Anda di halaman 1dari 11

Reliability assessment of an automated distribution

system
S. Kazemi, M. Fotuhi-Firuzabad and R. Billinton

Abstract: Automation can greatly enhance distribution-network reliability by speeding up service


restoration and thus significantly reduce customer-outage time. The paper presents an approach to
assess quantitatively the adequacy of a particular automated distribution scheme designated as the
low interruption system (LIS). Owing to the use of a high-speed communication system and line
sensors, this automated scheme can reduce drastically the number of interruptions, the service
interruption time and also the area affected by the fault. This scheme provides a simple and cost-
effective way to automate distribution systems in which the remotely controlled switches speed up
isolation of faulted sections and the restoration of healthy sections through alternative routes. The
step-by-step calculation procedure is presented using a typical small automated distribution system.
The proposed technique is then applied to a larger distribution system to examine the effectiveness
of the technique and also to examine the level of reliability improvement achieved by automation.

1 Introduction the LIS automated scheme is expressed in terms of the


degree of improvement in the reliability indexes. Customer-
In todays competitive electricity market, utilities are interruption cost is considered to be a surrogate for the
expected to provide a highly reliable power supply at the actual worth of supply reliability and expressed in terms
lowest possible cost. Analysis of the customer-failure stat- of the cost per unit of unserved energy. The reduction in
istics of most utilities indicate that the distribution system the unserved energy owing to employment of the automated
makes the greatest individual contribution to the unavailabil- scheme is referred to as the incremental cost. The reduction
ity of supply to a customer. Electric-power-distribution in the interruption cost is then compared with the capital,
systems face a number of challenges and opportunities such operating and maintenance costs of an automated distri-
as ageing systems, availability of improved distribution- bution scheme. This, however, is a complex procedure
system technologies, demand for higher reliability, customer- and involves a number of factors and constraints, which
outage intolerance etc. These challenges reinforce the need to will be included in future work.
examine quantitatively the merits of the various reinforce-
ment schemes available to system planners so as to achieve 2 Low-interruption system
the highest possible incremental reliability and improvement
in the system. Distribution automation is recognised as a 2.1 Concepts
way to use appropriate technology intelligently to enhance
the reliability at reduced system-operation cost. Automated Distribution systems are normally in the form of radial
operation and service restoration can eliminate the need to feeders. Each feeder consists of a set of load sections with
perform switching operations manually and could have a sig- sectionalising switches and normally open loop switches.
nificant effect on the system reliability [13]. Installation of Any short circuit on a feeder causes the main breaker to
remotely controlled switches on distribution feeders is an operate. After the fault has been detected, however, the rel-
automation function that provides significant benefits both evant sectionalising switches can be opened and the breaker
during normal operation and under emergencies [4, 5]. reclosed. This procedure permits the restoration of as many
An approach is presented in this paper to assess quantitat- disconnected load points as possible to the main supply or to
ively the reliability of a specific automated distribution another feeder through normally open switches.
system designated as the LIS automated scheme. The The above operations are performed automatically when
technique is based on the event-tree methodology. To an automated scheme is employed in a distribution network.
demonstrate the impact of implementing the LIS automated In this case, the fault detection, isolation and service restor-
scheme on the distribution-network performance, com- ation can be accomplished sequentially and automatically,
parative studies are conducted using a typically large by controlling the automation equipment installed on the
distribution reliability-test system. The worth of employing network so as to reduce significantly the customer-outage
time. The distribution automation discussed in this paper
# The Institution of Engineering and Technology 2007 is restricted to the fault-isolation and service-restoration
doi:10.1049/iet-gtd:20050261 switching operations considering the fact that the majority
Paper first received 16th June 2005 and in revised form 19th January 2006 of fault currents in distribution systems are not too large
S. Kazemi and M. Fotuhi-Firuzabad are with the Department of Electrical
and can therefore be interrupted by section switches. This
Engineering, Sharif University of Technology, Tehran, Iran is particularly true in nonearthed and resistance-earthed
R. Billinton is with the Department of Electrical Engineering, University of systems. Consequently, with an earth fault, service interrup-
Saskatchewan, Saskatoon, Canada tions on the healthy sections are prevented by interrupting
E-mail: fotuhi@sharif.edu the fault current using the associated section switches.
IET Gener. Transm. Distrib., 2007, 1, (2), pp. 223 233 223

