GAMBARAN UMUM PROYEK PENGURUGAN

JALAN TOLL PEJAGAN - PEMALANG

OWNER : BAKRIE BROTHERS

MAIN KONTRAKTOR : PT. SMR (PT. SEMESTA MARGA RAYA)


PT. TRI MANUNGGAL

PEMBAYARAN : PER 500.000 M3. (SKBDN / BANK GARANSI)

VOLUME KONTRAK : 5.000.000 M3. ATAU 250,000 DUMP

HARGA KONTRAK : Rp. 72,000.00 / M3. PADAT VIBRO

RENCANA ANGGARAN PELAKSANAAN ( PER M3. )

BIAYA RITASI DT & QUARRY :


1. SEWA DUMP TRUCK = Rp. 8,910
2. BIAYA BBM DT = Rp. 6,000
3. BIAYA SUPIR DT = Rp. 2,255
4. DEPOSIT TANAH = Rp. 6,250
5. SEWA EXCAVATOR = Rp. 935
6. BIAYA BBM ALAT = Rp. 802
7. BIAYA OPERATOR ALAT = Rp. 167
BIAYA PEMADATAN :
1. SEWA VIBRO & BULDOZER = Rp. 1,007
2. BIAYA BBM ALAT = Rp. 807
3. BIAYA OPERATOR ALAT = Rp. 203
BIAYA UMUM & ADMIN. :
1. PEMOTONGAN OLEH MAIN KONTRAKTOR
( UNTUK BIAYA PAJAK & ADMINISTRASI ) = Rp. 12,000
2. BIAYA PERSIAPAN/PENDAHULUAN = Rp. 2,000
JUMLAH = Rp. 41,336
PROFIT = Rp. 30,665
JUMLAH = Rp. 72,000

CATATAN : PROFIT Rp 30,665 /M3. BELUM TERMASUK UNTUK FEE SUKSES PHK MEDIASI

ASUMSI - ASUMSI :

WAKTU PELAKSANAAN :
VOLUME KONTRAK : 5,000,000 M3.
1. EXCAVATOR (BEKO)
KEMAMPUAN ALAT (EXCAVATOR) 50 M3./JAM
GALI/MUAT PER HARI = 10 JAM 500 M3.
JML PEMAKAIAN ALAT 10 UNIT
GALI/MUAT PER HARI = 10 JAM 5,000 M3.

JML WAKTU PELAKSANAAN 1,000 HARI


33 BULAN
2. DUMP TRUCK :
Kapasitas Dump truk 20 m3/DT
Frequensi Dump Truk 250 trip/hari
Jumlah armada 8 DT
Frequensi tiap 1 DT 33 trip

WAKTU SIKLUS ALAT/DT :


1. EXCAVATOR (BEKO)
Kapasitas Bucket 1.2 M3.
Kapasitas Produksi Per Jam 50 M3.
Jumlah Jam Kerja 10 Jam
Jumlah Produksi/Alat 500 M3.
Jumlah Pemakaian Alat 10 Unit
GAMBARAN UMUM PROYEK PENGURUGAN
JALAN TOLL PEJAGAN - PEMALANG

OWNER : BAKRIE BROTHERS

MAIN KONTRAKTOR : PT. SMR (PT. SEMESTA MARGA RAYA)


PT. TRI MANUNGGAL

PEMBAYARAN : PER 500.000 M3. (SKBDN / BANK GARANSI)


Jumlah Produksi Per Hari 5,000 M3.
GAMBARAN UMUM PROYEK PENGURUGAN
JALAN TOLL PEJAGAN - PEMALANG

OWNER : BAKRIE BROTHERS

MAIN KONTRAKTOR : PT. SMR (PT. SEMESTA MARGA RAYA)


PT. TRI MANUNGGAL

PEMBAYARAN : PER 500.000 M3. (SKBDN / BANK GARANSI)


2. DUMP TRUCK :
Jarak Tempuh 2 km
Waktu muat dan manouver 6 menit
Kecepatan (dgn muatan) 20 km/jam
Waktu tempuh (dgn muatan) 6 menit
Waktu bongkar dan manouver 2 menit
Kecepatan (tanpa muatan) 30 km/jam
Waktu tempuh (tanpa muatan) 4 menit
Jml Waktu Bongkar/Muat/Perjalanan 18 menit/trip
Jumlah trip tiap jam 3.33 trip/jam
0.30 jam/trip
Jam kerja per hari 10 jam/hari
Total trip per hari (real time) 33 trip/hari

