i Preparation & Submission - SLD GA 28 24-09-2016 22-10-2016 24-09-2016 03-11-2016 MSETCL & CR
delayed Activity finished
ii NONO / NONOC 21 23-10-2016 13-11-2016 23-10-2016 31-03-2017 approvals
iii Preparation & Submission - GTP 25 13-11-2016 04-12-2016 01-04-2017 26-04-2017
iv NONO / NONOC 20 23-12-2016 12-01-2017 27-04-2017 18-05-2017
v buiilding design 40 12-01-2017 21-02-2017 12-04-2017 22-05-2017
4 construction Activity
Ground clearance,Earthwrk,installation of
i Ground mat Foundations of Structures & 127 15-09-2016 20-01-2017 15-03-2017 15-03-2017 08-09-2017
Equipment,Fencing,Water Supply,Sewerage