Anda di halaman 1dari 3

National System Control Centre andInstallation of

SCADA/EMS System
Central Engineering Consultancy Bureau
415, Bauddhaloka Mawatha
Colombo 07, Sri Lanka.
Tel &Fax:(9411) 2668800, (9411) 2668956 E-mail: thusithapeiriscecb@yahoo.com Web:
www.cecbsl.lk
CECB/SCCMP/ELEC/046 PD/SCCMP/PkgA/LOT1/Gen/1
OUR REF. YOUR REF. 61-273
DATE 28-12-2016 DATE 19-12-2016
FROM PROJECT MANAGER, CECB
TO PROJECT DIRECTOR, CEB (SCCMP)
COPIES 01 DTS No.(for CEB use only)
DOCUMENT TRANSMITTAL SHEET
Electrical coordination plan on ceiling for equipment rooms- 1st floor
Location/ Subject
and Reflected ceiling for equipment rooms- 1st floor
Re COMMENTS
Ite
v Description Ref STATU
m DOCUMENT .
No S
No.
.
1.0 CEB-SCCMPL1-A/GEN-7- A 1. Provided drawing is not to scale which - AN(CAT
018-1 -II)
is mentioned in the drawing and duct
Electrical coordination sizes, heights etc are not indicated
plan on ceiling for
2. With reference to the fixing method of
equipment rooms- 1st
floor light fitting on ceiling, clarify whether
the provided space for AC duct above
light fitting at critical points are
sufficient
3. CCTV camera location in equipment
room shall be shifted from current
location to avoid visual barriers
occurred from precision AC ducting
4. Location of smoke detectors shall be
middle of the ceiling, hence speaker
location and smoke detector location
shall be interchanged
5. Powering the access controller shall be
done by a socket outlet fed by UPS
system and update the UPS power
drawings appropriately

2.0 CEB-SCCMPL1-A/GEN-7- B 1. Symbol location in drawing shall AN(CAT


013 be revised as per comments for -II)
Drawing No CEB-SCCMPL1-
Reflected ceiling for A/GEN-7-018-1 revision A
equipment
DATE rooms- 1stNAME SIGNATU
floor RE
Prepared 28.12.20 Eng. (Ms) T.
by 16 Sajani (CECB)
Checked
& 28.12.20 Eng. G.R.M.E.
Approve 16 Kumara (CECB)
d by