Anda di halaman 1dari 108

Analisa Page 1

DAFTAR ANALYSA BIAYA KONSTRUKSI SNI


TAHUN ANGGARAN 2015
SEMESTER I

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
1 1 M' PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 M
1.000 Btg Kayu seseh balok 8/12 x 3 3,772,700.00 - 3,772,700.00 3,772,700.00
2.500 Kg Semen portland 1,400.00 - 3,500.00 3,500.00
1.200 Lbr Seng gelombang 3" - 5" 56,500.00 - 67,800.00 67,800.00
0.005 M3 Pasir beton ex karangasem 230,000.00 - 1,150.00 1,150.00
0.009 M3 Krikil beton / koral pilihan 210,000.00 - 1,890.00 1,890.00
0.012 M3 Kayu usuk bayur 5,000,000.00 - 60,000.00 60,000.00
0.060 Kg Paku biasa 2" - 5" 31,800.00 - 1,908.00 1,908.00
0.450 Kg Meni besi 35,450.00 - 15,952.50 15,952.50
0.200 Oh Tukang kayu 85,000.00 17,000.00 - 17,000.00
0.400 Oh Pekerja 65,000.00 26,000.00 - 26,000.00
0.020 Oh Kepala Tukang kayu 90,000.00 1,800.00 - 1,800.00
0.020 Oh Mandor 95,000.00 1,900.00 - 1,900.00
46,700.00 3,924,900.50 3,971,600.50
2 1 M' PAGAR SEMENTARA DARI KAWAT BERDURI TINGGI 1,8 M
1.000 Btg Kayu seseh balok 8/12 x 3 3,772,700.00 - 3,772,700.00 3,772,700.00
2.000 Kg Semen portland 1,400.00 - 2,800.00 2,800.00
0.250 Kg Kawat duri 16,300.00 - 4,075.00 4,075.00
0.005 M3 Pasir beton ex karangasem 230,000.00 - 1,150.00 1,150.00
0.009 M3 Krikil beton / koral pilihan 210,000.00 - 1,890.00 1,890.00
0.060 Kg Paku biasa 2"- 5" 31,800.00 - 1,908.00 1,908.00
0.200 Oh Tukang kayu 85,000.00 17,000.00 - 17,000.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.020 Oh Kepala tukang kayu 90,000.00 1,800.00 - 1,800.00
0.020 Oh Mandor 95,000.00 1,900.00 - 1,900.00
40,200.00 3,784,523.00 3,824,723.00
3 1 M' PEMASANGAN BOUWPLANK
0.012 M3 Kayu begisting 2,350,000.00 - 28,200.00 28,200.00
0.020 Kg Paku biasa 2" - 5" 31,800.00 - 636.00 636.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
16,375.00 28,836.00 45,211.00
4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT
1.700 Btg kayu seseh 6/10x3M 3,772,700.00 - 6,413,590.00 6,413,590.00
0.210 M3 Kayu usuk bayur 5,000,000.00 - 1,050,000.00 1,050,000.00
0.300 Kg Paku biasa 2" - 5" 31,800.00 - 9,540.00 9,540.00
10.500 Kg Semen portland 1,400.00 - 14,700.00 14,700.00
0.030 M3 Pasir beton ex karangasem 230,000.00 - 6,900.00 6,900.00
0.050 M3 Koral beton 210,000.00 - 10,500.00 10,500.00
1.500 Lbr Seng gelombang BJLS 32 56,500.00 - 84,750.00 84,750.00
2.000 Oh Tukang kayu 85,000.00 170,000.00 - 170,000.00
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
Analisa Page 2

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.020 Oh Kepala Tukang kayu 90,000.00 1,800.00 - 1,800.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
241,550.00 7,589,980.00 7,831,530.00
Analisa Page 3

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
5 1 M2 PEMBUATAN RUMAH JAGA / KONSTRUKSI KAYU
3.000 Btg kayu seseh 6/10x3M 3,772,700.00 - 11,318,100.00 11,318,100.00
0.276 M3 Kayu usuk bayur 5,000,000.00 - 1,380,000.00 1,380,000.00
0.700 Kg Paku biasa 2" - 5" 31,800.00 - 22,260.00 22,260.00
1.500 Lbr Seng gelombang BJLS 32 56,500.00 - 84,750.00 84,750.00
1.500 Oh Tukang kayu 85,000.00 127,500.00 - 127,500.00
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
0.150 Oh Kepala Tukang kayu 90,000.00 13,500.00 - 13,500.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
210,750.00 12,805,110.00 13,015,860.00
6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERALATAN
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
11,250.00 - 11,250.00
7 1 M2 PEMBUATAN BEDENG BURUH
1.250 Btg kayu seseh 6/10x3M 3,772,700.00 - 4,715,875.00 4,715,875.00
0.186 M3 Kayu usuk bayur 5,000,000.00 - 930,000.00 930,000.00
0.300 Kg Paku biasa 2" - 5" 31,800.00 - 9,540.00 9,540.00
18.000 Kg Semen portland 1,400.00 - 25,200.00 25,200.00
0.030 M3 Pasir beton ex karangasem 230,000.00 - 6,900.00 6,900.00
0.050 M3 Koral beton 210,000.00 - 10,500.00 10,500.00
1.500 Lbr Seng gelombang BJLS 32 56,500.00 - 84,750.00 84,750.00
1.350 Lbr Plywood 4 MM 68,000.00 - 91,800.00 91,800.00
2.000 Oh Tukang kayu 85,000.00 170,000.00 - 170,000.00
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
0.200 Oh Kepala Tukang kayu 90,000.00 18,000.00 - 18,000.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
257,750.00 5,874,565.00 6,132,315.00
8 1 M2 PEMBUATAN BAK ADUKAN ( 40X50X20) CM
0.036 M3 Kayu bekisting 2,350,000.00 - 84,600.00 84,600.00
0.080 Kg Paku biasa 2" - 5" 31,800.00 - 2,544.00 2,544.00
0.007 M3 Usuk bayur 5,000,000.00 - 36,000.00 36,000.00
0.300 Oh Tukang kayu 85,000.00 25,500.00 - 25,500.00
0.002 Oh Mandor 95,000.00 142.50 - 142.50
25,642.50 123,144.00 148,786.50
9 1 M2 PEMBUATAN STEGGER DARI BAMBU UKURAN (40 X 50 X 20) CM
1.000 Btg Bambu dia 6-8/6 m 15,200.00 - 15,200.00 15,200.00
0.250 Kg Kawat beton 22,600.00 - 5,650.00 5,650.00
0.017 Oh Tukang kayu 85,000.00 1,445.00 - 1,445.00
0.002 Oh Kepala tukang kayu 90,000.00 180.00 - 180.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
19,110.00 20,850.00 39,960.00
10 1 M2 PEMBUATAN JALAN SEMENTARA
0.150 M3 Batu belah 15/20 ( telford ) 245,000.00 - 36,750.00 36,750.00
0.090 M3 Batu pecah 5/7 172,500.00 - 15,525.00 15,525.00
0.010 M3 Pasir pasang ( lokal ) 150,000.00 - 1,500.00 1,500.00
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
69,750.00 53,775.00 123,525.00
11 1 M3 BONGKARAN BETON BERTULANG
3.667 Oh Pekerja 65,000.00 238,355.00 - 238,355.00
Analisa Page 4

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.333 Oh Mandor 95,000.00 31,635.00 - 31,635.00
269,990.00 - 269,990.00
12 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH
2.667 Oh Pekerja 65,000.00 173,355.00 - 173,355.00
0.033 Oh Mandor 95,000.00 3,135.00 - 3,135.00
176,490.00 - 176,490.00
Analisa Page 5

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
13 1 M' PASANG PAGAR BETON PRACETAK (5 X 50 X 213) CM
0.986 Lbr Panel beton pracetak 135,000.00 - 133,110.00 133,110.00
0.525 Btg Kolom beton pracetak 115,000.00 - 60,375.00 60,375.00
0.074 M3 Pasir beton ex karangasem 230,000.00 - 17,020.00 17,020.00
0.146 M3 Krikil beton 210,000.00 - 30,660.00 30,660.00
45.000 Kg Semen portland 1,400.00 - 63,000.00 63,000.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.375 Oh Pekerja 65,000.00 24,375.00 - 24,375.00
0.012 Oh Kepala Tukang batu 90,000.00 1,080.00 - 1,080.00
0.019 Oh Mandor 95,000.00 1,805.00 - 1,805.00
37,885.00 304,165.00 342,050.00
II PEKERJAAN TANAH
1 1 M3 GALIAN TANAH BIASA SEDALAM 1 METER
0.750 Oh Pekerja 65,000.00 48,750.00 - 48,750.00
0.025 Oh Mandor 95,000.00 2,375.00 - 2,375.00
51,125.00 - 51,125.00
2 1 M3 GALIAN TANAH BIASA SEDALAM 2 METER
0.900 Oh Pekerja 65,000.00 58,500.00 - 58,500.00
0.045 Oh Mandor 95,000.00 4,275.00 - 4,275.00
62,775.00 - 62,775.00
3 1 M3 GALIAN TANAH BIASA SEDALAM 3 METER
1.050 Oh Pekerja 65,000.00 68,250.00 - 68,250.00
0.067 Oh Mandor 95,000.00 6,365.00 - 6,365.00
74,615.00 - 74,615.00
4 1 M3 GALIAN TANAH KERAS SEDALAM 1 METER
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
0.032 Oh Mandor 95,000.00 3,040.00 - 3,040.00
68,040.00 - 68,040.00
5 1 M3 GALIAN TANAH CADAS SEDALAM 1 METER
1.500 Oh Pekerja 65,000.00 97,500.00 - 97,500.00
0.060 Oh Mandor 95,000.00 5,700.00 - 5,700.00
103,200.00 - 103,200.00
6 1 M3 GALIAN TANAH LUMPUR SEDALAM 1 METER
1.200 Oh Pekerja 65,000.00 78,000.00 - 78,000.00
0.045 Oh Mandor 95,000.00 4,275.00 - 4,275.00
82,275.00 - 82,275.00
7 1 M2 PEKERJAAN STRIPPING SETINGGI 10 CM
0.050 Oh Pekerja 65,000.00 3,250.00 - 3,250.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
3,725.00 - 3,725.00
8 1 M3 PEMBUANGAN TANAH SEJAUH 15 METER
0.330 Oh Pekerja 65,000.00 21,450.00 - 21,450.00
0.010 Oh Mandor 95,000.00 950.00 - 950.00
22,400.00 - 22,400.00
9 1 M3 URUGAN KEMBALI
( Mengurug kembali 1 M3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian )
0.333 Pekerjaan galian biasa 51,125.00 17,041.67 - 17,041.67
17,041.67 - 17,041.67
10 1 M3 URUGAN KEMBALI
( Mengurug kembali 1 M3 galian dihitung dari 1/3 kali dari indeks pekerjaan galian )
0.333 Pekerjaan galian keras 68,040.00 22,680.00 - 22,680.00
22,680.00 - 22,680.00
Analisa Page 6

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
11 1 M3 PEMADATAN TANAH
0.500 Oh Pekerja 65,000.00 32,500.00 - 32,500.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
37,250.00 - 37,250.00
12 1 M3 URUGAN PASIR
1.200 M3 Pasir urug 150,000.00 - 180,000.00 180,000.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.010 Oh Mandor 95,000.00 950.00 - 950.00
20,450.00 180,000.00 200,450.00
13 1 M3 PEMASANGAN LAPISAN IJUK
6.000 Kg Ijuk 15,300.00 - 91,800.00 91,800.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
11,175.00 91,800.00 102,975.00
14 1 M3 URUGAN TASIRTU
1.200 M3 Tasirtu 96,000.00 - 115,200.00 115,200.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.025 Oh Mandor 95,000.00 2,375.00 - 2,375.00
18,625.00 115,200.00 133,825.00
15 1 M3 URUGAN TANAH URUG
1.200 M3 Tanah Urug 96,000.00 - 115,200.00 115,200.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.025 Oh Mandor 95,000.00 2,375.00 - 2,375.00
18,625.00 115,200.00 133,825.00
16 1 M3 PEMBUATAN JALAN SEMENTARA, TBL. 25 CM
0.275 M3 Batu belah 15/20 Cm 236,000.00 - 64,900.00 64,900.00
0.030 M3 Krikil beton / koral pilihan 210,000.00 - 6,300.00 6,300.00
0.050 M3 Pasir pasang ( lokal ) 150,000.00 - 7,500.00 7,500.00
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
0.100 Oh Mandor 95,000.00 9,500.00 - 9,500.00
74,500.00 78,700.00 153,200.00
III PEKERJAAN PONDASI
1 1 M3 PASANG PONDASI BATU KOSONG ( ANSTAMPING )
1.200 M3 Batu kali 236,000.00 - 283,200.00 283,200.00
0.432 M3 Pasir urug 150,000.00 - 64,800.00 64,800.00
0.780 Oh Pekerja 65,000.00 50,700.00 - 50,700.00
0.390 Oh Tukang batu 85,000.00 33,150.00 - 33,150.00
0.039 Oh Kepala tukang batu 90,000.00 3,510.00 - 3,510.00
0.039 Oh Mandor 95,000.00 3,705.00 - 3,705.00
91,065.00 348,000.00 439,065.00
2 1 M3 PASANG PONDASI BATU KALI 1 Pc : 3 Ps
1.200 M3 Batu kali 236,000.00 - 283,200.00 283,200.00
202.000 Kg Semen porland 1,400.00 - 282,800.00 282,800.00
0.485 M3 Pasir Pasang ex karangasem 235,000.00 - 113,975.00 113,975.00
1.500 Oh Pekerja 65,000.00 97,500.00 - 97,500.00
0.750 Oh Tukang batu 85,000.00 63,750.00 - 63,750.00
0.075 Oh Kepala tukang batu 90,000.00 6,750.00 - 6,750.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
175,125.00 679,975.00 855,100.00
3 1 M3 PASANG PONDASI BATU KALI 1 Pc : 4 Ps
1.200 M3 Batu kali 236,000.00 - 283,200.00 283,200.00
163.000 Kg Semen porland 1,400.00 - 228,200.00 228,200.00
Analisa Page 7

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.485 M3 Pasir pasang ex karangasem 235,000.00 - 113,975.00 113,975.00
1.500 Oh Pekerja 65,000.00 97,500.00 - 97,500.00
0.750 Oh Tukang batu 85,000.00 63,750.00 - 63,750.00
0.075 Oh Kepala tukang batu 90,000.00 6,750.00 - 6,750.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
175,125.00 625,375.00 800,500.00
4 1 M3 PASANG PONDASI BATU KALI 1 Pc : 5 Ps
1.100 M3 Batu kali 236,000.00 - 259,600.00 259,600.00
136.000 Kg Semen porland 1,400.00 - 190,400.00 190,400.00
0.544 M3 Pasir pasang ex karangasem 235,000.00 - 127,840.00 127,840.00
1.500 Oh Pekerja 65,000.00 97,500.00 - 97,500.00
0.750 Oh Tukang batu 85,000.00 63,750.00 - 63,750.00
0.075 Oh Kepala tukang batu 90,000.00 6,750.00 - 6,750.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
175,125.00 577,840.00 752,965.00
5 1 M3 PASANG PONDASI BATU KALI 1 Pc : 6 Ps
1.100 M3 Batu kali 236,000.00 - 259,600.00 259,600.00
117.000 Kg Semen porland 1,400.00 - 163,800.00 163,800.00
0.561 M3 Pasir pasang ex karangasem 235,000.00 - 131,835.00 131,835.00
1.500 Oh Pekerja 65,000.00 97,500.00 - 97,500.00
0.750 Oh Tukang batu 85,000.00 63,750.00 - 63,750.00
0.075 Oh Kepala tukang batu 90,000.00 6,750.00 - 6,750.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
175,125.00 555,235.00 730,360.00
2 1 M3 PASANG PONDASI BATU KALI 1 Pc : 8 Ps
1.100 M3 Batu kali 236,000.00 - 259,600.00 259,600.00
104.333 Kg Semen porland 1,400.00 - 146,066.20 146,066.20
0.578 M3 Pasir pasang ex karangasem 235,000.00 - 135,830.00 135,830.00
1.500 Oh Pekerja 65,000.00 97,500.00 - 97,500.00
0.750 Oh Tukang batu 85,000.00 63,750.00 - 63,750.00
0.075 Oh Kepala tukang batu 90,000.00 6,750.00 - 6,750.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
175,125.00 541,496.20 716,621.20
7 1 M3 PASANG PONDASI SUMURAN DIAMETER 1 M
0.450 M3 Batu kali 236,000.00 - 106,200.00 106,200.00
194.000 Kg Semen porland 1,400.00 - 271,600.00 271,600.00
0.312 M3 Pasir pasang ex karangasem 235,000.00 - 73,320.00 73,320.00
0.468 M3 Koral beton 210,000.00 - 98,280.00 98,280.00
2.400 Oh Pekerja 65,000.00 156,000.00 - 156,000.00
0.800 Oh Tukang batu 85,000.00 68,000.00 - 68,000.00
0.080 Oh Kepala tukang batu 90,000.00 7,200.00 - 7,200.00
0.119 Oh Mandor 95,000.00 11,305.00 - 11,305.00
242,505.00 549,400.00 791,905.00
8 1 M' PEMBANGUNAN TIANG PANCANG 40 X 40 CM BETON BERTULANG
0.019 M3 Pasir urug 150,000.00 - 2,850.00 2,850.00
0.094 M3 Pasir beton ex karangasem 235,000.00 - 22,090.00 22,090.00
0.150 M3 Koral beton 210,000.00 - 31,500.00 31,500.00
60.500 Kg Semen porland 1,400.00 - 84,700.00 84,700.00
45.000 Kg Besi beton U 32 14,918.00 - 671,310.00 671,310.00
0.900 Kg Kawat beton 22,600.00 - 20,340.00 20,340.00
0.032 M3 Kayu usuk bayur 5,000,000.00 - 160,000.00 160,000.00
0.120 Kg Paku reng 31,800.00 - 3,816.00 3,816.00
Analisa Page 8

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
0.670 Oh Tukang batu 85,000.00 56,950.00 - 56,950.00
0.067 Oh Kepala Tukang batu 90,000.00 6,030.00 - 6,030.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
132,730.00 996,606.00 1,129,336.00
Analisa Page 9

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
9 1 M' PEMBANGUNAN TIANG PANCANG 35 X 35 CM BETON BERTULANG
0.016 M3 Pasir urug 150,000.00 - 2,400.00 2,400.00
0.080 M3 Pasir beton ex karangasem 235,000.00 - 18,800.00 18,800.00
0.125 M3 Koral beton 210,000.00 - 26,250.00 26,250.00
49.000 Kg Semen porland 1,400.00 - 68,600.00 68,600.00
45.500 Kg Besi beton U 32 14,918.00 - 678,769.00 678,769.00
0.700 Kg Kawat beton 22,600.00 - 15,820.00 15,820.00
0.027 M3 Kayu kaso 5/7 bayur 5,000,000.00 - 135,000.00 135,000.00
0.120 Kg Paku reng 31,800.00 - 3,816.00 3,816.00
0.800 Oh Pekerja 65,000.00 52,000.00 - 52,000.00
0.500 Oh Tukang batu 85,000.00 42,500.00 - 42,500.00
0.050 Oh Kepala Tukang batu 90,000.00 4,500.00 - 4,500.00
0.040 Oh Mandor 95,000.00 3,800.00 - 3,800.00
102,800.00 949,455.00 1,052,255.00
10 1 M3 Memasang Pondasi Siklop, 60 % Beton Campuran 1PC : PB : 3 Kr dan 40 Batu Kali
0.450 M3 Batu kali belah 15/20 cm 236,000.00 - 106,200.00 106,200.00
194.000 Kg Semen porland 1,400.00 - 271,600.00 271,600.00
0.312 M3 Pasir pasang ex karangasem 235,000.00 - 73,320.00 73,320.00
0.468 M3 Koral beton 210,000.00 - 98,280.00 98,280.00
2.400 Oh Pekerja 65,000.00 156,000.00 - 156,000.00
0.800 Oh Tukang batu 85,000.00 68,000.00 - 68,000.00
0.080 Oh Kepala tukang batu 90,000.00 7,200.00 - 7,200.00
0.119 Oh Mandor 95,000.00 11,305.00 - 11,305.00
242,505.00 549,400.00 791,905.00
IV PEKERJAAN DINDING
1 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA , 1 PC : 2 PS
140.000 Bh Bata merah 5 x 11 x 22 Cm 900.00 - 126,000.00 126,000.00
43.500 Kg Semen porland 1,400.00 - 60,900.00 60,900.00
0.080 M3 Pasir pasang ex karangasem 235,000.00 - 18,800.00 18,800.00
0.600 Oh Pekerja 65,000.00 39,000.00 - 39,000.00
0.200 Oh Tukang batu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang batu 90,000.00 1,800.00 - 1,800.00
0.030 Oh Mandor 95,000.00 2,850.00 - 2,850.00
60,650.00 205,700.00 266,350.00
2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA , 1 PC : 3 PS
140.000 Bh Bata merah 5 x 11 x 22 Cm 900.00 - 126,000.00 126,000.00
32.950 Kg Semen porland 1,400.00 - 46,130.00 46,130.00
0.091 M3 Pasir pasang ex karangasem 235,000.00 - 21,385.00 21,385.00
0.600 Oh Pekerja 65,000.00 39,000.00 - 39,000.00
0.200 Oh Tukang batu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang batu 90,000.00 1,800.00 - 1,800.00
0.030 Oh Mandor 95,000.00 2,850.00 - 2,850.00
60,650.00 193,515.00 254,165.00
3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA , 1 PC : 4 PS
140.000 Bh Bata merah 5 x 11 x 22 Cm 900.00 - 126,000.00 126,000.00
26.550 Kg Semen porland 1,400.00 - 37,170.00 37,170.00
0.093 M3 Pasir pasang ex karangasem 235,000.00 - 21,855.00 21,855.00
0.600 Oh Pekerja 65,000.00 39,000.00 - 39,000.00
0.200 Oh Tukang batu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang batu 90,000.00 1,800.00 - 1,800.00
0.030 Oh Mandor 95,000.00 2,850.00 - 2,850.00
60,650.00 185,025.00 245,675.00
Analisa Page 10

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
4 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA ,1 PC : 5 PS
140.000 Bh Bata merah 5 x 11 x 22 Cm 900.00 - 126,000.00 126,000.00
22.200 Kg Semen porland 1,400.00 - 31,080.00 31,080.00
0.102 M3 Pasir pasang ex karangasem 235,000.00 - 23,970.00 23,970.00
0.600 Oh Pekerja 65,000.00 39,000.00 - 39,000.00
0.200 Oh Tukang batu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang batu 90,000.00 1,800.00 - 1,800.00
0.030 Oh Mandor 95,000.00 2,850.00 - 2,850.00
60,650.00 181,050.00 241,700.00
5 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 6 PS
140.000 Bh Bata merah 5 x 11 x 22 Cm 900.00 - 126,000.00 126,000.00
18.500 Kg Semen porland 1,400.00 - 25,900.00 25,900.00
0.122 M3 Pasir pasang ex karangasem 235,000.00 - 28,670.00 28,670.00
0.600 Oh Pekerja 65,000.00 39,000.00 - 39,000.00
0.200 Oh Tukang batu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang batu 90,000.00 1,800.00 - 1,800.00
0.030 Oh Mandor 95,000.00 2,850.00 - 2,850.00
60,650.00 180,570.00 241,220.00
6 1 M2 PASANGAN BATACO/HOLLOWBLOCK / CONE BLOCK (HB.20/CB20) 1 Pc : 3 Ps
12.500 Bh Bataco 10 x 20 x 40 2,200.00 - 27,500.00 27,500.00
8.500 Kg Semen porland 1,400.00 - 11,900.00 11,900.00
0.028 M3 Pasir pasang ex karangasem 235,000.00 - 6,514.20 6,514.20
0.350 Oh Pekerja 65,000.00 22,750.00 - 22,750.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
33,575.00 45,914.20 79,489.20
7 1 M2 PASANGAN BATACO/HOLLOWBLOCK / CONE BLOCK (HB.20/CB20) 1 Pc : 4 Ps
12.500 Bh Bataco 10 x 20 x 40 2,200.00 - 27,500.00 27,500.00
7.500 Kg Semen porland 1,400.00 - 10,500.00 10,500.00
0.028 M3 Pasir pasang ex karangasem 235,000.00 - 6,514.20 6,514.20
0.350 Oh Pekerja 65,000.00 22,750.00 - 22,750.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
33,575.00 44,514.20 78,089.20
8 1 M2 PASANGAN BATACO/HOLLOWBLOCK / CONE BLOCK (HB.15/CB15) 1 Pc : 4 Ps
18.500 Bh Bataco 8 x 15 x 36 2,000.00 - 37,000.00 37,000.00
11.250 Kg Semen porland 1,400.00 - 15,750.00 15,750.00
0.042 M3 Pasir pasang ex karangasem 235,000.00 - 9,870.00 9,870.00
0.320 Oh Pekerja 65,000.00 20,800.00 - 20,800.00
0.120 Oh Tukang batu 85,000.00 10,200.00 - 10,200.00
0.012 Oh Kepala tukang batu 90,000.00 1,080.00 - 1,080.00
0.016 Oh Mandor 95,000.00 1,520.00 - 1,520.00
33,600.00 62,620.00 96,220.00
9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 2 PS
70.000 Bh Bata merah 5 x 11 x 22 Cm 900.00 - 63,000.00 63,000.00
18.950 Kg Semen porland 1,400.00 - 26,530.00 26,530.00
0.038 M3 Pasir pasang ex karangasem 235,000.00 - 8,930.00 8,930.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
Analisa Page 11

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
30,325.00 98,460.00 128,785.00
Analisa Page 12

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
10 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 3 PS
70.000 Bh Bata merah 5 x 11 x 22 Cm 900.00 - 63,000.00 63,000.00
14.370 Kg Semen porland 1,400.00 - 20,118.00 20,118.00
0.040 M3 Pasir pasang ex karangasem 235,000.00 - 9,400.00 9,400.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
30,325.00 92,518.00 122,843.00
11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 4 PS
70.000 Bh Bata merah 5 x 11 x 22 Cm 900.00 - 63,000.00 63,000.00
11.500 Kg Semen porland 1,400.00 - 16,100.00 16,100.00
0.043 M3 Pasir pasang ex karangasem 235,000.00 - 10,105.00 10,105.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
30,325.00 89,205.00 119,530.00
12 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 5 PS
70.000 Bh Bata merah 5 x 11 x 22 Cm 900.00 - 63,000.00 63,000.00
9.680 Kg Semen porland 1,400.00 - 13,552.00 13,552.00
0.045 M3 Pasir pasang ex karangasem 235,000.00 - 10,575.00 10,575.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
30,325.00 87,127.00 117,452.00
13 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 6 PS
70.000 Bh Bata merah 5 x 11 x 22 Cm 900.00 - 63,000.00 63,000.00
8.320 Kg Semen porland 1,400.00 - 11,648.00 11,648.00
0.049 M3 Pasir pasang ex karangasem 235,000.00 - 11,515.00 11,515.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
30,325.00 86,163.00 116,488.00
14 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 8 PS
70.000 Bh Bata merah 5 x 11 x 22 Cm 900.00 - 63,000.00 63,000.00
6.500 Kg Semen porland 1,400.00 - 9,100.00 9,100.00
0.050 M3 Pasir pasang ex karangasem 235,000.00 - 11,750.00 11,750.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
30,325.00 83,850.00 114,175.00
15 1 M2 PASANGAN DINDING ROSTER 10 X 10 X 20 CM
50.000 Bh Roster/Kerawang merah 3,850.00 - 192,500.00 192,500.00
7.500 Kg Semen porland 1,400.00 - 10,500.00 10,500.00
0.035 M3 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
Analisa Page 13

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
30,325.00 18,725.00 241,550.00
Analisa Page 14

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
16 1 M2 PASANGAN DINDING BATA BERONGGA (12 X 11 X 24 CM) 1 PC : 3 PS
30.000 Bh Bata berongga ekspose 900.00 - 27,000.00 27,000.00
7.500 Kg Semen porland 1,400.00 - 10,500.00 10,500.00
0.035 M3 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
30,325.00 18,725.00 76,050.00
17 1 M2 PASANGAN DINDING BEDEG, RANGKA KAYU
1.500 M2 Bedeg/bilik bambu, klas I 59,090.00 - 88,635.00 88,635.00
0.014 Kg Kayu usuk 5/7 bayur 5,000,000.00 - 70,000.00 70,000.00
0.012 M3 Paku biasa 31,800.00 - 381.60 381.60
1.000 M' List kayu 2/4 bayur 13,100.00 - 13,100.00 13,100.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.050 Oh Tukang kayu 85,000.00 4,250.00 - 4,250.00
0.005 Oh Kepala tukang kayu 90,000.00 450.00 - 450.00
0.002 Oh Mandor 95,000.00 190.00 - 190.00
11,390.00 172,116.60 183,506.60
V PEKERJAAN PLESTERAN
1 1 M2 PLESTERAN 1 PC : 1 PS, TEBAL 15 MM
15.504 Kg Semen porland 1,400.00 - 21,705.60 21,705.60
0.016 M3 Pasir pasang ex karangasem 235,000.00 - 3,760.00 3,760.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.150 Oh Tukang batu 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang batu 90,000.00 1,350.00 - 1,350.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
35,025.00 25,465.60 60,490.60
2 1 M2 PLESTERAN 1 PC : 2 PS, TEBAL 15 MM
10.224 Kg Semen porland 1,400.00 - 14,313.60 14,313.60
0.020 M3 Pasir pasang ex karangasem 235,000.00 - 4,700.00 4,700.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.150 Oh Tukang batu 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang batu 90,000.00 1,350.00 - 1,350.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
35,025.00 19,013.60 54,038.60
3 1 M2 PLESTERAN 1 PC : 3 PS, TEBAL 15 MM
7.776 Kg Semen porland 1,400.00 - 10,886.40 10,886.40
0.023 M3 Pasir pasang ex karangasem 235,000.00 - 5,405.00 5,405.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.150 Oh Tukang batu 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang batu 90,000.00 1,350.00 - 1,350.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
35,025.00 16,291.40 51,316.40
4 1 M2 PLESTERAN 1 PC : 4 PS, TEBAL 15 MM
6.240 Kg Semen porland 1,400.00 - 8,736.00 8,736.00
0.024 M3 Pasir pasang ex karangasem 235,000.00 - 5,640.00 5,640.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.150 Oh Tukang batu 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang batu 90,000.00 1,350.00 - 1,350.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
35,025.00 14,376.00 49,401.00
Analisa Page 15

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
5 1 M2 PLESTERAN 1 PC : 5 PS, TEBAL 15 MM
5.184 Kg Semen porland 1,400.00 - 7,257.60 7,257.60
0.026 M3 Pasir pasang ex karangasem 235,000.00 - 6,110.00 6,110.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.150 Oh Tukang batu 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang batu 90,000.00 1,350.00 - 1,350.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
35,025.00 13,367.60 48,392.60
6 1 M2 PLESTERAN 1 PC : 6 PS, TEBAL 15 MM
4.416 Kg Semen porland 1,400.00 - 6,182.40 6,182.40
0.027 M3 Pasir pasang ex karangasem 235,000.00 - 6,345.00 6,345.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.150 Oh Tukang batu 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang batu 90,000.00 1,350.00 - 1,350.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
35,025.00 12,527.40 47,552.40
7 1 M2 PLESTERAN 1 PC : 7 PS, TEBAL 15 MM
3.936 Kg Semen porland 1,400.00 - 5,510.40 5,510.40
0.028 M3 Pasir pasang ex karangasem 235,000.00 - 6,580.00 6,580.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.150 Oh Tukang batu 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang batu 90,000.00 1,350.00 - 1,350.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
35,025.00 12,090.40 47,115.40
8 1 M2 PLESTERAN 1 PC : 8 PS, TEBAL 15 MM
3.456 Kg Semen porland 1,400.00 - 4,838.40 4,838.40
0.029 M3 Pasir pasang ex karangasem 235,000.00 - 6,815.00 6,815.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.150 Oh Tukang batu 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang batu 90,000.00 1,350.00 - 1,350.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
35,025.00 11,653.40 46,678.40
9 1 M2 PLESTERAN PONDASI 1 PC : 2 PS, TEBAL 20 MM
13.632 Kg Semen porland 1,400.00 - 19,084.80 19,084.80
0.027 M3 Pasir pasang ex karangasem 235,000.00 - 6,345.00 6,345.00
0.400 Oh Pekerja 65,000.00 26,000.00 - 26,000.00
0.200 Oh Tukang batu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang batu 90,000.00 1,800.00 - 1,800.00
0.022 Oh Mandor 95,000.00 2,090.00 - 2,090.00
46,890.00 25,429.80 72,319.80
10 1 M2 PLESTERAN PONDASI 1 PC : 3 PS, TEBAL 20 MM
10.368 Kg Semen porland 1,400.00 - 14,515.20 14,515.20
0.031 M3 Pasir pasang ex karangasem 235,000.00 - 7,285.00 7,285.00
0.400 Oh Pekerja 65,000.00 26,000.00 - 26,000.00
0.200 Oh Tukang batu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang batu 90,000.00 1,800.00 - 1,800.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
46,035.00 21,800.20 67,835.20
11 1 M2 PLESTERAN PONDASI 1 PC : 4 PS, TEBAL 20 MM
8.320 Kg Semen porland 1,400.00 - 11,648.00 11,648.00
0.032 M3 Pasir pasang ex karangasem 235,000.00 - 7,520.00 7,520.00
0.400 Oh Pekerja 65,000.00 26,000.00 - 26,000.00
Analisa Page 16

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.200 Oh Tukang batu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang batu 90,000.00 1,800.00 - 1,800.00
0.022 Oh Mandor 95,000.00 2,090.00 - 2,090.00
46,890.00 19,168.00 66,058.00
Analisa Page 17

