.00

SUB JUMLAH C 96,188.78

JUMLAH TOTAL (A+B+C) 485,148.51

UMUM DAN KEUNTUNGAN =10% x D 48,514.85

HARGA SATUAN = (D+E) 533,663.36


HARGA SATUAN JUMLAH HARGA
(RP) (Rp)

7,650.00 1,195.70

11,000.00 344.30

SUB JUMLAH A 1,540.00

280,439.00 336,526.80

SUB JUMLAH B 336,526.80

337,643.00 10,568.23

257,815.00 68,346.76

388,598.00 2,020.71

334,399.00 3,043.03

215,659.00 2,242.85

200.00 200.00

SUB JUMLAH C 86,421.58

JUMLAH TOTAL (A+B+C) 424,488.37

UMUM DAN KEUNTUNGAN =10% x D 42,448.84

HARGA SATUAN = (D+E) 466,937.21


HARGA SATUAN JUMLAH HARGA
(Rp) (Rp)

7,650.00 24.48

11,000.00 3.30

SUB JUMLAH A 27.78

13,250.00 9,171.650

12,000.00 4,536.000

SUB JUMLAH B 13,707.65

252,493.00 75.75

147,635.00 339.56

SUB JUMLAH C 415.31

JUMLAH TOTAL (A+B+C) 14,150.74

UMUM DAN KEUNTUNGAN =10% x D 1,415.07

HARGA SATUAN = (D+E) 15,565.81


HARGA SATUAN JUMLAH HARGA
(RP) (Rp)

7,650.00 1,500.17

11,000.00 215.60

SUB JUMLAH A 1,715.77

346,478.00 135,472.90

380,643.00 103,877.47

1,450.00 15,225.00

13,250.00 777,907.50

SUB JUMLAH B 1,032,482.87

337,643.00 3,579.02

6,548,792.00 128,356.32

324,283.00 6,355.95

257,815.00 61,927.16

611,868.00 5,812.75

329,304.00 3,062.53

343,152.00 1,372.61

5,000.00 5,000.00

SUB JUMLAH C 215,466.33

JUMLAH TOTAL (A+B+C) 1,249,664.97

UMUM DAN KEUNTUNGAN =10% x D 124,966.50

HARGA SATUAN = (D+E) 1,374,631.46


HARGA SATUAN JUMLAH HARGA
(Rp) (Rp)

7,650.00 95,625.00

11,000.00 11,458.70

9,500.00 39,583.65

SUB JUMLAH A 146,667.35

310,659.00 275,958.39

1,450.00 698,537.50

90,000.00 37,935.00

1,500,000.00 225,000.00

7,500.00 13,500.00

SUB JUMLAH B 1,250,930.89

57,377.00 59,769.62

42,027.00 43,779.53

215,650.00 24,735.06

800.00 800.00

SUB JUMLAH C 129,084.20

JUMLAH TOTAL (A+B+C) 1,526,682.44

UMUM DAN KEUNTUNGAN =10% x D 152,668.24

HARGA SATUAN = (D+E) 1,679,350.69


HARGA SATUAN JUMLAH HARGA
(Rp) (Rp)

7,650.00 803.25

11,000.00 385.00

9,500.00 332.50

SUB JUMLAH A 1,520.75

10500 11,550.00

20000 400.00

SUB JUMLAH B 11,950.00

250.00 250.00

SUB JUMLAH C 250.00

JUMLAH TOTAL (A+B+C) 13,720.75

UMUM DAN KEUNTUNGAN =10% x D 1,372.08

HARGA SATUAN = (D+E) 15,092.83


UNIVERSITAS KATOLIK WIDYA MANDIRA KUPANG
FAKULTAS TEKNIK JURUSAN SIPIL
FORMULIR TUGAS MENEJEMEN KONSTRUKI

HARGA SATUAN SUMBERDAYA


PROYEK : PEMB. AKSES PELABUHAN TERMINAL ANTARA BANGSA

LOKASI : 0

NO SUMBERDAYA SATUAN

A TENAGA KERJA

1 MANDOR Jam

2 PEKERJA Jam

3 TUKANG Jam

B MATERIAL

1 AGREGAT KELAS A m3

2 AGREGAT KELAS B m3

3 ASPAL kg

4 KEROSIN Ltr

5 AGREGAT 5-10 & 10-15 m3

6 AGREGAT 0-5 m3

7 FILLER kg

8 ASPAL CAIR kg

9 BATU PECAH m3

10 SEMEN (PC) kg

11 PASIR m3

12 KAYU PERANCAH LS

13 PAKU kg

14 BESI BETON kg

15 KAWAT kg

C PERALATAN

1 EXAVATOR Jam

2 DUMP TRUCK Jam

3 MOTOR GRADER Jam

4 VIBRO ROLLER Jam


5 WATER TANK TRUCK Jam

6 WHEEL LOADER Jam

7 ASPHALT DISTRIBUTOR Jam

8 AIR COMPRESSOR Jam

9 AMP Jam

10 GENSET Jam

11 ASPHALT FINISHER Jam

12 TANDEM ROLLER Jam

13 P. TIRE ROLLER Jam

14 CONCRETE MIXER Jam

15 CONCRETE VIBRATOR Jam

15 ALAT BANTU LS
HARGA SATUAN (Rp)

11,000.00

7,650.00

9,500.00

321,568.00

280,439.00

13,250.00

12,000.00

346,478.00

380,643.00

1,450.00

13,250.00

310,659.00

1,450.00

90,000.00

1,500,000.00

7,500.00

10,500.00

20,000.00

522,901.00

257,815.00

388,598.00

334,399.00
215,650.00

337,643.00

252,493.00

147,635.00

6,548,792.00

324,283.00

611,868.00

329,304.00

343,152.00

57,377.00

42,027.00

5,000.00
PRODUKSI DAN WAKTU PENYELESAIAN ITEM PEKERJAAN
PROYEK : PEMB. AKSES PELABUHAN TERMINAL ANTARA BANGSA
LOKASI : KAB. TTU

VOLUME KEBUTUHAN SUMBER DAYA PROD


NO ITEM PEKERJAAN KUANTITAS KOEFISIEN TOTAL (UNIT
1 2 3 4 5 = 3x 4 6=(
1 GALIAN BIASA (m3) 2800.00
TENAGA KERJA
Pekerja (jam) 0.3375 0.3375 0.1125 = 3 1
Mandor (jam) 0.1125 0.1125 0.1125 = 1 1
MATERIAL

PERALATAN
Excavator (jam) 0.1125 8.89 8.89 = 1 1
Dump Truck (jam) 0.0460 8.89 21.74 = 0.41 1
Alat Bantu (Ls) 1.0000 1.000
2 PENYIAPAN BADAN JALAN (m2) 53,120.00
TENAGA KERJA
Pekerja (jam) 0.0071 0.0071 0.0018 = 4 1
Mandor (jam) 0.0018 0.0018 0.0018 = 1 1
MATERIAL

