I PEKERJAAN PERSIAPAN
1 1 M' PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 M
1.000 Btg Kayu seseh balok 8/12 x 3 3,772,700.00 - 3,772,700.00 3,772,700.00
2.500 Kg Semen portland 1,400.00 - 3,500.00 3,500.00
1.200 Lbr Seng gelombang 3" - 5" 56,500.00 - 67,800.00 67,800.00
0.005 M3 Pasir beton ex karangasem 230,000.00 - 1,150.00 1,150.00
0.009 M3 Krikil beton / koral pilihan 210,000.00 - 1,890.00 1,890.00
0.012 M3 Kayu usuk bayur 5,000,000.00 - 60,000.00 60,000.00
0.060 Kg Paku biasa 2" - 5" 31,800.00 - 1,908.00 1,908.00
0.450 Kg Meni besi 35,450.00 - 15,952.50 15,952.50
0.200 Oh Tukang kayu 85,000.00 17,000.00 - 17,000.00
0.400 Oh Pekerja 65,000.00 26,000.00 - 26,000.00
0.020 Oh Kepala Tukang kayu 90,000.00 1,800.00 - 1,800.00
0.020 Oh Mandor 95,000.00 1,900.00 - 1,900.00
46,700.00 3,924,900.50 3,971,600.50
2 1 M' PAGAR SEMENTARA DARI KAWAT BERDURI TINGGI 1,8 M
1.000 Btg Kayu seseh balok 8/12 x 3 3,772,700.00 - 3,772,700.00 3,772,700.00
2.000 Kg Semen portland 1,400.00 - 2,800.00 2,800.00
0.250 Kg Kawat duri 16,300.00 - 4,075.00 4,075.00
0.005 M3 Pasir beton ex karangasem 230,000.00 - 1,150.00 1,150.00
0.009 M3 Krikil beton / koral pilihan 210,000.00 - 1,890.00 1,890.00
0.060 Kg Paku biasa 2"- 5" 31,800.00 - 1,908.00 1,908.00
0.200 Oh Tukang kayu 85,000.00 17,000.00 - 17,000.00
0.300 Oh Pekerja 65,000.00 19,500.00 - 19,500.00
0.020 Oh Kepala tukang kayu 90,000.00 1,800.00 - 1,800.00
0.020 Oh Mandor 95,000.00 1,900.00 - 1,900.00
40,200.00 3,784,523.00 3,824,723.00
3 1 M' PEMASANGAN BOUWPLANK
0.012 M3 Kayu begisting 2,350,000.00 - 28,200.00 28,200.00
0.020 Kg Paku biasa 2" - 5" 31,800.00 - 636.00 636.00
0.100 Oh Tukang kayu 85,000.00 8,500.00 - 8,500.00
0.100 Oh Pekerja 65,000.00 6,500.00 - 6,500.00
0.010 Oh Kepala tukang kayu 90,000.00 900.00 - 900.00
0.005 Oh Mandor 95,000.00 475.00 - 475.00
16,375.00 28,836.00 45,211.00
4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT
1.700 Btg kayu seseh 6/10x3M 3,772,700.00 - 6,413,590.00 6,413,590.00
0.210 M3 Kayu usuk bayur 5,000,000.00 - 1,050,000.00 1,050,000.00
0.300 Kg Paku biasa 2" - 5" 31,800.00 - 9,540.00 9,540.00
10.500 Kg Semen portland 1,400.00 - 14,700.00 14,700.00
0.030 M3 Pasir beton ex karangasem 230,000.00 - 6,900.00 6,900.00
0.050 M3 Koral beton 210,000.00 - 10,500.00 10,500.00
1.500 Lbr Seng gelombang BJLS 32 56,500.00 - 84,750.00 84,750.00
2.000 Oh Tukang kayu 85,000.00 170,000.00 - 170,000.00
1.000 Oh Pekerja 65,000.00 65,000.00 - 65,000.00
Analisa Page 2
b. MEDIUM ( A )
Black :
- Black 1/4" lonjor 81,058.00 73,600.00
- Black 3/8" lonjor 99,955.00 90,800.00
- Black 1/2" lonjor 147,570.00 134,000.00
- Black 3/4" lonjor 190,586.00 173,000.00
- Black 1" lonjor 292,157.00 265,500.00
- Black 1 1/4" lonjor 386,394.00 351,000.00
- Black 1 1/2" lonjor 450,917.00 410,000.00
- Black 2" lonjor 612,536.00 556,800.00
- Black 2 1/2" lonjor 804,242.00 731,000.00
- Black 3" lonjor 1,038,590.00 944,000.00
- Black 4" lonjor 1,500,075.00 1,363,000.00
- Black 5" lonjor 1,954,225.00 1,776,000.00
- Black 6" lonjor 2,322,344.00 2,111,000.00
- Black 6" lonjor 3,628,227.00 3,298,000.00
- Black 10" lonjor 5,245,912.00 4,769,000.00
- Black 12" lonjor 6,239,994.00 5,672,000.00
Galv :
- Galv 1/2" lonjor 185,240.00 168,400.00
- Galv 3/4" lonjor 216,445.00 196,700.00
- Galv 1" lonjor 367,124.00 333,700.00
- Galv 1 1/4" lonjor 484,857.00 440,700.00
- Galv 1 1/2" lonjor 565,543.00 514,000.00
- Galv 2" lonjor 763,313.00 694,000.00
- Galv 2 1/2" lonjor 1,008,752.00 917,000.00
- Galv 3" lonjor 1,302,651.00 1,184,200.00
- Galv 4" lonjor 1,880,999.00 1,710,000.00
- Galv 5" lonjor 2,425,034.00 2,204,000.00
- Galv 6" lonjor 2,913,124.00 2,648,000.00
- Galv 6" lonjor 4,551,322.00 4,137,565.45
- Galv 10" lonjor 6,621,292.00 6,019,356.36
- Galv 12" lonjor 7,876,451.00 7,160,410.00
Jasa Konsultasi
1 Perlengkapan Kantor :
a.sewa Komputer Laptop Rp/Bulan 600,000.00 545,000.00
b.SewaKomputer Destop PC Rp/Bulan 450,000.00 410,000.00
c.Sewa Printer Rp/Bulan 300,000.00 272,500.00
d.Sewa LCD Rp/Hari 100,000.00 90,000.00
2 Kendaraan Kerja
a.Sewa Kendaraan Roda 4 Unit/bulan 5,500,000.00 5,000,000.00
b.Sewa Kendaraan Roda 2 Unit/Bulan 600,000.00 545,000.00
3 Perlengkapan Khusus :
a. Sewa Alat Ukur Digital/GPS dan kelengkapannya Unit/Bulan 750,000.00 681,000.00
b.Sewa Alat Ukur Theodolite Unit/Bulan 2,500,000.00 2,272,700.00
c.Sewa Kamera Digital Unit/Bulan 200,000.00 181,800.00
4. Biaya Pelaporan :
a.Laporan Pendahuluan/Inception report Rp/Buku 100,000.00 90,900.00
b.Laporan Fakta Analisa/Interim Report Rp/Buku 125,000.00 113,600.00
c.Laporan Rancangan Rencana/draf Final report Rp/Buku 150,000.00 136,300.00
d.Laporan rencana/Final report Rp/Buku 150,000.00 136,300.00
e.Laporan ringkasan Eksekutif/Executif Rp/Buku 30,000.00 27,000.00
Summary
ff.Rancangan Peraturan Daerah/Bupati Rp/Buku 50,000.00 45,400.00
g.Album Peta Berwarna/ A.3 Rp/Buku 200,000.00 181,800.00
h.Album Peta Berwarna /A 2 Rp/buku 500,000.00 454,500.00
i.Album Peta Berwarna/A 1 Rp/buku 750,000.00 681,800.00
j.Album Peta Tematik Rp/Buah 300,000.00 272,700.00
k.Peta Display AO Rp/Keping 350,000.00 318,000.00
l.Peta Berfigura Rp/buah 400,000.00 3,636.00
m.Back Up Laporan dan Peta dalam CD Rp/Kepeing 25,000.00 22,700.00
n.CD File Pembuatan Peta, Dokumentasi dan Kegiatan Rp/ Keping 25,000.00 22,700.00
NO URAIAN BAHAN SAT HARGA
HARGA DASAR KET.