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
12 1 M2 PLESTERAN PONDASI 1 PC : 5 PS, TEBAL 20 MM
6.912 Kg Semen porland 1,400.00 - 9,676.80 9,676.80
0.035 M3 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
0.400 Oh Pekerja 65,000.00 26,000.00 - 26,000.00
0.200 Oh Tukang batu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang batu 90,000.00 1,800.00 - 1,800.00
0.022 Oh Mandor 95,000.00 2,090.00 - 2,090.00
46,890.00 17,901.80 64,791.80
13 1 M2 PLESTERAN PONDASI 1 PC : 6 PS, TEBAL 20 MM
5.888 Kg Semen porland 1,400.00 - 8,243.20 8,243.20
0.036 M3 Pasir pasang ex karangasem 235,000.00 - 8,460.00 8,460.00
0.400 Oh Pekerja 65,000.00 26,000.00 - 26,000.00
0.200 Oh Tukang batu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang batu 90,000.00 1,800.00 - 1,800.00
0.022 Oh Mandor 95,000.00 2,090.00 - 2,090.00
46,890.00 16,703.20 63,593.20
14 1 M2 PLESTERAN SKONENG 1 PC : 2 PS, LEBAR 10 MM
0.500 Kg Semen porland 1,400.00 - 700.00 700.00
0.013 M3 Pasir pasang ex karangasem 235,000.00 - 3,055.00 3,055.00
0.080 Oh Pekerja 65,000.00 5,200.00 - 5,200.00
0.400 Oh Tukang batu 85,000.00 34,000.00 - 34,000.00
0.040 Oh Kepala tukang batu 90,000.00 3,600.00 - 3,600.00
0.004 Oh Mandor 95,000.00 380.00 - 380.00
43,180.00 3,755.00 46,935.00
15 1 M2 PLESTERAN GRANIT 1 PC : 2 GRANIT, TEBAL 10 MM
10.000 Kg Semen porland 1,400.00 - 14,000.00 14,000.00
15.000 Kg Batu Granit 9,000.00 - 135,000.00 135,000.00
0.450 Oh Pekerja 65,000.00 29,250.00 - 29,250.00
0.225 Oh Tukang batu 85,000.00 19,125.00 - 19,125.00
0.023 Oh Kepala tukang batu 90,000.00 2,070.00 - 2,070.00
0.023 Oh Mandor 95,000.00 2,185.00 - 2,185.00
52,630.00 149,000.00 201,630.00
16 1 M2 PLESTERAN TERASO 1 PC : 2 TERASO, TEBAL 10 MM
10.000 Kg Semen porland 1,400.00 - 14,000.00 14,000.00
15.000 M3 Batu teraso 8,000.00 - 120,000.00 120,000.00
0.450 Oh Pekerja 65,000.00 29,250.00 - 29,250.00
0.225 Oh Tukang batu 85,000.00 19,125.00 - 19,125.00
0.023 Oh Kepala tukang batu 90,000.00 2,070.00 - 2,070.00
0.023 Oh Mandor 95,000.00 2,185.00 - 2,185.00
52,630.00 134,000.00 186,630.00
17 1 M2 PLESTERAN CIPRAT / KAMPROT 1 PC : 2 PS.
4.320 Kg Semen porland 1,400.00 - 6,048.00 6,048.00
0.006 M3 Pasir pasang ex karangasem 235,000.00 - 1,410.00 1,410.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
30,325.00 7,458.00 37,783.00
18 1 M2 PLESTERAN SIAR 1 PC : 2 PS ( ACIAN )
6.340 Kg Semen porland 1,400.00 - 8,876.00 8,876.00
0.012 M3 Pasir pasang ex karangasem 235,000.00 - 2,820.00 2,820.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
Analisa Page 18

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.150 Oh Tukang batu 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang batu 90,000.00 1,350.00 - 1,350.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
35,025.00 11,696.00 46,721.00
Analisa Page 19

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
5 1 M2 ACIAN PC
3.250 Kg Semen porland 1,400.00 - 4,550.00 4,550.00
0.200 Oh Pekerja 65,000.00 13,000.00 - 13,000.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.010 Oh Mandor 95,000.00 950.00 - 950.00
23,350.00 4,550.00 27,900.00
VI PEKERJAAN KAYU
1 1 M3 PEKERJAAN KUSEN PINTU DAN JENDELA KAMPER
1.100 M3 Kayu kamper balok 6/12 8,700,000.00 - 9,570,000.00 9,570,000.00
1.250 Kg Paku 10 cm 33,900.00 - 42,375.00 42,375.00
1.000 Kg Lem Kayu ( lem fox ) 13,636.36 - 13,636.36 13,636.36
6.000 Oh Pekerja 65,000.00 390,000.00 - 390,000.00
18.000 Oh Tukang kayu 85,000.00 1,530,000.00 - 1,530,000.00
1.800 Oh Kepala tukang kayu 90,000.00 162,000.00 - 162,000.00
0.300 Oh Mandor 95,000.00 28,500.00 - 28,500.00
2,110,500.00 9,626,011.36 11,736,511.36
2 1 M3 PASANGAN KUSEN PINTU DAN JENDELA KAYU JATI
1.100 M3 Kayu jati balok 6/12 18,000,000.00 - 19,800,000.00 19,800,000.00
1.250 Kg Paku 10 cm 33,900.00 - 42,375.00 42,375.00
1.000 Kg Lem Kayu ( lem fox ) 13,636.36 - 13,636.36 13,636.36
6.000 Oh Pekerja 65,000.00 390,000.00 - 390,000.00
18.000 Oh Tukang kayu 85,000.00 1,530,000.00 - 1,530,000.00
1.800 Oh Kepala tukang kayu 90,000.00 162,000.00 - 162,000.00
0.300 Oh Mandor 95,000.00 28,500.00 - 28,500.00
2,110,500.00 19,856,011.36 21,966,511.36
3 1 M3 PASANGAN KUSEN PINTU DAN JENDELA KAYU BENGKIRAI
1.100 M3 Kayu bengkirai balok 6/12 12,500,000.00 - 13,750,000.00 13,750,000.00
1.250 Kg Paku 10 cm 33,900.00 - 42,375.00 42,375.00
1.000 Kg Lem Kayu 13,636.36 - 13,636.36 13,636.36
6.000 Oh Pekerja 65,000.00 390,000.00 - 390,000.00
18.000 Oh Tukang kayu 85,000.00 1,530,000.00 - 1,530,000.00
1.800 Oh Kepala tukang kayu 90,000.00 162,000.00 - 162,000.00
0.300 Oh Mandor 95,000.00 28,500.00 - 28,500.00
2,110,500.00 13,806,011.36 15,916,511.36
4 1 M3 PEKERJAAN KUSEN PINTU DAN JENDELA KERUING
1.100 M3 Kayu keruing balok 6/12 7,200,000.00 - 7,920,000.00 7,920,000.00
1.250 Kg Paku 10 cm 33,900.00 - 42,375.00 42,375.00
1.000 Kg Lem Kayu ( lem fox ) 13,636.36 - 13,636.36 13,636.36
6.000 Oh Pekerja 65,000.00 390,000.00 - 390,000.00
18.000 Oh Tukang kayu 85,000.00 1,530,000.00 - 1,530,000.00
1.800 Oh Kepala tukang kayu 90,000.00 162,000.00 - 162,000.00
0.300 Oh Mandor 95,000.00 28,500.00 - 28,500.00
2,110,500.00 7,976,011.36 10,086,511.36
5 1 M3 PEKERJAAN KUSEN PINTU DAN JENDELA BAYUR
1.100 M3 Kayu bayur balok 8/12 5,000,000.00 - 5,500,000.00 5,500,000.00
1.250 Kg Paku 10 cm 33,900.00 - 42,375.00 42,375.00
1.000 Kg Lem Kayu ( lem fox ) 13,636.36 - 13,636.36 13,636.36
6.000 Oh Pekerja 65,000.00 390,000.00 - 390,000.00
18.000 Oh Tukang kayu 85,000.00 1,530,000.00 - 1,530,000.00
1.800 Oh Kepala tukang kayu 90,000.00 162,000.00 - 162,000.00
0.300 Oh Mandor 95,000.00 28,500.00 - 28,500.00
Analisa Page 20

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
2,110,500.00 5,556,011.36 7,666,511.36
Analisa Page 21

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
6 1 M2 PEKERJAAN PINTU KLAMP KAYU BAYUR
0.040 M3 Kayu bayur papan 3/20 5,200,000.00 - 208,000.00 208,000.00
0.500 Kg Paku biasa 2" - 5" 13,636.36 - 6,818.18 6,818.18
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
3.000 Oh Tukang kayu 85,000.00 255,000.00 - 255,000.00
0.300 Oh Kepala tukang kayu 90,000.00 27,000.00 - 27,000.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
351,750.00 214,818.18 566,568.18
7 1 M2 PEKERJAAN PINTU PANEL KAYU KAMPER
0.040 M3 Kayu kamper papan 3/20 9,000,000.00 - 360,000.00 360,000.00
0.500 Kg Lem Kayu ( lem fox ) 13,636.36 - 6,818.18 6,818.18
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
3.000 Oh Tukang kayu 85,000.00 255,000.00 - 255,000.00
0.300 Oh Kepala tukang 90,000.00 27,000.00 - 27,000.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
351,750.00 366,818.18 718,568.18
8 1 M2 PEKERJAAN PINTU PANEL KAYU JATI
0.040 M3 Kayu jati papan 3/20 18,500,000.00 - 740,000.00 740,000.00
0.500 Kg Lem Kayu ( lem fox ) 13,636.36 - 6,818.18 6,818.18
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
3.000 Oh Tukang kayu 85,000.00 255,000.00 - 255,000.00
0.300 Oh Kepala tukang kayu 90,000.00 27,000.00 - 27,000.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
351,750.00 746,818.18 1,098,568.18
9 1 M2 PEKERJAAN PINTU DAN JENDELA KACA KAYU BAYUR
0.024 M3 Kayu bayur papan 3/20 5,200,000.00 - 124,800.00 124,800.00
0.950 M2 Kaca bening 5 mm 105,000.00 - 99,750.00 99,750.00
0.500 Kg Lem Kayu ( lem fox ) 13,636.36 - 6,818.18 6,818.18
0.800 Oh Pekerja 65,000.00 52,000.00 - 52,000.00
2.400 Oh Tukang kayu 85,000.00 204,000.00 - 204,000.00
0.240 Oh Kepala tukang kayu 90,000.00 21,600.00 - 21,600.00
0.040 Oh Mandor 95,000.00 3,800.00 - 3,800.00
281,400.00 231,368.18 512,768.18
9 1 M2 PEKERJAAN PINTU DAN JENDELA KACA KAYU KAMPER
0.024 M3 Kayu kamper papan 3/20 9,000,000.00 - 216,000.00 216,000.00
0.950 M2 Kaca bening 5 mm 105,000.00 - 99,750.00 99,750.00
0.500 Kg Lem Kayu ( lem fox ) 13,636.36 - 6,818.18 6,818.18
0.800 Oh Pekerja 65,000.00 52,000.00 - 52,000.00
2.400 Oh Tukang kayu 85,000.00 204,000.00 - 204,000.00
0.240 Oh Kepala tukang kayu 90,000.00 21,600.00 - 21,600.00
0.040 Oh Mandor 95,000.00 3,800.00 - 3,800.00
281,400.00 322,568.18 603,968.18
10 1 M2PEKERJAAN PINTU DAN JENDELA KACA KAYU KERUING
0.024 M3 Kayu keruing papan 3/20 7,600,000.00 - 182,400.00 182,400.00
0.950 M2 Kaca bening 5 mm 105,000.00 - 99,750.00 99,750.00
0.500 Kg Lem Kayu 13,636.36 - 6,818.18 6,818.18
0.800 Oh Pekerja 65,000.00 52,000.00 - 52,000.00
2.400 Oh Tukang kayu 85,000.00 204,000.00 - 204,000.00
0.240 Oh Kepala tukang kayu 90,000.00 21,600.00 - 21,600.00
0.040 Oh Mandor 95,000.00 3,800.00 - 3,800.00
281,400.00 288,968.18 570,368.18
Analisa Page 22

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
11 1 M2PEKERJAAN PINTU DAN JENDELA KACA KAYU JATI
0.024 M3 Kayu jati papan 3/20 18,500,000.00 - 444,000.00 444,000.00
0.950 M2 Kaca bening 5 mm 105,000.00 - 99,750.00 99,750.00
0.500 Kg Lem Kayu 13,636.36 - 6,818.18 6,818.18
0.800 Oh Pekerja 65,000.00 52,000.00 - 52,000.00
2.400 Oh Tukang kayu 85,000.00 204,000.00 - 204,000.00
0.240 Oh Kepala tukang kayu 90,000.00 21,600.00 - 21,600.00
0.040 Oh Mandor 95,000.00 3,800.00 - 3,800.00
281,400.00 550,568.18 831,968.18
12 1 M2 PEKERJAAN PINTU PLYWOOD RANGKAP, RANGKA KAYU KAMPER
0.025 M3 Kayu kamper papan 3/20 9,000,000.00 - 225,000.00 225,000.00
0.030 Kg Paku biasa 1/2" - 1" 31,800.00 - 954.00 954.00
0.500 Ltr Lem Kayu ( lem fox ) 13,636.36 - 6,818.18 6,818.18
1.000 Lbr Plywood tbl. 3 mm (90x220) cm 68,000.00 - 68,000.00 68,000.00
0.700 Oh Pekerja 65,000.00 45,500.00 - 45,500.00
2.100 Oh Tukang kayu 85,000.00 178,500.00 - 178,500.00
0.210 Oh Kepala tukang kayu 90,000.00 18,900.00 - 18,900.00
0.035 Oh Mandor 95,000.00 3,325.00 - 3,325.00
246,225.00 300,772.18 546,997.18
13 1 M2 PEKERJAAN PINTU PLYWOOD RANGKAP, RANGKA KAYU KERUING
0.025 M3 Kayu keruing papan 3/20 7,600,000.00 - 190,000.00 190,000.00
0.030 Kg Paku biasa 1/2" - 1" 31,800.00 - 954.00 954.00
0.500 Ltr Lem Kayu ( lem fox ) 13,636.36 - 6,818.18 6,818.18
1.000 Lbr Plywood tbl. 4 mm (90x220) cm 68,000.00 - 68,000.00 68,000.00
0.700 Oh Pekerja 65,000.00 45,500.00 - 45,500.00
2.100 Oh Tukang kayu 85,000.00 178,500.00 - 178,500.00
0.210 Oh Kepala tukang kayu 90,000.00 18,900.00 - 18,900.00
0.035 Oh Mandor 95,000.00 3,325.00 - 3,325.00
246,225.00 265,772.18 511,997.18
14 1 M2 PEKERJAAN PINTU PLYWOOD RANGKAP, RANGKA KAYU BAYUR
0.025 M3 Kayu bayur papan 3/20 5,200,000.00 - 130,000.00 130,000.00
0.030 Kg Paku biasa 1/2" - 1" 31,800.00 - 954.00 954.00
0.500 Ltr Lem Kayu ( lem fox ) 13,636.36 - 6,818.18 6,818.18
1.000 Lbr Plywood tbl. 4 mm (90x220) cm 68,000.00 - 68,000.00 68,000.00
0.700 Oh Pekerja 65,000.00 45,500.00 - 45,500.00
2.100 Oh Tukang kayu 85,000.00 178,500.00 - 178,500.00
0.210 Oh Kepala tukang kayu 90,000.00 18,900.00 - 18,900.00
0.035 Oh Mandor 95,000.00 3,325.00 - 3,325.00
246,225.00 205,772.18 451,997.18
15 1 M2 PEKERJAAN PINTU TEAKWOOD RANGKAP, RANGKA KAYU KAMPER
0.025 M3 Kayu kamper papan 3/20 9,000,000.00 - 225,000.00 225,000.00
0.030 Kg Paku biasa 1/2" - 1" 31,800.00 - 954.00 954.00
0.500 Ltr Lem Kayu ( lem fox ) 13,636.36 - 6,818.18 6,818.18
1.000 Lbr Teakwood tbl. 4 mm (90x220) cm 107,000.00 - 107,000.00 107,000.00
0.700 Oh Pekerja 65,000.00 45,500.00 - 45,500.00
2.100 Oh Tukang kayu 85,000.00 178,500.00 - 178,500.00
0.210 Oh Kepala tukang kayu 90,000.00 18,900.00 - 18,900.00
0.035 Oh Mandor 95,000.00 3,325.00 - 3,325.00
246,225.00 339,772.18 585,997.18
Analisa Page 23

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
16 1 M2 PEKERJAAN PINTU TEAKWOOD RANGKAP, RANGKA KAYU KERUING
0.025 M3 Kayu keruing papan 3/20 7,600,000.00 - 190,000.00 190,000.00
0.030 Kg Paku biasa 1/2" - 1" 31,800.00 - 954.00 954.00
0.500 Ltr Lem Kayu ( lem fox ) 13,636.36 - 6,818.18 6,818.18
1.000 Lbr Teakwood 90 x 220 x 4 mm 107,000.00 - 107,000.00 107,000.00
0.700 Oh Pekerja 65,000.00 45,500.00 - 45,500.00
2.100 Oh Tukang kayu 85,000.00 178,500.00 - 178,500.00
0.210 Oh Kepala tukang kayu 90,000.00 18,900.00 - 18,900.00
0.035 Oh Mandor 95,000.00 3,325.00 - 3,325.00
246,225.00 304,772.18 550,997.18
17 1 M2 PEKERJAAN PINTU TEAKWOOD RANGKAP, RANGKA KAYU BAYUR
0.025 M3 Kayu Bayur papan 3/20 5,200,000.00 - 130,000.00 130,000.00
0.030 Kg Paku biasa 1/2" - 1" 31,800.00 - 954.00 954.00
0.500 Ltr Lem Kayu ( lem fox ) 13,636.36 - 6,818.18 6,818.18
1.000 Lbr Teakwood 90 x 220 x 4 mm 107,000.00 - 107,000.00 107,000.00
0.700 Oh Pekerja 65,000.00 45,500.00 - 45,500.00
2.100 Oh Tukang kayu 85,000.00 178,500.00 - 178,500.00
0.210 Oh Kepala tukang kayu 90,000.00 18,900.00 - 18,900.00
0.035 Oh Mandor 95,000.00 3,325.00 - 3,325.00
246,225.00 244,772.18 490,997.18
18 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA KONVENSIONAL
KAYU KAMPER BENTANG 6 M'
1.100 M3 Kayu kamper balok 8,700,000.00 - 9,570,000.00 9,570,000.00
15.000 Bh Besi strip / begel 19,000.00 - 285,000.00 285,000.00
5.600 Kg Paku 12 CM 33,900.00 - 189,840.00 189,840.00
4.000 Oh Pekerja 65,000.00 260,000.00 - 260,000.00
12.000 Oh Tukang kayu 85,000.00 1,020,000.00 - 1,020,000.00
1.200 Oh Kepala tukang kayu 90,000.00 108,000.00 - 108,000.00
0.200 Oh Mandor 95,000.00 19,000.00 - 19,000.00
1,407,000.00 10,044,840.00 11,451,840.00
19 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA KONVENSIONAL
KAYU KERUING BENTANG 6 M'
1.100 M3 Kayu keruing balok 7,200,000.00 - 7,920,000.00 7,920,000.00
15.000 Bh Besi strip / begel 19,000.00 - 285,000.00 285,000.00
5.600 Kg Paku biasa 2" - 5" 31,800.00 - 178,080.00 178,080.00
4.000 Oh Pekerja 65,000.00 260,000.00 - 260,000.00
12.000 Oh Tukang kayu 85,000.00 1,020,000.00 - 1,020,000.00
1.200 Oh Kepala tukang kayu 90,000.00 108,000.00 - 108,000.00
0.200 Oh Mandor 95,000.00 19,000.00 - 19,000.00
1,407,000.00 8,383,080.00 9,790,080.00
20 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA KONVENSIONAL
KAYU SESEH KLAS I BENTANG 6 M'
1.100 M3 Kayu Seseh Klas I 3,772,700.00 - 4,149,970.00 4,149,970.00
15.000 Bh Besi strip / begel 19,000.00 - 285,000.00 285,000.00
5.600 Kg Paku biasa 2" - 5" 31,800.00 - 178,080.00 178,080.00
4.000 Oh Pekerja 65,000.00 260,000.00 - 260,000.00
12.000 Oh Tukang kayu 85,000.00 1,020,000.00 - 1,020,000.00
1.200 Oh Kepala tukang kayu 90,000.00 108,000.00 - 108,000.00
0.200 Oh Mandor 95,000.00 19,000.00 - 19,000.00
1,407,000.00 4,613,050.00 6,020,050.00
Analisa Page 24

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
21 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA EXPOSE
1.100 M3 Kayu Kamper 8,700,000.00 - 9,570,000.00 9,570,000.00
15.000 Bh Besi strip / begel 19,000.00 - 285,000.00 285,000.00
5.600 Kg Paku biasa 2" - 5" 31,800.00 - 178,080.00 178,080.00
6.700 Oh Pekerja 65,000.00 435,500.00 - 435,500.00
20.100 Oh Tukang kayu 85,000.00 1,708,500.00 - 1,708,500.00
2.010 Oh Kepala tukang kayu 90,000.00 180,900.00 - 180,900.00
0.335 Oh Mandor 95,000.00 31,825.00 - 31,825.00
2,356,725.00 10,033,080.00 12,389,805.00
22 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA EXPOSE
1.100 M3 Kayu Jati 18,000,000.00 - 19,800,000.00 19,800,000.00
15.000 Bh Besi strip / begel 19,000.00 - 285,000.00 285,000.00
5.600 Kg Paku biasa 2" - 5" 31,800.00 - 178,080.00 178,080.00
6.700 Oh Pekerja 65,000.00 435,500.00 - 435,500.00
20.100 Oh Tukang kayu 85,000.00 1,708,500.00 - 1,708,500.00
2.010 Oh Kepala tukang kayu 90,000.00 180,900.00 - 180,900.00
0.335 Oh Mandor 95,000.00 31,825.00 - 31,825.00
2,356,725.00 20,263,080.00 22,619,805.00
23 1 M2 PASANG USUK DAN RENG KAYU KAMPER ( ATAP GENTENG )
0.014 M3 Usuk kamper 8,700,000.00 - 121,800.00 121,800.00
0.0036 M3 Reng kamper 8,700,000.00 - 31,320.00 31,320.00
0.150 Kg Paku biasa 2"- 5" 31,800.00 - 4,770.00 4,770.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
16,375.00 157,890.00 174,265.00
24 1 M2 PASANG USUK DAN RENG KAYU KRUING ( ATAP GENTENG )
0.014 M3 Usuk kruing 7,200,000.00 - 100,800.00 100,800.00
0.0036 M3 Reng kruing 7,200,000.00 - 25,920.00 25,920.00
0.150 Kg Paku biasa 2"- 5" 31,800.00 - 4,770.00 4,770.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
16,375.00 131,490.00 147,865.00
25 1 M2 PASANG USUK DAN RENG KAYU BAYUR ( ATAP GENTENG )
0.014 M3 Usuk bayur 5,000,000.00 - 70,000.00 70,000.00
0.0036 M3 Reng bayur 5,000,000.00 - 18,000.00 18,000.00
0.150 Kg Paku biasa 2"- 5" 31,800.00 - 4,770.00 4,770.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
16,375.00 92,770.00 109,145.00
26 1 M2 PASANG USUK DAN RENG KAYU KAMPER ( ATAP GENTENG BETON )
0.014 M3 Usuk kamper 8,700,000.00 - 121,800.00 121,800.00
0.0072 M3 Reng kamper 8,700,000.00 - 62,640.00 62,640.00
0.250 Kg Paku biasa 2"- 5" 31,800.00 - 7,950.00 7,950.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
Analisa Page 25

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.005 Oh Mandor 95,000.00 475.00 - 475.00
16,375.00 192,390.00 208,765.00
Analisa Page 26

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
27 1 M2 PASANG PLAFOND 1 X 1 M ASBES SEMEN tebal 4 mm
1.100 Lbr Eternit / Asbes Semen 18,000.00 - 19,800.00 19,800.00
0.010 Kg Paku Triplex 22,700.00 - 227.00 227.00
0.030 Oh Pekerja 65,000.00 1,950.00 - 1,950.00
0.070 Oh Tukang kayu 85,000.00 5,950.00 - 5,950.00
0.007 Oh Kepala tukang kayu 90,000.00 630.00 - 630.00
0.004 Oh Mandor 95,000.00 380.00 - 380.00
8,910.00 20,027.00 28,937.00
28 1 M2 PASANG PLAFOND 1 X 1 M ( AKUSTIK 30 X 30 )
1.000 Lbr Eternit 18,000.00 - 18,000.00 18,000.00
0.050 Kg Paku Triplex 22,700.00 - 1,135.00 1,135.00
0.120 Oh Pekerja 65,000.00 7,800.00 - 7,800.00
0.120 Oh Tukang kayu 85,000.00 10,200.00 - 10,200.00
0.012 Oh Kepala tukang kayu 90,000.00 1,080.00 - 1,080.00
0.006 Oh Mandor 95,000.00 570.00 - 570.00
19,650.00 19,135.00 38,785.00
29 1 M2 PASANG PLAFOND TRIPLEK 1,20 X 2,40 M, TEBAL 4 MM
0.375 Lbr Triplek 4 mm 68,000.00 - 25,500.00 25,500.00
0.030 Kg Paku Triplek 22,700.00 - 681.00 681.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
16,375.00 26,181.00 42,556.00
30 1 M2 PASANG PLAFOND LAMBIZIRING KAYU JATI, TEBAL 9 MM
0.015 M3 Papan Jati 18,500,000.00 - 277,500.00 277,500.00
0.110 Kg Paku biasa 2"- 5" 31,800.00 - 3,498.00 3,498.00
0.180 Oh Pekerja 65,000.00 11,700.00 - 11,700.00
0.320 Oh Tukang kayu 85,000.00 27,200.00 - 27,200.00
0.032 Oh Kepala tukang kayu 90,000.00 2,880.00 - 2,880.00
0.077 Oh Mandor 95,000.00 7,267.50 - 7,267.50
49,047.50 280,998.00 330,045.50
31 1 M2 PASANG PLAFOND LAMBIZIRING KAYU KAMPER, TEBAL 9 MM
0.015 M3 Papan Kamper 9,000,000.00 - 135,000.00 135,000.00
0.110 Kg Paku biasa 2"- 5" 31,800.00 - 3,498.00 3,498.00
0.180 Oh Pekerja 65,000.00 11,700.00 - 11,700.00
0.320 Oh Tukang kayu 85,000.00 27,200.00 - 27,200.00
0.032 Oh Kepala tukang kayu 90,000.00 2,880.00 - 2,880.00
0.077 Oh Mandor 95,000.00 7,267.50 - 7,267.50
49,047.50 138,498.00 187,545.50
32 1 M2 PASANG PLAFOND GYPSUM BOARD 1,2 X 2,4 TEBAL 9 MM
0.364 Lbr Gypsum Board 79,000.00 - 28,756.00 28,756.00
0.110 Kg Paku Sekrup 31,800.00 - 3,498.00 3,498.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.050 Oh Tukang kayu 85,000.00 4,250.00 - 4,250.00
0.005 Oh Kepala tukang kayu 90,000.00 450.00 - 450.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
11,675.00 32,254.00 43,929.00
33 1 M' PASANG LIST PLAFOND GYPSUM PROFIL 7 CM
1.050 m' List gypsum profil 34,000.00 - 35,700.00 35,700.00
0.150 Kg Cornice 3,250.00 - 487.50 487.50
0.060 Oh Pekerja 65,000.00 3,900.00 - 3,900.00
Analisa Page 27

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.060 Oh Tukang kayu 85,000.00 5,100.00 - 5,100.00
0.006 Oh Kepala tukang kayu 90,000.00 540.00 - 540.00
0.003 Oh Mandor 95,000.00 285.00 - 285.00
9,825.00 36,187.50 46,012.50
Analisa Page 28

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
34 1 M' PASANG LIST PLAFOND KAYU PROFIL KAMPER
1.050 m' List kayu profil kamper 3/6 21,400.00 - 22,470.00 22,470.00
0.100 Kg Paku list 31,800.00 - 3,180.00 3,180.00
0.050 Oh Pekerja 65,000.00 3,250.00 - 3,250.00
0.050 Oh Tukang kayu 85,000.00 4,250.00 - 4,250.00
0.005 Oh Kepala tukang kayu 90,000.00 450.00 - 450.00
0.003 Oh Mandor 95,000.00 285.00 - 285.00
8,235.00 25,650.00 33,885.00
34 1 M' PASANG LIST PLAFOND KAYU PROFIL BAYUR
1.050 m' List kayu profil bayur 3/6 13,100.00 - 13,755.00 13,755.00
0.100 Kg Paku list 31,800.00 - 3,180.00 3,180.00
0.050 Oh Pekerja 65,000.00 3,250.00 - 3,250.00
0.050 Oh Tukang kayu 85,000.00 4,250.00 - 4,250.00
0.005 Oh Kepala tukang kayu 90,000.00 450.00 - 450.00
0.003 Oh Mandor 95,000.00 285.00 - 285.00
8,235.00 16,935.00 25,170.00
35 1 M2 PASANG RANGKA PLAFOND AKUSTIK 30 X 30 CM KAYU KAMPER
0.027 M3 Kayu kamper usuk 4/6 8,700,000.00 - 234,900.00 234,900.00
0.200 Kg Paku biasa 2" - 5" 31,800.00 - 6,360.00 6,360.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.350 Oh Tukang kayu 85,000.00 29,750.00 - 29,750.00
0.035 Oh Kepala tukang kayu 90,000.00 3,150.00 - 3,150.00
0.013 Oh Mandor 95,000.00 1,187.50 - 1,187.50
50,337.50 241,260.00 291,597.50
36 1 M2 PASANG RANGKA PLAFOND ETERNIT 0,50 X 1 M KAYU KAMPER
0.0154 M3 Kayu kamper usuk 4/6 8,700,000.00 - 133,980.00 133,980.00
0.200 Kg Paku biasa 2" - 5" 31,800.00 - 6,360.00 6,360.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.300 Oh Tukang kayu 85,000.00 25,500.00 - 25,500.00
0.030 Oh Kepala tukang kayu 90,000.00 2,700.00 - 2,700.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
45,075.00 140,340.00 185,415.00
37 1 M2 PASANG RANGKA PLAFOND ETERNIT 0,50 X 1 M KAYU KERUING
0.0154 M3 Kayu usuk keruing 4/6 7,200,000.00 - 110,880.00 110,880.00
0.200 Kg Paku biasa 2" - 5" 31,800.00 - 6,360.00 6,360.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.300 Oh Tukang kayu 85,000.00 25,500.00 - 25,500.00
0.030 Oh Kepala tukang kayu 90,000.00 2,700.00 - 2,700.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
45,075.00 117,240.00 162,315.00
Analisa Page 29

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
38 1 M2 PASANG RANGKA PLAFOND ETERNIT 0,50 X 1 M KAYU BAYUR
0.0154 M3 Kayu usuk bayur 4/6 5,000,000.00 - 77,000.00 77,000.00
0.200 Kg Paku biasa 2" - 5" 31,800.00 - 6,360.00 6,360.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.300 Oh Tukang kayu 85,000.00 25,500.00 - 25,500.00
0.030 Oh Kepala tukang kayu 90,000.00 2,700.00 - 2,700.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
45,075.00 83,360.00 128,435.00
39 1 M2 PASANG RANGKA PLAFOND 30 X 60 CM KAYU KAMPER
0.0163 M3 Kayu kamper usuk 4/6 8,700,000.00 - 141,810.00 141,810.00
0.250 Kg Paku biasa 2" - 5" 31,800.00 - 7,950.00 7,950.00
0.200 Oh Pekerja 65,000.00 13,000.00 - 13,000.00
0.300 Oh Tukang kayu 85,000.00 25,500.00 - 25,500.00
0.030 Oh Kepala tukang kayu 90,000.00 2,700.00 - 2,700.00
0.010 Oh Mandor 95,000.00 950.00 - 950.00
42,150.00 149,760.00 191,910.00
40 1 M2 PASANG RANGKA PLAFOND 30 X 60 CM KAYU KERUING
0.0163 M3 Kayu usuk keruing 4/6 7,200,000.00 - 117,360.00 117,360.00
0.250 Kg Paku biasa 2" - 5" 31,800.00 - 7,950.00 7,950.00
0.200 Oh Pekerja 65,000.00 13,000.00 - 13,000.00
0.300 Oh Tukang kayu 85,000.00 25,500.00 - 25,500.00
0.030 Oh Kepala tukang kayu 90,000.00 2,700.00 - 2,700.00
0.010 Oh Mandor 95,000.00 950.00 - 950.00
42,150.00 125,310.00 167,460.00
41 1 M2 PASANG RANGKA PLAFOND 30 X 60 CM KAYU BAYUR
0.0163 M3 Kayu Bayur usuk 4/6 5,000,000.00 - 81,500.00 81,500.00
0.250 Kg Paku biasa 2" - 5" 31,800.00 - 7,950.00 7,950.00
0.200 Oh Pekerja 65,000.00 13,000.00 - 13,000.00
0.300 Oh Tukang kayu 85,000.00 25,500.00 - 25,500.00
0.030 Oh Kepala tukang kayu 90,000.00 2,700.00 - 2,700.00
0.010 Oh Mandor 95,000.00 950.00 - 950.00
42,150.00 89,450.00 131,600.00
42 1 M' PASANG LISPLANG 3 X 20 CM, KAYU KAMPER
0.0108 M3 Kayu kamper papan 3/20 9,000,000.00 - 97,200.00 97,200.00
0.050 Kg Paku biasa 2" - 5" 31,800.00 - 1,590.00 1,590.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.200 Oh Tukang kayu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang kayu 90,000.00 1,800.00 - 1,800.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
25,775.00 98,790.00 124,565.00
43 1 M' PASANG LISPLANG 3 X 30 CM, KAYU KAMPER
0.013 M3 Kayu kamper papan 3/30 9,000,000.00 - 112,500.00 112,500.00
0.050 Kg Paku biasa 2" - 5" 31,800.00 - 1,590.00 1,590.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.200 Oh Tukang kayu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang kayu 90,000.00 1,800.00 - 1,800.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
25,775.00 114,090.00 139,865.00
44 1 M' PASANG LISPLANG 2 X (3 x 20) CM, KAYU KAMPER
0.015 M3 Kayu kamper papan 9,000,000.00 - 130,500.00 130,500.00
0.060 Kg Paku biasa 2" - 5" 31,800.00 - 1,908.00 1,908.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
Analisa Page 30

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.250 Oh Tukang kayu 85,000.00 21,250.00 - 21,250.00
0.025 Oh Kepala tukang kayu 90,000.00 2,250.00 - 2,250.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
40,375.00 132,408.00 172,783.00
Analisa Page 31

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
45 1 M' PASANG LISPLANG 3 X 20 CM, KAYU KERUING
0.0108 M3 Kayu keruing papan 3/20 7,600,000.00 - 82,080.00 82,080.00
0.050 Kg Paku biasa 2" - 5" 31,800.00 - 1,590.00 1,590.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.200 Oh Tukang kayu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang kayu 90,000.00 1,800.00 - 1,800.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
25,775.00 83,670.00 109,445.00
46 1 M' PASANG LISPLANG 2 X (3 x 20) CM, KAYU KERUING
0.015 M3 Kayu keruing papan 7,600,000.00 - 110,200.00 110,200.00
0.060 Kg Paku biasa 2" - 5" 31,800.00 - 1,908.00 1,908.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.250 Oh Tukang kayu 85,000.00 21,250.00 - 21,250.00
0.025 Oh Kepala tukang kayu 90,000.00 2,250.00 - 2,250.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
40,375.00 112,108.00 152,483.00
47 1 M' PASANG LISPLANG (3 X 20) CM KAYU BAYUR
0.0108 M3 Kayu bayur papan 2/20 5,200,000.00 - 56,160.00 56,160.00
0.050 Kg Paku biasa 2" - 5" 31,800.00 - 1,590.00 1,590.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.200 Oh Tukang kayu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang kayu 90,000.00 1,800.00 - 1,800.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
25,775.00 57,750.00 83,525.00
48 1 M' PASANG LISPLANG 2 X (2 X 20) CM KAYU BAYUR
0.009 M3 Kayu bayur papan 2/20 5,200,000.00 - 44,720.00 44,720.00
0.060 Kg Paku biasa 2" - 5" 31,800.00 - 1,908.00 1,908.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
20,650.00 46,628.00 67,278.00
49 1 M2 PASANG DINDING PEMISAH ( SKETSEL ) KAYU KAMPER + PLYWOOD 3 MM RANGKAP
0.028 M3 Kayu kamper balok 8,700,000.00 - 243,600.00 243,600.00
0.860 Lbr Plywood 4 mm 68,000.00 - 58,480.00 58,480.00
0.150 Kg Paku biasa 2" - 5" 31,800.00 - 4,770.00 4,770.00
0.560 Kg Lem kayu 13,636.36 - 7,636.36 7,636.36
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.450 Oh Tukang kayu 85,000.00 38,250.00 - 38,250.00
0.045 Oh Kepala tukang kayu 90,000.00 4,050.00 - 4,050.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
59,175.00 314,486.36 373,661.36
50 1 M2 PASANG DINDING PEMISAH ( SKETSEL ) KAYU KERUING + PLYWOOD 3 MM RANGKAP
0.028 M3 Kayu keruing balok 7,200,000.00 - 201,600.00 201,600.00
0.860 Lbr Plywood 3 mm 68,000.00 - 58,480.00 58,480.00
0.150 Kg Paku biasa 2" - 5" 31,800.00 - 4,770.00 4,770.00
0.560 Kg Lem kayu 13,636.36 - 7,636.36 7,636.36
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.450 Oh Tukang kayu 85,000.00 38,250.00 - 38,250.00
0.045 Oh Kepala tukang kayu 90,000.00 4,050.00 - 4,050.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
59,175.00 272,486.36 331,661.36
Analisa Page 32