PERALATAN
Motor Grader (jam) 0.0005 555.56 2000.00 = 0.28 1
Vibrator Roller (jam) 0.0018 555.56 555.56 = 1 1
Water Tank (jam) 0.0028 555.56 357.14 = 1.56 1
Alat Bantu (Ls) 1.0000 1
3 LAPISAN PONDASI AGREGAT KELAS A (m3) 540.00
TENAGA KERJA
Pekerja (jam) 0.3125 0.3125 0.0625 = 5 1
Mandor (jam) 0.0625 0.0625 0.0625 = 1 1
MATERIAL
Agregat kelas A (m3) 1.2000 540.00 x 1.2000 = 648.00
PERALATAN
Wheal Loader (jam) 0.0625 16.00 16.00 = 1.00 1
Dump Truck (jam) 0.2301 16.00 4.35 = 3.68 1
Motor Grader (jam) 0.0208 16.00 48.08 = 0.33 1
Vibrator Roller (jam) 0.0162 16.00 61.73 = 0.26 1
Water Tank (jam) 0.0104 16.00 96.15 = 0.17 1
Alat Bantu (Ls) 1.0000 1
4 LAPISAN PONDASI AGREGAT KELAS B (m3) 800.00
TENAGA KERJA
Pekerja (jam) 0.1563 0.1563 0.0313 = 5 1
Mandor (jam) 0.0313 0.0313 0.0313 = 1 1
MATERIAL
Agregat base kelas B (m3) 1.2000 800.00 x 1.2000 = 960.00
PERALATAN
Wheal Loader (jam) 0.0313 31.95 31.95 = 1.00 1
Dump Truck (jam) 0.2651 31.95 3.77 = 8.47 1
Motor Grader (jam) 0.0052 31.95 192.31 = 0.17 1
Vibrator Roller (jam) 0.0091 31.95 109.89 = 0.29 1
Water Tank (jam) 0.0104 31.95 96.15 = 0.33 1
Alat Bantu (Ls) 1.0000 1.00
5 LAPIS RESAP PENGIKAT - ASPAL CAIR (Ltr) 8,000.00
TENAGA KERJA
Pekerja (jam) 0.0032 0.0032 0.0003 = 11 1
Mandor (jam) 0.0003 0.0003 0.0003 = 1 1
MATERIAL
Aspal (kg) 0.6922 8,000.00 x 0.6922 = 5537.60
Kerosene (Liter) 0.3780 8,000.00 x 0.3780 = 3024.00
PERALATAN
Aspalt Distributor (jam) 0.0003 3,333.33 3333.3333 = 1.00 1
Air Kompresor (jam) 0.0023 3,333.33 434.7826 = 7.67 1
6 LASTON LAPIS ANTARA (AC - BC) (GRADASI HALUS/KASAR) (TON) 391.44
TENAGA KERJA
Pekerja (jam) 0.1961 0.1961 0.0196 = 10 1
Mandor (jam) 0.0196 0.0196 0.0196 = 1 1
MATERIAL
Agregat 5-10 dan 10-15 (m3) 0.3910 391.44 x 0.3910 = 153.05
Agregat 0-5 (m3) 0.2729 391.44 x 0.2729 = 106.82
Fillet (kg) 10.5000 391.44 x 10.5000 = 4,110.12
Aspal cair (kg) 58.7100 391.44 x 58.7100 = 22,981.44
PERALATAN
Wheal Loader (jam) 0.0106 51.02 / 94.34 = 0.54 1
AMP (jam) 0.0196 51.02 / 51.02 = 1 1
Genset (JAM) 0.0196 51.02 / 51.02 = 1 1
Dump Truck (jam) 0.2402 51.02 / 4.16 = 12.26 1
Asphalt Finisher (jam) 0.0095 51.02 / 105.26 = 0.48 1
Tandem Roller (jam) 0.0093 51.02 / 107.53 = 0.47 1
P.Tire Roller (jam) 0.0040 51.02 / 250.00 = 0.20 1
Alat Bantu (Ls) 1.0000 1.000
7 BETON MUTU SEDANG (K - 250) (m3) 10.08
TENAGA KERJA
Pekerja (jam) 12.5000 12.5000 1.0417 = 12 1
Mandor (jam) 1.0417 1.0417 1.0417 = 1 1
Tukang (jam) 4.1667 4.1667 1.0417 = 4 1
MATERIAL
Batu kali (m3) 0.8883 10.08 x 0.8883 = 8.95
Semen (zak) 481.7500 10.08 x 481.7500 = 4,856.04
Pasir (m3) 0.4215 10.08 x 0.4215 = 4.25
Kayu Perancah (Ls) 0.1500 10.08 x 0.1500 = 1.51
Paku (Kg) 1.8000 10.08 x 1.8000 = 18.14
PERALATAN
Concrert Mixer (jam) 1.0417 0.96 0.96 = 1 1
Concrert Vibrator (jam) 1.0417 0.96 0.96 = 1 1
Water Tank (jam) 0.1147 0.96 8.72 = 0.11 1
Alat Bantu (Ls) 1.0000 1.000
8 BAJA TULANGAN BJ 24 POLOS (Kg) 1203.06
TENAGA KERJA
Pekerja (jam) 0.1050 0.1050 0.0350 = 3 1
Mandor (jam) 0.0350 0.0350 0.0350 = 1 1
Tukang (jam) 0.0350 0.0350 0.0350 = 1 1
MATERIAL
Besi Beton (kg) 1.1000 1,203.06 x 1.1000 = 1,323.37
Kawat Baja (kg) 0.0200 1,203.06 x 0.0200 = 24.06
PERALATAN
Alat Bantu 1.0000
PRODUKSI PRODUKSI WAKTU PENYELESAIAN KEBUTUHAN SUMBER DAYA
(UNIT/JAM) (UNIT/HARI) (HARI) (PER- HARI)
6 = (1)/3 7 = 6 x Jef 8 = 3/Qmin 9 = 4 x Qmin
J.eff = 7 jam Qmin = 62.22

0.3375 x 3 = 8.89 8.89 x 7 = 62.22 2800.00 62.22 = 45.00 3 Orang


0.1125 x 1 = 8.89 8.89 x 7 = 62.22 1 Orang

0.1125 = 8.89 8.89 x 7 = 62.22 1 Unit


0.0460 = 21.74 21.74 x 7 = 152.17 0.41 Unit
1.0
J.eff = 7 jam Qmin 2,500.00

0.0071 x 4 = 555.56 555.56 x 7 = 3,888.89 53,120 2,500.00 = 21.25 4 Orang


0.0018 x 1 = 555.56 555.56 x 7 = 3,888.89 1 Orang

0.0005 = 2,000.00 2000.00 x 7 = 14,000.00 0.28 Unit


0.0018 = 555.56 555.56 x 7 = 3,888.89 1.00 Unit
0.0028 = 357.14 357.14 x 7 = 2,500.00 1.56 Unit
1.00
J.eff = 7 jam Qmin = 30.42

0.3125 x 5 = 16.00 16.00 x 7 = 112.00 540.00 30.42 = 17.75 5 Orang


0.0625 x 1 = 16.00 16.00 x 7 = 112.00 1 Orang

36.51

0.0625 = 16.00 16.00 x 7 = 112.00 1.00 Unit


0.2301 = 4.35 4.35 x 7 = 30.42 3.68 Unit
0.0208 = 48.08 48.08 x 7 = 336.54 0.33 Unit
0.0162 = 61.73 61.73 x 7 = 432.10 0.26 Unit
0.0104 = 96.15 96.15 x 7 = 673.08 0.17 Unit
1.000
J.eff = 7 jam Qmin = 26.41

0.1563 x 5 = 31.95 31.95 x 7 = 223.64 800.00 26.41 = 30.30 5 Orang


0.0313 x 1 = 31.95 31.95 x 7 = 223.64 1 Orang

31.69

0.03130 = 31.95 31.95 x 7 = 223.64 1.00 Unit


0.26510 = 3.77 3.77 x 7 = 26.41 8.47 Unit
0.00520 = 192.31 192.31 x 7 = 1,346.15 0.17 Unit
0.00910 = 109.89 109.89 x 7 = 769.23 0.29 Unit
0.01040 = 96.15 96.15 x 7 = 673.08 0.33 Unit
1.00
J.eff = 7 jam Qmin = 3,043.48

0.0032 x 11 = 3,333.33 3,333.33 x 7 = 23,333.33 8000.00 3,043.48 = 2.63 11 Orang


0.0003 x 1 = 3,333.33 3,333.33 x 7 = 23,333.33 1 Orang

2,106.70
1,150.43

0.0003 = 3,333.333 3333.33 x 7 = 23,333.33 1.00 Unit


0.0023 = 434.783 434.78 x 7 = 3,043.48 7.67 Unit
J.eff = 7 jam Qmin = 29.14

0.1961 x 10 = 51.02 51.02 x 7 = 357.14 391.44 29.14 = 13.43 10 Orang


0.0196 x 1 = 51.02 51.02 x 7 = 357.14 1 Orang

11.39
7.95
306.00
1,710.95

0.0106 = 94.34 94.340 x 7 = 660.38 0.54 Unit


0.0196 = 51.02 51.020 x 7 = 357.14 1.00 Unit
0.0196 = 51.02 51.020 x 7 = 357.14 1.00 Unit
0.2402 = 4.16 4.163 x 7 = 29.14 12.26 Unit
0.0095 = 105.26 105.263 x 7 = 736.84 0.48 Unit
0.0093 = 107.53 107.527 x 7 = 752.69 0.47 Unit
0.0040 = 250.00 250.000 x 7 = 1,750.00 0.20 Unit
1.0
J.eff = 7 jam Qmin = 6.72

12.5000 x 12 = 0.96 0.96 x 7 = 6.72 10.08 6.72 = 1.50 12 Orang


1.0417 x 1 = 0.96 0.96 x 7 = 6.72 1 Orang
4.1667 x 4 = 0.96 0.96 x 7 = 6.72 4 Orang

5.97
3,237.26
2.83
1.01
12.10

1.042 = 0.96 0.960 x 7 = 6.72 1.00 Unit


1.042 = 0.96 0.960 x 7 = 6.72 1.00 Unit
0.115 = 8.72 8.718 x 7 = 61.03 0.11 Unit
1.0
J.eff = 7 jam Qmin = 200.00

0.1050 x 3 = 28.57 28.57 x 7 = 200.00 1203.06 200.00 = 6.02 3 Orang


0.0350 x 1 = 28.57 28.57 x 7 = 200.00 1 Orang
0.0350 x 1 = 28.57 28.57 x 7 = 200.00 1 Orang

220.00
4.00
TANGGAL MULAI 10 JUNI 2015 s.d 6 DESEMBER 2015 (180) HARI KERJA

ESTIMASI HARI KERJA EFEKTIF DALAM 5 BULAN MASA PELAKSANAAN


TAHUN 2015

NO BULAN HARI SELAIN HARI MINGGU HARI HARI KETERANGAN HARI LIBUR

MINGGU LIBUR

A B C D E F

1 JUNI 18 3 0

2 JULI 27 4 0

3 AGUSTUS 25 5 1 HARI KEMERDEKAAN

4 SEPTEMBER 26 4 0

5 OKTOBER 27 4 0

6 NOVEMBER 25 5 0

7 DESEMBER 5 1 0

S TOTAL 153 26 1

JUMLAH HARI TIDAK BEKERJA : S (D+E) = 26 + 1 = 27 HARI

HARI KERJA EFEKTIF : S C- S E = 153 - 1 = 152 HARI


CATATAN:

