The super structure work will be started once the abutment /pier
caps are completed and sufficient cured
1. Ground preparation.
2. Erecting of staging and shuttering.
3. Reinforcement.
4. Balance shuttering.
5. Concreting.
6. Expansion joint and wearing coat.
Ground preparation:-
Erection:-
The centering for the support of the superstructure formwork
is proposed to be placed on dry level ground. Therefore each span in
turn shall be leveled to the required elevation above the water level
and the stream shall be diverted by suitable arrangement as per site
conditions. Cribs of 450 mm X 450 mm X 1500 mm, 600 mm X 600
mm X 1800 mm, 600 mm X 600 mm X 1000 mm and other suitable
sizes or pipes with cup lock system or any suitable type of centering
shall be used to support the super structure form work. The design of
the formwork shall be furnished and got approved by the Engineer
before starting formwork and shuttering.
QUALITY CONTROL
TOLERANCES:
Cast-in-situ Superstructure: