Kharbao commissioning schedule as per CCP & Basic Design Submission Plan

Actual Start Actual Finish Proposed New Proposed New


SR. Activity duration start date finish date cause of delay
Date Date Start Date Finish Date
incorporation
1 Access to site 0 16-05-2016 16-05-2016 14-10-2016 24-01-2017 Activity finished
of JM sheets
2 Construction of Site Hut 89 24-01-2017 23-04-2017 24-01-2017 01-05-2017 20-06-2017
3 construction design

i Preparation & Submission - SLD GA 28 24-09-2016 22-10-2016 24-09-2016 03-11-2016 MSETCL & CR
delayed Activity finished
ii NONO / NONOC 21 23-10-2016 13-11-2016 23-10-2016 31-03-2017 approvals
iii Preparation & Submission - GTP 25 13-11-2016 04-12-2016 01-04-2017 26-04-2017
iv NONO / NONOC 20 23-12-2016 12-01-2017 27-04-2017 18-05-2017
v buiilding design 40 12-01-2017 21-02-2017 12-04-2017 22-05-2017
4 construction Activity

Ground clearance,Earthwrk,installation of
i Ground mat Foundations of Structures & 127 15-09-2016 20-01-2017 15-03-2017 15-03-2017 08-09-2017
Equipment,Fencing,Water Supply,Sewerage

ii Construction of GIS Building 179 09-12-2016 06-06-2017 20-04-2017 29-05-2017 04-03-2018


iii Erection of 220 KV switch gear for MSETCL, 59 07-06-2017 05-08-2017 05-03-2018 13-05-2018
iv Laying & Termination of 220 KV Cable to TSS of 24 06-08-2017 30-08-2017 14-05-2018 07-07-2018
v Testing & Commissioning of 220 KV Switchgear 59 31-08-2017 29-10-2017 08-07-2018 25-09-2018