PRATIBHA INDUSTRIES LIMITED

CHECK LIST FOR MIVAN SHUTTERING WORKS

Location : ___________________________________________________________

Unit :

Drg. No. : Date :

Sr. No. Description of Check Yes No Remarks

1 Levels ( for Column and Slab) before center line, line out

2 Centre line, line out and Checking position of Kicker

3 Cleaning of Mivan Shuttering (Column, walls ,Beam and Slab)

4 Appling of shuttering oil for (Column, walls ,Beam and Slab)

5 Alignments and level, line and Plumb for (Column, walls ,Beam and Slab)

6 Line, Level, Plumb for (Column, walls ,Beam and Slab)

7 Tighten wall Ties and Pin Wedges properly.

8 Checking of PL props (Beam and Slab)

9 Shuttering work followed as per approved method statement.

10 Area cleared for reinforcement tying.

Note :

LABOUR HEAD FORAMEN FOR THE UNIT

SURVEYOR PIL

FORAMEN PIL

PIL V A (WADHWA) CONST P LT