ESTIMASI PELAKSANAAN PROYEK TAHUN 2015 MULAI PADA AWAL MINGGU KEDUA YAITU TGL 10 BULAN JUNI

ESTIMASI WAKTU KERJA EFEKTIF DALAM HARI KERJA EFEKTIF

NO WAKTU KERJA SEHARI WAKTU MAKAN WAKTU LAIN-LAIN WAKTU KERJA EFEKTIF

A B C D E=B-C-D

1 9 1 1 7

CATATAN: JADI WAKTU EFEKTIF DALAM 1 HARI KERJA ADALAH 7 JAM


= HARI AWAL PELAKSANAAN PROYEK

= HARI LIBUR

= HARI AKHIR PELAKSANAAN PROYEK


KELENDER TAHUN 2015

BULAN JUNI

HARI LIBUR MINGGU SENIN SELASA RABU KAMIS JUMAT SABTU

1 2 3 4 5 6

7 8 9 10 11 12 13

14 15 16 17 18 19 20

21 22 23 24 25 26 27

RDEKAAN 28 29 30

BULAN JULI

MINGGU SENIN SELASA RABU KAMIS JUMAT SABTU

1 2 3 4

5 6 7 8 9 10 11

12 13 14 15 16 17 18

19 20 21 22 23 24 25
26 27 28 29 30 31

BULAN AGUSTUS

MINGGU SENIN SELASA RABU KAMIS JUMAT SABTU

2 3 4 5 6 7 8
ERJA EFEKTIF
9 10 11 12 13 14 15

16 17 18 19 20 21 22

=B-C-D 23 24 25 26 27 28 29

7 30 31

BULAN SEPTEMBER

MINGGU SENIN SELASA RABU KAMIS JUMAT SABTU

1 2 3 4 5

6 7 8 9 10 11 12

13 14 15 16 17 18 19
20 21 22 23 24 25 26

27 28 29 30

BULAN OKTOBER

MINGGU SENIN SELASA RABU KAMIS JUMAT SABTU

1 2 3

4 5 6 7 8 9 10

11 12 13 14 15 16 17

18 19 20 21 22 23 24

25 26 27 28 29 30 31

BULAN NOVEMBER

MINGGU SENIN SELASA RABU KAMIS JUMAT SABTU

1 2 3 4 5 6 7

8 9 10 11 12 13 14

15 16 17 18 19 20 21

22 23 24 25 26 27 28

29 30
BULAN DESEMBER

MINGGU SENIN SELASA RABU KAMIS JUMAT SABTU

1 2 3 4 5

6 7 8 9 10 11 12

13 14 15 16 17 18 19

20 21 22 23 24 25 26

27 28 29 30 31
UNIVERSITAS KATOLIK WIDYA MANDIRA KUPANG

FAKULTAS TEKNIK JURUSAN SIPIL

FORMULIR TUGAS MENEJEMEN KONSTRUKI

BOBOT KEGIATAN

PROYEK :
LOKASI :

NO ITEM PEKERJAAN SATUAN VOLUME

1 GALIAN BIASA m3 2,800.00

2 PENYIAPAN BADAN JALAN m2 53,120.00

3 LAPIS PONDASI AGREGAT KELAS A m3 540.00

4 LAPIS PONDASI AGREGAT KELAS B m3 800.00

5 LAPIS RESAP PENGIKAT - ASPAL CAIR Ltr 8,000.00

6 LASTON LAPIS ANTARA (AC - BC) Ton 391.44

7 BETON MUTU SEDANG (K - 250) m3 10.08

8 BAJA TULANGAN BJ 24 POLOS kg 1,203.06

JUMLAH
JUMLAH BOBOT WAKTU PENYELESAIAN

HARGA % (HARI)

229,784,100.70 13.70 45.00

89,059,261.35 5.31 21.25

288,178,212.68 17.19 17.75

373,549,766.92 22.28 30.30

124,526,497.92 7.43 2.63

538,085,740.45 32.09 13.43

15,388,959.01 0.92 1.50

18,157,574.04 1.08 6.02

1,676,730,113.08 100 137.87


UNIVERSITAS KATOLIK WIDYA MANDIRA KUPANG
FAKULTAS TEKNIK JURUSAN SIPIL
FORMULIR TUGAS MANAJEMEN KONSTRUKSI

JADWAL PELAKSANAAN PEKERJAAN


PROYEK :
LOKASI :

ITEM PEKERJAAN BOBOT WAKTU Bulan juni Bulan Juli


NO. Minggu PENYELESAIAN 1 2 3 4 1 2
%
Hari Kerja Efektif (HARI) 6 6 6 6 6 4
1.83 1.83 1.83 1.83 1.83 1.22
1 GALIAN BIASA 13.70 45.00

PENYIAPAN BADAN JALAN 5.31 21.25


2

LAPIS PONDASI AGREGAT KELAS A 17.19 17.75


3

LAPIS PONDASI AGREGAT KELAS B 22.28 30.30


4

LAPIS RESAP PENGIKAT - ASPAL CAIR 7.43 2.63


5

LASTON LAPIS ANTARA (AC - BC) 32.09 13.43


6

BETON MUTU SEDANG (K - 250) 0.92 1.50


7

BAJA TULANGAN BJ 24 POLOS 1.08 6.02


8
Jumlah (%) 100 137.87 1.83 1.83 1.83 1.83 1.83 1.22
Kumulatif (%) - 0 1.83 3.65 5.48 7.31 9.14 10.35
Realisasi (%)
Deviasi (%)

catatan : waktu penyelesaian proyek kurang dari waktu estimasi awal


hal ini untuk antisipasi kemungkinan terjadi hal-hal yang di luar dugaan seperti hujan, dan lain-lain
Form 5b

Bulan Juli Bulan agustus Bulan sepember Bulan oktober


3 4 1 2 3 4 1 2 3 4 1 2 3 4
6 6 6 5 6 6 6 6 6 5 6 6 5 6
1.83 1.52

1.50 1.50 1.50 0.81

4.84 5.81 5.81 0.73

3.68 4.41 4.41 4.41 4.41 0.95

7.43

14.34 11.95 5.81

0.92

1.08 0.003

3.33 3.02 1.50 9.33 10.22 10.22 5.14 4.41 22.72 11.95 6.89 0.92
13.68 16.70 18.20 27.53 37.76 47.98 53.12 57.53 80.24 92.19 99.08 100.00
45.00 40 5.000000
21.25 18 3.248000
17.75 17 0.750571
30.30 29 1.297143
2.63 6 2.628571
13.43 11 2.431984

6.02 6 0.015300

13.6
5.27
17.75
22.1
7.37
31.84
1
1.07
100
JADWAL KEBUTUHAN TENAGA KERJA
PROYEK :
LOKASI :
ITEM PEKERJAAN Bulan juni Bulan Juli
WP
NO MINGGU 1 2 3 4 1 2 3 4
HARI KERJA EFEKTIF (HARI) 6 6 6 6 6 4 6 6
1 GALIAN BIASA 45.00 2 2 2 2 2 2 2 2
Pekerja 3 Orang 3 3 3 3 3 3 3 3
Mandor 1 Orang 1 1 1 1 1 1 1 1
2 PENYIAPAN BADAN JALAN 21.25 2 2
Pekerja 4 Orang 4 4
Mandor 1 Orang 1 1
3 LAPIS PONDASI AGREGAT KELAS A 17.75
Pekerja 5 Orang
Mandor 1 Orang
4 LAPIS PONDASI AGREGAT KELAS B 30.30
Pekerja 5 Orang
Mandor 1 Orang
5 LAPIS RESAP PENGIKAT - ASPAL CAIR 2.63
Pekerja 11 Orang
Mandor 1 Orang
6 LASTON LAPIS ANTARA (AC - BC) 13.43
Pekerja 10 Orang
Mandor 1 Orang
7 BETON MUTU SEDANG (K - 250) 1.50
Pekerja 12 Orang
Mandor 1 Orang
Tukang 4 Orang
8 BAJA TULANGAN BJ 24 POLOS 6.02
Pekerja 3 Orang
Mandor 1 Orang
Tukang 1 Orang
JUMLAH TENAGA KERJA
PEKERJA 3 3 3 3 3 3 7 7
MANDOR 1 1 1 1 1 1 2 2
TUKANG
Bulan agustus Bulan sepember
1 2 3 4 1 2 3
6 5 6 6 6 6 6

2 2
4 4
1 1
2 2 2 2
5 5 5 5
1 1 1 1
2 2 2 2 2 2
5 5 5 5 5 5
1 1 1 1 1 1
2
11
1
2
10
1

4 14 10 10 10 5 26
1 3 2 2 2 1 3
JADWAL KEBUTUHAN MATERIAL
PROYEK :
LOKASI :
ITEM PEKERJAAN
WP
NO MINGGU

HARI KERJA EFEKTIF (HARI)


