Answer:
Please refer to Scope of Work, section 3.2, which states that the Contractor shall be responsible to revalidate the geotechnical
report recommendations under report number 2015/104, Rev.1 provided by the Company.
Answer:
Request for extension of bid submission date is not entertained as the project scope is a straight forward. The current bidding
period is more than adequate for a project of this nature.
1 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Answer:
Please refer to Scope of Work, section 3.3.3 Lighting System. LSTK Contractor shall be responsible to provide all supports for
lighting, cable trays/conduits and all other welded parts with tanks.
Answer:
Please refer to Scope of Work, section 3.3.4 Grounding & Lighting Protection System Grounding lugs "bosses" shall be provided
by LSTK Contractor as per applicable standards.
Answer:
Please refer to Scope of Work, section 3.3.4 Grounding & Lighting Protection System. Lightning rod clip supports shall be
provided by LSTK Contractor.
Answer:
Please refer to Scope of Work, section 3.3.4 Grounding & Lighting Protection System. Lightning protection system shall be
designed by CMEI Contractor, LSTK contractor shall evaluate the design & provide recommendations about the best lightning
rod location. Welding to any clip supports is the responsibility of LSTK contractor.
2 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Answer:
LSTK Contractor shall be responsible to coordinate with CMEI Contractor, and will ensure it design comply with all the tank
associated HCIS requirement. (Reference to Schedule B paragraph 3.8 for interface coordination)
Answer:
The pipe size shown on the PIDs is preliminary, Scope break is shown on the PID between LSTK Contractor and CMEI
Contractor. LSTK Contractor is responsible to finalize the Foam water requirements for each tank including pipe sizing and
foam pourer?s selection. In addition, hydraulically size the Foam Ring and Foam piping up to the base of the tank. LSTK
Contractor to communicate final pipe sizing to base of the tank where the interface with the CMEI occurs.
Answer:
Manual call point, sounder & strobe are excluded from LSTK Contractor. However, Junction box related to Linear Heat Detector
System is included in LSTK Contractor scope.
Answer:
HCIS approval on the fire protection system for tanks is LSTK Contractor responsibility. The Company will only be responsible
in liaising with HCIS for approval.
3 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Answer:
Vendor shall specify the venting requirements per API 2000 and applicable Saudi Aramco material system specifications.
Answer:
Tank capacity, Liquid levels, and operating and design conditions, pumping in and out rates, fluid physical properties are final.
For vent calculations the tank vendor shall comply with the standard requirements of pump in and pump out rate. PFD are
being provided for reference. Provided tank dimensions are minimum (reference Tank Data Sheet Note) please Refer to
attahments
Attachments:
VA247849-001.pdf
VA247842-001.pdf
VA247840-001.pdf
VA247841-001.pdf
VA247839-001.pdf
VA247898-001.pdf
VA247899-001.pdf
VA247900-001.pdf
VA247901-001.pdf
VA247902-001.pdf
VA247903-001.pdf
VA247904-001.pdf
VA247905-001.pdf
VA247906-001.pdf
VA247907-001.pdf
VA247908-001.pdf
VA247909-001.pdf
VA247910-001.pdf
VA247911-001.pdf
VA247912-001.pdf
VA247913-001.pdf
VA247929-001.pdf
VA247836-001.pdf
VA247837-001.pdf
4 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Answer:
Reference P&ID are being provided. please refer to the attachments
Attachments:
VA247898-001.pdf
VA247899-001.pdf
VA247900-001.pdf
VA247901-001.pdf
VA247902-001.pdf
VA247903-001.pdf
VA247904-001.pdf
VA247905-001.pdf
VA247906-001.pdf
VA247907-001.pdf
VA247908-001.pdf
VA247909-001.pdf
VA247910-001.pdf
VA247911-001.pdf
VA247912-001.pdf
VA247913-001.pdf
VA247929-001.pdf
VA247836-001.pdf
VA247837-001.pdf
VA247839-001.pdf
VA247840-001.pdf
VA247841-001.pdf
VA247842-001.pdf
VA247849-001.pdf
Answer:
Bidder scope of supply is reflected through Data sheet, however any component which is essential for these tanks to comply
with SA/international standards shall be contractor scope.
5 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Answer:
Clean out connection is required for all Tanks as mentioned in Tank Datasheets under Index D
Answer:
Over Pressure/Vacuum Bleeder Vents are required for the floating roof tanks. Venting requirement provided in datasheet are
minimum requirement and vendor shall provide adequate vents as per the pump in pump out rate provided in data sheet
Answer:
Bidder shall detail the venting requirements as per API 2000 and applicable Saudi Aramco material system specifications.
