Maintenance Modifications
Previously the wall pusher has been electrically controlled, requiring charging after each
use. Reliability of the unit dropped off significantly last year and with the number of shift
calls increasing it was found that all failures were around the battery charger and the elec-
trical components.
At the same time, no shift calls had been made for the pneumatic/hydraulic pusher that is
in service.
With the help of Phil Martin, Neil Lindus and Nathan McLoughney the wall pusher has
been rebuilt to a pneumatic/hydraulic version. Central Maintenance did all the work in-
house and have achieved a great result under budget!
Initial feedback from the Refractory Supervisor has been extremely positive, thank you to
the team involved.
Story submitted by: Megan Scollay
Click on the light bulb icon & submit your idea online at the Good Ideas Page
2017 Certification Audit If its FloodedForget it!
Tomago recently underwent a Safety and Environment Management Systems
These photos are from the recent
audit, conducted by SAI Global. The audit once again resulted in Tomago re-
floods in Northern NSW
ceiving a recommendation that it be recertified as compliant against the interna-
tionally recognised standards of OHSAS 18001:2007 and ISO 14001:2004.
This is a fantastic achievement and would not be possible without the support
and commitment to safety and the environment across all areas of the site.
Tomagos consistently high standards of safety management and continued im-
proved performance over the past 2 to 3 years enabled our application for self-
insurance. SIRA (Self-Insurance Regulatory Authority) has assessed our appli-
I drive this road every day
cation which has progressed to the next stage for approval which is currently
listed on the SIRA website for public comment.
A special thankyou to everyone who provided the time to assist and sup-
port the auditor during their visit.
The idea was raised to use the skills of the onsite TAC
boiler maker which allowed the job to be completed
with all 12 HR ramps modified to a safer height. Some
of the hooks were in bad condition which have also
been repaired and straightened. This has taken a num-
ber of weeks but we have managed to complete the
work and at a cost of $5k. This is not only a cost saving
to the business and an efficient use of TAC labour, but
a safety improvement as well.
COURAGETRUSTPRIDE
Lucky Number 13
Two and half years ago the Casthouse experienced a change in process where Furnace 12 and 13 were no longer viable to
run and therefore mothballed. Since then, Peter Fishburn and his team have developed a project to re-use Furnace 13 as a
scrap remelt process.
The hard work and effort of many over five months has transformed the 30 year old furnace in the Casthouse.
A huge thanks to RIG Industrial Maintenance, Downer Electrical Maintenance, Macs Industrial Plumbing, Instrocal Instrumen-
tation along with Andrew Stoneman and Brent Dunn for their involvement with the project.
The testing and commissioning phase will start over the next few weeks.
Story submitted by: Peter Fishburn