1 GALIAN BIASA 2,800.00 m3 45.00
2 PENYIAPAN BADAN JALAN 53,120.00 m2 21.25
3 LAPIS PONDASI AGREGAT KELAS A 540.00 m3 17.75
Agregat kelas A 36.51
4 LAPIS PONDASI AGREGAT KELAS B 800.00 m3 30.30
Agregat base kelas B 31.69
5 LAPIS RESAP PENGIKAT - ASPAL CAIR 8,000.00 Ltr 2.63
Aspal 2,106.70
Kerosene 1,150.43
6 LASTON LAPIS ANTARA (AC - BC) 391.44 Ton 13.43
Agregat 5-10 dan 10-15 11.39
Agregat 0-5 7.95
Fillet 306.00
Aspal cair 1,710.95
7 BETON MUTU SEDANG (K - 250) 10.08 m3 1.50
Batu kali 5.97
Semen 3,237.26
Pasir 2.83
Kayu Perancah 1.01
Paku 12.10
8 BAJA TULANGAN BJ 24 POLOS 1,203.06 kg 6.02
Besi Beton 220.00
Kawat Baja 4.00
Bulan juni Bulan Juli Bulan agustu
1 2 3 4 1 2 3 4 1
6 6 6 6 6 4 6 6 6
2 2 2 2 2 2 2 2
2 2 2
Bulan agustus Bulan sepember Bulan oktober
2 3 4 1 2 3 4 1 2
5 6 6 6 6 6 5 6 6

2
2 2 2 2
10.28 12.34 12.34 1.54
2 2 2 2 2 2
5.23 6.28 6.28 6.28 6.28 1.36
2
2,106.70
1,150.43
2 2 2
5.09 4.24 2.06
3.55 2.96 1.44
136.69 113.91 55.36
764.27 636.89 309.53
2
5.97
3,237.26
2.83
1.01
12.10
2 2
219.44 0.73
3.99 0.01
Bulan oktober
3 4
5 6

5.00 GALIAN BIASA


3.25 PENYIAPAN BADAN JALAN
0.75 LAPIS PONDASI AGREGAT KELAS A
1.30 LAPIS PONDASI AGREGAT KELAS B
2.63 LAPIS RESAP PENGIKAT - ASPAL CAIR
2.43 LASTON LAPIS ANTARA (AC - BC)
1.50 BETON MUTU SEDANG (K - 250)
0.02 BAJA TULANGAN BJ 24 POLOS
JADWAL KEBUTUHAN PERALATAN
PROYEK :
LOKASI :
ITEM PEKERJAAN
WP
NO MINGGU

HARI KERJA EFEKTIF 7 (HARI)


1 GALIAN BIASA 45.00
Exavator JAM
Dump Truck JAM
Alat Bantu Ls
2 PENYIAPAN BADAN JALAN 21.25
Motor Grader JAM
Vibrator Roller JAM
Water Tank JAM
Alat Bantu Ls
3 LAPIS PONDASI AGREGAT KELAS A 17.75
Wheal Loader JAM
Dump Truck JAM
Motor Grader JAM
Vibrator Roller JAM
Water Tank JAM
Alat Bantu Ls
4 LAPIS PONDASI AGREGAT KELAS B 30.30
Wheal Loader JAM
Dump Truck JAM
Motor Grader JAM
Vibrator Roller JAM
Water Tank JAM
Alat Bantu Ls
5 LAPIS RESAP PENGIKAT - ASPAL CAIR 2.63
Asphalt Distributor JAM
Air Compresor JAM
6 LASTON LAPIS ANTARA (AC - BC) 13.43
Wheel Loader JAM
AMP JAM
Genset JAM
Dump Truck JAM
Asphalt Finisher JAM
Tandem Roller JAM
P. Tire Roller JAM
Alat Bantu Ls
7 BETON MUTU SEDANG (K - 250) 1.50
Concrete Mixer JAM
Concrete Vibrator JAM
Water Tank JAM
Alat Bantu Ls
8 BAJA TULANGAN BJ 24 POLOS 6.02
BULAN JUNI BULAN JULI
1 2 3 4 1 2
6 6 6 6 6 4
2.00 2.00 2.00 2.00 2.00 2.00
1.00 1.00 1.00 1.00 1.00 1.00
0.41 0.41 0.41 0.41 0.41 0.41
1.00 1.00 1.00 1.00 1.00 1.00
BULAN JULI BULAN AGUSTUS
3 4 1 2 3 4
6 6 6 5 6 6
2.00 2.00
1.00 1.00
0.41 0.41
1.00 1.00
2.00 2.00 2.00 2.00
0.28 0.28 0.28 0.28
1.00 1.00 1.00 1.00
1.56 1.56 1.56 1.56
1.00 1.00 1.00 1.00
2.00 2.00 2.00
1.00 1.00 1.00
3.68 3.68 3.68
0.33 0.33 0.33
0.26 0.26 0.26
0.17 0.17 0.17
1.00 1.00 1.00
2.00 2.00 2.00
1.00 1.00 1.00
8.47 8.47 8.47
0.17 0.17 0.17
0.29 0.29 0.29
0.33 0.33 0.33
1.00 1.00 1.00
BULAN SEPTEMBER BULAN OKTOBER
1 2 3 4 1 2
6 6 6 5 6 6

2.00
1.00
3.68
0.33
0.26
0.17
1.00
2.00 2.00 2.00
1.00 1.00 1.00
8.47 8.47 8.47
0.17 0.17 0.17
0.29 0.29 0.29
0.33 0.33 0.33
1.00 1.00 1.00
2.00

1.00
7.67
2.00 2.00 2.00
0.54 0.54 0.54
1.00 1.00 1.00
1.00 1.00 1.00
12.26 12.26 12.26
0.48 0.48 0.48
0.47 0.47 0.47
0.20 0.20 0.20
1.00 1.00 1.00
2.00
1.00
1.00
0.11
1.00
2.00 2.00
BULAN OKTOBER
3 4
5 6
BIAYA KEBUTUHAN TENAGA KERJA

PROYEK :

LOKASI :
NO ITEM PEKERJAAN WP

MINGGU (HARI)

JAM KERJA EFEKTIF 7 JTK

1 GALIAN BIASA 45.00

Pekerja 3

Mandor 1

2 PENYIAPAN BADAN JALAN 21.25

Pekerja 4

Mandor 1

3 LAPIS PONDASI AGREGAT KELAS A 17.75

Pekerja 5

Mandor 1

4 LAPIS PONDASI AGREGAT KELAS B 30.30

Pekerja 5

Mandor 1

5 LAPIS RESAP PENGIKAT - ASPAL CAIR 2.63

Pekerja 11

Mandor 1

6 LASTON LAPIS ANTARA (AC - BC) 13.43

Pekerja 5

Mandor 1

7 BETON MUTU SEDANG (K - 250) 1.50

Pekerja 12

Mandor 1
Tukang 4

8 BAJA TULANGAN BJ 24 POLOS 6.02

Pekerja 3

Mandor 1

Tukang 1

JUMLAH KEBUTUHAN BIAYA TENAGA KERJA

Mandor (orang)

Pekerja(orang)

Tukang (orang)

