A case study about :

Upgrade of mobile telecom network operation system project


) (selection of 2 work packages

Started 1-3-2016 finished 26-1-2017

EM669

:

2214630
Rafiq Algritly
2214630
EM669

1. Purpose
The purpose of this p is the analysis of two of the main Work Package in the project and to
evaluated the performance of the project management by calculating the variance between the
estimated and the actual time of completing the selected work packages .

2. Work Packages Description


The Packages consists of many tasks for software upgrade of the operation system .

The Work Package are:-

OSS (operation support system ) Upgrade which has the code 1.1.1.1
ENIQ (network performance management ) Upgrade which has the code 1.1.1.2

3. Project estimated time plane .

THE ESTAMATED START WHERE in February 3th and the estimated finished is in 30th of July as 180
day project duration .

2
Rafiq Algritly
2214630
EM669

4. Project selected work packages and activity .

Wpc work package WBS Task Name Duration Estimated


description cost
1.1.1.1 OSS Upgrade 1.1.1.1.1 OSS Health checkup 2 days 4160.820513
1.1.1.1.2 SFS/NAS Upgrade 2 days 4160.820513
1.1.1.1.3 MWS,Comif2, UAS2, 1 day 2080.410256
1.1.1.1.4 OMSAS,Amin server Pre 2 days 4160.820513
upgrade
1.1.1.1.5 Split cluster 1 day 2080.410256
1.1.1.1.6 Admin upgrade O12.2 - 2 days 4160.820513
13A
1.1.1.1.7 Admin upgrade O13A - 2 days 4160.820513
O13B R3L
1.1.1.1.8 Admin upgrade O13B 2 days 4160.820513
R3L- O14B.1
1.1.1.1.9 Amin server EU upgrade 1 day 2080.410256
on O14B.1
1.1.1.1.10 Admin server checks 1 day 2080.410256
1.1.1.1.11 Cut Over 1 day 2080.410256
1.1.1.1.12 Server Verification 1 day 2080.410256
1.1.1.1.13 COMIF1,UAS1 1 day 2080.410256

3
Rafiq Algritly
2214630
EM669

1.1.1.1.14 Cluster Build ,NEDSS 1 day 2080.410256


Upgrade
1.1.1.1.15 OSSRC Server 2 days 4160.820513
Monitoring
1.1.1.2 ENIQ Upgrade 1.1.1.2.1 Eniq Checkup 1 day 2080.410256
1.1.1.2.2 ENIQ Upgrade 13A.1 to 2 days 4160.820513
14A.1
1.1.1.2.3 ENIQ EU upgrade 1 day 2080.410256
1.1.1.2.4 DATA File verification 2 days 4160.820513
1.1.1.2.5 ENIQ Upgrade 14A.1 to 2 days 4160.820513
16A
1.1.1.2.6 ENIQ EU upgrade 1 day 2080.410256
TOTAL

4
Rafiq Algritly
2214630
EM669

5. Estimated cost work completion S -curve

70000 64,492.72

60000

50000

40000

30000
33,286.56
20000

10000 2,080.41
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

As can be seen that in the previous chart that the activity will take about 17 day to reach the
completion .

6. Learning curve during the project implementation


Cost

9000
8,321.64
8000

7000

6000 6,241.23

5000 4,160.82

4000

3000

2000

1000

5
Rafiq Algritly
2214630
EM669

As can be seen from thr above chart where the the earnd vaule can give estanation about the
learning prosses where at the start it was about 4160.8 Lyd at the end it has improved to 6241.23
which is due to buter communication between the project team leads to more productivity .

7. Project management performance


The all project was pa

Estimated project duration Actual project completion /day variance


/day

180 day 300 day -120 day

As can be seen from the above table the project is 3 months behind the schedule which due daly in
the preparation of the connection also 30 day delay in the HW delivery in the sea port and problem in
the access to danger site.