Corrigendum to TS No.

CET/01/RN/3537/TS/UT/01/R=5 (INSTALLATION OF ESP IN SINTER DISPATCH ROUTE OF SINTER


PLANT-II) issued in DECEMBER 2016:-

S. No TS Clause No. Existing wording To be read as


1. 3.7.11
3.7.11 Design Calculations, Drawings And 3.7.11 Design calculations, drawings and documents
Documents 3.7.11.1 The design calculations shall be submitted by the
The design calculations and drawing bidder for approval, prior to the submission of
shall be submitted by the Bidder for construction drawings. These shall include but not
approval as per the provisions of SBD. limited to, the following

3.7.11.1 Drawings 1) The design calculations shall include static


design calculations for all structures and
The Bidder shall submit for foundations, dynamic analysis for all
approval/reference of the Employer structures and foundations subjected to
general arrangement and detailed impact/vibration induced by equipment and
working drawings for all concrete, other external elements.
reinforced concrete and other civil 2) Building data shall include specifications of
work, as mentioned under chapter-2. materials, design standards followed, load
3.7.11.2 The design criteria mentioned above is data assumed including the loading on floor,
not exhaustive. However, the same bulk material density, crane and hoist
shall be discussed and detailed during loading, wind and seismic loading, wind
detail engineering stage thrusts and vibration considerations,
deflection, type of flooring, roofing and
sheeting and type of construction to be
indicated. The loading combinations and
other assumptions made in the design are to
be furnished.
3) Measures required for safety of the
foundations shall also be indicated.
BSP CORRIGENDUM to TS No. FEBRUARY 2017
INSTALLATION OF ESP IN SINTER CET/01/RN/3537/TS/UT/01/R=5
DISPATCH ROUTE OF SP-II Page 1 of 3
3.7.11.2 Drawings:
The bidder shall prepare general layout drawings
giving salient levels and dimensions of the whole
areas showing all services and facilities, nearby
buildings/roadways etc., provided for the co-
ordination with the other areas of the plant.
Detailed working drawings shall be prepared
based on the general layout drawings considering
overall foundation layout, building, services,
space requirement and clearances as necessary.
The bidder shall submit a comprehensive and
complete unit wise list of drawings ion
reproducible form/softcopy.
3.7.11.3 The bidder shall submit for approval/reference of
the employer general arrangement and detailed
working drawings for all concrete, reinforced
concrete and other civil works as indicated in
consolidated list of drawings in this document.
3.7.11.4 The bidder shall be responsible for protection and
diversion of all existing underground services,
wherever required and / or diversion of the
underground services which are indicated in the
drawings made available to the bidder. In case
there are underground services which need to be
protected and / or diverted but are not shown in the
drawing, the bidder shall be responsible to execute
the same at extra price, if any, to be mutually
agreed in advance between the bidder and the
employer.
BSP CORRIGENDUM to TS No. FEBRUARY 2017
INSTALLATION OF ESP IN SINTER CET/01/RN/3537/TS/UT/01/R=5
DISPATCH ROUTE OF SP-II Page 2 of 3
2. 4.2.4 LD clause referred in SBD is not applicable. Liquidated Damages for non-fulfilment of Performance
The other terms & condition of the PG test Guarantee (PG) parameters of facilities referred in Standard
shall be as stipulated in the Standard Bidding Bidding Document (SBD) is not applicable. However, the
Document (SBD). Liquidated Damages due to delay in completion of facilities
shall be as per the relevant clause of SBD.
The other terms & condition of the PG test shall be as
stipulated in the SBD.
3. 4.3.2.2 Commissioning of the complete system shall be Commissioning of the complete system shall be deemed to be
deemed to be successfully completed when all successfully completed when all the equipment shall operate
the equipment shall operate in an integrated in an integrated manner uninterruptedly, for a period of 72
manner uninterruptedly, for a period of 72 hours at a minimum flow rate of 66 % of the rated capacity of
hours at a minimum flow rate of 66 % of the the system (i.e., 66 % of the rated capacity of the ID fan).
rated capacity of the system.

BSP CORRIGENDUM to TS No. FEBRUARY 2017


INSTALLATION OF ESP IN SINTER CET/01/RN/3537/TS/UT/01/R=5
DISPATCH ROUTE OF SP-II Page 3 of 3