TERMASUK PPN
1 2 3 4 5 6
5 Biaya Komunikasi Orang/Bula 25,000.00 22,700.00
6 Biaya Survey Orang/Hari 250,000.00 227,000.00
7 Biaya Pengadaan Peta Citra Satelit Rp/KM2 300,000.00 272,700.00
A. UPAH :
1 Pekerja OH 65,000.00
2 Pekerja trampil OH 70,000.00
3 Mandor OH 95,000.00
4 Tukang kayu OH 85,000.00
5 Tukang batu OH 85,000.00
6 kepala tukang kayu OH 90,000.00
7 Kepala tukang batu OH 90,000.00
8 Tukang besi OH 85,000.00
9 Kepala tukang besi OH 90,000.00
10 Tukang cat OH 80,000.00
11 Kepala tukang cat OH 85,000.00
12 Tukang style bali OH 90,000.00
13 Kepala tukang style bali OH 95,000.00
14 Tukang Las OH 85,000.00
15 Kepala Tukang Las OH 90,000.00
16 Peladen style bali OH 85,000.00
17 Operator terampil OH 110,000.00
18 Operator kurang terampil OH 85,000.00
19 Pembantu operator OH 80,000.00
20 Sopir terampil OH 85,000.00
21 Pembantu sopir / kernet OH 75,000.00
22 Upah pasang kunci pintu Unit 40,000.00
23 Upah pasang instalsi listrik Unit 40,000.00
24 Upah pasang instalasi air M' 10,000.00
25 Upah pasang kloset jongkok Unit 60,000.00
26 Upah pasang kloset duduk Unit 160,000.00
27 Upah pasang bak air Unit 60,000.00
28 Upah pasang urinoir pot Unit 95,000.00
29 Upah pasang washtafel Unit 100,000.00
30 Upah pasang paping stone M2 40,000.00
31 Upah pasang batu bata dan paras kombinasi M2 120,000.00
32 Upah pasang paras hitam kombinasi M2 120,000.00
33 Upah pasang I bh kran dan 1 m pipa pvc Unit 15,000.00
34 Upah Kerja Konstruksi LS 2,750,000.00
35 Upah Kerja Mesin LS 1,650,000.00
36 Upah Kerja Konstruksi Pintu Air > 100 cm 2,750,000.00
37 Upah Kerja Konstruksi Pintu Air < 100 cm 1,650,000
38 Upah Kerja mesin > 100 cm 1,750,000
39 Upah Kerja Mesin < 100 cm 1,000,000
40 Ongkos Pemasangan Pintu air 1,000,000
41 Ongkos Pembongkaran pintu air 600,000
42 Transport mobilisasi pintu air 600,000
B. ALAT :
1 Aspahalt Sprayer 1000 Liter Jam 130,000.00
2 Buldozer 100 Hp Jam 565,000.00
3 Buldozer 65 Hp Jam 462,000.00
4 Concrete Mixer 0,3 - 0,6 M3 Jam 130,000.00
5 Concrete Vibrator Jam 50,000.00
6 Grader 110 Hp Jam 470,000.00
NO NAMA DAN UPAH PEKERJA SATUAN HARGA KETERANGAN
1 2 3 4 5
7 Mesin Penyaring Jam 90,000.00
8 Mesin Gilas 3 Roda 6-8 ton Jam 150,000.00
9 Mesin Gilas Tandem 8 - 10 ton Jam 175,000.00
10 Mesin Gilas Tandem 2,5 ton Jam 125,000.00
11 Mesin Gilas Roda 8 - 15 ton Jam 250,000.00
12 Pemecah Batu Jam 288,500.00
13 Pompa Air f 50 mm Jam 32,000.00
14 Pompa Air f 40 mm Jam 32,000.00
15 Roller Vibrator 1,0 ton Jam 28,500.00
16 Stamper Vibrating Plate 1 Hp Jam 23,000.00