Total

Kumulatif

Presentase Kumulatif terhadap nilai kontrak


40.00
Bulan juni

1 2 3 4

6 6 6 6

963,900.00 963,900.00 963,900.00 963,900.00

462,000.00 462,000.00 462,000.00 462,000.00


462,000.00 462,000.00 462,000.00 462,000.00

963,900.00 963,900.00 963,900.00 963,900.00

1,425,900.00 1,425,900.00 1,425,900.00 1,425,900.00

1,425,900.00 2,851,800.00 4,277,700.00 5,703,600.00

0.07 0.14 0.21 0.28

Btk Total = W x Jtk x Hj x Jam Kerja efektif


Btk Mingguan = Jtk x Hj x Jam Kerja Efektif x Hari Kerja Efektif per Minggu

Jtk : Jumlah Tenaga kerja

Hj : Harga satuan tenga kerja dalam satuan jam

W : Waktu penyelesaian item pekerjaan dalam satuan hari


Bulan Juli

1 2 3 4

6 4 6 6

963,900.00 642,600.00 963,900.00 803,250.00

462,000.00 308,000.00 462,000.00 385,000.00

1,267,350.00 1,267,350.00

462,000.00 462,000.00
462,000.00 308,000.00 924,000.00 847,000.00

963,900.00 642,600.00 2,231,250.00 2,070,600.00

1,425,900.00 950,600.00 3,155,250.00 2,917,600.00

7,129,500.00 8,080,100.00 11,235,350.00 14,152,950.00

0.35 0.40 0.55 0.70

er Minggu
RUMUS MENGHITUNG JADWAL KEBUTUHAN TENAGA KERJA

= JUMLAH TENAGA KERJA * JAM KERJA EFEKRIF * HARGA SATUAN TENAGA K

Bulan agustus

1 2 3 4

6 5 6 6

1,267,350.00 686,058.80

462,000.00 250,096.00

1,338,750.00 1,606,500.00 1,606,500.00

385,000.00 462,000.00 462,000.00

1,337,039.14 1,604,446.96 1,604,446.96

385,000.00 462,000.00 462,000.00


462,000.00 1,020,096.00 924,000.00 924,000.00

1,267,350.00 3,361,847.94 3,210,946.96 3,210,946.96

1,729,350.00 4,381,943.94 4,134,946.96 4,134,946.96

15,882,300.00 20,264,243.94 24,399,190.90 28,534,137.87

0.78 1.00 1.20 1.41


HARGA SATUAN TENAGA KERJA * HARI KERJA EFEKTIF

Bulan sepember

1 2 3 4

6 6 6 5

200,965.50

57,794.00

1,604,446.96 1,604,446.96 346,866.15

462,000.00 462,000.00 99,880.00

1,501,440.00

202,400.00

1,606,500.00 1,338,750.00

462,000.00 385,000.00
519,794.00 462,000.00 764,280.00 385,000.00

1,805,412.46 1,604,446.96 3,454,806.15 1,338,750.00

2,325,206.46 2,066,446.96 4,219,086.15 1,723,750.00

30,859,344.33 32,925,791.30 37,144,877.45 38,868,627.45

1.52 1.62 1.83 1.92


Bulan oktober

1 2 3 4

6 6 5 6

651,163.72

187,262.77

963,900.00

115,503.70
399,003.19

963,900.00 2,457.95

462,000.00 1,178.10

399,000.00 1,017.45

649,262.77 116,681.80

1,615,063.72 966,357.95

399,000.00 400,020.64

2,663,326.48 1,483,060.38 43,015,014.32

41,531,953.93 43,015,014.32

2.05 2.12 18.15


5.00 GALIAN BIASA

3.248 PENYIAPAN BADAN JALAN

0.7505714286 LAPIS PONDASI AGREGAT KELAS A

1.2971428571 LAPIS PONDASI AGREGAT KELAS B

2.6285714286 LAPIS RESAP PENGIKAT - ASPAL CAI

2.431984 LASTON LAPIS ANTARA (AC - BC)

1.5 BETON MUTU SEDANG (K - 250)

0.0153 BAJA TULANGAN BJ 24 POLOS


43,015,014.32

18.15
N BADAN JALAN

NDASI AGREGAT KELAS A

NDASI AGREGAT KELAS B

SAP PENGIKAT - ASPAL CAIR

APIS ANTARA (AC - BC)

UTU SEDANG (K - 250)

ANGAN BJ 24 POLOS
BIAYA KEBUTUHAN MATERIAL
PROYEK :
LOKASI :
ITEM PEKERJAAN
MINGGU WAKTU PENYELESAIAN
NO HARI KERJA EFEKTIF (HARI)
1 GALIAN BIASA 45.0
2 PENYIAPAN BADAN JALAN 21.2
3 LAPIS PONDASI AGREGAT KELAS A 17.7
Agregat kelas A 1.2000
4 LAPIS PONDASI AGREGAT KELAS B 30.3
Agregat base kelas B 1.2000
5 LAPIS RESAP PENGIKAT - ASPAL CAIR 2.6
Aspal 0.6922
Kerosene 0.3780
6 LASTON LAPIS ANTARA (AC - BC) 13.4
Agregat 5-10 dan 10-15 0.3910
Agregat 0-5 0.2729
Fillet 10.5000
Aspal cair 58.7100
7 BETON MUTU SEDANG (K - 250) 1.5
Batu kali 0.8883
Semen 481.7500
Pasir 0.4215
Kayu Perancah 0.1500
Paku 1.8000
8 BAJA TULANGAN BJ 24 POLOS 6.0
Besi Beton 1.1000
Kawat Baja 0.0200
JUMLAH KEBUTUHAN BIAYA MATERIAL
Agregat kelas A
Agregat base kelas B
Aspal
Kerosene
Agregat 5-10 dan 10-15
Agregat 0-5
Fillet
Aspal cair
Batu kali
Semen
Pasir
Kayu Perancah
Paku
Besi Beton
Kawat Baja
Total
Kumulatif
Presentase Kumulatif terhadap nilai kontrak
Bulan juni
U PENYELESAIAN QM 1 2
(HARI) 6 6
45.00 62.22
21.25 2,500.00
17.75 30.42
m3
30.30 26.41
m3
2.63 3,043.48
kg
liter
13.43 29.14
m3
m3
kg
kg
1.50 6.72
m3
zak
m3
Ls
kg
6.02 200.00
kg
kg
0 0
0.00 0
0.00 0.00

BM Total = Vi x KMij x Hj
BM Mingguan = QM x KMij x Hj x Hari Ker

BM Total
BM Harian
Vi
Kmij
Hj
QM
Bulan juni Bulan Juli
3 4 1 2
6 6 6 4
0 0 0 0
0 0 0 0
0.00 0.00 0.00 0.00

= Vi x KMij x Hj
gguan = QM x KMij x Hj x Hari Kerja Efektif per Minggu

: Biaya Material Total Item Pekerjaan


: Biaya Material Harian Item Pekerjaan
: Volume item Pekerjaan yang Bersangkutan
: Koefisien Material item pekerjaan yang bersangkutan
: Harga satuan material
: Produksi minimum kelompok kerja
Bulan Juli Bulan agustus
3 4 1 2
6 6 6 5

58,695,593.22

44,430,169.75

58,695,593.22
44,430,169.75

0 0 0 103,125,763
0 0 0 103,125,763
0.00 0.00 0.00 5.08

BM Total = Vi x KMij x Hj
BM Mingguan = QM x KMij x Hj x Hari Kerja Efekt
Bulan agustus Bulan sepember
3 4 1 2
6 6 6 6

70,434,711.86 70,434,711.86 8,811,047.05 208,376,064

53,316,203.70 53,316,203.70 53,316,203.70 53,316,203.70

70,434,711.86 70,434,711.86 8,811,047.05


53,316,203.70 53,316,203.70 53,316,203.70 53,316,203.70

123,750,916 123,750,915.6 62,127,250.7 53,316,203.7


226,876,679 350,627,594.1 412,754,844.8 466,071,048.5
11.18 17.28 20.34 22.97

Hj
Hj x Hari Kerja Efektif per Minggu
Bulan sepember Bulan oktober
3 4 1
6 5 6

11,526,455.47

73,373,200.00
36,288,000.00

23,688,017.14 19,740,014.28 9,601,479.78


18,163,421.89 15,136,184.91 7,362,191.90
2,662,156.54 2,218,463.78 1,079,053.68
136,020,462.11 113,350,385.10 55,133,264.59

13,860,000.00
480,000.00
11,526,455.47
73,373,200.00
36,288,000.00
23,688,017.14 19,740,014.28 9,601,479.78
18,163,421.89 15,136,184.91 7,362,191.90
2,662,156.54 2,218,463.78 1,079,053.68
136,020,462.11 113,350,385.10 55,133,264.59

13,860,000.00
480,000.00
301,721,713.1 150,445,048.1 87,515,990.0
767,792,761.7 918,237,809.7 1,005,753,799.7
37.84 45.26 49.57
Bulan oktober
2 3 4
6 5 6

2,781,660.57
7,041,258.00
382,384.80
2,268,000.00
136,080.00

35,343.00
1,224.00
2,781,660.57
7,041,258.00
382,384.80
2,268,000.00
136,080.00
35,343.00
1,224.00
12,645,950.4 1,018,399,750.06

1,018,399,750.1
50.20 259.74
5.0000 GALIAN BIASA
3.2480 PENYIAPAN BADAN JALAN
0.7506 LAPIS PONDASI AGREGAT KELAS A
1.2971 LAPIS PONDASI AGREGAT KELAS B
2.6286 LAPIS RESAP PENGIKAT - ASPAL CAIR
2.4320 LASTON LAPIS ANTARA (AC - BC)
1.5000 BETON MUTU SEDANG (K - 250)
0.0153 BAJA TULANGAN BJ 24 POLOS
260 1,018,399,750
SPAL CAIR
BIAYA KEBUTUHAN PERALATAN
PROYEK :
LOKASI :
ITEM PEKERJAAN
NO
MINGGU

JAM KERJA EFEKTIF 7

1 GALIAN BIASA

Excavator

Dump Truck

Alat Bantu
2 PENYIAPAN BADAN JALAN

Motor Grader

Vibrator Roller

Water Tank

Alat Bantu

3 LAPIS PONDASI AGREGAT KELAS A

Wheal Loader

Dump Truck

Motor Grader

Vibrator Roller

Water Tank

Alat Bantu

4 LAPIS PONDASI AGREGAT KELAS B

Wheal Loader

Dump Truck

Motor Grader

Vibrator Roller

Water Tank
Alat Bantu

5 LAPIS RESAP PENGIKAT - ASPAL CAIR

Aspalt Distributor

Air Kompresor

6 LASTON LAPIS ANTARA (AC - BC)

Wheal Loader

AMP

Genset

Dump Truck

Asphalt Finisher

Tandem Roller

P.Tire Roller

Alat Bantu

7 BETON MUTU SEDANG (K - 250)

Concrert Mixer

Concrert Vibrator

Water Tank

Alat Bantu

8 BAJA TULANGAN BJ 24 POLOS

Alat Bantu

JUMLAH KEBUTUHAN PERALAYAN

DUMP TRUCK

WATER TANK TRUCK

EXAVATOR

MOTOR GRADER

VIBRO ROLLER

WHEEL LOADER

ASPHALT DISTRIBUTOR
AIR COMPRESSOR

AMP

GENSET

ASPHALT FINISHER

TANDEM ROLLER

P. TIRE ROLLER

CONCRETE MIXER

CONCRETE VIBRATOR

ALAT BANTU

Total

Kumulatif

Presentase Kumulatif terhadap nilai kontrak


BPTotal = W x JP x Hj x Jam Kerja efektif
BP Mingguan = JP x Hj x Jam Kerja Efektif x Hari Kerja Efektif per Minggu