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
51 1 M2 PASANG DINDING PEMISAH ( SKETSEL ) KAYU BAYUR + PLYWOOD 3 MM RANGKAP
0.028 M3 Kayu bayur balok 5,000,000.00 - 140,000.00 140,000.00
0.860 Lbr Plywood 4 mm 68,000.00 - 58,480.00 58,480.00
0.150 Kg Paku biasa 2" - 5" 31,800.00 - 4,770.00 4,770.00
0.560 Kg Lem kayu 13,636.36 - 7,636.36 7,636.36
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.450 Oh Tukang kayu 85,000.00 38,250.00 - 38,250.00
0.045 Oh Kepala tukang kayu 90,000.00 4,050.00 - 4,050.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
59,175.00 210,886.36 270,061.36
52 1 M2 PASANG DINDING PEMISAH ( SKETSEL ) KAYU KAMPER + TEAKWOOD 3 MM RANGKAP
0.028 M3 Kayu kamper balok 8,700,000.00 - 243,600.00 243,600.00
0.860 Lbr Teakwood 4 mm ( 120 x 220 ) 107,000.00 - 92,020.00 92,020.00
0.150 Kg Paku biasa 2" - 5" 31,800.00 - 4,770.00 4,770.00
0.560 Kg Lem kayu 13,636.36 - 7,636.36 7,636.36
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.450 Oh Tukang kayu 85,000.00 38,250.00 - 38,250.00
0.045 Oh Kepala tukang kayu 90,000.00 4,050.00 - 4,050.00
0.075 Oh Mandor 95,000.00 7,125.00 - 7,125.00
59,175.00 348,026.36 407,201.36
53 1 M2 PASANG DINDING LAMBRIZIRING KAMPER
0.007 M3 Kayu kamper papan 9,000,000.00 - 63,000.00 63,000.00
0.100 Kg Paku biasa 2" - 5" 31,800.00 - 3,180.00 3,180.00
0.600 Oh Pekerja 65,000.00 39,000.00 - 39,000.00
1.800 Oh Tukang kayu 85,000.00 153,000.00 - 153,000.00
0.180 Oh Kepala tukang kayu 90,000.00 16,200.00 - 16,200.00
0.080 Oh Mandor 95,000.00 7,600.00 - 7,600.00
215,800.00 66,180.00 281,980.00
54 1 M2 PASANG DINDING LAMBRIZIRING PLYWOOD ( 1,2 X 2,4 ) M
0.400 M3 Plywood 3 mm 68,000.00 - 27,200.00 27,200.00
0.050 Kg Paku biasa 1' - 2" 31,800.00 - 1,590.00 1,590.00
0.025 Oh Pekerja 65,000.00 1,625.00 - 1,625.00
0.075 Oh Tukang kayu 85,000.00 6,375.00 - 6,375.00
0.180 Oh Kepala tukang kayu 90,000.00 16,200.00 - 16,200.00
0.080 Oh Mandor 95,000.00 7,600.00 - 7,600.00
31,800.00 28,790.00 60,590.00
55 1 M2 PASANG DINDING BILIK BAMBU R. KAYU BAYUR
0.400 M2 Bilik Bambu / Bide kulit 59,090.00 - 23,636.00 23,636.00
0.014 M3 Usuk bayur 4/6 5,000,000.00 - 70,000.00 70,000.00
0.003 M' List Kayu 2/4 bayur 13,100.00 - 39.30 39.30
0.050 Kg Paku biasa 1' - 2" 31,800.00 - 1,590.00 1,590.00
0.025 Oh Pekerja 65,000.00 1,625.00 - 1,625.00
0.075 Oh Tukang kayu 85,000.00 6,375.00 - 6,375.00
0.180 Oh Kepala tukang kayu 90,000.00 16,200.00 - 16,200.00
0.080 Oh Mandor 95,000.00 7,600.00 - 7,600.00
31,800.00 95,265.30 127,065.30
VII PEKERJAAN BETON
1 1 M3 MEMBUAT BETON 1 PC : 2 PS : 4. KRL ( K 150 )
232.0000 Kg Semen porland 1,400.00 - 324,800.00 324,800.00
0.4500 M3 Pasir beton ex karangasem 230,000.00 - 103,500.00 103,500.00
0.9000 M3 Bt Pecah 1 - 2 300,000.00 - 270,000.00 270,000.00
1.6500 Oh Pekerja 65,000.00 107,250.00 - 107,250.00
Analisa Page 33

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.2500 Oh Tukang batu 85,000.00 21,250.00 - 21,250.00
0.0250 Oh Kepala Tukang batu 90,000.00 2,250.00 - 2,250.00
0.0800 Oh Mandor 95,000.00 7,600.00 - 7,600.00
138,350.00 698,300.00 836,650.00
Analisa Page 34

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
2 1 M3 MEMBUAT BETON 1 PC : 3 PS : 5 KRL ( K 125 )
218.0000 Kg Semen porland 1,400.00 - 305,200.00 305,200.00
0.5200 M3 Pasir beton ex karangasem 230,000.00 - 119,600.00 119,600.00
0.7800 M3 Bt Pecah 1 - 2 300,000.00 - 234,000.00 234,000.00
1.6500 Oh Pekerja 65,000.00 107,250.00 - 107,250.00
0.2500 Oh Tukang batu 85,000.00 21,250.00 - 21,250.00
0.0250 Oh Kepala Tukang batu 90,000.00 2,250.00 - 2,250.00
0.0800 Oh Mandor 95,000.00 7,600.00 - 7,600.00
138,350.00 658,800.00 797,150.00
3 1 M3 MEMBUAT BETON 1 PC : 2 PS : 3 Bt. Pc ( K. 175 )
280.0000 Kg Semen porland 1,400.00 - 392,000.00 392,000.00
0.5200 M3 Pasir beton ex karangasem 230,000.00 - 119,600.00 119,600.00
0.7800 M3 Bt Pecah 1 - 2 300,000.00 - 234,000.00 234,000.00
1.6500 Oh Pekerja 65,000.00 107,250.00 - 107,250.00
0.2500 Oh Tukang batu 85,000.00 21,250.00 - 21,250.00
0.0250 Oh Kepala Tukang batu 90,000.00 2,250.00 - 2,250.00
0.0800 Oh Mandor 95,000.00 7,600.00 - 7,600.00
138,350.00 745,600.00 883,950.00
4 1 M3 MEMBUAT BETON ( K 225 )
386.0000 Kg Semen porland 1,400.00 - 540,400.00 540,400.00
0.4700 M3 Pasir beton ex karangasem 230,000.00 - 108,100.00 108,100.00
0.7800 M3 Bt Pecah 1 - 2 300,000.00 - 234,000.00 234,000.00
1.6500 Oh Pekerja 65,000.00 107,250.00 - 107,250.00
0.2500 Oh Tukang batu 85,000.00 21,250.00 - 21,250.00
0.0250 Oh Kepala Tukang batu 90,000.00 2,250.00 - 2,250.00
0.0800 Oh Mandor 95,000.00 7,600.00 - 7,600.00
138,350.00 882,500.00 1,020,850.00
5 1 M3 MEMBUAT BETON KEDAP AIR DENGAN ADITIVE ( K 250 )
400.000 Kg Semen porland 1,400.00 - 560,000.00 560,000.00
0.480 M3 Pasir beton ex karangasem 230,000.00 - 110,400.00 110,400.00
0.800 M3 Bt Pecah 1 - 2 300,000.00 - 240,000.00 240,000.00
1.200 Kg Zat Aditive 85,000.00 - 102,000.00 102,000.00
210.000 Liter Air 700.00 - 147,000.00 147,000.00
2.100 Oh Pekerja 65,000.00 136,500.00 - 136,500.00
0.350 Oh Tukang batu 85,000.00 29,750.00 - 29,750.00
0.035 Oh Kepala Tukang batu 90,000.00 3,150.00 - 3,150.00
0.105 Oh Mandor 95,000.00 9,975.00 - 9,975.00
179,375.00 1,159,400.00 1,338,775.00
6 1 M' MEMBUAT WATER STOP LEBAR 150 MM
1.050 M' Water stop 150 mm 20,000.00 - 21,000.00 21,000.00
0.060 Oh Pekerja 65,000.00 3,900.00 - 3,900.00
0.030 Oh Tukang batu 85,000.00 2,550.00 - 2,550.00
0.003 Oh Kepala Tukang batu 90,000.00 270.00 - 270.00
0.003 Oh Mandor 95,000.00 285.00 - 285.00
7,005.00 21,000.00 28,005.00
7 1 M' MEMBUAT WATER STOP LEBAR 200 MM
1.050 M' Water stop 200 mm 25,000.00 - 26,250.00 26,250.00
0.060 Oh Pekerja 65,000.00 3,900.00 - 3,900.00
0.030 Oh Tukang batu 85,000.00 2,550.00 - 2,550.00
0.003 Oh Kepala Tukang batu 90,000.00 270.00 - 270.00
0.003 Oh Mandor 95,000.00 285.00 - 285.00
7,005.00 26,250.00 33,255.00
Analisa Page 35

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
8 1 M' MEMBUAT WATER STOP LEBAR 230 - 320 MM
1.050 M' Water stop 300 mm 30,000.00 - 31,500.00 31,500.00
0.060 Oh Pekerja 65,000.00 3,900.00 - 3,900.00
0.030 Oh Tukang batu 85,000.00 2,550.00 - 2,550.00
0.003 Oh Kepala Tukang batu 90,000.00 270.00 - 270.00
0.003 Oh Mandor 95,000.00 285.00 - 285.00
7,005.00 31,500.00 38,505.00
9 10 KG PEMBESIAN DENGAN BESI POLOS
10.500 Kg Besi beton U 24 12,500.00 - 131,250.00 131,250.00
0.150 Kg Kawat beton 22,600.00 - 3,390.00 3,390.00
0.070 Oh Pekerja 65,000.00 4,550.00 - 4,550.00
0.070 Oh Tukang besi 85,000.00 5,950.00 - 5,950.00
0.007 Oh Kepala tukang besi 90,000.00 630.00 - 630.00
0.004 Oh Mandor 95,000.00 380.00 - 380.00
11,510.00 134,640.00 146,150.00
10 10 KG PEMBESIAN DENGAN BESI ULIR
10.500 Kg Besi beton U 32 14,918.00 - 156,639.00 156,639.00
0.150 Kg Kawat beton 22,600.00 - 3,390.00 3,390.00
0.070 Oh Pekerja 65,000.00 4,550.00 - 4,550.00
0.070 Oh Tukang besi 85,000.00 5,950.00 - 5,950.00
0.007 Oh Kepala tukang besi 90,000.00 630.00 - 630.00
0.004 Oh Mandor 95,000.00 380.00 - 380.00
11,510.00 160,029.00 171,539.00
11 1 M2 PASANG JARING KAWAT BAJA / WIRE MESH
1.020 Kg Jaring Kawat Baja Las M5 55,000.00 - 56,100.00 56,100.00
0.050 Kg Kawat beton 22,600.00 - 1,130.00 1,130.00
0.025 Oh Pekerja 65,000.00 1,625.00 - 1,625.00
0.025 Oh Tukang besi 85,000.00 2,125.00 - 2,125.00
0.002 Oh Kepala tukang besi 90,000.00 180.00 - 180.00
0.001 Oh Mandor 95,000.00 95.00 - 95.00
4,025.00 57,230.00 61,255.00
12 1 M2 PASANG JARING KAWAT BAJA / WIRE MESH
1.020 Kg Jaring Kawat Baja Las M6 75,000.00 - 76,500.00 76,500.00
0.050 Kg Kawat beton 22,600.00 - 1,130.00 1,130.00
0.025 Oh Pekerja 65,000.00 1,625.00 - 1,625.00
0.025 Oh Tukang besi 85,000.00 2,125.00 - 2,125.00
0.002 Oh Kepala tukang besi 90,000.00 180.00 - 180.00
0.001 Oh Mandor 95,000.00 95.00 - 95.00
4,025.00 77,630.00 81,655.00
12 1 M2 PASANG BEGESTING UNTUK PONDASI
0.040 M3 Kayu klas III ( begisting ) 2,350,000.00 - 94,000.00 94,000.00
0.300 Kg Paku biasa 5 - 10 cm 31,800.00 - 9,540.00 9,540.00
0.520 Oh Pekerja 65,000.00 33,800.00 - 33,800.00
0.260 Oh Tukang kayu 85,000.00 22,100.00 - 22,100.00
0.026 Oh Kepala Tukang kayu 90,000.00 2,340.00 - 2,340.00
0.026 Oh Mandor 95,000.00 2,470.00 - 2,470.00
60,710.00 103,540.00 164,250.00
13 1 M2 PASANG BEGESTING UNTUK SLOOFT
0.045 M3 Kayu klas III ( begisting ) 2,350,000.00 - 105,750.00 105,750.00
0.300 Kg Paku biasa 5 - 10 cm 31,800.00 - 9,540.00 9,540.00
0.520 Oh Pekerja 65,000.00 33,800.00 - 33,800.00
0.260 Oh Tukang kayu 85,000.00 22,100.00 - 22,100.00
Analisa Page 36

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.026 Oh Kepala Tukang kayu 90,000.00 2,340.00 - 2,340.00
0.026 Oh Mandor 95,000.00 2,470.00 - 2,470.00
60,710.00 115,290.00 176,000.00
Analisa Page 37

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
14 1 M2 PASANG BEGESTING UNTUK KOLOM
0.040 M3 Kayu klas III ( begisting ) 2,350,000.00 - 94,000.00 94,000.00
0.400 Kg Paku biasa 5 - 10 cm 31,800.00 - 12,720.00 12,720.00
0.350 Lbr Plywood tebal 9 mm 132,000.00 - 46,200.00 46,200.00
2.000 Btg Bambu dia 8 - 10 cm / 6 m 15,200.00 - 30,400.00 30,400.00
0.660 Oh Pekerja 65,000.00 42,900.00 - 42,900.00
0.330 Oh Tukang kayu 85,000.00 28,050.00 - 28,050.00
0.033 Oh Kepala Tukang kayu 90,000.00 2,970.00 - 2,970.00
0.033 Oh Mandor 95,000.00 3,135.00 - 3,135.00
77,055.00 183,320.00 260,375.00
15 1 M2 PASANG BEGESTING UNTUK BALOK
0.040 M3 Kayu klas III ( begisting ) 2,350,000.00 - 94,000.00 94,000.00
0.400 Kg Paku biasa 5 - 10 cm 31,800.00 - 12,720.00 12,720.00
0.350 Lbr Plywood tebal 9 mm 132,000.00 - 46,200.00 46,200.00
2.000 Btg Bambu dia 8 - 10 cm / 6 m 15,200.00 - 30,400.00 30,400.00
0.660 Oh Pekerja 65,000.00 42,900.00 - 42,900.00
0.330 Oh Tukang kayu 85,000.00 28,050.00 - 28,050.00
0.033 Oh Kepala Tukang kayu 90,000.00 2,970.00 - 2,970.00
0.033 Oh Mandor 95,000.00 3,135.00 - 3,135.00
77,055.00 183,320.00 260,375.00
16 1 M2 PASANG BEGESTING UNTUK LANTAI
0.040 M3 Kayu klas III ( begisting ) 2,350,000.00 - 94,000.00 94,000.00
0.400 Kg Paku biasa 5 - 10 cm 31,800.00 - 12,720.00 12,720.00
0.350 Lbr Plywood tebal 9 mm 132,000.00 - 46,200.00 46,200.00
6.000 Btg Bambu dia 8 - 10 cm / 6 m 15,200.00 - 91,200.00 91,200.00
0.660 Oh Pekerja 65,000.00 42,900.00 - 42,900.00
0.330 Oh Tukang kayu 85,000.00 28,050.00 - 28,050.00
0.033 Oh Kepala Tukang kayu 90,000.00 2,970.00 - 2,970.00
0.033 Oh Mandor 95,000.00 3,135.00 - 3,135.00
77,055.00 244,120.00 321,175.00
17 1 M2 PASANG BEKISTING UNTUK DINDING
0.030 M3 Kayu klas III ( begisting ) 2,350,000.00 - 70,500.00 70,500.00
0.400 Kg Paku biasa 5 - 10 cm 31,800.00 - 12,720.00 12,720.00
0.350 Lbr Plywood tebal 9 mm 132,000.00 - 46,200.00 46,200.00
4.000 Btg Bambu dia 8 - 10 cm / 6 m 15,200.00 - 60,800.00 60,800.00
0.660 Oh Pekerja 65,000.00 - 42,900.00 42,900.00
0.330 Oh Tukang kayu 85,000.00 28,050.00 - 28,050.00
0.033 Oh Kepala Tukang kayu 90,000.00 2,970.00 - 2,970.00
0.033 Oh Mandor 95,000.00 3,135.00 - 3,135.00
34,155.00 233,120.00 267,275.00
18 1 M2 PASANG BEGESTING UNTUK TANGGA
0.030 M3 Kayu klas III ( begisting ) 2,350,000.00 - 70,500.00 70,500.00
0.400 Kg Paku biasa 5 - 10 cm 31,800.00 - 12,720.00 12,720.00
0.350 Lbr Plywood tebal 9 mm 132,000.00 - 46,200.00 46,200.00
2.000 Btg Bambu dia 8 - 10 cm / 6 m 15,200.00 - 30,400.00 30,400.00
0.660 Oh Pekerja 65,000.00 42,900.00 - 42,900.00
0.330 Oh Tukang kayu 85,000.00 28,050.00 - 28,050.00
0.033 Oh Kepala Tukang kayu 90,000.00 2,970.00 - 2,970.00
0.033 Oh Mandor 95,000.00 3,135.00 - 3,135.00
77,055.00 159,820.00 236,875.00
Analisa Page 38

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
19 1 M2 PASANG JEMBATAN COR BETON
0.026 Kg Kayu klas III ( begisting ) 2,350,000.00 - 62,040.00 62,040.00
0.600 M3 Paku biasa 5 - 10 cm 31,800.00 - 19,080.00 19,080.00
0.500 M3 Bambu dia 6-8 cm/6 m 15,200.00 - 7,600.00 7,600.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.050 Oh Tukang kayu 85,000.00 4,250.00 - 4,250.00
0.005 Oh Kepala tukang kayu 90,000.00 450.00 - 450.00
0.008 Oh Mandor 95,000.00 760.00 - 760.00
15,210.00 88,720.00 103,930.00
20 1 M3 MEMBUATPONDASI BETON BERTULANG (60 KG BESI + BEKESTING)
0.200 M3 Kayu klas III ( begisting ) 2,350,000.00 - 470,000.00 470,000.00
1.500 Kg Paku biasa 5 - 10 cm 31,800.00 - 47,700.00 47,700.00
67.500 Kg Besi beton polos 12,500.00 - 843,750.00 843,750.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.262 Oh Kepala Tukang 90,000.00 23,580.00 - 23,580.00
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,380.00 2,249,900.00 2,866,280.00
21 1 M3 MEMBUATPONDASI BETON BERTULANG (80 KG BESI + BEKESTING)
0.200 M3 Kayu klas III ( begisting ) 2,350,000.00 - 470,000.00 470,000.00
1.500 Kg Paku biasa 5 - 10 cm 31,800.00 - 47,700.00 47,700.00
87.500 Kg Besi beton polos 12,500.00 - 1,093,750.00 1,093,750.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.262 Oh Kepala Tukang 90,000.00 23,580.00 - 23,580.00
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,380.00 2,499,900.00 3,116,280.00
22 1 M3 MEMBUATPONDASI BETON BERTULANG (100 KG BESI + BEKESTING)
0.200 M3 Kayu klas III ( begisting ) 2,350,000.00 - 470,000.00 470,000.00
1.500 Kg Paku biasa 5 - 10 cm 31,800.00 - 47,700.00 47,700.00
107.500 Kg Besi beton polos U 24 12,500.00 - 1,343,750.00 1,343,750.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.262 Oh Kepala Tukang 90,000.00 23,580.00 - 23,580.00
Analisa Page 39

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,380.00 2,749,900.00 3,366,280.00
Analisa Page 40

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
23 1 M3 MEMBUATPONDASI BETON BERTULANG (125 KG BESI + BEKESTING)
0.200 M3 Kayu klas III ( begisting ) 2,350,000.00 - 470,000.00 470,000.00
1.500 Kg Paku biasa 5 - 10 cm 31,800.00 - 47,700.00 47,700.00
129.500 Kg Besi beton ulir U 32 14,918.00 - 1,931,881.00 1,931,881.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.262 Oh Kepala Tukang 90,000.00 23,580.00 - 23,580.00
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,380.00 3,338,031.00 3,954,411.00
24 1 M3 MEMBUAT PONDASI BETON BERTULANG (150 KG BESI + BEKESTING)
0.200 M3 Kayu klas III ( begisting ) 2,350,000.00 - 470,000.00 470,000.00
1.500 Kg Paku biasa 5 - 10 cm 31,800.00 - 47,700.00 47,700.00
157.500 Kg Besi beton ulir U 32 14,918.00 - 2,349,585.00 2,349,585.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.262 Oh Kepala Tukang 90,000.00 23,580.00 - 23,580.00
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,380.00 3,755,735.00 4,372,115.00
25 1 M3 MEMBUAT PONDASI BETON BERTULANG (175 KG BESI + BEKESTING)
0.200 M3 Kayu klas III ( begisting ) 2,350,000.00 - 470,000.00 470,000.00
1.500 Kg Paku biasa 5 - 10 cm 31,800.00 - 47,700.00 47,700.00
182.500 Kg Besi beton ulir U 32 14,918.00 - 2,722,535.00 2,722,535.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.262 Oh Kepala Tukang 90,000.00 23,580.00 - 23,580.00
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,380.00 4,128,685.00 4,745,065.00
Analisa Page 41

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
26 1 M3 MEMBUAT PONDASI BETON BERTULANG (200 KG BESI + BEKESTING)
0.200 M3 Kayu klas III ( begisting ) 2,350,000.00 - 470,000.00 470,000.00
1.500 Kg Paku biasa 5 - 10 cm 31,800.00 - 47,700.00 47,700.00
207.500 Kg Besi beton ulir U 32 14,918.00 - 3,095,485.00 3,095,485.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.262 Oh Kepala Tukang 90,000.00 23,580.00 - 23,580.00
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,380.00 4,501,635.00 5,118,015.00
27 1 M3 MEMBUAT SLOOF BETON BERTULANG (60 KG BESI + BEKESTING)
0.270 M3 Kayu klas III ( begisting ) 2,350,000.00 - 634,500.00 634,500.00
2.000 Kg Paku biasa 5 - 10 cm 31,800.00 - 63,600.00 63,600.00
63.000 Kg Besi beton polos U 24 12,500.00 - 787,500.00 787,500.00
3.000 Kg Kawat beton 22,600.00 - 67,800.00 67,800.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.650 Oh Pekerja 65,000.00 367,250.00 - 367,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.560 Oh Tukang kayu 85,000.00 132,600.00 - 132,600.00
1.400 Oh Tukang besi 85,000.00 119,000.00 - 119,000.00
0.323 Oh Kepala Tukang 90,000.00 29,070.00 - 29,070.00
0.283 Oh Mandor 95,000.00 26,885.00 - 26,885.00
698,180.00 2,391,000.00 3,089,180.00
28 1 M3 MEMBUAT SLOOF BETON BERTULANG (80 KG BESI + BEKESTING)
0.270 M3 Kayu klas III ( begisting ) 2,350,000.00 - 634,500.00 634,500.00
2.000 Kg Paku biasa 5 - 10 cm 31,800.00 - 63,600.00 63,600.00
84.000 Kg Besi beton polos U 24 12,500.00 - 1,050,000.00 1,050,000.00
3.000 Kg Kawat beton 22,600.00 - 67,800.00 67,800.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.650 Oh Pekerja 65,000.00 367,250.00 - 367,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.560 Oh Tukang kayu 85,000.00 132,600.00 - 132,600.00
1.400 Oh Tukang besi 85,000.00 119,000.00 - 119,000.00
0.323 Oh Kepala Tukang 90,000.00 29,070.00 - 29,070.00
0.283 Oh Mandor 95,000.00 26,885.00 - 26,885.00
698,180.00 2,653,500.00 3,351,680.00
Analisa Page 42

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
29 1 M3 MEMBUAT SLOOF BETON BERTULANG (90 KG BESI + BEKESTING)
0.270 M3 Kayu klas III ( begisting ) 2,350,000.00 - 634,500.00 634,500.00
2.000 Kg Paku biasa 5 - 10 cm 31,800.00 - 63,600.00 63,600.00
94.500 Kg Besi beton polos U 24 12,500.00 - 1,181,250.00 1,181,250.00
3.000 Kg Kawat beton 22,600.00 - 67,800.00 67,800.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.650 Oh Pekerja 65,000.00 367,250.00 - 367,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.560 Oh Tukang kayu 85,000.00 132,600.00 - 132,600.00
1.400 Oh Tukang besi 85,000.00 119,000.00 - 119,000.00
0.323 Oh Kepala Tukang 90,000.00 29,070.00 - 29,070.00
0.283 Oh Mandor 95,000.00 26,885.00 - 26,885.00
698,180.00 2,784,750.00 3,482,930.00
30 1 M3 MEMBUAT SLOOF BETON BERTULANG (100 KG BESI + BEKESTING)
0.270 M3 Kayu klas III ( begisting ) 2,350,000.00 - 634,500.00 634,500.00
2.000 Kg Paku biasa 5 - 10 cm 31,800.00 - 63,600.00 63,600.00
105.000 Kg Besi beton polos U 24 12,500.00 - 1,312,500.00 1,312,500.00
3.000 Kg Kawat beton 22,600.00 - 67,800.00 67,800.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.650 Oh Pekerja 65,000.00 367,250.00 - 367,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.560 Oh Tukang kayu 85,000.00 132,600.00 - 132,600.00
1.400 Oh Tukang besi 85,000.00 119,000.00 - 119,000.00
0.323 Oh Kepala Tukang 90,000.00 29,070.00 - 29,070.00
0.283 Oh Mandor 95,000.00 26,885.00 - 26,885.00
698,180.00 2,916,000.00 3,614,180.00
31 1 M3 MEMBUAT SLOOF BETON BERTULANG (125 KG BESI + BEKESTING)
0.270 M3 Kayu klas III ( begisting ) 2,350,000.00 - 634,500.00 634,500.00
2.000 Kg Paku biasa 5 - 10 cm 31,800.00 - 63,600.00 63,600.00
131.250 Kg Besi beton polos U 24 12,500.00 - 1,640,625.00 1,640,625.00
3.000 Kg Kawat beton 22,600.00 - 67,800.00 67,800.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.650 Oh Pekerja 65,000.00 367,250.00 - 367,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.560 Oh Tukang kayu 85,000.00 132,600.00 - 132,600.00
1.400 Oh Tukang besi 85,000.00 119,000.00 - 119,000.00
0.323 Oh Kepala Tukang 90,000.00 29,070.00 - 29,070.00
0.283 Oh Mandor 95,000.00 26,885.00 - 26,885.00
698,180.00 3,244,125.00 3,942,305.00
Analisa Page 43

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
32 1 M3 MEMBUAT SLOOF BETON BERTULANG (150 KG BESI + BEKESTING)
0.270 M3 Kayu klas III ( begisting ) 2,350,000.00 - 634,500.00 634,500.00
2.000 Kg Paku biasa 5 - 10 cm 31,800.00 - 63,600.00 63,600.00
157.500 Kg Besi beton ulir U 32 14,918.00 - 2,349,585.00 2,349,585.00
3.000 Kg Kawat beton 22,600.00 - 67,800.00 67,800.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.650 Oh Pekerja 65,000.00 367,250.00 - 367,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.560 Oh Tukang kayu 85,000.00 132,600.00 - 132,600.00
1.400 Oh Tukang besi 85,000.00 119,000.00 - 119,000.00
0.323 Oh Kepala Tukang 90,000.00 29,070.00 - 29,070.00
0.283 Oh Mandor 95,000.00 26,885.00 - 26,885.00
698,180.00 3,953,085.00 4,651,265.00
33 1 M3 MEMBUAT SLOOF BETON BERTULANG (200 KG BESI + BEKESTING)
0.270 M3 Kayu klas III ( begisting ) 2,350,000.00 - 634,500.00 634,500.00
2.000 Kg Paku biasa 5 - 10 cm 31,800.00 - 63,600.00 63,600.00
210.000 Kg Besi beton ulir U 32 14,918.00 - 3,132,780.00 3,132,780.00
3.000 Kg Kawat beton 22,600.00 - 67,800.00 67,800.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
5.650 Oh Pekerja 65,000.00 367,250.00 - 367,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.560 Oh Tukang kayu 85,000.00 132,600.00 - 132,600.00
1.400 Oh Tukang besi 85,000.00 119,000.00 - 119,000.00
0.323 Oh Kepala Tukang 90,000.00 29,070.00 - 29,070.00
0.283 Oh Mandor 95,000.00 26,885.00 - 26,885.00
698,180.00 4,736,280.00 5,434,460.00
34 1 M3 MEMBUAT KOLOM BETON BERTULANG (80 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2 - 5 cm 31,800.00 - 127,200.00 127,200.00
84.000 Kg Besi beton polos U 24 12,500.00 - 1,050,000.00 1,050,000.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
10.000 Bt Bambu 15,200.00 - 152,000.00 152,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 3,670,500.00 4,540,680.00
Analisa Page 44

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
35 1 M3 MEMBUAT KOLOM BETON BERTULANG (90 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2 - 5 cm 31,800.00 - 127,200.00 127,200.00
94.500 Kg Besi beton polos U 24 12,500.00 - 1,181,250.00 1,181,250.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
10.000 Bt Bambu 15,200.00 - 152,000.00 152,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 3,801,750.00 4,671,930.00
36 1 M3 MEMBUAT KOLOM BETON BERTULANG (100 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
105.000 Kg Besi Beton Polos 12,500.00 - 1,312,500.00 1,312,500.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
10.000 Bt Bambu 15,200.00 - 152,000.00 152,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 3,933,000.00 4,803,180.00
37 1 M3 MEMBUAT KOLOM BETON BERTULANG (125 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
131.250 Kg Besi beton ulir U 32 14,918.00 - 1,957,987.50 1,957,987.50
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
10.000 Bt Bambu 15,200.00 - 152,000.00 152,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 4,578,487.50 5,448,667.50
Analisa Page 45

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
38 1 M3 MEMBUAT KOLOM BETON BERTULANG (150 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
157.500 Kg Besi beton ulir U 32 14,918.00 - 2,349,585.00 2,349,585.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
10.000 Bt Bambu 15,200.00 - 152,000.00 152,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 4,970,085.00 5,840,265.00
39 1 M3 MEMBUAT KOLOM BETON BERTULANG (175 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
189.000 Kg Besi beton ulir U 32 14,918.00 - 2,819,502.00 2,819,502.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
10.000 Bt Bambu 15,200.00 - 152,000.00 152,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 5,440,002.00 6,310,182.00
40 1 M3 MEMBUAT KOLOM BETON BERTULANG (200 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
210.000 Kg Besi beton ulir U 32 14,918.00 - 3,132,780.00 3,132,780.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
10.000 Bt Bambu 15,200.00 - 152,000.00 152,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 5,753,280.00 6,623,460.00
Analisa Page 46

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
41 1 M3 MEMBUAT KOLOM BETON BERTULANG (250 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
262.500 Kg Besi beton ulir U 32 14,918.00 - 3,915,975.00 3,915,975.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
10.000 Bt Bambu 15,200.00 - 152,000.00 152,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 6,536,475.00 7,406,655.00
42 1 M3 MEMBUAT KOLOM BETON BERTULANG (300 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
315.000 Kg Besi beton ulir U 32 14,918.00 - 4,699,170.00 4,699,170.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
20.000 Bt Bambu 15,200.00 - 304,000.00 304,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 7,471,670.00 8,341,850.00
43 1 M3 MEMBUAT BALOK BETON BERTULANG (100 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
105.000 Kg Besi Beton Polos 14,918.00 - 1,566,390.00 1,566,390.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
20.000 Bt Bambu 15,200.00 - 304,000.00 304,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 4,338,890.00 5,209,070.00
Analisa Page 47

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
44 1 M3 MEMBUAT BALOK BETON BERTULANG (125 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
131.250 Kg Besi Beton Polos 14,918.00 - 1,957,987.50 1,957,987.50
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
20.000 Bt Bambu 15,200.00 - 304,000.00 304,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 4,730,487.50 5,600,667.50
45 1 M3 MEMBUAT BALOK BETON BERTULANG (150 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
157.500 Kg Besi beton ulir U 32 14,918.00 - 2,349,585.00 2,349,585.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
20.000 Bt Bambu 15,200.00 - 304,000.00 304,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 5,122,085.00 5,992,265.00
46 1 M3 MEMBUAT BALOK BETON BERTULANG (175 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
183.750 Kg Besi beton ulir U 32 14,918.00 - 2,741,182.50 2,741,182.50
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
20.000 Bt Bambu 15,200.00 - 304,000.00 304,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 5,513,682.50 6,383,862.50
Analisa Page 48

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
47 1 M3 MEMBUAT BALOK BETON BERTULANG (200 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
210.000 Kg Besi beton ulir U 32 14,918.00 - 3,132,780.00 3,132,780.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
20.000 Bt Bambu 15,200.00 - 304,000.00 304,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 5,905,280.00 6,775,460.00
48 1 M3 MEMBUAT BALOK BETON BERTULANG (250 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
262.500 Kg Besi beton ulir U 32 14,918.00 - 3,915,975.00 3,915,975.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
20.000 Bt Bambu 15,200.00 - 304,000.00 304,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 6,688,475.00 7,558,655.00
49 1 M3 MEMBUAT BALOK BETON BERTULANG (300 KG BESI + BEKESTING)
0.400 M3 Kayu klas III ( begisting ) 2,350,000.00 - 940,000.00 940,000.00
4.000 Kg Paku biasa 2' - 5' 31,800.00 - 127,200.00 127,200.00
315.000 Kg Besi beton ulir U 32 14,918.00 - 4,699,170.00 4,699,170.00
4.500 Kg Kawat beton 22,600.00 - 101,700.00 101,700.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
3.500 Lbr Plywood tebal 9 MM 132,000.00 - 462,000.00 462,000.00
20.000 Bt Bambu 15,200.00 - 304,000.00 304,000.00
7.050 Oh Pekerja 65,000.00 458,250.00 - 458,250.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.650 Oh Tukang kayu 85,000.00 140,250.00 - 140,250.00
2.100 Oh Tukang besi 85,000.00 178,500.00 - 178,500.00
0.403 Oh Kepala tukang 90,000.00 36,270.00 - 36,270.00
0.353 Oh Mandor 95,000.00 33,535.00 - 33,535.00
870,180.00 7,471,670.00 8,341,850.00
Analisa Page 49