17 Truck Tangki Air 115 Hp Jam 67,000.00
18 Truck Bak Terbuka 3,5 ton / 115 Hp Jam 67,000.00
19 Whell Loader Jam 545,000.00
20 Kompresor Jam 130,000.00
21 Asphalt Mixing Plant Jam 3,864,000.00
22 Generator Set Jam 288,500.00
23 Dump Truck 5 ton / 145 Hp Jam 250,000.00
24 Dump Truck 10 ton Jam 288,500.00
25 Asphalt Finisher Jam 1,603,000.00
26 Pneumatic Tire Roller Jam 834,000.00
27 Asphalt Sprayer Jam 129,000.00
28 Vibrating Compactor Jam 84,000.00
29 Truck Mixer Jam 125,000.00
JUMLAH
NO U RAIAN HAL.
(RP)
1 2 3 4
I PEKERJAAN PERSIAPAN
1 1 M' PAGAR SEMENTARA DARI SENG GELOMBANG TINGGI 2 M 3,971,600.50 1
2 1 M' PAGAR SEMENTARA DARI KAWAT BERDURI TINGGI 1,8 M 3,824,723.00 1
3 1 M' PEMASANGAN BOUWPLANK 45,211.00 1
4 1 M2 PEMBUATAN GUDANG SEMEN DAN ALAT-ALAT 7,831,530.00 1
5 1 M2 PEMBUATAN RUMAH JAGA / KONSTRUKSI KAYU 13,015,860.00 2
6 1 M2 MEMBERSIHKAN LAPANGAN DAN PERALATAN 11,250.00 2
7 1 M2 PEMBUATAN BEDENG BURUH 6,132,315.00 2
8 1 M2 PEMBUATAN BAK ADUKAN ( 40X50X20) CM 148,786.50 2
9 1 M2 PEMBUATAN STEGGER DARI BAMBU UKURAN (40 X 50 X 20) CM 39,960.00 2
10 1 M2 PEMBUATAN JALAN SEMENTARA 123,525.00 2
11 1 M3 BONGKARAN BETON BERTULANG 269,990.00 2
12 1 M3 BONGKARAN DINDING TEMBOK BATA MERAH 176,490.00 2
13 1 M' PASANG PAGAR BETON PRACETAK (5 X 50 X 213) CM 342,050.00 3
II PEKERJAAN TANAH
1 1 M3 GALIAN TANAH BIASA SEDALAM 1 METER 51,125.00 3
2 1 M3 GALIAN TANAH BIASA SEDALAM 2 METER 62,775.00 3
3 1 M3 GALIAN TANAH BIASA SEDALAM 3 METER 74,615.00 3
4 1 M3 GALIAN TANAH KERAS SEDALAM 1 METER 68,040.00 3
5 1 M3 GALIAN TANAH CADAS SEDALAM 1 METER 103,200.00 3
6 1 M3 GALIAN TANAH LUMPUR SEDALAM 1 METER 82,275.00 3
7 1 M2 PEKERJAAN STRIPPING SETINGGI 1 METER 3,725.00 3
8 1 M3 PEMBUANGAN TANAH SEJAUH 15 METER 22,400.00 3
9 1 M3 URUGAN KEMBALI TANAH BIASA 17,041.67 3
10 1 M3 URUGAN KEMBALI TANAH KERAS 22,680.00 3
11 1 M3 PEMADATAN TANAH 37,250.00 4
12 1 M3 URUGAN PASIR 200,450.00 4
13 1 M3 PEMASANGAN LAPISAN IJUK 102,975.00 4
14 1 M3 URUGAN TASIRTU 133,825.00 4
15 1 M3 URUGAN TANAH URUG 133,825.00 4
16 1 M3 PEMBUATAN JALAN SEMENTARA, TBL. 25 CM 153,200.00 4
IV PEKERJAAN DINDING
1 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA , 1 PC : 2 PS 266,350.00 6
2 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA , 1 PC : 3 PS 254,165.00 6
3 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA , 1 PC : 4 PS 245,675.00 6
4 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA ,1 PC : 5 PS 241,700.00 7
5 1 M2 PASANGAN BATA MERAH TEBAL 1 BATA, 1 PC : 6 PS 241,220.00 7
JUMLAH
NO U RAIAN HAL.