WP BULAN JUNI

(HARI) 1 2

JA BT 6 6

45.00
1.00 164,713,815.00 21,961,842.00 21,961,842.00

0.41 33,206,572.00 4,427,542.93 4,427,542.93

1.00 31,500.00 4,200.00 4,200.00

21.25

0.28 16,055,142.26

1.00 49,737,169.66

1.56 49,894,317.51

1.00 7,436.80

17.75

1.00 41,953,493.32

3.68 117,938,380.9

0.33 16,069,200.0

0.26 10,769,867.1

0.17 4,458,750.4

1.00 2,485.1

30.30

1.00 71,607,327.44

8.47 463,098,406.34

0.17 13,691,760.13

0.29 20,618,721.83

0.33 15,196,945.41
1.00 42,416.00

2.63
1.00 4,645,871.20
7.67 20,826,377.33

13.43
0.54 17,169,029.63
1.00 615,742,885.54
1.00 30,490,348.47
12.26 297,073,093.78
0.48 27,884,539.74
0.47 14,691,362.98
0.20 6,584,588.82
1.00 470,119.44

1.50
1.00 602,477.78
1.00 441,297.62
0.11 249,329.35
1.00 8,400.27

6.02

1.00 10,526.78

4,427,542.93 4,427,542.93

21,961,842.00 21,961,842.00
4,200.00 4,200.00

26,393,584.9 26,393,584.9

26,393,584.9 52,787,169.9

ai kontrak 1.30 2.60

BPTotal = W x JP x Hj x Ja
BP Mingguan = JP x Hj x Jam Ke
a Efektif per Minggu

BULAN JUNI BULAN JULI

3 4 1 2

6 6 6 4

21,961,842.00 21,961,842.00 21,961,842.00 14,641,228.00

4,427,542.93 4,427,542.93 4,427,542.93 2,951,695.29

4,200.00 4,200.00 4,200.00 2,800.00


4,427,542.93 4,427,542.93 4,427,542.93 2,951,695.29

21,961,842.00 21,961,842.00 21,961,842.00 14,641,228.00


4,200.00 4,200.00 4,200.00 2,800.00

26,393,584.9 26,393,584.9 26,393,584.9 17,595,723.3

79,180,754.8 105,574,339.7 131,967,924.7 149,563,648.0

3.90 5.20 6.50 7.37

= W x JP x Hj x Jam Kerja efektif


uan = JP x Hj x Jam Kerja Efektif x Hari Kerja Efektif per Minggu

JP : Jumlah Alat
Hj : Harga satuan alat dalam satuan jam

W : Waktu penyelesaian item pekerjaan dalam satuan hari


BULAN JULI BULAN AGUSTUS

3 4 1

6 6 6

21,961,842.00 18,301,535.00

4,427,542.93 3,689,619.11

4,200.00 3,500.00

4,533,643.33 4,533,643.33 4,533,643.33

14,044,758.00 14,044,758.00 14,044,758.00

14,089,133.33 14,089,133.33 14,089,133.33

2,100.00 2,100.00 2,100.00

71,607,327.440

463,098,406.342

13,691,760.127

20,618,721.830

15,196,945.415
42,416.000

4,427,542.93 3,689,619.11 0.00

14,089,133.33 14,089,133.33 14,089,133.33

21,961,842.00 18,301,535.00

4,533,643.33 4,533,643.33 4,533,643.33

14,044,758.00 14,044,758.00 14,044,758.00


6,300.00 5,600.00 2,100.00

59,063,219.6 54,664,288.8 32,669,634.7

208,626,867.6 263,291,156.3 295,960,791.0

10.28 12.98 14.59


BULAN AGUSTUS

2 3 4 1

5 6 6 6

2,454,212.26

7,602,895.66

7,626,917.51

1,136.80

11,817,505.0 14,181,006.0 14,181,006.0 1,773,976.3

33,221,009.6 39,865,211.6 39,865,211.6 4,986,948.1

4,526,389.5 5,431,667.4 5,431,667.4 679,475.7

3,033,667.7 3,640,401.3 3,640,401.3 455,396.9

1,255,945.6 1,507,134.7 1,507,134.7 188,535.4

700.0 840.0 840.0 105.1

11,817,505.0 14,181,006.0 14,181,006.0 14,181,006.0

76,426,085.5 91,711,302.7 91,711,302.7 91,711,302.7

2,259,579.4 2,711,495.3 2,711,495.3 2,711,495.3

3,402,750.2 4,083,300.2 4,083,300.2 4,083,300.2

2,507,983.3 3,009,579.9 3,009,579.9 3,009,579.9


7,000.0 8,400.0 8,400.0 8,400.0

109,647,095.18 131,576,514.22 131,576,514.22 96,698,250.78

11,390,846.37 4,516,714.63 4,516,714.63 3,198,115.29

9,240,181.19 8,143,162.71 8,143,162.71 3,390,971.04

14,039,313.60 7,723,701.52 7,723,701.52 4,538,697.11

23,635,010.00 28,362,012.00 28,362,012.00 15,954,982.32


8,836.80 9,240.00 9,240.00 8,505.08

167,961,283.1 180,331,345.1 180,331,345.1 123,789,521.6

463,922,074.1 644,253,419.2 824,584,764.3 948,374,285.9

22.87 31.75 40.64 46.74


BULAN SEPTEMBER

2 3 4

6 6 5

14,181,006.0 3,065,798.4

91,711,302.7 19,827,110.2

2,711,495.3 586,199.5

4,083,300.2 882,770.6

3,009,579.9 650,642.5
8,400.0 1,816.0

4,645,871.20

20,826,377.33

17,169,029.629 7,669,319.57 6,391,099.64

615,742,885.543 275,049,264.00 229,207,720.00

30,490,348.472 13,619,886.00 11,349,905.00

297,073,093.779 132,701,063.57 110,584,219.64

27,884,539.739 12,455,884.29 10,379,903.57

14,691,362.982 6,562,558.29 5,468,798.57

6,584,588.819 2,941,302.86 2,451,085.71

470,119.440 210,000.00 175,000.00

91,711,302.65 152,528,173.76 110,584,219.64

3,009,579.91 650,642.51

2,711,495.31 586,199.46

4,083,300.25 882,770.63

14,181,006.00 10,735,118.01 6,391,099.64

4,645,871.20
20,826,377.33

275,049,264.00 229,207,720.00

13,619,886.00 11,349,905.00

12,455,884.29 10,379,903.57

6,562,558.29 5,468,798.57

2,941,302.86 2,451,085.71

8,400.00 211,816.00 175,000.00

115,705,084.1 501,695,864.3 376,007,732.1

1,064,079,370.1 1,565,775,234.4 1,941,782,966.5

52.45 77.18 95.71


BULAN OKTOBER

1 2 3 4

6 6 5 6
3,108,610.41

111,485,901.54

5,520,557.47

53,787,810.56

5,048,751.88

2,660,006.12

1,192,200.25

85,119.44

602,477.78

441,297.62

249,329.35

8,400.27

10,500.00 26.78

53,787,810.56

249,329.35

3,108,610.41
111,485,901.54

5,520,557.47

5,048,751.88

2,660,006.12

1,192,200.25

602,477.78

441,297.62

95,619.44 8,427.04

182,899,457.7 1,301,531.8

2,124,682,424.2 2,125,983,956.0

104.72 104.79
5 GALIAN BIASA

3.248 PENYIAPAN BADAN JALAN

0.7505714286 LAPIS PONDASI AGREGAT KELAS A

1.2971428571 LAPIS PONDASI AGREGAT KELAS B

2.6285714286 LAPIS RESAP PENGIKAT - ASPAL CA

2.431984 LASTON LAPIS ANTARA (AC - BC)

1.500048 BETON MUTU SEDANG (K - 250)

0.0153 BAJA TULANGAN BJ 24 POLOS


2,125,983,956.0

104.788 50.20

2,125,983,956.03
BADAN JALAN

DASI AGREGAT KELAS A

DASI AGREGAT KELAS B

AP PENGIKAT - ASPAL CAIR

PIS ANTARA (AC - BC)

TU SEDANG (K - 250)

NGAN BJ 24 POLOS
18.15 173.136

100

73.136 1,844,403,124.39

Rp 1,348,929,682
FORM 7C

BIAYA KEBUTUHAN TENAGA KERJA


PROYEK
LOKASI
ITEM PEKERJAAN WAKTU PE- BULAN MEI BULAN JUNI
NYELESAIAN 1 2 3 4 1
NO
MINGUU 6 5 6 6 6
(HARI)
HARI KERJA EFEKTIF
FORM 7C
FORM 7C

BULAN JUNI BULAN JULI BULAN AGUSTUS


2 3 4 1 2 3 4 5 1
6 6 6 6 6 6 6 6 6
FORM 7C
FORM 7C

BULAN AGUSTUS
2 3 4
5 5 5
FORM 7C
Rincian Estimasi Biaya overhead
Jumlah Harga Jumlah Harga untuk bula
No Item pekerjaan
1 org/bulan (Rp) 5 Bulan
1 Gaji
Supervisior 1 2,500,000 12,500,000
Estimasitor 1 2,000,000 10,000,000
Tukang masak 1 1,000,000 5,000,000
Sopir pribadi 1 800,000 4,000,000
Staff 1 1,500,000 7,500,000
Keuangan 1 1,600,000 8,000,000
Jumlah Harga (Rp) 9,400,000 47,000,000