Authorized licensed use limited to: Universidad del Valle. Downloaded on April 23, 2009 at 20:34 from IEEE Xplore. Restrictions apply.
As noted above, this paper evaluates the performance of a 2.3 Reliability modelling
typical distribution automation system, designated as LIS
automated scheme, from a reliability point of view. The An appropriate reliability model associated with the switch-
construction of this automated scheme, as well as descrip- ing actions with respect to the earth and short-circuit faults
tions of its main components, can be found in detail in the is required to evaluate the reliability of the LIS automated
works of Kato et al. [6]. scheme. The concepts of passive and active failures [7, 8]
are used to include various operating states and switching
actions, as shown in Fig. 2. The passive-failure mode
2.2 Isolation procedures of faulted sections leads to state R while the active failure mode leads to
states S1 and S2 , respectively, for the earth and short-circuit
Fig. 1a shows a small distribution system with the LIS auto- faults. The three states passive, active S1 and active S2
mated scheme in the feeder. The system consists of several can be superimposed to create the combined state space
section switches (S) installed at judicious points along the diagram shown in Fig. 2. The repair process is assumed to
main feeder. Each switch is controlled by the associated be the same for both passive and active failures.
remote terminal unit (RTU) located beside it. The RTUB The state-space diagram includes the following states:
installed at the station provides supervisory monitoring U state before the fault;
and control for circuit breaker CB. A fault detector is also
located beside the switching device and has data links to R state after isolation but before repair is completed;
the RTU to distinguish a short-circuit fault from an earth S1 state after the earth fault but before isolation; and
fault. The fault-detector data analysed at the master S2 state after the short-circuit fault but before isolation.
station is used to determine the fault location. Owing to
the high-speed communication system and the line sensor,
the fault location is identified immediately after a fault 3 Evaluation procedure
occurs. Consequently, both the service-interruption time
and the number of load points to be disconnected are con- 3.1 General concepts
siderably reduced.
When an earth fault occurs, the faulted section is isolated Reliability assessment of a complex automatic-control
by section switches in the automated distribution system system is a relatively difficult task. It contains a large
and therefore does not cause interruption of the unfaulted number of automation components and control sequential
sections, as the main circuit breaker does not operate for actions. A modular approach is used to evaluate the
this type of fault. The isolation procedure on an earth reliability of an automatic-control system incorporating
fault between S2 and S3 is shown in Fig. 1b. If, however, these characteristics. This approach divides the control
a short-circuit fault occurs, the switches cannot interrupt system into modules that can be analysed independently.
the fault current and therefore it will cause the main All the modules are then combined and analysed using the
breaker to operate. The isolation procedure on a short- event tree method [7 9]. The impacts of the communi-
circuit fault between S2 and S3 is shown in Fig. 1c. cation system on the reliability of automatic control of a

fibre optic cable


master station

supply point 1 S5 supply point 2


CB S1 S2 S3 S4
1 2 3 4 5

RTUB RTU1 RTU2 RTU3 RTU4 RTU5


6 7 8 9 10

LP1 LP2 LP3 LP4 LP5

a
CB S1 S2 S3 S4 S5
1-a shortcircuit occurs
S1 S2 S3 S4 S5 between S2 and S3
1-earth fault occurs CB fault
between S1 and S2 2-CB trips
fault
2-S5 closes 3-S2 and S3 open

3-S2 and S3 open 4-CB closes

5-S5 closes

open circuit breaker open section or loop switch


interruption area
closed circuit breaker closed section or loop switch

b c

Fig. 1 Small automated distribution system and isolation procedure for different types of fault
a Typical small automated distribution system
b Isolation procedure on an earth fault between S2 and S2
c Isolation procedure on a short-circuit fault between S2 and S3

224 IET Gener. Transm. Distrib., Vol. 1, No. 2, March 2007

Authorized licensed use limited to: Universidad del Valle. Downloaded on April 23, 2009 at 20:34 from IEEE Xplore. Restrictions apply.
local automation equipment including the RTUs, communi-
S2 cation systems, power supply units, switching devices, and
fault detectors. The protection relays, breaker and switching
devices are connected to the RTU.

sw
lt
e
au
t-c ilur

itc
(ii) Identify the operational procedure when an earth fault or

tf

hi
a
ui
sh ve f

n
irc
a short-circuit fault occurs. Develop the system event tree in

g
ti
ac

or
terms of the control-component modules. Identify the
passive failure sequence of events together with the associated outcomes
U R in the control procedure for the fault location, isolation
repair and service restoration. The control process, following
occurrence of a fault, involves the sequential operation
ea