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
50 1 M3 MEMBUAT PLAT BETON BERTULANG (60 KG BESI + BEKESTING)
0.320 M3 Kayu klas III ( begisting ) 2,350,000.00 - 752,000.00 752,000.00
3.200 Kg Paku biasa 2' - 5' 31,800.00 - 101,760.00 101,760.00
63.000 Kg Besi beton polos U 24 12,500.00 - 787,500.00 787,500.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
2.800 Lbr Plywood tebal 9 MM 132,000.00 - 369,600.00 369,600.00
32.000 Btg Bambu dia 6-8 Cm /6 m 15,200.00 - 486,400.00 486,400.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.265 Oh Kepala tukang 90,000.00 23,850.00 - 23,850.00
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,650.00 3,385,710.00 4,002,360.00
51 1 M3 MEMBUAT PLAT BETON BERTULANG (85 KG BESI + BEKESTING)
0.320 M3 Kayu klas III ( begisting ) 2,350,000.00 - 752,000.00 752,000.00
3.200 Kg Paku biasa 2' - 5' 31,800.00 - 101,760.00 101,760.00
93.500 Kg Besi beton polos U 24 12,500.00 - 1,168,750.00 1,168,750.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
2.800 Lbr Plywood tebal 9 MM 132,000.00 - 369,600.00 369,600.00
32.000 Btg Bambu dia 6-8 Cm /6 m 15,200.00 - 486,400.00 486,400.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.265 Oh Kepala tukang 90,000.00 23,850.00 - 23,850.00
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,650.00 3,766,960.00 4,383,610.00
52 1 M3 MEMBUAT PLAT BETON BERTULANG (100 KG BESI + BEKESTING)
0.320 M3 Kayu klas III ( begisting ) 2,350,000.00 - 752,000.00 752,000.00
3.200 Kg Paku biasa 2' - 5' 31,800.00 - 101,760.00 101,760.00
105.000 Kg Besi beton polos U 24 12,500.00 - 1,312,500.00 1,312,500.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
2.800 Lbr Plywood tebal 9 MM 132,000.00 - 369,600.00 369,600.00
32.000 Btg Bambu dia 6-8 Cm /6 m 15,200.00 - 486,400.00 486,400.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.265 Oh Kepala tukang 90,000.00 23,850.00 - 23,850.00
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,650.00 3,910,710.00 4,527,360.00
Analisa Page 50

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
53 1 M3 MEMBUAT PLAT BETON BERTULANG (125 KG BESI + BEKESTING)
0.320 M3 Kayu klas III ( begisting ) 2,350,000.00 - 752,000.00 752,000.00
3.200 Kg Paku biasa 2' - 5' 31,800.00 - 101,760.00 101,760.00
131.250 Kg Besi beton polos U 24 12,500.00 - 1,640,625.00 1,640,625.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
2.800 Lbr Plywood tebal 9 MM 132,000.00 - 369,600.00 369,600.00
32.000 Btg Bambu dia 6-8 Cm /6 m 15,200.00 - 486,400.00 486,400.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.265 Oh Kepala tukang 90,000.00 23,850.00 - 23,850.00
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,650.00 4,238,835.00 4,855,485.00
54 1 M3 MEMBUAT PLAT BETON BERTULANG (150 KG BESI + BEKESTING)
0.320 M3 Kayu klas III ( begisting ) 2,350,000.00 - 752,000.00 752,000.00
3.200 Kg Paku biasa 2' - 5' 31,800.00 - 101,760.00 101,760.00
157.500 Kg Besi beton polos U 24 12,500.00 - 1,968,750.00 1,968,750.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
2.800 Lbr Plywood tebal 9 MM 132,000.00 - 369,600.00 369,600.00
32.000 Btg Bambu dia 6-8 Cm /6 m 15,200.00 - 486,400.00 486,400.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.265 Oh Kepala tukang 90,000.00 23,850.00 - 23,850.00
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,650.00 4,566,960.00 5,183,610.00
55 1 M3 MEMBUAT DINDING BETON BERTULANG (150 KG BESI + BEKESTING)
0.240 M3 Kayu klas III ( begisting ) 2,350,000.00 - 564,000.00 564,000.00
0.320 Kg Paku biasa 2' - 5' 31,800.00 - 10,176.00 10,176.00
262.500 Kg Besi beton polos U 24 12,500.00 - 3,281,250.00 3,281,250.00
2.250 Kg Kawat beton 22,600.00 - 50,850.00 50,850.00
336.000 Kg Semen porland 1,400.00 - 470,400.00 470,400.00
0.540 M3 Pasir beton ex karangasem 230,000.00 - 124,200.00 124,200.00
0.810 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 243,000.00 243,000.00
2.800 Lbr Plywood tebal 9 MM 132,000.00 - 369,600.00 369,600.00
24.000 Btg Bambu dia 6-8 Cm /6 m 15,200.00 - 364,800.00 364,800.00
5.300 Oh Pekerja 65,000.00 344,500.00 - 344,500.00
0.275 Oh Tukang batu 85,000.00 23,375.00 - 23,375.00
1.300 Oh Tukang kayu 85,000.00 110,500.00 - 110,500.00
1.050 Oh Tukang besi 85,000.00 89,250.00 - 89,250.00
0.265 Oh Kepala tukang 90,000.00 23,850.00 - 23,850.00
0.265 Oh Mandor 95,000.00 25,175.00 - 25,175.00
616,650.00 5,478,276.00 6,094,926.00
Analisa Page 51

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
56 1 M' MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11) CM
0.002 M3 Kayu klas III ( begisting ) 2,350,000.00 - 4,700.00 4,700.00
0.010 Kg Paku biasa 2' - 5' 31,800.00 - 318.00 318.00
3.000 Kg Besi beton polos 12,500.00 - 37,500.00 37,500.00
0.450 Kg Kawat beton 22,600.00 - 10,170.00 10,170.00
4.000 Kg Semen porland 1,400.00 - 5,600.00 5,600.00
0.006 M3 Pasir beton ex karangasem 230,000.00 - 1,380.00 1,380.00
0.009 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 2,700.00 2,700.00
0.180 Oh Pekerja 65,000.00 11,700.00 - 11,700.00
0.020 Oh Tukang batu 85,000.00 1,700.00 - 1,700.00
0.020 Oh Tukang kayu 85,000.00 1,700.00 - 1,700.00
0.020 Oh Tukang besi 85,000.00 1,700.00 - 1,700.00
0.006 Oh Kepala tukang 90,000.00 540.00 - 540.00
0.009 Oh Mandor 95,000.00 855.00 - 855.00
18,195.00 62,368.00 80,563.00
57 1 M' MEMBUAT RING BALOK BETON BERTULANG (10 X 15) CM
0.003 M3 Kayu klas III ( begisting ) 2,350,000.00 - 7,050.00 7,050.00
0.020 Kg Paku biasa 2' - 5' 31,800.00 - 636.00 636.00
3.600 Kg Besi beton polos 12,500.00 - 45,000.00 45,000.00
0.050 Kg Kawat beton 22,600.00 - 1,130.00 1,130.00
5.500 Kg Semen porland 1,400.00 - 7,700.00 7,700.00
0.009 M3 Pasir beton ex karangasem 230,000.00 - 2,070.00 2,070.00
0.015 M3 Batu pecah 1 - 2 ( mesin ) 300,000.00 - 4,500.00 4,500.00
0.297 Oh Pekerja 65,000.00 19,305.00 - 19,305.00
0.033 Oh Tukang batu 85,000.00 2,805.00 - 2,805.00
0.033 Oh Tukang kayu 85,000.00 2,805.00 - 2,805.00
0.033 Oh Tukang besi 85,000.00 2,805.00 - 2,805.00
0.010 Oh Kepala tukang 90,000.00 900.00 - 900.00
0.015 Oh Mandor 95,000.00 1,425.00 - 1,425.00
30,045.00 68,086.00 98,131.00
VIII PEKERJAAN PENUTUP ATAP
1 1 M2 PASANG ATAP GENTENG PLENTONG BESAR
25.000 Bh Genteng plentong besar jd jaya 3,000.00 - 75,000.00 75,000.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.060 Oh Tukang kayu 85,000.00 5,100.00 - 5,100.00
0.006 Oh Kepala tukang kayu 90,000.00 540.00 - 540.00
0.008 Oh Mandor 95,000.00 760.00 - 760.00
16,150.00 75,000.00 91,150.00
2 1 M2 PASANG BUBUNGAN PLENTONG BESAR
5.000 Bh Bubungan plentong besar jd jaya 8,100.00 - 40,500.00 40,500.00
8.000 Kg Semen porland 1,400.00 - 11,200.00 11,200.00
0.032 M3 Pasir pasang ex karangasem 235,000.00 - 7,520.00 7,520.00
0.400 Oh Pekerja 65,000.00 26,000.00 - 26,000.00
0.200 Oh Tukang kayu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang kayu 90,000.00 1,800.00 - 1,800.00
0.002 Oh Mandor 95,000.00 190.00 - 190.00
44,990.00 59,220.00 104,210.00
3 1 M2 PASANG ATAP GENTENG PLENTONG KECIL
28.000 Bh Genteng plentong kecil 1,800.00 - 50,400.00 50,400.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.060 Oh Tukang kayu 85,000.00 5,100.00 - 5,100.00
0.006 Oh Kepala tukang kayu 90,000.00 540.00 - 540.00
Analisa Page 52

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.008 Oh Mandor 95,000.00 760.00 - 760.00
16,150.00 50,400.00 66,550.00
Analisa Page 53

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
4 1 M2 PASANG BUBUNGAN PLENTONG MINI
5.000 Bh Bubungan plentong mini 2,200.00 - 11,000.00 11,000.00
8.000 Kg Semen porland 1,400.00 - 11,200.00 11,200.00
0.032 M3 Pasir pasang ex karangasem 235,000.00 - 7,520.00 7,520.00
0.400 Oh Pekerja 65,000.00 26,000.00 - 26,000.00
0.200 Oh Tukang kayu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang kayu 90,000.00 1,800.00 - 1,800.00
0.002 Oh Mandor 95,000.00 190.00 - 190.00
44,990.00 29,720.00 74,710.00
5 1 M2 PASANG ATAP GENTENG KODOK
25.000 Bh Genteng kodok 3,725.00 - 93,125.00 93,125.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.060 Oh Tukang kayu 85,000.00 5,100.00 - 5,100.00
0.006 Oh Kepala tukang kayu 90,000.00 540.00 - 540.00
0.008 Oh Mandor 95,000.00 760.00 - 760.00
16,150.00 93,125.00 109,275.00
6 1 M2 PASANG BUBUNGAN PLENTONG KODOK
5.000 Bh Bubungan kodok 9,000.00 - 45,000.00 45,000.00
8.000 Kg Semen porland 1,400.00 - 11,200.00 11,200.00
0.032 M3 Pasir pasang ex karangasem 235,000.00 - 7,520.00 7,520.00
0.400 Oh Pekerja 65,000.00 26,000.00 - 26,000.00
0.200 Oh Tukang kayu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang kayu 90,000.00 1,800.00 - 1,800.00
0.002 Oh Mandor 95,000.00 190.00 - 190.00
44,990.00 63,720.00 108,710.00
7 1 M2 PASANG ATAP ASBES GELOMBANG 1,80 X 0,92 X 5 MM
0.750 Lbr Asbes gelombang 36,000.00 - 27,000.00 27,000.00
0.120 Kg Paku asbes 31,800.00 - 3,816.00 3,816.00
0.140 Oh Pekerja 65,000.00 9,100.00 - 9,100.00
0.070 Oh Tukang kayu 85,000.00 5,950.00 - 5,950.00
0.007 Oh Kepala tukang kayu 90,000.00 630.00 - 630.00
0.007 Oh Mandor 95,000.00 665.00 - 665.00
16,345.00 30,816.00 47,161.00
8 1 M' PASANG BUBUNGAN ASBES GELOMBANG 0,92 mm
0.240 Lbr Bubungan asbes gelombang 32,300.00 - 7,752.00 7,752.00
0.120 Kg Paku skrup 3,5" 31,800.00 - 3,816.00 3,816.00
0.084 Oh Pekerja 65,000.00 5,460.00 - 5,460.00
0.125 Oh Tukang kayu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala tukang kayu 90,000.00 1,170.00 - 1,170.00
0.004 Oh Mandor 95,000.00 380.00 - 380.00
17,635.00 11,568.00 29,203.00
9 1 M2 PASANG ATAP SIRAP
60.000 Bh Genteng sirap 1,250.00 75,000.00 75,000.00
0.200 Kg Paku biasa 1/2" - 1" 31,800.00 - 6,360.00 6,360.00
0.166 Oh Pekerja 65,000.00 10,790.00 - 10,790.00
0.250 Oh Tukang kayu 85,000.00 21,250.00 - 21,250.00
0.025 Oh Kepala tukang kayu 90,000.00 2,250.00 - 2,250.00
0.008 Oh Mandor 95,000.00 760.00 - 760.00
35,050.00 6,360.00 116,410.00
Analisa Page 54

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
10 1 M' PASANG NOK ATAP SIRAP
0.400 Lbr seng plat 3" x 6" BJLS 28 58,700.00 - 23,480.00 23,480.00
0.060 Kg Paku biasa 1/2" - 1" 31,800.00 - 1,908.00 1,908.00
0.050 Kg Paku biasa 2" - 5" 31,800.00 - 1,590.00 1,590.00
0.004 M3 Kayu papan 3 Cm kamper 9,000,000.00 - 36,000.00 36,000.00
0.125 Oh Pekerja 65,000.00 8,125.00 - 8,125.00
0.250 Oh Tukang kayu 85,000.00 21,250.00 - 21,250.00
0.025 Oh Kepala tukang kayu 90,000.00 2,250.00 - 2,250.00
0.008 Oh Mandor 95,000.00 760.00 - 760.00
32,385.00 62,978.00 95,363.00
11 1 M2 PASANG ATAP GENTENG BETON
11.000 Bh Genteng beton 3,000.00 33,000.00 33,000.00
0.030 Kg Paku biasa 1/2" - 1" 31,800.00 - 954.00 954.00
0.200 Oh Pekerja 65,000.00 13,000.00 - 13,000.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.010 Oh Mandor 95,000.00 950.00 - 950.00
23,350.00 33,954.00 57,304.00
12 1 M' PASANG BUBUNGAN GENTENG BETON
3.500 Bh Nok genteng beton 9,000.00
0.050 Kg Paku biasa 2"- 5" 31,800.00 - 1,590.00 1,590.00
10.800 Kg Semen portland 1,400.00 - 15,120.00 15,120.00
0.032 M3 Pasir pasang ex karangasem 235,000.00 - 7,520.00 7,520.00
0.400 Oh Pekerja 65,000.00 26,000.00 - 26,000.00
0.200 Oh Tukang kayu 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang kayu 90,000.00 1,800.00 - 1,800.00
0.020 Oh Mandor 95,000.00 1,900.00 - 1,900.00
46,700.00 24,230.00 70,930.00
13 1 M2 PASANG GENTENG METAL ( BERPASIR EKS. MULTIROOF)
1.020 Lbr Genteng metal ( Ek. Multi Roof ) 100,000.00 - 102,000.00 102,000.00
0.200 Kg Paku biasa 1/2" - 1" 31,800.00 - 6,360.00 6,360.00
0.200 Oh Pekerja 65,000.00 13,000.00 - 13,000.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.001 Oh Mandor 95,000.00 95.00 - 95.00
22,495.00 108,360.00 130,855.00
14 1 M2 PASANG GENTENG METAL POLOS MULTI COLOUR
1.020 Lbr Genteng metal ( Ek. Multi Colour ) 84,500.00 - 86,190.00 86,190.00
0.200 Kg Paku biasa 1/2" - 1" 31,800.00 - 6,360.00 6,360.00
0.200 Oh Pekerja 65,000.00 13,000.00 - 13,000.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.001 Oh Mandor 95,000.00 95.00 - 95.00
22,495.00 92,550.00 115,045.00
15 1 M2 PASANG GENTENG METAL ( BERPASIR EKS. SAKURA ROOF )
1.020 Lbr Genteng metal ( Ek. Sakura Roof ) 67,000.00 - 68,340.00 68,340.00
0.200 Kg Paku biasa 1/2" - 1" 31,800.00 - 6,360.00 6,360.00
0.200 Oh Pekerja 65,000.00 13,000.00 - 13,000.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.001 Oh Mandor 95,000.00 95.00 - 95.00
22,495.00 74,700.00 97,195.00
Analisa Page 55

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
16 1 M2 PASANG GENTENG METAL POLOS SAKURA COLOUR
1.020 Lbr Genteng metal ( Ek. Sakura Colour ) 52,000.00 - 53,040.00 53,040.00
0.200 Kg Paku biasa 1/2" - 1" 31,800.00 - 6,360.00 6,360.00
0.200 Oh Pekerja 65,000.00 13,000.00 - 13,000.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.001 Oh Mandor 95,000.00 95.00 - 95.00
22,495.00 59,400.00 81,895.00
17 1 M2 PASANG ATAP ZINKALUM
1.050 M2 Atap zinkalum glbng tebal 0,3 95,000.00 99,750.00 99,750.00
0.020 Kg Paku hak panjang 33,900.00 678.00 678.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.750 Oh Tukang kayu 85,000.00 63,750.00 - 63,750.00
0.008 Oh Kepala tukang kayu 90,000.00 720.00 - 720.00
0.006 Oh Mandor 95,000.00 570.00 - 570.00
74,790.00 100,428.00 175,218.00
18 1 M2 PASANG NOK ALUMINIUM
1.200 M2 Nok standar 40 Cm 18, swg 22 85,000.00 102,000.00 102,000.00
0.040 Kg Paku hak panjang 33,900.00 1,356.00 1,356.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
1.000 Oh Tukang kayu 85,000.00 85,000.00 - 85,000.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.010 Oh Mandor 95,000.00 950.00 - 950.00
93,350.00 103,356.00 196,706.00
19 1 M2 PASANG ALUMINIUM FOIL/SISALATION
1.050 M2 Aluminium foil/sisalation 3,500.00 - 3,675.00 3,675.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.050 Oh Tukang kayu 85,000.00 4,250.00 - 4,250.00
0.005 Oh Kepala tukang kayu 90,000.00 450.00 - 450.00
0.008 Oh Mandor 95,000.00 760.00 - 760.00
15,210.00 3,675.00 18,885.00
20 1 M2 PASANG ATAP ALANG-ALANG 3 M'
6.500 Lbr Alang-alang 22,500.00 146,250.00 146,250.00
0.500 Glg Tali pengikat/kawat 22,600.00 11,300.00 11,300.00
0.200 Oh Pekerja (pas. Atap alang-alang) 65,000.00 13,000.00 13,000.00
0.010 Oh Mandor 95,000.00 950.00 950.00
13,950.00 157,550.00 171,500.00
21 1 M2 PASANG ATAP SENG GELOMBANG
0.700 Lbr Seng glb. 3" x 6" BJLS 28 56,500.00 - 39,550.00 39,550.00
0.020 Kg Paku seng 33,900.00 - 678.00 678.00
0.120 Oh Pekerja 65,000.00 7,800.00 - 7,800.00
0.060 Oh Tukang kayu 85,000.00 5,100.00 - 5,100.00
0.006 Oh Kepala tukang kayu 90,000.00 540.00 - 540.00
0.006 Oh Mandor 95,000.00 570.00 - 570.00
14,010.00 40,228.00 54,238.00
22 1 M2 PASANG NOK SENG GELOMBANG
0.300 Lbr Seng glb. 3" x 6" BJLS 28 56,500.00 - 16,950.00 16,950.00
0.040 Kg Paku seng 33,900.00 - 1,356.00 1,356.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.070 Oh Tukang kayu 85,000.00 5,950.00 - 5,950.00
0.008 Oh Kepala tukang kayu 90,000.00 720.00 - 720.00
0.006 Oh Mandor 95,000.00 570.00 - 570.00
Analisa Page 56

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
16,990.00 18,306.00 35,296.00
Analisa Page 57

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
IX PEKERJAAN LANGIT-LANGIT
1 1 M2 PASANG PENUTUP LANGIT-LANGIT ETERNIT 1 X 1 M / 4 MM
1.100 Lbr Eternit 18,000.00 - 19,800.00 19,800.00
0.010 Kg Paku biasa 1/2" - 1" 31,800.00 - 318.00 318.00
0.030 Oh Pekerja 65,000.00 1,950.00 - 1,950.00
0.070 Oh Tukang kayu 85,000.00 5,950.00 - 5,950.00
0.007 Oh Kepala tukang kayu 90,000.00 630.00 - 630.00
0.002 Oh Mandor 95,000.00 142.50 - 142.50
8,672.50 20,118.00 28,790.50
2 1 M2 PASANG PENUTUP LANGIT-LANGIT KALSIBOARD 4 MM
0.347 Lbr Kalsiboard 1,2X1,8 81,000.00 - 28,107.00 28,107.00
0.010 Kg Paku biasa 1/2" - 1" 31,800.00 - 318.00 318.00
0.030 Oh Pekerja 65,000.00 1,950.00 - 1,950.00
0.070 Oh Tukang kayu 85,000.00 5,950.00 - 5,950.00
0.007 Oh Kepala tukang kayu 90,000.00 630.00 - 630.00
0.002 Oh Mandor 95,000.00 142.50 - 142.50
8,672.50 28,425.00 37,097.50
3 1 M2 PASANG PENUTUP LANGIT-LANGIT PLYWOOD 30 X 60 CM / 4 MM
0.360 Lbr Plywood 3 mm 68,000.00 - 24,480.00 24,480.00
0.030 Kg Paku biasa 1/2" - 1" 31,800.00 - 954.00 954.00
0.070 Oh Pekerja 65,000.00 4,550.00 - 4,550.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.004 Oh Mandor 95,000.00 332.50 - 332.50
14,282.50 25,434.00 39,716.50
4 1 M' PASANG PENUTUP LANGIT-LANGIT KAYU PROFIL
0.250 M' List kayu profil kamper 21,400.00 - 5,350.00 5,350.00
0.010 Kg Paku biasa 2" - 5" 31,800.00 - 318.00 318.00
0.050 Oh Pekerja 65,000.00 3,250.00 - 3,250.00
0.050 Oh Tukang kayu 85,000.00 4,250.00 - 4,250.00
0.005 Oh Kepala tukang kayu 90,000.00 450.00 - 450.00
0.003 Oh Mandor 95,000.00 285.00 - 285.00
8,235.00 5,668.00 13,903.00
5 1 M2 PASANG PENUTUP LANGIT-LANGIT PLYWOOD 3 MM + RANGKA BAYUR
0.014 M3 usuk 4/6 cm bayur 5,000,000.00 - 72,000.00 72,000.00
0.010 Kg Paku biasa 2" - 5" 31,800.00 - 318.00 318.00
0.347 Lbr Plywood 3 mm 68,000.00 - 23,596.00 23,596.00
0.270 Oh Pekerja 65,000.00 17,550.00 - 17,550.00
0.400 Oh Tukang kayu 85,000.00 34,000.00 - 34,000.00
0.040 Oh Kepala tukang kayu 90,000.00 3,600.00 - 3,600.00
0.014 Oh Mandor 95,000.00 1,282.50 - 1,282.50
56,432.50 95,914.00 152,346.50
X PEKERJAAN SANITASI
1 MEMASANG 1 BUAH KLOSET DUDUK
1.000 Bh Kloset duduk str. Toto 2,750,000.00 - 2,750,000.00 2,750,000.00
0.600 Set Perlengkapan 1,650,000.00 - 99,000.00 99,000.00
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
1.000 Oh Tukang batu 85,000.00 85,000.00 - 85,000.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
155,650.00 2,849,000.00 3,004,650.00
Analisa Page 58

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN
1.000 Bh Kloset jongkok porselin 240,000.00 - 240,000.00 240,000.00
5.000 Kg Semen porland 1,400.00 - 7,000.00 7,000.00
0.010 M3 Pasir pasang ex karangasem 235,000.00 - 2,350.00 2,350.00
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
1.000 Oh Tukang batu 85,000.00 85,000.00 - 85,000.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
155,650.00 249,350.00 405,000.00
3 MEMASANG 1 BUAH URINOIR KIA
1.000 Bh Urinoir 863,600.00 - 863,600.00 863,600.00
0.300 Set Perlengkapan 259,080.00 - 77,724.00 77,724.00
6.000 M3 Semen porland 1,400.00 - 8,400.00 8,400.00
0.010 M3 Pasir pasang ex karangasem 235,000.00 - 2,350.00 2,350.00
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
1.000 Oh Tukang batu 85,000.00 85,000.00 - 85,000.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
155,650.00 952,074.00 1,107,724.00
4 MEMASANG 1 BUAH WASTAFEL KIA
1.000 Bh Wastafel 565,000.00 - 565,000.00 565,000.00
0.120 Set Perlengkapan 169,500.00 - 20,340.00 20,340.00
5.000 Kg Semen porland 1,400.00 - 7,000.00 7,000.00
0.010 M3 Pasir pasang ex karangasem 235,000.00 - 2,350.00 2,350.00
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
1.000 Oh Tukang batu 85,000.00 85,000.00 - 85,000.00
0.010 Oh Kepala tukang 90,000.00 900.00 - 900.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
155,650.00 594,690.00 750,340.00
5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3
1.000 Bh Bak fibreglass 380,000.00 - 380,000.00 380,000.00
1.800 Oh Pekerja 65,000.00 117,000.00 - 117,000.00
2.700 Oh Tukang batu 85,000.00 229,500.00 - 229,500.00
0.540 Oh Kepala tukan 90,000.00 48,600.00 - 48,600.00
0.110 Oh Mandor 95,000.00 10,450.00 - 10,450.00
405,550.00 380,000.00 785,550.00
Analisa Page 59

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
6 MEMASANG 1 BUAH BAK MANDI PORSELIN/KERAMIK, VOLUME 0,30 M3
1.000 Bh Bak mandiPorselin/keramik 227,000.00 - 227,000.00 227,000.00
1.800 Oh Pekerja 65,000.00 117,000.00 - 117,000.00
2.700 Oh Tukang batu 85,000.00 229,500.00 - 229,500.00
0.540 Oh Kepala tukan 90,000.00 48,600.00 - 48,600.00
0.110 Oh Mandor 95,000.00 10,450.00 - 10,450.00
405,550.00 227,000.00 632,550.00
7 MEMASANG 1M' PIPA PVC PENYALUR AIR LIMBAH DIA 15 CM( DIA 4")
0.265 Btg Pipa PVC dia 4" str. Maspion 359,000.00 - 95,135.00 95,135.00
0.680 Kg Semen portland 1,400.00 - 952.00 952.00
0.013 M3 Pasir pasang 235,000.00 - 3,055.00 3,055.00
0.011 M3 Pasir urug 150,000.00 - 1,650.00 1,650.00
0.060 Oh Pekerja 65,000.00 3,900.00 - 3,900.00
0.030 Oh Tukang batu 85,000.00 2,550.00 - 2,550.00
0.003 Oh Kepala tukang batu 90,000.00 270.00 - 270.00
0.003 Oh Mandor 95,000.00 237.50 - 237.50
6,957.50 100,792.00 107,749.50
8 MEMASANG 1 BUAH BAK KONTROL, PASANGAN BATU BATA 30 X 30 / T. 35 CM
0.145 M3 Batu bata 900.00 - 130.50 130.50
44.000 Kg Semen porland 1,400.00 - 61,600.00 61,600.00
0.070 M3 Pasir pasang 235,000.00 - 16,450.00 16,450.00
0.070 M3 Koral beton 210,000.00 - 14,700.00 14,700.00
0.600 Kg Besi beton U 24 12,500.00 - 7,500.00 7,500.00
0.060 M3 Pasir beton 235,000.00 - 14,100.00 14,100.00
0.200 Oh Pekerja 65,000.00 13,000.00 - 13,000.00
0.015 Oh Tukang batu 85,000.00 1,275.00 - 1,275.00
0.002 Oh Kepala tukang batu 90,000.00 135.00 - 135.00
0.010 Oh Mandor 95,000.00 950.00 - 950.00
15,360.00 114,480.50 129,840.50
9 MEMASANG 1M' PIPA GALVANIS DIAMETER 0,5"
1.200 M' Pipa galvanis 0,5" 28,066.67 - 33,680.00 33,680.00
0.350 Perlengkapan 8,420.00 - 2,947.00 2,947.00
0.540 Oh Pekerja 65,000.00 35,100.00 - 35,100.00
0.090 Oh Tukang batu 85,000.00 7,650.00 - 7,650.00
0.009 Oh Kepala tukang batu 90,000.00 810.00 - 810.00
0.027 Oh Mandor 95,000.00 2,565.00 - 2,565.00
46,125.00 36,627.00 82,752.00
10 MEMASANG 1M' PIPA GALVANIS DIAMETER 3/4"
1.200 M' Pipa galvanis 3/4" 32,783.33 - 39,340.00 39,340.00
0.350 Perlengkapan 9,835.00 - 3,442.25 3,442.25
0.108 Oh Pekerja 65,000.00 7,020.00 - 7,020.00
0.180 Oh Tukang batu 85,000.00 15,300.00 - 15,300.00
0.018 Oh Kepala tukang batu 90,000.00 1,620.00 - 1,620.00
0.005 Oh Mandor 95,000.00 513.00 - 513.00
24,453.00 42,782.25 67,235.25
11 MEMASANG 1M' PIPA GALVANIS DIAMETER 1"
1.200 M' Pipa galvanis 1" 49,883.33 - 59,860.00 59,860.00
0.350 Perlengkapan 14,965.00 - 5,237.75 5,237.75
0.108 Oh Pekerja 65,000.00 7,020.00 - 7,020.00
0.180 Oh Tukang batu 85,000.00 15,300.00 - 15,300.00
0.018 Oh Kepala tukang batu 90,000.00 1,620.00 - 1,620.00
0.005 Oh Mandor 95,000.00 513.00 - 513.00
Analisa Page 60

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
24,453.00 65,097.75 89,550.75
Analisa Page 61

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
12 MEMASANG 1M' PIPA GALVANIS DIAMETER 2"
1.200 M' Pipa galvanis 2" 116,333.33 - 139,600.00 139,600.00
0.350 Perlengkapan 34,900.00 - 12,215.00 12,215.00
0.108 Oh Pekerja 65,000.00 7,020.00 - 7,020.00
0.180 Oh Tukang batu 85,000.00 15,300.00 - 15,300.00
0.018 Oh Kepala tukang batu 90,000.00 1,620.00 - 1,620.00
0.005 Oh Mandor 95,000.00 513.00 - 513.00
24,453.00 151,815.00 176,268.00
13 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 0,5"
1.200 M' Pipa PVC 0,5" 7,950.00 - 9,540.00 9,540.00
0.350 Perlengkapan 2,385.00 - 834.75 834.75
0.036 Oh Pekerja 65,000.00 2,340.00 - 2,340.00
0.060 Oh Tukang batu 85,000.00 5,100.00 - 5,100.00
0.006 Oh Kepala tukang batu 90,000.00 540.00 - 540.00
0.002 Oh Mandor 95,000.00 171.00 - 171.00
8,151.00 10,374.75 18,525.75
13 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3/4"
1.200 M' Pipa PVC 3/4" 10,900.00 - 13,080.00 13,080.00
0.350 Perlengkapan 3,270.00 - 1,144.50 1,144.50
0.036 Oh Pekerja 65,000.00 2,340.00 - 2,340.00
0.060 Oh Tukang batu 85,000.00 5,100.00 - 5,100.00
0.006 Oh Kepala tukang batu 90,000.00 540.00 - 540.00
0.002 Oh Mandor 95,000.00 171.00 - 171.00
8,151.00 14,224.50 22,375.50
15 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1"
1.200 M' Pipa PVC 1 " 50,900.00 - 61,080.00 61,080.00
0.350 Perlengkapan 15,270.00 - 5,344.50 5,344.50
0.036 Oh Pekerja 65,000.00 2,340.00 - 2,340.00
0.060 Oh Tukang batu 85,000.00 5,100.00 - 5,100.00
0.006 Oh Kepala tukang batu 90,000.00 540.00 - 540.00
0.002 Oh Mandor 95,000.00 171.00 - 171.00
8,151.00 66,424.50 74,575.50
16 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1,5"
1.200 M' Pipa PVC 1,5 " 28,300.00 - 33,960.00 33,960.00
0.350 Perlengkapan 8,490.00 - 2,971.50 2,971.50
0.036 Oh Pekerja 65,000.00 2,340.00 - 2,340.00
0.060 Oh Tukang batu 85,000.00 5,100.00 - 5,100.00
0.006 Oh Kepala tukang batu 90,000.00 540.00 - 540.00
0.002 Oh Mandor 95,000.00 171.00 - 171.00
8,151.00 36,931.50 45,082.50
17 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 2"
1.200 M' Pipa PVC 2" 33,175.00 - 39,810.00 39,810.00
0.350 Perlengkapan 9,952.50 - 3,483.38 3,483.38
0.054 Oh Pekerja 65,000.00 3,510.00 - 3,510.00
0.090 Oh Tukang batu 85,000.00 7,650.00 - 7,650.00
0.009 Oh Kepala tukang batu 90,000.00 810.00 - 810.00
0.003 Oh Mandor 95,000.00 256.50 - 256.50
12,226.50 43,293.38 55,519.88
Analisa Page 62

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
14 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3"
1.200 M' Pipa PVC 3" 60,225.00 - 72,270.00 72,270.00
0.350 Perlengkapan 18,067.50 - 6,323.63 6,323.63
0.081 Oh Pekerja 65,000.00 5,265.00 - 5,265.00
0.135 Oh Tukang batu 85,000.00 11,475.00 - 11,475.00
0.014 Oh Kepala tukang batu 90,000.00 1,215.00 - 1,215.00
0.004 Oh Mandor 95,000.00 389.50 - 389.50
18,344.50 78,593.63 96,938.13
19 1 BH PASANG BAK CUCI PIRING STAINLES STEEL
1.000 Bh Bak cuci stainles steel 375,000.00 - 375,000.00 375,000.00
1.000 Set water drain + acsesoris 25,000.00 - 25,000.00 25,000.00
0.030 Oh Pekerja 65,000.00 1,950.00 - 1,950.00
0.300 Oh Tukang batu 85,000.00 25,500.00 - 25,500.00
0.030 Oh Kepala tukang batu 90,000.00 2,700.00 - 2,700.00
0.002 Oh Mandor 95,000.00 142.50 - 142.50
30,292.50 400,000.00 430,292.50
20 MEMASANG 1 BUAH KRAN KUNINGAN DIAMETER 0,75" ATAU 0,5"
1.000 Bh Kran air 77,200.00 - 77,200.00 77,200.00
0.025 Bh Seal tape 3,400.00 - 85.00 85.00
0.010 Oh Pekerja 65,000.00 650.00 - 650.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
10,525.00 77,285.00 87,810.00
21 MEMASANG 1 BUAH KRAN STEINLESS DIAMETER 0,75" ATAU 0,5"
1.000 Bh Kran air 81,800.00 - 81,800.00 81,800.00
0.025 Bh Seal tape 3,400.00 - 85.00 85.00
0.010 Oh Pekerja 65,000.00 650.00 - 650.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
10,525.00 81,885.00 92,410.00
15 1 BH PASANG FLOOR DRAIN PLASTIK
1.000 Bh Floor drain plastik 27,200.00 - 27,200.00 27,200.00
0.010 Oh Pekerja 65,000.00 650.00 - 650.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
10,525.00 27,200.00 37,725.00
23 1 BH PASANG FLOOR DRAIN STEINLESS
1.000 Bh Floor drain steinless 77,200.00 - 77,200.00 77,200.00
0.010 Oh Pekerja 65,000.00 650.00 - 650.00
0.100 Oh Tukang batu 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang batu 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
10,525.00 77,200.00 87,725.00
XI PEKERJAAN BESI DAN ALUMINIUM
1 1 KG PASANG RANGKA KUDA - KUDA BAJA I WF
1.150 Kg Besi profil I WF 21,000.00 - 24,150.00 24,150.00
0.060 Oh Pekerja 65,000.00 3,900.00 - 3,900.00
0.060 Oh Tukang besi 85,000.00 5,100.00 - 5,100.00
0.006 Oh Kepala tukang besi 90,000.00 540.00 - 540.00
Analisa Page 63

