Mast & Gantry Sheave Replacement Information - CKE2500-2

1.Mast Sheave Replacement Overall procedure

Machine posture
Mast tip supported by stand Push rod lifted by 10 ton crane Boom wire retained by steel bar
Boom base : Removed
Boom wire : Not removed Bell hammering by 70ton hook block
1 hour required
CW : Not removed Push rod inserted completely.
Machine disassembling : 6 hours Sheave replacement one by one
2. Gantry Sheave Replacement Overall procedure 3.5 Hours required

Machine posture Push rod lifted by 10 ton crane. Original pins came out but still Bell hammering by 70ton hook block
CW : removed remained in the gantry Push rod inserted completely.
Boom wire : Not removed frame.(Cantilever)
Bell hammering from opposite side.
Platform : on the CW (7mx3m size)
Sheave replacement one by one
2 Hours required for preparation
2 Hours required
Bell Hammering method
Old sheave

Original Pin Push Rod

Necessary Tools

25 Ton RTC for machine


disassembling
and Bell hammering
12 Ton Hydra for Push Rod Lifting

Push Rod : Dia 106 x Length 1200


(Pine hole dia is 110mm)

New sheave

Replacement of sheave
shall be done one by one.
Caution

Loadcell Harness should be removed


before bell-hammering to avoid any
damage by mis-hitting.

Without removal of CW, CWB hanger


interferes with gantry tention memmer.

So CW and CWB should be removed to


the ground.