logic of a set of control component modules which can be


rth fail
ac
tiv

fau ure

g
in
recognised using an event tree. The isolation procedure
e

lt

itch
has been described in Section 2.2. If failure events occur

sw
in the control operating systems, e.g. a switch fails to
operate, the automation system will continue trying to
S1
restore as many load points as possible. For example,
when the control path to boundary switches fails, the
Fig. 2 State-space diagram for passive and active failures master station (MS) continues communicating with the
adjacent switches to isolate the fault and restore the discon-
nected healthy sections. For illustration purposes, assume
special automated scheme is presented in the works of He that an earth fault occurs between S2 and S3 in Fig. 1a.
et al. [9] using the concept of the event tree. The scheme An event tree can be developed for the control procedure
does not distinguish the occurrence of the earth faults in terms of its component modules, as shown in Fig. 4.
from the short-circuit faults. The LIS automated scheme The paths leading to the required outcome are first ident-
used in this paper is, however, more complicated than the ified. The probability of occurrence of each relevant path
scheme described in the works of He et al. [9]. For this is the product of the event probabilities in the path. The res-
reason, more detailed formula derivations and sensitivity toration probability of a particular load point can then be
analysis, as well as application to larger automated distri- obtained by summing the probabilities of each path
bution systems, are needed, which have been included in leading to the restoration of that load point.
this paper. (iii) Determine the contribution to the failure rate of
The system event trees are analysed according to two load point Lj by component Ci based on the concepts of
different starting points including occurrence of earth and conditional probability theory and using the restoration
short-circuit faults. When a fault occurs, the event tree is probabilities identified in step (ii)
deduced as a sequence of events involving success and
failure of the control modules. Using this approach, the
various possible outcomes of the control processes are lCi Lj fblGFCi Lj jGFCi  PGFCi c
identified and the associated outcome and restoration prob-
abilities are calculated. The average restoration time and blSFCi Lj jSFCi  PSFCi cg 1
average failure rate for the load points are calculated
using the restoration and failure probabilities. The system-
reliability indexes are then determined by aggregating the where
load-point indexes.
lCiLj overall contribution to the failure
rate of load point Lj due to earth
3.2 Steps of the evaluation procedure and short-circuit faults on com-
ponent Ci .
The procedure for reliability assessment of a LIS automated
scheme can be summarised in the following steps:
(i) Divide the automation system into modules which may MS LS5 LS2 LS1 LS3 LS4 LPs restored
contain a small or a large number of individual components.
Modules should be independent of each other, based on
S
their functional or operational features. The reliability S S
P1 = 1-2-4-5
P2 = 1-2-5
data associated with each module can be either derived by F
F
a separate reliability analysis or obtained from a data- S S P3 = 1-2
collection scheme. For illustration purposes, the control S S P4 = 1-4-5
F P5 = 1-5
system for the LIS automated scheme of Fig. 1a is S
F
F
divided into seven modules as depicted in Fig. 3. These S P6 = 1
F P7 = 4-5
modules have no shared components and are considered S
P8 = 5
F
to be independent. The local system (LS) contains the fault F
S P9 = none
F P10 = 1-2
S
F P11 = 1
master station
F
F P12 = none
P13 = none
LSB LS1 LS2 LS3 LS4 LS5
Fig. 4 Event-tree procedure when an earth fault occurs between
Fig. 3 System modules of Fig. 1 S2 and S3
LS1 LS5 local system of switches S success
LSB local system of breakers F failure