(RP)
1 2 3 4
6 1 M2 PASANGAN BATACO / HB / CONE BLOCK (HB.20/CB20) 1 Pc : 3 Ps 79,489.20 7
7 1 M2 PASANGAN BATACO / HB / CONE BLOCK (HB.20/CB20) 1 Pc : 4 Ps 78,089.20 7
8 1 M2 PASANGAN BATACO / HB / CONE BLOCK (HB.15/CB15) 1 Pc : 4 Ps 96,220.00 7
9 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 2 PS 128,785.00 7
10 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 3 PS 122,843.00 8
11 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 4 PS 119,530.00 8
14 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 5 PS 117,452.00 8
15 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 6 PS 116,488.00 8
16 1 M2 PASANGAN BATA MERAH TEBAL 1/2 BATA, 1 PC : 8 PS 114,175.00 9
17 1 M2 PASANGAN DINDING ROSTER 10 X 10 X 20 CM 241,550.00 9
18 1 M2 PASANGAN DINDING BATA BERONGGA (12 X 11 X 24 CM) 1 PC : 3 PS 76,050.00 9
19 1 M2 PASANGAN DINDING BEDEG, RANGKA KAYU 183,506.60 9
V PEKERJAAN PLESTERAN
1 1 M2 PLESTERAN 1 PC : 1 PS, TEBAL 15 MM 60,490.60 9
2 1 M2 PLESTERAN 1 PC : 2 PS, TEBAL 15 MM 54,038.60 9
3 1 M2 PLESTERAN 1 PC : 3 PS, TEBAL 15 MM 51,316.40 9
4 1 M2 PLESTERAN 1 PC : 4 PS, TEBAL 15 MM 49,401.00 9
5 1 M2 PLESTERAN 1 PC : 5 PS, TEBAL 15 MM 48,392.60 10
6 1 M2 PLESTERAN 1 PC : 6 PS, TEBAL 15 MM 47,552.40 10
7 1 M2 PLESTERAN 1 PC : 7 PS, TEBAL 15 MM 47,115.40 10
8 1 M2 PLESTERAN 1 PC : 8 PS, TEBAL 15 MM 46,678.40 10
9 1 M2 PLESTERAN PONDASI 1 PC : 2 PS, TEBAL 20 MM 72,319.80 10
10 1 M2 PLESTERAN PONDASI 1 PC : 3 PS, TEBAL 20 MM 67,835.20 10
11 1 M2 PLESTERAN PONDASI 1 PC : 4 PS, TEBAL 20 MM 66,058.00 10
12 1 M2 PLESTERAN PONDASI 1 PC : 5 PS, TEBAL 20 MM 64,791.80 11
13 1 M2 PLESTERAN PONDASI 1 PC : 6 PS, TEBAL 20 MM 63,593.20 11
14 1 M2 PLESTERAN SKONENG 1 PC : 2 PS, LEBAR 10 MM 46,935.00 11
15 1 M2 PLESTERAN GRANIT 1 PC : 2 GRANIT, TEBAL 10 MM 201,630.00 11