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.003 Oh Mandor 95,000.00 285.00 - 285.00
9,825.00 24,150.00 33,975.00
Analisa Page 64

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
2 1 KG PASANG BESI PROFIL
1.150 Kg Besi profil 14,918.00 - 17,155.70 17,155.70
0.060 Oh Pekerja 65,000.00 3,900.00 - 3,900.00
0.060 Oh Tukang las konstruksi 85,000.00 5,100.00 - 5,100.00
0.006 Oh Kepala tukang besi 90,000.00 540.00 - 540.00
0.003 Oh Mandor 95,000.00 285.00 - 285.00
9,825.00 17,155.70 26,980.70
3 100 KG PEKERJAAN PERAKITAN
1.000 Liter Solar 6,600.00 - 6,600.00 6,600.00
0.100 Liter Minyak Pelumas 13,000.00 - 1,300.00 1,300.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.100 Oh Tukang las konstruksi 85,000.00 8,500.00 - 8,500.00
0.001 Oh Kepala tukang besi 90,000.00 90.00 - 90.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
15,565.00 7,900.00 23,465.00
4 1 M2 PASANG PINTU BESI PLAT BAJA, RANGKA BAJA SIKU
15.000 Kg Besi siku L 30.30.3 13,200.00 - 198,000.00 198,000.00
21.800 Kg Besi plat baja 13,200.00 - 287,760.00 287,760.00
0.050 Kg Komponen las 3,960.00 - 198.00 198.00
1.050 Oh Pekerja 65,000.00 68,250.00 - 68,250.00
1.050 Oh Tukang las biasa 85,000.00 89,250.00 - 89,250.00
0.105 Oh Kepala tukang besi 90,000.00 9,450.00 - 9,450.00
0.052 Oh Mandor 95,000.00 4,940.00 - 4,940.00
171,890.00 485,958.00 657,848.00
5 10 CM PEKERJAAN PENGELASAN DENGAN LAS LISTRIK
0.400 Kg Kawat las listrik 13,200.00 - 5,280.00 5,280.00
0.300 Kg Solar 4,500.00 - 1,350.00 1,350.00
0.040 Kg Minyak Pelumas 13,000.00 - 520.00 520.00
0.040 Oh Pekerja 65,000.00 2,600.00 - 2,600.00
0.020 Oh Tukang las konstruksi 85,000.00 1,700.00 - 1,700.00
0.002 Oh Kepala tukang 90,000.00 180.00 - 180.00
0.002 Oh Mandor 95,000.00 190.00 - 190.00
4,670.00 7,150.00 11,820.00
6 1 M2 PEKERJAAN JENDELA BESI SCUARE TUBE ( 25 X 5 ) CM
4.760 m' Besi Scuare tube 13,200.00 - 62,832.00 62,832.00
4.522 m' Besi lis kaca ( 1 x 1 ) cm 4,500.00 - 20,349.00 20,349.00
20.000 cm Pengelasan 1,182.00 - 23,640.00 23,640.00
0.650 Oh Pekerja 65,000.00 42,250.00 - 42,250.00
0.650 Oh Tukang las konstruksi 85,000.00 55,250.00 - 55,250.00
0.065 Oh Kepala tukang 90,000.00 5,850.00 - 5,850.00
0.032 Oh Mandor 95,000.00 3,040.00 - 3,040.00
106,390.00 106,821.00 213,211.00
7 1 M2 PASANG ROLLING DOOR BESI ( PLAT )
1.000 M2 Pintu Gulung Besi 325,000.00 - 325,000.00 325,000.00
1.200 Oh Pekerja 65,000.00 78,000.00 - 78,000.00
1.200 Oh Tukang besi 85,000.00 102,000.00 - 102,000.00
0.120 Oh Kepala tukang besi 90,000.00 10,800.00 - 10,800.00
0.006 Oh Mandor 95,000.00 532.00 - 532.00
191,332.00 325,000.00 516,332.00
Analisa Page 65

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
8 1 M2 PASANG ROLLING DOOR ALIMINIUM
1.000 M2 Slit Aluminium 350,000.00 - 350,000.00 350,000.00
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
1.000 Oh Tukang besi 85,000.00 85,000.00 - 85,000.00
0.100 Oh Kepala tukang besi 90,000.00 9,000.00 - 9,000.00
0.050 Oh Mandor 95,000.00 4,750.00 - 4,750.00
163,750.00 350,000.00 513,750.00
9 1 M2 PINTU LIPAT ( FOLDING DOOR ) BAHAN BAHAN PLASTIK / PVC
1.000 M2 Pintu lipat 450,000.00 - 450,000.00 450,000.00
0.440 Oh Pekerja 65,000.00 28,600.00 - 28,600.00
0.440 Oh Tukang besi 85,000.00 37,400.00 - 37,400.00
0.044 Oh Kepala tukang besi 90,000.00 3,960.00 - 3,960.00
0.022 Oh Mandor 95,000.00 2,090.00 - 2,090.00
72,050.00 450,000.00 522,050.00
10 1 M2 SUNSCREEN ALUMINIUM
1.000 M2 Sunscreen aluminium 400,000.00 - 400,000.00 400,000.00
0.080 Oh Pekerja 65,000.00 5,200.00 - 5,200.00
0.800 Oh Tukang besi 85,000.00 68,000.00 - 68,000.00
0.080 Oh Kepala tukang 90,000.00 7,200.00 - 7,200.00
0.004 Oh Mandor 95,000.00 380.00 - 380.00
80,780.00 400,000.00 480,780.00
11 1 M' KUSEN ALUMINIUM
1.100 M2 Profil aliminium 105,000.00 - 115,500.00 115,500.00
2.000 Bh Skrup fixer 500.00 - 1,000.00 1,000.00
0.060 Sealant 7,500.00 - 450.00 450.00
0.043 Oh Pekerja 65,000.00 2,795.00 - 2,795.00
0.043 Oh Tukang kusen aluminium 85,000.00 3,655.00 - 3,655.00
0.004 Oh Kepala tukang 90,000.00 387.00 - 387.00
0.002 Oh Mandor 95,000.00 199.50 - 199.50
7,036.50 116,950.00 123,986.50
12 1 M2 PASANG JENDELA NAKO
1.100 M2 Jendela nako 135,000.00 148,500.00 148,500.00
0.020 Kg Paku biasa 0,5" - 1" atau skrup 31,800.00 636.00 636.00
0.025 M2 Besi strip 13,200.00 330.00 330.00
0.200 Oh Pekerja 65,000.00 13,000.00 - 13,000.00
0.200 Oh Tukang besi 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala Tukang besi 90,000.00 1,800.00 - 1,800.00
0.001 Oh Mandor 95,000.00 95.00 - 95.00
31,895.00 149,466.00 181,361.00
13 1 M' PASANG TALANG DATAR, SENG BJLS 28 R. KAMPER
0.500 Lbr Seng plat 3" x 6" BJLS 28 58,700.00 - 29,350.00 29,350.00
0.015 Kg Paku biasa 0,5" - 1" atau skrup 31,800.00 - 477.00 477.00
0.010 M3 Kayu papan kamper 9,000,000.00 - 86,400.00 86,400.00
0.150 Oh Pekerja 65,000.00 9,750.00 - 9,750.00
0.400 Oh Tukang besi 85,000.00 34,000.00 - 34,000.00
0.025 Oh Kepala Tukang besi 90,000.00 2,250.00 - 2,250.00
0.001 Oh Mandor 95,000.00 123.50 - 123.50
46,123.50 116,227.00 162,350.50
Analisa Page 66

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
14 1 M' PASANG TALANG MIRING, SENG BJLS 28 R. KAMPER
0.500 Lbr Seng plat 3" x 6" BJLS 28 58,700.00 - 29,350.00 29,350.00
0.015 Kg Paku biasa 0,5" - 1" 31,800.00 - 477.00 477.00
0.019 M3 Kayu papan kamper 9,000,000.00 - 171,000.00 171,000.00
0.040 Oh Pekerja 65,000.00 2,600.00 - 2,600.00
0.400 Oh Tukang besi 85,000.00 34,000.00 - 34,000.00
0.025 Oh Kepala Tukang besi 90,000.00 2,250.00 - 2,250.00
0.001 Oh Mandor 95,000.00 123.50 - 123.50
38,973.50 200,827.00 239,800.50
XII PEKERJAAN KUNCI DAN KACA
1 1 BH PASANG KUNCI
1.000 Bh Kunci tanam 2 slaag ( Milano/Solid ) 363,000.00 - 363,000.00 363,000.00
0.010 Oh Pekerja 65,000.00 650.00 - 650.00
0.500 Oh Tukang besi 85,000.00 42,500.00 - 42,500.00
0.010 Oh Kepala tukang besi 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
44,525.00 363,000.00 407,525.00
2 1 BH PASANG KUNCI
1.000 Bh Kunci 2 Slaag ( Cess/Royal/Yalle ) 322,700.00 - 322,700.00 322,700.00
0.010 Oh Pekerja 65,000.00 650.00 - 650.00
0.500 Oh Tukang besi 85,000.00 42,500.00 - 42,500.00
0.010 Oh Kepala tukang besi 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
44,525.00 322,700.00 367,225.00
3 1 BH PASANG KUNCI
1.000 Bh Kunci tanam 1 Slaag ( KM ) 81,000.00 - 81,000.00 81,000.00
0.010 Oh Pekerja 65,000.00 650.00 - 650.00
0.500 Oh Tukang besi 85,000.00 42,500.00 - 42,500.00
0.010 Oh Kepala tukang besi 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
44,525.00 81,000.00 125,525.00
4 1 PS PASANG ENGSEL PINTU
1.000 Bh Engsel pintu kuningan 59,000.00 - 59,000.00 59,000.00
0.015 Oh Pekerja 65,000.00 975.00 - 975.00
0.150 Oh Tukang besi 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang besi 90,000.00 1,350.00 - 1,350.00
0.001 Oh Mandor 95,000.00 76.00 - 76.00
15,151.00 59,000.00 74,151.00
5 1 PS PASANG ENGSEL PINTU
1.000 Bh Engsel pintu setara YESS 68,000.00 - 68,000.00 68,000.00
0.015 Oh Pekerja 65,000.00 975.00 - 975.00
0.150 Oh Tukang besi 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang besi 90,000.00 1,350.00 - 1,350.00
0.001 Oh Mandor 95,000.00 76.00 - 76.00
15,151.00 68,000.00 83,151.00
6 1 PS PASANG ENGSEL JENDELA KUPU-KUPU
1.000 Bh Engsel jendela setara YESS 60,800.00 - 60,800.00 60,800.00
0.010 Oh Pekerja 65,000.00 650.00 - 650.00
0.100 Oh Tukang besi 85,000.00 8,500.00 - 8,500.00
0.010 Oh Kepala tukang besi 90,000.00 900.00 - 900.00
0.001 Oh Mandor 95,000.00 47.50 - 47.50
10,097.50 60,800.00 70,897.50
Analisa Page 67

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
7 1 BH PASANG KAIT ANGIN
1.000 Bh Kait angin pintu 31,800.00 - 31,800.00 31,800.00
0.015 Oh Pekerja 65,000.00 975.00 - 975.00
0.150 Oh Tukang besi 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang besi 90,000.00 1,350.00 - 1,350.00
0.001 Oh Mandor 95,000.00 76.00 - 76.00
15,151.00 31,800.00 46,951.00
8 1 BH PASANG KAIT ANGIN
1.000 Bh Kait angin jendela 27,200.00 - 27,200.00 27,200.00
0.015 Oh Pekerja 65,000.00 975.00 - 975.00
0.150 Oh Tukang besi 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang besi 90,000.00 1,350.00 - 1,350.00
0.001 Oh Mandor 95,000.00 76.00 - 76.00
15,151.00 27,200.00 42,351.00
9 1 BH PASANG KUNCI SLOT
1.000 Bh Kunci slot/gembok 107,700.00 - 107,700.00 107,700.00
0.020 Oh Pekerja 65,000.00 1,300.00 - 1,300.00
0.200 Oh Tukang besi 85,000.00 17,000.00 - 17,000.00
0.020 Oh Kepala tukang besi 90,000.00 1,800.00 - 1,800.00
0.001 Oh Mandor 95,000.00 95.00 - 95.00
20,195.00 107,700.00 127,895.00
10 1 M2 PASANG KACA, TEBAL 5 MM
1.100 M2 Kaca bening 5 mm 105,000.00 - 115,500.00 115,500.00
0.015 Oh Pekerja 65,000.00 975.00 - 975.00
0.150 Oh Tukang kayu 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang kayu 90,000.00 1,350.00 - 1,350.00
0.001 Oh Mandor 95,000.00 76.00 - 76.00
15,151.00 115,500.00 130,651.00
11 1 M2 PASANG KACA, TEBAL 5 MM
1.100 M2 Kaca riben 5 mm 148,000.00 - 162,800.00 162,800.00
0.015 Oh Pekerja 65,000.00 975.00 - 975.00
0.150 Oh Tukang besi 85,000.00 12,750.00 - 12,750.00
0.015 Oh Kepala tukang besi 90,000.00 1,350.00 - 1,350.00
0.001 Oh Mandor 95,000.00 76.00 - 76.00
15,151.00 162,800.00 177,951.00
XIII PEKERJAAN PENUTUP LANTAI DAN DINDING
1 1 M2 PASANG LANTAI KERAMIK PUTIH 40 X 40 CM
6.630 Bh Lantai keramik 40 x 40 putih 12,000.00 - 79,560.00 79,560.00
9.800 Kg Semen porland 1,400.00 - 13,720.00 13,720.00
0.045 M2 Pasir pasang ex karangasem 235,000.00 - 10,575.00 10,575.00
1.300 Kg Semen warna 1,500.00 - 1,950.00 1,950.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala Tukang batu 90,000.00 1,170.00 - 1,170.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
29,280.00 105,805.00 135,085.00
Analisa Page 68

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
2 1 M2 PASANG LANTAI KERAMIK WARNA 40 X 40 CM
6.630 Bh Lantai keramik 40 x 40 warna 12,833.33 - 85,085.00 85,085.00
9.800 Kg Semen porland 1,400.00 - 13,720.00 13,720.00
0.045 M2 Pasir pasang ex karangasem 235,000.00 - 10,575.00 10,575.00
1.300 Kg Semen warna 1,500.00 - 1,950.00 1,950.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala Tukang batu 90,000.00 1,170.00 - 1,170.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
29,280.00 111,330.00 140,610.00
3 1 M2 PASANG LANTAI KERAMIK RUSTIK 40 X 40 CM
6.630 Bh Lantai keramik 40 x 40 rustik 13,666.67 - 90,610.00 90,610.00
9.800 Kg Semen porland 1,400.00 - 13,720.00 13,720.00
0.045 M2 Pasir pasang ex karangasem 235,000.00 - 10,575.00 10,575.00
1.300 Kg Semen warna 1,500.00 - 1,950.00 1,950.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala Tukang batu 90,000.00 1,170.00 - 1,170.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
29,280.00 116,855.00 146,135.00
4 1 M2 PASANG LANTAI KERAMIK PUTIH 30 X 30 CM
11.870 Bh Lantai keramik 30 x 30 putih 5,363.64 - 63,666.36 63,666.36
10.000 Kg Semen porland 1,400.00 - 14,000.00 14,000.00
0.045 M2 Pasir pasang ex karangasem 235,000.00 - 10,575.00 10,575.00
1.500 Kg Semen warna 1,500.00 - 2,250.00 2,250.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala Tukang batu 90,000.00 1,170.00 - 1,170.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
29,280.00 90,491.36 119,771.36
5 1 M2 PASANG LANTAI KERAMIK MOTIP 30 X 30 CM
11.870 Bh Lantai keramik 30x30 motif 6,190.91 - 73,486.09 73,486.09
10.000 Kg Semen porland 1,400.00 - 14,000.00 14,000.00
0.045 M2 Pasir pasang ex karangasem 235,000.00 - 10,575.00 10,575.00
1.500 Kg Semen warna 1,500.00 - 2,250.00 2,250.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala Tukang batu 90,000.00 1,170.00 - 1,170.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
29,280.00 100,311.09 129,591.09
6 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM PUTIH
26.500 Bh Lantai keramik 20 x 20 putih 3,088.00 - 81,832.00 81,832.00
10.400 Kg Semen porland 1,400.00 - 14,560.00 14,560.00
0.045 M2 Pasir pasang ex karangasem 235,000.00 - 10,575.00 10,575.00
1.620 Kg Semen warna 1,500.00 - 2,430.00 2,430.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala Tukang batu 90,000.00 1,170.00 - 1,170.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
29,280.00 109,397.00 138,677.00
Analisa Page 69

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
7 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM WARNA
26.500 Bh Lantai keramik 20 x 20 warna 3,452.00 - 91,478.00 91,478.00
10.400 Kg Semen porland 1,400.00 - 14,560.00 14,560.00
0.045 M2 Pasir pasang ex karangasem 235,000.00 - 10,575.00 10,575.00
1.620 Kg Semen warna 1,500.00 - 2,430.00 2,430.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala Tukang batu 90,000.00 1,170.00 - 1,170.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
29,280.00 119,043.00 148,323.00
8 1 M2 PASANG LANTAI GRANIT 40 X 40 CM
6.000 Bh Ubin granito 60,666.67 - 364,000.00 364,000.00
9.800 Kg Semen porland 1,400.00 - 13,720.00 13,720.00
0.045 M2 Pasir pasang ex karangasem 235,000.00 - 10,575.00 10,575.00
1.620 Kg Semen warna 1,500.00 - 2,430.00 2,430.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala Tukang batu 90,000.00 1,170.00 - 1,170.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
29,280.00 390,725.00 420,005.00
9 1 M2 PASANG LANTAI GRANIT 60 X 60 CM
3.000 Bh Ubin str niro grass 106,666.67 - 320,000.00 320,000.00
10.000 Kg Semen porland 1,400.00 - 14,000.00 14,000.00
0.045 M2 Pasir pasang ex karangasem 235,000.00 - 10,575.00 10,575.00
1.500 Kg Semen warna 1,500.00 - 2,250.00 2,250.00
0.500 Oh Pekerja 65,000.00 32,500.00 - 32,500.00
0.250 Oh Tukang batu 85,000.00 21,250.00 - 21,250.00
0.130 Oh Kepala Tukang batu 90,000.00 11,700.00 - 11,700.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
66,685.00 346,825.00 413,510.00
10 1 M2 PASANG LANTAI FLOOR HARDENER
5.000 Kg Floor Hardener ( natural ) 9,500.00 - 47,500.00 47,500.00
0.120 Oh Pekerja 65,000.00 7,800.00 - 7,800.00
0.120 Oh Tukang batu 85,000.00 10,200.00 - 10,200.00
0.012 Oh Kepala Tukang batu 90,000.00 1,080.00 - 1,080.00
0.006 Oh Mandor 95,000.00 570.00 - 570.00
19,650.00 47,500.00 67,150.00
11 1 M2 PASANG LANTAI FLOOR HARDENER
5.000 Kg Floor Hardener ( Warna ) 12,500.00 - 62,500.00 62,500.00
0.120 Oh Pekerja 65,000.00 7,800.00 - 7,800.00
0.120 Oh Tukang batu 85,000.00 10,200.00 - 10,200.00
0.012 Oh Kepala Tukang batu 90,000.00 1,080.00 - 1,080.00
0.006 Oh Mandor 95,000.00 570.00 - 570.00
19,650.00 62,500.00 82,150.00
12 1 M2 PASANG DINDING KERAMIK 20 X 25 CM
20.000 Bh Keramik 20 x 25 putih 3,635.00 - 72,700.00 72,700.00
9.300 Kg Semen porland 1,400.00 - 13,020.00 13,020.00
0.018 M2 Pasir pasang ex karangasem 235,000.00 - 4,230.00 4,230.00
2.750 Kg Semen warna 1,500.00 - 4,125.00 4,125.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala Tukang 90,000.00 1,170.00 - 1,170.00
Analisa Page 70

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
29,280.00 94,075.00 123,355.00
Analisa Page 71

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
17 1 M2 PASANG DINDING KERAMIK 20 X 25 CM
20.000 Bh Keramik 20 x 25 warna 3,850.00 - 77,000.00 77,000.00
9.300 Kg Semen porland 1,400.00 - 13,020.00 13,020.00
0.018 M2 Pasir pasang ex karangasem 235,000.00 - 4,230.00 4,230.00
2.750 Kg Semen warna 1,500.00 - 4,125.00 4,125.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala Tukang 90,000.00 1,170.00 - 1,170.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
29,280.00 98,375.00 127,655.00
14 1 M2 PASANG DINDING KERAMIK 20 X 20 CM
26.500 Bh Keramik 20 x 20 3,088.00 - 81,832.00 81,832.00
9.300 Kg Semen porland 1,400.00 - 13,020.00 13,020.00
0.018 M2 Pasir pasang ex karangasem 235,000.00 - 4,230.00 4,230.00
2.750 Kg Semen warna 1,500.00 - 4,125.00 4,125.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala Tukang 90,000.00 1,170.00 - 1,170.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
29,280.00 103,207.00 132,487.00
15 1 M2 PASANG DINDING KERAMIK 10 X 20 CM
53.000 Bh Keramik 10 x 20 1,540.00 - 81,620.00 81,620.00
9.300 Kg Semen porland 1,400.00 - 13,020.00 13,020.00
0.018 M2 Pasir pasang ex karangasem 235,000.00 - 4,230.00 4,230.00
2.750 Kg Semen warna 1,500.00 - 4,125.00 4,125.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.125 Oh Tukang batu 85,000.00 10,625.00 - 10,625.00
0.013 Oh Kepala Tukang 90,000.00 1,170.00 - 1,170.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
29,280.00 102,995.00 132,275.00
16 1 M2 PASANG DINDING MARMER 20 X 20 CM
26.500 Bh Marmer 20 x 20 10,500.00 - 278,250.00 278,250.00
12.440 Kg Semen porland 1,400.00 - 17,416.00 17,416.00
0.025 M2 Pasir pasang ex karangasem 235,000.00 - 5,875.00 5,875.00
0.650 Kg Semen warna 1,500.00 - 975.00 975.00
0.750 Oh Pekerja 65,000.00 48,750.00 - 48,750.00
0.500 Oh Tukang batu 85,000.00 42,500.00 - 42,500.00
0.130 Oh Kepala Tukang 90,000.00 11,700.00 - 11,700.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
104,185.00 302,516.00 406,701.00
17 1 M2 PASANG LANTAI MARMER 30 X 30 CM
11.111 Bh Marmer 30 x 30 ( warna serasi ) 26,500.00 - 294,444.44 294,444.44
12.440 Kg Semen porland 1,400.00 - 17,416.00 17,416.00
0.025 M2 Pasir pasang ex karangasem 235,000.00 - 5,875.00 5,875.00
0.650 Kg Semen warna 1,500.00 - 975.00 975.00
0.750 Oh Pekerja 65,000.00 48,750.00 - 48,750.00
0.500 Oh Tukang batu 85,000.00 42,500.00 - 42,500.00
0.130 Oh Kepala Tukang 90,000.00 11,700.00 - 11,700.00
0.013 Oh Mandor 95,000.00 1,235.00 - 1,235.00
104,185.00 318,710.44 422,895.44
Analisa Page 72

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
18 1 M2 PASANGSTYLE BALI DINDING PARAS KLATING
1.100 m2 Paras kelating 91,685.00 - 100,853.50 100,853.50
11.750 Kg Semen porland 1,400.00 - 16,450.00 16,450.00
0.035 M2 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
1.400 Oh Peladen Style bali 85,000.00 119,000.00 - 119,000.00
1.000 Oh Tukang style bali 90,000.00 90,000.00 - 90,000.00
0.100 Oh Kepala Tukang style bali 95,000.00 9,500.00 - 9,500.00
0.100 Oh Mandor 95,000.00 9,500.00 - 9,500.00
228,000.00 125,528.50 353,528.50
19 1 M2 PASANG DINDING PARAS BELAYU
1.100 m2 Paras belayu 108,355.00 - 119,190.50 119,190.50
11.750 Kg Semen porland 1,400.00 - 16,450.00 16,450.00
0.035 M2 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
1.400 Oh Peladen Style bali 85,000.00 119,000.00 - 119,000.00
1.200 Oh Tukang style bali 90,000.00 108,000.00 - 108,000.00
0.120 Oh Kepala Tukang style bali 95,000.00 11,400.00 - 11,400.00
0.120 Oh Mandor 95,000.00 11,400.00 - 11,400.00
249,800.00 143,865.50 393,665.50
18 1 M2 PASANG DINDING BATA GOSOK
105.000 Bh Bata gosok 2,200.00 - 231,000.00 231,000.00
11.750 Kg Semen porland 1,400.00 - 16,450.00 16,450.00
0.035 M2 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
1.400 Oh Peladen Style bali 85,000.00 119,000.00 - 119,000.00
1.200 Oh Tukang style bali 90,000.00 108,000.00 - 108,000.00
0.120 Oh Kepala Tukang style bali 95,000.00 11,400.00 - 11,400.00
0.120 Oh Mandor 95,000.00 11,400.00 - 11,400.00
249,800.00 255,675.00 505,475.00
21 1 M2 PASANG DINDING PARAS TEMPEL PALIMANAN ( JOGJA )
1.100 m2 Batu tempel ( putih ) 125,000.00 - 137,500.00 137,500.00
11.750 Kg Semen porland 1,400.00 - 16,450.00 16,450.00
0.035 M2 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
1.400 Oh Peladen Style bali 85,000.00 119,000.00 - 119,000.00
1.000 Oh Tukang style bali 90,000.00 90,000.00 - 90,000.00
0.100 Oh Kepala Tukang style bali 95,000.00 9,500.00 - 9,500.00
0.100 Oh Mandor 95,000.00 9,500.00 - 9,500.00
228,000.00 162,175.00 390,175.00
22 1 M2 PASANG DINDING PARAS TEMPEL PALIMANAN ( JOGJA )
1.100 m2 Batu tempel ( serat ) 120,000.00 - 132,000.00 132,000.00
11.750 Kg Semen porland 1,400.00 - 16,450.00 16,450.00
0.035 M2 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
1.400 Oh Pekerja 85,000.00 119,000.00 - 119,000.00
1.000 Oh Tukang batu 85,000.00 85,000.00 - 85,000.00
0.100 Oh Kepala Tukang Batu 90,000.00 9,000.00 - 9,000.00
0.100 Oh Mandor 95,000.00 9,500.00 - 9,500.00
222,500.00 156,675.00 379,175.00
23 1 M2 PASANG DINDING PARAS LORENG KIDUL ( JOGJA )
1.100 m2 Paras loreng jogja 110,000.00 - 121,000.00 121,000.00
11.750 Kg Semen porland 1,400.00 - 16,450.00 16,450.00
0.035 M2 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
1.400 Oh Pekerja 85,000.00 119,000.00 - 119,000.00
1.000 Oh Tukang batu 85,000.00 85,000.00 - 85,000.00
0.100 Oh Kepala Tukang 90,000.00 9,000.00 - 9,000.00
Analisa Page 73

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.100 Oh Mandor 95,000.00 9,500.00 - 9,500.00
222,500.00 145,675.00 368,175.00
Analisa Page 74

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
24 1 M2 PASANG DINDING BATU BATIK GREEN
1.100 m2 batu batik green 115,000.00 - 126,500.00 126,500.00
11.750 Kg Semen porland 1,400.00 - 16,450.00 16,450.00
0.035 M2 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
1.400 Oh Pekerja 85,000.00 119,000.00 - 119,000.00
1.000 Oh Tukang batu 85,000.00 85,000.00 - 85,000.00
0.100 Oh Kepala Tukang Batu 90,000.00 9,000.00 - 9,000.00
0.100 Oh Mandor 95,000.00 9,500.00 - 9,500.00
222,500.00 151,175.00 373,675.00
25 1 M2 PASANG DINDING BATU ANDESIT BAKAR ( JOGJA )
1.100 m2 batu andesit 20/30 158,000.00 - 173,800.00 173,800.00
11.750 Kg Semen porland 1,400.00 - 16,450.00 16,450.00
0.035 M2 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
1.400 Oh Pekerja 85,000.00 119,000.00 - 119,000.00
1.000 Oh Tukang batu 85,000.00 85,000.00 - 85,000.00
0.100 Oh Kepala Tukang 90,000.00 9,000.00 - 9,000.00
0.100 Oh Mandor 95,000.00 9,500.00 - 9,500.00
222,500.00 198,475.00 420,975.00
26 1 M2 PASANG DINDING BATU CANDI ( JOGJA )
1.100 m2 batu candi 20/30 95,000.00 - 104,500.00 104,500.00
11.750 Kg Semen porland 1,400.00 - 16,450.00 16,450.00
0.035 M2 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
1.400 Oh Pekerja 85,000.00 119,000.00 - 119,000.00
1.000 Oh Tukang batu 85,000.00 85,000.00 - 85,000.00
0.100 Oh Kepala Tukang 90,000.00 9,000.00 - 9,000.00
0.100 Oh Mandor 95,000.00 9,500.00 - 9,500.00
222,500.00 129,175.00 351,675.00
27 1 M2 PASANG DINDING BATU PILAH
1.100 m2 batu pilah 35,000.00 - 38,500.00 38,500.00
11.750 Kg Semen porland 1,400.00 - 16,450.00 16,450.00
0.035 M2 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
1.400 Oh Pekerja 85,000.00 119,000.00 - 119,000.00
1.000 Oh Tukang batu 85,000.00 85,000.00 - 85,000.00
0.100 Oh Kepala Tukang 90,000.00 9,000.00 - 9,000.00
0.100 Oh Mandor 95,000.00 9,500.00 - 9,500.00
222,500.00 63,175.00 285,675.00
28 1 M2 PASANG DINDING BATU ALUR GREEN
1.100 m2 Batu alur green 158,000.00 - 173,800.00 173,800.00
11.750 Kg Semen porland 1,400.00 - 16,450.00 16,450.00
0.035 M2 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
1.400 Oh Pekerja 85,000.00 119,000.00 - 119,000.00
1.000 Oh Tukang batu 85,000.00 85,000.00 - 85,000.00
0.100 Oh Kepala Tukang 90,000.00 9,000.00 - 9,000.00
0.100 Oh Mandor 95,000.00 9,500.00 - 9,500.00
222,500.00 198,475.00 420,975.00
29 1 M2 PASANG DINDING BATU CANDI ALUR
1.100 m2 Batu candi alur 155,000.00 - 170,500.00 170,500.00
11.750 Kg Semen porland 1,400.00 - 16,450.00 16,450.00
0.035 M2 Pasir pasang ex karangasem 235,000.00 - 8,225.00 8,225.00
1.400 Oh Pekerja 85,000.00 119,000.00 - 119,000.00
1.000 Oh Tukang batu 85,000.00 85,000.00 - 85,000.00
0.100 Oh Kepala Tukang 90,000.00 9,000.00 - 9,000.00
Analisa Page 75

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.100 Oh Mandor 95,000.00 9,500.00 - 9,500.00
222,500.00 195,175.00 417,675.00
Analisa Page 76

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
19 1 M' PASANG PLIN KERAMIK 10 X 30
3.530 Bh Plin keramik 10 x 30 putih 1,787.88 - 6,311.21 6,311.21
1.140 Kg Semen portland 1,400.00 - 1,596.00 1,596.00
0.003 M3 Pasir pasang ex karangasem 235,000.00 - 752.00 752.00
0.100 Kg Semen warna 1,500.00 - 150.00 150.00
0.090 Oh Pekerja 65,000.00 5,850.00 - 5,850.00
0.090 Oh Tukang batu 85,000.00 7,650.00 - 7,650.00
0.009 Oh Kepala tukang batu 90,000.00 810.00 - 810.00
0.005 Oh Mandor 95,000.00 427.50 - 427.50
14,737.50 8,809.21 23,546.71
31 1 M' PASANG PLIN KERAMIK 10 X 30
3.530 Bh Plin keramik 10 x 30 warna 2,063.64 - 7,284.64 7,284.64
1.140 Kg Semen portland 1,400.00 - 1,596.00 1,596.00
0.003 M3 Pasir pasang ex karangasem 235,000.00 - 752.00 752.00
0.100 Kg Semen warna 1,500.00 - 150.00 150.00
0.090 Oh Pekerja 65,000.00 5,850.00 - 5,850.00
0.090 Oh Tukang batu 85,000.00 7,650.00 - 7,650.00
0.009 Oh Kepala tukang batu 90,000.00 810.00 - 810.00
0.005 Oh Mandor 95,000.00 427.50 - 427.50
14,737.50 9,782.64 24,520.14
32 1 M' PASANG PLIN KERAMIK 10 X 40
2.650 Bh Plin keramik 10 x 40 putih 3,000.00 - 7,950.00 7,950.00
1.140 Kg Semen portland 1,400.00 - 1,596.00 1,596.00
0.003 M3 Pasir pasang ex karangasem 235,000.00 - 752.00 752.00
0.100 Kg Semen warna 1,500.00 - 150.00 150.00
0.090 Oh Pekerja 65,000.00 5,850.00 - 5,850.00
0.090 Oh Tukang batu 85,000.00 7,650.00 - 7,650.00
0.009 Oh Kepala tukang batu 90,000.00 810.00 - 810.00
0.005 Oh Mandor 95,000.00 427.50 - 427.50
14,737.50 10,448.00 25,185.50
33 1 M' PASANG PLIN KERAMIK 10 X 40
2.650 Bh Plin keramik 10 x 40 warna 3,208.33 - 8,502.08 8,502.08
1.140 Kg Semen portland 1,400.00 - 1,596.00 1,596.00
0.003 M3 Pasir pasang ex karangasem 235,000.00 - 752.00 752.00
0.100 Kg Semen warna 1,500.00 - 150.00 150.00
0.090 Oh Pekerja 65,000.00 5,850.00 - 5,850.00
0.090 Oh Tukang batu 85,000.00 7,650.00 - 7,650.00
0.009 Oh Kepala tukang batu 90,000.00 810.00 - 810.00
0.005 Oh Mandor 95,000.00 427.50 - 427.50
14,737.50 11,000.08 25,737.58
34 1 M' PASANG PLIN KERAMIK 10 X 40
2.650 Bh Plin keramik 10 x 40 rustik 3,416.67 - 9,054.17 9,054.17
1.140 Kg Semen portland 1,400.00 - 1,596.00 1,596.00
0.003 M3 Pasir pasang ex karangasem 235,000.00 - 752.00 752.00
0.100 Kg Semen warna 1,500.00 - 150.00 150.00
0.090 Oh Pekerja 65,000.00 5,850.00 - 5,850.00
0.090 Oh Tukang batu 85,000.00 7,650.00 - 7,650.00
0.009 Oh Kepala tukang batu 90,000.00 810.00 - 810.00
0.005 Oh Mandor 95,000.00 427.50 - 427.50
14,737.50 11,552.17 26,289.67
Analisa Page 77