Total daya angkut per hari/DT 667 m3 /hr/DT


Target Volume Angkut per hari 5,000 m3
Jumlah Dump Truk yg diperlukan 8 Unit DT

PREDIKSI PELAKSANAAN PEKERJAAN PENGURUGAN :

1 PEKERJAAN PERSIAPAN :
- DIREKSI KEET / SITE OFFICE
- MOBILISASI DAN DEMOBILISASI PERLATAN & PERSONIL
- PENGUKURAN LEVELING TANAH DASAR
- PEMBUATAN JALAN AKSES DARI QUARRY KE JALAN UMUM

2 PEKERJAAN PEMATANGAN LAHAN SEPANJANG DAERAH TIMBUNAN TANAH :


- PEMBONGKARAN TERHADAP PENGHALANG YANG MUNGKIN ADA
- MEMINDAHKAN DAN MENANGANI AIR YANG ADA AGAR TIDAK TERHENTI
- MEMBUANG DAN MENANGANI LOKASI TIMBUNAN TANAH YANG BERLUMPUR
- MENGHENTIKAN / MENYUMBAT SUMBER AIR TANAH YANG TIMBUL APABILA ADA

3 PEKERJAAN PEMADATAN TANAH DASAR SEPANJANG LOKASI KERJA

4 PEKERJAAN PENIMBUNAN TANAH DAN PEMADATAN


- SETIAP PENGHAMPARAN 30 CM. ATAU SESUAI KETENTUAN YANG ADA DALAM
SPESIFIKASI YANG DIKELUARKAN PIHAK OWNER DAN ATAU STANDAR PT. JASA MARGA

5 PEKERJAAN COMMISIONING TEST PEMADATAN DENGAN MENGGUNAKAN PERALATAN


SAND CONE DAN ATAU SHEEP FOOT ROLLER SAMPAI DENGAN MEMENUHI TINGKAT
KEPADATAN DAN DAYA DUKUNG YANG DITETAPKAN SESUAI PERATURAN UNTUK
JALAN TOLL.

PERALATAN YANG DIGUNAKAN :

1 EXCAVATOR 5 MOTOR GRADER


2 DUMP TRUCK 6 SHEEP FOOT ROLLER
3 BULDOZER 7 TRUCK TANGKI AIR
4 COMPACTOR / VIBRO ROLLER 8 PERALATAN PENDUKUNG LAINNYA

CILEGON, 12 DESEMBER 2009


S E & O
GAMBARAN UMUM PROYEK PENGURUGAN
JALAN TOLL PEJAGAN - PEMALANG

OWNER : BAKRIE BROTHERS

MAIN KONTRAKTOR : PT. SMR (PT. SEMESTA MARGA RAYA)


PT. TRI MANUNGGAL

PEMBAYARAN : PER 500.000 M3. (SKBDN / BANK GARANSI)


JAUHARY
RENCANA ANGGARAN PENDAPATAN DAN BIAYA OPERASIONAL
PROYEK PENGURUGAN JALAN TOLL PEJAGAN - PEMALANG

I. PENDAPATAN :
NILAI KONTRAK PENGURUGAN TANAH MERAH : 5.000.000 M3. x Rp. 72.000,- = Rp. 360,000,000,000

II. BIAYA OPERASIONAL (PENGELUARAN PROYEK) :

A. BIAYA RITASE DUMP TRUCK DAN QUARRY :


1 DUMP TRUCK :
SEWA : 135 UNIT x Rp. 30.000.000,- x 11 BULAN = Rp. 44,550,000,000
BBM : 20 LTR/TRIP x 250.000 TRIP x Rp. 6.000,- = Rp. 30,000,000,000
SUPIR : Rp. 250.000,-/HARI x 334 HARI x 135 UNIT = Rp. 11,272,500,000
= Rp. 85,822,500,000
2 EXCAVATOR :
SEWA : 10 UNIT x 3.340 JAM x Rp. 140.000,- / JAM = Rp. 4,676,000,000
BBM : 20 LTR x 3.340 JAM x 10 UNIT x Rp. 6.000,- = Rp. 4,008,000,000
OPERATOR : Rp. 250.000,-/HARI x 334 HARI x 10 UNIT = Rp. 835,000,000
= Rp. 9,519,000,000
3 PEMBELIAN TANAH MERAH :
: 250.000 DUMP (RIT) x Rp. 125.000,-/DUMP = Rp. 31,250,000,000
JUMLAH BIAYA RITASE DUMP TRUCK DAN QUARRY : = Rp. 126,591,500,000