16 1 M2 PLESTERAN TERASO 1 PC : 2 TERASO, TEBAL 10 MM 186,630.00 11
17 1 M2 PLESTERAN CIPRAT / KAMPROT 1 PC : 2 PS. 37,783.00 11
18 1 M2 PLESTERAN SIAR 1 PC : 2 PS ( ACIAN ) 46,721.00 11
19 1 M2 ACIAN PC 27,900.00 12
VI PEKERJAAN KAYU
1 1 M3 PEKERJAAN KUSEN PINTU DAN JENDELA KAMPER 11,736,511.36 12
2 1 M3 PASANGAN KUSEN PINTU DAN JENDELA KAYU JATI 21,966,511.36 12
3 1 M3 PASANGAN KUSEN PINTU DAN JENDELA KAYU BENGKIRAI 15,916,511.36 12
4 1 M3 PEKERJAAN KUSEN PINTU DAN JENDELA KERUING 10,086,511.36 12
5 1 M3 PEKERJAAN KUSEN PINTU DAN JENDELA BAYUR 7,666,511.36 12
6 1 M2 PEKERJAAN PINTU KLAMP KAYU KAMPER 566,568.18 13
7 1 M2 PEKERJAAN PINTU PANEL KAYU BAYUR 566,568.18 13
8 1 M2 PEKERJAAN PINTU PANEL KAYU KAMPER 718,568.18 13
9 1 M2 PEKERJAAN PINTU PANEL KAYU JATI 1,098,568.18 13
10 1 M2 PEKERJAAN PINTU DAN JENDELA KACA KAYU BAYUR 512,768.18 13
11 1 M2 PEKERJAAN PINTU DAN JENDELA KACA KAYU KAMPER 603,968.18 14
12 1 M2 PEKERJAAN PINTU DAN JENDELA KACA KAYU KERUING 570,368.18 14
13 1 M2PEKERJAAN PINTU DAN JENDELA KACA KAYU JATI 831,968.18 14
14 1 M2 PEKERJAAN PINTU PLYWOOD RANGKAP, RANGKA KAYU KAMPER 546,997.18 14
15 1 M2 PEKERJAAN PINTU PLYWOOD RANGKAP, RANGKA KAYU KERUING 511,997.18 15
16 1 M2 PEKERJAAN PINTU PLYWOOD RANGKAP, RANGKA KAYU BAYUR 451,997.18 15
17 1 M2 PEKERJAAN PINTU TEAKWOOD RANGKAP, RANGKA KAYU KAMPER 585,997.18 15
18 1 M2 PEKERJAAN PINTU TEAKWOOD RANGKAP, RANGKA KAYU KERUING 550,997.18 15
19 1 M2 PEKERJAAN PINTU TEAKWOOD RANGKAP, RANGKA KAYU BAYUR 490,997.18 15
20 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA KONVENSIONAL
KAYU KAMPER BENTANG 6 M' 11,451,840.00 15
21 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA KONVENSIONAL
KAYU KERUING BENTANG 6 M' 9,790,080.00 16
JUMLAH
NO U RAIAN HAL.