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
35 1 M' PASANG PLIN GRANIT 10 X 40
2.650 Bh Plin keramik 10 x 40 warna 15,166.67 - 40,191.67 40,191.67
1.140 Kg Semen portland 1,400.00 - 1,596.00 1,596.00
0.003 M3 Pasir pasang ex karangasem 235,000.00 - 752.00 752.00
0.100 Kg Semen warna 1,500.00 - 150.00 150.00
0.090 Oh Pekerja 65,000.00 5,850.00 - 5,850.00
0.090 Oh Tukang batu 85,000.00 7,650.00 - 7,650.00
0.009 Oh Kepala tukang batu 90,000.00 810.00 - 810.00
0.005 Oh Mandor 95,000.00 427.50 - 427.50
14,737.50 42,689.67 57,427.17
36 1 M' PASANG PLIN GRANIT 10 X 60
1.666 Bh Plin keramik 10 x 40 warna 35,555.56 - 59,235.56 59,235.56
1.140 Kg Semen portland 1,400.00 - 1,596.00 1,596.00
0.003 M3 Pasir pasang ex karangasem 235,000.00 - 752.00 752.00
0.100 Kg Semen warna 1,500.00 - 150.00 150.00
0.090 Oh Pekerja 65,000.00 5,850.00 - 5,850.00
0.090 Oh Tukang batu 85,000.00 7,650.00 - 7,650.00
0.009 Oh Kepala tukang batu 90,000.00 810.00 - 810.00
0.005 Oh Mandor 95,000.00 427.50 - 427.50
14,737.50 61,733.56 76,471.06
37 1 M' PASANG PLIN KAYU KAMPER 2 X 10 CM
0.002 M3 Kayu papan kamper 9,000,000.00 21,600.00 21,600.00
0.050 Kg Paku skrup 3,5' 39,500.00 1,975.00 1,975.00
0.120 Oh Pekerja 65,000.00 7,800.00 7,800.00
0.120 Oh Tukang kayu 85,000.00 10,200.00 10,200.00
0.012 Oh Kepala tukang kayu 90,000.00 1,080.00 1,080.00
0.006 Oh Mandor 95,000.00 570.00 570.00
19,650.00 23,575.00 43,225.00
38 1 M2 PASANG LANTAI KARPET
1.050 M3 Karpet 45,000.00 47,250.00 47,250.00
0.350 Kg Lem 11,500.00 4,025.00 4,025.00
0.120 Oh Pekerja 65,000.00 7,800.00 7,800.00
0.120 Oh Tukang kayu 85,000.00 10,200.00 10,200.00
0.012 Oh Kepala tukang kayu 90,000.00 1,080.00 1,080.00
0.006 Oh Mandor 95,000.00 570.00 570.00
19,650.00 51,275.00 70,925.00
39 1 M2 PASANG UNDERLAYER / Pelapis Bawah Karpet
1.050 M3 Under Layer / Rubber corugated 35,000.00 36,750.00 36,750.00
0.350 Kg Lem 11,500.00 4,025.00 4,025.00
0.120 Oh Pekerja 65,000.00 7,800.00 7,800.00
0.120 Oh Tukang kayu 85,000.00 10,200.00 10,200.00
0.012 Oh Kepala tukang kayu 90,000.00 1,080.00 1,080.00
0.006 Oh Mandor 95,000.00 570.00 570.00
19,650.00 40,775.00 60,425.00
40 1 M2 PASANG LANTAI PARQUET JATI
1.050 M2 Parquet jati 525,000.00 551,250.00 551,250.00
0.600 Kg Lem vinyil 11,500.00 6,900.00 6,900.00
0.700 Oh Pekerja 65,000.00 45,500.00 45,500.00
0.350 Oh Tukang kayu 85,000.00 29,750.00 29,750.00
0.035 Oh Kepala tukang kayu 90,000.00 3,150.00 3,150.00
0.033 Oh Mandor 95,000.00 3,087.50 3,087.50
81,487.50 558,150.00 639,637.50
Analisa Page 78

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
40 1 M2 PASANG LANTAI PARQUET BENGKIRAI
1.050 M2 Parquet Bengkirai 355,000.00 372,750.00 372,750.00
0.600 Kg Lem vinyil 11,500.00 6,900.00 6,900.00
0.700 Oh Pekerja 65,000.00 45,500.00 45,500.00
0.350 Oh Tukang kayu 85,000.00 29,750.00 29,750.00
0.035 Oh Kepala tukang kayu 90,000.00 3,150.00 3,150.00
0.033 Oh Mandor 95,000.00 3,087.50 3,087.50
81,487.50 379,650.00 461,137.50
41 1 M2 PASANG LANTAI KAYU ( gymfloor )
1.050 M2 Gymfloor 475,000.00 498,750.00 498,750.00
0.600 Kg Lem 11,500.00 6,900.00 6,900.00
0.700 Oh Pekerja 65,000.00 45,500.00 45,500.00
0.350 Oh Tukang kayu 85,000.00 29,750.00 29,750.00
0.035 Oh Kepala tukang kayu 90,000.00 3,150.00 3,150.00
0.033 Oh Mandor 95,000.00 3,087.50 3,087.50
81,487.50 505,650.00 587,137.50
XIV PEKERJAAN PENGECATAN
1 1 M2 PENGECATAN BIDANG KAYU BARU (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0.200 Kg Cat meni 35,450.00 - 7,090.00 7,090.00
0.150 Kg Plamuur 27,200.00 - 4,080.00 4,080.00
0.170 Kg Cat dasar 86,150.00 - 14,645.50 14,645.50
0.260 Kg cat penutup 2x 86,150.00 - 22,399.00 22,399.00
0.070 Oh Pekerja 65,000.00 4,550.00 - 4,550.00
0.009 Oh Tukang cat 80,000.00 720.00 - 720.00
0.006 Oh Kepala tukang cat 85,000.00 510.00 - 510.00
0.003 Oh Mandor 95,000.00 237.50 - 237.50
6,017.50 48,214.50 54,232.00
2 1 M2 PENGECATAN BIDANG KAYU LAMA
0.150 Kg Plamuur 27,200.00 - 4,080.00 4,080.00
0.170 Kg cat penutup 2x 86,150.00 - 14,645.50 14,645.50
0.070 Oh Pekerja 65,000.00 4,550.00 - 4,550.00
0.075 Oh Tukang cat 80,000.00 6,000.00 - 6,000.00
0.008 Oh Kepala tukang 85,000.00 637.50 - 637.50
0.003 Oh Mandor 95,000.00 237.50 237.50
11,425.00 18,725.50 30,150.50
3 1 M2 PENGECATAN BIDANG KAYU DENGAN PERNIS
0.250 Kg Pernis str. Cap dayak 70,000.00 - 17,500.00 17,500.00
0.100 Lbr Amplas 5,400.00 - 540.00 540.00
0.160 Oh Pekerja 65,000.00 10,400.00 - 10,400.00
0.160 Oh Tukang cat 80,000.00 12,800.00 - 12,800.00
0.016 Oh Kepala tukang 85,000.00 1,360.00 - 1,360.00
0.003 Oh Mandor 95,000.00 237.50 - 237.50
24,797.50 18,040.00 42,837.50
4 1 M2 PENGECATAN BIDANG KAYU DENGAN POLITUR
0.150 Kg Wood filler 36,363.64 - 5,454.55 5,454.55
0.075 Kg Impra/mowilek 81,800.00 - 6,135.00 6,135.00
0.075 Kg Sending sealer 65,000.00 - 4,875.00 4,875.00
1.000 Lbr Amplas 5,400.00 - 5,400.00 5,400.00
0.250 Oh Pekerja 65,000.00 16,250.00 - 16,250.00
0.200 Oh Tukang cat 80,000.00 16,000.00 - 16,000.00
0.020 Oh Kepala tukang 85,000.00 1,700.00 - 1,700.00
0.003 Oh Mandor 95,000.00 237.50 - 237.50
Analisa Page 79

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
34,187.50 21,864.55 56,052.05
Analisa Page 80

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
5 1 M2 PENGECATAN TEMBOK BARU (1 LAPIS PLAMIR, 1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0.100 Kg Plamur 15,000.00 - 1,500.00 1,500.00
0.120 Kg Cat dasar 20,900.00 - 2,508.00 2,508.00
0.300 Kg cat penutup 2x (str. metrolith) 20,900.00 - 6,270.00 6,270.00
0.050 Oh Pekerja 65,000.00 3,250.00 - 3,250.00
0.125 Oh Tukang cat 80,000.00 10,000.00 - 10,000.00
0.013 Oh Kepala tukang 85,000.00 1,062.50 - 1,062.50
0.003 Oh Mandor 95,000.00 237.50 - 237.50
14,550.00 10,278.00 24,828.00
6 1 M2 PENGECATAN TEMBOK LAMA (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0.120 Kg Cat dasar 20,900.00 2,508.00 2,508.00
0.300 Kg cat penutup 2x (str. metrolith) 20,900.00 - 6,270.00 6,270.00
0.050 Oh Pekerja 65,000.00 3,250.00 - 3,250.00
0.125 Oh Tukang cat 80,000.00 10,000.00 - 10,000.00
0.013 Oh Kepala tukang 85,000.00 1,062.50 - 1,062.50
0.003 Oh Mandor 95,000.00 237.50 - 237.50
14,550.00 6,270.00 23,328.00
7 1 M2 PENGECATAN PLAFOND (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0.120 Kg Cat dasar 20,900.00 2,508.00 2,508.00
0.300 Kg cat penutup 2x (str. metrolith) 20,900.00 - 6,270.00 6,270.00
0.050 Kg Pekerja 65,000.00 3,250.00 - 3,250.00
0.125 Oh Tukang cat 80,000.00 10,000.00 - 10,000.00
0.013 Oh Kepala tukang 85,000.00 1,062.50 - 1,062.50
0.003 Oh Mandor 95,000.00 237.50 - 237.50
14,550.00 6,270.00 23,328.00
8 1 M2 PENGECATAN DASAR PERMUKAAN BAJA DENGAN MENI BESI
0.100 Kg Meni besi 79,000.00 - 7,900.00 7,900.00
0.020 Kg Pekerja 65,000.00 1,300.00 - 1,300.00
0.200 Oh Tukang cat 80,000.00 16,000.00 - 16,000.00
0.020 Oh Kepala tukang 85,000.00 1,700.00 - 1,700.00
0.010 Oh Mandor 95,000.00 950.00 - 950.00
19,950.00 7,900.00 27,850.00
9 1 M2 PEKERJAAN PENGECATAN BESI HALUS
0.300 Kg Cat besi 79,000.00 - 23,700.00 23,700.00
0.006 Oh Pekerja 65,000.00 390.00 - 390.00
0.060 Oh Tukang cat 80,000.00 4,800.00 - 4,800.00
0.012 Oh Kepala tukang 85,000.00 1,020.00 - 1,020.00
0.006 Oh Mandor 95,000.00 570.00 - 570.00
6,780.00 23,700.00 30,480.00
10 1 M2 PENGECATAN GENTENG (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0.120 Kg Cat dasar 36,363.64 4,363.64 4,363.64
0.300 Kg cat penutup 2x (str. Aga / jarum) 36,363.64 - 10,909.09 10,909.09
0.050 Oh Pekerja 65,000.00 3,250.00 - 3,250.00
0.125 Oh Tukang cat 80,000.00 10,000.00 - 10,000.00
0.013 Oh Kepala tukang 85,000.00 1,062.50 - 1,062.50
0.003 Oh Mandor 95,000.00 237.50 - 237.50
14,550.00 10,909.09 29,822.73
11 1 M2 PENGECATAN LAPANGAN (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP)
0.120 Kg Cat dasar 45,000.00 5,400.00 5,400.00
0.300 Kg cat penutup 2x (str. Technocoat) 45,000.00 - 13,500.00 13,500.00
0.050 Oh Pekerja 65,000.00 3,250.00 - 3,250.00
0.125 Oh Tukang cat 80,000.00 10,000.00 - 10,000.00
Analisa Page 81

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
0.013 Oh Kepala tukang 85,000.00 1,062.50 - 1,062.50
0.003 Oh Mandor 95,000.00 237.50 - 237.50
14,550.00 13,500.00 33,450.00
Analisa Page 82

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
XV PEKERJAAN PELENGKAP
1 1 M2 PASANGAN PAVING STONE PC K. 175 Tbl. 6 cm
1.000 M2 Paving block PC K. 175 60,000.00 - 60,000.00 60,000.00
0.025 M3 Pasir urug 150,000.00 - 3,750.00 3,750.00
1.000 M2 Upah pasang 37,500.00 37,500.00 - 37,500.00
37,500.00 63,750.00 101,250.00
2 1 M2 PASANGAN PAVING STONE PC K. 175 Tbl. 8 cm
1.000 M2 Paving block PC K. 175 80,000.00 - 80,000.00 80,000.00
0.025 M3 Pasir urug 15,300.00 - 382.50 382.50
1.000 M2 Upah pasang 37,500.00 37,500.00 - 37,500.00
37,500.00 80,382.50 117,882.50
3 1 M2 PASANGAN PAVING STONE WARNA K. 175 Tbl 6
1.000 M2 Paving block warna K. 175 68,000.00 - 68,000.00 68,000.00
0.025 M3 Pasir urug 150,000.00 - 3,750.00 3,750.00
1.000 M2 Upah pasang 37,500.00 37,500.00 - 37,500.00
37,500.00 71,750.00 109,250.00
4 1 M2 PASANGAN PAVING STONE WARNA K. 175 Tbl 8
1.000 M2 Paving block warna K. 175 72,000.00 - 72,000.00 72,000.00
0.025 M3 Pasir urug 150,000.00 - 3,750.00 3,750.00
1.000 M2 Upah pasang 37,500.00 37,500.00 - 37,500.00
37,500.00 75,750.00 113,250.00
5 1 M2 PASANGAN PAVING STONE KHUSUS K. 225 Tbl. 6
1.000 M2 Paving block khusus K. 225 77,000.00 - 77,000.00 77,000.00
0.025 M3 Pasir urug 150,000.00 - 3,750.00 3,750.00
1.000 M2 Upah pasang 37,500.00 37,500.00 - 37,500.00
37,500.00 80,750.00 118,250.00
6 1 M2 PASANGAN PAVING STONE KHUSUS K. 225 Tbl. 8
1.000 M2 Paving block khusus K. 225 80,000.00 - 80,000.00 80,000.00
0.025 M3 Pasir urug 150,000.00 - 3,750.00 3,750.00
1.000 M2 Upah pasang 37,500.00 37,500.00 - 37,500.00
37,500.00 83,750.00 121,250.00
7 1 M2 PASANGAN PAVING STONE KHUSUS K. 300 Tbl. 6
1.000 M2 Paving block khusus K. 225 85,000.00 - 85,000.00 85,000.00
0.025 M3 Pasir urug 150,000.00 - 3,750.00 3,750.00
1.000 M2 Upah pasang 37,500.00 37,500.00 - 37,500.00
37,500.00 88,750.00 126,250.00
8 1 M2 PASANGAN PAVING STONE KHUSUS K. 300 Tbl. 8
1.000 M2 Paving block khusus K. 225 90,000.00 - 90,000.00 90,000.00
0.025 M3 Pasir urug 150,000.00 - 3,750.00 3,750.00
1.000 M2 Upah pasang 37,500.00 37,500.00 - 37,500.00
37,500.00 93,750.00 131,250.00
9 1 M3 BETON COR 1:2:3 + M 5 tebal 5 cm
1.000 M3 Beton Cor 1:2:3 883,950.00 - 883,950.00 883,950.00
20.000 M2 Besi M 5 61,255.00 - 1,225,100.00 1,225,100.00
- 2,109,050.00 2,109,050.00
10 1 M3 BETON COR 1:2:3 + M 5 tebal 10 cm
1.000 M3 Beton Cor 1:2:3 883,950.00 - 883,950.00 883,950.00
10.000 M2 Besi M 5 61,255.00 - 612,550.00 612,550.00
- 1,496,500.00 1,496,500.00
11 1 M3 BETON COR 1:2:3 + M 6 tebal 5 cm
1.000 M3 Beton Cor 1:2:3 883,950.00 - 883,950.00 883,950.00
20.000 M2 Besi M 6 81,655.00 - 1,633,100.00 1,633,100.00
Analisa Page 83

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
- 2,517,050.00 2,517,050.00
Analisa Page 84

NO URAIAN H. SATUAN UPAH BAHAN JUMLAH


(RP) (RP) (RP) (RP)
1 2 3 4 5 6
12 1 M3 BETON COR 1:2:3 + M 6 tebal 10 cm
1.000 M3 Beton Cor 1:2:3 883,950.00 - 883,950.00 883,950.00
10.000 M2 Besi M 6 81,655.00 - 816,550.00 816,550.00
- 1,700,500.00 1,700,500.00

Negara, 5 Januari 2015


Kepala Dinas Pekerjaan Umum
Kabupaten Jembrana

Drs. I Gusti Putu Mertadana, M.si


Pembina Utama Muda
Nip. 19581231 198110 1 016
DAFTAR HARGA SATUAN BAHAN BANGUNAN
SEMESTER I TAHUN 2015

NO URAIAN BAHAN SAT HARGA


HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6

1 Abu batu M3 334,500.00 304,000.00


2 Aluminium foil Rol 650,000.00 590,000.00
3 Amplas Lbr 6,000.00 5,400.00
4 Amplas Fleying Will Lbr 6,000.00 5,400.00
5 Amplas Air Lbr 9,000.00 8,000.00
6 Amplas Norton M' 11,000.00 10,000.00
7 Asbes gelombang tebal 4 mm Lbr 40,000.00 36,000.00
8 Asbes Jabesmen 150x105 Lbr 40,000.00 36,000.00
9 Asbes Jabesmen 180x105 Lbr 31,900.00 29,000.00
10 Asbes Jabesmen 240x105 Lbr 56,000.00 50,000.00
11 Asbes Jabesmen 270x105 Lbr 67,000.00 60,000.00
12 Asbes Jabesmen 300x105 Lbr 75,000.00 68,000.00
13 Asphalt Kg 13,750.00 12,500.00
14 Agregat kasar M3 362,375.00 329,000.00
15 Agregat halus M3 306,625.00 278,500.00
16 Agregat A M3 379,500.00 345,000.00
17 Agregat B M3 319,000.00 290,000.00
18 Alat - Alat Bantu Set 186,483.00 169,000.00
19 Baja konstruksi / propil Kg 23,500.00 21,000.00
20 Baja ringan 8 < 10 M UK Profie ( Zinkalum ) M2 342,000.00 310,000.00
21 Baja ringan 8 < 10 M C Profie ( Zinkalum ) M2 275,000.00 250,000.00
22 Baja ringan < 8 M UK Profie ( Zinkalum ) M2 245,000.00 225,000.00
23 Baja ringan < 8 M C Profie ( Zinkalum ) M2 200,000.00 180,000.00
24 Bak air porselint 40 x 40 x 40 Bh 250,000.00 227,000.00
25 Bak air porselint 60 x 60 x 60 Bh 275,000.00 250,000.00
26 Bak air fiber glas 80 x 80 x 1 m Bh 418,125.00 380,000.00
27 Bataco cetak padat besar Bh 2,250.00 2,200.00
28 Bataco cetak padat kecil Bh 2,090.00 2,000.00
29 Batu bata gosok Tumpuk 5 (Mendoyo) Bh 2,400.00 2,200.00
30 Batu bata lokal Tumpuk 4 (Baluk) Bh 1,000.00 900.00
31 Batu bata lokal Tumpuk 5 (Baluk) Bh 800.00 725.00
32 Batu bata lokal Tumpuk 5 (Mendoyo) Bh 1,000.00 1,000.00
33 Batu belah 10 - 15 Cm (manual) M3 269,500.00 245,000.00
34 Batu kali belah / Batu muka M3 259,600.00 236,000.00
35 Batu kali bulat M3 253,000.00 230,000.00
36 Batu kerawang merah 10 x 20 Bh 27,350.00 24,500.00
37 Batu pecah 0,5 - 1 Cm M3 330,000.00 300,000.00
38 Batu pecah 1 - 2 Cm M3 330,000.00 300,000.00
39 Batu pecah 2 - 3 Cm M3 302,500.00 275,000.00
40 Batu pecah 3 - 5 Cm M3 302,500.00 275,000.00
41 Batu pecah 5 - 7 Cm M3 190,000.00 172,500.00
42 Batu seplit jagung Karangasem M3 198,916.00 180,800.00
43 Batu tempel Singaraja M2 68,500.00 62,200.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
44 Baut dan mur Kg 17,600.00 16,000.00
45 Begel U Set 20,900.00 19,000.00
46 Bensin / premium Ltr 9,350.00 8,500.00
47 Besi beton polos (U 24) Kg 13,750.00 12,500.00
-Besi beton 6 mm x 12 m bt 35,695.00 32,450.00
-Besi beton 8 mm x 12 m bt 53,845.00 48,950.00
-Besi beton 10 mm x 12 m bt 76,835.00 69,850.00
48 -Besi beton 12 mm x 12 m bt 113,135.00 102,850.00
-Besi beton 16 mm x 12 m bt 196,020.00 178,200.00
49 Besi ulir (U 32) Kg 16,409.80 14,918.00
-Besi beton 13 mm bt 127,050.00 115,500.00
-Besi beton 16 mm bt 196,020.00 178,200.00
50 Besi Galvanis Kg 35,000.00 31,500.00
51 Besi Siku L 60.60.6 Kg 21,230.00 19,300.00
52 Besi Siku L 50.50.5 Kg 14,520.00 13,200.00
53 Kanstin K-175 BH 60,500.00 55,000.00
54 Bide kulit M2 64,999.00 59,090.00
55 Bide basang M2 65,000.00 29,000.00
56 Bide basang kulit M2 60,000.00 54,500.00
57 Bubungan morando (bulat) Bh 10,000.00 9,000.00
58 Bubungan pres kodok (Jadi Jaya) Bh 10,000.00 9,000.00
59 Bubungan pres mini eks pejaten Bh 2,500.00 2,200.00
60 Bubungan pres pelentong (Jadi Jaya) Bh 9,000.00 8,100.00
61 Bubungan pres pelentong eks pejaten Bh 7,500.00 6,800.00
62 Buis beton diameter 50 Cm Bh 94,775.00 86,000.00
63 Buis beton diameter 60 Cm Bh 105,925.00 96,200.00
64 Buis beton diameter 80 Cm Bh 139,375.00 126,700.00
65 Buis beton diameter 100 Cm Bh 234,150.00 212,800.00
66 Calsiboard 3,5 mm lbr 89,200.00 81,000.00
67 Cat halus setara Emco Lux Kg 94,775.00 86,150.00
68 Cat menie kayu Kg 39,000.00 35,450.00
69 Cat Besi Kg 86,970.00 79,000.00
70 Cat tembok Metrolith Kg 37,296.00 33,900.00
71 Cat tembok Setara Djarum Kg 26,000.00 23,600.00
72 Cat tembok Interior Dulux ( 2,5 lt ) galon 245,300.00 223,000.00
73 Cat tembok Interior Dulux ( 20 lt ) Pail 1,200,000.00 1,090,000.00
74 Cat tembok Interior Mowilex( 2,5 lt ) galon 225,000.00 204,000.00
75 Cat tembok Interior Mowilex ( 20 lt ) Pail 1,850,000.00 1,681,000.00
76 Cat tembok Interior Catylac ( 5 kg ) galon 99,500.00 90,454.00
77 Cat tembok Interior Catylac ( 25 kg ) Pail 485,000.00 440,900.00
78 Cat tembok Interior Vinilex ( 5 kg ) galon 140,000.00 127,000.00
79 Cat tembok Interior Vinilek ( 25 kg ) Pail 700,000.00 636,000.00
80 Cat tembok Interior Metrolite ( 5 lt ) galon 115,000.00 104,500.00
81 Cat tembok Interior Metrolite ( 25 kg ) Pail 550,000.00 500,000.00
82 Cat tembok InteriorMatex ( 4 kg ) galon 104,000.00 94,500.00
83 Cat tembok Interior Matex ( 25 kg ) Pail 227,000.00 206,000.00
84 Cat tembok Interior Profitex ( 25 kg ) Pail 176,537.00 160,000.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
85 Cat tembok Eksterior Dulux ( 2,5 lt ) Pail 237,331.00 215,000.00
86 Cat tembok Eksterior Dulux ( 20 lt ) Pail 2,191,681.35 1,992,000.00
87 Cat tembok Eksterior Mowilex ( 2,5 lt ) galon 275,000.00 250,000.00
88 Cat tembok Eksterior Mowilex ( 20 lt ) Pail 2,305,000.00 2,095,000.00
89 Cat tembok Properti galon 135,000.00 122,000.00
90 Cat tembok Decoplus galon 95,000.00 86,000.00
91 Cat tembok Aries galon 65,000.00 59,000.00
92 Cat tembok Altex galon 110,000.00 100,000.00
93 Cat kayu Altex galon 55,000.00 50,000.00
94 Cat Kayu Dulux 1 kg Kaleng 78,323.00 71,200.00
95 Cat Kayu Mowilex 1kg Kaleng 79,566.00 72,300.00
96 Cat Kayu Catylac 1kg Kaleng 43,202.00 39,200.00
97 Cat Kayu Glotex 1kg Kaleng 45,750.00 41,500.00
98 Cat Kayu Emco 1kg Kaleng 79,000.00 71,800.00
99 Cat Kayu Globe Supergloss Kaleng 28,594.00 25,990.00
100 Clear glass / impra Kg 85,000.00 77,200.00
101 Closet Jongkok INA Bh 195,000.00 177,200.00
102 Egspanoledh Bh 124,322.00 113,000.00
103 Elbow 8" Bh 65,000.00 59,000.00
104 Engsel pintu YES 5 " Ps 75,000.00 68,000.00
105 Engsel pintu kuningan Ps 65,000.00 59,000.00
106 Engsel jendela YES 4 " Ps 66,900.00 60,800.00
107 Engsel Nylon Ps 17,000.00 15,400.00
108 Eternit 100 x 100 tebal 3 mm Lbr 20,000.00 18,000.00
109 Exhaust fan 10" unit 525,000.00 477,000.00
110 Floor drain aluminium Bh 85,000.00 77,200.00
111 Floor drain plastik Bh 30,000.00 27,200.00
112 Filler Kg 5,500.00 5,000.00
113 Genteng keramik Kanmuri Milenio Warna Natural Bh 9,025.00 8,000.00
114 Genteng keramik Kanmuri Milenio Warna Standard Bh 5,114.00 4,600.00
115 Genteng keramik Kanmuri Milenio WarnaSpesial Bh 9,700.00 8,800.00
116 Genteng keramik Kanmuri Milenio Warna Exclusive Bh 20,000.00 18,100.00
117 Genteng keramik Kanmuri Espancia Warna Natural Bh 8,123.00 7,300.00
118 Genteng keramik Kanmuri Espancia WarnaStandard Bh 12,786.00 11,600.00
119 Genteng keramik Kanmuri Espancia Warna Spesial Bh 14,290.00 12,900.00
120 Genteng keramik Kanmuri Espancia Warna Exclusive Bh 15,795.00 14,350.00
121 Genteng keramik M Class Warna Natural Bh 18,000.00 16,300.00
122 Genteng keramik M Class Warna Standard Bh 22,000.00 20,000.00
123 Genteng keramik M Class Warna Spesial Bh 30,000.00 27,200.00
124 Genteng keramik M Class Warna Premium Bh 40,000.00 36,300.00
125 Genteng Knok Natural Bh 65,000.00 59,000.00
126 Genteng Metal Sun Roof Venus - 38,5 x 80 cm S/S Bh 29,500.00 26,800.00
127 Genteng Metal Sun Roof Venus - 38,5 x 80 cm D/S Bh 33,846.00 30,700.00
128 Genteng Metal Sun Roof Pluto - 38,5 x 80 cm S/S Bh 26,325.00 23,900.00
129 Genteng Metal Sun Roof Pluto - 38,5 x 80 cm D/S Bh 29,333.00 26,600.00
130 Genteng Beton Morando Berglzur Bh 3,500.00 3,000.00
131 Genteng Beton Morando Natural Bh 2,256.00 2,000.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
132 Genteng Beton Morando Moner Bh 4,500.00 4,000.00
133 Genteng kodok (Jadi Jaya) Bh 4,102.00 3,725.00
134 Genteng Metal multiroof berpasir Bh 110,000.00 100,000.00
135 Genteng Metal multiroof polos multi colour Bh 93,000.00 84,500.00
136 Genteng Metal Sakura roof Bh 74,000.00 67,000.00
137 Genteng Metal Sakura colour Bh 57,000.00 52,000.00
138 Genteng morando kodok Bh 1,500.00 1,350.00
139 Genteng morando pelentong Bh 1,800.00 1,600.00
140 Genteng pres mini eks Pejaten Bh 2,000.00 1,800.00
141 Genteng pres pelentong eks Pejaten Bh 2,000.00 1,800.00
142 Genteng pres pelentong lokal (Jadi Jaya) Bh 3,500.00 3,000.00
143 Glass block Bh 38,000.00 34,500.00
144 Granular pail 160,000.00 145,000.00
145 Granit Impero 40 x 40 m2 188,000.00 170,000.00
146 Granit Granito 40 x 40 m2 401,400.00 364,000.00
147 Granit Inesia 40 x 40 m2 196,500.00 178,600.00
148 Granit Niro 40 x 40 m2 250,000.00 227,000.00
149 Granit Essenza 40 x 40 m2 230,618.00 209,600.00
150 Granit niro grass 60 x 60 m2 350,000.00 320,000.00
151 Grendel biasa Bh 15,000.00 13,600.00
152 Grendel kecil Bh 17,000.00 15,400.00
153 Grendel tanam Bh 118,500.00 107,700.00
154 Gypsum board M2 87,025.00 79,000.00
155 Hak angin jendela besar Bh 39,025.00 35,400.00
156 Hand sprayer bh 932,418.00 847,000.00
157 HCL kg 26,000.00 23,600.00
158 Infra Mowilek Kg 90,000.00 81,800.00
159 Kaca polos 3 mm M2 98,000.00 89,000.00
160 Kaca polos 5 mm M2 116,552.00 105,000.00
161 Kaca riben 5 mm M2 163,173.00 148,000.00
162 Kaca film hitam m 125,000.00 113,600.00
163 Kait angin jendela kecil Bh 20,000.00 18,100.00
164 Kait angin pintu besar Bh 35,000.00 31,800.00
165 Kait angin pintu kecil Bh 30,000.00 27,200.00
166 Kapur gamping Zak 16,725.00 15,200.00
167 Karet talang lebar 60 C, M' 47,242.00 42,900.00
168 Kawat beton Kg 24,864.00 22,600.00
169 Kawat bronjong Kg 18,026.00 16,300.00
170 Kawat sling diameter 1,5 Cm M' 78,944.00 71,700.00
171 Kawat sling diameter 2,0 Cm M' 141,416.00 128,500.00
172 Kayu bayur balok M3 4,500,000.00 5,000,000.00
173 Kayu bayur papan M3 5,848,577.00 5,200,000.00
174 Kayu bengkarai balok M3 13,292,875.00 12,500,000.00
175 Kayu bingkarai papan M3 14,049,000.00 12,750,000.00
176 Kayu jati balok M3 19,500,000.00 18,000,000.00
177 Kayu jati papan M3 19,900,000.00 18,500,000.00
178 Kayu kamper balok M3 11,122,125.00 8,700,000.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
179 Kayu kamper papan M3 12,878,250.00 9,000,000.00
180 Kayu konstruksi jembatan Ulin M3 19,000,000.00 17,200,000.00
181 Kayu kruing balok M3 7,700,000.00 7,200,000.00
182 Kayu kruing papan M3 9,477,500.00 7,600,000.00
183 Kayu meranti balok ( 6 x 12 ) - Pj = 4 m' M3 5,575,000.00 5,050,000.00
184 Kayu meranti balok ( 8 x 12 ) - Pj = 4 m' M3 4,700,000.00 4,270,000.00
185 Kayu reng Borneo ( 2x3 ) - Pj = 4 m' batang 16,725.00 15,200.00
186 Kayu reng borneo ( 3 x 4 ) - Pj = 4 m' batang 22,300.00 20,200.00
187 Kayu reng Borneo ( 4 x 6 ) - Pj = 4 m' batang 69,688.00 63,350.00
188 Kayu reng Borneo ( 5 x 7 ) - Pj = 4 m' batang 102,580.00 93,250.00
189 Kayu reng Kamper ( 2 x 3 ) - Pj = 4 m' batang 27,000.00 24,500.00
190 Kayu reng Kamper ( 3 x 4 ) - Pj = 4 m' batang 63,555.00 57,700.00
191 Kayu reng Kamper ( 4 x 6 ) - Pj = 4 m' batang 95,000.00 86,300.00
192 Kayu reng Kamper ( 5 x 7 ) - Pj = 4 m' batang 150,525.00 136,800.00
193 Kayu reng Meranti ( 2 x 3 ) - Pj = 4 m' batang 17,000.00 15,400.00
194 Kayu reng Meranti ( 3 x 4 ) - Pj = . 4 m' batang 24,000.00 21,800.00
195 Kayu reng Meranti ( 5 x 7 ) - Pj = 4 m' batang 59,000.00 53,600.00
196 Kayu reng Meranti ( 5 x 10 ) - Pj = 4 m' batang 85,500.00 77,700.00
197 Kayu Galar Borneo ( 5 x 10 ) - Pj = 4 m' batang 60,172.00 54,700.00
198 Kayu Galar Kamper ( 5 x 10 ) -Pj = 4 m' batang 211,850.00 192,500.00
199 Kayu Balok Meranti ( 6 x 12 ) - Pj = 4 m' batang 161,675.00 146,700.00
200 Kayu Balok Meranti ( 8 x 12 ) - Pj = 4 m' batang 185,500.00 168,600.00
201 Kayu Balok Borneo ( 6 x 12 ) - Pj = 4 m' batang 228,296.00 207,500.00
202 Kayu Balok Borneo ( 8 x 12 ) - Pj = 4 m' batang 275,126.00 250,000.00
203 Kayu Balok Kamper ( 6 x 12 ) -Pj = 4 m' batang 353,566.00 321,400.00
204 Kayu Balok Kamper ( 8 x 12 ) -Pj = 4 m' batang 423,700.00 385,000.00
205 Kayu Begesting M3 2,585,000.00 2,350,000.00
206 Kayu Meranti papan M3 6,133,000.00 5,575,000.00
207 Kayu seseh kelas I / super M3 4,150,000.00 3,772,700.00
208 Kayu usuk/reng bayur M3 5,500,000.00 5,000,000.00
209 Kayu usuk/reng bengkarai M3 8,500,000.00 12,700,000.00
210 Kayu usuk/reng kamper M3 9,570,000.00 8,700,000.00
211 Kayu usuk/reng kruing M3 7,900,000.00 7,200,000.00
212 Kayu usuk/reng meranti M3 4,900,000.00 4,450,000.00
213 Keramik 10 x 30 Bh 19,500.00 17,700.00
214 Keramik 10 x 20 warna M2 85,000.00 77,000.00
215 Keramik 20 x 20 anti slip M2 75,000.00 68,100.00
216 Keramik 30 x 30 warna / motif M2 75,000.00 68,100.00
217 Keramik 30 x 30 putih polos M2 65,000.00 59,000.00
218 Keramik 40 x 40 putih polos M2 80,000.00 72,000.00
219 Keramik 40 x 40 warna / motif M2 85,000.00 77,000.00
220 Keramik 40 x 40 warna / motif M2 90,000.00 82,000.00
221 Keramik dinding 10 x 20 M2 70,000.00 63,600.00
222 Keramik dinding 20 x 25 polos M2 80,000.00 72,700.00
223 Keramik dinding 20 x 25 warna M2 85,000.00 77,000.00
224 Keramik Mulia 20 x 20 Warna Tua M2 85,000.00 77,200.00
225 Keramik Mulia 20 x 20 Warna Muda M2 95,000.00 86,300.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
226 Keranjang Bambu Bh 15,000.00 13,600.00
227 Kereta dorong / Arco unit 625,000.00 568,000.00
228 Kloset duduk porselin setara KIA Bh 1,650,000.00 1,500,000.00
229 Kloset jongkok porselin setara KIA Bh 165,000.00 150,000.00
230 Kloset duduk Lexington unit 4,600,000.00 4,180,000.00
231 Kloset duduk Projecta unit 2,300,000.00 2,090,000.00
232 Kloset duduk Sanremo Classic unit 1,500,000.00 1,350,000.00
233 Kloset duduk Granada 3000 CCST unit 1,900,000.00 1,727,000.00
234 Kloset jongkok Toto unit 265,000.00 240,000.00
235 Kloset jongkok Global unit 130,000.00 118,000.00
236 KLINPAK Aluminium Foil JMB Rol 42,500.00 38,600.00
237 KLINPAK Aluminium Foil REF Rol 31,500.00 28,600.00
238 Kont Bondex M2 212,000.00 192,700.00
239 Koral pilihan M3 232,000.00 210,000.00
240 Kran air setara San'ei Bh 90,000.00 81,800.00
241 Kran 1/2 " Bh 85,000.00 77,200.00
242 Kran 3/4 " Bh 105,000.00 95,000.00
243 Kran wastafel Bh 265,000.00 240,000.00
244 Krikil beton M3 302,500.00 275,000.00
245 Kuas biasa Buah 25,000.00 22,700.00
246 Kuas rol Buah 30,000.00 27,200.00
247 Kunci pintu 2 slaag setara SES Bh 400,000.00 363,000.00
248 Kunci pintu 2 slaag setara UNION Bh 217,425.00 197,600.00
249 Kunci pintu KM/WC setara cap KUDA Bh 89,200.00 81,000.00
250 Kunci tanam cap KUDA Bh 99,000.00 90,000.00
251 Kunci tanam cap setara SES Bh 355,000.00 322,700.00
252 Kunci tanam cap UNION Bh 120,000.00 109,000.00
253 Lampu Down ligh Bh 112,000.00 101,000.00
254 Lampu Philips SL Bh 112,000.00 45,000.00
255 Lampu pijar Bh 10,000.00 9,000.00
256 Lampu TL 20 watt Bh 82,000.00 74,500.00
257 Lem pipa kg 93,300.00 84,800.00
258 Lem pipa Bh 12,750.00 11,500.00
259 Limestone M3 275,000.00 250,000.00
260 List plafon 3/6 dipropil kayu bayur M' 14,500.00 13,100.00
261 List plafon 3/6 dipropil kayu kamper M' 22,500.00 21,400.00
262 List plafon 3/6 dipropil kayu kruing M' 14,500.00 13,100.00
263 Lis gypsum m 37,450.00 34,000.00
264 Lumber sering M2 68,500.00 62,250.00
265 Minyak cat (tiner A) Kg 50,000.00 45,400.00
266 Minyak diasel / solar Ltr 8,250.00 7,500.00
267 Minyak diasel / solar (Industri ) Ltr 15,125.00 13,750.00
268 Minyak tanah Ltr 13,200.00 12,000.00
269 Minyak tanah (Industri) Ltr 14,850.00 13,500.00
270 Minyak pelumas / oil Ltr 35,420.00 32,200.00
271 Mowilek Kg 95,000.00 86,300.00
272 Nylon brush bh 62,161.25 56,500.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
273 Pagar BRC T.120 Bh 651,639.00 592,200.00
274 Pagar BRC T.150 Bh 775,000.00 704,500.00
275 Pagar BRC T.175 - 2,4 M Bh 1,072,635.89 975,100.00
276 Pagar BRC T.190 - 2,4 M Bh 1,150,175.83 1,045,000.00
277 Pagar BRC T.90 Bh 583,190.64 530,000.00
278 Paku asbes Kg 35,000.00 31,800.00
279 Paku baja Kg 25,000.00 22,700.00
280 Paku jembatan Kg 43,512.00 39,500.00
281 Paku list Kg 25,000.00 22,700.00
282 Paku reng Kg 35,000.00 31,800.00
283 Paku seng Kg 35,000.00 31,800.00
284 Paku usuk Kg 37,296.75 33,900.00
285 Papan Gypsum Jaya Board(120x240) 9 mm Lbr 115,000.00 104,500.00
286 Papan Gypsum Jaya Star(120x240) 9 mm Lbr 110,000.00 100,000.00
287 Papan Gypsum Jaya Elephant (120x240) 9 mm Lbr 110,000.00 100,000.00
288 Papan Gypsum Jaya Knauf (120x240) 9 mm Lbr 110,000.00 100,000.00
289 Paping stone khusus K. 225 tbl. 8 cm M2 90,000.00 80,000.00
290 Paping stone khusus K. 225 tbl. 6 cm M2 85,000.00 77,000.00
291 Paping stone khusus K. 175 tbl. 8 cm M2 90,000.00 80,000.00
292 Paping stone PC K. 175 tbl. 6 cm M2 65,000.00 60,000.00
293 Paping stone warna K. 175 tbl. 6 cm M2 75,000.00 68,000.00
294 Paping stone warna K. 175 tbl. 8 cm M2 80,000.00 72,000.00
295 Paras batik Bj 17,094.00 15,500.00
296 Paras gosok berserat Gianyar kelas I Bj 16,783.54 15,200.00
297 Paras gosok berserat Gianyar kelas II Bj 15,478.15 14,000.00
298 Paras gosok berserat Gianyar kelas III Bj 14,794.38 13,400.00
299 Paras gosok Silakarang Bj 14,607.89 13,200.00
300 Paras hitam (ex Kerobokan) M2 30,769.82 27,900.00
301 Paras Kerobokan Bj 6,153.96 5,500.00
302 Paras merah (ex Gerana) Bj 18,524.05 16,800.00
303 Paras taro Bj 14,872.71 13,500.00
304 Paras Yogyakarta (Palimanan) 30 x 30 M2 256,415.16 233,000.00
305 Paras Yogyakarta (Palimanan) 40 x 40 M2 276,928.37 251,000.00
306 Pasir eks Karangasem M3 258,500.00 235,000.00
307 Pasir Mundu M3 314,600.00 286,000.00
308 Pasir pasang Penyaringan M3 176,000.00 160,000.00
309 Pasir pasang Pk. Manggis M3 170,500.00 155,000.00
310 Pasir urug / timbunan M3 165,000.00 150,000.00
311 Pasir pasang Peh M3 165,000.00 150,000.00
312 Pasir Beton M3 253,000.00 230,000.00
313 Pernis setara cat dayak Kg 78,000.00 70,000.00
314 Pintu putar chroom bh 85,000.00 77,000.00