IET Gener. Transm. Distrib., Vol. 1, No. 2, March 2007 225

Authorized licensed use limited to: Universidad del Valle. Downloaded on April 23, 2009 at 20:34 from IEEE Xplore. Restrictions apply.
lGFCiLj and lSFCiLj contribution to the failure rate of concept of expectation
load point Lj by an earth fault or
a short-circuit fault on component 
Ci , respectively. lSFCi Lj lCi jSFCi Lj  PSFCi Lj lCi jSFCi Lj
GFCi and SFCi event that an earth fault or a short- 
circuit fault occurs on component
 PSFCi Lj lCi jSFCi Lj  PSFCi Lj
Ci , respectively.
P(GFCi) and P(SFCi) probability that an earth fault or a
3
short-circuit fault occurs on com-
ponent Ci , respectively. where:
SFCiLj and P(SFCiLj) event that the automation system
If an earth fault on component Ci does not affect load point can successfully remove the
Lj , then lGFCiLj zero. Otherwise, the following three effect on load point Lj of a short
different cases may occur based on the operation procedure circuit fault on component Ci
described in Section 2.2 and step (ii): and its associated probability,
respectively.
(a) The automation system can successfully remove the
SF Ci Lj and P(SF Ci Lj ) event that the automation system
effect on load point Lj of an earth fault on component Ci .
fails but the effect on load point
This condition has no effect on load point Lj .
Lj of a short-circuit fault on com-
(b) The automation system fails but the effect on load point
ponent Ci is removed by switch-
Lj of an earth fault on component Ci is removed by switch-
ing action and its associated
ing action. This condition affects load point Lj by the
probability, respectively.
average failure rate of component Ci .
(c) The effect on load point Lj of an earth fault on com- SF Ci Lj and P(SF Ci Lj ) event that the effect on load point
ponent Ci cannot be removed by the automation system or Lj of a short circuit fault on com-
switching action. This condition affects load point Lj by ponent Ci cannot be removed by
average failure rate of component Ci . the automation system or switch-
ing action and its associated prob-
The above cases are then weighted by their probabilities ability, respectively.
identified in step (ii) as shown below using the concepts This integrates the effects of each failure mode on the
of expectation outcome probabilities.
(iv) Determine the restoration time for each load point.
 Once a fault occurs, the affected load points can either be
lGFCi Lj 0jGFCi Lj  PGFCi Lj lCi jGFCi Lj restored by switching action or they have to remain isolated
until the failed component is repaired. For the former load
 points, two different possibilities can be considered:
 PGFCi Lj lCi jGFCi Lj  PGFCi Lj
(a) the control system is available, and switching is
achieved automatically; or
2
(b) the control system is not available, and switching
should be performed manually.
where
The restoration time for a LIS can therefore be determined
GFCiLj and P(GFCiLj) event that the automation system using the concepts of expectation:
can successfully remove the
effect on load point Lj of an rCi Lj fbrGFCi Lj jGFCi  PGFCi c
earth fault on component Ci
brSFCi Lj jSFCi  PSFCi cg 4
and its associated probability,
respectively.
where
GF Ci Lj and P(GF Ci Lj ) event that the automation system
fails but the effect on load point rCiLj overall outage time of load point
Lj of an earth fault on com- Lj due to earth and short-circuit
ponent Ci is removed by switch- faults of component Ci .
ing action and its associated rGFCiLj and rSFCiLj outage time of load point Lj due to
probability, respectively. an earth fault or a short-circuit
GF Ci Lj and P(GF Ci Lj ) event that the effect on load fault of component Ci ,
point Lj of an earth fault on com- respectively.
ponent Ci cannot be removed by If an earth fault on component Ci does not affect load point
the automation system or Lj , then rGFCiLj zero. Otherwise, the following three
switching action and its associ- different cases may occur based on the operation procedure
ated probability, respectively. described in Section 2.2 and step (ii):
lCi average failure rate of com-
ponent Ci . (a) The automation system can successfully remove the
effect on load point Lj of an earth fault on component Ci .
Also, if a short-circuit fault on component Ci does not This condition does not affect load point Lj .
affect load point Lj , then lSFCiLj zero. Otherwise, as in (b) The automation system fails but the effect on load point
(2), the average value of lSFCiLj is determined using the Lj of an earth fault on component Ci is removed by
226 IET Gener. Transm. Distrib., Vol. 1, No. 2, March 2007

Authorized licensed use limited to: Universidad del Valle. Downloaded on April 23, 2009 at 20:34 from IEEE Xplore. Restrictions apply.
switching action. This condition affects load point Lj by 4 Study results
manual switching time.
(c) The effect on load point Lj of an earth fault on com- The application of the proposed technique to a multiload
ponent Ci cannot be removed by automation system or point distribution system is illustrated using the system
switching action. This condition affects load point Lj by described in the works of Allan et al. [10]. The test
average repair time of component Ci . system is the distribution system connected to bus 2 of
the RBTS [10]. It is a relatively large distribution
In the following equation, the above conditions are system and consists of 22 load points. The required
weighted by their probabilities identified in step (ii) using reliability data are given in the works of Allan et al.
the concept of conditional probability theory [10]. A computer program has been developed to
perform the necessary computations. In the studies
 presented in this paper, only the 11 kV feeders are con-
rGFCi Lj 0jGFCi Lj  PGFCi Lj TMSW jGFCi Lj sidered and any failures in the 33 kV system, the 33/
11 kV substation, fuses, section and loop switches are
 ignored. They assume that the 11 kV source breakers
 PGFCi Lj rCi jGFCi Lj  PGFCi Lj 5 operate successfully when required to do so. Section
switches are assumed to open whenever possible to
isolate a fault. If possible, the load points that have
been disconnected are recovered using relevant section
where switches. It is also assumed that a spare transformer is
rCi average repair time of component Ci available for the low voltage transformer to reduce the
TMSW manual switching time. effect of transformer failure. In this case, a failed trans-
former can be replaced by the spare one within the instal-
Also, rSFCiLj is equal to zero if a short-circuit fault on com- lation time rather than leaving the load point
ponent Ci does not affect load point Lj . Otherwise, as in (5), disconnected for the repair time of the failed one.
the average value of rSFCiLj is determined as shown below When employing the LIS automated scheme for the test
system, it is assumed that breakers and each section and
 loop switch have an individual local system, and that they
rSFCi Lj TASW jSFCi Lj  PSFCi Lj TMSW jSFCi Lj are supervised and controlled by a local system of the
master station.