B. BIAYA PEMADATAN :
1 SEWA ALAT :
- BULDOZER D6 : 6 UNIT x 3.340 JAM x Rp. 135.000,-/JAM = Rp. 2,705,400,000
- COMPACTOR/VIBRO R. : 3 UNIT x 2.338 JAM x Rp. 130.000,-/JAM = Rp. 911,820,000
- MOTOR GRADER : 3 UNIT x 2.338 JAM x Rp. 130.000,-/JAM = Rp. 911,820,000
- SHEEP FOOT ROLLER : 1 UNIT x 500 JAM x Rp. 135.000,-/JAM = Rp. 67,500,000
- TRUK TANGKI AIR : 2 UNIT x Rp. 20.000.000,- x 11 BULAN = Rp. 440,000,000
= Rp. 5,036,540,000
2 BBM ALAT :
- BULDOZER D6 : 20 LTR x 3.340 JAM x 6 UNIT x Rp. 6.000,- = Rp. 2,404,800,000
- COMPACTOR/VIBRO R. : 15 LTR x 2.338 JAM x 3 UNIT x Rp. 6.000,- = Rp. 631,260,000
- MOTOR GRADER : 15 LTR x 2.338 JAM x 3 UNIT x Rp. 6.000,- = Rp. 631,260,000
- SHEEP FOOT ROLLER : 15 LTR x 500 JAM x 1 UNIT x Rp. 6.000,- = Rp. 45,000,000
- TRUK TANGKI AIR : 80 LTR x 334 HARI x 2 UNIT x Rp. 6.000,- = Rp. 320,640,000
= Rp. 4,032,960,000
3 OPERATOR ALAT :
- BULDOZER D6 : Rp. 250.000,-/HARI x 334 HARI x 6 UNIT = Rp. 501,000,000
- COMPACTOR/VIBRO R. : Rp. 250.000,-/HARI x 224 HARI x 3 UNIT = Rp. 168,000,000
- MOTOR GRADER : Rp. 250.000,-/HARI x 224 HARI x 3 UNIT = Rp. 168,000,000
- SHEEP FOOT ROLLER : Rp. 250.000,-/HARI x 50 HARI x 1 UNIT = Rp. 12,500,000
- TRUK TANGKI AIR : Rp. 250.000,-/HARI x 334 HARI x 2 UNIT = Rp. 167,000,000
= Rp. 1,016,500,000
JUMLAH BIAYA PEMADATAN : = Rp. 10,086,000,000

C. BIAYA PEMOTONGAN DARI MAIN KONTRAKTOR :


UNTUK BIAYA PPH PAJAK KONSTRUKSI DAN BIAYA ADMINISTRASI : 5.000.000 M3. x Rp. 12.000,-/M3. = Rp. 60,000,000,000

D. BIAYA PERSIAPAN / PENDAHULUAN PROYEK :


1 BIAYA BIKIN DIREKSI KIT / SITE OFFICE = Rp. 75,000,000
2 BIAYA MOBILISASI DAN DEMOBILISASI PERALATAN & PERSONIL = Rp. 230,000,000
3 BIAYA PENGUKURAN LEVELING TANAH DASAR = Rp. 100,000,000
4 BIAYA BIKIN JALAN AKSES DARI QUARRY KE JALAN UMUM = Rp. 3,500,000,000
5 BIAYA PEMATANGAN LAHAN SEPANJANG LOKASI KERJA = Rp. 2,750,000,000
6 BIAYA OVERHEAD PROYEK, BIAYA COMMISIONING TEST PEMADATAN DAN BIAYA TAK TERDUGA LAINNYA = Rp. 3,345,000,000

JUMLAH BIAYA PERSIAPAN / PENDAHULUAN PROYEK : = Rp. 10,000,000,000

REKAPITULASI :

PENDAPATAN : = Rp. 360,000,000,000

BIAYA OPERASIONAL (PENGELUARAN PROYEK) :


A. JUMLAH BIAYA RITASE DUMP TRUCK DAN QUARRY = Rp. 126,591,500,000
B. JUMLAH BIAYA PEMADATAN = Rp. 10,086,000,000
C. JUMLAH PEMOTONGAN OLEH MAIN KONTRAKTOR = Rp. 60,000,000,000
D. JUMLAH BIAYA PERSIAPAN / PENDAHULUAN PROYEK = Rp. 10,000,000,000
= Rp. 206,677,500,000
KEUNTUNGAN KOTOR PROYEK : = Rp. 153,322,500,000

NOTE : BELUM TERMASUK FEE SUKSES UNTUK PIHAK MEDIASI.-