Accordingly Bidder to consider Open Vent, Over Pressure/Vacuum Bleeder Vent or Pressure/Vacuum Relief Valve. This is
already mentioned in submitted Tank datasheets under Index D
Answer:
Bidder understanding is not correct. Elevation and Orientation will be provided (by CMEI Contractor) at later stage and
accordingly needed drawings, steel structure, access platform, access ladder shall be considered in estimate.
6 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Description:
GEN-E0107 "Reference to Tanks Package Scope Of Work (PACKAGE 3) document# GEN-E0107, section 2.5, ?CONTRACTOR
will not supply the instrument devices? Accordingly Contractor understand that there is Scope of Work for Instrumentation and
Control in this Project. Company to confirm"
Answer:
Please refer document# GEN-E0107, section 2.5.
Answer:
Please refer Project Scope of work Doc NO GEN-E0107 for detail scope.
Answer:
Reinforcement % shown in the proposal drawings is indicative and for that reason number of bars are not mentioned on
drawings. It is LSTK contractor's responsibility to design ring wall foundation as per vendor load data and geotechnical
recommendation and arrive at design including % of reinforcement; this shall be in compliance with Saudi Aramco standards
requirement.
Answer:
Please refer geotechnical report number 2015/104, Rev.1, point (xii) on page 63.
7 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Answer:
Immediate settlement reported in geotechnical report number 2015/104, Rev.1 is corresponds to settlement during hydro test.
Answer:
Yes, provided the contractor gains approval from the Company.
Answer:
Extension for "last day to ask questions" is extended for a period of one (1) week till Aug. 23, 2016. However, the bid closing
date (BCD) remains the same as Sept. 20, 2016.
Answer:
Extension for "last day to ask questions" is extended for a period of one (1) week till Aug. 23, 2016. However, the bid closing
date (BCD) remains the same as Sept. 20, 2016.
8 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Answer:
Saudi Aramco will manage this project.
Answer:
No change in provided schedule dates, please refer Schedule B attachment II
Answer:
Yes, Saudi Aramco fully own this project.
Answer:
No change in provided schedule dates, please refer Schedule B attachment II
Answer:
LSTK contractor shall develop his design based on the parameter specified in the SAES A-114. The actual site preparation
report will be provided as soon as it is available and contractor has to validate its design based on actual numbers. Soil
improvement, foundation and substructure for the tanks as per geotechnical report findings is the responsibility of the
contractor.
9 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Answer:
Working Capacities are provided in datasheet are as per SAES-D-100. Nominal capacities of the tanks are specified in the
datasheets and contractor to comply with the requirements.
Answer:
Revised LLLL is 1992 mm. And revised Working capacity is 334190 bbl (53132 m3) Please find attached the revised Data
sheet.
Attachments:
EQE00029004.pdf
Answer:
1. Supported Cone roof can be accepted as per 32 SAMSS 005. Aluminum Dome roof is acceptable for Tank dia. above 30 m
as per SAES D-100 2. Top Wind Girder, Intermediate Girder to be decided based on calculation of stiffness as per API 650 &
32-SAMSS-005.
10 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Description:
Ref.: EQ-E00023 & EQ-E00026 Tank Data Sheet for tank # X4-D-0006 & X4-D-0011 Page 3/4 item 4.0 Question: Cleanout
Connection specify "YES" however size specify "NA". Company to advise the size of cleanout connection.
Answer:
Refer API 650 for Size of Cleanout opening.
Answer:
Bidder to consider Maximum allowable Piping loads calculated as per Appendix P of API 650 for Nozzle sizes above 28 ".
Answer:
Yes. Floating suction to be provided. Floating suction to be provided on Outlet Nozzle. It is to be finalized with the piping
contractor during detailed design.
Answer:
Preservation of tanks for up to 1 years after hydro test without product being stored is the contractors responsibility.
Necessary arrangement to be considered by contractor. Contractor to submit the preservation procedure before hydro test for
Saudi Aramco review and approval.
11 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Answer:
Material of construction is mentioned in datasheet, pg. 2 of 4.
Answer:
Saudi Aramco believes that the procurement and expediting activities continues till the late stage of construction and will be
project focused if the associated personnel will be available at site, hence contractor to ensure compliance to the
requirements.
Answer:
GI 202.305 attached.
Attachments:
0202_305.pdf
12 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Answer:
Document titled 'Sch."G" Att.-I' consists of all attachments from I to VII
Answer:
Floating Roof Legs are part of tank and must be considered as pipe purchased through Saudi Aramco approved stockist.
Answer:
Contractor to use all welding specifications, procedures and requirements as approved in Saudi Aramco Standards.
Answer:
To be tested by independent Saudi Aramco approved laboratory.
Answer:
13 of 14 8/21/2016 1:23 PM
https://ecnx.aramco.com/ecnx/ecn/web/qa/bqa/new_bqa.jsp
Answer:
The overall plot plan is attached for reference.