Anda di halaman 1dari 3

Government of Nepal

Ministry of Physical Infrastructure and Transport


Department of Roads
Division Roads Office, Bhaktapur
Katunje

Bill of Quantities

Name of work :Roadway Excavation,Humepipe Culverts & wall works etc


Name of Road: Pokharichauri - Dhuseni - Shivalaya
Contract No. DROBKT/337123/4/2071/072/109

Rate (NRs.)
S. N. Description of work Unit Quantity Amount( NRs.)
In figure In words
A General item
Insurance for the loss of damage to works, plant,
1 material, equipment property and personnel injury or Ls 1.00
death and third party as per contract data.
B Roadway Excavation
Earth work excavation for road works in all types of
1 soil/rock including disposal etc. all complete as per m3 2250.00
specification.(905)*
C Quantity of 60 cm diameter Humepipe Culvert
Earth work excavation for drain and trenches
1 including shoring,struting,bracing,sheeting, disposal m3 33.42
and all complete as per specification.

Providing and laying dry stone solling /pitching as


2 m3 3.66
per specification.(Spec. 2403,4)

Supply, mixing, placing and curing PCC (1:2:4) with


3 m3 3.66
all work complete (2000)

Providing and Laying of 60 cm dia. NP3 RCC Hume


pipe with necessary fittings jointed with stiff mixture
4 RM 7.50
of cement mortar in proportion of 1:2( 1 cement : 2
fine sand) as per specification (701)

BoQ Page 1 of 3
Bill of Quantities

Name of work :Roadway Excavation,Humepipe Culverts & wall works etc


Name of Road: Pokharichauri - Dhuseni - Shivalaya
Contract No. DROBKT/337123/4/2071/072/109
Providing and laying Random rubble masonry in 1:4
cement mortatr including scaffolding, curing,
5 m3 16.45
preparation of mortar etc. complete, masoned
height 0-5m, (2602, 2603, 2607)*
Providing, Mixing and Pointing cement mortar (1:3)
6 over rubble mansory works including scaffolding m2 16.15
etc.complete as per specification (2602/2603/2510)
Making gabion boxes including cutting wire &
netting etc. Hexagonal mesh size 100 mm x 120
mm, mesh wire-10 SWG, selvedge wire-8 SWG;
Gabion construction works including placing in
7 m3 10.00
position, tying gabion by tightening wire closing from
the top, tying wire-12 SWG; and filling stones in
gabion box, including supply of materials all
complete. [2400]
Backfilling in layers in foundation trenches, retaining
walls etc with excavated materials including
8 m3 18.00
compaction and watering all complete as per
specification. (908)
D Road Protection Work
Earth work excavation for foundation, protection
work and trenches including shoring, struting,
1 m3 75.00
bracing, sheeting , disposal and all complete as per
specification.
Making gabion boxes including cutting wire &
netting etc. Hexagonal mesh size 100 mm x 120
mm, mesh wire-10 SWG, selvedge wire-8 SWG;
Gabion construction works including placing in
2 m3 75.00
position, tying gabion by tightening wire closing from
the top, tying wire-12 SWG; and filling stones in
gabion box, including supply of materials all
complete. (2400)

BoQ Page 2 of 3
Bill of Quantities

Name of work :Roadway Excavation,Humepipe Culverts & wall works etc


Name of Road: Pokharichauri - Dhuseni - Shivalaya
Contract No. DROBKT/337123/4/2071/072/109
Backfilling in layers in foundation trenches, retaining
walls etc with excavated materials including
3 m3 15.00
compaction and watering all complete as per
specification. (908)
Providing, laying and levelling of dry stone soling
4 works in roadway and bends all complete. (2602, m3 78.75
2603)

TOTAL

VAT (13%)
GRAND TOTAL

Notes :
1 All the works as listed above shall be completed complying the Specification, Name of the Bidder's Firm:
the Special Provision and other Contract Documents. The numbers enclosed
in the bracket in the particulars represent DOR Standard Specifications
Section Number.
2 The cost of laboratory tests as stipulated in the Standard Specification and Signature of the Authorised Person:
QAP shall be borne by the Contractor and such cost is deemed to be included
in the relevant BOQ items.
Name of the Authorised Person:
3 The payment against Provisional Sum item is based on the net cost as
supported by original invoices plus 10% of the total amount to cover all costs
of handling, transportation, storage, ancilliary works, overhead and profit. Seal of the Firm:

BoQ Page 3 of 3