315 Pipa PVC SNI S. 12,5 :


- Pipa PVC 1" SNI S.12,5 M' 14,000.00 12,700.00
- Pipa PVC 1 1/2" SNI S.12,5 M' 29,000.00 26,300.00
- Pipa PVC 1 1/4" SNI S.12,5 M' 25,000.00 22,700.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
- Pipa PVC 1/2" SNI S.12,5 M' 7,500.00 6,800.00
- Pipa PVC 10" SNI S.12,5 M' 560,202.00 509,000.00
- Pipa PVC 12" SNI S.12,5 M' 892,078.00 810,000.00
- Pipa PVC 14" SNI S.12,5 M' 1,187,072.00 1,079,000.00
- Pipa PVC 2" SNI S.12,5 M' 33,545.00 30,400.00
- Pipa PVC 2 1/2" SNI S.12,5 M' 48,137.00 43,700.00
- Pipa PVC 3" SNI S.12,5 M' 69,717.00 63,300.00
- Pipa PVC 4" SNI S.12,5 M' 103,085.00 93,700.00
- Pipa PVC 5" SNI S.12,5 M' 136,877.00 124,400.00
- Pipa PVC 6" SNI S.12,5 M' 220,517.00 200,000.00
- Pipa PVC 8" SNI S.12,5 M' 357,381.00 324,800.00
- Pipa PVC 9" SNI S.12,5 M' 451,290.00 410,200.00
- Pipa PVC 11" SNI S.12,5 M' 701,551.00 637,700.00
- Pipa PVC 16" SNI S.12,5 M' 1,499,392.00 1,363,000.00
- Pipa PVC 18" SNI S.12,5 M' 1,891,605.00 1,719,000.00
- Pipa PVC 20" SNI S.12,5 M' 2,372,228.00 2,156,000.00
- Pipa PVC 24" SNI S.12,5 M' 3,854,815.00 3,504,000.00
- Pipa PVC 28" SNI S.12,5 M' 6,318,042.00 5,743,000.00

316 Pipa PVC SNI S. 10 :


- Pipa PVC 1" SNI S.10 M' 14,495.00 13,100.00
- Pipa PVC 1 1/2" SNI S.10 M' 31,220.00 28,300.00
- Pipa PVC 1 1/4" SNI S.10 M' 17,025.00 15,400.00
- Pipa PVC 1/2" SNI S.10 M' 6,304.00 5,700.00
- Pipa PVC 10" SNI S.10 M' 687,124.00 624,000.00
- Pipa PVC 12" SNI S.10 M' 1,094,721.00 995,000.00
- Pipa PVC 14" SNI S.10 M' 1,442,352.00 1,311,000.00
- Pipa PVC 2" SNI S.10 M' 41,532.00 37,000.00
- Pipa PVC 2 1/2" SNI S.10 M' 58,859.00 53,500.00
- Pipa PVC 3" SNI S.10 M' 84,924.00 77,200.00
- Pipa PVC 4" SNI S.10 M' 127,824.00 116,200.00
- Pipa PVC 5" SNI S.10 M' 207,976.00 189,000.00
- Pipa PVC 6" SNI S.10 M' 270,418.00 245,800.00
- Pipa PVC 8" SNI S.10 M' 441,225.00 401,000.00

317 Pipa PVC AW :


- Pipa PVC Rucika 0,5 inci "AW" Ljr 45,676.00 41,500.00
- Pipa PVC Rucika 1 inci "AW" Ljr 80,015.00 72,700.00
- Pipa PVC Rucika 2 inci "AW" Ljr 199,867.00 181,600.00
- Pipa PVC Rucika 4 inci "AW" Ljr 606,519.00 551,300.00
- Pipa PVC Rucika 8 inci "AW" Ljr 1,802,861.00 1,638,000.00
- Pipa PVC Wavin 0,5 inci "AW" Ljr 27,350.00 24,800.00
- Pipa PVC Wavin 0,75 inci "AW" Ljr 37,296.75 33,900.00
- Pipa PVC Wavin 1 inci "AW" Ljr 49,729.00 45,200.00
- Pipa PVC Wavin 2 inci "AW" Ljr 105,674.00 96,000.00
- Pipa PVC Wavin 3 inci "AW" Ljr 205,132.00 186,000.00
- Pipa PVC Wavin 4 inci "AW" Ljr 339,400.00 308,000.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6

318 Pipa PVC Lucky :


- Pipa PVC Lucky 0,5 inci Ljr 13,675.00 12,431.00
- Pipa PVC Lucky 0,75 inci Ljr 20,513.00 18,600.00
- Pipa PVC Lucky 1 inci Ljr 24,615.00 22,300.00
- Pipa PVC Lucky 2 inci Ljr 50,093.00 45,500.00
- Pipa PVC Lucky 3 inci Ljr 96,275.00 87,500.00
- Pipa PVC Lucky 4 inci Ljr 169,279.00 153,800.00

319 Pipa PVC Maspion :


- Pipa PVC Maspion 0,5 inci Ljr 35,000.00 31,800.00
- Pipa PVC Maspion 0,75 inci Ljr 48,000.00 43,600.00
- Pipa PVC Maspion 1 inci Ljr 56,000.00 50,900.00
- Pipa PVC Maspion 2 inci Ljr 146,000.00 132,700.00
- Pipa PVC Maspion 3 inci Ljr 265,000.00 240,900.00
- Pipa PVC Maspion 4 inci Ljr 395,000.00 359,000.00

320 Pipa PVC Unggul :


- Pipa PVC Unggul 0,5 inci Ljr 22,714.00 20,600.00
- Pipa PVC Unggul 0,75 inci Ljr 31,262.00 28,200.00
- Pipa PVC Unggul 1 inci Ljr 42,776.00 38,800.00
- Pipa PVC Unggul 2 inci Ljr 94,141.00 85,500.00
- Pipa PVC Unggul 3 inci Ljr 220,000.00 200,000.00
- Pipa PVC Unggul 4 inci Ljr 307,780.00 279,800.00

321 Pipa Galvanis ( BSA ) :


- Pipa galvanis 1/2" Pj = 6 m Ljr 185,240.00 168,400.00
- Pipa galvanis 1" Pj = 6 m Ljr 329,259.00 299,300.00
- Pipa galvanis 2" Pj = 6 m Ljr 768,313.00 698,000.00
- Pipa galvanis 3/4" Pj = 6 m Ljr 216,445.00 196,700.00

322 Pipa HDPE :


- Pipa HDPE PE 110 mm, PN 10 Bar ( 4" ) Mtr 85,039.00 77,300.00
- Pipa HDPE PE 75 mm, PN 10 Bar ( 3" ) Mtr 56,916.00 51,700.00
- Pipa HDPE PE 50 mm, PN 10 Bar ( 2" ) Mtr 28,765.00 26,150.00
- Pipa HDPE PE 25 mm, PN 16 Bar ( 1/2" ) Mtr 6,776.00 6,160.00

323 Pipa HDPE Accessories :


- Bend 90 HDPE OD 110 mm, PN 10 Bar Bh 371,724.00 337,900.00
- Bend 45 HDPE OD 110 mm, PN 10 Bar Bh 371,724.00 337,900.00
- Bend 90 HDPE OD 75 mm, PN 10 Bar Bh 228,753.00 207,000.00
- Bend 45 HDPE OD 75 mm, PN 10 Bar Bh 228,753.00 207,000.00
- Bend 90 HDPE OD 50 mm, PN 10 Bar Bh 92,931.00 84,000.00
- Bend 45 HDPE OD 50 mm, PN 10 Bar Bh 92,931.00 84,000.00
- Tee Egual DN 110 mm, PN 10 Bar Bh 689,260.00 626,600.00
- Tee Egual DN 75 mm, PN 10 Bar Bh 400,318.00 363,000.00
- Tee Egual DN 50 mm, PN 10 Bar Bh 121,525.00 110,000.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
- Tee Egual DN 25 mm, PN 10 Bar Bh 107,228.00 97,000.00
- Tee Reducer HDPE PE 75 x 50 mm, PN 10 Bar Bh 400,318.00 363,000.00
- Reducer HDPE PE 110 x 50 mm, PN 10 Bar Bh 500,398.00 454,000.00
- Reducer HDPE PE 75 x 50 mm, PN 10 Bar Bh 392,859.00 357,000.00
- Stub End HDPE PE 110 mm Bh 277,219.00 252,000.00
- Stub End HDPE PE 75 mm Bh 171,565.00 155,900.00
- Stub End HDPE PE 50 mm Bh 92,931.00 84,400.00
- Baciking Ring Steel OD 110 mm Bh 135,822.00 12,400.00
- Baciking Ring Steel OD 75 mm Bh 114,376.00 103,000.00
- Baciking Ring Steel OD 50 mm Bh 92,931.00 84,400.00
- Blind Flage Steel DN 75 mm Bh 114,376.00 103,000.00
- Blind Flage Steel DN 50 mm Bh 92,931.00 84,400.00
- Gate Valve OD 110 mm Bh 1,286,737.00 1,160,700.00
- Gate Valve OD 75 mm Bh 1,072,281.00 974,000.00
- Gate Valve OD 50 mm Bh 822,082.00 747,000.00

324 Pintu Air :


Pintu Air ( B =1,40 X H =1,50 ) Unit 20,102,948.00 18,275,000.00
Pintu Air ( B =1,20 X H =1,85 ) Unit 21,538,872.00 29,580,000.00
Pintu Air ( B =1,70 X H =86 ) Unit 14,359,248.00 13,050,000.00
Pintu Air ( B =2.00 X H =2,20 ) Unit 35,898,121.00 31,634,000.00
Pintu Air ( B =0,95 X H =0,70 ) Unit 12,923,323.00 11,748,000.00
Pintu Air ( B =0,50 X H =0,50 ) Unit 11,487,399.00 11,443,000.00

325 BAHAN KONSTRUKSI PINTU AIR


- Besi Siku L 10.10 M' 231,000.00 210,000.00
- Besi Siku l.8.8 M' 371,250.00 337,500.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
- Besi Plate Eser T . 1 Cm 240.120 M2 970,200.00 882,000.00
- Besi UNP 20 Cm M' 433,125.00 393,750.00
- Besi UNP 15 Cm M' 288,750.00 262,500.00
- Besi UNP 10 Cm M' 115,500.00 105,000.00
- Besi Beton 16 MM KG 20,927.00 19,000.00
- Besi Bulat 2 "ST.42+DRAT M' 1,917,300.00 1,743,000.00
- Besi Bulat 1,5ST.42+BRAT M' 1,836,450.00 1,669,500.00
- Bronze KG 202,125.00 183,750.00
- Besi Cor KG 69,300.00 6,300.00
- Roda GIGI PS 2,887,500.00 2,625,000.00
- DRAT Kuningan KG 173,250.00 157,500.00
- MUR 1/2 ", 5/8", 7/8 " Biji 8,662.00 7,800.00
- Gembok BH 28,875.00 26,250.00
- DRUC Klager /Klagger Lones ( Besar/Kecil ) BH 231,000.00 210,000.00
- Angker Balt ( 20 KG ) BH 28,875.00 26,250.00
- Splite Pen/Pengunci/ Stir 2 ET 577,500.00 525,000.00
- Karet Bantalan Khusus BH 866,250.00 787,500.00
- Plat bantalan 30,30 BH 404,250.00 367,500.00
- Rantai besi BH 40,000.00 36,300.00
326 Plamur kayu Kg 30,000.00 27,200.00
327 Plamur tembok Kg 17,500.00 15,000.00
328 Plywood 3 mm Lbr 75,000.00 68,000.00
329 Plywood 6 mm Lbr 95,000.00 86,500.00
330 Plywood 9 mm Lbr 145,000.00 132,000.00
331 Plywood aluminium Lbr 185,000.00 168,000.00
332 Politur ultran Kg 80,000.00 72,700.00
333 Saklar ganda setara Broco Bh 48,000.00 43,600.00
334 Saklar tunggal setara Broco Bh 15,000.00 13,600.00
335 Semen porland (PC) 40 Kg Gresik Zak 61,600.00 56,000.00
336 Semen porland (PC) 50 Kg Gresik Zak 77,000.00 70,000.00
337 Semen porland (PC) 50 Kg Tiga roda Zak 74,800.00 68,000.00
338 Semen Tiga Roda 40 Kg Zak 59,400.00 54,000.00
339 Semen Bozowa Zak 57,200.00 52,000.00
340 Semen Tonasa Zak 55,000.00 50,000.00
341 Seng gelombang BJLS 0,27 Lbr 62,161.00 56,500.00
342 Seng Gelombang 0.30 Lbr 58,080.00 52,800.00
343 Seng Gelombang 0,40 Lbr 41,250.00 37,500.00
344 seng plat BJLS 0,27 mm Lbr 64,647.00 58,700.00
345 Seltif bh 3,729.00 3,400.00
346 Selang spiral bh 55,945.00 50,800.00
347 Selang splingker bh 68,377.00 62,100.00
348 Sock drat 1/2" bh 7,247.00 6,500.00
349 Siphon stenless steel bh 122,650.00 111,500.00
350 Stop kontak setara Broco Bh 33,450.00 30,400.00
351 Stop kran 1/2 " Bh 89,200.00 81,000.00
352 Super teaxwood / melamin Lbr 111,890.00 101,700.00
353 Talang U 6" Pj = 6 m' Bt 125,995.00 114,500.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
354 Talang U 8" Pj = 6 m' Bt 161,675.00 146,700.00
355 Tanah urug pilihan M3 105,674.00 96,000.00
356 Tasirtu M3 105,674.00 96,000.00
357 Tangga besi ( melingkar 0,8m pj.4,3 m ) Set 1,100,254.00 1,000,000.00
358 Teaxwood 4 mm Lbr 118,106.00 107,000.00
359 Tegel PC 20 x 20 abu-abu M2 52,800.00 48,000.00
360 Tegel PC 20 x 20 warna M2 57,200.00 52,000.00
361 Tegel plint 15 x 20 abu-abu M' 46,000.00 41,800.00
362 Tegel porselin 11 x 11 Bh 52,000.00 47,200.00
363 Tegel wafel 20 x 20 abu-abu M2 47,000.00 42,700.00
364 Tegel wafel 20 x 20 warna M2 49,000.00 44,500.00
365 Tempat sabun porselin Bh 74,593.00 67,800.00
366 Terali besi M2 323,238.00 293,800.00
367 Tiang BRC + tutup dan baut T.120 diameter 1 1/2" Bh 153,786.00 139,800.00
368 Tiang BRC + tutup dan baut T.150 diameter 1 1/2" Bh 225,023.00 204,500.00
369 Tiang BRC + tutup dan baut T.150 diemeter 2" Bh 315,157.00 286,500.00
370 Tiang BRC + tutup dan baut T.175 diameter 2" Bh 337,535.00 306,580.00
371 Tiang BRC + tutup dan baut T.190 diemeter 2" Bh 390,372.00 234,500.00
372 Tiang BRC + tutup dan baut T.90 diameter 1 1/2" Bh 240,253.00 218,000.00
373 Ucklip BRC Bh 684,395.00 622,000.00
374 Urinoir pot setara KIA Bh 950,000.00 863,600.00
375 Wastafel San Remo 55 Lava & Pedestial unit 750,907.00 682,500.00
376 Wastafel Studio 3000 Lava & Pedestial unit 554,478.00 504,000.00
377 Wastafel Studio 50 Lava & Pedestial unit 293,028.00 266,300.00
378 Wastafel lengkap setara KIA Bh 621,612.00 565,000.00
379 Water Frofing Ltr 95,000.00 86,363.64
380 Wood Filler Kg 40,000.00 36,363.64
381 Wire Mesh M.5 M2 60,500.00 55,000.00
382 Wire Mesh M.6 M2 82,500.00 75,000.00
383 Wire Mesh M.7 M2 93,500.00 85,000.00

384 Pipa Besi :


a. MEDIUM ( B )
Black :
- Black 1/2" lonjor 123,949.00 112,600.00
- Black 3/4" lonjor 153,165.00 139,200.00
- Black 1" lonjor 233,850.00 212,500.00
- Black 1 1/4" lonjor 303,346.00 275,500.00
- Black 1 1/2" lonjor 359,292.00 326,600.00
- Black 2" lonjor 528,494.00 480,400.00
- Black 2 1/2" lonjor 681,287.00 619,300.00
- Black 3" lonjor 834,203.00 758,000.00
- Black 4" lonjor 1,219,976.00 1,109,000.00
- Black 5" lonjor 1,580,263.00 1,436,000.00
- Black 6" lonjor 1,909,469.00 1,735,000.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
Galv :
- Galv 1/2" lonjor 155,651.00 141,500.00
- Galv 3/4" lonjor 192,078.00 174,600.00
- Galv 1" lonjor 294,395.00 267,600.00
- Galv 1 1/4" lonjor 380,426.00 345,000.00
- Galv 1 1/2" lonjor 451,290.00 410,000.00
- Galv 2" lonjor 662,887.00 602,600.00
- Galv 2 1/2" lonjor 854,592.00 776,900.00
- Galv 3" lonjor 1,046,298.00 951,000.00
- Galv 4" lonjor 1,532,026.00 1,392,750.00
- Galv 5" lonjor 1,982,446.00 1,802,200.00
- Galv 6" lonjor 2,398,056.00 2,180,000.00

b. MEDIUM ( A )
Black :
- Black 1/4" lonjor 81,058.00 73,600.00
- Black 3/8" lonjor 99,955.00 90,800.00
- Black 1/2" lonjor 147,570.00 134,000.00
- Black 3/4" lonjor 190,586.00 173,000.00
- Black 1" lonjor 292,157.00 265,500.00
- Black 1 1/4" lonjor 386,394.00 351,000.00
- Black 1 1/2" lonjor 450,917.00 410,000.00
- Black 2" lonjor 612,536.00 556,800.00
- Black 2 1/2" lonjor 804,242.00 731,000.00
- Black 3" lonjor 1,038,590.00 944,000.00
- Black 4" lonjor 1,500,075.00 1,363,000.00
- Black 5" lonjor 1,954,225.00 1,776,000.00
- Black 6" lonjor 2,322,344.00 2,111,000.00
- Black 6" lonjor 3,628,227.00 3,298,000.00
- Black 10" lonjor 5,245,912.00 4,769,000.00
- Black 12" lonjor 6,239,994.00 5,672,000.00

Galv :
- Galv 1/2" lonjor 185,240.00 168,400.00
- Galv 3/4" lonjor 216,445.00 196,700.00
- Galv 1" lonjor 367,124.00 333,700.00
- Galv 1 1/4" lonjor 484,857.00 440,700.00
- Galv 1 1/2" lonjor 565,543.00 514,000.00
- Galv 2" lonjor 763,313.00 694,000.00
- Galv 2 1/2" lonjor 1,008,752.00 917,000.00
- Galv 3" lonjor 1,302,651.00 1,184,200.00
- Galv 4" lonjor 1,880,999.00 1,710,000.00
- Galv 5" lonjor 2,425,034.00 2,204,000.00
- Galv 6" lonjor 2,913,124.00 2,648,000.00
- Galv 6" lonjor 4,551,322.00 4,137,565.45
- Galv 10" lonjor 6,621,292.00 6,019,356.36
- Galv 12" lonjor 7,876,451.00 7,160,410.00

385 Beton ready Mix K 175 M3 1,139,160 1,035,600.00


386 Beton ready Mix K 225 M3 1,452,000 1,320,000.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
387 Beton ready Mix K 250 M3 1,518,000 1,380,000.00
388 Beton ready Mix K 300 M3 1,650,000 1,500,000.00
389 Beton ready Mix K 350 M3 1,716,000 1,560,000.00
390 Beton ready Mix K 400 M3 1,782,000 1,620,000.00
391 Cat Aga Genteng Kg 40,000 36,363.64
392 Lem Fox BK 15,000 13,636.36
393 Canstein Pres 35/60 K. 125 BH 50,175 45,600.00
394 Ijuk Kg 17,875 15,300.00
395 Bambu BT 16,725 15,200.00

Jasa Konsultasi

1 Perlengkapan Kantor :
a.sewa Komputer Laptop Rp/Bulan 600,000.00 545,000.00
b.SewaKomputer Destop PC Rp/Bulan 450,000.00 410,000.00
c.Sewa Printer Rp/Bulan 300,000.00 272,500.00
d.Sewa LCD Rp/Hari 100,000.00 90,000.00

2 Kendaraan Kerja
a.Sewa Kendaraan Roda 4 Unit/bulan 5,500,000.00 5,000,000.00
b.Sewa Kendaraan Roda 2 Unit/Bulan 600,000.00 545,000.00

3 Perlengkapan Khusus :
a. Sewa Alat Ukur Digital/GPS dan kelengkapannya Unit/Bulan 750,000.00 681,000.00
b.Sewa Alat Ukur Theodolite Unit/Bulan 2,500,000.00 2,272,700.00
c.Sewa Kamera Digital Unit/Bulan 200,000.00 181,800.00

4. Biaya Pelaporan :
a.Laporan Pendahuluan/Inception report Rp/Buku 100,000.00 90,900.00
b.Laporan Fakta Analisa/Interim Report Rp/Buku 125,000.00 113,600.00
c.Laporan Rancangan Rencana/draf Final report Rp/Buku 150,000.00 136,300.00
d.Laporan rencana/Final report Rp/Buku 150,000.00 136,300.00
e.Laporan ringkasan Eksekutif/Executif Rp/Buku 30,000.00 27,000.00
Summary
ff.Rancangan Peraturan Daerah/Bupati Rp/Buku 50,000.00 45,400.00
g.Album Peta Berwarna/ A.3 Rp/Buku 200,000.00 181,800.00
h.Album Peta Berwarna /A 2 Rp/buku 500,000.00 454,500.00
i.Album Peta Berwarna/A 1 Rp/buku 750,000.00 681,800.00
j.Album Peta Tematik Rp/Buah 300,000.00 272,700.00
k.Peta Display AO Rp/Keping 350,000.00 318,000.00
l.Peta Berfigura Rp/buah 400,000.00 3,636.00
m.Back Up Laporan dan Peta dalam CD Rp/Kepeing 25,000.00 22,700.00
n.CD File Pembuatan Peta, Dokumentasi dan Kegiatan Rp/ Keping 25,000.00 22,700.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
5 Biaya Komunikasi Orang/Bula 25,000.00 22,700.00
6 Biaya Survey Orang/Hari 250,000.00 227,000.00
7 Biaya Pengadaan Peta Citra Satelit Rp/KM2 300,000.00 272,700.00

Negara, 5 Januari 2015

Kepala Dinas Pekerjaan Umum


Kabupaten Jembrana

Drs. I Gusti Putu Mertadana, M.si


Pembina Utama Muda
Nip. 19581231 198110 1 016
DAFTAR HARGA SATUAN UPAH KERJA
SEMESTER I / 2015

NO NAMA DAN UPAH PEKERJA SATUAN HARGA KETERANGAN


1 2 3 4 5

A. UPAH :
1 Pekerja OH 65,000.00
2 Pekerja trampil OH 70,000.00
3 Mandor OH 95,000.00
4 Tukang kayu OH 85,000.00
5 Tukang batu OH 85,000.00
6 kepala tukang kayu OH 90,000.00
7 Kepala tukang batu OH 90,000.00
8 Tukang besi OH 85,000.00
9 Kepala tukang besi OH 90,000.00
10 Tukang cat OH 80,000.00
11 Kepala tukang cat OH 85,000.00
12 Tukang style bali OH 90,000.00
13 Kepala tukang style bali OH 95,000.00
14 Tukang Las OH 85,000.00
15 Kepala Tukang Las OH 90,000.00
16 Peladen style bali OH 85,000.00
17 Operator terampil OH 110,000.00
18 Operator kurang terampil OH 85,000.00
19 Pembantu operator OH 80,000.00
20 Sopir terampil OH 85,000.00
21 Pembantu sopir / kernet OH 75,000.00
22 Upah pasang kunci pintu Unit 40,000.00
23 Upah pasang instalsi listrik Unit 40,000.00
24 Upah pasang instalasi air M' 10,000.00
25 Upah pasang kloset jongkok Unit 60,000.00
26 Upah pasang kloset duduk Unit 160,000.00
27 Upah pasang bak air Unit 60,000.00
28 Upah pasang urinoir pot Unit 95,000.00
29 Upah pasang washtafel Unit 100,000.00
30 Upah pasang paping stone M2 40,000.00
31 Upah pasang batu bata dan paras kombinasi M2 120,000.00
32 Upah pasang paras hitam kombinasi M2 120,000.00
33 Upah pasang I bh kran dan 1 m pipa pvc Unit 15,000.00
34 Upah Kerja Konstruksi LS 2,750,000.00
35 Upah Kerja Mesin LS 1,650,000.00
36 Upah Kerja Konstruksi Pintu Air > 100 cm 2,750,000.00
37 Upah Kerja Konstruksi Pintu Air < 100 cm 1,650,000
38 Upah Kerja mesin > 100 cm 1,750,000
39 Upah Kerja Mesin < 100 cm 1,000,000
40 Ongkos Pemasangan Pintu air 1,000,000
41 Ongkos Pembongkaran pintu air 600,000
42 Transport mobilisasi pintu air 600,000

B. ALAT :
1 Aspahalt Sprayer 1000 Liter Jam 130,000.00
2 Buldozer 100 Hp Jam 565,000.00
3 Buldozer 65 Hp Jam 462,000.00
4 Concrete Mixer 0,3 - 0,6 M3 Jam 130,000.00
5 Concrete Vibrator Jam 50,000.00
6 Grader 110 Hp Jam 470,000.00
NO NAMA DAN UPAH PEKERJA SATUAN HARGA KETERANGAN
1 2 3 4 5
7 Mesin Penyaring Jam 90,000.00
8 Mesin Gilas 3 Roda 6-8 ton Jam 150,000.00
9 Mesin Gilas Tandem 8 - 10 ton Jam 175,000.00
10 Mesin Gilas Tandem 2,5 ton Jam 125,000.00
11 Mesin Gilas Roda 8 - 15 ton Jam 250,000.00
12 Pemecah Batu Jam 288,500.00
13 Pompa Air f 50 mm Jam 32,000.00
14 Pompa Air f 40 mm Jam 32,000.00
15 Roller Vibrator 1,0 ton Jam 28,500.00
16 Stamper Vibrating Plate 1 Hp Jam 23,000.00
17 Truck Tangki Air 115 Hp Jam 67,000.00
18 Truck Bak Terbuka 3,5 ton / 115 Hp Jam 67,000.00
19 Whell Loader Jam 545,000.00
20 Kompresor Jam 130,000.00
21 Asphalt Mixing Plant Jam 3,864,000.00
22 Generator Set Jam 288,500.00
23 Dump Truck 5 ton / 145 Hp Jam 250,000.00
24 Dump Truck 10 ton Jam 288,500.00
25 Asphalt Finisher Jam 1,603,000.00
26 Pneumatic Tire Roller Jam 834,000.00
27 Asphalt Sprayer Jam 129,000.00
28 Vibrating Compactor Jam 84,000.00
29 Truck Mixer Jam 125,000.00

Negara, 5 Januari 2015

Kepala Dinas Pekerjaan Umum


Kabupaten Jembrana

Drs. I Gusti Putu Mertadana, M.si


Pembina Utama Muda
Nip. 19581231 198110 1 016
DAFTAR ANALYSA BIAYA KONSTRUKSI SNI
TAHUN ANGGARAN 2015 ( SEMESTER I )