(RP)
1 2 3 4
22 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA KONVENSIONAL
KAYU SESEH KELAS I BENTANG 6 M' 6,020,050.00 16
23 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA EXPOSE KAMPER 12,389,805.00 16
24 1 M3 PEKERJAAN KONSTRUKSI KUDA-KUDA EXPOSE JATI 22,619,805.00 16
25 1 M2 PASANG USUK DAN RENG KAYU KAMPER ( ATAP GENTENG ) 174,265.00 16
26 1 M2 PASANG USUK DAN RENG KAYU KRUING ( ATAP GENTENG ) 147,865.00 16
27 1 M2 PASANG USUK DAN RENG KAYU BAYUR ( ATAP GENTENG ) 109,145.00 17
28 1 M2 PASANG USUK DAN RENG KAYU KAMPER ( ATAP GENTENG BETON ) 208,765.00 17
29 1 M2 PASANG PLAFOND 1 X 1 M ASBES SEMEN tebal 4 mm 28,937.00 17
30 1 M2 PASANG PLAFOND 1 X 1 M ( AKUSTIK 30 X 30 ) 38,785.00 17
31 1 M2 PASANG PLAFOND TRIPLEK 1,20 X 2,40 M, TEBAL 4 MM 42,556.00 17
32 1 M2 PASANG PLAFOND LAMBIZIRING KAYU JATI, TEBAL 9 MM 330,045.50 17
33 1 M2 PASANG PLAFOND LAMBIZIRING KAYU KAMPER, TEBAL 9 MM 187,545.50 17
34 1 M2 PASANG PLAFOND GYPSUM BOARD 1,2 X 2,4 TEBAL 9 MM 43,929.00 18
35 1 M' PASANG LIST PLAFOND GYPSUM PROFIL 46,012.50 18
36 1 M' PASANG LIST PLAFOND KAYU PROFIL KAMPER 33,885.00 18
37 1 M' PASANG LIST PLAFOND KAYU PROFIL BAYUR 25,170.00 18
38 1 M2 PASANG RANGKA PLAFOND AKUSTIK 30 X 30 CM KAYU KAMPER 291,597.50 19
39 1 M2 PASANG RANGKA PLAFOND ETERNIT 0,50 X 1 M KAYU KAMPER 185,415.00 19
40 1 M2 PASANG RANGKA PLAFOND ETERNIT 0,50 X 1 M KAYU KERUING 162,315.00 19
41 1 M2 PASANG RANGKA PLAFOND ETERNIT 0,50 X 1 M KAYU BAYUR 128,435.00 19
42 1 M2 PASANG RANGKA PLAFOND 30 X 60 CM KAYU KAMPER 191,910.00 19
43 1 M2 PASANG RANGKA PLAFOND 30 X 60 CM KAYU KERUING 167,460.00 19
44 1 M2 PASANG RANGKA PLAFOND 30 X 60 CM KAYU BAYUR 131,600.00 19
45 1 M' PASANG LISPLANG 3 X 20 CM, KAYU KAMPER 124,565.00 20
46 1 M' PASANG LISPLANG 3 X 30 CM, KAYU KAMPER 139,865.00 20
47 1 M' PASANG LISPLANG 2 X (3 x 20) CM, KAYU KAMPER 172,783.00 20
48 1 M' PASANG LISPLANG 3 X 20 CM, KAYU KERUING 109,445.00 20
49 1 M' PASANG LISPLANG 2 X (3 x 20) CM, KAYU KERUING 152,483.00 20
50 1 M' PASANG LISPLANG (3 X 20) CM KAYU BAYUR 83,525.00 20
51 1 M' PASANG LISPLANG 2 X (2 X 20) CM KAYU BAYUR 67,278.00 21
52 1 M2 PAS. DINDING PEMISAH / SKETSEL R. KAMPER + PLYWOOD 3 MM RANGKA 373,661.36 21
53 1 M2 PAS. DINDING PEMISAH / SKETSEL R. KERUING + PLYWOOD 3 MM RANGK 331,661.36 21
54 1 M2 PAS. DINDING PEMISAH / SKETSEL R. BAYUR + PLYWOOD 3 MM RANGKAP 270,061.36 21
55 1 M2 PAS. DINDING PEMISAH / SKETSEL R. KAMPER + TEAKWOOD 3 MM RANG 407,201.36 21
56 1 M2 PASANG DINDING LAMBRIZIRING KAMPER 281,980.00 21
57 1 M2 PASANG DINDING LAMBRIZIRING PLYWOOD ( 1,2 X 2,4 ) M 60,590.00 21
58 1 M2 PASANG DINDING BILIK BAMBU R. KAYU BAYUR 127,065.30 21