 PSFCi Lj rCi jSFCi Lj  PSFCi Lj 6
4.1 Comparative studies

where TASW is automatic switching time. To examine the reliability benefits of employing the auto-
(v) Deduce reliability indexes. The load-point and mated distribution scheme, several different comparative
system-reliability indexes can be obtained by analysing studies were conducted. An overall brief description of
the contribution associated with each failure event. For a various case studies is as follows:
given load point Lj , the reliability indexes are determined
by aggregating the calculated lCiLj and rCiLj . Cases 1 and 2: The automated scheme is not used and the
The load-point indexes are calculated as follows manual switching time is equal to 1 h and 3 h, respectively.
Cases 3 and 4: The automated scheme is used, the manual
switching time is equal to 1 h and 70% and 20% of the
X
NC failure events are assumed to be earth faults, respectively.
lLj lCi Lj 7 Cases 5 and 6: The automated scheme is used, the
i1 manual switching time is equal to 3 h and 70% and 20%
PNC of the failure events are assumed to be earth faults,
i1 lCi Lj rCi Lj
rLj PNC 8 respectively.
i1 lCi Lj
Descriptions of these case studies has been tabulated in
ULj lLj rLj 9 Table 1.
Tables 2 7 show the reliability indexes associated with
ENSLj ULj Laj 10 a selected number of load points in each feeder of the test
system. Overall system-reliability indexes are shown in
Table 8. Automation features are not included in the
where study results presented for cases 1 and 2. Table 2 (case
lLj average failure rate of load point Lj failure/year 1) shows the reliability indexes assuming the total iso-
lation and switching time to be 1 h. This is the time
rLj average outage time of load point Lj in (h)
required to restore the interrupted load points between
ULj average annual outage time of load point Lj in the supply point and the point of isolation before the
(h/year) repair process has been completed. The reliability
Laj average load connected to load point Lj in (kW) indexes are modified as this time is increased to 3 h, as
ENSLj average energy not supplied of load point Lj in shown in Table 3. In this case, the energy not supplied
(kWh/year) is increased from 6% for load point 8 to 22% for load
points 10 and 15. This can be seen clearly by comparing
NC number of components. the results shown in Tables 2 and 3. Impacts of employing
The system indexes such as SAIFI, SAIDI, CAIDI, AENS automation features are illustrated in Tables 4 7 in which
and ASAI are calculated using the load-point indexes [8]. the availability of the local systems for the master station,
IET Gener. Transm. Distrib., Vol. 1, No. 2, March 2007 227

Authorized licensed use limited to: Universidad del Valle. Downloaded on April 23, 2009 at 20:34 from IEEE Xplore. Restrictions apply.
Table 1: Description of various case studies

Case Automation system MST , hrs Probability of


Not used Used Earth fault P(GFCi) Short-circuit fault
P(SFCi) 1 2 P(GFCi)

1 X 1
2 X 3
3 X 1 0.7 0.3
4 X 1 0.2 0.8
5 X 3 0.7 0.3
6 X 3 0.2 0.8


MST: manual switching time in hours

Table 2: Load-point reliability indexes for case 1

Load point l (failures/year) r, h U, h/year ENS, kWh/year

1 0.22425 5.5753 1.2503 668.88


5 0.23225 6.4166 1.4902 843.48
7 0.23225 6.2487 1.4512 658.87
8 0.11975 10.378 1.2427 1242.7
9 0.11975 10.052 1.2037 1384.3
10 0.22750 5.5099 1.2535 670.62
13 0.23350 5.9722 1.3945 789.29
15 0.22750 5.5099 1.2535 569.09
16 0.23350 6.1949 1.4465 656.71
20 0.23550 6.3418 1.4935 845.32
22 0.23550 6.1762 1.4545 660.34

Table 3: Load-point reliability indexes for case 2

Load point l (failures/year) r, h U, h/year ENS, kWh/year

1 0.22425 6.7926 1.5233 814.94


5 0.23225 7.5920 1.7632 998.00
7 0.23225 7.5081 1.7437 791.66
8 0.11975 11.029 1.3207 1320.7
9 0.11975 10.866 1.3013 1496.4
10 0.22750 6.7385 1.5330 820.15
13 0.23350 7.2527 1.6935 958.52
15 0.22750 6.7385 1.5330 695.98
16 0.23350 7.3640 1.7195 780.65
20 0.23550 7.5287 1.7730 1003.5
22 0.23550 7.4459 1.7535 796.09