JUMLAH
NO U RAIAN HAL.
(RP)
1 2 3 4

I PEKERJAAN PERSIAPAN
1 1 M' PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 M 3,971,600.50 1
2 1 M' PAGAR SEMENTARA DARI KAWAT BERDURI TINGGI 1,8 M 3,824,723.00 1
3 1 M' PEMASANGAN BOUWPLANK 45,211.00 1
4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT 7,831,530.00 1
5 1 M2 PEMBUATAN RUMAH JAGA / KONSTRUKSI KAYU 13,015,860.00 2
6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERALATAN 11,250.00 2
7 1 M2 PEMBUATAN BEDENG BURUH 6,132,315.00 2
8 1 M2 PEMBUATAN BAK ADUKAN ( 40X50X20) CM 148,786.50 2
9 1 M2 PEMBUATAN STEGGER DARI BAMBU UKURAN (40 X 50 X 20) CM 39,960.00 2
10 1 M2 PEMBUATAN JALAN SEMENTARA 123,525.00 2
11 1 M3 BONGKARAN BETON BERTULANG 269,990.00 2
12 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH 176,490.00 2
13 1 M' PASANG PAGAR BETON PRACETAK (5 X 50 X 213) CM 342,050.00 3

II PEKERJAAN TANAH
1 1 M3 GALIAN TANAH BIASA SEDALAM 1 METER 51,125.00 3
2 1 M3 GALIAN TANAH BIASA SEDALAM 2 METER 62,775.00 3
3 1 M3 GALIAN TANAH BIASA SEDALAM 3 METER 74,615.00 3
4 1 M3 GALIAN TANAH KERAS SEDALAM 1 METER 68,040.00 3
5 1 M3 GALIAN TANAH CADAS SEDALAM 1 METER 103,200.00 3
6 1 M3 GALIAN TANAH LUMPUR SEDALAM 1 METER 82,275.00 3
7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER 3,725.00 3
8 1 M3 PEMBUANGAN TANAH SEJAUH 15 METER 22,400.00 3
9 1 M3 URUGAN KEMBALI TANAH BIASA 17,041.67 3
10 1 M3 URUGAN KEMBALI TANAH KERAS 22,680.00 3
11 1 M3 PEMADATAN TANAH 37,250.00 4
12 1 M3 URUGAN PASIR 200,450.00 4
13 1 M3 PEMASANGAN LAPISAN IJUK 102,975.00 4
14 1 M3 URUGAN TASIRTU 133,825.00 4
15 1 M3 URUGAN TANAH URUG 133,825.00 4
16 1 M3 PEMBUATAN JALAN SEMENTARA, TBL. 25 CM 153,200.00 4

III PEKERJAAN PONDASI


1 1 M3 PASANG PONDASI BATU KOSONG ( ANSTAMPING ) 439,065.00 4
2 1 M3 PASANG PONDASI BATU KALI 1 Pc : 3 Ps 855,100.00 4
3 1 M3 PASANG PONDASI BATU KALI 1 Pc : 4 Ps 800,500.00 4
4 1 M3 PASANG PONDASI BATU KALI 1 Pc : 5 Ps 752,965.00 5
5 1 M3 PASANG PONDASI BATU KALI 1 Pc : 6 Ps 730,360.00 5
6 1 M3 PASANG PONDASI BATU KALI 1 Pc : 8 Ps 716,621.20 5
7 1 M3 PASANG PONDASI SUMURAN DIAMETER 1 M 791,905.00 5
8 1 M' PEMBANGUNAN TIANG PANCANG 40 X 40 CM BETON BERTULANG 1,129,336.00 5
9 1 M' PEMBANGUNAN TIANG PANCANG 35 X 35 CM BETON BERTULANG 1,052,255.00 6
10 1 M3 Memasang Pondasi Siklop, 60 % Beton 1 :2 : 3 Kr dan 40% Batu Kali 791,905.00 6

IV PEKERJAAN DINDING
1 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA , 1 PC : 2 PS 266,350.00 6
2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA , 1 PC : 3 PS 254,165.00 6
3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA , 1 PC : 4 PS 245,675.00 6
4 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA ,1 PC : 5 PS 241,700.00 7
5 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 6 PS 241,220.00 7
JUMLAH
NO U RAIAN HAL.
(RP)
1 2 3 4
6 1 M2 PASANGAN BATACO / HB / CONE BLOCK (HB.20/CB20) 1 Pc : 3 Ps 79,489.20 7
7 1 M2 PASANGAN BATACO / HB / CONE BLOCK (HB.20/CB20) 1 Pc : 4 Ps 78,089.20 7
8 1 M2 PASANGAN BATACO / HB / CONE BLOCK (HB.15/CB15) 1 Pc : 4 Ps 96,220.00 7
9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 2 PS 128,785.00 7
10 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 3 PS 122,843.00 8
11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 4 PS 119,530.00 8
14 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 5 PS 117,452.00 8
15 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 6 PS 116,488.00 8
16 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 8 PS 114,175.00 9
17 1 M2 PASANGAN DINDING ROSTER 10 X 10 X 20 CM 241,550.00 9
18 1 M2 PASANGAN DINDING BATA BERONGGA (12 X 11 X 24 CM) 1 PC : 3 PS 76,050.00 9
19 1 M2 PASANGAN DINDING BEDEG, RANGKA KAYU 183,506.60 9

V PEKERJAAN PLESTERAN
1 1 M2 PLESTERAN 1 PC : 1 PS, TEBAL 15 MM 60,490.60 9
2 1 M2 PLESTERAN 1 PC : 2 PS, TEBAL 15 MM 54,038.60 9
3 1 M2 PLESTERAN 1 PC : 3 PS, TEBAL 15 MM 51,316.40 9
4 1 M2 PLESTERAN 1 PC : 4 PS, TEBAL 15 MM 49,401.00 9
5 1 M2 PLESTERAN 1 PC : 5 PS, TEBAL 15 MM 48,392.60 10
6 1 M2 PLESTERAN 1 PC : 6 PS, TEBAL 15 MM 47,552.40 10
7 1 M2 PLESTERAN 1 PC : 7 PS, TEBAL 15 MM 47,115.40 10
8 1 M2 PLESTERAN 1 PC : 8 PS, TEBAL 15 MM 46,678.40 10
9 1 M2 PLESTERAN PONDASI 1 PC : 2 PS, TEBAL 20 MM 72,319.80 10
10 1 M2 PLESTERAN PONDASI 1 PC : 3 PS, TEBAL 20 MM 67,835.20 10
11 1 M2 PLESTERAN PONDASI 1 PC : 4 PS, TEBAL 20 MM 66,058.00 10
12 1 M2 PLESTERAN PONDASI 1 PC : 5 PS, TEBAL 20 MM 64,791.80 11
13 1 M2 PLESTERAN PONDASI 1 PC : 6 PS, TEBAL 20 MM 63,593.20 11
14 1 M2 PLESTERAN SKONENG 1 PC : 2 PS, LEBAR 10 MM 46,935.00 11
15 1 M2 PLESTERAN GRANIT 1 PC : 2 GRANIT, TEBAL 10 MM 201,630.00 11
16 1 M2 PLESTERAN TERASO 1 PC : 2 TERASO, TEBAL 10 MM 186,630.00 11
17 1 M2 PLESTERAN CIPRAT / KAMPROT 1 PC : 2 PS. 37,783.00 11
18 1 M2 PLESTERAN SIAR 1 PC : 2 PS ( ACIAN ) 46,721.00 11
19 1 M2 ACIAN PC 27,900.00 12

VI PEKERJAAN KAYU
1 1 M3 PEKERJAAN KUSEN PINTU DAN JENDELA KAMPER 11,736,511.36 12
2 1 M3 PASANGAN KUSEN PINTU DAN JENDELA KAYU JATI 21,966,511.36 12
3 1 M3 PASANGAN KUSEN PINTU DAN JENDELA KAYU BENGKIRAI 15,916,511.36 12
4 1 M3 PEKERJAAN KUSEN PINTU DAN JENDELA KERUING 10,086,511.36 12
5 1 M3 PEKERJAAN KUSEN PINTU DAN JENDELA BAYUR 7,666,511.36 12
6 1 M2 PEKERJAAN PINTU KLAMP KAYU KAMPER 566,568.18 13
7 1 M2 PEKERJAAN PINTU PANEL KAYU BAYUR 566,568.18 13
8 1 M2 PEKERJAAN PINTU PANEL KAYU KAMPER 718,568.18 13
9 1 M2 PEKERJAAN PINTU PANEL KAYU JATI 1,098,568.18 13
10 1 M2 PEKERJAAN PINTU DAN JENDELA KACA KAYU BAYUR 512,768.18 13
11 1 M2 PEKERJAAN PINTU DAN JENDELA KACA KAYU KAMPER 603,968.18 14
12 1 M2 PEKERJAAN PINTU DAN JENDELA KACA KAYU KERUING 570,368.18 14
13 1 M2PEKERJAAN PINTU DAN JENDELA KACA KAYU JATI 831,968.18 14
14 1 M2 PEKERJAAN PINTU PLYWOOD RANGKAP, RANGKA KAYU KAMPER 546,997.18 14
15 1 M2 PEKERJAAN PINTU PLYWOOD RANGKAP, RANGKA KAYU KERUING 511,997.18 15
16 1 M2 PEKERJAAN PINTU PLYWOOD RANGKAP, RANGKA KAYU BAYUR 451,997.18 15
17 1 M2 PEKERJAAN PINTU TEAKWOOD RANGKAP, RANGKA KAYU KAMPER 585,997.18 15
18 1 M2 PEKERJAAN PINTU TEAKWOOD RANGKAP, RANGKA KAYU KERUING 550,997.18 15
19 1 M2 PEKERJAAN PINTU TEAKWOOD RANGKAP, RANGKA KAYU BAYUR 490,997.18 15
20 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA KONVENSIONAL
KAYU KAMPER BENTANG 6 M' 11,451,840.00 15
21 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA KONVENSIONAL
KAYU KERUING BENTANG 6 M' 9,790,080.00 16
JUMLAH
NO U RAIAN HAL.
(RP)
1 2 3 4
22 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA KONVENSIONAL
KAYU SESEH KELAS I BENTANG 6 M' 6,020,050.00 16
23 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA EXPOSE KAMPER 12,389,805.00 16
24 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA EXPOSE JATI 22,619,805.00 16
25 1 M2 PASANG USUK DAN RENG KAYU KAMPER ( ATAP GENTENG ) 174,265.00 16
26 1 M2 PASANG USUK DAN RENG KAYU KRUING ( ATAP GENTENG ) 147,865.00 16
27 1 M2 PASANG USUK DAN RENG KAYU BAYUR ( ATAP GENTENG ) 109,145.00 17
28 1 M2 PASANG USUK DAN RENG KAYU KAMPER ( ATAP GENTENG BETON ) 208,765.00 17
29 1 M2 PASANG PLAFOND 1 X 1 M ASBES SEMEN tebal 4 mm 28,937.00 17
30 1 M2 PASANG PLAFOND 1 X 1 M ( AKUSTIK 30 X 30 ) 38,785.00 17
31 1 M2 PASANG PLAFOND TRIPLEK 1,20 X 2,40 M, TEBAL 4 MM 42,556.00 17
32 1 M2 PASANG PLAFOND LAMBIZIRING KAYU JATI, TEBAL 9 MM 330,045.50 17
33 1 M2 PASANG PLAFOND LAMBIZIRING KAYU KAMPER, TEBAL 9 MM 187,545.50 17
34 1 M2 PASANG PLAFOND GYPSUM BOARD 1,2 X 2,4 TEBAL 9 MM 43,929.00 18
35 1 M' PASANG LIST PLAFOND GYPSUM PROFIL 46,012.50 18
36 1 M' PASANG LIST PLAFOND KAYU PROFIL KAMPER 33,885.00 18
37 1 M' PASANG LIST PLAFOND KAYU PROFIL BAYUR 25,170.00 18
38 1 M2 PASANG RANGKA PLAFOND AKUSTIK 30 X 30 CM KAYU KAMPER 291,597.50 19
39 1 M2 PASANG RANGKA PLAFOND ETERNIT 0,50 X 1 M KAYU KAMPER 185,415.00 19
40 1 M2 PASANG RANGKA PLAFOND ETERNIT 0,50 X 1 M KAYU KERUING 162,315.00 19
41 1 M2 PASANG RANGKA PLAFOND ETERNIT 0,50 X 1 M KAYU BAYUR 128,435.00 19
42 1 M2 PASANG RANGKA PLAFOND 30 X 60 CM KAYU KAMPER 191,910.00 19
43 1 M2 PASANG RANGKA PLAFOND 30 X 60 CM KAYU KERUING 167,460.00 19
44 1 M2 PASANG RANGKA PLAFOND 30 X 60 CM KAYU BAYUR 131,600.00 19
45 1 M' PASANG LISPLANG 3 X 20 CM, KAYU KAMPER 124,565.00 20
46 1 M' PASANG LISPLANG 3 X 30 CM, KAYU KAMPER 139,865.00 20
47 1 M' PASANG LISPLANG 2 X (3 x 20) CM, KAYU KAMPER 172,783.00 20
48 1 M' PASANG LISPLANG 3 X 20 CM, KAYU KERUING 109,445.00 20
49 1 M' PASANG LISPLANG 2 X (3 x 20) CM, KAYU KERUING 152,483.00 20
50 1 M' PASANG LISPLANG (3 X 20) CM KAYU BAYUR 83,525.00 20
51 1 M' PASANG LISPLANG 2 X (2 X 20) CM KAYU BAYUR 67,278.00 21
52 1 M2 PAS. DINDING PEMISAH / SKETSEL R. KAMPER + PLYWOOD 3 MM RANGKA 373,661.36 21
53 1 M2 PAS. DINDING PEMISAH / SKETSEL R. KERUING + PLYWOOD 3 MM RANGK 331,661.36 21
54 1 M2 PAS. DINDING PEMISAH / SKETSEL R. BAYUR + PLYWOOD 3 MM RANGKAP 270,061.36 21
55 1 M2 PAS. DINDING PEMISAH / SKETSEL R. KAMPER + TEAKWOOD 3 MM RANG 407,201.36 21
56 1 M2 PASANG DINDING LAMBRIZIRING KAMPER 281,980.00 21
57 1 M2 PASANG DINDING LAMBRIZIRING PLYWOOD ( 1,2 X 2,4 ) M 60,590.00 21
58 1 M2 PASANG DINDING BILIK BAMBU R. KAYU BAYUR 127,065.30 21

VII PEKERJAAN BETON


1 1 M3 MEMBUAT BETON 1 PC : 2 PS : 4. KRL ( K 150 ) 836,650.00 21
2 1 M3 MEMBUAT BETON 1 PC : 3 PS : 5 KRL ( K 125 ) 797,150.00 22
3 1 M3 MEMBUAT BETON 1 PC : 2 PS : 3 Bt. Pc ( K. 175 ) 883,950.00 22
4 1 M3 MEMBUAT BETON ( K 225 ) 1,020,850.00 22
5 1 M3 MEMBUAT BETON KEDAP AIR DENGAN ADITIVE ( K 250 ) 1,338,775.00 22
6 1 M' MEMBUAT WATER STOP LEBAR 150 MM 28,005.00 22
7 1 M' MEMBUAT WATER STOP LEBAR 200 MM 33,255.00 22
8 1 M' MEMBUAT WATER STOP LEBAR 230 - 320 MM 38,505.00 23
9 10 KG PEMBESIAN DENGAN BESI POLOS 146,150.00 23
10 10 KG PEMBESIAN DENGAN BESI ULIR 171,539.00 23
12 1Kg M2 PASANG JARING KAWAT BAJA / WIRE MESH 61,255.00 23
13 1 M2 PASANG BEGESTING UNTUK PONDASI 164,250.00 23
14 1 M2 PASANG BEGESTING UNTUK SLOOFT 176,000.00 24
15 1 M2 PASANG BEGESTING UNTUK KOLOM 260,375.00 24
16 1 M2 PASANG BEGESTING UNTUK BALOK 260,375.00 24
17 1 M2 PASANG BEGESTING UNTUK LANTAI 321,175.00 24
18 1 M2 PASANG BEKISTING UNTUK DINDING 267,275.00 24
19 1 M2 PASANG BEGESTING UNTUK TANGGA 236,875.00 25
20 1 M2 PASANG JEMBATAN COR BETON 103,930.00 25
21 1 M3 MEMBUATPONDASI BETON BERTULANG (60 KG BESI + BEKESTING) 2,866,280.00 25
JUMLAH
NO U RAIAN HAL.
(RP)
1 2 3 4
22 1 M3 MEMBUATPONDASI BETON BERTULANG (80 KG BESI + BEKESTING) 3,116,280.00 25
23 1 M3 MEMBUATPONDASI BETON BERTULANG (100 KG BESI + BEKESTING) 3,366,280.00 26
24 1 M3 MEMBUATPONDASI BETON BERTULANG (125 KG BESI + BEKESTING) 3,954,411.00 26
25 1 M3 MEMBUAT PONDASI BETON BERTULANG (150 KG BESI + BEKESTING) 4,372,115.00 26
26 1 M3 MEMBUAT PONDASI BETON BERTULANG (175 KG BESI + BEKESTING) 4,745,065.00 27
27 1 M3 MEMBUAT PONDASI BETON BERTULANG (200 KG BESI + BEKESTING) 5,118,015.00 27
28 1 M3 MEMBUAT SLOOF BETON BERTULANG (60 KG BESI + BEKESTING) 3,089,180.00 27
29 1 M3 MEMBUAT SLOOF BETON BERTULANG (80 KG BESI + BEKESTING) 3,351,680.00 28
30 1 M3 MEMBUAT SLOOF BETON BERTULANG (90 KG BESI + BEKESTING) 3,482,930.00 28
31 1 M3 MEMBUAT SLOOF BETON BERTULANG (100 KG BESI + BEKESTING) 3,614,180.00 28
32 1 M3 MEMBUAT SLOOF BETON BERTULANG (125 KG BESI + BEKESTING) 3,942,305.00 29
33 1 M3 MEMBUAT SLOOF BETON BERTULANG (150 KG BESI + BEKESTING) 4,651,265.00 29
34 1 M3 MEMBUAT SLOOF BETON BERTULANG (200 KG BESI + BEKESTING) 5,434,460.00 29
35 1 M3 MEMBUAT KOLOM BETON BERTULANG (80 KG BESI + BEKESTING) 4,540,680.00 30
36 1 M3 MEMBUAT KOLOM BETON BERTULANG (90 KG BESI + BEKESTING) 4,671,930.00 30
37 1 M3 MEMBUAT KOLOM BETON BERTULANG (100 KG BESI + BEKESTING) 4,803,180.00 30
38 1 M3 MEMBUAT KOLOM BETON BERTULANG (125 KG BESI + BEKESTING) 5,448,667.50 31
39 1 M3 MEMBUAT KOLOM BETON BERTULANG (150 KG BESI + BEKESTING) 5,840,265.00 31
40 1 M3 MEMBUAT KOLOM BETON BERTULANG (175 KG BESI + BEKESTING) 6,310,182.00 31
41 1 M3 MEMBUAT KOLOM BETON BERTULANG (200 KG BESI + BEKESTING) 6,623,460.00 32
42 1 M3 MEMBUAT KOLOM BETON BERTULANG (250 KG BESI + BEKESTING) 7,406,655.00 32
43 1 M3 MEMBUAT KOLOM BETON BERTULANG (300 KG BESI + BEKESTING) 8,341,850.00 33
44 1 M3 MEMBUAT BALOK BETON BERTULANG (100 KG BESI + BEKESTING) 5,209,070.00 33
45 1 M3 MEMBUAT BALOK BETON BERTULANG (125 KG BESI + BEKESTING) 5,600,667.50 33
46 1 M3 MEMBUAT BALOK BETON BERTULANG (150 KG BESI + BEKESTING) 5,992,265.00 33
47 1 M3 MEMBUAT BALOK BETON BERTULANG (175 KG BESI + BEKESTING) 6,383,862.50 34
48 1 M3 MEMBUAT BALOK BETON BERTULANG (200 KG BESI + BEKESTING) 6,775,460.00 34
49 1 M3 MEMBUAT BALOK BETON BERTULANG (250 KG BESI + BEKESTING) 7,558,655.00 34
50 1 M3 MEMBUAT BALOK BETON BERTULANG (300 KG BESI + BEKESTING) 8,341,850.00 35
51 1 M3 MEMBUAT PLAT BETON BERTULANG (60 KG BESI + BEKESTING) 4,002,360.00 35
52 1 M3 MEMBUAT PLAT BETON BERTULANG (85 KG BESI + BEKESTING) 4,383,610.00 35
53 1 M3 MEMBUAT PLAT BETON BERTULANG (100 KG BESI + BEKESTING) 4,527,360.00 36
54 1 M3 MEMBUAT PLAT BETON BERTULANG (125 KG BESI + BEKESTING) 4,855,485.00 36
55 1 M3 MEMBUAT PLAT BETON BERTULANG (150 KG BESI + BEKESTING) 5,183,610.00 36
56 1 M3 MEMBUAT DINDING BETON BERTULANG (150 KG BESI + BEKESTING) 6,094,926.00 37
57 1 M' MEMBUAT KOLOM PENGUAT BETON BERTULANG (11 X 11) CM 80,563.00 37
58 1 M' MEMBUAT RING BALOK BETON BERTULANG (10 X 15) CM 98,131.00 37

VIII PEKERJAAN PENUTUP ATAP


1 1 M2 PASANG ATAP GENTENG PLENTONG BESAR 91,150.00 37
2 1 M2 PASANG BUBUNGAN PLENTONG BESAR 104,210.00 37
3 1 M2 PASANG ATAP GENTENG PLENTONG MINI 66,550.00 37
4 1 M2 PASANG BUBUNGAN PLENTONG MINI 74,710.00 38
5 1 M2 PASANG ATAP GENTENG KODOK 109,275.00 38
6 1 M2 PASANG BUBUNGAN PLENTONG KODOK 108,710.00 38
7 1 M2 PASANG ATAP ASBES GELOMBANG 1,80 X 0,92 X 5 MM 47,161.00 38
8 1 M' PASANG BUBUNGAN ASBES GELOMBANG 0,92 mm 29,203.00 38
9 1 M2 PASANG ATAP SIRAP 116,410.00 38
10 1 M' PASANG NOK ATAP SIRAP 95,363.00 39
11 1 M2 PASANG ATAP GENTENG BETON 57,304.00 39
12 1 M' PASANG BUBUNGAN GENTENG BETON 70,930.00 39
13 1 M2 PASANG GENTENG METAL ( BERPASIR EKS. MULTIROOF) 130,855.00 39
14 1 M2 PASANG GENTENG METAL POLOS MULTI COLOUR 115,045.00 39
15 1 M2 PASANG GENTENG METAL ( BERPASIR EKS. SAKURA ROOF ) 97,195.00 39
16 1 M2 PASANG GENTENG METAL POLOS SAKURA COLOUR 81,895.00 40
17 1 M2 PASANG ATAP ZINKALUM 175,218.00 40
18 1 M2 PASANG NOK ALUMINIUM 196,706.00 40
19 1 M2 PASANG ALUMINIUM FOIL/SISALATION 18,885.00 40
20 1 M2 PASANG ATAP ALANG-ALANG 3 M' 171,500.00 40
21 1 M2 PASANG ATAP SENG GELOMBANG 54,238.00 40
JUMLAH
NO U RAIAN HAL.
(RP)
1 2 3 4
22 1 M2 PASANG NOK SENG GELOMBANG 35,296.00 40

IX PEKERJAAN LANGIT-LANGIT
1 1 M2 PASANG PENUTUP LANGIT-LANGIT ETERNIT 1 X 1 M / 4 MM 28,790.50 41
2 1 M2 PASANG PENUTUP LANGIT-LANGIT KALSIBOARD 1 X 1 M / 4 MM 37,097.50 41
3 1 M2 PASANG PENUTUP LANGIT-LANGIT PLYWOOD 30 X 60 CM / 4 MM 39,716.50 41
4 1 M' PASANG PENUTUP LANGIT-LANGIT KAYU PROFIL 13,903.00 41
5 1 M2 PASANG PENUTUP LANGIT-LANGIT PLYWOOD 4 MM + RANGKA BAYUR 152,346.50 41

X PEKERJAAN SANITASI
1 MEMASANG 1 BUAH KLOSET DUDUK 3,004,650.00 41
2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN 405,000.00 42
3 MEMASANG 1 BUAH URINOIR KIA 1,107,724.00 42
4 MEMASANG 1 BUAH WASTAFEL KIA 750,340.00 42
5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3 785,550.00 42
6 MEMASANG 1 BUAH BAK MANDI PORSELIN/KERAMIK, VOLUME 0,30 M3 632,550.00 43
7 MEMASANG 1M' PIPA PVC PENYALUR AIR LIMBAH DIA 15 CM( DIA 4") 107,749.50 43
8 MEMASANG 1 BUAH BAK KONTROL, PASANGAN BATU BATA 30 X 30 / T. 35 CM 129,840.50 43
9 MEMASANG 1M' PIPA GALVANIS DIAMETER 0,5" 82,752.00 43
10 MEMASANG 1M' PIPA GALVANIS DIAMETER 3/4" 67,235.25 43
11 MEMASANG 1M' PIPA GALVANIS DIAMETER 1" 89,550.75 43
12 MEMASANG 1M' PIPA GALVANIS DIAMETER 2" 176,268.00 44
13 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 0,5" 18,525.75 44
14 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3/4" 22,375.50 44
15 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1" 74,575.50 44
16 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1,5" 45,082.50 44
17 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 2" 55,519.88 44
18 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3" 96,938.13 45
19 1 BH PASANG BAK CUCI PIRING STAINLES STEEL 430,292.50 45
20 MEMASANG 1 BUAH KRAN KUNINGAN DIAMETER 0,75" ATAU 0,5" 87,810.00 45
21 MEMASANG 1 BUAH KRAN STEINLESS DIAMETER 0,75" ATAU 0,5" 92,410.00 45
22 1 BH PASANG FLOOR DRAIN PLASTIK 37,725.00 45
23 1 BH PASANG FLOOR DRAIN STEINLESS 87,725.00 45

XI PEKERJAAN BESI DAN ALUMINIUM


1 1 KG PASANG RANGKA KUDA - KUDA BAJA I WF 33,975.00 45
2 1 KG PASANG BESI PROFIL 26,980.70 46
3 100 KG PEKERJAAN PERAKITAN 23,465.00 46
4 1 M2 PASANG PINTU BESI PLAT BAJA, RANGKA BAJA SIKU 657,848.00 46
5 10 CM PEKERJAAN PENGELASAN DENGAN LAS LISTRIK 11,820.00 46
6 1 M2 PEKERJAAN JENDELA BESI SCUARE TUBE ( 25 X 5 ) CM 213,211.00 46
7 1 M2 PASANG ROLLING DOOR BESI ( PLAT ) 516,332.00 46
8 1 M2 PASANG ROLLING DOOR ALIMINIUM 513,750.00 47
9 1 M2 PINTU LIPAT ( FOLDING DOOR ) BAHAN BAHAN PLASTIK / PVC 522,050.00 47
10 1 M2 SUNSCREEN ALUMINIUM 480,780.00 47
11 1 M' KUSEN ALUMINIUM 123,986.50 47
12 1 M2 PASANG JENDELA NAKO 181,361.00 47
13 1 M' PASANG TALANG DATAR, SENG BJLS 28 R. KAMPER 162,350.50 47
14 1 M' PASANG TALANG MIRING, SENG BJLS 28 R. KAMPER 239,800.50 48

XII PEKERJAAN KUNCI DAN KACA


1 1 BH PASANG KUNCI EX. MILANO 407,525.00 48
2 1 BH PASANG KUNCI EX. CESS / YALLE / ROYAL 367,225.00 48
3 1 BH PASANG KUNCI KM 125,525.00 48
4 1 BH PASANG ENGSEL PINTU KUNINGAN 74,151.00 48
5 1 BH PASANG ENGSEL PINTU STEINLESS 83,151.00 48
6 1 BH PASANG ENGSEL JENDELA KUPU-KUPU KUNINGAN 70,897.50 48
7 1 BH PASANG KAIT ANGIN PINTU 46,951.00 49
8 1 BH PASANG KAIT ANGIN JENDELA 42,351.00 49
9 1 BH PASANG KUNCI SLOT 127,895.00 49
JUMLAH
NO U RAIAN HAL.
(RP)
1 2 3 4
10 1 M2 PASANG KACA PUTIH POLOS,TEBAL 5 MM 130,651.00 49
11 1 M2 PASANG KACA RIBEN, TEBAL 5 MM 177,951.00 49

XIII PEKERJAAN PENUTUP LANTAI DAN DINDING


1 1 M2 PASANG LANTAI KERAMIK PUTIH 40 X 40 CM 135,085.00 49
2 1 M2 PASANG LANTAI KERAMIK WARNA 40 X 40 CM 140,610.00 50
3 1 M2 PASANG LANTAI KERAMIK RUSTIK 40 X 40 CM 146,135.00 50
4 1 M2 PASANG LANTAI KERAMIK PUTIH 30 X 30 CM 119,771.36 50
5 1 M2 PASANG LANTAI KERAMIK MOTIP 30 X 30 CM 129,591.09 50
6 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM PUTIH 138,677.00 50
7 1 M2 PASANG LANTAI KERAMIK 20 X 20 CM WARNA 148,323.00 51
8 1 M2 PASANG LANTAI GRANIT 40 X 40 CM 420,005.00 51
9 1 M2 PASANG LANTAI GRANIT 60 X 60 CM 413,510.00 51
10 1 M2 PASANG LANTAI FLOOR HARDENER NATURAL 67,150.00 51
11 1 M2 PASANG LANTAI FLOOR HARDENER WARNA 82,150.00 51
12 1 M2 PASANG DINDING KERAMIK 20 X 25 CM 123,355.00 52
13 1 M2 PASANG DINDING KERAMIK 20 X 25 CM 127,655.00 52
14 1 M2 PASANG DINDING KERAMIK 20 X 20 CM 132,487.00 52
15 1 M2 PASANG DINDING KERAMIK 10 X 20 CM 132,275.00 52
16 1 M2 PASANG DINDING MARMER 20 X 20 CM 406,701.00 52
17 1 M2 PASANG LANTAI MARMER 30 X 30 CM 422,895.44 52
18 1 M2 PASANG STYLE BALI DINDING PARAS KLATING 353,528.50 53
19 1 M2 PASANG DINDING PARAS BELAYU 393,665.50 53
20 1 M2 PASANG DINDING BATA EXPOSE 505,475.00 53
21 1 M2 PASANG DINDING PARAS TEMPEL PALIMANAN ( JOGJA ) 390,175.00 53
22 1 M2 PASANG DINDING PARAS TEMPEL PALIMANAN ( JOGJA ) 379,175.00 53
23 1 M2 PASANG DINDING PARAS LORENG KIDUL ( JOGJA ) 368,175.00 53
24 1 M2 PASANG DINDING BATU BATIK GREEN 373,675.00 54
25 1 M2 PASANG DINDING BATU ANDESIT BAKAR ( JOGJA ) 420,975.00 54
26 1 M2 PASANG DINDING BATU CANDI ( JOGJA ) 351,675.00 54
27 1 M2 PASANG DINDING BATU PILAH 285,675.00 54
28 1 M2 PASANG DINDING BATU ALUR GREEN 420,975.00 54
29 1 M2 PASANG DINDING BATU CANDI ALUR 417,675.00 54
30 1 M' PASANG PLIN KERAMIK 10 X 30 PUTIH 23,546.71 55
31 1 M' PASANG PLIN KERAMIK 10 X 30 WARNA 24,520.14 55
32 1 M' PASANG PLIN KERAMIK 10 X 40 PUTIH 25,185.50 55
33 1 M' PASANG PLIN KERAMIK 10 X 40 WARNA 25,737.58 55
34 1 M' PASANG PLIN KERAMIK 10 X 40 RUSTIK 26,289.67 55
35 1 M' PASANG PLIN GRANIT 10 X 40 57,427.17 56
36 1 M' PASANG PLIN GRANIT 10 X 60 76,471.06 56
37 1 M' PASANG PLIN KAYU KAMPER 2 X 10 CM 43,225.00 56
38 1 M2 PASANG LANTAI KARPET 70,925.00 56
39 1 M2 PASANG UNDERLAYER / Pelapis Bawah Karpet 60,425.00 56
40 1 M2 PASANG LANTAI PARQUET JATI 639,637.50 56
41 1 M2 PASANG LANTAI PARQUET BENGKIRAI 461,137.50 57
42 1 M2 PASANG LANTAI KAYU ( gymfloor ) 587,137.50 57

XIV PEKERJAAN PENGECATAN


1 1 M2 PENGECATAN BID. KAYU BARU (1 x PLAMIR, 1 x CAT DASAR, 2 x CAT PENU 54,232.00 57
2 1 M2 PENGECATAN BIDANG KAYU LAMA 30,150.50 57
3 1 M2 PENGECATAN BIDANG KAYU DENGAN PERNIS 42,837.50 57
4 1 M2 PENGECATAN BIDANG KAYU DENGAN POLITUR 56,052.05 57
5 1 M2 PENGECATAN TEMBOK BARU (1 x PLAMIR, 1 x CAT DASAR, 2 x CAT PENUT 24,828.00 58
6 1 M2 PENGECATAN TEMBOK LAMA (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) 23,328.00 58
7 1 M2 PENGECATAN PLAFOND (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) 23,328.00 58
8 1 M2 PENGECATAN DASAR PERMUKAAN BAJA DENGAN MENI BESI 27,850.00 58
9 1 M2 PEKERJAAN PENGECATAN BESI HALUS 30,480.00 58
10 1 M2 PENGECATAN GENTENG (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) 29,822.73 58
11 1 M2 PENGECATAN LAPANGAN (1 LAPIS CAT DASAR, 2 LAPIS CAT PENUTUP) 33,450.00 58
JUMLAH
NO U RAIAN HAL.
(RP)
1 2 3 4

XV PEKERJAAN PELENGKAP
1 1 M2 PASANGAN PAVING STONE PC K. 175 Tbl. 6 cm 101,250.00 59
2 1 M2 PASANGAN PAVING STONE PC K. 175 Tbl. 8 cm 117,882.50 59
3 1 M2 PASANGAN PAVING STONE WARNA K. 175 Tbl 6 109,250.00 59
4 1 M2 PASANGAN PAVING STONE WARNA K. 175 Tbl 8 113,250.00 59
5 1 M2 PASANGAN PAVING STONE KHUSUS K. 225 Tbl. 6 118,250.00 59
6 1 M2 PASANGAN PAVING STONE KHUSUS K. 225 Tbl. 8 121,250.00 59
7 1 M2 PASANGAN PAVING STONE KHUSUS K. 300 Tbl. 6 126,250.00 59
8 1 M2 PASANGAN PAVING STONE KHUSUS K. 300 Tbl. 8 131,250.00 59
9 1 M3 BETON COR 1:2:3 + M 5 tebal 5 cm 2,109,050.00 59
10 1 M3 BETON COR 1:2:3 + M 5 tebal 10 cm 1,496,500.00 59
11 1 M3 BETON COR 1:2:3 + M 6 tebal 5 cm 2,517,050.00 59
12 1 M3 BETON COR 1:2:3 + M 6 tebal 10 cm 1,700,500.00 60

Negara, 5 Januari 2015

Kepala Dinas Pekerjaan Umum


Kabupaten Jembrana

Drs. I Gusti Putu Mertadana, M.Si


Pembina Utama Muda
NIP. 19581231 198110 1 016

Anda mungkin juga menyukai