Anda di halaman 1dari 5

4/23/2017 3performancefactorsyoumustconsiderwhensizingbatteries|EEP

Menu
Searchforarticles,software&guides

Home
Technical Articles
Engineering Guides
Power Substations
Electrical Software
PLC Training

3performancefactorsyoumustconsiderwhen
sizingbatteries

Sizing batteries and 3 most important factors you must consider (photo credit: eepowersolutions.com)

Sizingbatteriescorrectly
Batteries need to be sized correctly to be able to feed the required load for the required time, and a number of
factors need to be decided to be able to optimize the battery for the duty expected. Some of these factors are
fixed within the chemistry of each type of cell and, in some cases, the physical structure of the plates that make up
the cell.

The performance is also influenced by the temperature and other location factors, and as an optimal
combination of cells is needed to provide the required performance, the following important factors need to be
considered:

http://electricalengineeringportal.com/performancefactorssizingbatteries 1/5
4/23/2017 3performancefactorsyoumustconsiderwhensizingbatteries|EEP

1. Maximum and minimum system voltage


2. Correction factor
3. Duty cycle

Systemvoltage(maximumandminimum)

The cells that make up any battery have a limited voltage range specific to the type of cell being used. In the case
of lead acid batteries, the cell nominal voltage, which is the voltage of a fully charged cell without any input charge
or load, is 2 V.

On the other hand, the minimum voltage that a battery cell can safely supply a load without damage is typically 1.7
V, although to give a margin of safety, it is more normal to use 1.75 as the operating minimum. Similarly, to be
able to charge a battery, the voltage across each cell must be more than the nominal 2 V, and to keep a battery
fully charged, each cell typically needs to be kept energized at 2.2 to 2.25 V, dependent on cell construction.

This is the float-charge voltage. Because individual cells in a battery can develop higher impedance than others
when floated for a significant time, or after they are discharged, batteries only charged on float can result in
some cells being less charged than others.

To overcome this condition, it is necessary to subject the battery to a higher voltage, the equalize charge voltage,
which could be up to 2.7 V per cell.

Although the higher voltage would allow a faster recharge and would even up the charge on individual cells more
quickly, this level of cell voltage would make the battery voltage range exceed the rating of most equipment that
uses DC supplies.

It is therefore usual practice to keep the equalize charge in the range of 2.33 to 2.5 V per cell and extend the
time required to equalize the battery.

Based on the above, the common battery size for a 125 V North American battery uses 60 cells with a battery
voltage range of 105 to 140 V DC. This range is computed as follows:

Equalizing voltage = 2.33 V per cell


Maximum battery voltage under equalized charge = 60 V 2.33 = 140 V
Minimum volts per cell = 1.75 V
Minimum battery voltage = 60 V 1.75 = 105 V

Because the equipment fed by such a battery must also be operable with a level of voltage drop in the associated
distribution cables, the operating range should cover the range 100140 V. For international use, the typical lead
acid battery consists of 55 cells having a battery voltage range of 96128 V, resulting in a required equipment
voltage range of 91128 V.

Some earlier equipment, particularly the incandescent lights used for display indications, could not cover this range
easily, and hence there is some use of batteries with a smaller number of cells and some use of end-cell switching
when equalizing a battery.

http://electricalengineeringportal.com/performancefactorssizingbatteries 2/5
4/23/2017 3performancefactorsyoumustconsiderwhensizingbatteries|EEP

It should be noted that, when using a smaller number of cells and a fixed minimum equipment operating voltage, the actual
Ah rating needs to be increased to match the lower voltage range available unless the minimum equipment voltage
rating can also be reduced.

The above examples are based on lead acid battery designs. For nickel cadmium and for other battery types, a
similar series of voltage levels, and hence the number of cells used for a particular battery rating, can be
established.

In this respect, as nickel cadmium is the most common, the associated voltages over and above their 1.2 V per
cell are 1.41.47 V float charge, 1.501.65 V equalize, and 0.951.0 V for the minimum for discharge, typically
leading to the use of 100 cells for a North American battery design and 9294 cells internationally.

It should be also noted that the voltage range for the nickel cadmium battery system is larger than for the lead
acid- based system, and hence precautions may need to be taken to protect sensitive equipment when nickel
cadmium batteries are used.

However, for many modern digital systems, wide-range power units are used, and the large range of battery
systems is less of a problem.

Lead Acid Battery Balancer

Go back to sizing batteries factors

2.Correctionfactor

The capacity of all batteries changes with temperature, and for lead acid batteries, more change is found,
particularly at the lower temperatures. The battery therefore has to be sized to provide the required standby time
even under the worst applicable temperature conditions.

As each particular cell type has its own particular characteristics, the design curves for the particular cell type
should be used in calculating the appropriate derating factor.

http://electricalengineeringportal.com/performancefactorssizingbatteries 3/5
4/23/2017 3performancefactorsyoumustconsiderwhensizingbatteries|EEP

Batteries also age with time, and it is usual to add a margin of 25% to cover that factor. Also, as loads may
increase, even during plant design, a design margin of about 1015% would be appropriate.

In new installations, the initial capacity is usually less than 100% (about 90%), and will only reach 100% after a
few equalizing charges.

Industrial Batteries: The Dos and Donts

Industrial Batteries: The Dos and Don'ts

Go back to sizing batteries factors

3.Dutycycle

It is necessary to detail the amount of power required for each function over the design discharge period.
Typically, the various classes of load considered are as follows:

1. Continuous load (indicating lamps, relays, etc.): 8 h


2. Communications (UPS, etc.): 3 h
3. Emergency light: 123 h
4. Intermittent or momentary (CB close and trip): 1 min

General-purpose battery systems typically include both load types 1 and 4, as noted above, while the other types,
particularly UPS, would be provided by dedicated batteries and require sufficient size to feed a fixed load level for
a fixed time.

For mixed-use batteries, the loading with time and the method recommended to calculate the battery size required
in power houses and switchyards is detailed in IEEE standards 485 [S1] and 1115 [S2], and are equally applicable
to industrial situations.

In such a case, the worst-case loading needs to consider a significant amount of momentary switching load
both at the start and end of the duty cycle, with a few random load events throughout the discharge cycle. When

http://electricalengineeringportal.com/performancefactorssizingbatteries 4/5
4/23/2017 3performancefactorsyoumustconsiderwhensizingbatteries|EEP

this duty is added up, the peak and total load can be calculated and then, using the specific battery-type
design figures, the battery-plate configuration and amp-hour rating can be computed.

The battery size given by each supplier depends on the minimum voltage at the end of the cycle which, for a lead acid
battery with an 8-h standby time, should be not less than 1.75 V per cell.

Although actual switchgear operating times are short, the standards recommend using a 1-min value for a sum of
the current taken by all devices simultaneously, with the circuit breakers tripping at the beginning and closing at
the end (8 h) of the discharge cycle.

Go back to sizing batteries factors

Reference // Industrial power systems by Khan Shoaib


Relatedelectricalguides&articles//

Sharewithengineers//

AboutAuthor//
Edvard Csanyi

Edvard - Electrical engineer, programmer and founder of EEP. Highly specialized for
design of LV high power busbar trunking (<6300A) in power substations, buildings and
industry fascilities. Designing of LV/MV switchgears.Professional in AutoCAD
programming and web-design.Present on Google+

2017 EEP - Electrical Engineering Portal. All Rights Reserved | Privacy Policy |
Terms of Service | 12 queries in 0.194 seconds.
Energy & Power For All!

SHARE

TOP
Get PDF

http://electricalengineeringportal.com/performancefactorssizingbatteries 5/5

Anda mungkin juga menyukai