2 Akomodasi
Penginapan 50,000 250,000
Jumlah Harga(Rp) 50,000 250,000

3 Konsumsi
katering untuk supervisor 1 300,000 1,500,000
Belanja bahan makanan 1 4,000,000 20,000,000
Jumlah Harga(Rp) 4,300,000 21,500,000

4 Rapat Lapangan
Rapat Lapangan 1 300,000 Ls 1,500,000
Jumlah Harga(Rp) 300,000 1,500,000

5 Admistrasi
Admisatrsi 1 250,000 Ls 1,250,000
Jumlah Harga(Rp) 250,000 1,250,000

6 Transportasi
Bahan bakar minyak 1 800,000 4,000,000
Reparasi kend.pribadi 1 350,000 Ls 1,750,000
Jumlah Harga(Rp) 1,150,000 5,750,000
Total keseluruhan biaya overhead 15,450,000 77,250,000
Jumlah Harga untuk bulan
(Rp)

12,500,000
10,000,000
5,000,000
4,000,000
7,500,000
8,000,000
47,000,000

250,000
250,000

1,500,000
20,000,000
21,500,000

1,500,000
1,500,000

1,250,000
1,250,000

4,000,000
1,750,000
5,750,000
77,250,000
FAKULTAS TEKNIK JURUSAN SIPIL
FORMULIR TUGAS MANAJEMEN KONSTRUKSI

JADWAL BIAYA OVERHEAD


PROYEK : Peningkatan Jalan Oelmasi - Kuka
LOKASI : Oelmasi-Kukak-Barate
PANJANG EFEKTIF : 1.25 Km (HRS-Base)

NO. ITEM PEKERJAAN SATUAN

1 Gaji
1.1 Kepala Proyek Orang/bulan
1.2 Supervisor Orang/bulan
1.3 Keuangan Orang/bulan
1.4 Staf Orang/bulan
BIAYA (A)

2 Akomodasi Per bulan


3 Konsumsi Per bulan
4 Administrasi Per bulan
5 Transportasi Per bulan
6 Rapat Lapangan Per bulan
BIAYA (B)
BIAYA = (A) + (B)

Catatan :
1 Bulan = 30 hari
Biaya ini hanya berlaku selama 90 hari atau 3 bulan masa pelaksanaan
proyek
gkatan Jalan Oelmasi - Kukak - Barate
si-Kukak-Barate
Km (HRS-Base)

HARGA SATUAN

(Rp)

2,000,000.00 10,000,000.00
1,750,000.00 8,750,000.00
1,500,000.00 7,500,000.00
1,250,000.00 6,250,000.00
6,500,000.00 32,500,000.00

500,000.00 2,500,000.00
400,000.00 2,000,000.00
300,000.00 1,500,000.00
200,000.00 1,000,000.00
100,000.00 500,000.00
1,500,000.00 7,500,000.00
8,000,000.00 40,000,000.00
FAKULTAS TEKNIK JURUSAN SIPIL
FORMULIR TUGAS MANAJEMEN KONSTRUKSI

JADWAL KEBUTUHAN OVERHEAD

PROYEK :
LOKASI :
PANJANG EFEKTIF :
waktu penyelesaian :
TOTAL BIAYA TOTAL BIAYA
NO. Minggu Rp
Hari Kerja Efektif

1 Gaji
1,1 Kepala Proyek 10,000,000.00
1,2 Supervisor 8,750,000.00
1,3 Keuangan 7,500,000.00
1,4 Staf 6,250,000.00
2 Akomodasi 2,500,000.00
3 Konsumsi 2,000,000.00
4 Administrasi 1,500,000.00
5 Transportasi 1,000,000.00
6 Rapat Lapangan 100,000.00

JUMLAH BIAYA OVERHEAD/BULAN


5 bulan
Bulan juni
1 2 3 4
6 6 6 6

2,000,000.00 - - -
1,750,000.00 - - -
1,500,000.00 - - -
1,250,000.00 - - -
500,000.00 - - -
400,000.00 - - -
300,000.00 - - -
200,000.00 - - -
20,000.00 - - -

7,920,000.00

7,920,000.00 7,920,000.00 7,920,000.00 7,920,000.00


Bulan Juli
1 2 3 4
6 4 6 6

2,000,000.00 - - -
1,750,000.00 - - -
1,500,000.00 - - -
1,250,000.00 - - -
500,000.00 - - -
400,000.00 - - -
300,000.00 - - -
200,000.00 - - -
20,000.00 - - -

7,920,000.00

7,920,000.00
Bulan agustus
1 2 3 4
6 5 6 6

2,000,000.00 - - -
1,750,000.00 - - -
1,500,000.00 - - -
1,250,000.00 - - -
500,000.00 - - -
400,000.00 - - -
300,000.00 - - -
200,000.00 - - -
20,000.00 - - -

7,920,000.00
Bulan sepember
1 2 3 4
6 6 6 5

2,000,000.00 - - -
1,750,000.00 - - -
1,500,000.00 - - -
1,250,000.00 - - -
500,000.00 - - -
400,000.00 - - -
300,000.00 - - -
200,000.00 - - -
20,000.00 - - -

7,920,000.00
Bulan oktober
1 2 3 4
6 6 5 6

2,000,000.00 - - -
1,750,000.00 - - -
1,500,000.00 - - -
1,250,000.00 - - -
500,000.00 - - -
400,000.00 - - -
300,000.00 - - -
200,000.00 - - -
20,000.00 - - -

7,920,000.00
JADWAL KEBUTUHAN BIAYA TOTAL
PROYEK :
LOKASI :
ITEM PEKERJAAN WP Bulan
NO MINGGU (HARI) 1

HARI KERJA EFEKTIF 7 JA BT 6


1 BIAYA TENAGA KERJA 1,425,900.00
2 BIAYA MATERIAL 0.00

3 BIAYA PERALATAN 26,393,584.93


4 BIAYA OVERHEAD 7,920,000.00

Jumlah 35,739,485
Kumulatif 35,739,485
Bulan juni Bulan Ju
2 3 4 1
6 6 6 6
1,425,900.00 1,425,900.00 1,425,900.00 1,425,900.00
0.00 0.00 0.00 0.00

26,393,584.93 26,393,584.93 26,393,584.93 26,393,584.93


0.00 0.00 0.00 7,920,000.00

27,819,485 27,819,485 27,819,485 35,739,485


63,558,970 91,378,455 119,197,940 154,937,425
Bulan Juli Bulan agu
2 3 4 1
4 6 6 6
950,600.00 3,155,250.00 2,917,600.00 1,729,350.00
0.00 0.00 0.00 0.00

17,595,723.29 59,063,219.60 54,664,288.78 32,669,634.67


0.00 0.00 0.00 7,920,000.00

18,546,323 62,218,470 57,581,889 42,318,985


173,483,748 235,702,218 293,284,106 335,603,091
Bulan agustus Bulan sepe
2 3 4 1
5 6 6 6
4,381,943.94 4,134,946.96 4,134,946.96 2,325,206.46
103,125,762.97 123,750,915.56 123,750,915.56 62,127,250.75

167,961,283.14 180,331,345.09 180,331,345.09 123,789,521.62


0.00 0.00 0.00 7,920,000.00

275,468,990 308,217,208 308,217,208 196,161,979


611,072,081 919,289,289 1,227,506,496 1,423,668,475
Bulan sepember Bulan okto
2 3 4 1
6 6 5 6
2,066,446.96 4,219,086.15 1,723,750.00 2,663,326.48
53,316,203.70 301,721,713.14 150,445,048.06 87,515,989.95

115,705,084.12 501,695,864.34 376,007,732.14 182,899,457.69


0.00 0.00 0.00 7,920,000.00

171,087,735 807,636,664 528,176,530 280,998,774


1,594,756,210 2,402,392,874 2,930,569,404 3,211,568,178
Bulan oktober
2 3 4
6 5 6
1,483,060.38
12,645,950.37

1,301,531.80
0.00

15,430,543
3,226,998,720
0.00
GRAFIK PENGELURAN (CASH OUT)
PROYEK :
LOKASI :
RANGE BIAYA BULAN JUNI BULAN JULI
1 2 3 4 1 2 3
(Rp)
6 6 6 6 6 4 6
3500000000

NK = Rp1.874.345.781
3000000000

RAP =Rp1.604.850.938

2500000000

2000000000

1500000000

1000000000

500000000

0
0 2 4 6 8
Jumlah (Rp) 35,739,485 27,819,485 27,819,485 27,819,485 35,739,485 18,546,323 62,218,470
Kumulatif (Rp) 0 35,739,485 63,558,970 91,378,455 119,197,940 154,937,425 173,483,748 235,702,218
Realisasi (Rp)
Devisiasi (Rp)

JUMLAH + OVER HEAD = Rp1,844,403,124

PAJAK = Rp184,440,312

TOTAL = Rp2,028,843,437

FEE = -Rp1,382,595,596 249,646,914.50

Nilai kontrak = Rp3,226,998,720

Rp1,844,403,124
Rp184,440,312
Rp2,028,843,437
-Rp1,198,155,284
BULAN AGUSTUS BULAN SEPTEMBER
4 1 2 3 4 1 2 3 4
6 6 5 6 6 6 6 6 5