Table 4: Load-point reliability indexes for case 3

Load point l (failures/year) r, h U, h/year ENS, kWh/year

1 0.13518 8.2687 1.1178 598.01


5 0.14764 9.2120 1.3600 769.78
7 0.14155 9.2647 1.3115 595.40
8 0.09511 12.673 1.2054 1205.4
9 0.09057 12.783 1.1578 1331.5
10 0.13636 8.1980 1.1179 598.08
13 0.14078 8.8927 1.2519 708.56
15 0.14061 7.9635 1.1198 508.37
16 0.14443 9.0979 1.3140 596.57
20 0.14884 9.1385 1.3602 769.85
22 0.14274 9.1885 1.3116 595.45

228 IET Gener. Transm. Distrib., Vol. 1, No. 2, March 2007

Authorized licensed use limited to: Universidad del Valle. Downloaded on April 23, 2009 at 20:34 from IEEE Xplore. Restrictions apply.
Table 5: Load-point reliability indexes for case 4

Load point l (failures/year) r (h) U (h/year) ENS (kWh/year)

1 0.19880 5.6644 1.1261 602.46


5 0.20807 6.5766 1.3684 774.53
7 0.20634 6.3942 1.3194 598.99
8 0.11271 10.719 1.2082 1208.2
9 0.11141 10.421 1.1610 1335.1
10 0.20146 5.5914 1.1264 602.65
13 0.20701 6.0925 1.2612 713.83
15 0.20267 5.5616 1.1272 511.75
16 0.20805 6.3558 1.3223 600.34
20 0.21074 6.4948 1.3687 774.69
22 0.20900 6.3141 1.3196 599.11

Table 6: Load-point reliability indexes for case 5

Load point l (failures/year) r, h U, h/year ENS, kWh/year

1 0.13518 8.3268 1.1256 602.22


5 0.14764 9.2957 1.3724 776.77
7 0.14155 9.3541 1.3241 601.15
8 0.09512 12.706 1.2086 1208.6
9 0.09057 12.845 1.1634 1337.9
10 0.13636 8.2574 1.1260 602.42
13 0.14078 8.9887 1.2654 716.21
15 0.14061 8.0474 1.1316 513.73
16 0.14443 9.1523 1.3219 600.14
20 0.14884 9.2231 1.3727 776.97
22 0.14274 9.2789 1.3245 601.31

Table 7: Load-point reliability indexes for case 6

Load point l (failures/year) r, h U, h/year ENS, kWh/year

1 0.19880 5.7820 1.1495 614.97


5 0.20807 6.7113 1.3965 790.40
7 0.20634 6.5265 1.3467 611.38
8 0.11271 10.795 1.2167 1216.7
9 0.11141 10.524 1.1725 1348.4
10 0.20146 5.7108 1.1505 615.52
13 0.20701 6.2419 1.2921 731.34
15 0.20267 5.6875 1.1527 523.33
16 0.20805 6.4682 1.3457 610.96
20 0.21074 6.6303 1.3973 790.86
22 0.20900 6.4472 1.3475 611.74

Table 8: System-reliability indexes for different cases

Case SAIFI (interruption/ SAIDI CAIDI (h/customer AENS ASAI


customer year) (h/customer year) interruption) (kWh/customer year)

1 0.230541 1.3840 6.0034 8.811 0.9998420


2 0.230541 1.6592 7.1972 10.40 0.9998106
3 0.142522 1.2514 8.7808 8.047 0.9998571
4 0.205392 1.2601 6.1350 8.096 0.9998562
5 0.142522 1.2613 8.8498 8.112 0.9998560
6 0.205392 1.2860 6.2614 8.251 0.9998532