IX PEKERJAAN LANGIT-LANGIT
1 1 M2 PASANG PENUTUP LANGIT-LANGIT ETERNIT 1 X 1 M / 4 MM 28,790.50 41
2 1 M2 PASANG PENUTUP LANGIT-LANGIT KALSIBOARD 1 X 1 M / 4 MM 37,097.50 41
3 1 M2 PASANG PENUTUP LANGIT-LANGIT PLYWOOD 30 X 60 CM / 4 MM 39,716.50 41
4 1 M' PASANG PENUTUP LANGIT-LANGIT KAYU PROFIL 13,903.00 41
5 1 M2 PASANG PENUTUP LANGIT-LANGIT PLYWOOD 4 MM + RANGKA BAYUR 152,346.50 41
X PEKERJAAN SANITASI
1 MEMASANG 1 BUAH KLOSET DUDUK 3,004,650.00 41
2 MEMASANG 1 BUAH KLOSET JONGKOK PORSELIN 405,000.00 42
3 MEMASANG 1 BUAH URINOIR KIA 1,107,724.00 42
4 MEMASANG 1 BUAH WASTAFEL KIA 750,340.00 42
5 MEMASANG 1 BUAH BAK MANDI FIBREGLASS, VOLUME 0,30 M3 785,550.00 42
6 MEMASANG 1 BUAH BAK MANDI PORSELIN/KERAMIK, VOLUME 0,30 M3 632,550.00 43
7 MEMASANG 1M' PIPA PVC PENYALUR AIR LIMBAH DIA 15 CM( DIA 4") 107,749.50 43
8 MEMASANG 1 BUAH BAK KONTROL, PASANGAN BATU BATA 30 X 30 / T. 35 CM 129,840.50 43
9 MEMASANG 1M' PIPA GALVANIS DIAMETER 0,5" 82,752.00 43
10 MEMASANG 1M' PIPA GALVANIS DIAMETER 3/4" 67,235.25 43
11 MEMASANG 1M' PIPA GALVANIS DIAMETER 1" 89,550.75 43
12 MEMASANG 1M' PIPA GALVANIS DIAMETER 2" 176,268.00 44
13 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 0,5" 18,525.75 44
14 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3/4" 22,375.50 44
15 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1" 74,575.50 44
16 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 1,5" 45,082.50 44
17 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 2" 55,519.88 44
18 MEMASANG 1M' PIPA PVC TIPE AW DIAMETER 3" 96,938.13 45
19 1 BH PASANG BAK CUCI PIRING STAINLES STEEL 430,292.50 45
20 MEMASANG 1 BUAH KRAN KUNINGAN DIAMETER 0,75" ATAU 0,5" 87,810.00 45
21 MEMASANG 1 BUAH KRAN STEINLESS DIAMETER 0,75" ATAU 0,5" 92,410.00 45
22 1 BH PASANG FLOOR DRAIN PLASTIK 37,725.00 45
23 1 BH PASANG FLOOR DRAIN STEINLESS 87,725.00 45
XV PEKERJAAN PELENGKAP
1 1 M2 PASANGAN PAVING STONE PC K. 175 Tbl. 6 cm 101,250.00 59
2 1 M2 PASANGAN PAVING STONE PC K. 175 Tbl. 8 cm 117,882.50 59
3 1 M2 PASANGAN PAVING STONE WARNA K. 175 Tbl 6 109,250.00 59
4 1 M2 PASANGAN PAVING STONE WARNA K. 175 Tbl 8 113,250.00 59
5 1 M2 PASANGAN PAVING STONE KHUSUS K. 225 Tbl. 6 118,250.00 59
6 1 M2 PASANGAN PAVING STONE KHUSUS K. 225 Tbl. 8 121,250.00 59
7 1 M2 PASANGAN PAVING STONE KHUSUS K. 300 Tbl. 6 126,250.00 59
8 1 M2 PASANGAN PAVING STONE KHUSUS K. 300 Tbl. 8 131,250.00 59
9 1 M3 BETON COR 1:2:3 + M 5 tebal 5 cm 2,109,050.00 59
10 1 M3 BETON COR 1:2:3 + M 5 tebal 10 cm 1,496,500.00 59
11 1 M3 BETON COR 1:2:3 + M 6 tebal 5 cm 2,517,050.00 59
12 1 M3 BETON COR 1:2:3 + M 6 tebal 10 cm 1,700,500.00 60