Row 3

10 12 14 16 18 20
57,581,889 42,318,985 275,468,990 308,217,208 308,217,208 196,161,979 171,087,735 807,636,664 528,176,530
293,284,106 335,603,091 611,072,081 919,289,289 1,227,506,496 1,423,668,475 1,594,756,210 2,402,392,874 2,930,569,404
BULAN OKTOBER
1 2 3 4
6 6 5 6

Pajak=Rp170.395.071

Free =Rp99.099.772

Row 37

20
280,998,774 15,430,543
3,211,568,178 3,226,998,720 3,226,998,720
0.00
PERHITUNGAN PEMBAYARAN ANGSURAN
Presentase Kemajuan Fisik
Bulan 1 = 7.31 %
Bulan 2 = 16.70 %
Bulan 3 = 47.98 %
Bulan 4 = 92.19 %
Bulan 5 = 100.00 %
Diketahui:
NK = 2,028,843,436.83
Pajak (PPN) = 10/110
Uang yang diterima = 20 % dari NK
Retensi Pemeliharaan = 5 %

a Uang Muka
Uang muka yang diterima = 20 % x 2,028,843,436.83 =
Pajak(PPN) = 1/110 x 405,768,687.37 =
Sisa yang diterima

b Angsuran 1 = 7.31 %
Jumlah yang diterima = 7.31 % x 2,028,843,436.83 =
Potongan:
Uang muka = 7.31 % x 405,768,687.37 =
Retensi = 5 % x 148,287,339.65 =
Sisa =
Pajak(PPN) = 10/110 x 111,215,504.74 =
Jumlah Angsuran 1 =

c Angsuran 2 = 16.70 %
Jumlah yang diterima = 16.70 % x 2,028,843,436.83 =
Potongan:
Uang muka = 16.70 % x 405,768,687.37 =
Retensi = 5 % x 338,898,159.19 =
Angsuran 1
Sisa =
Pajak(PPN) = 10/110 x 142,958,114.66 =
Jumlah Angsuran 2 =
d Angsuran 3 = 47.98 %
Jumlah yang diterima = 47.98 % x 2,028,843,436.83 =
Potongan:
Uang muka = 47.98 % x 405,768,687.37 =
Retensi = 5 % x 973,370,327.75 =
Angsuran 1 =
Angsuran 2 =
Sisa =
Pajak(PPN) = 10/110 x 475,854,126.42 =
Jumlah Angsuran 3 = =

e Angsuran 4 = 92.19 %
Jumlah yang diterima = 92.19 % x 2,028,843,436.83 =
Potongan:
Uang muka = 92.19 % x 405,768,687.37 =
Retensi = 5 % x 2,028,843,436.83 =
Angsuran 1 =
Angsuran 2 =
Angsuran 3 =
Sisa =
Pajak(PPN) = 10/110 x 791,604,831.80 =
Jumlah Angsuran 4 =

f Angsuran 5 = 100.00 %
Jumlah yang diterima = 100.00 % x 2,028,843,436.83 =
Pajak(PPN) = 10/110 x 2,028,843,436.83 =
Jumlah Angsuran =
TABEL RENCANA ANGSURAN
NO Tahap Penerimaan Jumlah Penerimaan (Rp) Pajak (Rp)
1 Uang Muka 368,880,624.88 36,888,062.49
2 Angsuran 1 101,105,004.31 10,110,500.43
3 Angsuran 2 129,961,922.41 12,996,192.24
4 Angsuran 3 432,594,660.38 43,259,466.04
5 Angsuran 4 719,640,756.19 71,964,075.62
6 Angsuran 5 1,844,403,124.39 184,440,312.44
Jumlah 3,596,586,092.56 359,658,609.26
Jumlah Total 3,956,244,701.81

TABEL PREDIKSI PENCAIRAN ANGSURAN


NO Tahap Pembayaran Realisasi Fisik Prediksi Pencaira
1 Uang Muka minggu 1, bulan 1

2 Angsuran 1, 7% minggu 4, bulan 1 minggu 1, bulan 2

3 Angsuran 2, 17 % minggu 4, bulan 2 minggu 1, bulan 3

4 Angsuran 3, 48 % minggu 5, bulan 3 minggu 2, bulan 4

5 Angsuran 4, 92 % minggu 1, bulan 4 minggu 3,bulan 4

6 Angsuran 5,Pemeliharaan(5%) minggu 3, bulan 4 minggu 4, bulan 4

catatan :

- Prediksi pencairan angsuran adalah 1 minggu setelah pengajuan dokumen

- Masa pelaksanaan pekerjaan 4 bulan dan masa pemeliharaan diprediksi 2 bulan

- Satu bulan ekuivalen dengan 3 minggu


N

405,768,687.37
36,888,062.49
368,880,624.88

148,287,339.65

29,657,467.93
7414366.98258667
111,215,504.74
10,110,500.43
101,105,004.31

338,898,159.19

67,779,631.84
16944907.95965
111,215,504.74
142,958,114.66
12,996,192.24
129,961,922.41

973,370,327.75

194,674,065.55
48668516.3876862
111,215,504.74
142,958,114.66
475,854,126.42
43,259,466.04
432,594,660.38

2,028,843,436.83

405,768,687.37
101442171.84135
111,215,504.74
142,958,114.66
475,854,126.42
791,604,831.80
71,964,075.62
719,640,756.19

2,028,843,436.83
184,440,312.44
1,844,403,124.39
Pajak (Rp)
36,888,062.49
10,110,500.43
12,996,192.24
43,259,466.04
71,964,075.62
184,440,312.44
359,658,609.26
01.81

Prediksi Pencairan
minggu 1, bulan 1

minggu 1, bulan 2

minggu 1, bulan 3

minggu 2, bulan 4

minggu 3,bulan 4

minggu 4, bulan 4
UNIVERSITAS KATOLIK WIDYA MANDIRA KUPANG
FAKULTAS TEKNIK JURUSAN SIPIL
FORMULIR TUGAS MANAJEMEN KONSTRUKSI

ALIRAN KAS

PROYEK :
LOKASI :

MINGGU ANGSURAN KUMULATIF PENGELUARAN


Rp. ANGSURAN RP. TOTAL Rp.
Bulan 1
1 368,880,624.88 368,880,624.88 35,739,484.93
2 27,819,484.93
3 27,819,484.93
4 27,819,484.93
Bulan 2
1 101,105,004.31 469,985,629.19 35,739,484.93
2 18,546,323.29
3 62,218,469.60
4 57,581,888.78
Bulan 3
1 129,961,922.41 599,947,551.60 42,318,984.67
2 275,468,990.04
3 308,217,207.61
4 308,217,207.61
5 432,594,660.38 196,161,978.84
Bulan 4
1 719,640,756.19 1,319,588,307.79 171,087,734.78
2
3 1,844,403,124.39 3,163,991,432.17
4
JUMLAH 3,596,586,092.56 1,594,756,209.89
Form 10a

KUMULATIF SELISIH
Rp. Rp.

35,739,484.93
63,558,969.87
91,378,454.80
119,197,939.73 249,682,685.14

154,937,424.67
173,483,747.96
235,702,217.56
293,284,106.33 176,701,522.85

335,603,091.00
611,072,081.04
919,289,288.66
1,227,506,496.27
196,161,978.84 403,785,572.76

1,319,588,307.79

3,163,991,432.17
GRAFIK ALIRAN KAS (CASH FLOW)
PROYEK :
LOKASI :
RANGE BIAYA BULAN JUNI BULAN JULI
1 2 3 4 1 2 3
Rp
6 6
Rp3,500,000,000.00 6 6 6 4 6

NK = Rp1.874.345.781 Rp3,000,000,000.00

RAP =Rp1.604.850.938

Rp2,500,000,000.00

Rp2,000,000,000.00

Rp1,500,000,000.00

Rp1,000,000,000.00

Rp500,000,000.00

Rp-
Jumlah (Rp) 35,739,485 27,819,485 27,819,485 27,819,485 35,739,485 18,546,323 62,218,470
Kumulatif (Rp) 35,739,485 63,558,970 91,378,455 119,197,940 154,937,425 173,483,748 235,702,218
Realisasi (Rp)
Devisiasi (Rp)
JUMLAH + OVER HEAD = Rp1,844,403,124
PAJAK = Rp184,440,312
TOTAL = Rp2,028,843,437
FREE = Rp249,646,914 249,646,914.50
Nilai kontrak = Rp1,594,756,210
BULAN AGUSTUS BULAN SEPTEMBER
4 1 2 3 4 1 2 3 4 1
6 6 5 6 6 6 6 6 5 6

Pajak=Rp170.395.071

Free =Rp99.099.772
57,581,889 42,318,985 275,468,990 308,217,208 308,217,208 196,161,979 171,087,735 807,636,664 528,176,530 280,998,774
293,284,106 335,603,091 611,072,081 919,289,289 1,227,506,496 1,423,668,475 1,594,756,210 2,402,392,874 2,930,569,404 3,211,568,178
BULAN OKTOBER
2 3 4
6 5 6

Pajak=Rp170.395.071

Free =Rp99.099.772
15,430,543
3,226,998,720
0.00

Anda mungkin juga menyukai