IET Gener. Transm. Distrib., Vol. 1, No. 2, March 2007 229

Authorized licensed use limited to: Universidad del Valle. Downloaded on April 23, 2009 at 20:34 from IEEE Xplore. Restrictions apply.
section switches, loop switches and breakers are assumed the results that the reliability indexes are considerably
to be 0.95. improved for all the load points. This is obvious, if the
Tables 4 and 5 show the study results associated with results presented in Tables 6 and 7 are compared with
cases 3 and 4, respectively. Switching time is assumed those shown in Table 3. The following concluding
to be 1 h for both cases. It can be seen that the reliability remarks can be made by comparing the results presented
indexes are improved for all the load points, although in Tables 2 8:
the amount of improvement is not the same for different
load points in the system. This can clearly be seen by (a) Employment of the automated distribution scheme will
comparing the results shown in Tables 4 and 5 with considerably improve the load point and system reliability if
those shown in Table 2. In addition, for a given load the earth-fault probability is high.
point this improvement is lower for the results shown in (b) Employment of the automated distribution scheme will
Table 5 than for those shown in Table 4. The reason for considerably improve the load-point and system reliability
this is that the degree of reliability improvement through if the manual switching time is high.
employing the automation system is higher for the case
when the earth-fault probability is more than that of a
short-circuit fault. In other words, the automation system 4.2 Sensitivity analysis
can prove to be more effective when earth-fault probability
is high. As can seen from Table 1, the earth-fault probabil- In the results presented in Section 4.1, it was assumed that
ties P(GFCi) for cases 3 and 4 are 0.7 and 0.2, the availabilities of the local systems for the master
respectively. station, section switches, loop switches and breakers are
Tables 6 and 7 show the study results associated 0.95. It is important to perform sensitivity studies and to
with cases 5 and 6, respectively. Switching time is consider the impacts on system and load-point indexes
assumed to be 3 h for both cases. It can be seen from of automation-system-component availabilities. This is

Fig. 5 Effects of different sensitivity analysis on the failure rate of load point 20
a Effects of availability of the local system breakers on the failure rate of load point 20
b Effects of availability of the local system master station on the failure rate of load point 20
c Effects of availability of the local system loop switches on the failure rate of load point 20
d Effects of availability of the local system section switches on the failure rate of load point 20

230 IET Gener. Transm. Distrib., Vol. 1, No. 2, March 2007

Authorized licensed use limited to: Universidad del Valle. Downloaded on April 23, 2009 at 20:34 from IEEE Xplore. Restrictions apply.
Fig. 6 Effects of different sensitivity analyses on the average energy not supplied at load point 20
a Effects of availability of the local system breakers on the ENS of load point 20
b Effects of availability of the local system master station on the ENS of load point 20
c Effects of availability of the local system loop switches on the ENS of load point 20
d Effects of availability of the local system section switches on the ENS of load point 20

illustrated in this Section by varying the availabilities of cases 3 and 5 with cases 4 and 6). The availability of the
these components and determining their effects on load- local system of breakers has no effect on SAIFI and the
point and system indexes. All the sensitivity analyses are failure rate of the load points, as it has been assumed that
conducted for the six case studies described in Table 1. circuit breakers operate successfully when required to do
Figs. 5 and 6, respectively, show the effects on the so. It can also be seen that SAIFI and the load-point
average failure rate and energy not supplied indices at failure rate are more sensitive to the availability of the
Load point 20 of the variation in the availabilities of the local systems of the master station and the section switches
local systems for the master station, section switches, than the availability of the local systems of loop switches or
loop switches and breakers. Similar sensitivity analyses breakers.
have been conducted to illustrate the effects of local- Fig. 8 shows the variation of SAIDI with respect to the
system availability on the system indexes. The results for availability of the local systems. It can be seen from
SAIFI and SAIDI are shown in Figs. 7 and 8. In these Fig. 8 that, for a large value of manual switching time
analyses, when the availability of a given local system is (cases 5 and 6), SAIDI decreases as the availability of
changed, the other local systems are assumed to be 95% the local systems is increased. SAIDI is not so sensitive
available. The results shown in Figs. 58 clearly demon- to the availability of the local systems when the manual
strate the reliability enhancement of the load point and switching time is small (cases 3 and 4). The values of
system indexes of employing the LIS automated scheme. earth- and short-circuit-fault probabilities have little
From the results shown in Figs. 5 and 7, it can be seen effect on SAIDI compared with their effects on SAIFI.
that SAIFI and average failure rate of load point 20 decrease It can also be seen from Fig. 8 that the set of results
as the availabilities associated with local systems of master associated with cases 1, 3, 4, 5 and 6 almost converges
station, section and loop switches are increased. For a given at large values of local-system availability. The reason
local-system availability, SAIFI and the average failure rate for this is that, at large values of local-system availability,
decrease as the earth-fault probability is increased (compare system unreliability (here SAIDI) is low irrespective of
IET Gener. Transm. Distrib., Vol. 1, No. 2, March 2007 231

Authorized licensed use limited to: Universidad del Valle. Downloaded on April 23, 2009 at 20:34 from IEEE Xplore. Restrictions apply.
Fig. 7 Effects of different sensitivity analyses on the system average interruption frequency index SAIFI
a Effects of availability of the local system breakers on SAIFI
b Effects of availability of the local system master station on SAIFI
c Effects of availability of the local system loop switches on SAIFI
d Effects of availability of the local system section switches on SAIFI

the amount of manual switching time or the earth- and 5 Conclusions


short-circuit-fault probabilities. As in Figs. 5 and 7, the
availability of the local systems of the master station This paper presents an approach for reliability assessment
and section switches have more effect on SAIDI than of a specific automated distribution system designated the
that of the availability of the local systems of loop LIS. The technique is based on the event-tree method-
switches or breakers. ology in which the impacts of earth- and short-circuit-fault
Other system indexes, i.e. CAIDI, AENS and ASAI, can probabilities, different values of manual switching time
be calculated for the above cases. Overall, the following and local-systems availability are included in the analyses.
concluding remarks can be made from the results presented The proposed technique is examined using a typical distri-
in Figs. 5 8 in conjunction with employment of the LIS bution system. Comparative studies were conducted to
automated scheme: illustrate the benefits of employing the automated
scheme using a distribution network. The study results
(i) Load-point-failure rates and SAIFI decrease, especially presented in this paper indicate that the load-point and
when the majority of failure events are earth faults. system reliability indexes are improved significantly by
(ii) Average down time and average energy not supplied of implementing this scheme. A sensitivity analysis is per-
the load points and the overall system decrease, especially formed to illustrate the impacts on the reliability indexes
when the value of the manual switching time is significantly of varying the availability of the local systems of the
high. master station, section switches, loop switches and break-
(iii) The availability of the local systems of the master ers. The results show clearly that short-circuit faults have
station and section switches have more effect on the more negative impacts on system reliability than do earth
load-point and overall-system-reliability indexes, than the faults. The effects of the automated scheme on the
availability of the local systems of the loop switches or reliability indexes is particularly obvious when the value
breakers. of manual switching time is significant.
232 IET Gener. Transm. Distrib., Vol. 1, No. 2, March 2007

Authorized licensed use limited to: Universidad del Valle. Downloaded on April 23, 2009 at 20:34 from IEEE Xplore. Restrictions apply.
Fig. 8 Effects of different sensitivity analyses on the system average interruption duration index SAIDI
a Effects of availability of the local system breakers on SAIDI
b Effects of availability of the local system master station on SAIDI
c Effects of availability of the local system loop switches on SAIDI
d Effects of availability of the local system section switches on SAIDI

6 References 6 Kato, K., Nagasaka, H., Okimoto, A., Kunieda, T., and
Nakamura, T.: Distribution automation systems for high
1 Atwell, E., Gamvrelis, T., Kearns, D., and Landman, R.: Automated quality power supply, IEEE Trans. Power Deliv., 1991, 6, (3),
distribution scheme speeds service restoration, IEEE Comput. Appl. pp. 11961204
Power, 1996, 9, (1), pp. 3337 7 Billinton, R., and Allan, R.N.: Reliability evaluation of engineering
2 Kendrew, T.J., and Marks, J.A.: Automated distribution comes of systems (Plenum Press, 1992, 2nd edn.)
age, IEEE Comput. Appl. Power, 1989, 2, (1), pp. 7 10 8 Bilinton, R., and Allan, R.N.: Reliability evaluation of power
3 Rigler, D.M., Hodgkins, W.R., and Allan, R.N.: Quantitative systems (Plenum Press, 1996, 2nd edn.)
reliability analysis of distribution system: automation, Power Eng. 9 He, Y., Soder, L., and Allan, R.N.: Distribution automation: impact of
J., 1999, 13, (4), pp. 201 204 communication system on reliability of automatic control. Proc.
4 Pahwa, A.: Role of distribution automation in restoration of Power Tech., 2001, Porto, vol. 3
distribution systems after emergencies. Transmission and 10 Allan, R.N., Billinton, R., Sjarief, I., Goel, L., and So, K.S.: A
Distribution Conf. Exp., IEEE/PES, 2001, vol. 2, pp. 1204 1205 reliability test system for educational purposes basic distribution
5 Hager, G.E., Bear, R.N.M., and Baum, A.S.: Automated distribution system data and results, IEEE Trans. Power Syst., 1991, 6, (2),
fault location system, IEEE Trans. Ind. Appl., 1996, 32, (3), pp. 813 820
pp. 704708

IET Gener. Transm. Distrib., Vol. 1, No. 2, March 2007 233

Authorized licensed use limited to: Universidad del Valle. Downloaded on April 23, 2009 at 20:34 from IEEE Xplore. Restrictions apply.

Anda mungkin juga menyukai